CN101468772B - 电梯的平衡重 - Google Patents
电梯的平衡重 Download PDFInfo
- Publication number
- CN101468772B CN101468772B CN200810185631XA CN200810185631A CN101468772B CN 101468772 B CN101468772 B CN 101468772B CN 200810185631X A CN200810185631X A CN 200810185631XA CN 200810185631 A CN200810185631 A CN 200810185631A CN 101468772 B CN101468772 B CN 101468772B
- Authority
- CN
- China
- Prior art keywords
- counterbalanced weight
- weight
- counterbalanced
- foundry goods
- steel plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Cage And Drive Apparatuses For Elevators (AREA)
Abstract
提供一种通过有效地利用空间从而能够降低成本的电梯的平衡重。提供一种电梯的平衡重(2),在平衡重框架(21)内装载有用于与电梯轿厢取得重量平衡的副平衡重(22),在所述电梯的平衡重中,在平衡重框架(21)内混合装载具有大致相同的投影剖面的铸件制副平衡重(22a)以及钢板制副平衡重(22b),不仅能够使平衡重(2)达到所需的重量,并且能够在平衡重框架(21)的可装载体积内尽可能地装载比重小但成本却低的铸件制副平衡重(22a)。
Description
技术领域
本发明涉及一种电梯的平衡重,在平衡重框架内安装有用于与电梯轿厢取得重量平衡的副平衡重(sub-weight)。
背景技术
电梯具有在升降通道内进行升降的电梯轿厢和重量与该电梯轿厢相当的用来与该电梯轿厢保持重量平衡的平衡重,电梯轿厢和平衡重被连接成吊桶形状,同时,平衡重由与吊索连接的平衡重框架以及装载在该平衡重框架中的副平衡重构成。并且,作为副平衡重,现在主要采用铸件制或者钢板制的副平衡重。可是,近年来,由于钢材的价格在全球范围内大幅度上升,使得平衡重框架以及安装在平衡重框架中的副平衡重对电梯成本所带来的影响占到了很大的比率,因此,从降低成本这一方面考虑,如何选择副平衡重成了一个重要的因素。在现有技术中,在选择副平衡重时,为了在平衡重框架的可装载体积范围内使平衡重满足必要的重量要求,要么选择比重小但成本低的铸件制副平衡重,或者要么选择比重大但成本高的钢板制副平衡重。
如此,在现有的平衡重中,由于要么选择铸件制的副平衡重,或者要么选择钢板制的副平衡重,所以经常会出现如果选用比重小的铸件制副平衡重,则即使在平衡重框架的可装载体积范围内装满了副平衡重,平衡重的重量仍然比所需重量少一点,因此不得不选择成本高的钢板制副平衡重的情况。在发生了上述情况时,不仅会导致成本上升,而且由于平衡重框架中装载的全部是比重大的钢板制的副平衡重,所以平衡重框架的可装载体积与实际装载的副平衡重的总体积相比,具有过大的富裕量,因此,也存在空间得不到有效利用的问题。
发明内容
本发明是鉴于上述现有技术中所存在的实际问题而作出的,本发明的目在于提供一种通过有效地利用空间从而能够降低成本的电梯的平衡重。
为了实现上述目的,本发明的第1方面的发明涉及一种电梯的平衡重,其在平衡重框架内装载有用于与电梯轿厢取得重量平衡的副平衡重,所述电梯的平衡重的特征在于,所述副平衡重通过混合装载具有大致相同的投影剖面的铸件制副平衡重以及钢板制副平衡重而成。
根据具有上述结构的本发明第1方面的发明,通过在平衡重框架中混合装载具有大致相同的投影剖面的铸件制副平衡重以及钢板制副平衡重,不仅能够使平衡重达到所需的重量,并且能够在平衡重框架的可装载体积内尽可能地使用比重小但成本低的铸件制副平衡重。由此,能够有效地利用空间并降低成本。
此外,本发明的第2方面的发明的特征在于,所述钢板制副平衡重装载在所述平衡重框架的下方,所述铸件制副平衡重装载在所述平衡重框架的上方。
根据具有上述结构的本发明的第2方面的发明,因增设了设备等理由,使得安装后的电梯轿厢的重量增加了时,为了与电梯轿厢在重量上实现平衡,需要在平衡重中增加副平衡重。但是,如上述所示,由于在平衡重框架的可装载体积内以混合装载的方式装满了铸件制副平衡重和钢板制副平衡重,平衡重框架达到了饱和状态,使得无法进一步增加副平衡重。此时,在拿掉比重小的铸件制副平衡重的同时,装载重量与被拿掉的铸件制副平衡重的重量加上增加的重量而得到的总重量相当的钢板制副平衡重。因此,通过将比重小的铸件制副平衡重设置在比重大的钢板制副平衡重的上方,能够使作业变得更为方便。
根据本发明,通过在平衡重框架内混合装载铸件制的副平衡重以及钢板制的副平衡重,不仅能够使平衡重达到所需的重量,并且还能够在平衡重框架的可装载体积内尽可能地使用比重小但成本低的铸件制副平衡重,由此能够有效地降低成本。此外,通过将比重小的铸件制副平衡重设置在比重大的钢板制副平衡重的上方,能够使得副平衡重的增设作业变得更为方便。
附图说明
图1是表示本发明所涉及的电梯的平衡重的一实施方式的主视图。
图2是表示以与图1不同的方法来装载副平衡重时的状态的主视图。
图3是表示进行了副平衡重增设作业后的状态的主视图。
图4是铸件制副平衡重的俯视图。
图5是铸件制副平衡重的主视图。
图6是铸件制副平衡重的侧视图。
图7是钢板制副平衡重的俯视图。
图8是钢板制副平衡重的主视图。
图9是钢板制副平衡重的侧视图。
图10是电梯的结构示意图。
符号说明
1电梯轿厢
2平衡重
3滑轮
4吊索
5卷扬机
21平衡重框架
22副平衡重
22a铸件制副平衡重
22b钢板制副平衡重
具体实施方式
以下,参照附图对本发明所涉及的电梯的平衡重的实施方式进行说明。
图1是表示本发明所涉及的电梯的平衡重的一实施方式的主视图,图2是表示以与图1不同的方法来装载副平衡重时的状态的主视图,图3是表示进行了副平衡重增设作业后的状态的主视图,图4是铸件制副平衡重的俯视图,图5是铸件制副平衡重的主视图,图6是铸件制副平衡重的侧视图,图7是钢板制副平衡重的俯视图,图8是钢板制副平衡重的主视图,图9是钢板制副平衡重的侧视图,图10是电梯的结构示意图。
如图10所示,下悬吊式电梯具备:在升降通道内进行升降的升降体,即电梯轿厢1以及平衡重2;吊索4,其一端连接在升降通道上部而另一端连接平衡重2上,并且其中间部分通过滑轮3与电梯轿厢1卡合;卷扬机5,吊索4的中间部分卷绕在卷扬机5上,并且该卷扬机5向吊索4施加驱动力。
平衡重2由在上部连接有吊索4的平衡重框架21以及装载在平衡重框架21内的多个副平衡重22构成,所述多个副平衡重22和平衡重框架21的总重量与电梯轿厢1的重量相对应。此外,平衡重框架21的可装载体积被设定为规定的体积,通过装载平衡重框架21的装载体积能够允许的数量的副平衡重22,与电梯轿厢1在重量上保持平衡。
此外,如图1以及图2所示,在本实施方式的电梯的平衡重的平衡重框架21内混合装载了具有大致相同的投影剖面的铸件制副平衡重22a以及钢板制副平衡重22b。
如图4以及图7所示,铸件制的副平衡重22a以及钢板制的副平衡重22b分别具有大致相同的投影剖面。但是,如图5、图6、图8以及图9所示,铸件制的副平衡重22a与钢板制的副平衡重22b相比,比重较小,具有较大的高度尺寸。另一方面,钢板制的副平衡重22b与铸件制的副平衡重22a相比,比重较大,具有较小的高度尺寸。此外,铸件制的副平衡重22a与钢板制的副平衡重22a相比,具有能够降低成本的优点。
因而,根据各种铸件制的副平衡重22a的重量和高度尺寸、各种钢板制的副平衡重22b的重量和高度尺寸,计算铸件制的副平衡重22a以及钢板制的副平衡重22b的数量,使得平衡重框架21的可装载体积达到饱和,并且使成本较低的铸件制副平衡重22b的数量达到最大值。另外,例如如图1所示,将与计算数量相等的数量的钢板制副平衡重22b装载在平衡重框架21的下方,并且将与计算数量相等的数量的铸件制副平衡重22a装载在平衡重框架21的上方。或者,如图2所示,将与计算数量相等的数量的铸件制副平衡重22a装载在平衡重框架21的下方,并且将与计算数量相等的数量的钢板制副平衡重22b装载在平衡重框架21的上方。
可是,在设置电梯时,经常会出现在电梯安装好以后,因客户的要求等而在电梯轿厢1中增加设备的情况,例如安装重量为50kg的空调等。此时,平衡重框架21中也需要增加重量为50kg的副平衡重22。但是,在上述本实施方式的平衡重2中,由于在平衡重框架21内混合装载了铸件制的副平衡重22a以及钢板制的副平衡重22b,该平衡重框架21的可装载体积已达到了饱和,因此不能进一步增设副平衡重22。在此,以图1为例进行说明,首先,拿掉规定数量的装载在平衡重框架21上部的比重小的铸件制副平衡重22a,然后,如图3所示,装载重量与拿掉的铸件制副平衡重22a的重量加上增加的重量(在本实施方式中为50kg)后得到的总重量相当的钢板制副平衡重22b。如此,考虑到在电梯安装后可能会需要在电梯轿厢1中增加设备,因此,作为副平衡重22的装载方法,优选如图1所示,将比重大的钢板制副平衡重22b装载在平衡重框架21的下方,而将比重小的铸件制副平衡重22a装载在平衡重框架21的上方。
根据本实施方式,通过在平衡重框架21内混合装载铸件制的副平衡重22a以及钢板制的副平衡重22b,不仅能够使平衡重2达到所需的重量,并且能够在平衡重框架21的可装载体积内尽可能地使用比重小但成本低的铸件制副平衡重22a,由此能够有效地降低成本。此外,通过将比重小的铸件制副平衡重22a设置在比重大的钢板制副平衡重22b的上方,能够使得副平衡重22的增设作业变得更为方便。
Claims (2)
1.一种电梯的平衡重,其在平衡重框架内装载有用于与电梯轿厢取得重量平衡的副平衡重,所述电梯的平衡重的特征在于,
所述副平衡重通过混合装载具有大致相同的投影剖面的铸件制副平衡重以及钢板制副平衡重而成,
所述钢板制副平衡重与所述铸件制副平衡重相比,比重大,具有小的高度尺寸,
根据所述铸件制副平衡重的重量和高度尺寸、所述钢板制副平衡重的重量和高度尺寸,计算所述铸件制副平衡重以及所述钢板制副平衡重的数量,使得所述平衡重框架的可装载体积达到饱和,并且使所述铸件制副平衡重的数量达到最大值。
2.如权利要求1所述的电梯的平衡重,其特征在于,
所述钢板制副平衡重装载在所述平衡重框架的下方,所述铸件制副平衡重装载在所述平衡重框架的上方。
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2007334325A JP5354898B2 (ja) | 2007-12-26 | 2007-12-26 | エレベータのつり合いおもり |
JP2007334325 | 2007-12-26 | ||
JP2007-334325 | 2007-12-26 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101468772A CN101468772A (zh) | 2009-07-01 |
CN101468772B true CN101468772B (zh) | 2012-05-30 |
Family
ID=40826629
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN200810185631XA Active CN101468772B (zh) | 2007-12-26 | 2008-12-17 | 电梯的平衡重 |
Country Status (3)
Country | Link |
---|---|
JP (1) | JP5354898B2 (zh) |
CN (1) | CN101468772B (zh) |
HK (1) | HK1131376A1 (zh) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011037577A (ja) * | 2009-08-11 | 2011-02-24 | Toshiba Elevator Co Ltd | エレベータの釣り合いおもり |
CN101948071B (zh) * | 2010-08-25 | 2012-08-22 | 康力电梯股份有限公司 | 一种电梯配重块 |
CN102616636A (zh) * | 2012-04-10 | 2012-08-01 | 希姆斯电梯(中国)有限公司 | 一种货梯对重架结构 |
CN104030138B (zh) * | 2014-04-24 | 2016-07-06 | 宣城市华菱精工科技股份有限公司 | 一种整体式电梯对重装置 |
CN104709797B (zh) * | 2015-03-12 | 2018-10-26 | 日立电梯(中国)有限公司 | 一种电梯平衡对重 |
JP2016210558A (ja) * | 2015-05-08 | 2016-12-15 | 三菱電機株式会社 | エレベータの釣合おもり装置及びその改修方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000313579A (ja) * | 1999-04-30 | 2000-11-14 | Hitachi Building Systems Co Ltd | エレベータのカウンタウエイト |
JP2001080856A (ja) * | 1999-09-09 | 2001-03-27 | Toshiba Corp | エレベーター |
CN1394187A (zh) * | 2000-10-20 | 2003-01-29 | 株式会社东芝 | 无机房电梯 |
CN1549789A (zh) * | 2002-06-13 | 2004-11-24 | 三菱电机株式会社 | 配重 |
CN1764592A (zh) * | 2004-03-16 | 2006-04-26 | 东芝电梯株式会社 | 用于电梯的平衡装置 |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5978089A (ja) * | 1982-10-27 | 1984-05-04 | 株式会社日立製作所 | エレベ−タ−用釣合おもり |
JPH07223788A (ja) * | 1994-02-03 | 1995-08-22 | Otis Elevator Co | エレベーターのカウンターウェイト |
JPH1072179A (ja) * | 1996-08-30 | 1998-03-17 | Hitachi Building Syst Co Ltd | エレベータの釣合い錘 |
JP2001192190A (ja) * | 2000-01-12 | 2001-07-17 | Mitsubishi Electric Corp | エレベーター装置 |
JP4861661B2 (ja) * | 2005-08-25 | 2012-01-25 | 東芝エレベータ株式会社 | エレベータの釣合錘 |
-
2007
- 2007-12-26 JP JP2007334325A patent/JP5354898B2/ja active Active
-
2008
- 2008-12-17 CN CN200810185631XA patent/CN101468772B/zh active Active
-
2009
- 2009-10-02 HK HK09109120.5A patent/HK1131376A1/xx unknown
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000313579A (ja) * | 1999-04-30 | 2000-11-14 | Hitachi Building Systems Co Ltd | エレベータのカウンタウエイト |
JP2001080856A (ja) * | 1999-09-09 | 2001-03-27 | Toshiba Corp | エレベーター |
CN1394187A (zh) * | 2000-10-20 | 2003-01-29 | 株式会社东芝 | 无机房电梯 |
CN1549789A (zh) * | 2002-06-13 | 2004-11-24 | 三菱电机株式会社 | 配重 |
CN1764592A (zh) * | 2004-03-16 | 2006-04-26 | 东芝电梯株式会社 | 用于电梯的平衡装置 |
Also Published As
Publication number | Publication date |
---|---|
CN101468772A (zh) | 2009-07-01 |
JP2009155024A (ja) | 2009-07-16 |
JP5354898B2 (ja) | 2013-11-27 |
HK1131376A1 (en) | 2010-01-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101468772B (zh) | 电梯的平衡重 | |
US9193567B2 (en) | Method in the manufacture of an elevator | |
CN105939955B (zh) | 用于钢丝绳提升机的低结构台车 | |
CN102126662A (zh) | 电梯平衡锤的锤体 | |
EP2206673B2 (en) | Lifting device for elevator, elevator car frame, and lifting method for elevator | |
CN105110149A (zh) | 水平衡安全电梯 | |
CN105600636A (zh) | 一种电梯层门***软摆锤试验装置 | |
CN103072877A (zh) | 一种单井道双轿厢电梯 | |
JP4774429B2 (ja) | エレベーター装置 | |
JP2007238208A (ja) | 釣合錘 | |
CN100569621C (zh) | 电梯装置 | |
CN107215746A (zh) | 一种电梯用减震垫机构 | |
CN207551656U (zh) | 一种大载重货梯轿架 | |
CN205076626U (zh) | 无机房电梯轿顶反绳轮安装结构 | |
CN206767399U (zh) | 组合式曳引机座 | |
CN110683445B (zh) | 无机房后对重承重结构 | |
CN107720481A (zh) | 一种气压式缓冲桩装置 | |
CN103991777A (zh) | 一种电梯 | |
CN207209666U (zh) | 电梯用减震垫机构 | |
WO2013170439A1 (en) | Elevator system | |
CN208980118U (zh) | 一种无机房电梯绳头固定装置 | |
CN103711344B (zh) | 大跨度机械车库升降平台 | |
CN205662194U (zh) | 一种电梯轿顶的反绳轮结构 | |
CN209721311U (zh) | 新型无机房电梯曳引*** | |
CN110304521A (zh) | 超高层建筑超重设备吊运装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
REG | Reference to a national code |
Ref country code: HK Ref legal event code: DE Ref document number: 1131376 Country of ref document: HK |
|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
REG | Reference to a national code |
Ref country code: HK Ref legal event code: GR Ref document number: 1131376 Country of ref document: HK |