CN101144259A - 大吨位整孔箱梁运输及架设施工方法 - Google Patents

大吨位整孔箱梁运输及架设施工方法 Download PDF

Info

Publication number
CN101144259A
CN101144259A CNA2007100500676A CN200710050067A CN101144259A CN 101144259 A CN101144259 A CN 101144259A CN A2007100500676 A CNA2007100500676 A CN A2007100500676A CN 200710050067 A CN200710050067 A CN 200710050067A CN 101144259 A CN101144259 A CN 101144259A
Authority
CN
China
Prior art keywords
posts
post
bridge
transportation vehicle
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2007100500676A
Other languages
English (en)
Other versions
CN100513694C (zh
Inventor
李华月
邹宏伟
王强
韩伟
钟卫翔
梁兴华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 2 Engineering Group Co Ltd
Xinyun Emgineering Co Ltd of China Railway No 2 Engineering Group Co Ltd
Original Assignee
China Railway Erju Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Erju Co Ltd filed Critical China Railway Erju Co Ltd
Priority to CNB2007100500676A priority Critical patent/CN100513694C/zh
Publication of CN101144259A publication Critical patent/CN101144259A/zh
Application granted granted Critical
Publication of CN100513694C publication Critical patent/CN100513694C/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种大吨位整孔箱梁运输及架设施工方法,包括箱梁的运输和箱梁的架设,箱梁运输施工主要包括运梁准备、装梁、运送箱梁等步骤;箱梁的架设包括架桥机纵移过孔、喂梁和吊梁纵移。本方法有效解决了现有运、架施工的辅助作业时间长、辅助设备多、变跨梁架设及不能平行作业等诸多施工问题,提出了一种架梁辅助作业时间短,辅助设备少,能平行作业,可以同时满足首孔梁和末孔梁变跨桥架设的科学施工方法。本方法施工效率高,桥间转移便利,适应性强,既适合多孔连续的特大桥施工,也能很好地适应一座桥中只有几孔箱梁的中小桥分散桥群施工。

Description

大吨位整孔箱梁运输及架设施工方法
技术领域
本发明涉及到铁路整孔箱梁运输及架设施工领域,特别是涉及一种大吨位整孔箱梁运输及架设施工方法。
背景技术
随着我国高速铁路的迅速发展,如何提高铁路建设的速度和效率,成为非常重要的课题,而如何改进铁路箱梁运输和架设施工的方法也是这一课题的重要组成部分。在现有铁路箱梁运输和架设施工的方法中,下导梁式架桥机型施工方法在首、末孔梁架设施工,工地桥间转移复杂,需解部分体拆除导梁和重新组装在施工方法上无法克服效率较低的特点;运架一体机施工方法所使用的设备集梁场提梁机、运梁车、架桥机三者功能于一身,但该施工方法只能顺序作业,施工效率较低。步履式架桥机施工方法架梁、运梁平行作业,施工效率高;桥间转移便利,适应性强。既适合多孔连续的特大桥施工,也能很好地适应一座桥中只有几孔箱梁的中小桥分散桥群施工。为了解决现有运、架施工的辅助作业时间长、辅助设备多、变跨梁架设及不能平行作业等诸多施工问题,必须设计一种架梁辅助作业时间短,辅助设备少及能平行作业,并能同时满足首孔梁和末孔梁变跨桥架设的科学施工方法。
发明内容
为了达到上述目的,本发明公开了一种步履式架桥机和轮胎式运梁车配套完成大吨位整孔箱梁运输及架设施工方法:
一、箱梁的运输
箱梁运输施工主要包括运梁准备、装梁、运送箱梁对位几个步骤,施工作业方法如下:
(1)运梁车空车行驶至装梁位,按照要求调整就位。
(2)利用门式起重机将箱梁提升至运梁车上。
(3运梁车运输箱梁至架桥机尾部。
(4)架桥机三号柱由窄式变宽式,运梁车载梁驶入架桥机二号柱,接近二号柱时应尽可能慢速靠近,防止运梁车冲撞架桥机。
(5)支撑支腿,架桥机一号起重小车吊梁,拖梁前行,二号起重小车吊梁,纵移台车回位。
(6)运梁车空车返回装梁位。
二、箱梁的架设
1、架桥机纵移过孔
(1)架桥机由宽式变窄式:一、二号起重小车走行到落梁位,联结三号柱下横联,操作三号柱的液压***,拔出三号柱柱体定位销,提升三号柱,操作折叠机构由宽式变窄式,走行轮组内摆至走行位置,穿好柱体定位销成窄式支撑。
(2)架桥机纵移:二号起重小车退到机臂尾部,用刚性横联将一号柱与已架设箱梁吊梁孔张紧并用手动葫芦做好一号柱保险张拉,拆除二号柱支撑垫木,取去一号柱定位销,驱动三号柱走行机构纵移架桥机。
支撑二号柱:架桥机纵移到位后,垫好二号柱支撑垫木,一号起重小车退到机臂尾部准备纵移一号柱。
(3)一号柱纵移:操作一号柱液压***,拔出一号柱下升降油缸定位销,将一号柱下柱身上提,纵移一号柱,走到一号柱机臂上定位销座穿定位销,在桥墩上支撑一号柱并穿定位销,拧好一号柱附助螺旋支腿。
(4)架桥机窄式变宽式:一、二号起重小车走行到机臂前端,操作三号柱的液压***,拔出三号柱升降的定位销,提升三号柱,操作折叠机构使走行轮组外摆至宽式支撑并穿好定位销,打开三号柱下横联。
准备吊梁:一、二号起重小车走行到后机臂取梁位置,让一号起重小车距二号柱中心2.8米处等待吊梁。
2、喂梁
(1)三号柱窄式变宽式,调整均衡油缸并支撑到桥面上,拆除三号柱的下横联,转动90度,让出喂梁通道。
(2)运梁车继续前行至一号起重小车吊梁位,运梁车停车,支起运梁车前机组液压辅助支腿受力。
3、吊梁纵移
(1)一号起重小车取梁:将一号起重小车运行到待架梁的前吊梁孔,安装吊架起吊箱梁。
(2)拖梁:一号起重小车吊起箱梁,使箱梁底面离开运梁车支承面100毫米,一号吊梁起重小车与运梁台车同步运行,将梁拖到二号起重小车取梁位。二号起重小车取梁,运梁车退出:将二号起重小车运行到待架梁的后吊梁孔,安装吊架起吊箱梁,运梁车从三号柱下部退出,到梁场装运下一孔箱梁。
(3)落梁:一、二号起重小车走行到位后降低梁体的高度,箱梁底面距支座上平面1.5米停止,安装支座板预埋螺栓。
本发明与现有技术相比具有以下特点:
本方法架梁辅助作业时间短,辅助设备少,能平行作业,可以同时满足首孔梁和末孔梁变跨桥架设。而且本方法施工效率高,桥间转移便利,适应性强,既适合多孔连续的特大桥施工,也能很好地适应一座桥中只有几孔箱梁的中小桥分散桥群施工。
附图说明
图1大吨位整孔箱梁运输及架设施工设备示意图
图2大吨位整孔箱梁运输及架设施工方法图
图中标注:1为架桥机机臂,2为运梁车,3为架桥机三号柱,4为架桥机
二号柱,5为架桥机一号柱,6为架桥机二号起重小车,7为
架桥机一号起重小车。
具体实施方式
实施例1
架设新建铁路西安一南京线合肥至南京段,使用900吨步履式架桥机、900吨轮胎式运梁车进行运输和架设施工。
一、箱梁的运输
(1)运梁车2空车行驶至装梁位,按照要求调整就位。
(2)利用MQ450/34m门式起重机将箱梁提升至运梁车2上。
(3运梁车2运输箱梁至架桥机尾部。
(4)架桥机三号柱3由窄式变宽式,运梁车载梁驶入架桥机二号柱4,接近二号柱4时应尽可能慢速靠近,防止运梁车2冲撞架桥机。
(5)支撑支腿,架桥机一号起重小车7吊梁,拖梁前行,二号起重小车6吊梁,纵移台车回位。
(6)运梁车2空车返回装梁位。
二、箱梁的架设
1、架桥机纵移过孔
(1)架桥机由宽式变窄式:一、二号起重小车7、6走行到落梁位,联结三号柱3下横联,操作三号柱3的液压***,拔出三号柱3柱体定位销,提升三号柱3,操作折叠机构由宽式变窄式,走行轮组内摆至走行位置,穿好柱体定位销成窄式支撑。
(2)架桥机纵移:二号起重小车6退到机臂尾部,用刚性横联将1号柱5与已架设箱梁吊梁孔张紧并用手动葫芦做好一号柱保险张拉,拆除二号柱4支撑垫木,取去一号柱5定位销,驱动三号柱3走行机构纵移架桥机。
支撑二号柱4:架桥机纵移到位后,垫好二号柱4支撑垫木,一号起重小车7退到机臂尾部准备纵移一号柱5。
(3)一号柱5纵移:操作一号柱5液压***,拔出一号柱5下升降油缸定位销,将一号柱5下柱身上提,纵移一号柱5,走到一号柱5机臂上定位销座穿定位销,在桥墩上支撑一号柱5并穿定位销,拧好一号柱5附助螺旋支腿。
(4)架桥机窄式变宽式:一、二号起重小车7、6走行到机臂前端,操作三号柱3的液压***,拔出三号柱3升降的定位销,提升三号柱3,操作折叠机构使走行轮组外摆至宽式支撑并穿好定位销,打开三号柱3下横联。
准备吊梁:一、二号起重小车7、6走行到后机臂取梁位置,让一号起重小车7距二号柱4中心2.8米处等待吊梁。
2、喂梁
(1)三号柱3窄式变宽式,调整均衡油缸并支撑到桥面上,拆除三号柱3的下横联,转动90度,让出喂梁通道。
(2)运梁车2继续前行至一号起重小车吊梁位,运梁车2停车,支起运梁车2前机组液压辅助支腿受力。
3、吊梁纵移
(1)一号起重小车7取梁:将一号起重小车7运行到待架梁的前吊梁孔,安装吊架起吊箱梁。
(2)拖梁:一号起重小车7吊起箱梁,使箱梁底面离开运梁车支承面100毫米,一号吊梁起重小车7与运梁车2同步运行,将梁拖到二号起重小车6取梁位。二号起重小车6取梁,运梁车2退出:将二号起重小车6运行到待架梁的后吊梁孔,安装吊架起吊箱梁,运梁车2从三号柱下部退出,到梁场装运下一孔箱梁。
(3)落梁:一、二号起重小车7、6走行到位后降低梁体的高度,箱梁底面距支座上平面1.5米停止,安装支座板预埋螺栓。
使用上述方法,完成了该线441孔预制预应力混凝土简支箱梁运输、架设,其中:32米箱梁117孔,24米箱梁324孔,桥3座,桥的间距3-7公里。单片箱梁重778吨。并在架梁过程中完成架桥机桥间转移架桥机5次。事实证明,采用该设备进行大型箱梁架设施工方案是先进的、可靠的,完全满足了合宁铁路32米/900吨级箱梁运架施工,为今后类似桥梁项目的施工,总结出了先进、成熟的施工技术和经验,值得在国内外进行推广和应用。

Claims (2)

1.一种大吨位整孔箱梁运输及架设施工方法,包括箱梁的运输和箱梁的架设,
其特征在于包括以下步骤:
一、箱梁的运输:
a.运梁车(2)空车行驶至装梁位,按照要求调整就位。
b.利用门式起重机将箱梁提升至运梁车(2)上。
c.运梁车(2)运输箱梁至架桥机尾部。
d.架桥机三号柱(3)由窄式变宽式,运梁车载梁驶入架桥机二号柱(4),接近二号柱(4)时应尽可能慢速靠近,防止运梁车(2)冲撞架桥机。
e.支撑支腿,架桥机一号起重小车(7)吊箱梁,拖梁前行,二号起重小车(6)吊梁,纵移台车回位。
f.运梁车(2)空车返回装梁位。
二、箱梁的架设:
A.架桥机纵移过孔
a.架桥机由宽式变窄式:一、二号起重小车(7)、(6)走行到落梁位,联结三号柱(3)下横联,操作三号柱(3)的液压***,拔出三号柱(3)柱体定位销,提升三号柱(3),操作折叠机构由宽式变窄式,走行轮组内摆至走行位置,穿好柱体定位销成窄式支撑。
b.架桥机纵移:二号起重小车(6)退到机臂(1)尾部,用刚性横联将一号柱(5)与已架设箱梁吊梁孔张紧并用手动葫芦做好一号柱(5)保险张拉,拆除二号柱(4)支撑垫木,取去一号柱(6)定位销,驱动三号柱(3)走行机构纵移架桥机。架桥机纵移到位后,垫好二号柱(4)支撑垫木,一号起重小车(7)退到机臂尾部准备纵移一号柱(5)。
c.一号柱(5)纵移:操作一号柱(5)液压***,拔出一号柱(5)下升降油缸定位销,将一号柱(5)下柱身上提,纵移一号柱(5),走到一号柱(5)机臂上定位销座穿定位销,在桥墩上支撑一号柱(5)并穿定位销,拧好一号柱(5)附助螺旋支腿。
d.架桥机窄式变宽式:一、二号起重小车(7)、(6)走行到机臂前端,操作三号柱(3)的液压***,拔出三号柱(3)升降的定位销,提升三号柱(3),操作折叠机构使走行轮组外摆至宽式支撑并穿好定位销,打开三号柱(3)下横联。一、二号起重小车(7)、(6)走行到后机臂取梁位置,让一号起重小车(7)距二号柱(4)中心2.8米处等待吊梁。
B.喂梁
a.三号柱(3)窄式变宽式,调整均衡油缸并支撑到桥面上,拆除三号柱(3)的下横联,转动90度,让出喂梁通道。
b.运梁车继续前行至一号起重小车(7)吊梁位,运梁车(2)停车,支起运梁车(2)前机组液压辅助支腿受力。
C.吊梁纵移
a.一号起重小车(7)取梁:将一号起重小车(7)运行到待架梁的前吊梁孔,安装吊架起吊箱梁。
b.拖梁:一号起重小车(7)吊起箱梁,使箱梁底面离开运梁车支承面100毫米,一号吊梁起重小车(7)与运梁车(2)同步运行,将梁拖到二号起重小车(6)取梁位。二号起重小车(6)取梁,运梁车(2)退出:将二号起重小车(2)运行到待架梁的后吊梁孔,安装吊架起吊箱梁,运梁车(2)从三号柱(3)下部退出,到梁场装运下一孔箱梁。
c.落梁:一、二号起重小车(7)、(6)走行到位后降低梁体的高度,箱梁底面距支座上平面1.5米停止,安装支座板预埋螺栓。
2.根据权利要求1所述的一种大吨位整孔箱梁运输及架设施工方法,其特征在于:所述架桥机和运梁车为900吨级步履式架桥机和900吨级轮胎式运梁车。
CNB2007100500676A 2007-09-20 2007-09-20 大吨位整孔箱梁运输及架设施工方法 Active CN100513694C (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2007100500676A CN100513694C (zh) 2007-09-20 2007-09-20 大吨位整孔箱梁运输及架设施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2007100500676A CN100513694C (zh) 2007-09-20 2007-09-20 大吨位整孔箱梁运输及架设施工方法

Publications (2)

Publication Number Publication Date
CN101144259A true CN101144259A (zh) 2008-03-19
CN100513694C CN100513694C (zh) 2009-07-15

Family

ID=39206973

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2007100500676A Active CN100513694C (zh) 2007-09-20 2007-09-20 大吨位整孔箱梁运输及架设施工方法

Country Status (1)

Country Link
CN (1) CN100513694C (zh)

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101434344B (zh) * 2008-12-30 2011-07-20 天津第三市政公路工程有限公司 一种桥梁箱梁自浮运输方法
CN101956370B (zh) * 2009-07-20 2012-01-25 苏州大方特种车股份有限公司 可变跨架设的导梁式架桥机
CN102660926A (zh) * 2012-05-04 2012-09-12 秦皇岛天业通联重工股份有限公司 一种节段拼装步履式架桥机降低后支腿反力的过孔方法
CN102797226A (zh) * 2012-07-26 2012-11-28 中铁六局集团有限公司 60米钢箱梁整体架设施工方法
CN104495653A (zh) * 2014-12-22 2015-04-08 中铁大桥局集团有限公司 一种多功能大吨位架梁起重机及架梁方法
CN104801983A (zh) * 2015-03-27 2015-07-29 安徽江淮起重运输机械有限公司 起重机箱梁流水生产线
CN106320181A (zh) * 2016-09-14 2017-01-11 中交第航务工程局有限公司 一种采用架桥机安装预制梁板的施工工法
CN106544958A (zh) * 2016-11-25 2017-03-29 中铁三局集团有限公司 辅助导梁式900吨架桥机低位过提梁拱的施工方法
CN106592431A (zh) * 2016-11-25 2017-04-26 中铁三局集团有限公司 辅助导梁式900吨架桥机高位过提梁拱的施工方法
WO2017088117A1 (zh) * 2015-11-25 2017-06-01 陈修缘 桥梁上部结构施工使用的升降式施工***及其施工方法
CN106836000A (zh) * 2017-04-06 2017-06-13 中铁六局集团有限公司 基于dj系列架桥机的曲线过孔架桥施工方法
CN107165055A (zh) * 2017-07-07 2017-09-15 中铁二局集团有限公司 一种大吨位、非对称、分幅预制箱梁梁上运梁及整孔架设施工方法
CN107401124A (zh) * 2017-09-15 2017-11-28 中铁第五勘察设计院集团有限公司 T型梁桥的架桥机
CN107558378A (zh) * 2017-09-21 2018-01-09 郑州新大方重工科技有限公司 一种用于架设全预制梁的架桥机及其架桥方法
CN107604828A (zh) * 2017-09-15 2018-01-19 中铁第五勘察设计院集团有限公司 双t型梁桥的架桥机
CN107604824A (zh) * 2017-09-15 2018-01-19 中铁第五勘察设计院集团有限公司 双t型梁桥的架桥方法
CN107604825A (zh) * 2017-09-15 2018-01-19 中铁第五勘察设计院集团有限公司 T型梁桥的架桥方法
CN110743693A (zh) * 2019-09-30 2020-02-04 山西钢铁建设(集团)有限公司 一种矿山破碎站整体移设方法
CN111893893A (zh) * 2020-08-01 2020-11-06 中桥科建(德州)路桥工程有限公司 一种新型架梁装备及架设方法
CN113605248A (zh) * 2021-09-06 2021-11-05 中铁二十二局集团第二工程有限公司 1000t/40m箱梁的施工方法、高速铁路、运梁车及架桥机
CN114438901A (zh) * 2022-03-22 2022-05-06 四川发展磁浮科技有限公司 一种内嵌式磁浮高架线路架桥机架梁施工方法
CN114737477A (zh) * 2022-02-16 2022-07-12 中铁十一局集团有限公司 一种基于发梁台车的运梁车发梁施工方法

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101831888B (zh) * 2010-05-14 2011-12-28 郑州新大方重工科技有限公司 1200吨级水利渡槽运、架设备

Cited By (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101434344B (zh) * 2008-12-30 2011-07-20 天津第三市政公路工程有限公司 一种桥梁箱梁自浮运输方法
CN101956370B (zh) * 2009-07-20 2012-01-25 苏州大方特种车股份有限公司 可变跨架设的导梁式架桥机
CN102660926A (zh) * 2012-05-04 2012-09-12 秦皇岛天业通联重工股份有限公司 一种节段拼装步履式架桥机降低后支腿反力的过孔方法
CN102797226A (zh) * 2012-07-26 2012-11-28 中铁六局集团有限公司 60米钢箱梁整体架设施工方法
CN102797226B (zh) * 2012-07-26 2014-07-23 中铁六局集团有限公司 60米钢箱梁整体架设施工方法
CN104495653B (zh) * 2014-12-22 2016-10-05 中铁大桥局集团有限公司 一种多功能大吨位架梁起重机及架梁方法
CN104495653A (zh) * 2014-12-22 2015-04-08 中铁大桥局集团有限公司 一种多功能大吨位架梁起重机及架梁方法
CN104801983B (zh) * 2015-03-27 2017-10-13 安徽江淮起重运输机械有限公司 起重机箱梁流水生产线
CN104801983A (zh) * 2015-03-27 2015-07-29 安徽江淮起重运输机械有限公司 起重机箱梁流水生产线
WO2017088117A1 (zh) * 2015-11-25 2017-06-01 陈修缘 桥梁上部结构施工使用的升降式施工***及其施工方法
CN106320181A (zh) * 2016-09-14 2017-01-11 中交第航务工程局有限公司 一种采用架桥机安装预制梁板的施工工法
CN106544958A (zh) * 2016-11-25 2017-03-29 中铁三局集团有限公司 辅助导梁式900吨架桥机低位过提梁拱的施工方法
CN106592431A (zh) * 2016-11-25 2017-04-26 中铁三局集团有限公司 辅助导梁式900吨架桥机高位过提梁拱的施工方法
CN106544958B (zh) * 2016-11-25 2018-07-06 中铁三局集团有限公司 辅助导梁式900吨架桥机低位过提梁拱的施工方法
CN106592431B (zh) * 2016-11-25 2018-02-23 中铁三局集团有限公司 辅助导梁式900吨架桥机高位过提梁拱的施工方法
CN106836000A (zh) * 2017-04-06 2017-06-13 中铁六局集团有限公司 基于dj系列架桥机的曲线过孔架桥施工方法
CN107165055A (zh) * 2017-07-07 2017-09-15 中铁二局集团有限公司 一种大吨位、非对称、分幅预制箱梁梁上运梁及整孔架设施工方法
CN107604824A (zh) * 2017-09-15 2018-01-19 中铁第五勘察设计院集团有限公司 双t型梁桥的架桥方法
CN107604828A (zh) * 2017-09-15 2018-01-19 中铁第五勘察设计院集团有限公司 双t型梁桥的架桥机
CN107604825A (zh) * 2017-09-15 2018-01-19 中铁第五勘察设计院集团有限公司 T型梁桥的架桥方法
CN107401124A (zh) * 2017-09-15 2017-11-28 中铁第五勘察设计院集团有限公司 T型梁桥的架桥机
CN107604828B (zh) * 2017-09-15 2023-09-29 中国铁路总公司 双t型梁桥的架桥机
CN107558378A (zh) * 2017-09-21 2018-01-09 郑州新大方重工科技有限公司 一种用于架设全预制梁的架桥机及其架桥方法
CN110743693A (zh) * 2019-09-30 2020-02-04 山西钢铁建设(集团)有限公司 一种矿山破碎站整体移设方法
CN111893893A (zh) * 2020-08-01 2020-11-06 中桥科建(德州)路桥工程有限公司 一种新型架梁装备及架设方法
CN113605248A (zh) * 2021-09-06 2021-11-05 中铁二十二局集团第二工程有限公司 1000t/40m箱梁的施工方法、高速铁路、运梁车及架桥机
CN114737477A (zh) * 2022-02-16 2022-07-12 中铁十一局集团有限公司 一种基于发梁台车的运梁车发梁施工方法
CN114438901A (zh) * 2022-03-22 2022-05-06 四川发展磁浮科技有限公司 一种内嵌式磁浮高架线路架桥机架梁施工方法

Also Published As

Publication number Publication date
CN100513694C (zh) 2009-07-15

Similar Documents

Publication Publication Date Title
CN100513694C (zh) 大吨位整孔箱梁运输及架设施工方法
CN101851898B (zh) 能通过隧道且实现隧道口架梁的架桥机及其架桥工序
CN101586330B (zh) 预应力砼连续梁桥挂篮后退施工方法
CN102367651B (zh) U型混凝土梁架桥机
CN101260650B (zh) 50m/1430t双幅整体箱梁架设工艺
CN102425120B (zh) 分体导梁式过隧道架桥机
CN101831888B (zh) 1200吨级水利渡槽运、架设备
CN104631335A (zh) 新型大吨位架桥机及其施工方法
CN101324053A (zh) 双线箱梁下行式移动模架造桥机及其施工方法
CN109653105A (zh) 箱梁桥悬臂施工挂篮主桁***及其使用方法
CN106917356B (zh) 一种新型钢桁梁桥道砟槽板高效安装方法
CN103485282A (zh) 运架一体机进出隧道口架设箱梁的施工方法
CN202544854U (zh) 地铁车站衬砌台车
CN102198695A (zh) 箱梁外膜之外侧模的纵向移动方法
CN106223983A (zh) 一种引水隧洞斜井、平段全断面通用钢模台车
CN202187298U (zh) 分体导梁式过隧道架桥机
CN102134832A (zh) 活动支架辅助不变幅架梁吊机架设钢箱梁方法及活动支架
CN101885206A (zh) 高速铁路预制箱梁液压内模桁架式行走轨***
CN201268830Y (zh) 便捷式多功能架桥车
CN204662270U (zh) 一种箱梁转运***
CN201746780U (zh) 能通过隧道且实现隧道口架梁的架桥机
CN201546176U (zh) 遮板安装小车
CN209652772U (zh) 箱梁桥悬臂施工挂篮主桁***
CN104929045B (zh) 一种箱梁转运平台以及喂梁、取梁方法
WO2018214893A1 (zh) 一种用于悬索桥的架桥机及其施工法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160111

Address after: Jinniu District Kam Tong Road Chengdu city Sichuan province 610031 No. 16

Patentee after: CHINA RAILWAY NO.2 BUREAU ENGINEERING CO., LTD.

Address before: 610041 high building, No. nine Hing Road, Chengdu hi tech Development Zone, Sichuan, 6

Patentee before: China Railway Erju Co., Ltd.

TR01 Transfer of patent right

Effective date of registration: 20180823

Address after: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Co-patentee after: China Railway Erju Corporation Ching Engineering Co., Ltd.

Patentee after: CHINA RAILWAY NO.2 BUREAU ENGINEERING CO., LTD.

Address before: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Patentee before: CHINA RAILWAY NO.2 BUREAU ENGINEERING CO., LTD.

TR01 Transfer of patent right
CP01 Change in the name or title of a patent holder

Address after: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Co-patentee after: China Railway Erju Corporation Ching Engineering Co., Ltd.

Patentee after: China Railway No. 2 Engineering Group Co., Ltd.

Address before: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Co-patentee before: China Railway Erju Corporation Ching Engineering Co., Ltd.

Patentee before: CHINA RAILWAY NO.2 BUREAU ENGINEERING CO., LTD.

CP01 Change in the name or title of a patent holder