CN100564676C - The portal jib crane transfer cart - Google Patents

The portal jib crane transfer cart Download PDF

Info

Publication number
CN100564676C
CN100564676C CNB2005101268047A CN200510126804A CN100564676C CN 100564676 C CN100564676 C CN 100564676C CN B2005101268047 A CNB2005101268047 A CN B2005101268047A CN 200510126804 A CN200510126804 A CN 200510126804A CN 100564676 C CN100564676 C CN 100564676C
Authority
CN
China
Prior art keywords
loading platform
base plate
crawler belt
belt running
jib crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2005101268047A
Other languages
Chinese (zh)
Other versions
CN1779073A (en
Inventor
约瑟夫·陶依尔
曼弗雷德·布伦宁格
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Franz Plasser Bahnbaumaschinen Industrie GmbH
Original Assignee
Franz Plasser Bahnbaumaschinen Industrie GmbH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Franz Plasser Bahnbaumaschinen Industrie GmbH filed Critical Franz Plasser Bahnbaumaschinen Industrie GmbH
Publication of CN1779073A publication Critical patent/CN1779073A/en
Application granted granted Critical
Publication of CN100564676C publication Critical patent/CN100564676C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/02Transporting, laying, removing, or renewing lengths of assembled track, assembled switches, or assembled crossings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Jib Cranes (AREA)
  • Machines For Laying And Maintaining Railways (AREA)
  • Warehouses Or Storage Devices (AREA)
  • Carriers, Traveling Bodies, And Overhead Traveling Cranes (AREA)

Abstract

The invention discloses a kind of transfer cart that utilizes the loading platform (2) of rail travelling mechanism (3) traveling that has, be used to transport portal jib crane (10) with crawler belt running mechanism (11), it is characterized in that: be provided with the paired base plate (7) of edge above this loading platform (2) perpendicular to the direction positioned opposite of longitudinal direction of car (5), be used to support described crawler belt running mechanism (11), can be moved along direction with respect to loading platform (7) by the described base plate of drive unit (9) (7) and to adjust to an installation site perpendicular to vertical (5) of vehicle, in the time of on this installation site, described base plate (7) exceeds described loading platform (2) boundary line (6) parallel with longitudinal direction of car (5).So just can crawler belt running mechanism (11) and portal jib crane (10) be coupled together with simple method.

Description

The portal jib crane transfer cart
Technical field
The present invention relates to one and have a transfer cart that can utilize the loading platform of rail travelling mechanism traveling, be used to transport the crawler type portal jib crane.
Background technology
A kind of transfer cart that the EP0725859B1 patent is introduced, known.This car is used to load one for transporting the set portal jib crane with crawler belt running mechanism of the simple section of track.In order also to transport track switch, just must be according to the distance between two crawler belt running mechanisms of horizontal this portal jib crane of increasing of vehicle.When but this just requires to load and transport this portal jib crane with transfer cart, must remove the crawler belt running mechanism that exceeds structure clearance.
Summary of the invention
The technical problem to be solved in the present invention will be created a this paper exactly and start described transfer cart, utilizes it can guarantee to debug again easily a portal jib crane that is transported on this transfer cart, promptly debugs again from the operation operating mode and shifts operating mode.
Above-mentioned technical problem has loading platform that utilizes the rail travelling mechanism traveling by a kind of like this, the transfer cart that is used to transport the portal jib crane with crawler belt running mechanism solves, according to the present invention, this is provided with the paired base plate of edge perpendicular to the direction positioned opposite of longitudinal direction of car above loading platform, be used to support described crawler belt running mechanism, by drive unit, described base plate can be moved along the direction longitudinally perpendicular to vehicle with respect to loading platform and adjust to an installation site, in the time of on this installation site, described base plate exceeds the described loading platform boundary line parallel with longitudinal direction of car.
The advantage of this structure is embodied in this case especially, that is, and and in the time when shifting the building site, can't being positioned in the structure clearance along two relative crawler belt running mechanisms of lateral direction of car.Therefore, the crawler belt running mechanism of dismantling of just having in this case.By just can be very simply according to base plate of the present invention laterally moving described crawler belt running mechanism along vehicle, even its from one be positioned at structure clearance with the position along laterally the moving of vehicle, can successfully be connected up to it with described portal jib crane.
Description of drawings
Further illustrate the present invention by the accompanying drawing illustrated embodiment below, in the accompanying drawing:
Fig. 1 is the lateral view of the transfer cart of loading portal jib crane,
Fig. 2 is the diagrammatic top view of portal jib crane and transfer cart,
Fig. 3 is for seeing diagrammatic front view in the past along longitudinal direction of car.
The specific embodiment
Fig. 1, transfer cart 1 shown in 2 and 3 has a loading platform 2, utilizes the rail travelling mechanism 3 can traveling on track 4.Loading platform limits along seeing by two boundary lines that are parallel to each other 6 perpendicular to the direction of longitudinal direction of car 5.
Four base plates 7 are arranged on the loading platform, wherein, per two be along perpendicular to the horizontal one-tenth two-phase of longitudinal direction of car 5 to arranging.Every base plate 7 can laterally moving along guide rail 8 along vehicle.Start a drive unit 9 every base plate 7 is laterally moved with respect to loading platform 2, promptly be positioned at inboard position, transfer building site (seeing Fig. 2 left side) and move on to an installation site (seeing Fig. 2 right side) from one.This moment, base plate 7 stretched out (see figure 3) beyond the corresponding edge boundary line 6.
In order to make portal jib crane 10 transfer to a building site, crawler belt running mechanism 11 must be unclamped from a walking frame 12.Only in this way just can avoid exceeding structure clearance.
For a crawler belt running mechanism 11 and a Height Adjustable vertical support frame 13 of described walking frame 12 are coupled together, base plate 7 is moved on to above-mentioned installation site together with top crawler belt traveling framework 11, rotate the described walking frame 12 that is connected with a portal jib crane mechanism 15 by crossbeam 14 around a vertical axis 16 then, be positioned at hookup 17 tops of a crawler belt running mechanism 11 up to each vertical support frame 13.With after vertical support frame 13 is connected, the drive unit 18 of walking frame 12 lifts a little with crawler belt running mechanism 11 from base plate 7 at crawler belt running mechanism 11.When promotion base plate 7 is got back to transfer position, building site, can utilize drive unit 18 unhinderedly to fall portal jib crane 10, make it to reach a railway roadbed.Crossbeam 14 is designed to by well-known method can be by the flexible form of drive unit.Unclamp crawler belt running mechanism 11 and be placed on the base plate 7 from walking frame 12 and in like manner undertaken by opposite order.
List of numerals
1 transfer cart
2 loading platforms
3 rail travelling mechanisms
4 tracks
5 longitudinal direction of car
6 boundary lines
7 base plates
8 guide rails
9 drive units
10 portal jib cranes
11 crawler belt running mechanisms
12 walking frames
13 vertical support frames
14 crossbeams
15 portal jib crane frameworks
16 axis
17 hookups
18 drive units

Claims (1)

1. one kind has a transfer cart that utilizes the loading platform (2) of rail travelling mechanism (3) traveling, be used to transport portal jib crane (10) with crawler belt running mechanism (11), it is characterized in that: be provided with the paired base plate (7) of edge above this loading platform (2) perpendicular to the direction positioned opposite of longitudinal direction of car (5), be used to support described crawler belt running mechanism (11), can be moved along direction with respect to loading platform (2) by the described base plate of drive unit (9) (7) and to adjust to an installation site perpendicular to vertical (5) of vehicle, in the time of on this installation site, described base plate (7) laterally outwards exceeds described loading platform (2) boundary line (6) parallel with longitudinal direction of car (5) along track.
CNB2005101268047A 2004-11-22 2005-11-22 The portal jib crane transfer cart Expired - Fee Related CN100564676C (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
AT0195404A AT501047B1 (en) 2004-11-22 2004-11-22 TRANSPORT CAR FOR THE TRANSPORT OF A PORTAL CRANE
ATA1954/2004 2004-11-22

Publications (2)

Publication Number Publication Date
CN1779073A CN1779073A (en) 2006-05-31
CN100564676C true CN100564676C (en) 2009-12-02

Family

ID=35589636

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2005101268047A Expired - Fee Related CN100564676C (en) 2004-11-22 2005-11-22 The portal jib crane transfer cart

Country Status (7)

Country Link
US (1) US20060117987A1 (en)
EP (1) EP1659221B1 (en)
JP (1) JP4669378B2 (en)
CN (1) CN100564676C (en)
AT (2) AT501047B1 (en)
AU (1) AU2005234729B2 (en)
DE (1) DE502005004712D1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2952656B1 (en) * 2009-11-16 2012-12-14 Geismar Ancien Ets L METHOD AND SYSTEM FOR EXTENDING A RAILWAY PATH
CN104131501B (en) * 2014-07-01 2015-12-30 昆明理工大学 A kind of mobile loading car
CN104709152B (en) * 2014-11-24 2017-04-19 中国煤炭科工集团太原研究院有限公司 Middle trough moving van

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3929204A (en) * 1975-01-22 1975-12-30 Lawrence Hugh Newell Trailer crane with outrigger to crawler conversion
JPS5844103A (en) * 1981-09-11 1983-03-15 株式会社日立製作所 Vertical taking type track handling apparatus
JPS62152964A (en) * 1985-12-26 1987-07-07 富士重工業株式会社 Flat freight car with self-travelling crane
JPS631698A (en) * 1986-06-19 1988-01-06 堀川工機株式会社 Method of transporting crane mounted and fixed to freight train
US5174211A (en) * 1991-08-05 1992-12-29 Snead Edwin D Panel track delivery system
FI94447C (en) 1993-05-07 1995-09-11 Desec Instmsto Lifting device for handling a rail element
FR2780993B1 (en) * 1998-07-10 2000-10-13 Fassetta Mecanique METHOD AND DEVICE FOR LAYING TRACK ELEMENT BY TRACKED LORRIES

Also Published As

Publication number Publication date
DE502005004712D1 (en) 2008-08-28
AU2005234729A1 (en) 2006-06-08
EP1659221A1 (en) 2006-05-24
AU2005234729B2 (en) 2010-10-21
US20060117987A1 (en) 2006-06-08
CN1779073A (en) 2006-05-31
ATE401456T1 (en) 2008-08-15
JP2006143201A (en) 2006-06-08
EP1659221B1 (en) 2008-07-16
AT501047B1 (en) 2006-06-15
JP4669378B2 (en) 2011-04-13
AT501047A4 (en) 2006-06-15

Similar Documents

Publication Publication Date Title
US4249467A (en) Mobile apparatus for receiving and laying as assembled track switch or crossing section
JP3746105B2 (en) Rail loading car
RU2088720C1 (en) Track section transportation device
RU2207423C2 (en) Machine for and method of removing old and laying new rail track
CN104355122A (en) Conveyor of lifting roller machine
CN110273375B (en) Bridge erecting machine
CN100564676C (en) The portal jib crane transfer cart
RU2117721C1 (en) Machine for laying railway track
CN200974948Y (en) Longitudinal-moving platform car for railroad switch laying
KR20150070578A (en) Construction Method
JPH08245161A (en) Track-running movable crane
JP3831487B2 (en) Track construction machine for digging track material
JP2018100587A (en) Rail transport vehicle
CN211815503U (en) Obstacle-crossing support type aluminum ladder system
CN207903820U (en) A kind of two-way side draw device
BG64731B1 (en) Apparatus for moving containers
CN203821184U (en) Spreader used for separating and paving roadbed slabs
CN101052767B (en) Mechanism for updating rail
CN107963572A (en) A kind of two-way side draw device
CN215401345U (en) Brick feeding equipment for brick making machine
CN201849911U (en) Conveying device for heavy equipment
CN2412801Y (en) Rail train marshalling station railway carriage transversing transponting equipment
CN218657642U (en) Automatic replacing equipment for efficient bogie
RU2222658C2 (en) Cantilever track-laying machine for changing switch units (versions)
CN216893560U (en) Conveyer on complex steel structure bridge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20091202

Termination date: 20201122