spring plate
shield
steel spring
rubber tile
walling crib
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2005101120995A
Other languages
Chinese (zh)
Other versions
CN1807839A (en
Inventor
陆明
朱祖熹
邵臻
乔宗昭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Tunnel Engineering and Rail Transit Design and Research Institute
Original Assignee
Shanghai Tunnel Engineering and Rail Transit Design and Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Tunnel Engineering and Rail Transit Design and Research Institute filed Critical Shanghai Tunnel Engineering and Rail Transit Design and Research Institute
Priority to CNB2005101120995A priority Critical patent/CN100552186C/en
Publication of CN1807839A publication Critical patent/CN1807839A/en
Application granted granted Critical
Publication of CN100552186C publication Critical patent/CN100552186C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention relates to the waterproof method class, concrete relate to a kind of be used for the underground structure shield tunnel advance the hole waterproof method, the characteristics of this waterproof method are: before cast tunnel walling crib concrete, pre-buried gas tube, the mouth of pipe connects air bag and extraneous source of the gas; Before shield, cord rubber tile, steel spring plate and air bag are installed afterwards; During shield, airbag aeration is expanded, compressing promotes steel spring plate, thereby compresses rubber tile, and its advantage is when shield, airbag aeration expands, rubber tile closely is wrapped in shield structure or lining cutting external surface, makes that gap location has good watertightness between shield structure and the walling crib, avoided issuable muddy water seepage, change the single measure that shield in the past only depends on soil stabilization, improved the safety factor of shield.

Description

Shield tunnel advance the hole waterproof method
Technical field
The present invention relates to the waterproof method class, relate to concretely a kind of be used for the underground structure shield tunnel advance the hole waterproof method.
Background technology
The hole waterproof of advancing of existing shield tunnel is undertaken by the soil stabilization mode, general main is to advance soil body processing modes constructions such as the employing of surrounding area, hole agitation pile, rotary churning pile or freezing process, agitation pile, rotary churning pile are mainly constructed principle for forming continuous water-stop curtain in the soil body in the certain limit of hole, in conjunction with and the point dewatering method excavate the safety of face to guarantee shield; Freezing process is mainly constructed principle for advancing hole employing freezing equipment, makes the soil body in the certain limit freeze hardening, has guaranteed the safety of shield excavation face.Its shortcoming is that the soil stabilization scope is bigger, guarantee that the homogenieity of reinforcing is very difficult, though the on-the-spot detection of can taking a sample, sample point is limited, can't guarantee that the whole soil body all reaches designing requirement.
Summary of the invention
The objective of the invention is according to above-mentioned the deficiencies in the prior art part, what a kind of shield tunnel was provided advances the hole waterproof method, this method is in walling crib import department rubber tile to be set, and by the pressing to it of air bag and steel spring plate, the watertight requirement when satisfying shield.
The object of the invention realizes being finished by following technical scheme:
A kind of shield tunnel advance the hole waterproof method, comprise walling crib, lining segment, cord rubber tile, the cord rubber tile is between walling crib and lining segment outer wall, it is characterized in that this method adopts following step: before cast tunnel walling crib concrete, pre-buried gas tube, the mouth of pipe connects air bag and extraneous source of the gas; Before shield, cord rubber tile, steel spring plate and air bag are installed afterwards; During shield, airbag aeration is expanded, compressing promotes steel spring plate, thereby compresses rubber tile.
Pre-buried gas tube radical is corresponding one by one with the air bag number that is connected.
Wherein the installation of cord rubber tile, steel spring plate can be that steel spring plate and rubber tile are fitted, form fit, and an end of the two fitting body is fixedlyed connected with the walling crib inwall, and other end steel spring plate tightly is wrapped in the lining segment outer wall by rubber tile.
Angle Selection is set in the installation of steel spring plate and rubber tile and the lining segment outer wall is about 45, and effect is relatively good.
The installation of steel spring plate also comprises the installation of an other arcuation steel spring plate, the installation site of this steel plate and steel spring plate installation site are arranged in a crossed manner, its mounting method can be that the one end is fixedlyed connected with the walling crib inwall, it is circular-arc that the other end is, this circular-arc end contacts with steel spring plate under the air bag effect after the inflation, and to its generation pressure, what of airbag aeration amount are the size of pressure depend on.
Described fixedly connected be before cast walling crib concrete, embedded nut adopts bolt to connect on the walling crib steel plate afterwards.
Described air bag quantity is two, and the two discharges successively, inflates a back contact pressuring spring steel plate, another contact compressing arcuation latch plate.
Advantage of the present invention is, when shield, airbag aeration expands, rubber tile closely is wrapped in shield structure or lining cutting external surface, make that gap location has good watertightness between shield structure and the walling crib, avoid issuable muddy water seepage, changed the single measure that shield in the past only depends on soil stabilization, improved the safety factor of shield.
Description of drawings
Accompanying drawing 1 is shield soil stabilization figure;
Accompanying drawing 2 is the utility model structural representation;
The specific embodiment
Feature of the present invention and other correlated characteristic are described in further detail by embodiment below in conjunction with accompanying drawing, so that technician's of the same trade understanding:
Shown in Fig. 1-2, label 1-21 represents respectively: the circular-arc end 15 of acorn nut 1, tee junction 2, walling crib 3, packing ring 4, bolt 5, briquetting 6, air bag 7, cord rubber tile 8, steel spring plate 9, arcuation steel spring plate 10, lining segment outer wall 11, gas tube 12, walling crib steel plate 13, acorn nut 14, arcuation steel spring plate 10, shield structure direction of propulsion 16, the soil body through reinforcing 17, space enclosing structure 18, liner 19, pre-buried steel loop 20, steel hoop concrete protective circle 21.
The shield tunnel that present embodiment relates to advance the hole waterproof method, comprise walling crib 3, lining segment outer wall 11, cord rubber tile 8, steel spring plate 9, arcuation steel spring plate 10, air bag 7 and gas tube 12 thereof, cord rubber tile 8 is between walling crib 3 and lining segment outer wall 11, and this method adopts following step:
Before cast tunnel walling crib concrete, pre-buried acorn nut 1 on walling crib steel plate 13, pre-buried two gas tubes 12 simultaneously, gas tube 12 is connected with tee junction 2.
Afterwards before shield, cord rubber tile 8 and steel spring plate 9, arcuation steel spring plate 10, air bag 7 are installed, wherein the installation of cord rubber tile 8, steel spring plate 9 is that steel spring plate 9 and cord rubber tile 8 are fitted, the two form fit, and an end of the two fitting body and walling crib steel plate 13 adopt briquetting 6 to be fixed in pre-buried acorn nut 1 place by bolt 5, other end steel spring plate 9 tightly is wrapped in lining segment outer wall 11 by cord rubber tile 8, and it is to be 45 with lining segment outer wall 11 that the installation of steel spring plate 9 and cord rubber tile 8 is provided with angle; The installation of arcuation steel spring plate 10, the installation site of this steel plate 10 and steel spring plate 9 installation sites are arranged in a crossed manner, its mounting method is to adopt bolt 5 to be fixed in pre-buried acorn nut 14 places at one end and walling crib steel plate 13, it is circular-arc that the other end is, this circular-arc end contacts with steel spring plate under the air bag effect after the inflation, and to its generation pressure, what of airbag aeration amount are the size of pressure depend on.
When shield, airbag aeration is expanded at last, compressing promotes steel spring plate 9 and arcuation steel spring plate 10, thereby acts on cord rubber tile 8, makes cord rubber tile 8 closely be wrapped in lining segment outer wall 11, reaches the watertight requirement.
One end of above-mentioned two pre-buried gas tubes 12 is connected to air bag 7 respectively, and the other end is communicated with extraneous source of the gas by tee junction 2.
Above-mentioned air bag 7 quantity are two, and the two discharges successively, inflate a back contact pressuring spring steel plate 9, another contact compressing arcuation latch plate 10.
In the present embodiment steel spring plate 9 and arcuation steel spring plate 10 and air bag 7 all be to be provided with ringwise along walling crib inwall circumferencial direction.Obviously the setting that those skilled in the art will recognize that air bag 7 also can be evenly segmentation setting along the circumferential direction, and the position of set certainly gas tube is also corresponding with it, so long as can realize steel plate 9, the 10 even application of forces are got final product.

Claims (5)

1, a kind of shield tunnel advances the hole waterproof method, comprise walling crib, lining segment, cord rubber tile, the cord rubber tile is between walling crib and lining segment outer wall, it is characterized in that this method adopts following step: before cast tunnel doubling-up concrete, pre-buried gas tube, the mouth of pipe connects air bag and extraneous source of the gas; Afterwards before shield, the cord rubber tile is installed, steel spring plate and air bag, described cord rubber tile, the installation of steel spring plate is that steel spring plate and rubber tile are fitted, form fit, one end of the two fitting body is fixedlyed connected with the walling crib inwall, other end steel spring plate tightly is wrapped in the lining segment outer wall by rubber tile, the installation of described steel spring plate also comprises the installation of an other arcuation steel spring plate, the installation site of this steel plate and steel spring plate installation site are arranged in a crossed manner, its mounting method is that the one end is fixedlyed connected with the walling crib inwall, it is circular-arc that the other end is, this circular-arc end contacts with steel spring plate under the air bag effect after the inflation, and to its generation pressure, what of airbag aeration amount are the size of pressure depend on; During shield, airbag aeration is expanded, compressing promotes steel spring plate, thereby compresses rubber tile.
2, a kind of shield tunnel according to claim 1 advance the hole waterproof method, it is characterized in that pre-buried gas tube radical corresponding one by one with the air bag number that is connected.
3, a kind of shield tunnel according to claim 1 advance the hole waterproof method, it is to be 45 with the lining segment outer wall that the installation that it is characterized in that described steel spring plate and rubber tile is provided with angle.
4, a kind of shield tunnel according to claim 1 advance the hole waterproof method, it is characterized in that described fixedly connected be before cast walling crib concrete, embedded nut adopts bolt to connect on the walling crib steel plate afterwards.
5, a kind of shield tunnel according to claim 1 advance the hole waterproof method, it is characterized in that set air bag quantity is two, the two is closely discharging successively, inflates a back contact pressuring spring steel plate, another contact compressing arcuation steel spring plate.
CNB2005101120995A 2005-12-27 2005-12-27 Shield tunnel advance the hole waterproof method Expired - Fee Related CN100552186C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2005101120995A CN100552186C (en) 2005-12-27 2005-12-27 Shield tunnel advance the hole waterproof method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2005101120995A CN100552186C (en) 2005-12-27 2005-12-27 Shield tunnel advance the hole waterproof method

Publications (2)

Publication Number Publication Date
CN1807839A CN1807839A (en) 2006-07-26
CN100552186C true CN100552186C (en) 2009-10-21

Family

ID=36839916

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2005101120995A Expired - Fee Related CN100552186C (en) 2005-12-27 2005-12-27 Shield tunnel advance the hole waterproof method

Country Status (1)

Country Link
CN (1) CN100552186C (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101660419B (en) * 2008-08-27 2013-05-29 上海市机械施工有限公司 Construction method for putting tunnel shield into hole in special stratum
CN101566063B (en) * 2009-06-04 2011-02-09 上海交通大学 Method of reinforcing soil body for inlet and outlet cave mouths of tunnel shield
CN102296621B (en) * 2011-05-27 2013-09-25 深圳市市政设计研究院有限公司 Construction method of ground sectional water-stop curtain
CN102588609A (en) * 2012-03-16 2012-07-18 盾建重工制造有限公司 Emergency tail seal device for shield machine and mounting structure thereof
CN102797468B (en) * 2012-08-22 2015-04-22 中铁第四勘察设计院集团有限公司 Minimum over-burden originating method for shield tunnel
CN104033167B (en) * 2013-03-08 2016-02-24 国家电网公司 The water-tight device of cable tunnel outlet and waterproof method
CN103867158B (en) * 2014-02-28 2017-01-25 中铁隧道集团有限公司 Underwater drilling fast blockage air bag and blockage method thereof
CN109026150B (en) * 2018-08-30 2020-09-15 上海隧道工程有限公司 Built-in air bag sealing device and sealing method for pipe joint of tunnel connecting channel pipe jacking method
CN110374640B (en) * 2019-08-19 2021-07-30 上海市基础工程集团有限公司 Sand-stopping and water-stopping device for head of pipe-jacking tunnel
CN111828094B (en) * 2020-06-30 2021-10-12 上海大学 Deep-buried earth pressure balance shield hole-entering double-air-bag sealing device and sealing method thereof

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
盾构法隧道出洞防水装置的设计优化与演变. 陆明,曹伟飚,朱祖熹.中国建筑防水,第10期. 2005
盾构法隧道出洞防水装置的设计优化与演变. 陆明等陆明,曹伟飚,朱祖熹中国建筑防水.中国建筑防水,第10期. 2005
盾构法隧道出洞防水装置的设计优化与演变. 陆明,曹伟飚,朱祖熹.中国建筑防水,第10期. 2005 *
盾构法隧道防水堵漏技术. 温竹茵,张庆贺,郑,坚,秦鸿元.盾构法隧道防水堵漏技术,第28卷第4期. 1999
盾构法隧道防水堵漏技术. 温竹茵,张庆贺,郑坚,秦鸿元.盾构法隧道防水堵漏技术,第28卷第4期. 1999 *

Also Published As

Publication number Publication date
CN1807839A (en) 2006-07-26

Similar Documents

Publication Publication Date Title
CN100552186C (en) Shield tunnel advance the hole waterproof method
CN100419210C (en) Waterproof device for entrance of shield tunnel
CN209742914U (en) Backfill grouting rubber and inflate plugging device behind underground construction
CN109595392B (en) F-shaped reinforced concrete relay room jacking pipe
US3665717A (en) Method and apparatus for installing elongated rods in unstable earth formations
CN205025479U (en) Administer bottom plate support system of soft rock tunnel pucking
WO2008009344A3 (en) Fastening of plastic film and precast concrete parts to anchors
CN207761660U (en) A kind of relaying jacking system of band support adjusted device
CN2856419Y (en) Cave entrance waterproof appts of shield tunnel
CN203145029U (en) Plugging structure for deep foundation pit dewatering well
CN101705788B (en) Construction method using blowout plug to shield oblique drilling hole
CN114718060A (en) Wing-type inflatable anchor pipe and construction method thereof
CN203175569U (en) Steel tube piece tunnel portal water-proof sealing structure in shield-driven tunnel breakthrough
CN210978736U (en) Curved pipe jacking interface water stop structure suitable for high water pressure condition
CN1166852C (en) Construction mode with full cross-section tunneller
CN214384161U (en) Shield constructs quick-witted tunnel portal sealing water stop device that starts
JP4482423B2 (en) Pipe line replacement method and new pipe update device
CN210661351U (en) Air-filled sealing protective air bag of shield machine
CN201407051Y (en) Karst formation pile hole wall protection structure
CN202531092U (en) Hole packer
JP2002180780A (en) Sealing method for shaft arrival of shield machine and its device
CN216715579U (en) Interim plugging device of pipeline
JP3401177B2 (en) Sewer renewal shield excavator
CN212839736U (en) Reinforced concrete roof pipe structure
CN210395454U (en) Open caisson reserved hole plugging waterproof structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20091021

Termination date: 20171227