CN100464055C - 利用pba法进行浅埋暗挖隧道超大断面的施工方法 - Google Patents

利用pba法进行浅埋暗挖隧道超大断面的施工方法 Download PDF

Info

Publication number
CN100464055C
CN100464055C CNB2007100599130A CN200710059913A CN100464055C CN 100464055 C CN100464055 C CN 100464055C CN B2007100599130 A CNB2007100599130 A CN B2007100599130A CN 200710059913 A CN200710059913 A CN 200710059913A CN 100464055 C CN100464055 C CN 100464055C
Authority
CN
China
Prior art keywords
tunnel
construction
section
arch
pba
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2007100599130A
Other languages
English (en)
Other versions
CN101225742A (zh
Inventor
童顺军
黄广锴
安建平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
Original Assignee
China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 18th Bureau Group Co Ltd filed Critical China Railway 18th Bureau Group Co Ltd
Priority to CNB2007100599130A priority Critical patent/CN100464055C/zh
Publication of CN101225742A publication Critical patent/CN101225742A/zh
Application granted granted Critical
Publication of CN100464055C publication Critical patent/CN100464055C/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

一种利用PBA法进行浅埋暗挖隧道超大断面的施工方法,1.对于大跨度隧道结构上方地层空洞进行检测;2.布置地面降水井和洞内水平井;3.利用竖井横通道施作主体拱部超前大管棚,并预注浆加固地层;4.进行小导洞边跨扣拱施工和主体扣顶大弧施工;5.开挖下断面土体施作扩大基础及中隔壁;6.分段拆除底部中隔壁,施工底部垫层、防水层,浇筑钢筋混凝土;7.分段拆除上部中隔壁及小导洞内临时钢支撑、施作边墙及主拱防水层、混凝土。本发明的优点是:可保证施工安全、质量和工期,并可节省费用、提高工效。

Description

利用PBA法进行浅埋暗挖隧道超大断面的施工方法
技术领域:
本发明属于一种建筑施工方法,特别涉及一种利用PBA法进行浅埋暗挖隧道超大断面的施工方法。
背景技术:
目前国内大跨隧道的施工技术水平,适合选用的施工方法主要有明挖法和浅埋暗挖法。其中浅埋暗挖法又包括双侧壁导坑法和在大跨地铁车站采用过的“PBA”法。但是,这些方法对于周边环境复杂、地下管线密集、地质条件差、地下水丰富,并且断面跨度大的施工环境,均存在不同的缺陷和局限性。
1、明挖法对于地面交通繁多、地下管线繁多的工况,施工时必须进行管线改移和交通疏解,因此施工所受干扰大,工期长;另外,在进行管线临时改移及占地费用高,经济性差。
2、采用的浅埋暗挖双侧壁导坑法,对于隧道地质条件差、周边环境复杂、涉及影响地下管线繁多的施工环境,对结构上方管线及周边环境安全控制极为不利,施工风险大,从理论上分析难以保证安全。
而PBA法由于其适用范围较广,适用于地层、地质条件很差、跨度大、地面沉降要求严格的隧道开挖,并且可减小地面沉降、拆除临时支护工作量相对较小,简化了施工工艺、工效较高,从而应用在大跨地铁车站的施工中,但是还没有应用在大跨度隧道的施工。
发明内容:
本发明的目的就在于克服上述现有技术中存在的不足,而提供一种利用PBA法进行浅埋暗挖隧道超大断面的施工方法,该施工方法可保证施工安全、质量和工期,并可节省费用、提高工效。
本发明的技术方案是:一种利用PBA法进行浅埋暗挖隧道超大断面的施工方法,其特征在于:依照下列步骤进行:
(1)对于大跨度隧道结构上方地层空洞进行检测;
(2)布置地面降水井和洞内水平井;
(3)利用竖井横通道(管棚操作室)施作主体拱部超前大管棚,并预注浆加固地层;
(4)施工小导洞并预埋连接钢筋;
(5)架设小导洞格栅拱架,并与预埋连接钢筋连接;
(6)对导洞内初支背后灌注混凝土回填混凝土;
(7)开挖左、右侧拱部,架设主拱格栅,并与预埋连接钢筋连接;
(8)开挖左侧下导洞和右侧下导洞,施作中隔墙和下部临时支撑;
(9)开挖下断面土体施作扩大基础及中隔壁;
(10)分段拆除底部中隔壁,施工底部垫层、防水层,浇筑钢筋混凝土;
(11)分段拆除上部中隔壁及小导洞内临时钢支撑、施作边墙及主拱防水层、混凝土。
上述大管棚的施作采用无缝钢管分段打设的方法,每段之间纵向搭接。
上述大管棚的施工采用钻孔静压顶入法施工,设备选用HXY-500M地质钻机。
上述大跨度隧道结构上方地层空洞的检测采用探地雷达检测GPR技术。
上述小导洞格栅与预埋钢筋采用搭接焊连接,主拱格栅与连接钢筋采用搭接焊连接,使之与小导洞格栅连接成整体。
本发明具有如下的优点和积极效果:
(1)突破了以往“PBA”法仅局限用于多跨多层地下车站及停车场浅埋暗挖工程项目中,解决了“PBA”法应用于浅埋暗挖单跨超大断面隧道中综合性技术难题。
(2)采用探地雷达检测(GPR)技术进行大跨段隧道结构上方地层空洞的检测,解决了在地层条件差,周边环境复杂,受施工干扰大的情况下,进行浅埋暗挖大跨隧道施工前,如何进行地层空洞检测的难题;
(3)采用地面井点+洞内水平井降水的处理措施,有效地解决了“PBA”法在富水区域进行大跨隧道浅埋暗挖施工时地下水处理的难题。
(4)采用钻孔静压顶入,并在主体结构中部增设管棚操作室办法,解决了施工操作空间受限,上部管线密集,对管棚施工精度、沉降要求极高的情况下,进行长大管棚施作的技术性难题;
(5)格栅钢架连接施工方法后,解决了大跨隧道“PBA”工法扣拱施工安全性差,两次扣拱连接精度不高的技术性难题;
(6)选用合理的临时支护拆除、换撑方法及二衬砼支撑体系,确保了大跨隧道二衬施工临时支护拆除过程中结构的安全,保证了超大断面砼结构的施工质量。
附图说明:
图1是本发明的施工流程图。
图2是降水井施工工艺流程图。
图3是主体拱部大管棚设置示意图。
图4是管棚分段施工平面示意图。
图5是管棚施工流程图。
图6是扣拱施工示意图。其中,图6—1是施工小导洞并预埋连接钢筋示意图;图6-2是小导洞内扣拱示意图;图6-3是回填导洞内混凝土示意图;图6-4是开挖左侧拱部(1号导洞)并架设拱部格栅示意图;图6-5开挖右侧拱部(2号导洞)并架设拱部格栅示意图;图6-6是开挖左侧下导洞(3号导洞),施作下部临时支撑示意图;图6-7是开挖右侧拱部(4号导洞),施作下部临时支撑示意图。
具体实施方式:
苏黄区间超大断面隧道为北京地铁四、十号线联络线岔线段,由单孔双线过渡为单孔三线,设计采用拱顶直墙型断面。同时大跨段隧道根据线路走向又分成三种不同尺寸的断面:断面E,里程K2+240.3~K2+262.5,长22.2m,跨度15.076m,高度9.3m;断面E’,里程K2+262.5~K2+282.3,长19.8m,跨度15.937m,高9.855m;断面F,里程K2+282.3~K2+296.3,长14.0m,跨度17.5m,高度10.5m。其施工方法依照下列步骤进行:(如图1所示)
1、对于大跨度隧道结构上方地层空洞进行检测:
本次探测工作采用了目前国内外先进的高分辨率美国产SIR-2型探地雷达检测***。该探地雷达配置中心频率100MHz天线,可靠探测深度在6m左右,能满足本工程需求。
取顺隧道主体结构中心及隧道外结构线外侧5m方向布置3条测线,根据接收天线所接收并由仪器记录下来反射波的情况进行数据处理。
2、布置地面降水井和洞内水平井:
根据地质详勘资料表明,苏黄区间大跨段在开挖深度范围内主要受台地潜水、层间潜水的影响。台地潜水主要分布在结构顶板上方0.8~3.60m的范围内,并且顶板上方覆盖较厚的粉质粘土层,富水的粉质粘土经施工扰动后极易液化,成流泥状,隧道开挖过程种易出现坍塌、掉块现象,加之隧道开挖扰动及地下水流失容易加剧地表沉降,增大了施工风险。根据“PBA”工法特点,并结合水文、地质情况,施工中采用了地面井点+洞内水平井降水的处理措施,保证施工过程的安全。
(1)布置地面降水井。降水井顺线路方向,沿隧道两侧布置,间距6~8m,共布降水井20眼,采用φ400/50mm无砂水泥管,井管缠80目尼龙纱网,管外填φ20~40mm滤料至地面以下1.5m处。施工采用反循环和冲击钻钻机成孔,孔径600mm,采用高扬程潜水泵进行抽、排水。如图2所示:
具体施工过程如下:
A、定井位
根据降水井位图、地下管线分布图及坐标控制点施放降水井井位。为保证安全,定井位后应物探结合人工洛阳铲探明井位处有无地下管线、地下障碍物。
B、人工探孔
挖孔直径1000mm,每挖进800mm,做一次护壁,模板居中支撑,四周所留孔缝均匀,保证10cm厚度。每上、下两层护壁必须搭接50mm—100mm。对挖孔中遇到的可疑地物,不许直接破坏,经现场管理人员批准后方可继续施工。
C、挖坑垒砌泥浆池
为保证钻进过程水流循环及保存钻孔出渣,在现场用加气块围泥浆池,并在泥浆池内铺设塑料布,防止浆液外露,外部用土支撑,施工完毕后将所剩残渣除清场外。
D、钻机就位、调整
钻机就位时需调整钻机的平整度和钻塔的垂直度,对位后用机台木垫实,保证钻机安放平稳。
E、钻孔
在钻孔过程中应保证孔内泥浆液面在钢护桶之上。在地层条件允许的情况下,尽量使用地层自造泥浆成孔,若钻孔通过易塌孔的流砂层或泥浆漏失严重的地层时,可采用人工造浆护壁钻进,泥浆比重调至1.1~1.3。
F、下管
下管前应检查井管是否已按要求包缠尼龙网;无砂水泥管接口处要用塑料布包严,钢管上下段焊接时要保证垂直度并焊接严实。井管必须确保在井孔居中。
G、填滤料
填料必须从井四周均匀缓慢填入,避免造成孔内架桥现象,洗井后若发现滤料下沉应及时补充滤料,填料高度按设计要求填至地面下3m。
H、洗井
采用压风机洗井,若井内沉没比不够时应注入清水。
(2)布置洞内水平井。
从前期竖井横通道开挖情况来看,拱部及掌子面渗水量较大。特别是隧道拱部位于粘土层中,地面深井降水不能形成降水漏斗,开挖过程中容易形成流泥,引起大量周边土层流失,容易造成地表超量下沉。经过认真分析研究之后,决定在大跨段隧道施工之前,利用竖井横通道空间,向大跨隧道方向增设水平井,对局部滞水提前引流,开挖时起到超前降水的效果。
水平井共设置6个,长度30~40米。施工采用HXY-500M地质钻机成孔,孔径为108mm,然后在孔内安放φ50mm钢花管,钢花管外部并缠裹两层80目滤网。
具体施工过程是:
施放井位→钻机就位→钻机调平、对位→螺旋成孔→下管→封孔→引水至竖井→排水出竖井外。
3、利用竖井横通道施作主体拱部超前大管棚,并预注浆加固地层。
苏黄区间三线大跨段拱部超前大管棚设计采用Φ159,t=10.0mm,1=56.0m的无缝钢管1,间距为0.4m,管棚施工完毕后进行注浆,注浆材料采用水泥浆。如图3所示。
由于56m长管棚一次性打设不利于管棚施工精度控制,加之结构上方管线繁多,也难以保证结构上方管线安全。综合各方因素,我们决定采用将56m长管棚分段打设的方案,管棚之间纵向搭接长度为3m。
首先利用竖井横通道做为第一段管棚操作空间,管棚打设长度为25m;然后在两侧小导洞开挖至K2+279.3处时,把左线小导洞和右线小导洞连通,设置成管棚操作室,第二段和第三段管棚利用操作室空间分别向小里程(E’断面)和大里程(F断面)方向施作和各20米长的大管棚,如图4所示。
管棚的施工工艺采用受操作空间影响较小的钻孔静压顶入法施工,设备选用HXY-500M地质钻机。施工工艺如图5所示。
4、进行扣拱施工,并按照如下工序完成;如图6所示。
①施工小导洞并预埋连接钢筋2;②架设小导洞内格栅3;③对导洞内初支背后灌注混凝土回填4;④开挖左侧拱部(1号导洞)并架设拱部格栅5;⑤开挖右侧拱部(2号导洞)并架设拱部格栅6;6、开挖左侧下导洞(3号导洞),施作下部临时支撑7;7、开挖右侧拱部(4号导洞),施作下部临时支撑8。上述小导洞格栅与预埋钢筋采用搭接焊连接,在主体开挖时,将主拱格栅与连接钢筋采用搭接焊连接,使之与小导洞格栅连接成整体
5、开挖下断面土体施作扩大基础及中隔壁;
6、分段拆除底部中隔壁,施工底部垫层、防水层,浇筑钢筋混凝土;
7、分段拆除上部中隔壁及小导洞内临时钢支撑、施作边墙及主拱防水层、混凝土。

Claims (5)

1.一种利用PBA法进行浅埋暗挖隧道超大断面的施工方法,其特征在于:依照下列步骤进行:
(1)对于大跨度隧道结构上方地层空洞进行检测;
(2)布置地面降水井和洞内水平井;
(3)利用竖井横通道,即管棚操作室,施作主体拱部超前大管棚,并预注浆加固地层;
(4)施工小导洞并预埋连接钢筋;
(5)架设小导洞格栅拱架,并与预埋连接钢筋连接;
(6)对导洞内初支背后灌注混凝土回填混凝土;
(7)开挖左、右侧拱部,架设主拱格栅,并与预埋连接钢筋连接;
(8)开挖左侧下导洞和右侧下导洞,施作中隔墙和下部临时支撑;
(9)开挖下断面土体施作扩大基础及中隔壁;
(10)分段拆除底部中隔壁,施工底部垫层、防水层,浇筑钢筋混凝土;
(11)分段拆除上部中隔壁及小导洞内临时钢支撑、施作边墙及主拱防水层、混凝土。
2.根据权利要求1所述的利用PBA法进行浅埋暗挖隧道超大断面的施工方法,其特征在于:上述大管棚的施作采用无缝钢管分段打设的方法,每段之间纵向搭接。
3.根据权利要求1所述的利用PBA法进行浅埋暗挖隧道超大断面的施工方法,其特征在于:上述大管棚的施工采用钻孔静压顶入法施工,设备选用HXY-500M地质钻机。
4.根据权利要求1所述的利用PBA法进行浅埋暗挖隧道超大断面的施工方法,其特征在于:上述大跨度隧道结构上方地层空洞的检测采用探地雷达检测GPR技术。
5.根据权利要求1所述的利用PBA法进行浅埋暗挖隧道超大断面的施工方法,其特征在于:上述小导洞格栅与预埋钢筋采用搭接焊连接,主拱格栅与连接钢筋采用搭接焊连接,使之与小导洞格栅连接成整体。
CNB2007100599130A 2007-10-17 2007-10-17 利用pba法进行浅埋暗挖隧道超大断面的施工方法 Expired - Fee Related CN100464055C (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2007100599130A CN100464055C (zh) 2007-10-17 2007-10-17 利用pba法进行浅埋暗挖隧道超大断面的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2007100599130A CN100464055C (zh) 2007-10-17 2007-10-17 利用pba法进行浅埋暗挖隧道超大断面的施工方法

Publications (2)

Publication Number Publication Date
CN101225742A CN101225742A (zh) 2008-07-23
CN100464055C true CN100464055C (zh) 2009-02-25

Family

ID=39857920

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2007100599130A Expired - Fee Related CN100464055C (zh) 2007-10-17 2007-10-17 利用pba法进行浅埋暗挖隧道超大断面的施工方法

Country Status (1)

Country Link
CN (1) CN100464055C (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108729919A (zh) * 2018-06-07 2018-11-02 深圳市市政设计研究院有限公司 一种填石地层弧形变截面隧道浅埋暗挖施工方法

Families Citing this family (32)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101555798B (zh) * 2009-05-14 2011-03-23 中铁一局集团有限公司 逆向引孔机及用该引孔机进行pba边桩施工的方法
CN101812991B (zh) * 2009-10-30 2011-11-16 西南交通大学 铁路隧道回路式减压洞口的修建方法
CN102174894A (zh) * 2011-03-15 2011-09-07 中铁十二局集团第一工程有限公司 跟进式管棚施工方法
CN102226403B (zh) * 2011-03-30 2013-11-13 中铁一局集团有限公司 地铁大跨度车站主体拱盖法施工方法及车站主体结构
CN102287195B (zh) * 2011-05-13 2014-09-17 中铁四局集团第二工程有限公司 浅埋暗挖大跨度隧道下穿既有高速铁路施工方法
CN102305075A (zh) * 2011-06-28 2012-01-04 中国水利水电第五工程局有限公司 一种不良地质条件下的竖井施工方法
CN102505708B (zh) * 2011-10-21 2014-05-07 中冶建工集团有限公司 轨道交通超大断面明挖区间隧道施工方法
CN102518454B (zh) * 2011-12-22 2014-07-23 中铁工程设计咨询集团有限公司 一种用于暗挖工程的格栅装置及制作方法
CN102535302B (zh) * 2011-12-31 2014-01-01 北京工业大学 用于超浅埋暗挖地下工程的临时路面铺盖结构及施工方法
CN103075163B (zh) * 2012-12-28 2015-02-18 成都中铁隆工程集团有限公司 一种大断面隧道二衬施工换撑工艺
CN103244129B (zh) * 2013-05-22 2015-04-29 中铁十六局集团有限公司 一种立体交叉凹凸支点施工方法
CN103306248A (zh) * 2013-07-01 2013-09-18 中国水电顾问集团中南勘测设计研究院 一种高坝溢洪道地基排水***及开挖方法
CN103469817B (zh) * 2013-09-30 2015-05-13 中铁一局集团有限公司 一种既有地铁车站主体结构扩建施工方法
CN103527204B (zh) * 2013-11-06 2015-10-14 中铁第四勘察设计院集团有限公司 一种先墙后拱交叉中隔壁的隧道施工方法
CN104695877A (zh) * 2013-12-06 2015-06-10 中铁十三局集团有限公司 大管棚洛阳铲施工方法
CN104695983B (zh) * 2013-12-09 2017-02-01 中铁十三局集团有限公司 初支扣拱两端节点预埋钢筋焊接接头的焊接方法
CN104265305B (zh) * 2014-08-05 2016-06-01 中铁二十一局集团有限公司 从两个小断面洞室合并到一个大断面洞室的扩挖方法
CN104763433A (zh) * 2015-01-29 2015-07-08 中铁二院工程集团有限责任公司 上软下硬地层大跨地铁车站暗挖施工方法
CN105484777A (zh) * 2015-05-08 2016-04-13 中铁隧道勘测设计院有限公司 洞桩法车站导洞和主体钢拱架连接结构
CN106703814B (zh) * 2015-07-30 2019-07-12 宏润建设集团股份有限公司 暗挖地铁车站洞桩施工方法
CN106437726B (zh) * 2016-11-02 2018-04-13 中铁二十局集团第五工程有限公司 浅埋暗挖隧道过地裂缝破碎带施工方法
CN107023300A (zh) * 2017-04-13 2017-08-08 中铁十六局集团地铁工程有限公司 一种采用棚护法建造地铁车站的施工方法
CN107288656B (zh) * 2017-06-20 2019-12-13 清华大学 一种水封洞库围岩主动承载体系的构筑方法
CN107503755A (zh) * 2017-09-08 2017-12-22 中铁十六局集团地铁工程有限公司 一种用免扣拱平顶洞桩法建造地铁车站的施工方法
CN110566223B (zh) * 2019-09-16 2021-01-26 北京市市政四建设工程有限责任公司 一种深埋pba地铁车站断面设计方法
CN110593893B (zh) * 2019-11-01 2024-04-12 中建八局轨道交通建设有限公司 正线隧道与施工横通道交叉处主体结构施工方法及其***
CN111155542B (zh) * 2020-01-14 2021-04-30 中铁隧道集团二处有限公司 一种基于引孔技术的pba工法隧道止水帷幕施工方法
CN111764932B (zh) * 2020-07-06 2021-11-02 高军 一种泥质富水破碎浅埋隧道低风险施工方法
CN113153414B (zh) * 2021-01-06 2023-02-28 西南交通大学 瓦斯隧道穿越下伏煤层采空区的处置措施及其施工方法
CN113027495B (zh) * 2021-05-26 2021-07-23 中国铁路设计集团有限公司 一种由区间隧道组织实施的暗挖大跨度车站修建方法
CN113898348A (zh) * 2021-08-04 2022-01-07 中铁二院工程集团有限责任公司 一种超浅埋大跨暗挖地铁车站隧道修建方法
CN114320340B (zh) * 2021-12-28 2023-09-12 中铁第六勘察设计院集团有限公司 基于超前导洞及对拉锚索的大跨无柱地下隧洞结构及方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1055214A (zh) * 1991-05-25 1991-10-09 北京市城建设计研究院 修建大型地下空间的方法
JP2002242583A (ja) * 2001-02-22 2002-08-28 Ishikawajima Constr Materials Co Ltd トンネル構造物およびその施工方法
JP2005120622A (ja) * 2003-10-15 2005-05-12 Makoto Uemura 地下構造物の施工法
JP2006037496A (ja) * 2004-07-27 2006-02-09 Ohbayashi Corp 底設導坑先進アーチパイプルーフ工法
CN2839559Y (zh) * 2005-08-09 2006-11-22 同济大学 连拱隧道

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1055214A (zh) * 1991-05-25 1991-10-09 北京市城建设计研究院 修建大型地下空间的方法
JP2002242583A (ja) * 2001-02-22 2002-08-28 Ishikawajima Constr Materials Co Ltd トンネル構造物およびその施工方法
JP2005120622A (ja) * 2003-10-15 2005-05-12 Makoto Uemura 地下構造物の施工法
JP2006037496A (ja) * 2004-07-27 2006-02-09 Ohbayashi Corp 底設導坑先進アーチパイプルーフ工法
CN2839559Y (zh) * 2005-08-09 2006-11-22 同济大学 连拱隧道

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108729919A (zh) * 2018-06-07 2018-11-02 深圳市市政设计研究院有限公司 一种填石地层弧形变截面隧道浅埋暗挖施工方法
CN108729919B (zh) * 2018-06-07 2019-07-05 深圳市市政设计研究院有限公司 一种填石地层弧形变截面隧道浅埋暗挖施工方法

Also Published As

Publication number Publication date
CN101225742A (zh) 2008-07-23

Similar Documents

Publication Publication Date Title
CN100464055C (zh) 利用pba法进行浅埋暗挖隧道超大断面的施工方法
CN103089275B (zh) 富水极破碎围岩隧道塌方段围岩控制方法
CN104612162B (zh) 一种地铁车站深基坑开挖施工方法
CN101864960B (zh) 岩溶地区双连拱公路隧道施工方法
CN101994513B (zh) 上半断面完成全断面帷幕注浆隧道施工方法
CN102865103B (zh) 一种矿井地下水的分布式利用方法
CN106437726B (zh) 浅埋暗挖隧道过地裂缝破碎带施工方法
CN106837353A (zh) 填充性岩溶隧道施工处理方法
CN110080237A (zh) 坑底浅覆土地铁隧道基坑土方开挖抗浮施工方法及结构
CN102352757B (zh) 盾构机空推过矿山法隧道时控制管片上浮的方法
CN102425421B (zh) 适用于矿山竖井的防治水方法
CN106907164A (zh) 一种水底矿山盾构隧道组合对接结构形式及其施工方法
CN103603689A (zh) 一种采空区处理帷幕灌浆的施工方法
CN103628912A (zh) 一种采空区处理充填灌浆的施工方法
CN110512593A (zh) 填海区超深地连墙结构及其施工方法
CN109322330A (zh) 一种避免房屋拆迁的明暗挖结合地铁车站结构及其施工方法
CN105239598A (zh) 井式全自动立体车库的整体下沉施工方法
CN102748040A (zh) 地铁大跨度车站主体结构及其柱拱法施工方法
CN101205721A (zh) 深水低桩承台施工中用钢围堰结合高压旋喷桩围水的方法
CN107023300A (zh) 一种采用棚护法建造地铁车站的施工方法
CN108797620A (zh) 一种opt咬合桩施工方法
CN106122589A (zh) 一种土压平衡法
CN108678753B (zh) 反坡隧道施工方法
CN109706945A (zh) 滑坡断裂带隧道进洞施工方法
CN102808627A (zh) 钢管棚暗挖施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP02 Change in the address of a patent holder

Address after: 300222 No. 18 South Dagu Road, Shuang Gang Town, Jinnan District, Tianjin

Patentee after: CHINA RAILWAY 18 BUREAU GROUP Co.,Ltd.

Address before: 300222 Liulin, Hexi District, Tianjin

Patentee before: CHINA RAILWAY 18 BUREAU GROUP Co.,Ltd.

C56 Change in the name or address of the patentee
CP02 Change in the address of a patent holder

Address after: 300222 Tianjin Town, Jinnan District

Patentee after: CHINA RAILWAY 18 BUREAU GROUP Co.,Ltd.

Address before: 300222 No. 18 South Dagu Road, Shuang Gang Town, Jinnan District, Tianjin

Patentee before: CHINA RAILWAY 18 BUREAU GROUP Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090225