CH394057A - Procedure for the foundation of a prefabricated structure - Google Patents

Procedure for the foundation of a prefabricated structure

Info

Publication number
CH394057A
CH394057A CH184462A CH184462A CH394057A CH 394057 A CH394057 A CH 394057A CH 184462 A CH184462 A CH 184462A CH 184462 A CH184462 A CH 184462A CH 394057 A CH394057 A CH 394057A
Authority
CH
Switzerland
Prior art keywords
building
soil
foundation
base
excavation
Prior art date
Application number
CH184462A
Other languages
German (de)
Inventor
Wilhelm Dipl Ing Degen
Original Assignee
Wilhelm Dipl Ing Degen
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wilhelm Dipl Ing Degen filed Critical Wilhelm Dipl Ing Degen
Priority to CH184462A priority Critical patent/CH394057A/en
Publication of CH394057A publication Critical patent/CH394057A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/02Improving by compacting
    • E02D3/046Improving by compacting by tamping or vibrating, e.g. with auxiliary watering of the soil
    • E02D3/054Improving by compacting by tamping or vibrating, e.g. with auxiliary watering of the soil involving penetration of the soil, e.g. vibroflotation
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/08Sinking workpieces into water or soil inasmuch as not provided for elsewhere
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/26Compacting soil locally before forming foundations; Construction of foundation structures by forcing binding substances into gravel fillings

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Description

  

      Verfahren    zur Gründung     eines        vorgefertigten    Baukörpers    Die vorliegende Erfindung betrifft ein Verfahren  zur Gründung eines vorgefertigten Baukörpers.  



  Die Vorteile einer Gründung von Bauwerksteilen  in vorgefertigtem Zustand liegen insbesondere darin,  dass durch eine Herstellung dieser Baukörper ausser  halb der Baugrube und auf einem Werkplatz mit  wesentlich besserer Zugänglichkeit grössere Gewähr  für die Erzielung einwandfreier Festigkeit und Dich  tigkeit gegeben ist.  



  Besondere Vorteile ergeben sich auch noch bei  der Gründung vorgefertigter Baukörper unter Wasser,  wenn der Baukörper durch eine besondere Isolie  rung - sei es zum Schutz gegen     Wasserdurchtritt     oder gegen Angriff durch aggressives Wasser oder  Lösung - geschützt werden muss. Dabei ist es, wie  bislang üblich, nicht mehr erforderlich, unter den  erschwerenden Bedingungen in einer engen, künstlich  trocken gehaltenen Baugrube den Unterboden und  darauf die Isolierbahn zu verlegen, da die Isolierung  und darüber gegebenenfalls eine Schutzschicht bereits  mit dem Baukörper ausserhalb der Baugrube her  gestellt werden können.  



  Wenn man dabei so verfährt, wie dies bisher die  Regel ist, dass man die     Baugrubensohle    dem Plan  entsprechend einebnet - bei unter Wasser befindli  chen Baugruben beispielsweise mit unter Wasser ar  beitenden Planierungsgeräten - und auf die so ge  schaffene Gründungssohle ein vorgefertigtes Bau  werksteil absetzt, so besteht keinerlei Sicherheit, dass  eine derartige Gründung allen hierfür zu stellenden  Anforderungen genügt. Es lässt sich insbesondere bei       grossflächigen    Gründungssohlen nicht vermeiden, dass  zwischen Baukörper und     Baugrubensohle        Hohlräume     verbleiben oder sich bilden.

   Für die statische Be  rechnung des Baukörpers muss deshalb aus Sicher  heitsgründen die ungünstigste Punktauflagerung des  Baukörpers angenommen werden.    Bei dem Bau von Unterwassertunneln hat man  für diesen besonderen Fall vor dem     Einschwimmen     der grossen Baukörper die Baugrube zwar schon  tiefer über die geplante     Bauwerksunterkante    ausge  hoben und den für den Vorgang erforderlichen grösse  ren Zwischenraum zwischen     Baukörperunterfläche     und     Baugrubensohle    mittels unter dem Baukörper  geführter Rohre mit Sand unterspült.

   Es liegt jedoch  auf der Hand, dass ein derartiges Verfahren nicht  voll befriedigen kann, da sich lose unter die Bau  werksunterfläche eingespülter Sand nicht in durch  gehend gleicher Lagerungsdichte mit Sicherheit ab  setzen lässt und damit grössere ungleichmässige Set  zungen zu erwarten sind. Auch bei dieser Gründungs  art muss aus Sicherheitsgründen mit sehr ungünstigen  statischen     Verhältnissen    gerechnet werden.  



  Der Erfindung     liegt    die Aufgabe zu Grunde, die  bekannten Nachteile bei Gründung eines Baukörpers  zu beseitigen.  



  Erfindungsgemäss geschieht dies bei einem Ver  fahren zur Gründung eines vorgefertigten Baukörpers  mit mindestens annähernd ebener     Grundfläche    im  Grundwasser, freien Wasser oder im trockenen  Boden, wobei der     Baugrund    so     nivelliert    wird, dass  seine Sohle wenige Zentimeter unter der Solltiefe  der geplanten Gründungssohle liegt, und wobei der  Baukörper durch Aufhängen oder Abstützen in Höhe  der Solltiefe der Gründungssohle gehalten wird, da  durch,

   dass man längs der     Baukörperrandzonen    unter  Zugabe von Bodenmaterial einen     Tiefenrüttler    in  den Boden des Untergrundes niederbringt und mit  diesem den Boden um     die    Randbereiche des Bau  körpers verdichtet und unter den Baukörper stopft  und dass man     schliesslich,    sofern unter der Baukörper  unterseite nach innen zu noch ein     Hohlraum    ver  bleibt, diesen durch Einpressen von erhärtenden Stof  fen satt ausfüllt.

        Soweit bei     einem    grossflächigen Baukörper die  ausserhalb am Rand des Baukörpers angesetzten       Tiefenrüttler    in     ihrer    Wirkung in waagrechter Rich  tung nicht mehr ausreichen, verbleibt unter dem  Baukörper ein     Hohlraum,    der jedoch durch den  unterstopften und verdichteten     Auffüllungsboden    um  schlossen ist. Dieser eingeschlossene Hohlraum wird  durch Einpressen geeigneter     Materialien,    wie z. B.  Zementmörtel, satt ausgefüllt, so dass seine erforder  liche Tragkraft zuverlässig und gleichmässig erreicht  werden kann.

   Der verdichtete     Auffüllungsboden     unterhalb der     Baukörperunterfläche    entlang des  Randes vom Baukörper bildet für das Einpressen  z. B. des Zementmörtels ein einwandfreies Wider  lager. Um eine einwandfreie Injektion und satte     Ver-          pressung    in dem vom     Bodenmaterial    fest einge  schlossenen Zwischenraum besonders bei grossflächi  gen Baukörpern zu erreichen, kann man in dem  Boden des     Baukörpers    zur     Durchführung    der Injek  tion z. B.

   Löcher anordnen, die sowohl das Einpres  sen von Injektionsgut als auch das     Einsetzen    von  Kontrollorganen gestatten und nach Beendigung des       Einpressungsvorganges    leicht verschlossen werden  können.  



  Ist der Boden unterhalb der     Bauwerksohle    von  nicht ausreichender Tragkraft, so kann zunächst der  Baugrund vor Einbringen des Baukörpers durch     Tie-          fenrüttler    oder durch unter Wasser arbeitende     Ober-          flächenrüttler    verdichtet und so homogenisiert wer  den, dass nach Aufbringen der Belastung bleibende  Setzungen ausgeschlossen werden.

   Ist jedoch der Bo  den unterhalb der     Bauwerksohle    nicht verdichtungs  fähig und nicht von     ausreichender        Tragfähigkeit,    so  tauscht man zweckmässig den Boden vor dem Einbrin  gen des Baukörpers aus und verdichtet ihn, worauf in  der bereits     dargelegten    Weise verfahren wird.  



  Die Zeichnung     zeigt    schematisch zwei     bevorzugte     Anwendungsbeispiele, und zwar zeigt:       Fig.    1 Querschnitt durch eine mit Grundwasser       angefüllte    Baugrube und den an einem Kran hängen  den     vorgefertigten    Bauwerksteil,       Fig.    2     Querschnitt    durch die gleiche Baugrube.  Die Baugrube ist mit Boden wieder verfüllt. Durch       Tiefenverdichtung    liegt der Bauwerksteil auf dem  Gründungsboden satt auf.  



  In     Fig.    1 ist ein Bauwerksteil 1 an einem     Kran    2  hängend in eine zuvor ohne Wasserhaltung ausge  hobene Baugrube 3 dargestellt. Die Baugrube 3 ist  um ein weniges tiefer ausgehoben, so dass nach Ein  bringen des     Bauwerkteiles    1 in seine Bestimmungs  lage zwischen Bauwerks- und     Baugrubensohle    ein  kleiner Zwischenraum verbleibt. Der Boden am  Rande und zum Teil unterhalb der Bauwerkssohle  wird nach     Wiederverfüllung    der Baugrube durch  einen     Tiefenrüttler    S verdichtet und unterstopft, so  dass nunmehr der     Bauwerksteil    auf der Gründungs  sohle am     Umfang    gleichmässig satt aufliegt.  



       Fig.    2 zeigt den Querschnitt des Bauwerksteiles,  nachdem die Baugrube wieder     verfüllt    und die     Tie-          fenverdichtung        fertiggestellt    ist. Durch eine Öffnung    6 im Boden des     Bauwerkteiles    wird Zementmörtel       eingepresst    und der nach der Verdichtung noch ver  bliebene Zwischenraum in der Mitte der Bauwerk  sohle gefüllt. Der Fortgang und die Beendigung des       Verpressvorganges    wird über in die Bauwerkssohle  eingelegte Röhrchen 7 verfolgt.  



  Durch eine Gründung nach dem vorliegenden  Verfahren werden alle gründungstechnischen Erfor  dernisse erfüllt, insbesondere wird eine zuverlässige  und gleichmässige Schliessung des Zwischenraumes  zwischen Bauwerks- und     Baugrubensohle    ohne die  Gefahr ungleichmässiger späterer Setzungen erzielt.  Der Baukörper liegt an allen Stellen seiner gesamten  Grundfläche gleichmässig satt auf, so dass für die  statische Dimensionierung des Bauwerkskörpers nun  mehr die günstigsten     Auflagebedingungen    angenom  men werden können.  



  Auch die Bauarbeiten selbst können schneller  und unter geringerem Kostenaufwand     durchgeführt     werden, weil nicht nur die Bauzeit für die Herstel  lung und Erhärtung des Baukörpers entfällt, sondern  zum Aushub der Baugrube auch eine im allgemeinen  erforderliche Wasserhaltung erspart werden kann, da  der Aushub und die Gründungsarbeiten unter Wasser  durchführbar sind.  



  Wenn die Platzverhältnisse es gestatten, kann  die Baugrube auch ohne Versteifung als offene Bau  grube mit sehr steilen Böschungen ausgehoben wer  den, weil diese infolge der Ausgeglichenheit des inne  ren und äusseren Wasserdruckes standfester sind. Die  Standfestigkeit der Böschung kann man durch künst  lichen     Aufstau    des Wasserspiegels in der Baugrube  erheblich erhöhen und braucht in allen diesen Fällen  keine besonderen Sicherheitsvorkehrungen     bezüglich     Standfestigkeit der Böschungen, weil nach dem vor  liegenden     Verfahren    in der Baugrube selbst sich  keine Arbeiter aufzuhalten brauchen.  



  Nach Einbringen des Baukörpers in seine     Soll-          Lage,    was vom Baugelände aus geschehen kann,  und nach Auffüllen des Zwischenraumes zwischen       Baugrubensohle    und     Baukörperunterfläche    sowie  seine     Unterstopfung,    wozu ebenfalls kein Betreten  der Baugrube nötig ist, können, wie erwähnt, viel  mehr alle Arbeiten zur Bildung des gewünschten  Fundamentes vom Inneren des Baukörpers aus vor  genommen und kontrolliert werden.  



  Wesentlich für die Standfestigkeit der     Baugruben-          böschungen    ist im übrigen auch,     dass    die     Wiederver-          füllung    der Baugrube bereits schon unmittelbar nach  Einbringen des Baukörpers vorgenommen werden  kann.



      Method for the foundation of a prefabricated structure The present invention relates to a method for the foundation of a prefabricated structure.



  The advantages of founding structural parts in a prefabricated state are, in particular, that by producing these structures outside the excavation pit and in a work area with much better accessibility, greater guarantee is given of achieving perfect strength and tightness.



  Special advantages also result from the foundation of prefabricated structures under water, if the structure has to be protected by special insulation - be it to protect against water penetration or against attack by aggressive water or solution. As has been the case up to now, it is no longer necessary to lay the subfloor and the insulating membrane on top of it in a narrow, artificially dry excavation under the aggravating conditions, since the insulation and, if necessary, a protective layer on top of it are already made with the structure outside the excavation can be.



  If you proceed as has been the rule up to now, that you level the base of the excavation according to the plan - in the case of underwater excavation pits, for example, with leveling equipment that works under water - and place a prefabricated structural component on the foundation base created in this way, then there is no guarantee that such a foundation will meet all of the requirements. Particularly in the case of large foundation bases, it cannot be avoided that cavities remain or form between the building structure and the base of the excavation.

   For safety reasons, the most unfavorable point support of the building must therefore be assumed for the static calculation of the building. When building underwater tunnels in this special case, before the large structures were floated in, the construction pit was dug deeper over the planned lower edge of the structure and the larger space required for the process between the lower surface of the structure and the base of the excavation was washed with sand using pipes running under the structure .

   It is obvious, however, that such a method cannot be fully satisfactory, since sand that is loosely washed under the building's undersurface cannot be safely deposited in a consistently uniform density, and larger, uneven settlements are to be expected. For safety reasons, very unfavorable static conditions must also be expected with this type of foundation.



  The invention is based on the object of eliminating the known disadvantages of founding a building.



  According to the invention, this is done in a method for the foundation of a prefabricated structure with at least approximately flat base in groundwater, free water or in dry soil, the subsoil being leveled so that its base is a few centimeters below the target depth of the planned foundation base, and where the The structure is held by hanging or bracing at the level of the target depth of the foundation base, as

   that along the edge zones of the building, adding soil material, a deep vibrator is brought down into the subsoil and with this the soil around the edge areas of the building is compacted and stuffed under the building, and that finally, if under the building's underside, there is still a cavity towards the inside remains, this fills this by pressing in hardening substances.

        If, in the case of a large-scale structure, the depth vibrators attached to the edge of the structure are no longer sufficient in their effect in the horizontal direction, a cavity remains under the structure, which, however, is enclosed by the stuffed and compacted filling floor. This enclosed cavity is made by pressing in suitable materials, such as. B. cement mortar, filled so that its required load-bearing capacity can be achieved reliably and evenly.

   The compacted filling soil below the lower surface of the structure along the edge of the structure forms for pressing z. B. the cement mortar a perfect counter-camp. In order to achieve a perfect injection and full compression in the space firmly enclosed by the soil material, especially in the case of large-area structures, one can in the bottom of the structure to carry out the injection z. B.

   Arrange holes that allow both the Einpres sen of injection material and the insertion of control organs and can be easily closed after completion of the injection process.



  If the soil beneath the base of the structure does not have sufficient load-bearing capacity, the subsoil can first be compacted by deep vibrators or surface vibrators working under water and homogenized in such a way that permanent subsidence is excluded after the load has been applied.

   However, if the floor below the building floor is not capable of compacting and is not of sufficient load-bearing capacity, it is advisable to replace the soil before bringing in the structure and compact it, whereupon the procedure described above is used.



  The drawing shows schematically two preferred application examples, namely: FIG. 1 cross-section through an excavation filled with groundwater and the prefabricated structural part hanging on a crane, FIG. 2 cross-section through the same excavation. The construction pit is backfilled with soil. Due to deep compaction, the part of the structure lies firmly on the foundation soil.



  In Fig. 1, a structural part 1 is shown hanging on a crane 2 in a previously raised construction pit 3 without dewatering. The excavation 3 is dug a little deeper, so that after A bring the structural part 1 into its intended position between the building and the excavation base, a small space remains. The soil at the edge and partly below the base of the structure is compacted and tamped by a depth vibrator S after the construction pit has been backfilled, so that now the part of the structure rests on the foundation base evenly around the circumference.



       Fig. 2 shows the cross-section of the structural part after the excavation has been filled again and the deep compaction has been completed. Cement mortar is injected through an opening 6 in the bottom of the structural part and the space remaining after compaction in the middle of the structural floor is filled. The progress and completion of the pressing process is followed via tubes 7 inserted into the building floor.



  By a foundation according to the present method, all foundation-related requirements are met, in particular a reliable and even closure of the space between the building and excavation base is achieved without the risk of uneven subsequent subsidence. The structure lies evenly in all parts of its entire base area, so that the most favorable support conditions can now be assumed for the structural dimensioning of the structure.



  The construction work itself can be carried out more quickly and at lower cost, because not only does the construction time for the manufacture and hardening of the structure are omitted, but the generally required dewatering can also be saved to excavate the excavation, since the excavation and foundation work are under Water are feasible.



  If space permits, the excavation pit can also be excavated as an open construction pit with very steep embankments without reinforcement, because these are more stable due to the balance between the inner and outer water pressure. The stability of the embankment can be increased considerably by artificial damming up of the water level in the excavation and in all of these cases no special safety precautions regarding the stability of the embankments are required, because according to the present method, no workers need to be in the excavation itself.



  After the structure has been brought into its target position, which can be done from the building site, and after the space between the base of the building pit and the base of the structure has been filled, as well as its tamping, which also does not require entering the building pit, as mentioned, all of the educational work can be done much more of the desired foundation can be taken and checked from inside the building.



  It is also essential for the stability of the excavation slopes that the excavation can be refilled immediately after the structure has been installed.

 

Claims (1)

PATENTANSPRUCH Verfahren zur Gründung eines vorgefertigten Baukörpers mit mindestens annähernd ebener Grund fläche im Grundwasser, freien Wasser oder im trok- kenen Boden, wobei der Baugrund so nivelliert wird, dass seine Sohle wenige Zentimeter unter der Soll tiefe der geplanten Gründungssohle liegt, und wobei der Baukörper durch Aufhängen oder Abstützen in Höhe der Solltiefe der Gründungssohle gehalten wird, dadurch gekennzeichnet, PATENT CLAIM Process for the foundation of a prefabricated building structure with at least approximately level surface in groundwater, free water or in dry soil, whereby the building ground is leveled so that its base is a few centimeters below the target depth of the planned foundation base, and the building structure is held by hanging or supporting at the level of the target depth of the foundation base, characterized in that dass man längs der Baukörperrandzonen unter Zugabe von Bodenmate rial einen Tiefenrüttler in den Boden des Baugrundes niederbringt und mit diesem den Boden um die Rand bereiche des Baukörpers verdichtet und unter den Baukörper stopft und dass man schliesslich, sofern unter der Baukörperunterseite nach innen zu noch ein Hohlraum verbleibt, diesen durch Einpressen von erhärtenden Stoffen satt ausfüllt. UNTERANSPRÜCHE 1. that along the edge of the building, with the addition of soil material, a deep vibrator is brought down into the soil of the building ground and with this the soil around the edge areas of the building is compacted and stuffed under the building, and that finally, if there is still a cavity under the underside of the building inward remains, this fills full by pressing in hardening substances. SUBCLAIMS 1. Verfahren nach Patentanspruch, dadurch ge kennzeichnet, dass bevor der Baukörper mittels Rütt- ler unterstopft wird, der Baugrund seitlich des Bau körpers mit Verfüllungsmaterial überschichtet wird. 2. Verfahren nach Patentanspruch, dadurch ge kennzeichnet, dass der Baugrund vor Einbringen des Baukörpers verdichtet wird. 3. Verfahren nach Patentanspruch, dadurch ge kennzeichnet, dass die satte Verpressung des einge schlossenen Hohlraumes unter dem Baukörper nach Ausstopfung noch vorhandenen Hohlraumes durch die Sohle des Baukörpers erfolgt. 4. Method according to claim, characterized in that before the building is tamped by means of vibrators, the building ground is covered with backfill material on the side of the building. 2. The method according to claim, characterized in that the subsoil is compacted before the structure is introduced. 3. The method according to claim, characterized in that the full compression of the enclosed cavity is carried out under the structure after stuffing the remaining cavity through the sole of the structure. 4th Verfahren nach Patentanspruch und Unter anspruch 2, dadurch gekennzeichnet, dass die Ver dichtung des Baugrundes nach Austausch des anste henden Bodens durch geeignetes Bodenmaterial er folgt. Method according to claim and sub-claim 2, characterized in that the compaction of the subsoil is carried out after the existing soil has been replaced by suitable soil material.
CH184462A 1962-02-15 1962-02-15 Procedure for the foundation of a prefabricated structure CH394057A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CH184462A CH394057A (en) 1962-02-15 1962-02-15 Procedure for the foundation of a prefabricated structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH184462A CH394057A (en) 1962-02-15 1962-02-15 Procedure for the foundation of a prefabricated structure

Publications (1)

Publication Number Publication Date
CH394057A true CH394057A (en) 1965-06-15

Family

ID=4219924

Family Applications (1)

Application Number Title Priority Date Filing Date
CH184462A CH394057A (en) 1962-02-15 1962-02-15 Procedure for the foundation of a prefabricated structure

Country Status (1)

Country Link
CH (1) CH394057A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113482047A (en) * 2021-07-21 2021-10-08 中交二公局第六工程有限公司 Pipe gallery installation method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113482047A (en) * 2021-07-21 2021-10-08 中交二公局第六工程有限公司 Pipe gallery installation method

Similar Documents

Publication Publication Date Title
EP2698476B1 (en) Method for the construction of an offshore structure and foundation for an offshore structure
DE3445965A1 (en) COMPACTING DEPTH, METHOD AND DEVICE FOR PRODUCING THE SAME
CN107780418A (en) The rapid constructing method cheated in Deep Foundation Pit
DE19521986C2 (en) Process for the production of a dry construction pit for a civil engineering structure below the groundwater table
CH394057A (en) Procedure for the foundation of a prefabricated structure
DE1634589A1 (en) Network for consolidating the ground in the vicinity of already existing structures or for holding the ground in zones which are exposed to landslides, and method for producing such a network
DE102017129705B4 (en) Process for the production of a fastening of a terrain jump, for the renovation of a pile foundation and for the new construction of a pile foundation by means of a supporting body
AT238107B (en) Procedure for the foundation of prefabricated structures
DE102005001422A1 (en) Sinking pits or wells involves filling concrete in shell, compressing, removing soil to let concrete lower, introducing/compressing more concrete, removing more soil to let concrete, repeating until shaft at required depth, removing shell
DE970760C (en) Process for the production of concrete piles in the ground by pressing the sunk borehole filled with aggregate with cement milk or the like while gradually withdrawing the press pipe
DE2704442C3 (en) Method for producing the foot formation for shoring supports placed in cased boreholes of a shoring wall
DE2030259C3 (en) Process for the production of a structure below the water table
AT217676B (en) Method for the repair of soil mechanically stressed retaining walls, vaults and the like. like
CH245930A (en) Pressed concrete construction process for the production of building structures under water.
DE898723C (en) Process for the electrical drainage of fine-grained soil
DE3214648A1 (en) Method of producing foundations for shell-shaped containers
DE645287C (en) Process for the foundation of structures with artificial compaction of the subsoil
DE3716750A1 (en) Method of constructing and sinking foundation structures
DE609238C (en) Method for producing a sufficiently watertight construction pit enclosure within the soil surrounding the pit
DE19935366A1 (en) Foundation pit of floor plate and sidewalls depresses floor plate below sidewall ends and joins these via arched sector of floor plate thickness to resist floor lift via ground-embedded ties.
DE691962C (en) Method and device for reinforcing bank retaining walls, pillars and similar structures
DE815327C (en) Process for the production of deep foundations
AT265982B (en) Procedure for undertaking the foundation, which is only accessible from the outside of the building
DE727469C (en) Process for the production of structures in groundwater or open water
DE3735111A1 (en) Building foundation vertically adjustable in the event of mining subsidence