CH141248A - Process for making concrete piles molded into the ground, using a casing tube. - Google Patents

Process for making concrete piles molded into the ground, using a casing tube.

Info

Publication number
CH141248A
CH141248A CH141248DA CH141248A CH 141248 A CH141248 A CH 141248A CH 141248D A CH141248D A CH 141248DA CH 141248 A CH141248 A CH 141248A
Authority
CH
Switzerland
Prior art keywords
tube
concrete
plug
ground
mass
Prior art date
Application number
Other languages
French (fr)
Inventor
Compagnie Internationa Anonyme
Original Assignee
Frankignoul Pieux Armes
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Frankignoul Pieux Armes filed Critical Frankignoul Pieux Armes
Publication of CH141248A publication Critical patent/CH141248A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/44Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with enlarged footing or enlargements at the bottom of the pile

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Description

  

  Procédé pour la confection de     pieux    en béton moulés dans le sol,  an moyen     d'un    tube de cuvelage.    La présente invention a pour objet un  procédé pour la     confectiôn    de pieux en béton  moulés     danf    le sol, au moyen d'un tube de  cuvelage. notamment dans les terrains mous  ou aquifères. Le but visé est de faciliter le  fonçage et le retrait du tube de cuvelage,  tout en empêchant la rentrée d'eau, de boue  on de terre à l'intérieur de ce tube.  



  Ce procédé est caractérisé en ce qu'on  dispose une masse de pierres à. l'intérieur du  tube, en ce qu'on forme ensuite, à, l'intérieur  du tube. par dessus la masse de pierre, un       bouchon    étanche en béton sec que l'on com  prime à l'aide d'un mouton à tête pratique  ment tronconique, en vue de produire une  adhérence frictionnelle suffisante dudit bou  chon comprimé à la paroi du tube et l'obtu  ration de la partie inférieure de ce dernier,  et en -ce qu'on produit le fonçage de ce tube  par la frappe directe dudit mouton sur ce  bouchon de béton comprimé, grâce à l'adhé  rence frictionnelle dudit bouchon à la paroi    du tube, et en ce qu'on procède, ensuite, à       l'introduction    de béton dans le tube et au re  trait du tube, le tout de telle sorte que le  béton introduit constitue,

   après le retrait du  tube, un pieu moulé dans le sol.  



  Le dessin annexé représente, à titre  d'exemple, une mise en     aeuvre    du procédé  pour la confection de pieux de fondation. Les       fig.    1 à 8 représentent, par ordre chronolo  gique, différentes phases de     cette    mise en       oeuvre.     



  Selon cette mise en     aeuvre,    on dresse ver  ticalement sur le sol le tube de cuvelage a       (fig.    1) et on déverse à son intérieur     uhe     masse de pierre b (le mot ,pierres" est pris  ici dans un sens tout à fait général, il     peut;          gir    -de pierres concassées, de     .caillous    ou  s 'a,  d'objets     similaires).    Ensuite, une masse de  béton absolument sec c (c'est-à-dire constituée  de matériaux non liés) est disposée dans le  tube, au-dessus de la masse de pierre     (fig.    1).

    On comprime ou pilonne     cette    masse de bé-      ton c à l'aide d'un mouton d à tête pratique  ment tronconique, de manière à comprimer  latéralement la masse de béton contre la pa  roi du tube.  



  On forme ainsi un bouchon étanche c       (fig.    2) en béton fortement comprimé qui  adhère suffisamment à. la paroi du tube pour  que la frappe continue du mouton sur ce bou  chon provoque l'enfoncement progressif du  tube dans le sol jusqu'à la profondeur dési  rée.  



  De cette manière, toute rentrée d'eau, de  boue ou de terre dans le tube, au-dessus du  bouchon, est absolument empêchée pendant le  fonçage.  



  Au début du fonçage, le bouchon de bé  ton formé sous la frappe du mouton, a d'a  bord repoussé dans le sol une partie de la  masse de pierres se trouvant en dessous de  lui, de manière à constituer une sorte de  pointe pierreuse     (fig.    2).  



  En continuant la frappe sur ledit bou  chon, celui-ci entraîne le tube par friction  et l'enfonce progressivement dans le sol       (fig.    3).  



  Sous l'effet. de cette frappe, le bouchon  comprimé qui entraîne le tube, descend très  lentement vers     l'extrémtié    inférieure du tube  en repoussant progressivement la masse de  pierres et en refoulant latéralement un cer  tain nombre de celles-ci,     V,    qui déchirent ou  écartent le sol en dessous du tube,     c'est-à-          dire    produisent un affouillement permettant  au tube de s'enfoncer plus facilement     (fig.    3  et 4).  



  Les pierres ainsi refoulées,     b1,    viennent  s'incruster successivement dans le sol autour  du tube au fur et à. mesure que ce dernier  s'enfonce, de manière à. produire autour de  la     -partie    enfoncée de ce tube, une sorte de  gaine pierreuse qui facilite notablement le  glissement dudit tube dans le terrain.  



  Lorsque le tube est enfoncé à la profon  deur désirée, le bouchon se trouve amené par  descente progressive, vers l'orifice inférieur  dudit tube.  



  On déverse alors, au-dessus du bouchon,  une certaine quantité de béton frais     e'            (fig.    5), puis on relève le tube de     quelques     centimètres, de manière à laisser un certain  vide au-dessous de lui, et on le maintient  dans cette position, ensuite de quoi on frappe  énergiquement sur la masse de béton frais  pour chasser progressivement le bouchon hors  du tube tout en maintenant l'obturation de  l'orifice inférieur par cette masse de béton  frais     (fig.    5).  



  Une nouvelle quantité de béton frais,     e\          (fig.    6), est ensuite déversée et pilonnée,     puis     le tube est à nouveau relevé, et ainsi de  suite, de sorte que le fût du pieu en béton  se trouve moulé progressivement au fur et  a. mesure de     l'extraction    du tube     (fig.   <B>7).</B>  Le pilonnage est poursuivi à la partie infé  rieure du pieu pendant un certain temps, de  façon à constituer une base fortement élar  gie dans le sol     (fig.    6 à. 8).  



  I1 est à. remarquer que les pierres refou  lées latéralement au fur et à. mesure de l'en  foncement du tube, et qui se sont incrustées  dans le sol pour former la gaine pierreuse,  contribuent à. faciliter grandement le glisse  ment de     mce    tube dans le terrain pendant     1(,     relèvements successifs.  



  Au surplus, les refoulées successives de  béton par le mouton pendant la, confection  du pieu ont pour effet d'écarter latéralement  le terrain, de sorte que les pierres précédem  ment incrustées dans celui-ci se trouvent re  poussées vers le béton du pieu par le terrain  comprimé et viennent s'y incruster partielle  ment, de manière à. constituer sur le fût e       (fig.    8) dudit pieu et dans toute sa, hauteur,  une succession d'aspérités accentuées b\       (fig.    8) qui forment autant d'ancrages laté  raux dans le sol et qui augmentent très sen  siblement la force portante du pieu.  



  On peut aussi ne pas déverser le béton  frais     au-dessus    du     ,bouchon    et relever pro  gressivement le tube de 2 à. 3 centimètres  seulement -à. la fois, afin de chasser lente  ment le bouchon hors du tube. Dans ce cas,  on n'ajoute du béton frais qu'au moment où  le bouchon est presque entièrement sort du  tube. Dans les terrains secs, on peut chasser      le bouchon d'un seul coup sans prendre de  précautions spéciales, vu l'absence d'eau et  de boue.  



  L'emploi du     procédé    en question n'est  évidemment pas limité au cas des terrains  mous ou aquifères.  



  Ledit procédé s'applique également pour  l'exécution de pieux en tous terrains, même  très légèrement compressible. Si l'on n'opère  pas dans un terrain mou ou .aquifère, l'em  ploi du ciment n'est pas nécessaire pour cons  tituer le bouchon comprimé     c    dit en béton sec.  



  En terrain peu compressible et non aqui  fère, l'expulsion du bouchon comprimé peut  s'effectuer par frappe directe du mouton sur  ce bouchon, sans introduction préalable d'une       tuasse    de béton frais, puisque la rentrée  d'eau, de boue et même de terre n'est pas à  craindre.



  Process for making concrete piles molded into the ground, using a casing tube. The present invention relates to a process for the confectiôn of concrete piles molded danf the ground, by means of a casing tube. especially in soft ground or aquifers. The aim is to facilitate the sinking and removal of the casing tube, while preventing the entry of water, mud or earth inside this tube.



  This process is characterized in that a mass of stones is available. inside the tube, in that the inside of the tube is then formed. on top of the stone mass, a watertight dry concrete plug which is compressed using a ram with a practically frustoconical head, in order to produce sufficient frictional adhesion of said compressed plug to the wall of the tube and the obtu ration of the lower part of the latter, and in -ce that the sinking of this tube is produced by the direct impact of said ram on this compressed concrete plug, thanks to the frictional adhesion of said plug to the wall of the tube, and in that one proceeds, then, to the introduction of concrete into the tube and to the retreat of the tube, the whole so that the introduced concrete constitutes,

   after removing the tube, a stake cast into the ground.



  The appended drawing represents, by way of example, an implementation of the process for making foundation piles. Figs. 1 to 8 represent, in chronological order, different phases of this implementation.



  According to this implementation, one raises vertically on the ground the casing tube a (fig. 1) and one pours inside it a mass of stone b (the word, stones "is taken here in a quite general sense. , it can; gir - crushed stones, pebbles or s' a, of similar objects). Then, an absolutely dry concrete mass c (that is to say made of unbound materials) is placed in the tube, above the mass of stone (fig. 1).

    This mass of concrete c is compressed or pounded using a ram d with a practically frustoconical head, so as to compress the mass of concrete laterally against the pa king of the tube.



  This forms a tight plug c (Fig. 2) of strongly compressed concrete which adheres sufficiently to. the wall of the tube so that the continuous striking of the sheep on this plug causes the progressive sinking of the tube in the ground to the desired depth.



  In this way, any entry of water, mud or earth into the tube, above the plug, is absolutely prevented during sinking.



  At the start of sinking, the concrete plug formed under the strike of the sheep, first pushed into the ground part of the mass of stones located below it, so as to constitute a kind of stony point ( fig. 2).



  By continuing to strike the said plug, the latter drives the tube by friction and gradually pushes it into the ground (fig. 3).



  Under the effect. from this strike, the compressed stopper which drives the tube, descends very slowly towards the lower extremity of the tube, gradually pushing back the mass of stones and laterally pushing back a certain number of these, V, which tear or spread the ground below the tube, ie produce a scour allowing the tube to sink more easily (fig. 3 and 4).



  The stones thus driven back, b1, become embedded successively in the soil around the tube as and when. as the latter sinks, so as to. produce around the sunken part of this tube, a sort of stony sheath which significantly facilitates the sliding of said tube in the ground.



  When the tube is inserted to the desired depth, the stopper is brought by progressive descent, towards the lower orifice of said tube.



  A certain quantity of fresh concrete e 'is then poured over the stopper (fig. 5), then the tube is raised a few centimeters, so as to leave a certain void below it, and it is maintained. in this position, after which one strikes vigorously on the mass of fresh concrete to gradually drive the stopper out of the tube while maintaining the closure of the lower opening by this mass of fresh concrete (fig. 5).



  A new quantity of fresh concrete, e \ (fig. 6), is then poured out and pounded, then the tube is again raised, and so on, so that the shaft of the concrete pile is gradually molded as it goes. at. measurement of the extraction of the tube (fig. <B> 7). </B> The ramming is continued at the lower part of the pile for a certain time, so as to form a strongly widened base in the ground (fig. . 6 to. 8).



  He is at. note that the stones pushed back laterally as and when. measure of the sinking of the tube, and which have become encrusted in the ground to form the stony sheath, contribute to. greatly facilitate the sliding of this tube in the ground during 1 (, successive lifting.



  In addition, the successive pushbacks of concrete by the ram during the making of the pile have the effect of laterally moving the ground aside, so that the stones previously encrusted in it are pushed back towards the concrete of the pile by the pile. compressed ground and are partially embedded therein, so as to. constitute on the shaft e (fig. 8) of said pile and throughout its height, a succession of accentuated asperities b \ (fig. 8) which form as many lateral anchors in the ground and which very significantly increase the bearing strength of the pile.



  It is also possible not to pour the fresh concrete over the stopper and gradually raise the tube from 2 to. Only 3 centimeters away. at the same time in order to slowly push the stopper out of the tube. In this case, only add fresh concrete when the plug is almost completely out of the tube. In dry areas, the plug can be removed at once without taking special precautions, due to the absence of water and mud.



  The use of the process in question is obviously not limited to the case of soft soils or aquifers.



  Said method is also applicable for the execution of piles in all terrains, even very slightly compressible. If one does not operate in a soft or aquiferous ground, the use of cement is not necessary to constitute the compressed plug c said in dry concrete.



  In slightly compressible and non-aquiferous ground, the expulsion of the compressed plug can be effected by direct striking of the sheep on this plug, without the prior introduction of a fresh concrete slab, since the entry of water, mud and even of earth is not to be feared.

 

Claims (1)

REPENDICATION: Procédé pour la, confection de pieux en béton moulés dans le sol, au moyen d'un tube de cuvelage, caractérisé en ce qu'on dispose une masse de pierres à. l'intérieur du tube, en ce qu'on forme ensuite, à l'intérieur du tube, par dessus la masse de pierres, un bou chon étanche en béton sec, c'est-à-dire consti tué de matériaux non liés, que l'on com prime par pilonnage, à l'aide d'un mouton à, tête pratiquement tronconique en vue de produire une adhérence frictionnelle suffi sante dudit bouchon comprimé à la paroi du tube et l'obturation de la partie inférieure de ce dernier, et en ce qu'on produit le fon- çage de ce tube jusqu'à la profondeur dési rée, REPENDICATION: Process for the making of concrete piles molded into the ground, by means of a casing tube, characterized in that a mass of stones is placed at. inside the tube, in that a watertight plug in dry concrete, that is to say made of unbound materials, is then formed inside the tube, over the mass of stones, which is compressed by ramming, using a ram with a practically frustoconical head in order to produce sufficient frictional adhesion of said compressed stopper to the wall of the tube and the sealing of the lower part of the latter , and in that one produces the sinking of this tube to the desired depth, par la frappe directe dudit mouton sur ce bouchon de béton comprimé, grâce à l'ad hérence frictionnelle de ce bouchon à la pa roi du tube, et en ce qu'on procède, ensuite, à, l'introduction de béton dans le tube et au re trait du tube, le tout de telle sorte que le bé ton introduit constitue, après le retrait du tube un pieu moulé dans le sol. SOUS-REVENDICATIONS 1 Procédé selon la revendication, caractérisé en ce que, après avoir produit le fonçage du tube, on relève légèrement ce dernier, _ on le maintient dans cette position relevée et on provoque l'expulsion du bouchon comprimé par la. frappe continuée -du mou ton sur ce bouchon. by the direct striking of said ram on this compressed concrete plug, thanks to the frictional adhesion of this plug to the pa king of the tube, and in that one proceeds, then, to the introduction of concrete into the tube and at the end of the tube, the whole in such a way that the concrete introduced constitutes, after the withdrawal of the tube, a stake molded in the ground. SUB-CLAIMS 1 A method according to claim, characterized in that, after having produced the sinking of the tube, the latter is slightly raised, _ it is maintained in this raised position and the expulsion of the compressed plug is caused by the. continuous strike - soft tone on this stopper. 2 Procédé selon la revendication, caracté risé en ce que, au début du fonçage, on produit, par la frappe directe du mouton sur le bouchon de béton, une légère des cente de ce bouchon @à l'intérieur du tube, de manière à repousser dans le sol une par tie de la masse de pierres se trouvant au- dessous de lui, en vue de former une sorte de pointe pierreuse. 2 A method according to claim, character ized in that, at the start of sinking, is produced, by direct striking of the ram on the concrete plug, a slight cent of this plug @ inside the tube, so as to push part of the mass of stones below it into the ground, in order to form a kind of stony point. 3 Procédé selon la revendication et la sous- revendication 2, caractérisé en ce qu'on re foule hors du tube et latéralement dans le sol, au cours du fonçage, une partie des pierres se trouvant au-dessous du bou chon de béton, que l'on fait descendre len tement et progressivement à l'intérieur du tube, en vue d'obtenir que les pierres re foulées latéralement déchirent et écartent le terrain en dessous du tube, pour faci liter l'enfoncement de ce dernier. 3 A method according to claim and sub- claim 2, characterized in that re crowd out of the tube and laterally into the ground, during sinking, a part of the stones located below the concrete plug, that one lowers slowly and progressively inside the tube, in order to obtain that the stones re-trodden laterally tear and spread the ground below the tube, to facilitate the sinking of the latter. 4 Procédé selon la revendication et la sous- revendication 2, caractérisé en ce que, . quand le tube a été enfoncé @à la profon deur voulue, et avant que le bouchon de béton n'en soit expulsé, on introduit dans le tube une masse suffisante de béton frais au-dessus dudit bouchon, on relève légèrement- le tube et on le maintient dans cette position relevée et on pilonne, au moyen du mouton, la masse de béton frais ainsi introduite, pour expulser complète ment ce bouchon du tube tout en laissant l'orifice inférieur du tube obturé par la dite masse de béton frais. 4 A method according to claim and sub-claim 2, characterized in that,. when the tube has been inserted @ to the desired depth, and before the concrete plug is expelled from it, a sufficient mass of fresh concrete is introduced into the tube above said plug, the tube is raised slightly and it is maintained in this raised position and the mass of fresh concrete thus introduced is pounded by means of the ram, in order to completely expel this stopper from the tube while leaving the lower orifice of the tube closed by said mass of fresh concrete. 5 Procédé selon la revendication et les sous- revendications 2 et 4, caractérisé en ce que, après pilonnage de la première masse de béton frais introduite dans le tube, on pro duit le retrait de ce dernier par relève ments successifs d'une petite quantité à la fois, avec, après chaque relèvement, introduction d'une nouvelle masse de bé- ton frais que l'on pilonne, en vue d'obte nir que le fût du pieu en béton se trouve moulé progressivement au fur et à mesure de l'extraction du tube. 5 A method according to claim and sub-claims 2 and 4, characterized in that, after ramming the first mass of fresh concrete introduced into the tube, the withdrawal of the latter is produced by successive raising of a small quantity. at the same time, with, after each raising, the introduction of a new mass of fresh concrete which is pounded, with a view to obtaining that the shaft of the concrete pile is gradually molded as extracting the tube. 6 Procédé selon la revendication et les sous- revendications 2 et 4, caractérisé en ce que l'on poursuit le pilonnage à la partie infé- rieure du pieu pendant un certain temps, de façon à constituer une base fortement élargie dans le sol. 6. Method according to claim and sub-claims 2 and 4, characterized in that the ramming is continued at the lower part of the pile for a certain time, so as to constitute a greatly enlarged base in the ground.
CH141248D 1929-06-19 1929-06-19 Process for making concrete piles molded into the ground, using a casing tube. CH141248A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH141248T 1929-06-19

Publications (1)

Publication Number Publication Date
CH141248A true CH141248A (en) 1930-07-31

Family

ID=4398194

Family Applications (1)

Application Number Title Priority Date Filing Date
CH141248D CH141248A (en) 1929-06-19 1929-06-19 Process for making concrete piles molded into the ground, using a casing tube.

Country Status (1)

Country Link
CH (1) CH141248A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1992010637A2 (en) * 1990-12-12 1992-06-25 Van Dalfsen Rotar Equipment B.V. Tool for making holes in the ground
US5797705A (en) * 1990-12-12 1998-08-25 Willibald Kellner Method for manufacturing a tubular foundation in the ground

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1992010637A2 (en) * 1990-12-12 1992-06-25 Van Dalfsen Rotar Equipment B.V. Tool for making holes in the ground
WO1992010637A3 (en) * 1990-12-12 1992-12-10 Dalfsen Rotar Equipment B V Va Tool for making holes in the ground
US5797705A (en) * 1990-12-12 1998-08-25 Willibald Kellner Method for manufacturing a tubular foundation in the ground

Similar Documents

Publication Publication Date Title
CH141248A (en) Process for making concrete piles molded into the ground, using a casing tube.
US1794892A (en) Forming piles
FR2535760A1 (en) METHOD AND APPARATUS FOR REALIZING IN SITU CONCRETE PILES WITH EXTENDED BASES
BE498717A (en)
US2027511A (en) Method of casting bell-bottom place-piling in soft sandy material
BE361503A (en)
BE346159A (en)
FR2471451A1 (en) Driving and casting procedure for bulbous foot piles - uses concrete rammer inside pile tube with projection above tube being equal to volume of concrete cast
SU31376A1 (en) Method of casing immersion for forming concrete piles in the ground
BE369001A (en)
FR2646190A1 (en) Method for improving the mechanical characteristics and resistance to compacting of ground
CH208905A (en) Device to facilitate the execution of a concrete pile cast in the ground.
BE843209A (en) METHOD AND DEVICE FOR FORMING REINFORCED CONCRETE PILES MOLDED IN PLACE IN THE SOIL
BE334406A (en)
BE546120A (en)
PL31533B1 (en) Compagnie Internationale Des Pieux Armes Frankignoul, Societe Anonyme, Leodium. .- / Shoe for making molded concrete piles easier
BE508872A (en)
BE437054A (en)
CH180901A (en) Process for making piles with a widened base molded into the ground.
FR2491108A1 (en) Hook attachment for hydraulic shovel - has hook on each side of tooth to allow road surfaces to be excavated without use of pneumatic drills
FR2524383A1 (en) METHOD AND DEVICE FOR SEPARATING PHASES FOR MULTI-PHASE RIGID MATERIALS
BE360455A (en)
BE518438A (en)
CH299963A (en) Process for the execution of reinforced foundation piles with widened base.
BE530037A (en)