WO2024083144A1 - Liquid cooling device and battery pack - Google Patents

Liquid cooling device and battery pack Download PDF

Info

Publication number
WO2024083144A1
WO2024083144A1 PCT/CN2023/125188 CN2023125188W WO2024083144A1 WO 2024083144 A1 WO2024083144 A1 WO 2024083144A1 CN 2023125188 W CN2023125188 W CN 2023125188W WO 2024083144 A1 WO2024083144 A1 WO 2024083144A1
Authority
WO
WIPO (PCT)
Prior art keywords
liquid cooling
cooling device
mounting portion
box
plate
Prior art date
Application number
PCT/CN2023/125188
Other languages
French (fr)
Chinese (zh)
Inventor
田远伟
闫仕伟
刘华俊
范心
杨鹏
Original Assignee
湖北亿纬动力有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from CN202222783781.9U external-priority patent/CN218568984U/en
Priority claimed from CN202222781665.3U external-priority patent/CN218568983U/en
Application filed by 湖北亿纬动力有限公司 filed Critical 湖北亿纬动力有限公司
Publication of WO2024083144A1 publication Critical patent/WO2024083144A1/en

Links

Classifications

    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01MPROCESSES OR MEANS, e.g. BATTERIES, FOR THE DIRECT CONVERSION OF CHEMICAL ENERGY INTO ELECTRICAL ENERGY
    • H01M10/00Secondary cells; Manufacture thereof
    • H01M10/60Heating or cooling; Temperature control
    • H01M10/61Types of temperature control
    • H01M10/613Cooling or keeping cold
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01MPROCESSES OR MEANS, e.g. BATTERIES, FOR THE DIRECT CONVERSION OF CHEMICAL ENERGY INTO ELECTRICAL ENERGY
    • H01M10/00Secondary cells; Manufacture thereof
    • H01M10/60Heating or cooling; Temperature control
    • H01M10/62Heating or cooling; Temperature control specially adapted for specific applications
    • H01M10/625Vehicles
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01MPROCESSES OR MEANS, e.g. BATTERIES, FOR THE DIRECT CONVERSION OF CHEMICAL ENERGY INTO ELECTRICAL ENERGY
    • H01M10/00Secondary cells; Manufacture thereof
    • H01M10/60Heating or cooling; Temperature control
    • H01M10/65Means for temperature control structurally associated with the cells
    • H01M10/655Solid structures for heat exchange or heat conduction
    • H01M10/6554Rods or plates
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01MPROCESSES OR MEANS, e.g. BATTERIES, FOR THE DIRECT CONVERSION OF CHEMICAL ENERGY INTO ELECTRICAL ENERGY
    • H01M10/00Secondary cells; Manufacture thereof
    • H01M10/60Heating or cooling; Temperature control
    • H01M10/65Means for temperature control structurally associated with the cells
    • H01M10/655Solid structures for heat exchange or heat conduction
    • H01M10/6556Solid parts with flow channel passages or pipes for heat exchange
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01MPROCESSES OR MEANS, e.g. BATTERIES, FOR THE DIRECT CONVERSION OF CHEMICAL ENERGY INTO ELECTRICAL ENERGY
    • H01M10/00Secondary cells; Manufacture thereof
    • H01M10/60Heating or cooling; Temperature control
    • H01M10/65Means for temperature control structurally associated with the cells
    • H01M10/656Means for temperature control structurally associated with the cells characterised by the type of heat-exchange fluid
    • H01M10/6567Liquids
    • H01M10/6568Liquids characterised by flow circuits, e.g. loops, located externally to the cells or cell casings
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01MPROCESSES OR MEANS, e.g. BATTERIES, FOR THE DIRECT CONVERSION OF CHEMICAL ENERGY INTO ELECTRICAL ENERGY
    • H01M50/00Constructional details or processes of manufacture of the non-active parts of electrochemical cells other than fuel cells, e.g. hybrid cells
    • H01M50/20Mountings; Secondary casings or frames; Racks, modules or packs; Suspension devices; Shock absorbers; Transport or carrying devices; Holders
    • H01M50/204Racks, modules or packs for multiple batteries or multiple cells
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01MPROCESSES OR MEANS, e.g. BATTERIES, FOR THE DIRECT CONVERSION OF CHEMICAL ENERGY INTO ELECTRICAL ENERGY
    • H01M50/00Constructional details or processes of manufacture of the non-active parts of electrochemical cells other than fuel cells, e.g. hybrid cells
    • H01M50/20Mountings; Secondary casings or frames; Racks, modules or packs; Suspension devices; Shock absorbers; Transport or carrying devices; Holders
    • H01M50/244Secondary casings; Racks; Suspension devices; Carrying devices; Holders characterised by their mounting method
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01MPROCESSES OR MEANS, e.g. BATTERIES, FOR THE DIRECT CONVERSION OF CHEMICAL ENERGY INTO ELECTRICAL ENERGY
    • H01M50/00Constructional details or processes of manufacture of the non-active parts of electrochemical cells other than fuel cells, e.g. hybrid cells
    • H01M50/20Mountings; Secondary casings or frames; Racks, modules or packs; Suspension devices; Shock absorbers; Transport or carrying devices; Holders
    • H01M50/249Mountings; Secondary casings or frames; Racks, modules or packs; Suspension devices; Shock absorbers; Transport or carrying devices; Holders specially adapted for aircraft or vehicles, e.g. cars or trains

Definitions

  • the present application relates to the field of battery technology, and in particular to a liquid cooling device and a battery pack.
  • the battery pack includes a box body, a battery cell and a cooling plate arranged in the box body.
  • the cooling plate is connected to the cooling equipment on the external vehicle end through a joint, and cooling water is supplied to the cooling plate to cool the battery cell.
  • the quick-plug male connector is welded to the cooling plate and both are arranged inside the box body. The connector and the water inlet and outlet of the cooling equipment on the vehicle end are quickly connected through nylon pipes and quick-plug male connectors.
  • the quick-connect male connector since the quick-connect male connector is located inside the box, the number of times it can be disassembled and assembled is limited. After multiple insertions and removals, there is a risk of sealing failure between the nylon tube and the quick-connect male connector, resulting in leakage, which in turn leads to the risk of failure of the battery pack. In addition, the quick-connect male connector occupies space inside the box, placing high demands on the space inside the box.
  • the present application provides a liquid cooling device and a battery pack to solve the above-mentioned technical problems.
  • the present application provides a liquid cooling device, comprising:
  • a liquid cooling plate unit is arranged inside the box, and is used to cool the battery cells in the box.
  • the liquid cooling plate unit has a water inlet and a water outlet;
  • Two connectors provided outside the box, for connecting to external cooling equipment;
  • the channel unit comprises two pipeline assemblies fixed on the box body, one of the pipeline assemblies connects one of the joints and the water inlet, and the other pipeline assembly connects the other joint and the water outlet.
  • the present application also provides a battery pack, comprising a box body, a battery cell and the above-mentioned liquid cooling device.
  • the liquid cooling device provided by the present application by arranging the joint outside the box, realizes that the cooling equipment on the vehicle end can be directly connected to the joint outside the box; the specific joint can be a quick plug, and the cooling equipment on the vehicle end is connected to the quick plug through a nylon pipe, which avoids the prior art that the quick-insert male joint is arranged in the box and occupies the internal space of the box, and reduces the requirements for the internal space of the box.
  • the battery pack provided by the present application adopts the above-mentioned liquid cooling device, which is arranged in the box body and is used to liquid-cool the battery cells in the box body.
  • the liquid cooling device arranges the connector outside the box body, so that the cooling equipment on the vehicle side can be directly connected to the connector outside the box body, reducing the requirements for the internal space of the box body, facilitating the disassembly and assembly of the connector and the cooling equipment on the vehicle side, and improving convenience; at the same time, it eliminates the risk of failure of the battery pack caused by leakage of the quick-insert male connector, and improves the reliability of the battery pack.
  • the internal pipes and related accessories of the box body are simplified, the installation process is optimized, and the requirements for the box space are reduced.
  • FIG1 is an exploded view of a battery pack provided in Embodiment 1;
  • Fig. 2 is an enlarged view of point A in Fig. 1;
  • FIG3 is an exploded view of a channel unit provided in Embodiment 1;
  • FIG4 is a schematic diagram of a substrate provided in Example 1;
  • FIG5 is a partial schematic diagram of the bottom plate provided in Example 1;
  • FIG6 is an exploded view of a battery pack provided in Embodiment 2;
  • FIG7 is an enlarged view of point B in FIG6;
  • FIG8 is an exploded view of the connection block assembly provided in Embodiment 2;
  • FIG9 is a schematic structural diagram of a connecting block body provided in Embodiment 2.
  • FIG. 10 is a partial schematic diagram of the bottom plate provided in the second embodiment.
  • channel unit 21. pipeline assembly; 211. main pipeline; 212. branch pipeline; 213. hose; 22. base; 24a. accommodating cavity; 24b. accommodating space; 221. extension portion; 2211. through hole; 222. mounting portion; 2221. accommodating groove; 2222. flange; 23. groove; 24. cover plate; 25. sealing gasket;
  • Connector assembly 31. First connector body; 32. Second connector body;
  • connection should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements.
  • connection can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements.
  • a first feature being “above” or “below” a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them.
  • a first feature being “above”, “above” and “above” a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature.
  • a first feature being “below”, “below” and “below” a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.
  • the terms “upper”, “lower”, “right”, etc. are based on the directions or positions shown in the drawings, and are only for the convenience of description and simplification of operation, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as limiting the present application.
  • the terms “first” and “second” are only used to distinguish in the description and have no special meaning.
  • FIG. 1 and 2 it includes a box body 100, a battery cell 200 and a liquid cooling device.
  • This embodiment also provides a liquid cooling device, as shown in Figures 1 and 2, including a liquid cooling plate unit 1, two joints 4 (not shown in the figure) and a channel unit 2, the liquid cooling plate unit 1 is arranged inside the box body 100, the liquid cooling plate unit 1 is used to cool the battery cell 200 in the box body 100, and the liquid cooling plate unit 1 has a water inlet 11 and a water outlet 12; the two joints 4 are arranged outside the box body 100 for connecting to an external cooling device; the channel unit 2 includes two pipe assemblies 21 fixed on the box body 100, one pipe assembly 21 connects one of the joints 4 and the water inlet 11, and the other pipe assembly 21 connects the other joint 4 and the water outlet 12.
  • the first joint is connected to the outlet of the external cooling device, and the second joint is connected to the inlet of the external cooling device.
  • the coolant enters the liquid cooling plate unit 1 from the outlet through the first joint, the first pipe assembly 21 and the water inlet 11. After circulating in the liquid cooling plate unit 1, the coolant enters the second pipe assembly 21 from the water outlet 12, and flows back to the external cooling device through the second joint and the inlet, thereby realizing the circulation of the coolant between the external cooling device and the liquid cooling device.
  • the cooling equipment on the vehicle side can be directly connected to the connector 4 outside the box 100; specifically, the connector 4 can be a quick plug, and the cooling equipment on the vehicle side is connected to the quick plug through a nylon pipe, which avoids the quick-insert male connector being arranged inside the box 100 and occupying the internal space of the box 100 in the prior art, thereby reducing the requirements for the internal space of the box 100. It facilitates the disassembly and assembly of the connector 4 and the cooling equipment on the vehicle side, and improves convenience; the quick-insert male connector inside the box 100 is removed, eliminating the risk of failure of the battery pack caused by leakage of the quick-insert male connector, and improving the reliability of the battery pack.
  • the internal pipes and related accessories of the box 100 are simplified, the installation process is optimized, and the space requirements of the box 100 are reduced.
  • the pipeline assembly 21 when the liquid cooling plate unit 1 is provided with a plurality of water inlets 11 and a plurality of water outlets 12, the pipeline assembly 21 includes a main pipeline 211, the main pipeline 211 is connected to the joint 4, the main pipeline 211 of one pipeline assembly 21 is connected to the plurality of water inlets 11, the main pipeline 211 of another pipeline assembly 21 is connected to the plurality of water outlets 12, the plurality of water inlets 11 are connected to the joint 4 through the main pipeline 211, and the plurality of water outlets 12 are connected to the joint 4 through another main pipeline 211, which simplifies the connection structure between the plurality of water inlets 11 and the joint 4, and simplifies the connection structure between the plurality of water outlets 12 and the joint 4.
  • main pipeline 211 is connected to a plurality of branch pipelines 212, the plurality of branch pipelines 212 are connected to the plurality of water inlets 11 in a one-to-one correspondence, the other main pipeline 211 is connected to a plurality of branch pipelines 212, the plurality of branch pipelines 212 are connected to the plurality of water outlets 12 in a one-to-one correspondence.
  • the pipeline assembly 21 also includes a hose 213, which is used to connect the main pipeline 211 and the liquid cooling plate unit 1.
  • the hose 213 is flexible and can be deformed according to the actual space size to improve adaptability. Specifically, it includes multiple hoses 213, and the hose 213 connects the water inlet 11 and the branch pipeline 212, or the hose 213 connects the water outlet 12 and the branch pipeline 212.
  • the liquid cooling plate unit 1 includes two stamped cold plates 13, each stamped cold plate 13 includes a water inlet 11 and a water outlet 12.
  • the liquid cooling plate unit 1 may also include multiple stamped cold plates 13. The specific number of stamped cold plates 13 and the arrangement between the multiple stamped cold plates 13 can be set according to actual conditions and are not limited.
  • the pipeline assembly 21 also includes a clamp (not shown in the figure), and the hose 213 is fixed to the branch pipeline 212 by the clamp to ensure connection reliability, avoid leakage due to unreliable connection, and thus ensure safety.
  • the channel unit 2 also includes a base 22, the base 22 is fixed to the box 100, and the base 22 and the box 100 form a receiving cavity 22a, the main pipeline 211 is fixed to the base 22, and the receiving cavity 22a is used to connect the main pipeline 211, and the main pipeline 211 is fixed to the box 100 through the base 22 to make the installation stable.
  • a protrusion 221 is provided at one end of the base 22, and the protrusion 221 is provided outside the box 100.
  • the protrusion 221 is provided with two through holes 2211, and two joints 4 are respectively connected to the two through holes 2211.
  • the joints 4 are connected to the accommodating cavity 22a through the through holes 2211, so as to avoid the joints 4 being directly connected to the box 100.
  • the channel unit 2 can be installed on the box 100 according to actual requirements such as the interface connection position of the external cooling device, so as to improve the applicability to the external installation environment without modifying the box 100; further, the protrusion 221 abuts against the box 100, so as to improve the installation accuracy.
  • the box 100 includes a frame 104 arranged around it, and the protrusion 221 protrudes from the frame 104, and the base 22 and the frame 104 form a accommodating cavity 22a.
  • the other end of the base 22 is provided with a mounting portion 222, the mounting portion 222 is provided with a receiving groove 2221, and the main pipeline 211 is fixedly connected in the receiving groove 2221.
  • the box 100 is provided with an opening 1011, and the receiving groove 2221 is communicated with the opening 1011, so as to facilitate the installation and maintenance of the main pipeline 211 in the receiving groove 2221.
  • a flange 2222 is provided on the side of the mounting portion 222 away from the base 22, and when the mounting portion 222 is inserted into the opening 1011, the flange 2222 abuts against the inner wall of the box 100, and the flange 2222 and the inner wall of the box 100 can be limited, thereby improving the installation accuracy.
  • the mounting portion 222 is sealed and connected to the opening 1011, thereby ensuring the sealing inside the box 100.
  • the box 100 includes a bottom plate 101 and an upper cover 103, the opening 1011 is provided on the bottom plate 101, and the mounting portion 222 is sealed and installed on the bottom plate 101.
  • the mounting portion 222 can also be installed on the upper cover 103 according to actual conditions, without limitation.
  • the mounting portion 222 is connected to the opening 1011 by a sealing ring, which is convenient to install and has good reliability.
  • a potting glue structure is provided between the mounting portion 222 and the opening 1011 to avoid the risk of aging of the sealing ring due to long-term use and leakage.
  • the mounting portion 222 is installed downward from the inside of the box 100 to penetrate the opening 1011, and then the penetration position is filled and sealed with potting glue.
  • the box 100 further includes a protective plate 102, which is disposed outside the bottom plate 101 and can be sealed on the opening 1011 to protect the main pipeline 211 and other structures to prevent sealing failure caused by external stone impact.
  • the protective plate 102 can be a PVC board.
  • the housing 100 is provided with a recessed groove 1012 , the notch of the recessed groove 1012 faces outward, and the opening 1011 is provided at the bottom of the recessed groove 1012 to prevent the main pipeline 211 from protruding outward when installed on the housing 100 .
  • FIG. 6 and 7 it includes a box body 100, a battery cell 200 arranged in the box body 100, and a liquid cooling device, and the liquid cooling device is used to cool the battery cell 200.
  • This embodiment provides a liquid cooling device, as shown in Figure 6, including a liquid cooling plate unit 1, two joints (not shown in the figure) and a channel unit 2, the liquid cooling plate unit 1 is arranged inside the box body 100, the liquid cooling plate unit 1 is used to cool the battery cell 200 in the box body 100, and the liquid cooling plate unit 1 has a water inlet 11 and a water outlet 12; the two joints are arranged outside the box body 100 for connecting to an external cooling device; the channel unit 2 includes two pipe assemblies 21 fixed on the box body 100, one pipe assembly 21 connects one of the joints 4 and the water inlet 11, and the other pipe assembly 21 connects the other joint 4 and the water outlet 12.
  • the channel unit 2 is sealed and connected to the box body 100, and the channel unit 2 forms two separated accommodating spaces 22b;
  • the liquid cooling device also includes two connector assemblies 3, one of the connector assemblies 3 is connected to the water inlet 11 of the liquid cooling plate unit 1 and one of the accommodating spaces 22b, and the other of the connector assemblies 3 is connected to the water outlet 12 of the liquid cooling plate unit 1 and another of the accommodating spaces 22b; wherein, the two main pipelines 211 of the two pipeline assemblies 21 are fixed to the channel unit 2, and are respectively connected to the two accommodating spaces 22b.
  • the cooling equipment on the vehicle side can be directly connected to the connector outside the box 100; specifically, the connector 4 can be a quick plug, and the cooling equipment on the vehicle side is connected to the quick plug through a nylon pipe, which avoids the quick-insert male connector being arranged inside the box 100 and occupying the internal space of the box 100 in the prior art, thereby reducing the requirements for the internal space of the box 100. It facilitates the disassembly and assembly of the connector 4 and the cooling equipment on the vehicle side, and improves convenience; the quick-insert male connector inside the box 100 is removed, eliminating the risk of failure of the battery pack caused by leakage of the quick-insert male connector, and improving the reliability of the battery pack.
  • the internal pipes and related accessories of the box 100 are simplified, the installation process is optimized, and the space requirements of the box 100 are reduced.
  • a receiving cavity 22a is formed in the box body 100, and the receiving cavity 22a is communicated with the two receiving spaces 22b respectively.
  • the box body 100 is directly connected to the outside through the receiving cavity 22a.
  • the receiving cavity 22a is used as an intermediate cavity and is arranged between the main pipeline and the receiving space 22b.
  • the channel unit 2 includes a protruding portion 221, a base 22, and a mounting portion 222.
  • the base 22 and the box 100 enclose the accommodating cavity 22a.
  • the protruding portion 221 is provided at one end of the base 22.
  • the protruding portion 221 is located outside the box 100 and abuts against the outer wall of the box 100.
  • the mounting portion 222 is provided at the other end of the base 22.
  • Two accommodating spaces 22b are formed on the mounting portion 222.
  • Two main pipelines 211 are provided in the channel unit 2. One end of the two main pipelines 211 is respectively connected to the two accommodating spaces 22b. The other end of the two main pipelines 211 is passed through the protruding portion 221 and is connected to the two joints 4.
  • connection of the two main pipelines 211 can avoid liquid leakage and further improve the sealing performance.
  • the mounting portion 222 can be made of a lightweight material such as plastic, while the main pipeline 211 is made of a wear-resistant material such as metal to avoid failure when the interface is connected to a quick-connect connector, etc.
  • the main pipeline 211 and the mounting portion 222 are an integral injection molding structure.
  • the box 100 includes a frame 104, and the accommodating cavity 22a is provided on the frame 104, so that one end of the main pipeline 211 is provided through the side of the box 100, and the cooling equipment at the vehicle end is connected to the side of the box 100.
  • the bottom plate 101 is provided with a frame 104 on all four sides, and one end of the main pipeline 211 is provided through the frame 104 on one side.
  • the specific setting is based on the actual layout of the vehicle end, etc., and is not limited.
  • the extension portion 221 is provided through the frame 104 and forms the accommodating cavity 22a together with the frame 104.
  • the channel unit 2 includes a mounting portion 222 and a cover plate 24, the mounting portion 222 is connected to the box body 100, the mounting portion 222 is provided with two separated grooves 23, the cover plate 24 is connected to the mounting portion 222, the cover plate 24 and the two grooves 23 respectively form two accommodating spaces 22b, the mounting portion 222 and the cover plate 24 are separately arranged and connected to form the accommodating space 22b, which is convenient for manufacturing, and the cover plate 24 is locked with the connecting hole body to ensure the sealing of the accommodating space.
  • the channel unit 2 further includes a sealing gasket 25, and the cover plate 24 is sealed and connected to the mounting portion 222 through the sealing gasket 25, further improving the sealing performance of the accommodating space 22b.
  • the mounting portion 222 is provided with a receiving groove that is in communication with both grooves 23, and the sealing gasket 25 is arranged in the receiving groove, which limits the movement of the sealing gasket 25 and improves the installation reliability of the sealing gasket 25.
  • the sealing gasket 25 is provided with two holes corresponding to the positions, shapes and sizes of the two grooves 23, further ensuring the sealing reliability of the sealing gasket 25.
  • the box 100 includes a bottom plate 101, the bottom plate 101 is provided with an opening 1011, the opening 1011 is connected to the groove 23, the mounting portion 222 is provided inside the box 100, or the mounting portion 222 passes through the opening 1011 so that the cover plate 24 is connected to the mounting portion 222, and the channel unit 2 is connected to the bottom plate 101 according to the internal layout of the box 100 or the layout of the whole vehicle, so as to facilitate the layout; in other embodiments, the box 100 includes an upper cover 103, and the channel unit 2 can also be installed on the upper cover 103, which is specifically arranged according to actual conditions and is not limited.
  • the mounting portion 222 is provided on the side of the bottom plate 101 close to the inside of the box 100, and the bottom plate 101 is provided with an opening 1011 to facilitate the connection between the cover plate 24 and the mounting portion 222.
  • the internal structure of the box 100 can be assembled first, and finally the cover plate 24 can be connected from the outside of the box 100.
  • the channel unit 2 may be disposed inside the box body 100 , and the cover plate 24 may pass through the opening 1011 to be connected with the mounting portion 222 , without limitation.
  • the bottom plate 101 is provided with a recessed groove 1012, and the opening 1011 is provided at the bottom of the recessed groove 1012.
  • the cover plate 24 is connected, it is avoided to protrude from the surface of the bottom plate 101 and to avoid exceeding the space of the chassis.
  • the bottom plate 101 can be an integrally formed stamping part, and the recessed groove 1012 is formed by stamping toward one side.
  • the box body 100 also includes a protective plate 102, the protective plate 102 is connected to the bottom plate 101, and the cover plate 24 is provided on the side of the protective plate 102 facing the bottom plate 101.
  • the protective plate 102 is a PVC plate.
  • the channel unit 2 is sealed and connected to the opening 1011 by a sealant, so as to ensure the sealing between the channel unit 2 and the opening 1011 and avoid leakage, and also avoid the risk of leakage caused by aging of the sealing ring when the sealing connection is sealed by the sealing ring;
  • the mounting portion 222 is provided with a flange 2222, and the mounting portion 222 is installed from the top of the base plate 101 and passes through the opening 1011, and the flange 2222 abuts against the top periphery of the recessed groove 1012, and the mounting portion 222 passes through the opening 1011 and is filled and sealed with potting glue to ensure the sealing.
  • the mounting portion 222 passes through the opening 1011, and the flange 2222 is arranged on the side of the mounting portion 222 away from the protruding portion 221.
  • the liquid cooling plate unit 1 includes a plurality of stamped cold plates 13
  • two connector assemblies 3 include a first connector assembly and a second connector assembly
  • the first connector assembly includes a plurality of first connector bodies
  • the second connector assembly includes a plurality of second connector bodies 32
  • the plurality of first connector bodies 31 and the plurality of second connector bodies 32 correspond to the plurality of stamped cold plates 13 one by one, respectively
  • the stamped cold plate 13 is connected to one accommodating space 22b through the first connector body 31, and is connected to another accommodating space 22b through the second connector body 32.
  • the plurality of stamped cold plates 13 share the same channel unit 2 to be connected to the cooling equipment at the vehicle end, simplifying the structure; by increasing the number of stamped cold plates 13, the cooling effect is improved, and the number of liquid cooling plates can be set according to the number and arrangement of the battery cells 200 in the box 100, etc., without limitation.
  • two stamped cold plates 13 and two first connector bodies 31 and two second connector bodies 32 are provided, wherein one first connector body 31 is used as the water inlet 11 of the first stamped cold plate 13, one second connector body 32 is used as the water outlet 12 of the first stamped cold plate 13, and another first connector body 31 and another second connector body 32 are used as the water inlet 11 and water outlet 12 of the second stamped cold plate 13, respectively.
  • first connector body 31 and the second connector body 32 may be structures such as connecting pipes, and the structure and size are set according to the spatial layout.

Landscapes

  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • General Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Aviation & Aerospace Engineering (AREA)
  • Secondary Cells (AREA)

Abstract

A liquid cooling device and a battery pack. The liquid cooling device comprises a liquid cooling plate unit, two joints and a channel unit, wherein the liquid cooling plate unit is arranged in a box and is used for cooling a battery cell in the box, and the liquid cooling plate unit has a water inlet and a water outlet; the two joints are arranged on the outside of the box and used for connecting to an external cooling apparatus; and the channel unit comprises two pipeline components fixed to the box, one pipeline component being connected to one joint and the water inlet, and the other pipeline component being connected to the other joint and the water outlet.

Description

液冷装置及电池包Liquid cooling device and battery pack
本申请要求在2022年10月21日提交中国专利局、申请号分别为202222783781.9以及202222781665.3的中国专利申请的优先权,以上申请的全部内容通过引用结合在本申请中。This application claims the priority of Chinese patent applications filed with the China Patent Office on October 21, 2022, with application numbers 202222783781.9 and 202222781665.3, and the entire contents of the above applications are incorporated by reference into this application.
技术领域Technical Field
本申请涉及电池技术领域,尤其涉及一种液冷装置及电池包。The present application relates to the field of battery technology, and in particular to a liquid cooling device and a battery pack.
背景技术Background technique
电池包包括箱体和设于箱体内的电芯以及冷却板,冷却板的通过接头与外部整车端的冷却设备连接,向冷却板内供应冷却水以对电芯进行冷却。现有技术中,快插公接头与冷却板焊接且均设置在箱体内部,接头与整车端冷却设备的进、出水口通过尼龙管路与快插公接头进行快插连接。The battery pack includes a box body, a battery cell and a cooling plate arranged in the box body. The cooling plate is connected to the cooling equipment on the external vehicle end through a joint, and cooling water is supplied to the cooling plate to cool the battery cell. In the prior art, the quick-plug male connector is welded to the cooling plate and both are arranged inside the box body. The connector and the water inlet and outlet of the cooling equipment on the vehicle end are quickly connected through nylon pipes and quick-plug male connectors.
然而,由于快插公接头设于箱体内部,导致拆装的次数存在限制,尼龙管路与快插公接头经过多次插拔后存在密封失效的风险,产生漏液,从而导致电池包失效的风险;另外,快插公接头会占用箱体内部空间,对箱体内部空间要求较高。However, since the quick-connect male connector is located inside the box, the number of times it can be disassembled and assembled is limited. After multiple insertions and removals, there is a risk of sealing failure between the nylon tube and the quick-connect male connector, resulting in leakage, which in turn leads to the risk of failure of the battery pack. In addition, the quick-connect male connector occupies space inside the box, placing high demands on the space inside the box.
发明概述SUMMARY OF THE INVENTION
本申请提供一种液冷装置及电池包来解决上述技术问题。The present application provides a liquid cooling device and a battery pack to solve the above-mentioned technical problems.
本申请提供一种液冷装置,包括:The present application provides a liquid cooling device, comprising:
液冷板单元,设于箱体内部,所述液冷板单元用于对所述箱体内的电芯进行冷却,所述液冷板单元具有进水口和出水口;A liquid cooling plate unit is arranged inside the box, and is used to cool the battery cells in the box. The liquid cooling plate unit has a water inlet and a water outlet;
两个接头,设于所述箱体外部,用于与外部冷却设备连接;及,Two connectors, provided outside the box, for connecting to external cooling equipment; and,
通道单元,包括两个固定于所述箱体上的管路组件,一个所述管路组件连接其中一个所述接头和所述进水口,另一个所述管路组件连接另一个所述接头和所述出水口。The channel unit comprises two pipeline assemblies fixed on the box body, one of the pipeline assemblies connects one of the joints and the water inlet, and the other pipeline assembly connects the other joint and the water outlet.
本申请还提供一种电池包,包括箱体、电芯和上述的液冷装置。The present application also provides a battery pack, comprising a box body, a battery cell and the above-mentioned liquid cooling device.
有益效果Beneficial Effects
本申请的有益效果为:本申请提供的液冷装置,通过将接头设于箱体外部,实现了整车端的冷却设备可以在箱体外部直接与接头连接;具体接头可以是快插头,整车端的冷却设备通过尼龙管路与快插头连接,避免了现有技术中快插公接头设有箱体内而占用箱体内部空间,降低了对箱体内部空间的要求。方便了接头与整车端的冷却设备拆装,提高了便利性;除去了箱体内部快插公接头,消除了因快插公接头漏液导致电池包产生的失效风险,提高了电池包的可靠性。简化了箱体内部管路及相关配件,优化了安装过程,并且降低了箱体空间的要求。The beneficial effects of the present application are as follows: the liquid cooling device provided by the present application, by arranging the joint outside the box, realizes that the cooling equipment on the vehicle end can be directly connected to the joint outside the box; the specific joint can be a quick plug, and the cooling equipment on the vehicle end is connected to the quick plug through a nylon pipe, which avoids the prior art that the quick-insert male joint is arranged in the box and occupies the internal space of the box, and reduces the requirements for the internal space of the box. It facilitates the disassembly and assembly of the joint and the cooling equipment on the vehicle end, and improves convenience; the quick-insert male joint inside the box is removed, eliminating the risk of failure of the battery pack caused by leakage of the quick-insert male joint, and improving the reliability of the battery pack. The internal pipes and related accessories of the box are simplified, the installation process is optimized, and the requirements for the box space are reduced.
本申请提供的电池包,采用上述的液冷装置,液冷装置设于箱体,用于对箱体内的电芯进行液冷,液冷装置将接头设于箱体外部,实现了整车端的冷却设备可以在箱体外部直接与接头连接,降低了对箱体内部空间的要求,方便了接头与整车端的冷却设备拆装,提高了便利性;同时,消除了因快插公接头漏液导致电池包产生的失效风险,提高了电池包的可靠性。简化了箱体内部管路及相关配件,优化了安装过程,并且降低了箱体空间的要求。The battery pack provided by the present application adopts the above-mentioned liquid cooling device, which is arranged in the box body and is used to liquid-cool the battery cells in the box body. The liquid cooling device arranges the connector outside the box body, so that the cooling equipment on the vehicle side can be directly connected to the connector outside the box body, reducing the requirements for the internal space of the box body, facilitating the disassembly and assembly of the connector and the cooling equipment on the vehicle side, and improving convenience; at the same time, it eliminates the risk of failure of the battery pack caused by leakage of the quick-insert male connector, and improves the reliability of the battery pack. The internal pipes and related accessories of the box body are simplified, the installation process is optimized, and the requirements for the box space are reduced.
附图说明BRIEF DESCRIPTION OF THE DRAWINGS
图1是实施例一提供的电池包的***图;FIG1 is an exploded view of a battery pack provided in Embodiment 1;
图2是图1的A处放大图;Fig. 2 is an enlarged view of point A in Fig. 1;
图3是实施例一提供的通道单元的***图;FIG3 is an exploded view of a channel unit provided in Embodiment 1;
图4是实施例一提供的基体的示意图;FIG4 is a schematic diagram of a substrate provided in Example 1;
图5是实施例一提供的底板的局部示意图;FIG5 is a partial schematic diagram of the bottom plate provided in Example 1;
图6是实施例二提供的电池包的***图;FIG6 is an exploded view of a battery pack provided in Embodiment 2;
图7是图6的B处放大图;FIG7 is an enlarged view of point B in FIG6;
图8是实施例二提供的连接块组件的***图;FIG8 is an exploded view of the connection block assembly provided in Embodiment 2;
图9是实施例二提供的连接块本体的结构示意图;FIG9 is a schematic structural diagram of a connecting block body provided in Embodiment 2;
图10是实施例二提供的底板的局部示意图。FIG. 10 is a partial schematic diagram of the bottom plate provided in the second embodiment.
附图标记说明:Description of reference numerals:
1、液冷板单元;11、进水口;12、出水口;13、冲压冷板;1. Liquid cooling plate unit; 11. Water inlet; 12. Water outlet; 13. Stamping cold plate;
2、通道单元;21、管路组件;211、总管路;212、分管路;213、软管;22、基体;24a、容置腔;24b、容纳空间;221、伸出部;2211、通孔;222、安装部;2221、容纳槽;2222、凸缘;23、凹槽;24、盖板;25、密封垫;2. channel unit; 21. pipeline assembly; 211. main pipeline; 212. branch pipeline; 213. hose; 22. base; 24a. accommodating cavity; 24b. accommodating space; 221. extension portion; 2211. through hole; 222. mounting portion; 2221. accommodating groove; 2222. flange; 23. groove; 24. cover plate; 25. sealing gasket;
3、连接头组件;31、第一连接头本体;32、第二连接头本体;3. Connector assembly; 31. First connector body; 32. Second connector body;
4、接头;4. Connector;
100、箱体;101、底板;1011、开孔;1012、凹陷槽;102、防护板;103、上盖;104、边框; 200、电芯。100, housing; 101, bottom plate; 1011, opening; 1012, recessed groove; 102, protective plate; 103, upper cover; 104, frame; 200, battery cell.
本发明的实施方式Embodiments of the present invention
在本申请的描述中,除非另有明确的规定和限定,术语“相连”、“连接”、“固定”应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是机械连接,也可以是电连接;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通或两个元件的相互作用关系。对于本领域的普通技术人员而言,可视具体情况理解上述术语在本申请中的具体含义。In the description of this application, unless otherwise clearly specified and limited, the terms "connected", "connected", and "fixed" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to the specific circumstances.
在本申请中,除非另有明确的规定和限定,第一特征在第二特征之“上”或之“下”可以包括第一和第二特征直接接触,也可以包括第一和第二特征不是直接接触而是通过它们之间的另外的特征接触。而且,第一特征在第二特征“之上”、“上方”和“上面”包括第一特征在第二特征正上方和斜上方,或仅仅表示第一特征水平高度高于第二特征。第一特征在第二特征“之下”、“下方”和“下面”包括第一特征在第二特征正下方和斜下方,或仅仅表示第一特征水平高度小于第二特征。In the present application, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.
在本实施例的描述中,术语“上”、“下”、“右”、等方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述和简化操作,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本申请的限制。此外,术语“第一”、“第二”仅仅用于在描述上加以区分,并没有特殊的含义。In the description of this embodiment, the terms "upper", "lower", "right", etc., are based on the directions or positions shown in the drawings, and are only for the convenience of description and simplification of operation, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as limiting the present application. In addition, the terms "first" and "second" are only used to distinguish in the description and have no special meaning.
实施例一Embodiment 1
如图1和图2所示,包括箱体100、电芯200和液冷装置。本实施例还提供了一种液冷装置,如图1和图2所示,包括液冷板单元1、两个接头4(图中未示出)和通道单元2,液冷板单元1设于箱体100内部,液冷板单元1用于对箱体100内的电芯200进行冷却,液冷板单元1具有进水口11和出水口12;两个接头4设于箱体100外部,用于与外部冷却设备连接;通道单元2包括两个固定于箱体100上的管路组件21,一个管路组件21连接其中一个接头4和进水口11,另一个管路组件21连接另一个接头4和出水口12。As shown in Figures 1 and 2, it includes a box body 100, a battery cell 200 and a liquid cooling device. This embodiment also provides a liquid cooling device, as shown in Figures 1 and 2, including a liquid cooling plate unit 1, two joints 4 (not shown in the figure) and a channel unit 2, the liquid cooling plate unit 1 is arranged inside the box body 100, the liquid cooling plate unit 1 is used to cool the battery cell 200 in the box body 100, and the liquid cooling plate unit 1 has a water inlet 11 and a water outlet 12; the two joints 4 are arranged outside the box body 100 for connecting to an external cooling device; the channel unit 2 includes two pipe assemblies 21 fixed on the box body 100, one pipe assembly 21 connects one of the joints 4 and the water inlet 11, and the other pipe assembly 21 connects the other joint 4 and the water outlet 12.
第一个接头与外部冷却设备的出口连接,第二个接头与外部冷却设备的进口连接。冷却液从出口经过第一个接头、第一个管路组件21和进水口11进入液冷板单元1,经过在液冷板单元1内循环后,冷却液从出水口12进入第二个管路组件21,经过第二个接头和进口回流至外部冷却设备中,从而实现了冷却液在外部冷却设备和液冷装置之间循环。The first joint is connected to the outlet of the external cooling device, and the second joint is connected to the inlet of the external cooling device. The coolant enters the liquid cooling plate unit 1 from the outlet through the first joint, the first pipe assembly 21 and the water inlet 11. After circulating in the liquid cooling plate unit 1, the coolant enters the second pipe assembly 21 from the water outlet 12, and flows back to the external cooling device through the second joint and the inlet, thereby realizing the circulation of the coolant between the external cooling device and the liquid cooling device.
通过将接头设于箱体100外部,实现了整车端的冷却设备可以在箱体100外部直接与接头4连接;具体接头4可以是快插头,整车端的冷却设备通过尼龙管路与快插头连接,避免了现有技术中快插公接头设于箱体100内而占用箱体100内部空间,降低了对箱体100内部空间的要求。方便了接头4与整车端的冷却设备拆装,提高了便利性;除去了箱体100内部快插公接头,消除了因快插公接头漏液导致电池包产生的失效风险,提高了电池包的可靠性。简化了箱体100内部管路及相关配件,优化了安装过程,并且降低了箱体100空间的要求。By arranging the connector outside the box 100, the cooling equipment on the vehicle side can be directly connected to the connector 4 outside the box 100; specifically, the connector 4 can be a quick plug, and the cooling equipment on the vehicle side is connected to the quick plug through a nylon pipe, which avoids the quick-insert male connector being arranged inside the box 100 and occupying the internal space of the box 100 in the prior art, thereby reducing the requirements for the internal space of the box 100. It facilitates the disassembly and assembly of the connector 4 and the cooling equipment on the vehicle side, and improves convenience; the quick-insert male connector inside the box 100 is removed, eliminating the risk of failure of the battery pack caused by leakage of the quick-insert male connector, and improving the reliability of the battery pack. The internal pipes and related accessories of the box 100 are simplified, the installation process is optimized, and the space requirements of the box 100 are reduced.
在一种实施方式中,如图2和图3所示,液冷板单元1设有多个进水口11和多个出水口12时,管路组件21包括总管路211,总管路211与接头4连通,一个管路组件21的总管路211与多个进水口11连通,另一个管路组件21的总管路211与多个出水口12连通,多个进水口11通过总管路211与接头4连通,多个出水口12通过另一个总管路211与接头4连通,简化了多个进水口11与接头4之间的连接结构,以及简化了多个出水口12与接头4之间的连接结构。进一步地,总管路211上连接有多个分管路212,多个分管路212与多个进水口11一一对应连接,另一个总管路211上连接有多个分管路212,多个分管路212与多个出水口12一一对应连接。In one embodiment, as shown in FIG. 2 and FIG. 3 , when the liquid cooling plate unit 1 is provided with a plurality of water inlets 11 and a plurality of water outlets 12, the pipeline assembly 21 includes a main pipeline 211, the main pipeline 211 is connected to the joint 4, the main pipeline 211 of one pipeline assembly 21 is connected to the plurality of water inlets 11, the main pipeline 211 of another pipeline assembly 21 is connected to the plurality of water outlets 12, the plurality of water inlets 11 are connected to the joint 4 through the main pipeline 211, and the plurality of water outlets 12 are connected to the joint 4 through another main pipeline 211, which simplifies the connection structure between the plurality of water inlets 11 and the joint 4, and simplifies the connection structure between the plurality of water outlets 12 and the joint 4. Further, the main pipeline 211 is connected to a plurality of branch pipelines 212, the plurality of branch pipelines 212 are connected to the plurality of water inlets 11 in a one-to-one correspondence, the other main pipeline 211 is connected to a plurality of branch pipelines 212, the plurality of branch pipelines 212 are connected to the plurality of water outlets 12 in a one-to-one correspondence.
在一种实施方式中,如图2所示,管路组件21还包括软管213,软管213用于连接总管路211和液冷板单元1,软管213具有柔性可以根据实际空间大小发生形变,以提高适应性,具体包括多个软管213,软管213连接进水口11与分管路212,或者软管213连接出水口12与分管路212。In one embodiment, as shown in Figure 2, the pipeline assembly 21 also includes a hose 213, which is used to connect the main pipeline 211 and the liquid cooling plate unit 1. The hose 213 is flexible and can be deformed according to the actual space size to improve adaptability. Specifically, it includes multiple hoses 213, and the hose 213 connects the water inlet 11 and the branch pipeline 212, or the hose 213 connects the water outlet 12 and the branch pipeline 212.
本实施例中,如图2所示,液冷板单元1包括两个冲压冷板13,每个冲压冷板13包括一个进水口11和一个出水口12,其他实施例中,液冷板单元1也可以包括多个冲压冷板13,具体冲压冷板13的数量以及多个冲压冷板13之间的排布根据实际情况进行设置即可,不进行限定。In this embodiment, as shown in Figure 2, the liquid cooling plate unit 1 includes two stamped cold plates 13, each stamped cold plate 13 includes a water inlet 11 and a water outlet 12. In other embodiments, the liquid cooling plate unit 1 may also include multiple stamped cold plates 13. The specific number of stamped cold plates 13 and the arrangement between the multiple stamped cold plates 13 can be set according to actual conditions and are not limited.
进一步地,管路组件21还包括卡箍(图中未示出),软管213通过卡箍固定在分管路212上,保证连接可靠性,避免由于连接不可靠性而漏液,进而保证安全性。Furthermore, the pipeline assembly 21 also includes a clamp (not shown in the figure), and the hose 213 is fixed to the branch pipeline 212 by the clamp to ensure connection reliability, avoid leakage due to unreliable connection, and thus ensure safety.
在一种实施方式中,如图2和图3所示,通道单元2还包括基体22,基体22固定于箱体100,且基体22与箱体100形成容置腔22a,总管路211固定于基体22,且容置腔22a用于连通总管路211,总管路211通过基体22固定于箱体100上,使安装稳定。In one embodiment, as shown in Figures 2 and 3, the channel unit 2 also includes a base 22, the base 22 is fixed to the box 100, and the base 22 and the box 100 form a receiving cavity 22a, the main pipeline 211 is fixed to the base 22, and the receiving cavity 22a is used to connect the main pipeline 211, and the main pipeline 211 is fixed to the box 100 through the base 22 to make the installation stable.
在一种实施方式中,如图2和图4所示,基体22的一端设有伸出部221,伸出部221设于箱体100外部,伸出部221设有两个通孔2211,两个接头4分别连接于两个通孔2211,接头4通过通孔2211与容置腔22a连通,避免接头4直接连接在箱体100上,具体可以根据外部冷却设备的接口连接位置等实际需求将通道单元2安装在箱体100上,从而能够提高对外部安装环境的适用性而无需修改箱体100;进一步地,伸出部221抵靠在箱体100上,提高了安装精度。在一种实施方式中,箱体100包括四周围设的边框104,伸出部221伸出于边框104,基体22与边框104形成容置腔22a。In one embodiment, as shown in FIG. 2 and FIG. 4 , a protrusion 221 is provided at one end of the base 22, and the protrusion 221 is provided outside the box 100. The protrusion 221 is provided with two through holes 2211, and two joints 4 are respectively connected to the two through holes 2211. The joints 4 are connected to the accommodating cavity 22a through the through holes 2211, so as to avoid the joints 4 being directly connected to the box 100. Specifically, the channel unit 2 can be installed on the box 100 according to actual requirements such as the interface connection position of the external cooling device, so as to improve the applicability to the external installation environment without modifying the box 100; further, the protrusion 221 abuts against the box 100, so as to improve the installation accuracy. In one embodiment, the box 100 includes a frame 104 arranged around it, and the protrusion 221 protrudes from the frame 104, and the base 22 and the frame 104 form a accommodating cavity 22a.
在一种实施方式中,如图4所示,基体22的另一端设有安装部222,安装部222设有容纳槽2221,总管路211固定连接于容纳槽2221内。在一种实施方式中,如图4和图5所示,箱体100设有开孔1011,容纳槽2221与开孔1011连通,方便安装和维护容纳槽2221内的总管路211。在一种实施方式中,安装部222背离基体22的一侧设有凸缘2222,安装部222穿设于开孔1011时,凸缘2222抵接在箱体100的内壁上,凸缘2222与箱体100内壁能够实现限位,提高了安装精度。In one embodiment, as shown in FIG4 , the other end of the base 22 is provided with a mounting portion 222, the mounting portion 222 is provided with a receiving groove 2221, and the main pipeline 211 is fixedly connected in the receiving groove 2221. In one embodiment, as shown in FIG4 and FIG5 , the box 100 is provided with an opening 1011, and the receiving groove 2221 is communicated with the opening 1011, so as to facilitate the installation and maintenance of the main pipeline 211 in the receiving groove 2221. In one embodiment, a flange 2222 is provided on the side of the mounting portion 222 away from the base 22, and when the mounting portion 222 is inserted into the opening 1011, the flange 2222 abuts against the inner wall of the box 100, and the flange 2222 and the inner wall of the box 100 can be limited, thereby improving the installation accuracy.
在一种实施方式中,安装部222与开孔1011密封连接,从而保证了箱体100内部的密封性。具体地,箱体100包括底板101和上盖103,开孔1011开设在底板101上,安装部222密封安装在底板101上,其他实施例中,也可以根据实际情况将安装部222安装在上盖103上,不进行限定。在一种实施例中,安装部222与开孔1011之间通过密封圈连接,安装方便可靠性好。在另一种实施例中,安装部222与开孔1011之间设有灌封胶结构,避免密封圈长时间使用会出现老化而导致漏液风险。安装时,安装部222从箱体100内部向下安装穿设开孔1011,之后将穿出位置用灌封胶灌满密封。In one embodiment, the mounting portion 222 is sealed and connected to the opening 1011, thereby ensuring the sealing inside the box 100. Specifically, the box 100 includes a bottom plate 101 and an upper cover 103, the opening 1011 is provided on the bottom plate 101, and the mounting portion 222 is sealed and installed on the bottom plate 101. In other embodiments, the mounting portion 222 can also be installed on the upper cover 103 according to actual conditions, without limitation. In one embodiment, the mounting portion 222 is connected to the opening 1011 by a sealing ring, which is convenient to install and has good reliability. In another embodiment, a potting glue structure is provided between the mounting portion 222 and the opening 1011 to avoid the risk of aging of the sealing ring due to long-term use and leakage. During installation, the mounting portion 222 is installed downward from the inside of the box 100 to penetrate the opening 1011, and then the penetration position is filled and sealed with potting glue.
在一种实施方式中,如图1所示,箱体100还包括防护板102,防护板102设于底板101的外部,能够封堵在开孔1011上,对总管路211等结构进行防护,防止因外部石击造成的密封失效问题。具体防护板102可以是PVC板。In one embodiment, as shown in FIG1 , the box 100 further includes a protective plate 102, which is disposed outside the bottom plate 101 and can be sealed on the opening 1011 to protect the main pipeline 211 and other structures to prevent sealing failure caused by external stone impact. Specifically, the protective plate 102 can be a PVC board.
在一种实施方式中,如图5所示,箱体100设有凹陷槽1012,凹陷槽1012的槽口朝向外部,开孔1011开设于凹陷槽1012的槽底,避免总管路211安装在箱体100上向外凸出。In one embodiment, as shown in FIG. 5 , the housing 100 is provided with a recessed groove 1012 , the notch of the recessed groove 1012 faces outward, and the opening 1011 is provided at the bottom of the recessed groove 1012 to prevent the main pipeline 211 from protruding outward when installed on the housing 100 .
实施例二Embodiment 2
如图6和图7所示,包括箱体100、设于箱体100内的电芯200和液冷装置,液冷装置用于对电芯200进行冷却。本实施例提供了一种液冷装置,如图6所示,包括液冷板单元1、两个接头(图中未示出)和通道单元2,液冷板单元1设于箱体100内部,液冷板单元1用于对箱体100内的电芯200进行冷却,液冷板单元1具有进水口11和出水口12;两个接头设于箱体100外部,用于与外部冷却设备连接;通道单元2包括两个固定于箱体100上的管路组件21,一个管路组件21连接其中一个接头4和进水口11,另一个管路组件21连接另一个接头4和出水口12。所述通道单元2密封连接于所述箱体100上,所述通道单元2形成有相分隔的两个容纳空间22b;所述液冷装置还包括两个连接头组件3,一个所述连接头组件3连通所述液冷板单元1的进水口11和一个所述容纳空间22b,另一个所述连接头组件3连通所述液冷板单元1的出水口12和另一个所述容纳空间22b;其中,两个所述管路组件21的两个总管路211固定于所述通道单元2,且分别对应与两个所述容纳空间22b连通。As shown in Figures 6 and 7, it includes a box body 100, a battery cell 200 arranged in the box body 100, and a liquid cooling device, and the liquid cooling device is used to cool the battery cell 200. This embodiment provides a liquid cooling device, as shown in Figure 6, including a liquid cooling plate unit 1, two joints (not shown in the figure) and a channel unit 2, the liquid cooling plate unit 1 is arranged inside the box body 100, the liquid cooling plate unit 1 is used to cool the battery cell 200 in the box body 100, and the liquid cooling plate unit 1 has a water inlet 11 and a water outlet 12; the two joints are arranged outside the box body 100 for connecting to an external cooling device; the channel unit 2 includes two pipe assemblies 21 fixed on the box body 100, one pipe assembly 21 connects one of the joints 4 and the water inlet 11, and the other pipe assembly 21 connects the other joint 4 and the water outlet 12. The channel unit 2 is sealed and connected to the box body 100, and the channel unit 2 forms two separated accommodating spaces 22b; the liquid cooling device also includes two connector assemblies 3, one of the connector assemblies 3 is connected to the water inlet 11 of the liquid cooling plate unit 1 and one of the accommodating spaces 22b, and the other of the connector assemblies 3 is connected to the water outlet 12 of the liquid cooling plate unit 1 and another of the accommodating spaces 22b; wherein, the two main pipelines 211 of the two pipeline assemblies 21 are fixed to the channel unit 2, and are respectively connected to the two accommodating spaces 22b.
通过将接头设于箱体100外部,实现了整车端的冷却设备可以在箱体100外部直接与接头连接;具体接头4可以是快插头,整车端的冷却设备通过尼龙管路与快插头连接,避免了现有技术中快插公接头设于箱体100内而占用箱体100内部空间,降低了对箱体100内部空间的要求。方便了接头4与整车端的冷却设备拆装,提高了便利性;除去了箱体100内部快插公接头,消除了因快插公接头漏液导致电池包产生的失效风险,提高了电池包的可靠性。简化了箱体100内部管路及相关配件,优化了安装过程,并且降低了箱体100空间的要求。By arranging the connector outside the box 100, the cooling equipment on the vehicle side can be directly connected to the connector outside the box 100; specifically, the connector 4 can be a quick plug, and the cooling equipment on the vehicle side is connected to the quick plug through a nylon pipe, which avoids the quick-insert male connector being arranged inside the box 100 and occupying the internal space of the box 100 in the prior art, thereby reducing the requirements for the internal space of the box 100. It facilitates the disassembly and assembly of the connector 4 and the cooling equipment on the vehicle side, and improves convenience; the quick-insert male connector inside the box 100 is removed, eliminating the risk of failure of the battery pack caused by leakage of the quick-insert male connector, and improving the reliability of the battery pack. The internal pipes and related accessories of the box 100 are simplified, the installation process is optimized, and the space requirements of the box 100 are reduced.
在一种实施方式中,箱体100内形成容置腔22a,容置腔22a分别与两个所述容纳空间22b连通。一种实施例中,箱体100通过容置腔22a直接与外部连接,另一种实施例中,如图7和图8所示,容置腔22a作为中间腔体,设于总管路和容纳空间22b的中间。In one embodiment, a receiving cavity 22a is formed in the box body 100, and the receiving cavity 22a is communicated with the two receiving spaces 22b respectively. In one embodiment, the box body 100 is directly connected to the outside through the receiving cavity 22a. In another embodiment, as shown in Figures 7 and 8, the receiving cavity 22a is used as an intermediate cavity and is arranged between the main pipeline and the receiving space 22b.
具体地,如图9所示,所述通道单元2包括伸出部221、基体22以及安装部222,所述基体22与所述箱体100之间围合形成有所述容置腔22a,所述伸出部221设于基体22的一端,所述伸出部221处于所述箱体100外部且与所述箱体100的外壁抵接,所述安装部222设于所述基体22的另一端;其中,两个所述容纳空间22b形成于所述安装部222上;两个所述总管路211设于所述通道单元2,两个所述总管路211的一端分别对应与两个所述容纳空间22b连通,两个所述总管路211的另一端穿设于所述伸出部221且与两个所述接头4连通。通过两个所述总管路211连接,避免液体泄露,进一步提高了密封性。一般安装部222可采用塑料等轻质材质制成,而总管路211采用金属等耐磨材料制成,避免接口与快插接头等连接时出现失效。具体地,总管路211与安装部222为一体注塑成型结构。Specifically, as shown in FIG9 , the channel unit 2 includes a protruding portion 221, a base 22, and a mounting portion 222. The base 22 and the box 100 enclose the accommodating cavity 22a. The protruding portion 221 is provided at one end of the base 22. The protruding portion 221 is located outside the box 100 and abuts against the outer wall of the box 100. The mounting portion 222 is provided at the other end of the base 22. Two accommodating spaces 22b are formed on the mounting portion 222. Two main pipelines 211 are provided in the channel unit 2. One end of the two main pipelines 211 is respectively connected to the two accommodating spaces 22b. The other end of the two main pipelines 211 is passed through the protruding portion 221 and is connected to the two joints 4. The connection of the two main pipelines 211 can avoid liquid leakage and further improve the sealing performance. Generally, the mounting portion 222 can be made of a lightweight material such as plastic, while the main pipeline 211 is made of a wear-resistant material such as metal to avoid failure when the interface is connected to a quick-connect connector, etc. Specifically, the main pipeline 211 and the mounting portion 222 are an integral injection molding structure.
在一种实施方式中,如图8所示,箱体100包括边框104,容置腔22a设于边框104上,使总管路211的一端穿设于箱体100的侧面,整车端的冷却设备与箱体100侧面连接,具体底板101的四周均设有边框104,总管路211的一端穿设于其中一侧的边框104,具体根据实际整车端布局等进行设置,不进行限定。进一步地,伸出部221穿设于边框104并与边框104共同形成容置腔22a。In one embodiment, as shown in FIG8 , the box 100 includes a frame 104, and the accommodating cavity 22a is provided on the frame 104, so that one end of the main pipeline 211 is provided through the side of the box 100, and the cooling equipment at the vehicle end is connected to the side of the box 100. Specifically, the bottom plate 101 is provided with a frame 104 on all four sides, and one end of the main pipeline 211 is provided through the frame 104 on one side. The specific setting is based on the actual layout of the vehicle end, etc., and is not limited. Further, the extension portion 221 is provided through the frame 104 and forms the accommodating cavity 22a together with the frame 104.
在一种实施方式中,如图7和图8所示,通道单元2包括安装部222和盖板24,所述安装部222连接于所述箱体100,所述安装部222上开设有相分隔的两个凹槽23,所述盖板24连接于所述安装部222上,所述盖板24分别和两个所述凹槽23形成两个所述容纳空间22b,通过安装部222和盖板24分体设置,连接形成容纳空间22b,方便制作,通过盖板24与连接孔本体进行锁附,保证了容纳空间的密封性。In one embodiment, as shown in Figures 7 and 8, the channel unit 2 includes a mounting portion 222 and a cover plate 24, the mounting portion 222 is connected to the box body 100, the mounting portion 222 is provided with two separated grooves 23, the cover plate 24 is connected to the mounting portion 222, the cover plate 24 and the two grooves 23 respectively form two accommodating spaces 22b, the mounting portion 222 and the cover plate 24 are separately arranged and connected to form the accommodating space 22b, which is convenient for manufacturing, and the cover plate 24 is locked with the connecting hole body to ensure the sealing of the accommodating space.
在一种实施方式中,如图8所示,通道单元2还包括密封垫25,盖板24通过密封垫25与安装部222密封连接,进一步提高了容纳空间22b的密封性。进一步地,安装部222开设有与两个凹槽23均连通的容置槽,密封垫25设于容置槽内,限制了密封垫25的移动,提高了密封垫25安装可靠性。具体地,密封垫25开设有与两个凹槽23位置和形状大小相对应的两个孔,进一步保证了密封垫25的密封可靠性。In one embodiment, as shown in FIG8 , the channel unit 2 further includes a sealing gasket 25, and the cover plate 24 is sealed and connected to the mounting portion 222 through the sealing gasket 25, further improving the sealing performance of the accommodating space 22b. Furthermore, the mounting portion 222 is provided with a receiving groove that is in communication with both grooves 23, and the sealing gasket 25 is arranged in the receiving groove, which limits the movement of the sealing gasket 25 and improves the installation reliability of the sealing gasket 25. Specifically, the sealing gasket 25 is provided with two holes corresponding to the positions, shapes and sizes of the two grooves 23, further ensuring the sealing reliability of the sealing gasket 25.
在一种实施方式中,如图10所示,箱体100包括底板101,底板101设有开孔1011,开孔1011与凹槽23连通,安装部222设于箱体100内部,或安装部222穿过开孔1011以使盖板24与安装部222连接,根据箱体100内部布局或者整车布局,将通道单元2连接在底板101上,方便布局;其他实施例中,箱体100包括上盖103,通道单元2也可以安装在上盖103上,具体根据实际情况进行设置,不进行限定。安装部222设于底板101靠近箱体100内部一侧,底板101设有开孔1011,以方便盖板24与安装部222相连接,组装时可先进行箱体100内部结构组装,最后将盖板24从箱体100外部进行连接。另一个实施例中,也可以通道单元2设于箱体100内部,盖板24穿设于开孔1011以与安装部222连接,不进行限制。In one embodiment, as shown in FIG. 10 , the box 100 includes a bottom plate 101, the bottom plate 101 is provided with an opening 1011, the opening 1011 is connected to the groove 23, the mounting portion 222 is provided inside the box 100, or the mounting portion 222 passes through the opening 1011 so that the cover plate 24 is connected to the mounting portion 222, and the channel unit 2 is connected to the bottom plate 101 according to the internal layout of the box 100 or the layout of the whole vehicle, so as to facilitate the layout; in other embodiments, the box 100 includes an upper cover 103, and the channel unit 2 can also be installed on the upper cover 103, which is specifically arranged according to actual conditions and is not limited. The mounting portion 222 is provided on the side of the bottom plate 101 close to the inside of the box 100, and the bottom plate 101 is provided with an opening 1011 to facilitate the connection between the cover plate 24 and the mounting portion 222. When assembling, the internal structure of the box 100 can be assembled first, and finally the cover plate 24 can be connected from the outside of the box 100. In another embodiment, the channel unit 2 may be disposed inside the box body 100 , and the cover plate 24 may pass through the opening 1011 to be connected with the mounting portion 222 , without limitation.
在一种实施方式中,如图10所示,底板101设有凹陷槽1012,开孔1011开设于凹陷槽 1012的槽底,盖板24连接时避免凸出于底板101的表面,避免超过底盘的空间。具体地,底板101可以是一体成型的冲压件,凹陷槽1012通过朝一侧冲压形成。在一种实施方式中,箱体100还包括防护板102,防护板102连接于底板101,盖板24设于防护板102朝向底板101的一侧,通过增加一层防护板102,使底板101及与底板101连接的通道单元2受到防护,防止因外部石击造成密封失效问题,可选地,防护板102为PVC板。In one embodiment, as shown in FIG. 10 , the bottom plate 101 is provided with a recessed groove 1012, and the opening 1011 is provided at the bottom of the recessed groove 1012. When the cover plate 24 is connected, it is avoided to protrude from the surface of the bottom plate 101 and to avoid exceeding the space of the chassis. Specifically, the bottom plate 101 can be an integrally formed stamping part, and the recessed groove 1012 is formed by stamping toward one side. In one embodiment, the box body 100 also includes a protective plate 102, the protective plate 102 is connected to the bottom plate 101, and the cover plate 24 is provided on the side of the protective plate 102 facing the bottom plate 101. By adding a layer of protective plate 102, the bottom plate 101 and the channel unit 2 connected to the bottom plate 101 are protected to prevent sealing failure caused by external stone impact. Optionally, the protective plate 102 is a PVC plate.
在一种实施方式中,如图9所示,通道单元2通过密封胶密封连接于开孔1011,保证通道单元2与开孔1011之间的密封性,避免漏液,且避免了通过密封圈密封连接,当密封圈老化时而产生的漏液风险;具体地,安装部222设有凸缘2222,将安装部222从底板101的顶部安装并穿过开孔1011,凸缘2222抵接在凹陷槽1012的顶部周缘,安装部222穿过开孔1011位置用灌封胶灌满密封,保证了密封性,本实施例中,安装部222穿过开孔1011,凸缘2222设于安装部222背离伸出部221的一侧。In one embodiment, as shown in FIG. 9 , the channel unit 2 is sealed and connected to the opening 1011 by a sealant, so as to ensure the sealing between the channel unit 2 and the opening 1011 and avoid leakage, and also avoid the risk of leakage caused by aging of the sealing ring when the sealing connection is sealed by the sealing ring; specifically, the mounting portion 222 is provided with a flange 2222, and the mounting portion 222 is installed from the top of the base plate 101 and passes through the opening 1011, and the flange 2222 abuts against the top periphery of the recessed groove 1012, and the mounting portion 222 passes through the opening 1011 and is filled and sealed with potting glue to ensure the sealing. In this embodiment, the mounting portion 222 passes through the opening 1011, and the flange 2222 is arranged on the side of the mounting portion 222 away from the protruding portion 221.
在一种实施方式中,如图6和图7所示,液冷板单元1包括多个冲压冷板13,两个连接头组件3包括第一连接头组件和第二连接头组件,第一连接头组件包括多个第一连接头本体31,第二连接头组件包括多个第二连接头本体32,多个第一连接头本体31和多个第二连接头本体32分别与多个冲压冷板13一一对应,冲压冷板13通过第一连接头本体31与一个容纳空间22b连通,通过第二连接头本体32与另一个容纳空间22b连通。从而使多个冲压冷板13共用同一个通道单元2与整车端的冷却设备连接,简化了结构;通过增加冲压冷板13数量,提高了冷却效果,具体可以根据箱体100内电芯200的数量及排布等情况设置液冷板的数量,不进行限定。本实施例中,设有两个冲压冷板13和两个第一连接头本体31和两个第二连接头本体32,其中一个第一连接头本体31用作为第一个冲压冷板13的进水口11,一个第二连接头本体32用作为第一个冲压冷板13的出水口12,另一个第一连接头本体31和另一个第二连接头本体32分别用作为第二个冲压冷板13的进水口11和出水口12。In one embodiment, as shown in FIG6 and FIG7, the liquid cooling plate unit 1 includes a plurality of stamped cold plates 13, two connector assemblies 3 include a first connector assembly and a second connector assembly, the first connector assembly includes a plurality of first connector bodies 31, the second connector assembly includes a plurality of second connector bodies 32, the plurality of first connector bodies 31 and the plurality of second connector bodies 32 correspond to the plurality of stamped cold plates 13 one by one, respectively, the stamped cold plate 13 is connected to one accommodating space 22b through the first connector body 31, and is connected to another accommodating space 22b through the second connector body 32. Thus, the plurality of stamped cold plates 13 share the same channel unit 2 to be connected to the cooling equipment at the vehicle end, simplifying the structure; by increasing the number of stamped cold plates 13, the cooling effect is improved, and the number of liquid cooling plates can be set according to the number and arrangement of the battery cells 200 in the box 100, etc., without limitation. In this embodiment, two stamped cold plates 13 and two first connector bodies 31 and two second connector bodies 32 are provided, wherein one first connector body 31 is used as the water inlet 11 of the first stamped cold plate 13, one second connector body 32 is used as the water outlet 12 of the first stamped cold plate 13, and another first connector body 31 and another second connector body 32 are used as the water inlet 11 and water outlet 12 of the second stamped cold plate 13, respectively.
具体地第一个连接头本体31和第二连接头本体32可以是连接管等结构,根据空间布局进行设置结构和大小等。Specifically, the first connector body 31 and the second connector body 32 may be structures such as connecting pipes, and the structure and size are set according to the spatial layout.

Claims (23)

  1. 一种液冷装置,其中,包括:A liquid cooling device, comprising:
    液冷板单元(1),所述液冷板单元(1)设于箱体(100)内部,所述液冷板单元(1)用于对所述箱体(100)内的电芯(200)进行冷却,所述液冷板单元(1)具有进水口(11)和出水口(12);A liquid cooling plate unit (1), the liquid cooling plate unit (1) being arranged inside the box (100), the liquid cooling plate unit (1) being used to cool the battery core (200) inside the box (100), the liquid cooling plate unit (1) having a water inlet (11) and a water outlet (12);
    两个接头(4),两个所述接头(4)设于所述箱体(100)外部,两个所述接头(4)用于与外部冷却设备连接;及two connectors (4), the two connectors (4) being arranged outside the box (100), the two connectors (4) being used to connect to an external cooling device; and
    通道单元(2),所述通道单元(2)包括两个固定于所述箱体(100)上的管路组件(21),一个所述管路组件(21)连接其中一个所述接头(4)和所述进水口(11),另一个所述管路组件(21)连接另一个所述接头(4)和所述出水口(12)。A channel unit (2), the channel unit (2) comprising two pipe assemblies (21) fixed to the box body (100), one pipe assembly (21) connecting one of the joints (4) and the water inlet (11), and the other pipe assembly (21) connecting the other joint (4) and the water outlet (12).
  2. 根据权利要求1所述的液冷装置,其中,所述液冷板单元(1)设有多个所述进水口(11)和多个所述出水口(12)时,所述管路组件(21)包括总管路(211),所述总管路(211)与所述接头(4)连通,一个所述管路组件(21)的所述总管路(211)与多个所述进水口(11)连通,另一个所述管路组件(21)的所述总管路(211)与多个所述出水口(12)连通。The liquid cooling device according to claim 1, wherein when the liquid cooling plate unit (1) is provided with a plurality of the water inlets (11) and a plurality of the water outlets (12), the pipeline assembly (21) comprises a main pipeline (211), the main pipeline (211) is connected to the joint (4), the main pipeline (211) of one pipeline assembly (21) is connected to the plurality of the water inlets (11), and the main pipeline (211) of another pipeline assembly (21) is connected to the plurality of the water outlets (12).
  3. 根据权利要求2所述的液冷装置,其中,所述管路组件(21)还包括软管(213),所述软管(213)用于连接所述总管路(211)和所述液冷板单元(1)。The liquid cooling device according to claim 2, wherein the pipeline assembly (21) further comprises a hose (213), and the hose (213) is used to connect the main pipeline (211) and the liquid cooling plate unit (1).
  4. 根据权利要求2或3所述的液冷装置,其中,所述通道单元(2)还包括基体(22),所述基体(22)固定于所述箱体(100),且所述基体(22)与所述箱体(100)形成容置腔(22a),所述总管路(21)固定于所述基体(22),且所述容置腔(22a)用于连通所述总管路(21)。The liquid cooling device according to claim 2 or 3, wherein the channel unit (2) further comprises a base (22), the base (22) is fixed to the housing (100), and the base (22) and the housing (100) form a receiving cavity (22a), the main pipeline (21) is fixed to the base (22), and the receiving cavity (22a) is used to connect the main pipeline (21).
  5. 根据权利要求4所述的液冷装置,其中,所述基体(22)的一端设有伸出部(221),所述伸出部(221)设于所述箱体(100)外部,所述伸出部(221)设有两个通孔(2211),两个所述接头(4)分别连接于两个所述通孔(2211),所述接头(4)通过所述通孔(2211)与所述容置腔(22a)连通。The liquid cooling device according to claim 4, wherein an extension portion (221) is provided at one end of the base (22), the extension portion (221) is provided outside the box (100), the extension portion (221) is provided with two through holes (2211), the two joints (4) are respectively connected to the two through holes (2211), and the joint (4) is connected to the accommodating cavity (22a) through the through holes (2211).
  6. 根据权利要求4所述的液冷装置,其中,所述基体(22)的另一端设有安装部(222),所述安装部(222)设有容纳槽(2221),所述总管路(21)固定于所述容纳槽(2221)内。The liquid cooling device according to claim 4, wherein the other end of the base (22) is provided with a mounting portion (222), the mounting portion (222) is provided with a receiving groove (2221), and the main pipeline (21) is fixed in the receiving groove (2221).
  7. 根据权利要求6所述的液冷装置,其中,所述箱体(100)设有开孔(1011),所述容纳槽(2221)与所述开孔(1011)连通。The liquid cooling device according to claim 6, wherein the housing (100) is provided with an opening (1011), and the receiving groove (2221) is connected to the opening (1011).
  8. 根据权利要求7所述的液冷装置,其中,所述安装部(222)背离所述基体(22)的一侧设有凸缘(2222),所述安装部(222)穿设于所述开孔(1011)时,所述凸缘(2222)抵接在所述箱体(100)的内壁上。The liquid cooling device according to claim 7, wherein a flange (2222) is provided on a side of the mounting portion (222) facing away from the base (22), and when the mounting portion (222) is passed through the opening (1011), the flange (2222) abuts against the inner wall of the box body (100).
  9. 根据权利要求7所述的液冷装置,其中,所述安装部(222)与所述开孔(1011)密封连接。The liquid cooling device according to claim 7, wherein the mounting portion (222) is sealedly connected to the opening (1011).
  10. 根据权利要求9所述的液冷装置,其中,所述安装部(222)与所述开孔(1011)之间设有灌封胶结构。The liquid cooling device according to claim 9, wherein a potting glue structure is provided between the mounting portion (222) and the opening (1011).
  11. 根据权利要求7所述的液冷装置,其中,所述箱体(100)包括底板(101)和防护板(102),所述开孔(1011)开设于所述底板(101)上,所述防护板(102)设于所述底板(101)的外部。The liquid cooling device according to claim 7, wherein the housing (100) comprises a base plate (101) and a protective plate (102), the opening (1011) is provided on the base plate (101), and the protective plate (102) is provided outside the base plate (101).
  12. 根据权利要求7所述的液冷装置,其中,所述箱体(100)设有凹陷槽(1012),所述凹陷槽(1012)的槽口朝向外部,所述开孔(1011)开设于所述凹陷槽(1012)的槽底。The liquid cooling device according to claim 7, wherein the housing (100) is provided with a recessed groove (1012), the notch of the recessed groove (1012) faces outward, and the opening (1011) is provided at the bottom of the recessed groove (1012).
  13. 根据权利要求2所述的液冷装置,其中,所述通道单元(2)密封连接于所述箱体(100)上,所述通道单元(2)形成有相分隔的两个容纳空间(22b);The liquid cooling device according to claim 2, wherein the channel unit (2) is sealed and connected to the box body (100), and the channel unit (2) forms two separated accommodating spaces (22b);
    所述液冷装置还包括两个连接头组件(3),一个所述连接头组件(3)连通所述液冷板单元(1)的进水口(11)和一个所述容纳空间(22b),另一个所述连接头组件(3)连通所述液冷板单元(1)的出水口(12)和另一个所述容纳空间(22b);The liquid cooling device further comprises two connector assemblies (3), one of the connector assemblies (3) being connected to a water inlet (11) of the liquid cooling plate unit (1) and one of the accommodating spaces (22b), and the other of the connector assemblies (3) being connected to a water outlet (12) of the liquid cooling plate unit (1) and another of the accommodating spaces (22b);
    其中,两个所述管路组件(21)的两个总管路(21)固定于所述通道单元(2),且分别对应与两个所述容纳空间(22b)连通。The two main pipelines (21) of the two pipeline assemblies (21) are fixed to the channel unit (2) and are respectively connected to the two accommodating spaces (22b).
  14. 根据权利要求13所述的液冷装置,其中,所述箱体(100)内形成有容置腔(22a),所述容置腔(22a)与两个所述容纳空间(22b)连通。The liquid cooling device according to claim 13, wherein a accommodating cavity (22a) is formed in the box body (100), and the accommodating cavity (22a) is communicated with the two accommodating spaces (22b).
  15. 根据权利要求14所述的液冷装置,其中,所述通道单元(2)包括伸出部(221)、基体(22)以及安装部(222),所述基体(22)与所述箱体(100)之间围合形成有所述容置腔(22a),所述伸出部(221)设于基体(22)的一端,所述伸出部(221)处于所述箱体(100)外部且与所述箱体(100)的外壁抵接,所述安装部(222)设于所述基体(22)的另一端;The liquid cooling device according to claim 14, wherein the channel unit (2) comprises a protruding portion (221), a base (22) and a mounting portion (222), the base (22) and the housing (100) enclose the accommodating cavity (22a), the protruding portion (221) is arranged at one end of the base (22), the protruding portion (221) is located outside the housing (100) and abuts against an outer wall of the housing (100), and the mounting portion (222) is arranged at the other end of the base (22);
    其中,两个所述容纳空间(22b)形成于所述安装部(222)上;Wherein, the two accommodating spaces (22b) are formed on the mounting portion (222);
    两个所述总管路(21)设于所述通道单元(2),两个所述总管路(21)的一端分别对应与两个所述容纳空间(22b)连通,两个所述总管路(21)的另一端穿设于所述伸出部(221)且与两个所述接头(4)连通。The two main pipelines (21) are arranged in the channel unit (2), one end of the two main pipelines (21) is respectively connected to the two accommodating spaces (22b), and the other end of the two main pipelines (21) is passed through the extending portion (221) and is connected to the two joints (4).
  16. 根据权利要求15所述的液冷装置,其中,所述箱体(100)包括边框(103),所述容置腔(22a)设于所述边框(103)上。The liquid cooling device according to claim 15, wherein the box body (100) comprises a frame (103), and the accommodating cavity (22a) is arranged on the frame (103).
  17. 根据权利要求13-16任一项所述的液冷装置,其中,所述通道单元(2)包括安装部(222)和盖板(24),所述安装部(222)连接于所述箱体(100),所述安装部(222)上开设有相分隔的两个凹槽(23),所述盖板(24)连接于所述安装部(222)上,所述盖板(24)分别和两个所述凹槽(23)形成两个所述容纳空间(22b)。According to any one of claims 13 to 16, the channel unit (2) comprises a mounting portion (222) and a cover plate (24), the mounting portion (222) is connected to the box body (100), two separated grooves (23) are provided on the mounting portion (222), the cover plate (24) is connected to the mounting portion (222), and the cover plate (24) and the two grooves (23) respectively form two accommodating spaces (22b).
  18. 根据权利要求17所述的液冷装置,其中,所述箱体(100)包括底板(101),所述底板(101)设有开孔(1011),所述开孔(1011)与所述凹槽(23)连通,所述安装部(222)设于所述箱体(100)内部,所述盖板(24)和/或所述安装部(222)穿过所述开孔(1011)以使所述盖板(24)与所述安装部(222)连接。According to the liquid cooling device according to claim 17, the box body (100) includes a base plate (101), the base plate (101) is provided with an opening (1011), the opening (1011) is connected to the groove (23), the mounting portion (222) is provided inside the box body (100), and the cover plate (24) and/or the mounting portion (222) pass through the opening (1011) to connect the cover plate (24) with the mounting portion (222).
  19. 根据权利要求18所述的液冷装置,其中,所述底板(101)设有凹陷槽(1012),所述开孔(1011)开设于所述凹陷槽(1012)的槽底。The liquid cooling device according to claim 18, wherein the base plate (101) is provided with a recessed groove (1012), and the opening (1011) is provided at the bottom of the recessed groove (1012).
  20. 根据权利要求18所述的液冷装置,其中,所述箱体(100)还包括防护板(102),所述防护板(102)连接于所述底板(101),所述盖板(24)设于所述防护板(102)朝向所述底板(101)的一侧。The liquid cooling device according to claim 18, wherein the box body (100) further includes a protective plate (102), the protective plate (102) is connected to the base plate (101), and the cover plate (24) is arranged on a side of the protective plate (102) facing the base plate (101).
  21. 根据权利要求17所述的液冷装置,其中,所述通道单元(2)还包括密封垫(25),所述盖板(24)通过所述密封垫(25)与所述安装部(222)密封连接。The liquid cooling device according to claim 17, wherein the channel unit (2) further comprises a sealing gasket (25), and the cover plate (24) is sealedly connected to the mounting portion (222) via the sealing gasket (25).
  22. 根据权利要求18所述的液冷装置,其中,所述通道单元(2)通过密封胶密封。The liquid cooling device according to claim 18, wherein the channel unit (2) is sealed by a sealant.
  23. 一种电池包,其中,包括箱体(100)、电芯(200)和权利要求1-22任一项所述的液冷装置。A battery pack, comprising a box (100), a battery cell (200), and the liquid cooling device according to any one of claims 1 to 22.
PCT/CN2023/125188 2022-10-21 2023-10-18 Liquid cooling device and battery pack WO2024083144A1 (en)

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
CN202222783781.9 2022-10-21
CN202222781665.3 2022-10-21
CN202222783781.9U CN218568984U (en) 2022-10-21 2022-10-21 Liquid cooling device and battery pack
CN202222781665.3U CN218568983U (en) 2022-10-21 2022-10-21 Cooling device and battery pack

Publications (1)

Publication Number Publication Date
WO2024083144A1 true WO2024083144A1 (en) 2024-04-25

Family

ID=90736983

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2023/125188 WO2024083144A1 (en) 2022-10-21 2023-10-18 Liquid cooling device and battery pack

Country Status (1)

Country Link
WO (1) WO2024083144A1 (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207250677U (en) * 2017-04-26 2018-04-17 天津市捷威动力工业有限公司 A kind of liquid cooling plate structure of punching press cold plate form
CN208111625U (en) * 2018-02-28 2018-11-16 合肥国轩高科动力能源有限公司 Integrated inlet-outlet connector
WO2020098762A1 (en) * 2018-11-15 2020-05-22 宁德时代新能源科技股份有限公司 Box for battery pack, battery pack, and automobile
CN112151912A (en) * 2020-09-29 2020-12-29 东风汽车集团有限公司 Cooling liquid flow direction controllable battery pack, battery pack thermal management system and control method
CN215644642U (en) * 2021-04-14 2022-01-25 威马智慧出行科技(上海)股份有限公司 Liquid cooling plate and battery box
CN217009315U (en) * 2021-10-26 2022-07-19 长城汽车股份有限公司 Battery package and vehicle
CN218568984U (en) * 2022-10-21 2023-03-03 湖北亿纬动力有限公司 Liquid cooling device and battery pack
CN218568983U (en) * 2022-10-21 2023-03-03 湖北亿纬动力有限公司 Cooling device and battery pack

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207250677U (en) * 2017-04-26 2018-04-17 天津市捷威动力工业有限公司 A kind of liquid cooling plate structure of punching press cold plate form
CN208111625U (en) * 2018-02-28 2018-11-16 合肥国轩高科动力能源有限公司 Integrated inlet-outlet connector
WO2020098762A1 (en) * 2018-11-15 2020-05-22 宁德时代新能源科技股份有限公司 Box for battery pack, battery pack, and automobile
CN112151912A (en) * 2020-09-29 2020-12-29 东风汽车集团有限公司 Cooling liquid flow direction controllable battery pack, battery pack thermal management system and control method
CN215644642U (en) * 2021-04-14 2022-01-25 威马智慧出行科技(上海)股份有限公司 Liquid cooling plate and battery box
CN217009315U (en) * 2021-10-26 2022-07-19 长城汽车股份有限公司 Battery package and vehicle
CN218568984U (en) * 2022-10-21 2023-03-03 湖北亿纬动力有限公司 Liquid cooling device and battery pack
CN218568983U (en) * 2022-10-21 2023-03-03 湖北亿纬动力有限公司 Cooling device and battery pack

Similar Documents

Publication Publication Date Title
US20070134524A1 (en) Fuel cell stack structure
JP5971935B2 (en) Manifold block for fuel cell stack
WO2021136017A1 (en) Main board of intercooler, and intercooler and manufacturing method therefor
WO2021253753A1 (en) Housing of electronic device, electronic device, and movable platform
CN217934021U (en) Supporting structure and electric equipment
US20140196945A1 (en) Terminal box, solar cell module with terminal box, and method for manufacturing solar cell module with terminal box
WO2024083144A1 (en) Liquid cooling device and battery pack
CN113815451B (en) Charging gun liquid cooling system and charging gun
CN218568984U (en) Liquid cooling device and battery pack
CN212571121U (en) Battery box and power battery
CN217934077U (en) Supporting component and electric equipment
CN218568983U (en) Cooling device and battery pack
CN218783109U (en) Liquid cooling subassembly and electricity core module
US20230166611A1 (en) Charging gun cooling system and charging gun
WO2021065529A1 (en) Airtight connection unit, airtight connection assembly, airtight container and vaporizer, as well as method for manufacturing airtight connection assembly
CN219317917U (en) Metal quick connector, direct cooling system and battery pack
CN217877274U (en) Combined water cooling device
CN220870333U (en) Battery pack and vehicle
WO2024045754A1 (en) Battery module and battery case
KR101444983B1 (en) Gas distribution unit and method of assembling it
CN213340985U (en) Self-short-circuit aerial plug sealing structure
CN219658796U (en) Integrated liquid-cooled battery pack assembly
CN213818444U (en) Controller
CN105164873A (en) Cooling device for cooling laser arrangement and laser system comprising cooling devices
CN218887321U (en) Battery box body assembly and battery pack

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 23879132

Country of ref document: EP

Kind code of ref document: A1