WO2019085052A1 - 一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法 - Google Patents

一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法 Download PDF

Info

Publication number
WO2019085052A1
WO2019085052A1 PCT/CN2017/112100 CN2017112100W WO2019085052A1 WO 2019085052 A1 WO2019085052 A1 WO 2019085052A1 CN 2017112100 W CN2017112100 W CN 2017112100W WO 2019085052 A1 WO2019085052 A1 WO 2019085052A1
Authority
WO
WIPO (PCT)
Prior art keywords
coal
filling
mining
key layer
stability
Prior art date
Application number
PCT/CN2017/112100
Other languages
English (en)
French (fr)
Inventor
张吉雄
孙强
周楠
张强
姜淑印
Original Assignee
中国矿业大学
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中国矿业大学 filed Critical 中国矿业大学
Publication of WO2019085052A1 publication Critical patent/WO2019085052A1/zh

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • E21C41/18Methods of underground mining; Layouts therefor for brown or hard coal

Definitions

  • the invention relates to the field of filling coal mining and recovering left coal pillars, and particularly relates to a method for filling coal mining and recovering residual coal pillars and controlling the stability of the water-storing key layer.
  • Filling coal mining is a green mining technology that has been developed and widely used in recent years. This technology is a green mining and mining method with high recovery rate, which can make coal mine operations better adapt to local mining conditions, especially effective. Avoid mining damage to the ecological environment.
  • This technology is a green mining and mining method with high recovery rate, which can make coal mine operations better adapt to local mining conditions, especially effective. Avoid mining damage to the ecological environment.
  • filling materials such as meteorites and fly ash in the western mining area, and the abundant conditions of aeolian sand on the surface, how to maximize the use of surface aeolian sand materials for safety and environmental protection to improve the recovery rate of coal resources for local economic and social development Significance.
  • the object of the present invention is to provide a safe, efficient, high resource recovery rate of residual coal pillar recovery, while controlling the stability of the water-critical key layer.
  • the method for filling the recovered coal pillars of the present invention and recovering the stability of the water-storing key layer comprises the following steps:
  • the cementation filling material mainly composed of aeolian sand is used for cementing filling of the goaf in the first mining face;
  • the cemented filling material in the step a is filled with a certain bearing capacity and deformation resistance, the remaining coal pillars in the mining working face are recovered; the cementing filling material reaches a certain bearing capacity and the deformation resistance capability refers to cementation filling.
  • the material plays an effective supporting role on the top plate, and the cemented filling material is not easily deformed under the action of the upper load;
  • step b transporting the raw coal recovered in step b to the ground using transportation equipment
  • the mining is stopped, and the isolation protection coal pillar is set.
  • the certain distance L refers to the initial pressure and the falling step of the basic top.
  • the side roadway formed by the coal mining room in the first mining working face is used as the material conveying lane
  • the cementing filling pumping device is arranged in the conveying lane
  • the material is cemented and filled on both sides of the conveyance lane by a cement filling pumping device.
  • the cementing filling material achieves certain bearing capacity and anti-deformation ability, which means that the cementing filling material plays an effective supporting role on the top plate, and the cementing filling material is not easily deformed under the upper load.
  • the other side roadway formed by the coal mining room in the first mining working face is used as the coal transportation lane, and the recovered raw coal is transported to the ground through the coal transportation lane.
  • the aerated sand-based cementing filling material is selected by mixing natural aeolian sand in the western region with cement, fly ash and additives.
  • the filling rate ⁇ of the aeolian sand throwing filling in the step d is determined according to the position of the water-retaining key layer and the strength stability breaking condition.
  • the method of the invention firstly fills the cemented filling material mainly composed of aeolian sand according to the geological conditions of the mine, the ratio of the cementing material and the surrounding rock control of the working face, and the residual coal pillar is subjected to a certain bearing capacity and deformation resistance capability after the filling body reaches a certain bearing capacity and deformation resistance capacity.
  • Safety recovery then, a high-speed throwing machine and a bulldozer are used to fill a single aeolian sand in the goaf, and the filling rate of the secondary aeolian sand is determined according to the position of the aquifer and the breaking stability of the strength.
  • the method of the invention is mainly directed to the two aspects of the stability of the surrounding coal pillars and the stability control of the key layer of the water-retaining coal pillars in the western mining area, and the object is strong.
  • the stability control of the remaining coal pillars and the key layer of the water separation is carried out by cement filling and aeolian sand high-speed casting combined filling method.
  • the secondary filling is aimed at long-term stability of the key layer of water separation, and is filled with a high-speed throwing machine and a bulldozer;
  • the layer position and strength stability breaking conditions determine the filling rate of the secondary aeolian sand and control the sinking deformation of the key layer of the water barrier.
  • the technical method of the invention can utilize the surface abandonment of aeolian sand material to the maximum extent, has low cost, improves the recovery rate of coal resources, and effectively controls the long-term stability of the key layer of the quaternary clay water-separating layer and maintains the ecological environment of the local surface vegetation. It provides a new technical model for the control of high-strength mining and recovery of residual coal pillars and water-removing key layers in western mining areas of China. It is a green and efficient way to acquire resources. It has great significance in science and engineering and has broad application prospects.
  • the remaining coal pillars of the first mining working face can be recovered, and the coal resource recovery rate reaches over 90%.
  • the measured results show that the cemented filling material with a uniaxial compressive strength of 2.83 MPa or more and a filling rate of 85 %
  • the above aeolian sand throwing joint filling is combined, and the development height of the water guiding fracture zone is less than 40m, which can ensure the long-term stability of the quaternary clay aquifer at 70m position on the working surface.
  • Figure 1-1 is a plan view showing the arrangement of the working surface of the present invention.
  • Figure 1-2 is a cross-sectional view taken along line A-A of Figure 1-1;
  • Figure 2-1 is a plan view showing the filling process of the goaf of the coal house of the present invention
  • Figure 2-2 is a cross-sectional view taken along line B-B of Figure 2-1;
  • Figure 3-1 is a plan view showing the process of recycling the remaining coal pillars of the working face of the present invention
  • Figure 3-2 is a cross-sectional view taken along line C-C of Figure 3-1;
  • Figure 4-1 is a plan view showing the secondary filling process of the aeolian sand of the working face of the present invention
  • Figure 4-2 is a cross-sectional view taken along line D-D of Figure 4-1;
  • Figure 5-1 is a plan view showing the recovery of a single-cycle remaining coal pillar in the working face of the present invention
  • Figure 5-2 is a cross-sectional view taken along line E-E of Figure 5-1;
  • Figure 6-1 is a plan view of the first working face of the present invention after all the remaining coal pillars are recovered and filled;
  • Figure 6-2 is a cross-sectional view taken along line F-F of Figure 6-1.
  • a method for filling coal mining to recover residual coal pillars and controlling stability of water-storing key layers comprising the following steps:
  • the cementation filling material mainly composed of aeolian sand is used for cementing filling of the goaf in the first mining face;
  • the cemented filling material in the step a is filled with a certain bearing capacity and deformation resistance, the remaining coal pillars in the mining working face are recovered; the cementing filling material reaches a certain bearing capacity and the deformation resistance capability refers to cementation filling.
  • the material plays an effective supporting role on the top plate, and the cemented filling material is not easily deformed under the action of the upper load;
  • step b transporting the raw coal recovered in step b to the ground using transportation equipment
  • the side roadway formed by the coal mining room in the first mining face is used as the material conveying lane, and the cementing filling pumping device is arranged in the conveying lane, and the cementing filling material mainly composed of aeolian sand is cemented.
  • Filling pumping device transports coal pillars along The gob area on both sides of the roadway is cemented and filled. This filling method is more efficient and simpler.
  • the mining is stopped, and the isolation protection coal pillar is set; and the other side roadway formed by the coal mining room in the first mining working face is used as the coal transportation lane.
  • the certain distance L refers to the initial pressure and the stepping distance of the basic top.
  • a high-speed power-spraying machine can be used for the throwing machine.
  • the aerated sand-based cementing filling material is selected from natural aeolian sand in western China with cement, fly ash and a small amount of additives, and has high strength and good durability.
  • the bearing capacity and deformation resistance requirement of the aeolian sand-based cementing filling material are determined according to the geological conditions of the mine, the ratio of cementing materials and the surrounding rock control of the working face.
  • the mechanical calculation method of the elastic foundation of the rock beam is used to determine the filling rate ⁇ of the aeolian sand throwing filling in the step d, which can reduce soil erosion and water inrush disaster.
  • each adjacent two columns of coal pillars shall be arranged with a working face with a working height of 4.5 m and a working face length of 800 m.
  • the inclined length is 70m, and a partition wall 2 is left between adjacent working faces, as shown in Figure 1-1 and Figure 1-2;
  • the ground natural aeolian sand is transported to the underground and transported by the belt conveyor 5 to the secondary filling work.
  • the high-speed power-spraying machine 4 throws the aeolian sand 11 into the goaf, and when the aeolian sand 11 is piled up to a certain height, the high-speed power-spraying machine 4 is rotated, and the material is thrown to the other side of the gob;
  • the bulldozer 6 is started, and the natural aeolian sand 11 after the throwing is pushed and filled to make it topped; under the cooperation of the high-speed power-spraying machine 4 and the bulldozer 6, the sand casting and the tamping are repeated.
  • the top process is shown in Figure 4-1, Figure 4-2, Figure 5-1, Figure 5-2;
  • the remaining coal pillars of the first mining face can be recovered, and the recovery rate of coal resources reaches over 90%.
  • the measured results show that the cemented filling materials with a uniaxial compressive strength of 2.83 MPa or more and the enrichment rate are 85%.
  • the above aeolian sand throwing joint filling is combined, and the development height of the water guiding fracture zone is less than 40m, which can ensure the long-term stability of the quaternary clay aquifer at 70m position on the working surface.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Remote Sensing (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

本发明公开一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法,在已采煤房形成的巷道中布置胶结充填泵送装置;利用风积沙为主的胶结充填材料充填两侧采空区,待充填体达到一定承载能力后对遗留煤柱进行回采;煤柱回采后,采用高速动力抛投机与推土机进行采空区风积沙二次充填。本方法可最大限度利用地表天然风积沙材料,并有效控制上覆隔水关键层,为我国西部生态脆弱矿区遗留煤柱的回采与生态环境保护提供新的技术方法。

Description

一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法 技术领域
本发明涉及充填采煤回收遗留煤柱领域,并具体涉及一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法。
背景技术
随着我国煤炭资源的高强度开采,东部矿区煤炭资源的逐渐枯竭,我国西部矿区已成为煤炭资源开采的主体。“十三五”期间,国家重点建设的大型煤炭基地主要集中在生态环境十分脆弱、水土流失严重的晋、陕、蒙、宁、甘地区。该区域矿区长期以来一直采用房式采煤法,该方法造成大量煤炭资源浪费,煤炭资源开采率不足40%。另一方面,煤层开采后,由于覆岩的长期作用,易引发煤柱失稳破坏,顶板大面积垮落,造成上部第四系中更新统离石黄土和第三系上新统三趾马红土组成的粘土隔水层破坏,水土流失,加重当地生态脆弱环境的破坏。
充填采煤是近年来发展、应用较为广泛的绿色采煤技术,该技术是一种绿色环保、回收率较高的矿井开采方式,能够使煤矿作业更好地适应当地开采条件,特别是能够有效地避免开采对生态环境的破坏。针对西部矿区矸石、粉煤灰等充填材料短缺,而地表赋存风积沙丰富的条件,如何最大限度的利用地表风积沙材料安全、环保的提高煤炭资源回收率对于当地的经济社会发展具有重要的意义。
因此,针对当地的采矿地质条件,研究一种既能保证安全开采,又能解决房式开采遗留煤柱的回收问题的开采技术已成为当地煤矿开采的重大技术难题。
发明内容
本发明的目的是提供一种安全、高效、资源回收率高的遗留煤柱回收,同时控制隔水关键层稳定的方法。
为实现上述目的,本发明的充填采煤回收遗留煤柱并控制隔水关键层稳定的方法,包括以下步骤:
a.利用风积沙为主的胶结充填材料将首个回采工作面中的采空区进行胶结充填;
b.待步骤a中胶结填充后的胶结充填材料达到一定承载能力与抗变形能力后对上述回采工作面内的遗留煤柱进行回采;胶结充填材料达到一定承载能力与抗变形能力是指胶结充填材料对顶板起到有效支撑作用,在上部载荷作用下胶结充填材料不易产生变形;
c.利用运输设备将步骤b中回采的原煤运送到地面;
d.采用高速动力抛投机对上述遗留煤柱回采后形成的采空区进行风积沙抛投充填,采用推 土机将抛投后的风积沙推实,高速动力抛投机与推土机相互配合完成遗留煤柱回采后形成的采空区的充填;
e、重复上述步骤a~d,完成其余回采工作面内遗留煤柱的回采。
进一步地,所述步骤c中,当工作面回采至一定距离L时停止回采,设置隔离保护煤柱,所述的一定距离L是指基本顶的初次来压、垮落步距。
进一步地,所述步骤a中,将首个回采工作面中已采煤房形成的一侧巷道作为运料巷,在运料巷内布置胶结充填泵送装置,风积沙为主的胶结充填材料通过胶结充填泵送装置将运料巷的两侧采空区进行胶结充填。胶结充填材料达到一定承载能力与抗变形能力是指胶结充填材料对顶板起到有效支撑作用,在上部载荷作用下胶结充填材料不易产生变形。
进一步地,所述步骤c中,将首个回采工作面中已采煤房形成的另一侧巷道作为运煤巷,将回采的原煤经过运煤巷运送至地面。
进一步地,所述的风积沙为主的胶结充填材料选用西部地区天然的风积沙配以水泥、粉煤灰及添加剂混合而成。
进一步地,相邻回采工作面之间留设隔离墙。
进一步地,根据隔水关键层的位置及强度稳定性破断条件,确定所述步骤d中的风积沙抛投充填的充实率φ。
本发明的有益效果在于:
本发明方法首先是根据矿井地质条件、胶结材料配比及工作面围岩控制确定风积沙为主的胶结充填材料一次充填,待充填体达到一定承载能力与抗变形能力后对遗留煤柱进行安全回采;然后,采用高速抛投机与推土机对采空区进行单一风积沙充填,根据隔水层位置及强度稳定性破断条件,确定二次风积沙充填充实率。本发明的方法主要针对于西部矿区遗留煤柱回采围岩稳定性及隔水关键层稳定性控制两个方面,目的性强。遗留煤柱回采与隔水关键层稳定性控制采用胶结充填与风积沙高速抛投联合充填方式,二次充填以隔水关键层长期稳定为目的,采用高速抛投机与推土机充填;根据隔水层位置及强度稳定性破断条件,确定二次风积沙充填充实率,控制隔水关键层下沉变形。本发明的技术方法可最大限度利用地表废弃风积沙材料,成本低,提高煤炭资源采出率,同时有效控制第四系黏土类隔水关键层的长期稳定,维护当地地表植被的生态环境。为我国西部矿区高强度开采回收遗留煤柱及隔水关键层控制提供了一种全新的技术模式,是一种绿色、高效的资源获取方式,科学与工程意义重大,应用前景广阔。
采用本发明的方法后,可实现首采工作面剩余遗留煤柱的回采,煤炭资源回采率达到90%以上,实测结果表明,单轴抗压强度达到2.83MPa以上的胶结充填材料与充实率85% 以上的风积沙抛投联合充填,导水裂隙带发育高度小于40m,可以保证工作面上部70m位置第四系黏土类隔水层长期稳定性。
附图说明
图1-1是本发明工作面布置平面图;
图1-2是图1-1中A-A方向的剖面图;
图2-1是本发明煤房采空区充填过程的平面图;
图2-2是图2-1中B-B方向的剖面图;
图3-1是本发明工作面遗留煤柱回收过程的平面图;
图3-2是图3-1中C-C方向的剖面图;
图4-1是本发明工作面风积沙二次充填过程的平面图;
图4-2是图4-1中D-D方向的剖面图;
图5-1是本发明工作面完成单次循环遗留煤柱回收的平面图;
图5-2是图5-1中E-E方向的剖面图;
图6-1是本发明首个工作面完成所有遗留煤柱回采及充填后的平面图;
图6-2是图6-1中F-F方向的剖面图。
图中:1-停采线,2-隔离墙,3-胶结充填泵送装置,4-高速动力抛投机,5-带式输送机,6-推土机,7-无轨胶轮车,8-装载机,9-隔离保护煤柱,10-胶结充填材料,11-天然风积沙,12-运煤巷,13-运料巷,14-隔水关键层。
具体实施方式
下面结合具体的实施方式进一步说明。
一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法,包括以下步骤:
a.利用风积沙为主的胶结充填材料将首个回采工作面中的采空区进行胶结充填;
b.待步骤a中胶结填充后的胶结充填材料达到一定承载能力与抗变形能力后对上述回采工作面内的遗留煤柱进行回采;胶结充填材料达到一定承载能力与抗变形能力是指胶结充填材料对顶板起到有效支撑作用,在上部载荷作用下胶结充填材料不易产生变形;
c.利用运输设备将步骤b中回采的原煤运送到地面;
d.采用抛投机对上述遗留煤柱回采后形成的采空区进行风积沙抛投充填,采用推土机将抛投后的风积沙推实,抛投机与推土机相互配合完成遗留煤柱回采后形成的采空区的充填;
e、重复上述步骤a~d,完成其余回采工作面内遗留煤柱的回采。
所述步骤a中,将首个回采工作面中已采煤房形成的一侧巷道作为运料巷,在运料巷内布置胶结充填泵送装置,风积沙为主的胶结充填材料通过胶结充填泵送装置将煤柱沿运料 巷两侧采空区进行胶结充填,这种充填方式效率更高,更加简便。
所述步骤c中,当工作面回采至一定距离L时停止回采,设置隔离保护煤柱;并且,将首个回采工作面中已采煤房形成的另一侧巷道作为运煤巷。所述的一定距离L是指基本顶的初次来压、垮落步距。
抛投机可以选用高速动力抛投机。
所述的风积沙为主的胶结充填材料选用中国西部地区天然的风积沙配以水泥、粉煤灰及少部分添加剂混合而成,强度大,耐久性好。所述的风积沙为主的胶结充填材料的承载能力与抗变形能力要求,根据矿井地质条件、胶结材料配比及工作面围岩控制确定。
此外,相邻回采工作面之间留设隔离墙。
根据隔水关键层的位置及强度稳定性破断条件,利用岩梁弹性地基力学计算方法,确定所述步骤d中的风积沙抛投充填的充实率φ,能够减轻水土流失,突水溃沙灾害。
实施例1
某西部矿井原采用短壁条带房式开采,导致大量煤柱遗留井下,造成大量煤炭资源浪费,且近年来发现部分煤柱失稳与自燃发火严重,进而引发地表大面积塌陷,严重影响了当地的生态环境。为解决上述难题,结合本专利发明内容,针对首采工作面遗留煤柱的回采叙述具体实施方式如下:
(1)针对一盘区首采工作面已开采区域,沿垂直于大巷的方向,将每相邻的两列煤柱布置一个回采工作面,工作面采高4.5m,工作面走向长度800m,倾斜长度为70m,相邻回采工作面之间留设隔离墙2,如图1-1和图1-2所示;
(2)沿垂直于大巷的方向,将隔离墙左侧的第一列已采煤房作为运料巷13,第二列已采煤房作为运煤巷12;
(3)在运料巷13内布置胶结充填泵送装置3的输送管路,将地面配制好的以风积沙为主的胶结充填材料10输送至工作面煤房采空区进行充填,通过控制胶结充填泵送装置3的管口位置、高度以及物料流速使胶结充填材料逐步密实接顶,旋转胶结充填泵送装置3的输送管路进入另一侧采空区进行同样工艺胶结充填工作,如此反复地向前推进至停采线(1)位置结束充填作业,如图2-1和图2-2所示;
(4)待胶结充填材料达到一定强度及抗变形能力后,采用打眼放炮的方式对运煤巷12、运料巷13之间工作面的遗留煤柱进行***,利用矿用防爆装载机8将***落下的煤装载到无轨胶轮车7上,然后由无轨胶轮车7经运煤巷12将煤运送到地面,当工作面回采至距离L为120m左右距离时,设置隔离保护煤柱9,如图3-1和图3-2所示;
(5)遗留煤柱回采后,将地面天然风积沙运输至井下,由带式输送机5运至二次充填工作 面,利用高速动力抛投机4向采空区抛投风积沙11,当风积沙11堆积至一定的高度后,旋转高速动力抛投机4,向采空区的另一侧抛投物料;同时启动推土机6,对抛投后的天然风积沙11进行推压充填,使其接顶;在高速动力抛投机4与推土机6的配合下,如此反复的进行抛投风积沙以及夯实接顶工艺,如图4-1、图4-2以及图5-1、图5-2所示;
(6)当采空区两侧均被密实风积沙充填体11充满后,停止带式输送机5以及高速动力抛投机,至此,首个工作面的遗留煤柱回收以及采空区充填作业完成,如图6-1和图6-2所示;(7)重复上述步骤(2)、(3)、(4)、(5)、(6)进行下一回采工作面内的一次胶结充填、遗留煤柱回收、二次抛投充填的循环作业。
采用该技术方法后,可实现首采工作面剩余遗留煤柱的回采,煤炭资源回采率达到90%以上,实测结果表明,单轴抗压强度达到2.83MPa以上的胶结充填材料与充实率85%以上的风积沙抛投联合充填,导水裂隙带发育高度小于40m,可以保证工作面上部70m位置第四系黏土类隔水层长期稳定性。

Claims (7)

  1. 一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法,其特征在于,包括以下步骤:
    a.利用风积沙为主的胶结充填材料将一个回采工作面内的采空区进行胶结充填;
    b.待步骤a中胶结充填后的胶结充填材料达到一定承载能力与抗变形能力后对上述回采工作面内的遗留煤柱进行回采;
    c.利用运输设备将步骤b中回采的原煤运送到地面;
    d.采用抛投机对上述遗留煤柱回采后形成的采空区进行风积沙抛投充填,采用推土机将抛投后的风积沙推实,抛投机与推土机相互配合完成遗留煤柱回采后形成的采空区的充填;
    e、重复上述步骤a~d,完成其余回采工作面内遗留煤柱的回采。
  2. 根据权利要求1所述的一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法,其特征在于,所述步骤c中,当工作面回采至一定距离L时停止回采,设置隔离保护煤柱,所述一定距离L指的是基本顶的初次来压垮落步距。
  3. 根据权利要求1所述的一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法,其特征在于,所述步骤a中,将首个回采工作面中已采煤房形成的一侧巷道作为运料巷,在运料巷内布置胶结充填泵送装置,风积沙为主的胶结充填材料通过胶结充填泵送装置将运料巷的两侧采空区进行胶结充填。
  4. 根据权利要求3所述的一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法,其特征在于,所述步骤c中,将首个回采工作面中已采煤房形成的另一侧巷道作为运煤巷,将回采的原煤经过运煤巷运送至地面。
  5. 根据权利要求1所述的一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法,其特征在于:所述的风积沙为主的胶结充填材料选用天然的风积沙配以水泥、粉煤灰及添加剂混合而成。
  6. 根据权利要求1所述的一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法,其特征在于:相邻回采工作面之间留设隔离墙。
  7. 根据权利要求1所述的一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法,其特征在于:根据隔水关键层的位置及强度稳定性破断条件,确定所述步骤d中的风积沙抛投充填的充实率φ。
PCT/CN2017/112100 2017-11-01 2017-11-21 一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法 WO2019085052A1 (zh)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201711055756.6 2017-11-01
CN201711055756.6A CN108087021A (zh) 2017-11-01 2017-11-01 一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法

Publications (1)

Publication Number Publication Date
WO2019085052A1 true WO2019085052A1 (zh) 2019-05-09

Family

ID=62171893

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2017/112100 WO2019085052A1 (zh) 2017-11-01 2017-11-21 一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法

Country Status (2)

Country Link
CN (1) CN108087021A (zh)
WO (1) WO2019085052A1 (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2018431390B2 (en) * 2018-07-09 2021-05-06 China University Of Mining And Technology Method for recovering room-type coal pillars by cemented filling of reserved roadways
CN114370251A (zh) * 2022-01-14 2022-04-19 安徽理工大学 一种煤层群下行开采覆岩离层定向分级分区注浆方法
CN114961731A (zh) * 2022-07-28 2022-08-30 北京科技大学 一种倾斜薄矿体空场嗣后机制砂充填回收矿柱的方法

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109236296B (zh) * 2018-08-02 2019-09-13 缪协兴 一种安全开采保水煤柱的设计方法
CN109577982B (zh) * 2018-12-12 2020-09-04 中国矿业大学 壁式连采连充保水采煤及水资源运移监测、水害预警方法
CN110306983A (zh) * 2019-06-15 2019-10-08 龙口矿业集团有限公司 一种采区的边角煤柱工作面开采方法
CN110359910B (zh) * 2019-07-11 2020-12-04 新汶矿业集团有限责任公司 煤矿铁路下厚煤层条带综放高位充填开采方法
CN110410076B (zh) * 2019-08-16 2021-06-08 山东科技大学 一种用于老房柱采空区遗留煤柱回收的充填开采方法
CN111206956B (zh) * 2020-01-10 2021-03-02 中国矿业大学 一种房式采煤法采空区遗留煤柱充填加固方法
CN113704863B (zh) * 2021-10-28 2022-02-18 中煤科工集团西安研究院有限公司 一种房柱式采空区控制充填关键参数设计方法
CN114687794B (zh) * 2022-03-31 2023-11-17 中国矿业大学(北京) 一种煤矿充填复采方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101126316A (zh) * 2007-09-19 2008-02-20 中国矿业大学 一种长壁综采回收房式开采煤柱的方法
CN102155226A (zh) * 2010-11-30 2011-08-17 淄博市王庄煤矿 中厚及以上煤层的巷道式充填开采方法

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102011611A (zh) * 2010-11-30 2011-04-13 淄博市王庄煤矿 控制上覆岩层移动变形的高水膨胀材料条带式充填方法
CN102926770B (zh) * 2012-11-08 2015-01-07 中国神华能源股份有限公司 薄基岩、厚松散砂层富水区域井下疏水注浆工艺
CN103104287A (zh) * 2013-01-28 2013-05-15 山东科技大学 一种条带采空区充填复采方法
CN103527196B (zh) * 2013-10-28 2015-07-01 中国矿业大学 一种黄土充填回收房式煤柱的方法

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101126316A (zh) * 2007-09-19 2008-02-20 中国矿业大学 一种长壁综采回收房式开采煤柱的方法
CN102155226A (zh) * 2010-11-30 2011-08-17 淄博市王庄煤矿 中厚及以上煤层的巷道式充填开采方法

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
AN, BAIFU: "Controlling Mechanism of Surround Rock Stability in Recovering Room Mining Standing Pillars by Consolidated Solid Backfilling Mining", CHINA DOCTORAL DISSERTATIONS FULL-TEXT DATABASE (ENGINEERING SCIENCE AND TECHNOLOGY I), 15 February 2017 (2017-02-15), pages 68 - 92; 114-117 *
FANG, KUN: "Research on Principal Technology of Recovering Room Coal Pillar with Combined Artificial Pillar and Solid Backfill Mining", CHINESE MASTER'S THESES FULL-TEXT DATABASE (ENGINEERING SCIENCE AND TECHNOLOGY I, 15 February 2017 (2017-02-15), pages 15 - 17 *
LI, LIANG: "Basic Study on Flexible Strip Filling in Water Preserving Mining of Shallow Seam", CHINESE MASTER'S THESES FULL-TEXT DATABASE (ENGINEERING SCIENCE AND TECHNOLOGY I, 15 February 2013 (2013-02-15), pages 50 - 66 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2018431390B2 (en) * 2018-07-09 2021-05-06 China University Of Mining And Technology Method for recovering room-type coal pillars by cemented filling of reserved roadways
CN114370251A (zh) * 2022-01-14 2022-04-19 安徽理工大学 一种煤层群下行开采覆岩离层定向分级分区注浆方法
CN114370251B (zh) * 2022-01-14 2023-08-18 安徽理工大学 一种煤层群下行开采覆岩离层定向分级分区注浆方法
CN114961731A (zh) * 2022-07-28 2022-08-30 北京科技大学 一种倾斜薄矿体空场嗣后机制砂充填回收矿柱的方法

Also Published As

Publication number Publication date
CN108087021A (zh) 2018-05-29

Similar Documents

Publication Publication Date Title
WO2019085052A1 (zh) 一种充填采煤回收遗留煤柱并控制隔水关键层稳定的方法
CN112360462B (zh) 短壁综采矸石充填注浆的开采工艺
CN108661705B (zh) 条采采空区四位一体综合治理施工方法
WO2021068691A1 (zh) 一种煤矿强弱强全采全充方法
CN105317459B (zh) 一种用于控制坚硬顶板大面积垮落灾害的分区充填方法
CN102996131B (zh) 一种预掘两巷前进式固体充填采煤方法
US10612378B2 (en) Method for recovering room-mining coal pillars by solid filling in synergy with artificial pillars
WO2020062432A1 (zh) 近距离煤层群井下采选充协同开采方法
WO2016045440A1 (zh) 一种采矿方法
CN103821558B (zh) 煤矿采空区充填采矿及沿空留巷充填工艺
WO2014187163A1 (zh) 一种特厚煤层倾斜分层固体充填采煤方法
AU2018431390B2 (en) Method for recovering room-type coal pillars by cemented filling of reserved roadways
WO2018176892A1 (zh) 一种薄煤层综合开采与瓦斯治理网络一体协同控制***及方法
WO2015062195A1 (zh) 一种特厚煤层固体胶结充填巷式开采方法
WO2016074456A1 (zh) 控制覆岩裂隙与地表沉陷的掘采充平行作业的采煤方法
CN104481540A (zh) 一种利用高位钻孔注浆控制多种煤矿开采灾害的方法
CN104213919A (zh) 一种浅埋急倾斜煤层冲击地压的防治方法
WO2023029618A1 (zh) 高强度开采工作面煤矸石覆岩隔离注浆充填绿色开采方法
CN109869152B (zh) 煤与瓦斯突出煤层预留巷道开采方法
US20210180455A1 (en) Method for treating a high and steep landslide in a mine with a gently-inclined and weak interlayer
CN104564137A (zh) 双介质垛式支撑坚硬顶板的煤矿采空区处理方法及装置
CN106150545A (zh) 一种根据顶板垮落特征进行采空区部分充填的方法
CN104989408A (zh) 一种用于山区金属矿山安全高效的采矿方法
CN111577378A (zh) 一种煤与瓦斯突出煤层瓦斯抽采与充填协同开采方法
CN215520873U (zh) 一种煤矸石粉覆岩压实注浆充填开采***

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 17930578

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 17930578

Country of ref document: EP

Kind code of ref document: A1