WO1984001599A1 - Assembly for handling and racking drill pipe in a derrick - Google Patents

Assembly for handling and racking drill pipe in a derrick Download PDF

Info

Publication number
WO1984001599A1
WO1984001599A1 PCT/NO1983/000044 NO8300044W WO8401599A1 WO 1984001599 A1 WO1984001599 A1 WO 1984001599A1 NO 8300044 W NO8300044 W NO 8300044W WO 8401599 A1 WO8401599 A1 WO 8401599A1
Authority
WO
WIPO (PCT)
Prior art keywords
pipe
rack
derrick
racking
stands
Prior art date
Application number
PCT/NO1983/000044
Other languages
French (fr)
Inventor
Oeivind Tore Iversen
Original Assignee
Moss Rosenberg Verft As
Total Transportation
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Moss Rosenberg Verft As, Total Transportation filed Critical Moss Rosenberg Verft As
Publication of WO1984001599A1 publication Critical patent/WO1984001599A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B19/00Handling rods, casings, tubes or the like outside the borehole, e.g. in the derrick; Apparatus for feeding the rods or cables
    • E21B19/14Racks, ramps, troughs or bins, for holding the lengths of rod singly or connected; Handling between storage place and borehole
    • E21B19/146Carousel systems, i.e. rotating rack systems

Definitions

  • the drill string When drilling for oil, it is not uncommon that the length of the drill string exceeds 6000 meters.
  • the drill string is usually composed of lengths of pipe about 10 meters long. In the course of a drilling operation, the entire drill string has to be drawn up and disassembled several times for replacing the drill bit, rigging up and cementing casings, and for other reasons.
  • the drill string is normally broken down in lengths of three pipes, i.e., about 30 meters, and these stands or "thribbles" of pipe are temporarily stored verti ⁇ cally in the derrick.
  • the carousel comprises one or more fixed annular frames which are concentric with the axis of rotation of the carousel, each ring having a minimum aperture corresponding to the cross section of the bundle of pipe strings that the carousel can hold.
  • Each ring is discontin ⁇ uous, having a gap at the perimeter which forms the access opening to the rack.
  • Figure 1 is a schematic drawing, in cross section, of a derrick equipped with an assembly in accordance with the invention
  • Figure 2 shows the derrick of Figure 1 in plan view, with a horizontal section through the derrick along line II-II in Figure 1, drawn on a larger scale, and
  • the lower racking assembly 6 comprises essentially a racker arm 8 which in this case is movably supported by a horizontal support member 9.
  • a column 10 rotable about a vertical axis, is mounted on the racker arm 8 and carries a support arm 11 at the upper end thereof.
  • the support arm 11 is telescopic and the telescopic arm carries a grab/support head 12 formed for grasping and holding a stand of pipe 13, see Figure 3.
  • the horizontal support 9 is mounted in a guide 14 that permits upward and downward movement of the support member 9, as indicated by the twin-headed arrow at the guide 14.
  • a central column 17 is pivotally mounted on the drill floor 18 and on a bracket 19 at a higher point on the derrick 1, respectively. At its base, the central column 17 carries a circular storage platform 20, and spaced apart vertically above this platform, the central column carries
  • the stand of pipe is held by the grab head 16.
  • the stand of pipe 13 can be elevated as required ( Figure 3) .
  • the drill string remaining within the well is suspended from the rotary table by means of. slips, as known per se.
  • the racker arms 8 and 26 are driven back from the line of drilling 2, to a position corresponding to that shown in Figure 1.
  • the grab heads 12 and 16 are pivoted 90° one way or the other as indicated by the arrows in Figure 2, and the support arms 11 and 27 are extended, whereby the heads 12,16 are moved toward the selected rack 4 or 5.
  • the receiving groove in the selected rack has already been brought into position through a corres ⁇ ponding rotation of the carousel.
  • This rotary movement occurs in clearly defined stages, corresponding to the groove subdivision.
  • Two annular frames 28 and 29 are mounted on the derrick 1.
  • the apertures of the rings are adapted to the cross section of the pipe bundle 30 which can be placed in the carousel.
  • Each annular frame has a gap in the perimeter, at 31 and 32 respectively, thereby forming openings which are in alignment with the receiving groove lying internally thereof.
  • the stand of pipe 13 that is being racked is guided through the gaps 31,32 into the receiving grooves in the two finger boards 21 and 22.
  • the pipe string is moved inwardly until it meets some resistance, after which the stand of pipe is lowered down onto the storage platform 20 by moving the lower racker assembly downwardly in the guide 14.
  • the grab heads 12,16 are opened and guided back to the drill string at the line of drilling 2 with corresponding movements in reverse.
  • a retainer ring 31 is also preferably arranged around the storage platform 20.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Earth Drilling (AREA)

Abstract

For handling and racking drill pipe in a derrick (1), a storage rack (4) for vertical storage of the stands of pipe in the derrick is proposed. The rack (4) comprises a storage platform (20) and one or more finger boards (21, 22) spaced apart a distance above the storage platform (20). Racking equipment (6, 7) is also placed in the derrick for transporting the stands of pipe between the line of drilling (2) and the rack (4). The rack has a fixed access opening (31, 32) at a fixed location in the derrick, and the fingers and intermediate grooves for receiving the stands of pipe on the finger boards (21, 22) are movable to and from a position in which one groove is in alignment with the fixed access opening to the rack. The racking equipment (6, 7) can thus be given distinct and defined movements. In a preferred embodiment, the rack (4) is a carousel, with the finger boards (20, 21, 22) mounted on a rotatable, vertical, central column (17) within the derrick. Fixed annular arms (28, 29) hold around the bundle of pipe racked in the carousel and there is a gap at the perimeter (31, 32) of the respective rings that forms the access opening to the rack.

Description

ASSEMBLY FOR HANDLING AND RACKING DRILL PIPE IN A DERRICK The invention relates to an assembly for handling and racking stands of drill pipe in a derrick.
When drilling for oil, it is not uncommon that the length of the drill string exceeds 6000 meters. The drill string is usually composed of lengths of pipe about 10 meters long. In the course of a drilling operation, the entire drill string has to be drawn up and disassembled several times for replacing the drill bit, rigging up and cementing casings, and for other reasons. During a "trip", as the withdrawal of the drill string is known, the drill string is normally broken down in lengths of three pipes, i.e., about 30 meters, and these stands or "thribbles" of pipe are temporarily stored verti¬ cally in the derrick.
The normal procedure earlier was to have two derrickmen up in the derrick for guiding the screwed-apart stands of pipe to the side for racking the pipe lengths in the derrick, and this procedure is still followed to some extent today. This job, in addition to requiring the labor of two men, is both difficult and dangerous. The difficulties and risks increase in offshore drilling, especially when using drilling vessels and other floating platforms, and various solutions for semi- and fully-automatic handling and temporary storage of stands of drill pipe have been proposed and utilized in practice. The most advanced systems today comprise pipe- racking equipment which takes hold of the stand of pipe that has been pulled up by the hoisting equipment on the derrick before the length of pipe has been screwed apart from its neighbors, and after disengagement transports the pipe laterally to a storage automat in the derrick. The storage automat comprises a storage platform on the drill floor, and at least one so-called finger board, which is spaced a suitable vertical distance above the storage platform and contains grooves for receiving the respective stands of pipe. On each of the fingers of the finger board, wherein the spaces between the fingers form the grooves for receiving
-BURE U
OMPI the pipes, there are remotely controlled locking means which secure the individual lengths of pipe within the grooves. When the drill string is to be reassembled and guided down into the well once again, the lengths of pipe are retrieved one at a time from the vertical storage rack by means of the racking equipment. The pipe racking equipment consists primarily of horizontal arms with a grab/support claw an one end of the arm that is intended to engage with a length of pipe. The arms can be moved toward and away from the line of drilling (the well), and toward and away from the vertical storage rack. At least one of the arms can be moved vertically, for raising and lowering the stand of pipe.
Although the handling and racking of stands of pipe in the derrick can thus be said to be fully mechanized, there is a - need for improvements on the prior art systems. The pipe racking equipment, i.e., mainly the arms, should be able to execute more movements, and the arms should be able to be controlled accurately and stopped precisely at selected locations for depositing and retrieving the stands of pipe at the rack. The finger board has several parallel receiving grooves with associated access openings, and the respective stands of pipe must be guided into the correct groove during racking. There is therefore a need for simplifying the mechanized handling of pipe to enable the pipe racking to be accomplished with fewer, but controlled and defined, move¬ ments. This can be obtained by ensuring that the stands of pipe are deposited in and removed from the vertical storage rack at the same, fixed location, the lengths of pipe being moved in a defined manner between the line of drilling, where the drill string is located, and the fixed access opening to the rack, i.e., the place where a stand of pipe enters the groove of a finger board and is retained in that groove, the respective grooves being brought successively, as needed, into a position in which the groove opening coincides with the fixed deposit/retrieval location.
An embodiment of this type provides the advantage that racking
OMPI ~~ is performed between two fixed, defined positions, namely, the line of drilling and the rack access opening, and the racking operation therefore is accomplished with few and defined movements of the racking members. When the racking equipment comprises horizontal racker arms with a grab/ support head that is movable laterally within the derrick frame, the grab/support head is preferably mounted on a support arm that is pivotable about a vertical axis and is carried by the racker arm, said support arm also being telescopic so that the grab/support head can be moved relative to the axis of rotation of the support arm. For racking the drill string, the racker arm moves between two distinct positions, i.e., from the line of drilling to a position in which the length of pipe held by the grab, by pivoting the support arm, is moved into a position vis-a-vis the fixed entrance to the rack. Thereafter, the grab/ support head is moved in a direction toward the rack entrance and toward the groove in the finger board that has been brought into alignment with said entrance. This ove- ent will also be distinct and defined, since the movement of the pipe into the groove is translational, stopping when the the pipe abuts against a barrier in the groove or against another stand of pipe already deposited within the groove. Removal of pipe from the rack occurs in a similar manner, by reversing the above movements.
Preferably, the storage rack is formed as a carousel, wherein the finger boards are substantially circular and rotatable about a common vertical axis, with radially extending fingers and intermediate grooves therebetween. By rotating the finger boards, preferably utilizing a common, central, vertical column, the grooves can successively be brought into a predetermined orientation, with the groove opening ready to receive/release a stand of pipe, and this groove opening then represents the access opening of the rack. At this location a guide means can also be arranged, if desired, and in that case the guide means would then represent the access opening of the rack. In a preferred embodiment, the carousel comprises one or more fixed annular frames which are concentric with the axis of rotation of the carousel, each ring having a minimum aperture corresponding to the cross section of the bundle of pipe strings that the carousel can hold. Each ring is discontin¬ uous, having a gap at the perimeter which forms the access opening to the rack.
Preferably, two storage carousels are placed on each side of a joint racker- assembly, with the rack access openings facing toward each other.
Within the individual grooves of the finger board, simple snap-locks may be used for retaining the lengths of pipe in the groove. Alternately, remotely controlled latch mechanisms or the like could also be used. The annular frames form an outer safeguard for the pipe bundles, and the perimeter gaps in the rings form the fixed access openings to the racks.
The invention will be described in greater detail in the following with reference to the accompanying drawings, wherein:
Figure 1 is a schematic drawing, in cross section, of a derrick equipped with an assembly in accordance with the invention,
Figure 2 shows the derrick of Figure 1 in plan view, with a horizontal section through the derrick along line II-II in Figure 1, drawn on a larger scale, and
Figure 3 shows the derrick in cross section as in Figure 1, with a bundle of pipe strings stored vertically in the derrick.
The derrick is designated by reference numeral 1, and the line of drilling is designated by 2. The drill string is not shown, but during a drilling operation it will extend down into the well 3 along the line of drilling 2. The necessary equipment for drilling, such as hoisting equipment with elevator, kelly, rotary table, etc., is not shown, as the equipment utilized is known per se.
In the derrick 1, laterally of the line of drilling 2, two storage racks 4 and 5 are placed for temporary storage of stands of pipe during a "trip". Racking equipment is placed between the two racks 4,5, in this case comprising a lower racking assembly 6 and an upper racking assembly 7. The lower racking assembly 6 comprises essentially a racker arm 8 which in this case is movably supported by a horizontal support member 9. A column 10, rotable about a vertical axis, is mounted on the racker arm 8 and carries a support arm 11 at the upper end thereof. The support arm 11 is telescopic and the telescopic arm carries a grab/support head 12 formed for grasping and holding a stand of pipe 13, see Figure 3. The horizontal support 9 is mounted in a guide 14 that permits upward and downward movement of the support member 9, as indicated by the twin-headed arrow at the guide 14.
The upper racking assembly 7 is constructed in the same way as the lower assembly, but its horizontal support member 15 is fixedly attached to the derrick 1. The grab head 16 on the upper assembly can be formed like the grab head 12 , but it does not need to be made for supporting weight, as its function is only to hold about the pipe and guide it.
The racks 4 and 5 are identical, but mirror images of each other when in position, and only the rack 4 will be described. A central column 17 is pivotally mounted on the drill floor 18 and on a bracket 19 at a higher point on the derrick 1, respectively. At its base, the central column 17 carries a circular storage platform 20, and spaced apart vertically above this platform, the central column carries
-βURi- __OMPJ
WϊprJ- a lower and an upper finger board, 21 and 22, respectively. The two finger boards are identical, having radially extending fingers with intermediate grooves opening toward the peri¬ meter of the circular finger board. Per se, the finger boards
5 are made like prior art finger boards with parallel grooves and fingers, but in this case the grooves and fingers are oriented radially, see Figure 2, on which some of the grooves 23 and fingers 24 are shown. In the rack 4 in Figure 2, four grooves are shown as being full, and one empty. In the rack
10 5 there is one full groove, one groove containing one stand of pipe, and one empty groove. The grooves and fingers are distributed around the entire periphery, and in the exemplary embodiment each of the finger boards has a total of 24 grooves, or the capacity to hold 96 pipe strings (four stands
15 of pipe in each groove). , and the two racks together can thus contain 192 stands of pipe. Assuming that each stand of pipe is 30 meters long, this arrangement provides storage capacity for 5,760 meters of pipe. The storage capacity could be increased by increasing the dimensions of the racks.
20
The mode of operation of the assembly of the invention will be explained in further detail with reference to the draw¬ ings. Let us assume that a drill string, represented by the line of drilling 2, has to be pulled up from the well 3. By
25 means of an elevator (not shown) , the drill string is drawn up so that the uppermost stand of pipe is above the level of the drill floor 18. The racker assemblies 6 and 7 are then actuated and the respective grab heads 12 and 16 take hold around the pipe. The stand of pipe is unscrewed in a manner
30 known per se. During this operation, the lower racker assembly 6 is moved vertically into a position in which the grab head 12 grips around the stand of pipe 13 (see Figure 3) . The elevator is released and the stand of pipe is unscrewed. The stand of pipe is now supported by the grab/support head
35 12. At the top, the stand of pipe is held by the grab head 16. By an upward movement of the lower racker assembly 6, the stand of pipe 13 can be elevated as required (Figure 3) . The drill string remaining within the well is suspended from the rotary table by means of. slips, as known per se. From the position shown in Figure 3, the racker arms 8 and 26 are driven back from the line of drilling 2, to a position corresponding to that shown in Figure 1. The grab heads 12 and 16 are pivoted 90° one way or the other as indicated by the arrows in Figure 2, and the support arms 11 and 27 are extended, whereby the heads 12,16 are moved toward the selected rack 4 or 5. The receiving groove in the selected rack has already been brought into position through a corres¬ ponding rotation of the carousel. This rotary movement occurs in clearly defined stages, corresponding to the groove subdivision. Two annular frames 28 and 29 are mounted on the derrick 1. The apertures of the rings are adapted to the cross section of the pipe bundle 30 which can be placed in the carousel. Each annular frame has a gap in the perimeter, at 31 and 32 respectively, thereby forming openings which are in alignment with the receiving groove lying internally thereof. The stand of pipe 13 that is being racked is guided through the gaps 31,32 into the receiving grooves in the two finger boards 21 and 22. The pipe string is moved inwardly until it meets some resistance, after which the stand of pipe is lowered down onto the storage platform 20 by moving the lower racker assembly downwardly in the guide 14. The grab heads 12,16 are opened and guided back to the drill string at the line of drilling 2 with corresponding movements in reverse.
To retrieve stands of pipe from the pipe rack, the above procedure is reversed.
It should be understood that the carousel always rotates to a defined position and that all racking movements are distinct, from a fetching position to a delivery position. This provides more reliable operation and requires less inter¬ ference by the operator, and results in less damage to the pipes and threads during handling. The stands of pipe can be secured in the receiving grooves with simple snap-locks, or remotely controlled flaps could be utilized. The annular frames 28,29 provide an additional safeguard around the racked pipe bundle. A retainer ring 31 is also preferably arranged around the storage platform 20.
The racking assembly can be constructed in various ways, which will be familiar to the skilled person, without depart¬ ing from the scope of the present invention. Instead of rotatable columns 10, the support arms 11,27 could rotate about fixed columns, or optionally rotate directly on the racker arms 8,26. The columns 10 could optionally be tele¬ scopic. Different modifications could also be imagined for the racker arms, etc. The important point is that all move- ments are distinct. Hydraulic actuators are preferably utilized, especially for the radial movements of the grab heads 12,16 toward and away from the pipe racks.

Claims

Patent Claims
1. An assembly for handling and racking drill pipe in a derrick, comprising a rack for vertical storage of stands of drill pipe in the derrick, with a storage platform and one or more finger boards spaced apart vertically above the storage platform, and racking equipment for transporting the stands of pipe between the line of drilling and the rack in the derrick, characterized in that the rack in the derrick has a fixed access opening, and the fingers of the finger board with intermediate grooves for receiving lengths of pipe are movable to and from a position in which the groove opening of one of the grooves is located at the fixed access opening to the rack.
2. An assembly according to claim 1, having racking equipment that comprises horizontal racker arms with grab/ support heads that can be moved laterally in the derrick, characterized in that the grab/support head is mounted on a support arm that is pivotable about a vertical axis on the racker arm, in such manner that the grab/support head can be moved in relation to the axis of rotation of the support arm.
3. An assembly according to claims 1 or 2, character- ized in that the rack is formed as a carousel, the finger boards being substantially circular and rotatable about a common vertical axis, with radially extending fingers and intermediate grooves therebetween.
4. An assembly according to claim 3, characterized in that a common, rotatable, central column supports the finger boards.
5. An assembly according to one of the preceding claims, characterized by one or more fixed annular frames each having a minimum aperture corresponding to the cross section of the bundle of pipe lengths that the rack can contain, each annular frame having a gap in the perimeter which forms the access opening to the storage rack.
6. An assembly according to one of the preceding claims, characterized in that two racks are placed on either side of a common racker assembly, with the access openings to the racks facing toward each other.
PCT/NO1983/000044 1982-10-13 1983-10-13 Assembly for handling and racking drill pipe in a derrick WO1984001599A1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
NO823416 1982-10-13

Publications (1)

Publication Number Publication Date
WO1984001599A1 true WO1984001599A1 (en) 1984-04-26

Family

ID=19886752

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/NO1983/000044 WO1984001599A1 (en) 1982-10-13 1983-10-13 Assembly for handling and racking drill pipe in a derrick

Country Status (2)

Country Link
EP (1) EP0121545A1 (en)
WO (1) WO1984001599A1 (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0228907A2 (en) * 1986-01-03 1987-07-15 STRACHAN & HENSHAW LIMITED Apparatus for handling drilling equipment, especially for off-shore drilling
US4708563A (en) * 1984-09-07 1987-11-24 B.V. Koninklijke Maatschappij "De Schelde" Arrangement for storing pipes
US4862973A (en) * 1986-09-03 1989-09-05 Deutag Deutsche Tiefbohr-Ag Drilling derrick device
WO1990013730A1 (en) * 1989-05-12 1990-11-15 Hitec A.S. Arrangement in a pipe handling system
WO1991019880A1 (en) * 1990-06-15 1991-12-26 Tamrock Oy Apparatus for storing drill rods
WO1992008873A1 (en) * 1990-11-12 1992-05-29 Tamrock Oy A cartridge for drill rods
WO1994024410A1 (en) * 1993-04-08 1994-10-27 Tamrock Oy Rod cartridge for a rock drilling equipment
WO1998019039A2 (en) 1996-10-29 1998-05-07 Weatherford/Lamb, Inc. Apparatus and method for running tubulars
WO1999066171A2 (en) * 1998-06-12 1999-12-23 Shell Internationale Research Maatschappij B.V. Method and system for moving equipment into and through an oil and/or gas production well
US6543555B2 (en) 2000-03-08 2003-04-08 Casagrande Spa Automatic loader for drill rods
US8425171B2 (en) 2008-01-31 2013-04-23 Keppel Offshore & Marine Technology Centre Pte Ltd. Pipe handling system and method
US9441427B2 (en) 2012-10-22 2016-09-13 Ensco Services Limited Automated pipe tripping apparatus and methods
US10294737B2 (en) 2017-03-23 2019-05-21 Ensco International Incorporated Vertical lift rotary table
US10724310B2 (en) 2018-06-08 2020-07-28 Glider Products LLC Integrated pipe handling system for well completion and production

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103867144B (en) * 2014-04-09 2016-03-02 天时海洋工程及石油装备研究院(青岛)有限公司 The double-deck fingerboard system of derrick

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3633767A (en) * 1969-08-12 1972-01-11 Dresser Ind Pipe-racking apparatus for oil well derricks or the like
DE2550361A1 (en) * 1974-11-14 1976-05-26 Lamb Industries DEVICE ON DRILLING TUBES FOR OPERATING PIPE SECTIONS
SE388241B (en) * 1970-04-20 1976-09-27 Wirth Co Kg Masch Bohr DRILLING MACHINE WITH DRILLING STRAY MAGAZINE
NO135543B (en) * 1970-12-15 1977-01-10 Alsacienne Atom

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3633767A (en) * 1969-08-12 1972-01-11 Dresser Ind Pipe-racking apparatus for oil well derricks or the like
SE388241B (en) * 1970-04-20 1976-09-27 Wirth Co Kg Masch Bohr DRILLING MACHINE WITH DRILLING STRAY MAGAZINE
NO135543B (en) * 1970-12-15 1977-01-10 Alsacienne Atom
DE2550361A1 (en) * 1974-11-14 1976-05-26 Lamb Industries DEVICE ON DRILLING TUBES FOR OPERATING PIPE SECTIONS

Cited By (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4708563A (en) * 1984-09-07 1987-11-24 B.V. Koninklijke Maatschappij "De Schelde" Arrangement for storing pipes
EP0228907A3 (en) * 1986-01-03 1988-12-07 Drg (Uk) Limited Apparatus for handling drilling equipment, especially for off-shore drilling
EP0228907A2 (en) * 1986-01-03 1987-07-15 STRACHAN & HENSHAW LIMITED Apparatus for handling drilling equipment, especially for off-shore drilling
US4862973A (en) * 1986-09-03 1989-09-05 Deutag Deutsche Tiefbohr-Ag Drilling derrick device
US5437527A (en) * 1989-05-12 1995-08-01 Hitech A/S Arrangement in a pipe handling system
WO1990013730A1 (en) * 1989-05-12 1990-11-15 Hitec A.S. Arrangement in a pipe handling system
AU634548B2 (en) * 1989-05-12 1993-02-25 Hitec A.S. Arrangement in a pipe handling system
US5244329A (en) * 1989-05-12 1993-09-14 Hitec A.S. Arrangement in a pipe handling system
WO1991019880A1 (en) * 1990-06-15 1991-12-26 Tamrock Oy Apparatus for storing drill rods
US5297642A (en) * 1990-06-15 1994-03-29 Tamrock Oy Apparatus for storing drill rods
WO1992008873A1 (en) * 1990-11-12 1992-05-29 Tamrock Oy A cartridge for drill rods
AU678447B2 (en) * 1993-04-08 1997-05-29 Tamrock Oy Rod cartridge for a rock drilling equipment
WO1994024410A1 (en) * 1993-04-08 1994-10-27 Tamrock Oy Rod cartridge for a rock drilling equipment
WO1998019039A2 (en) 1996-10-29 1998-05-07 Weatherford/Lamb, Inc. Apparatus and method for running tubulars
WO1998019039A3 (en) * 1996-10-29 1998-07-23 Weather Ford Lamb Inc Apparatus and method for running tubulars
EA003317B1 (en) * 1998-06-12 2003-04-24 Шелл Интернэшнл Рисерч Маатсхаппий Б.В. Method and system for moving equipment into and through a conduit
WO1999066171A3 (en) * 1998-06-12 2001-11-08 Shell Int Research Method and system for moving equipment into and through an oil and/or gas production well
WO1999066171A2 (en) * 1998-06-12 1999-12-23 Shell Internationale Research Maatschappij B.V. Method and system for moving equipment into and through an oil and/or gas production well
US6543555B2 (en) 2000-03-08 2003-04-08 Casagrande Spa Automatic loader for drill rods
US8425171B2 (en) 2008-01-31 2013-04-23 Keppel Offshore & Marine Technology Centre Pte Ltd. Pipe handling system and method
US9441427B2 (en) 2012-10-22 2016-09-13 Ensco Services Limited Automated pipe tripping apparatus and methods
US10214977B2 (en) 2012-10-22 2019-02-26 Ensco Services Limited Automated pipe tripping apparatus and methods
US10975639B2 (en) 2012-10-22 2021-04-13 Ensco Services Limited Automated pipe tripping apparatus and methods
US10294737B2 (en) 2017-03-23 2019-05-21 Ensco International Incorporated Vertical lift rotary table
US10745980B2 (en) 2017-03-23 2020-08-18 Ensco International Incorporated Vertical lift rotary table
US10724310B2 (en) 2018-06-08 2020-07-28 Glider Products LLC Integrated pipe handling system for well completion and production
US11225846B2 (en) 2018-06-08 2022-01-18 Glider Products LLC Integrated pipe handling method for well completion and production

Also Published As

Publication number Publication date
EP0121545A1 (en) 1984-10-17

Similar Documents

Publication Publication Date Title
WO1984001599A1 (en) Assembly for handling and racking drill pipe in a derrick
US6763898B1 (en) Dual hoist system
AU717094B2 (en) Drilling apparatus
EP0265234B1 (en) Pipe handling apparatus
EP0228907B1 (en) Apparatus for handling drilling equipment, especially for off-shore drilling
EP1246998B1 (en) Horizontal pipe handling device
US4117941A (en) Device for handling and racking riser pipes and drill pipes
EP0174055B1 (en) An arrangement for storing pipes
EP1953334B1 (en) A pipe handling system and method
EP2425090B1 (en) A tubulars storage and handling system
US8052370B2 (en) System for handling pipes between a pipe rack and a derrick, and also a device for assembling and disassembling pipe stands
US20090053015A1 (en) Pipe Handling Equipment
KR940008639B1 (en) Well drilling
US20120093614A1 (en) Pipe handling system and method
CN102449259A (en) Pipe stand transfer systems and methods
JPH0432917B2 (en)
BRPI0721340B1 (en) A drilling system with a drilling platform, method for tubular assembling and method for moving a plurality of tubular
EP1836374A2 (en) A device for gripping and transporting pipe lenghts and an intermediate storage facility for storage of pipes
US4582133A (en) Pipe handling assembly
CN111594073A (en) Land off-line operation drilling machine
US4050590A (en) Drilling rigs
US10214975B2 (en) Vertical pipe handling system and method for its use
US3742562A (en) Well pipe supporting unit
JPH038716B2 (en)
US11927060B2 (en) Offshore vessel and method of operation of such an offshore vessel

Legal Events

Date Code Title Description
AK Designated states

Designated state(s): DE FI GB JP NL SE US

AL Designated countries for regional patents

Designated state(s): FR

REG Reference to national code

Ref country code: DE

Ref legal event code: 8642