US20120291378A1 - Express framing system - Google Patents
Express framing system Download PDFInfo
- Publication number
- US20120291378A1 US20120291378A1 US13/568,091 US201213568091A US2012291378A1 US 20120291378 A1 US20120291378 A1 US 20120291378A1 US 201213568091 A US201213568091 A US 201213568091A US 2012291378 A1 US2012291378 A1 US 2012291378A1
- Authority
- US
- United States
- Prior art keywords
- joist
- strapping
- slab
- walls
- stiffened
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/16—Load-carrying floor structures wholly or partly cast or similarly formed in situ
- E04B5/32—Floor structures wholly cast in situ with or without form units or reinforcements
- E04B5/36—Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
- E04B5/38—Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor with slab-shaped form units acting simultaneously as reinforcement; Form slabs with reinforcements extending laterally outside the element
- E04B5/40—Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor with slab-shaped form units acting simultaneously as reinforcement; Form slabs with reinforcements extending laterally outside the element with metal form-slabs
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/24—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/24—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
- E04B1/2403—Connection details of the elongated load-supporting parts
- E04B2001/2415—Brackets, gussets, joining plates
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/24—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
- E04B2001/2466—Details of the elongated load-supporting parts
- E04B2001/2472—Elongated load-supporting part formed from a number of parallel profiles
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/24—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
- E04B2001/2484—Details of floor panels or slabs
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y10—TECHNICAL SUBJECTS COVERED BY FORMER USPC
- Y10T—TECHNICAL SUBJECTS COVERED BY FORMER US CLASSIFICATION
- Y10T29/00—Metal working
- Y10T29/49—Method of mechanical manufacture
- Y10T29/49616—Structural member making
- Y10T29/49623—Static structure, e.g., a building component
Definitions
- the present invention relates to new building structures and to an improved method of building construction.
- the invention provides improvements to light gauge steel framed building construction techniques in load bearing applications.
- Light gauge steel framed buildings such as mid-rise buildings having up to about six stories in height offer cost-effective construction and a number of additional advantages including ease of construction as well as warp, fire, rust and pest resistance.
- the express framing building construction system of the present invention offers numerous advantages for the construction of mid-rise buildings.
- the system can drastically reduce the time required to construct the “shell” of a mid-rise building, perhaps by as much as two thirds, by allowing the concrete floor slab to be poured at any convenient time.
- the slab can be poured in an enclosed area, protecting the un-cured concrete from rain and wind.
- the system allows the un-cured concrete floor slab to be heated more efficiently during cold weather and eliminates the need for tenting or temporary shelter. During extreme weather conditions, the pouring of the floor slabs can be postponed until auxiliary heating no longer needs to be supplied.
- the express framing system of the present invention is safer because it allows the pouring of the concrete floor slab to be performed in a safer, interior environment by providing actual exterior walls to protect workers from falling from the building.
- the express framing system allows for the continuous erection and framing of the building shell.
- the construction crews do not have to wait for a slab to be poured or to sufficiently harden before proceeding to the next story.
- the express framing system eliminates the need for a pour stop or projected edge on the floor framing.
- a pour stop is necessary in conventional platform construction to cover retain the concrete until it sets.
- the present method eliminates the need to sheath the band of concrete at the edge of the slab.
- the express framing system provides continuous walls and also allows wall insulation to be vertically continuous throughout the building; thereby insulating the so-called exposed “slab edge”. This method is energy efficient and provides a warmer floor.
- the express framing system reduces the expenses incurred for equipment and subcontracted services, such as cranes and construction elevators and hoists, due to the reduction in the time it takes to construct the building shell.
- the express framing system provides a better connection between the successive stories of walls because the walls are connected directly to each other. This is especially advantageous when connecting the building's walls together vertically.
- the elimination of bolts installed through a concrete slab is of enormous value.
- the express framing system allows the erection of a complete building shell, properly braced against all gravity and lateral loading conditions, without the pouring of the concrete floor slabs.
- the concrete floor slabs can be poured at a time of the construction managers choosing.
- the slabs can be poured under the cover and protection of the floor system above (i.e., the slab decking above) and the exterior sheathed walls. If necessary, the slab can be heated within an enclosed building shell.
- the continuous nature of the framing or erection of the building results in much more scheduling control for the building construction manager or contractor.
- a light steel framing construction technique for load bearing type buildings is provided. Multiple stories can be erected without waiting for individual concrete slab floors to be poured at each story.
- the building under construction is protected from torsional warping, such as may be expected under wind loads, by installation of floor decking at each level. Additional torsional or warp resistance may be provided by a series of lateral and diagonal bracing structures at each level, affixed in the plane perpendicular to the load bearing elements.
- Multiple concrete floor slabs can be poured simultaneously upon the previously installed metal decks, or, sequentially as desired, during the construction process.
- Walls consisting of light gauge, cold formed steel studs are erected on a foundation or other super-structure.
- the walls may be sheathed with an appropriate sheathing product, and many types are available.
- Such walls may be panelized off-site or framed at the building site.
- the express framing building construction system provides several types of brackets for supporting joists and floor decking These brackets are placed on or near the top of the load bearing walls.
- joist support angle brackets are affixed near the upper portion of parallel walls to support conventional joist constructions running between such walls.
- a second pair of walls perpendicular to the foregoing have decking support angles affixed near the top of such walls.
- the decking support angles are therefore parallel to the joists and perpendicular to the joist support angle brackets.
- Both the brackets and angles, in combination with the requisite joists, are capable of supporting the floor decking
- the floor decking is typically corrugated metal decking Additional bracing may be utilized to reinforce the wall, bracket and joist sub-assembly. Thereafter, the foregoing construction may be completed by pouring a concrete slab floor at any desired time.
- the express framing building construction system utilizes a combination of unique bracket constructions including a suspended slab joist support bracket and a suspended slab deck support bracket.
- the suspended slab joist support brackets may be of an exterior-type or interior-type, depending on the requirements of the building under construction.
- the expression “suspended slab' refers to the fact that the poured concrete floor does not rest directly on top of the load bearing walls, as in conventional platform framing construction. Rather, in the express framing system, the slab floor is supported by the joists and decking in combination with the unique angles and brackets disclosed herein.
- floor joists are placed atop either the joist support angle brackets or into the stirrups of the suspended slab joist support brackets and fastened securely, such as by bolts that utilize pre-drilled slotted holes in the brackets or stirrups.
- Warp resisting or diaphragm bracing may be applied in diagonal or other patterns and fastened across or below the floor joists.
- Preferred bracing is comprised of reinforcing stiffened strapping as will be discussed below.
- the bracing web ends are fastened at each end and may be attached to light gauge steel clip angles or other conventional fasteners. Additionally, the bracing web may be intermittently fastened along its length to construction members requiring reinforcement. For example, it may be applied to the joist members to prevent twisting and swaying.
- lateral bracing may be applied perpendicular to and across or below the bottom of the joists.
- the preferred lateral bracing is stiffened strapping, conventional hat channel may be used.
- the ends of the diaphragm bracing may be attached to light gauge steel clip angles.
- a roof or floor deck usually a metal deck and particularly a steel deck, is installed over the joists.
- the decking is attached to the joists and to either the horizontal leg of the suspended slab deck support brackets or to the alternative decking support angle brackets.
- each building story is constructed of exterior bearing walls, interior bearing walls, the floor system and the decking
- each story is a self-contained structural element capable of resisting all loads which it has been designed to carry or resist, as a component of the building as a whole.
- scheduling the pouring of the concrete floor slabs is discretionary.
- the framing and erection of the building can be performed without interruption and independently of the need to pour and cure the concrete slab floors.
- FIG. 1 is an illustration of a foundation upon which load bearing walls are to be erected.
- FIG. 2 depicts load bearing walls comprised of steel stud framing and sheathing panels erected on the foundation.
- FIG. 3 illustrates a suspended slab joist support bracket having an upside-down L-shape, and including a welded stirrup to receive a joist.
- FIG. 4 illustrates a suspended slab deck support bracket having a Z-shaped element, which receives the edges of the deck sheathing and forms a seal for containing the eventual poured slab.
- FIG. 5 is a detail of a joist support stirrup.
- FIG. 6 illustrates pairs of suspended slab joist support brackets installed opposite each other, atop parallel load bearing walls; and pairs of suspended slab deck support brackets installed perpendicular to the joist brackets, atop the remaining walls.
- FIG. 7 illustrates joist assemblies installed between the suspended slab joist support brackets.
- FIG. 8 illustrates diagonal or diaphragm bracing reinforcing the structure before a suspended slab deck is laid down and a slab floor is poured.
- FIG. 9 illustrates additional reinforcement with lateral bracing.
- FIG. 10 illustrates metal decking which will receive a poured slab installed atop the joists.
- the metal decking is surrounded by two sets of parallel suspended slab joist brackets and, parallel to these, two other sets of parallel suspended slab deck support brackets, thereby creating a form or mold for a poured slab deck.
- FIG. 11 illustrates a second story of load bearing walls erected atop the first story prior to the first deck slab being poured.
- FIG. 11 also depicts the first slab deck or sheathing, suspended from the first story load bearing walls.
- FIGS. 12-13 illustrate construction details.
- FIG. 14 depicts a cross-section of stiffened reinforcement strapping, having arc-shaped flutes for added strength, and used for lateral or diagonal bracing.
- FIG. 14 a depicts a length of the stiffened reinforcement strapping having continuous arc-shaped flutes.
- FIG. 15 is a detail depicting the attachment of the stiffened bracing to a clip angle.
- FIG. 16 is a detail depicting installation of a double or interior type suspended joist saddle bracket installed atop an interior load bearing wall.
- FIG. 17 is a cross-section of an installed double or interior type suspended joist saddle bracket construction assembly.
- FIG. 18 is a perspective view of a joist support angle bracket.
- FIG. 19 is a perspective view of a reinforced joist support angle bracket.
- FIG. 20 is an elevation view of a joist support angle bracket installed on stud framing and securing a joist seen in cross-section.
- FIG. 21 is a cross-section of a joist support angle bracket installed on stud framing and securing a joist and decking assembly, also seen in cross-section.
- FIG. 22 is a cross-section of a decking support angle bracket installed on stud framing and securing a decking assembly, also seen in cross-section.
- FIG. 23 is a cross-section depiction of prior art platform framing.
- the express framing construction system provides a method of erecting a building, and includes the steps of locating vertically extending and oppositely facing walls to form a set of joist supporting walls of a building, the joist supporting walls having upper load bearing surfaces; placing oppositely located rigid suspended slab joist supporting brackets on the wall upper surfaces; placing the ends of generally horizontal extending joists on the rigid suspended slab joist supporting brackets; and placing a sheet of slab decking on top of the joists.
- the decking is supported by the joists and the weight of the decking is borne by the joist supporting walls.
- the suspended slab joist supporting brackets are replaced with joist support angle brackets affixed to load bearing elements of the joist supporting walls.
- the method may include the additional step of locating a pair of oppositely placed rigid suspended slab deck support brackets on top of a pair of vertically extending and oppositely facing walls which are perpendicular to the joist supporting walls and the suspended slab joist supporting brackets.
- the slab deck support brackets may be replaced with lengths of slab deck support angles attached to the upper region of the perpendicular walls.
- bracing the wall and joist assemblies to reinforce and rigidify the assemblies and to inhibit relative twisting or warping by wind or other forces may be used.
- the bracing is preferably the reinforcing stiffened strapping described below.
- the method may continue with the additional step of pouring a layer of concrete or similar floor material on top of the decking to thereby form a floor for the building.
- An interior load bearing wall will support symmetrical joist supporting brackets on opposite sides of the interior wall.
- the method may include the additional step of erecting a subsequent assembly of load bearing walls, suspended slab joist and deck support brackets and suspended slab decking prior to the pouring of one or more concrete slab floors.
- a building constructed in accordance with the foregoing method is thereby provided.
- a building sub-assembly in the express framing system, includes a lower set of vertically extending walls, an upper set of vertically extending walls, the upper set of walls resting on the lower set of walls, a bracket affixed to the lower walls, the bracket having a cantilever portion extending away from its corresponding lower wall panel, a horizontal joist extending from and having one end supported by the cantilever bracket portion, a generally horizontal decking lying atop and supported by the joist, whereby concrete may be poured at any time on the decking to form a concrete floor.
- This sub-assembly may include a second sub-assembly mounted on top of the first mentioned sub-assembly, thereby yielding two vertically spaced horizontal deckings, the respective walls of the two building sub-assemblies being coplanar, and whereby concrete may be poured on the two spaced horizontal deckings sequentially or simultaneously.
- the construction method of the present invention utilizes a number of unique components in combination with conventional building materials.
- the conventional components typically include light gauge steel stud walls, sheathing, floor and roof joists, steel roofing and floor decking, and miscellaneous light gauge steel framing accessories such as angles, fasteners, clips, etc.
- Fasteners are generally selected as appropriate from among conventional screws, rivets and nut, bolt and washer assemblies.
- the first unique element utilized in the express framing system of this invention is a suspended slab joist support bracket. It may be of an exterior or interior type. This bracket is for the support of the floor joists which subsequently support the decking and poured slab. It is characterized herein as a “suspended slab” joist support bracket because, unlike conventional platform framing methods, the slab flooring is not installed atop the load bearing walls. Thus, the bracket supports or hangs the joists so that the load on the joist is eccentric to the centerline of the wall that is carrying the joist load. This bracket may form a continuous support for the floor joists and readily provides automatic “on center” distance locations for the placing of the joists.
- the eccentricity of the joist support allows the walls for successive stories to be placed on and fastened to the walls directly above and below each other. And unlike conventional platform framing mentioned above, construction of successive stories need not await the pouring and curing of concrete slab flooring. Rather, sufficient warp and twist resistance is provided by installation of the joist support brackets, the joists, the floor decking, and any bracing material which is utilized.
- the suspended slab joist support bracket 8 of FIG. 3 is an inverted L-shape having a horizontal and vertical leg with a formed “stirrup” welded to the vertical leg.
- the stirrup is located at the “on center” points of a load bearing wall and receives the floor joists.
- the stirrup is located below the horizontal leg of the bracket at a distance which equals the thickness of a subsequently poured concrete slab.
- the vertical face of the bracket acts as a leveling screed or pour stop to prevent the liquid slab concrete from exiting the desired area.
- the distance from the top of the bracket to the stirrup can be varied to achieve different results. Matching a desired slab depth with a specific stirrup location represents a typical application for bracket 8 .
- the suspended slab joist support bracket 8 is fastened through the vertical leg of the bracket to a track atop the conventional metal studs of a bearing wall. Fastening the bracket through the vertical leg allows the coplanar wall for the next story to rest on an upper load bearing surface that is flat and free from projections such as screws.
- the wall of the story above is fastened through its bottom track, the horizontal leg of the bracket and the top track of the wall below.
- the horizontal leg of the bracket is the same width as the metal stud bearing wall upon which it rests.
- a second unique element of the express framing system is an interior-type slab joist support bracket.
- This bracket is used on interior load bearing walls. If this bracket is made as an integral unit, stirrups are welded on both sides of an inverted U-shaped element. It is preferred however, that instead of a single integral interior bracket, a pair of symmetrical half-units will be used as described below.
- the vertical legs of the bracket face downward, and the horizontal leg rests on top of the upper track of the bearing wall.
- the interior bracket is otherwise similar to the exterior joist support bracket.
- a suspended slab deck support bracket is for the support of the metal decking at those of its perimeter edges which are perpendicular to those decking edges which are supported by the suspended slab deck support brackets.
- the bracket supports the edge of the metal decking and is located parallel to the direction of the floor joists. It forms a continuous support for the decking and also provides an automatic ledger for the slab, where no additional measuring is required.
- the suspended slab deck bracket is a Z-shaped steel element having upper horizontal, vertical and lower horizontal legs.
- An upper horizontal leg sits on top of the wall, the vertical leg equals the depth of the concrete slab, and the lower horizontal leg supports the metal decking.
- the horizontal leg that supports the decking is typically about 2 in. wide.
- the upper horizontal leg equals the width of the bearing wall.
- the vertical face of the bracket also acts as a pour stop to prevent the liquid slab concrete from exiting the desired area.
- the suspended slab deck bracket is fastened through the vertical leg of the bracket to the upper portion of the metal studs or top track of the bearing wall. Fastening the bracket through the vertical leg allows the wall for the next story to rest on a surface that is flat and free from projections such as screws.
- the wall of the story above is fastened through its bottom track, the horizontal leg of the bracket and the top track of the wall below.
- the upper horizontal leg of the bracket is the same width as the metal stud bearing wall upon which it rests.
- the suspended slab deck support brackets are installed on the walls that are parallel to the floor joists.
- the suspended slab joist support brackets may be replaced with joint support angle brackets which are affixed near the top of the bearing walls which support the joists.
- deck support angles may be utilized and affixed near the top of the perpendicular walls, to receive and support the floor decking Both such sets of brackets, in combination with the joist system and bracing, support the floor decking and the subsequently poured slab.
- the decking is suspended from, rather than resting upon, the load bearing walls.
- a further unique element of the present system is stiffened strapping for lateral or diagonal bracing.
- Light gauge steel strapping may be stiffened by forming one or more continuous stiffening impressions, or beads, parallel to the long dimension of the strap. Stiffening impressions, such as flutes, enable the strapping to be easily handled. The flutes greatly add to the rigidity and structural properties of the strapping.
- the stiffened strapping provided herein may be used in a wide variety of applications requiring enhanced reinforcement. It is particularly useful in the subject express framing construction method where, when installed below the suspended joists and secured thereto, it serves to prevent swaying and twisting of the hanging joists.
- the stiffened strapping may be used for lateral or diagonal bracing and is preferably formed from a coil of steel, which is preferably galvanized steel conforming to the requirements of ASTM A 653, having a yield strength of 33 or 50 ksi and a minimum of G-60 galvanized coating.
- the steel coil is decoiled and flattened by conventional means before the stiffening impressions are imparted.
- the stiffening impressions may be applied to any length of coil but generally the dimensions of the strapping will be selected in accordance with the specified construction requirements and ease of handling.
- a typical installation will utilize 12 foot lengths of stiffened strapping having dimensions of about 2 in width and thickness of 54 mils (16 gauge). In other applications, lengths from about 2 in to 30 feet may be used as required and the width of the strapping may vary from about 1.5 in to 12 in while the thickness may vary from about 30 to 70 mils.
- One or more stiffening impressions are imparted to the web by conventional mechanical metal pressing, rolling or stamping. Hot or cold methods may be utilized as appropriate.
- the preferred stiffening impressions are flute-shaped impressions, but other shapes may be utilized depending upon the chosen methods of fabrication. It should be possible, for example, to create a v-shaped stiffening impression which ought to function similarly in appropriate applications. All such shapes and channels effective for stiffening the strapping are contemplated for use as the stiffening impressions.
- the preferred flute-shaped stiffening impressions are generally semi-circular in shape since an arc is readily impressed during fabrication.
- the flutes are generally centered along the length of the strapping, or symmetrically oriented from the center line when more than a single flute is utilized. It will be recognized, however, that the stiffening flutes may be offset from the center if a larger flat edge of the strapping is required for some other function, such as securing an edge along its length.
- a single stiffening impression such as a flute can be effective in some applications, especially less critical applications or where strapping lengths are minimized. Three or more stiffening impressions can be used for longer lengths of stiffened strapping or where applications will benefit from additional stiffening strength.
- a pair of parallel flutes was impressed upon the stiffened strapping and these were found to be satisfactory.
- the stiffened strapping can be readily cut to order in the fabricator's shop and transported in flat bundles to a worksite. At the worksite, the stiffened strapping is readily installed using conventional fasteners including machine and metal screws, bolts, etc. Rivets could be utilized but are no longer a popular choice.
- FIG. 1 illustrates a concrete or masonry foundation 1 A having a flat surface 1 upon which load bearing walls are to be erected.
- An outline of the location of an alternative steel beam bearing 2 is also indicated by the dotted lines.
- FIG. 2 depicts panelized load bearing walls 5 comprised of steel stud framing 6 and sheathing panels erected on surface 1 of foundation 1 A.
- FIG. 3 illustrates a rigid suspended slab joist support bracket 8 having an inverted L-shape, and includes a welded-thereto joist stirrup 9 to receive the joists.
- the joist stirrup 9 is generally U-shaped, as detailed in FIG. 5 .
- the bracket 8 also includes pre-drilled holes 10 , while a rear edge of bracket 8 is denoted as 11 .
- the horizontal width of the top surface of bracket 8 is denoted as 12 and matches the upper load bearing surface of a wall upon which it is installed.
- the downward width of bracket 8 is denoted as 13 and varies with the desired depth of the poured slab flooring.
- the on-center distance between later-installed studs is denoted as 14 .
- the bracket is fastened to thee vertical studs with screws through pre-drilled holes 10 .
- FIG. 4 illustrates a rigid suspended slab deck support bracket 20 which is generally Z-shaped, and which receives the edges of the deck sheathing and forms a seal for the later poured concrete slab.
- Slab deck support bracket 20 includes pre-drilled holes 21 .
- the later-installed stud on-center distance is denoted as 22 .
- a horizontal rear edge of bracket 20 is denoted as 23 .
- the slab deck support bracket 20 placed atop a wall parallel to the joists, has a first or upper horizontal edge or width 24 , a vertical edge 25 , and a second or lower horizontal edge or width 27 .
- Deck support lip 26 lies in a horizontal plane.
- FIG. 5 is a detail of a joist support stirrup 9 of FIG. 3 .
- Reference numeral 9 denotes a joist stirrup which in this embodiment has typical dimensions of 4 in by 3 in by 2.5 in.
- Reference numeral 9 a denotes either of two vertical side portions, while 9 c denotes a flat, cantilever portion.
- Pre-drilled attachment holes 10 are in a vertical portion of 8 , while the stirrup 9 is welded at 30 to provide a slab joist support.
- Crimped reinforcing ribs 32 are provided on the outside walls of stirrup 9 .
- Pre-drilled, elongated holes 33 are provided at the bottom, flat portion of the stirrup.
- FIG. 6 illustrates several suspended slab joist support brackets 8 installed in pairs opposite each other, atop parallel load bearing walls, and also includes several suspended slab deck support brackets 20 installed perpendicular to the slab joist support brackets and atop the remaining walls which run lengthwise.
- FIG. 7 illustrates several joist assemblies 40 installed between the suspended slab joist support brackets 8 , the joist ends resting in respective stirrups 9 .
- Each joist may include a lower strut 40 a such as may be utilized for supporting a suspended ceiling or to affix reinforcing bracing.
- the bracing may be stiffened strapping described herein.
- FIG. 8 illustrates several diagonal bracing members 55 reinforcing the structure before a deck and concrete slab are installed.
- Such bracing is preferably stiffened strapping which is fastened to conventional clip angle 50 .
- FIG. 9 illustrates additional reinforcement with lateral bracing 60 , the latter attached to respective pairs of opposite walls 5 .
- the preferred bracing is stiffened strapping.
- FIG. 10 illustrates decking 65 which is usually corrugated metal decking and which is installed atop underlying joists and which will receive a poured slab on top thereof.
- the decking is peripherally surrounded by slab joist brackets 8 and slab deck support brackets 20 to create a form or mold for the poured slab deck.
- the concrete may be poured at any convenient time on decking 65 .
- FIG. 11 illustrates the construction of a second story 67 A atop a lower load bearing first story 67 .
- the first and second stories are comprised of wall sections 5 and 5 A, respectively.
- the walls are sheathed with conventional sheathing panels or sections.
- Decking 65 is ready to receive concrete to form a poured slab deck.
- the illustrated second or upper story 67 A utilizes steel stud framing 6 A interior to the sheathing panels which together comprise the load bearing wall construction which supports any subsequent stories.
- FIG. 12 is a cross-section of the suspended slab joist support bracket 8 , taken along 12 - 12 of FIG. 11 , installed between lower wall 70 and upper wall 70 a and secured with screw fasteners 71 .
- Fluted metal decking 65 supports poured concrete deck slab 66 .
- An end of a joist 40 is inserted into joist stirrup 9 and secured with bolt, nut and washer assembly 73 .
- One end of joist 40 is supported by cantilever portion 9 c of stirrup 9 .
- FIG. 13 is a cross-section detail of the suspended slab deck support 20 installed between lower light gauge wall 72 and upper light gauge wall 72 a and secured through wall tracks 77 and 78 with screw fasteners 71 . Seams 77 A and 78 A are exaggerated for clarity. It will be noted that the suspended slab deck support 20 and walls 72 and 72 a depicted in FIG. 13 are perpendicular to walls 70 on 70 a and suspended slab joist support 8 illustrated in FIG. 12 . Also depicted in FIG. 13 is concrete decking slab 66 poured atop metal decking 65 .
- FIG. 14 depicts a cross-section of a stiffened reinforcement strapping 80 , the latter provided with continuous and parallel stiffening impressions which in this embodiment are flutes 81 and 82 .
- the stiffened strapping used for the lateral and diagonal bracing is seen for example as diagonal bracing 55 in FIG. 8 and lateral bracing 60 in FIG. 9 .
- the strapping width in this figure has a width of about 2 inches.
- FIG. 14A is a perspective view of the stiffened reinforcement strapping 80 , further illustrating its parallel strengthening flutes, 81 and 82 . Holes 85 may be used to fasten the stiffened strapping.
- FIG. 15 is a detail depicting the attachment of lateral bracing 80 to clip angle 50 .
- Diagonal bracing is similarly attached.
- Fasteners 71 pass through preformed openings to secure the bracing to the angle.
- Conventional fasteners, clip angles, screws and the like are selected as may be appropriate in a given application.
- FIG. 16 is a detail perspective depicting installation of an interior-type suspended slab joist saddle bracket 83 installed atop an interior load bearing wall 84 .
- the saddle bracket may be a single, symmetrical unit or may be comprised of a pair of symmetrical half-units as illustrated in FIGS. 16 and 17 . In either case, joists hang on opposite sides of interior load bearing wall 84 .
- the joists are herein depicted with struts 79 and lower joist tracks 40 A.
- FIG. 17 is a cross-section showing symmetrical interior suspended joist saddle brackets 83 installed atop an interior load bearing wall 84 . It will be observed that lower wall 84 and upper wall 84 A of FIG. 17 are substantially coplanar. That is, each lies in the same vertical plane. This also the case for walls 70 and 70 A of FIG. 12 , and for walls 72 and 72 A of FIG. 13 .
- joists 40 are secured to brackets 83 by nut and bolt assemblies 73 .
- Corrugated decking 65 and poured slab 66 are shown.
- Bearing walls 84 and 84 A are capped with tracks 85 and 86 and secured with screw fasteners 71 .
- FIG. 18 is a perspective view of a joist support angle bracket 100 having holes 102 for fastening a joist to bracket 100 , typically via a bolt, nut and washer assembly.
- bracket 100 also has holes for fastening the bracket to the top track of a bearing wall or stud.
- Holes 104 may receive bolts or other fasteners but will typically utilize screws for securing brackets 100 to the track or studs.
- FIG. 19 is a perspective view of an alternative reinforced joist support angle bracket 101 additionally having reinforcing member 101 A.
- Reinforcing member 101 A is typically a metal wedge welded in placed or forged in the initial fabrication of the bracket.
- FIG. 20 is an elevation view of joist support angle bracket 100 installed with fasteners 140 on left and right stud framing members 105 and 105 A.
- fasteners 140 may be metal screws.
- left and right portions of a joist section 109 and 109 A are seen in cross-section and are secured to joist support angle bracket 100 by nut, bolt and washer assemblies 107 and 107 A.
- Joist support angle bracket 100 shown in cross-section, is installed on lower wall stud framing member 110 and secured thereon by fasteners 140 .
- the vertical portion of this bracket may be a 4 in by 5 in flange which attaches to the studs with six 5/16 th in screws.
- the horizontal joist ledger portion of the bracket can attach the joist seat with 1 ⁇ 2 in bolts which are 31 ⁇ 2 in on-center.
- joist members 150 , 152 and 154 are shown in cross-section.
- the joist is secured to joist support angle bracket 100 by bolt 130 having bolt head 138 , washers 134 and 136 , and nut 132 .
- a cross-section of corrugated decking 156 is shown atop joist portion 154 .
- concrete decking slab 158 has been poured atop deck sheathing 156 .
- lower framing member 110 is capped with upper rail 111 shown in cross-section and supports upper framing member 112 and its associated lower rail 113 .
- These framing members are preferably metal framing studs having conventional framing hardware.
- These upper and lower members are securely fastened, as by screws 114 .
- exaggerated seam 119 is shown only for clarity between the sections. In practice, the seam is eliminated when the upper and lower sections are secured together.
- Lower and upper sheathing panels 116 and 118 are depicted in cross section on the vertical wall panel opposite the joist. It will be understood that the concrete slab decking is poured up to the wall members, but not between them. Sheathing panels 116 and 118 may be gypsum board or other suitable panelized sheathing product.
- FIG. 22 Construction details for installation of a deck support angle and related assemblies are shown in FIG. 22 .
- Deck support angle 160 shown in cross-section, is installed on lower wall 110 ′ and secured thereon by fasteners 145 which may be metal screws.
- decking 162 is shown in cross-section.
- the suspended slab deck support angle is continuous conventional angle, e.g. 3 in by 3 in, trimmed to suitable lengths for ease of handling and effective for supporting the edge of the suspended decking and acting as a pour stop for the concrete floor.
- the decking is secured to deck support angle 160 by fastener 145 .
- concrete decking slab 158 has been poured atop deck sheathing 162 . In this construction, as in FIG.
- lower framing member 110 ′ is capped with upper rail 111 ′ shown in cross-section and which supports upper framing member 112 ′ and its associated lower rail 113 ′. These upper and lower members are securely fastened, as by screws 114 .
- exaggerated seam 147 is shown only for clarity between the sections. In practice, the seam is tight and essentially eliminated as the upper and lower sections are secured together.
- Lower and upper sheathing panels 116 ′ and 118 ′ are here depicted in cross section on the vertical wall panel opposite the decking 162 and deck support bracket 160 . In this embodiment, sheathing panels 116 ′ and 118 ′ are gypsum board.
- FIG. 23 is a cross-section of a prior art platform framing construction including exterior sheathing a, an upper load bearing wall b, a lower load bearing wall c, a concrete deck d, a joist hanger e, and a joist f. It is noteworthy that in such a construction, the poured slab floor d is located between the upper and lower load bearing walls b and c and therefore must be installed prior to construction of the upper walls. FIG. 23 shows that each concrete floor d must be poured and set prior to the formation of the next and, above, story. In stark contrast, the present invention permits all of the concrete floors to be poured at the same time, or as may be optimally desired.
- the express framing system provides buildings comparable to those provided by other light gauge steel methods, such as the aforementioned platform framing technique.
- a building may have one or more load bearing quadrilaterals of about 100 ft by 100 ft.
- an interior load bearing quadrilateral section might then be 50 ft by 100 ft.
- the typical height per story is 10 ft.
- the typical number of stories is 2 to 4, with 6 stories being the maximum for this type of light gauge steel mid-rise construction.
- the joists run either lengthwise or widthwise, as the structure design dictates.
- Specifications for construction members and hardware are typical of light gauge steel framing techniques.
- the preferred grades of steel vary with the parts and application.
- the specification for joists, joist brackets, decking hangers, decking, support fixtures and other rolled structural steel shapes is ASTM A572.
- the specification for structural steel plates and items made from such plates is ASTM A36.
- the specification for structural steel tubes is A500 Gr. B.
- the specification for cold formed light gauge steel, used for the stiffened strapping is ASTM A653 with yield strength of 33 ksi or 50 ksi, and galvanized to a G-60 coating as per ASTM C955.
- the specification for bolts, joints, fittings, etc. is ASTM A325 TC, with hardened nuts & washers. In typical applications, any grade or type of concrete slab would be suitable.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
A light steel framing construction technique for light gauge load bearing wall type buildings uses specialized brackets to suspend poured slab floors. Multiple stories of the building can be erected without waiting for individual concrete slab floors to be poured and set at each story. During construction, a building is protected from torsional warping, such as may be occur under wind loads, by a series of lateral and diagonal bracing structures at each level affixed in a plane perpendicular to the load bearing elements. Multiple concrete floor slabs can be poured sequentially or simultaneously, as desired, during the construction process.
Description
- This application claims the benefit of provisional patent application Ser. No. 60/713,455, filed Sep. 1, 2005 by the present inventors.
- Not Applicable
- Not Applicable
- BACKGROUND OF THE INVENTION
- 1. Field of the Invention
- The present invention relates to new building structures and to an improved method of building construction. In particular, the invention provides improvements to light gauge steel framed building construction techniques in load bearing applications.
- 2. Prior Art
- Light gauge steel framed buildings, such as mid-rise buildings having up to about six stories in height offer cost-effective construction and a number of additional advantages including ease of construction as well as warp, fire, rust and pest resistance.
- Currently, mid-rise buildings, constructed with light gauge steel stud bearing walls, and concrete slab floors use “Platform Framing” methodology. Platform framing construction is that type of building where the floor system rests directly above and upon the walls below. Therefore, the continuation of the building erection process depends entirely upon the pouring and curing of each successive concrete floor. This method requires waiting for the concrete floor to cure or set in order to support imposed loads during further construction. Also, the poured slab floor must attain enough surface hardness to resist damage. If the building is constructed during winter conditions, providing temporary heat to protect the curing concrete can be quite cumbersome and costly. The problem of protecting concrete is exacerbated when the concrete is open to the weather in the absence of enclosing walls and a ceiling or roof above. Poured concrete which is subject to rain and wind exposure can be easily damaged.
- Waiting for the concrete to be poured and to attain optimum structural properties interrupts the erection of the building frame, and results in labor force disruptions and rescheduling problems. The prompt return of work crews such as a displaced carpentry work force can be problematic. Also, the efficient use of construction equipment such as cranes is adversely affected by the interruption of the framing process. Either the crane sits idle, which is costly, or the crane leaves the site and its timely return is as problematic as that of the other work crews.
- Therefore, current construction methods result in the interruption of the carpentry, plumbing, electrical and other trades, and makes the pouring of concrete inefficient and subject to inordinate delays.
- The express framing building construction system of the present invention offers numerous advantages for the construction of mid-rise buildings. The system can drastically reduce the time required to construct the “shell” of a mid-rise building, perhaps by as much as two thirds, by allowing the concrete floor slab to be poured at any convenient time. Furthermore, the slab can be poured in an enclosed area, protecting the un-cured concrete from rain and wind. The system allows the un-cured concrete floor slab to be heated more efficiently during cold weather and eliminates the need for tenting or temporary shelter. During extreme weather conditions, the pouring of the floor slabs can be postponed until auxiliary heating no longer needs to be supplied.
- The express framing system of the present invention is safer because it allows the pouring of the concrete floor slab to be performed in a safer, interior environment by providing actual exterior walls to protect workers from falling from the building.
- The express framing system allows for the continuous erection and framing of the building shell. The construction crews do not have to wait for a slab to be poured or to sufficiently harden before proceeding to the next story.
- The express framing system eliminates the need for a pour stop or projected edge on the floor framing. A pour stop is necessary in conventional platform construction to cover retain the concrete until it sets. The present method eliminates the need to sheath the band of concrete at the edge of the slab.
- The express framing system provides continuous walls and also allows wall insulation to be vertically continuous throughout the building; thereby insulating the so-called exposed “slab edge”. This method is energy efficient and provides a warmer floor.
- The express framing system reduces the expenses incurred for equipment and subcontracted services, such as cranes and construction elevators and hoists, due to the reduction in the time it takes to construct the building shell.
- The express framing system provides a better connection between the successive stories of walls because the walls are connected directly to each other. This is especially advantageous when connecting the building's walls together vertically. Here, the elimination of bolts installed through a concrete slab is of enormous value.
- The express framing system allows the erection of a complete building shell, properly braced against all gravity and lateral loading conditions, without the pouring of the concrete floor slabs. The concrete floor slabs can be poured at a time of the construction managers choosing. The slabs can be poured under the cover and protection of the floor system above (i.e., the slab decking above) and the exterior sheathed walls. If necessary, the slab can be heated within an enclosed building shell. The continuous nature of the framing or erection of the building results in much more scheduling control for the building construction manager or contractor.
- Other objects, features and advantages of the present invention will be apparent upon consideration of the following detailed descriptions and the accompanying drawings, which should be construed as illustrative and not limiting.
- A light steel framing construction technique for load bearing type buildings is provided. Multiple stories can be erected without waiting for individual concrete slab floors to be poured at each story. The building under construction is protected from torsional warping, such as may be expected under wind loads, by installation of floor decking at each level. Additional torsional or warp resistance may be provided by a series of lateral and diagonal bracing structures at each level, affixed in the plane perpendicular to the load bearing elements. Multiple concrete floor slabs can be poured simultaneously upon the previously installed metal decks, or, sequentially as desired, during the construction process.
- Walls, consisting of light gauge, cold formed steel studs are erected on a foundation or other super-structure. The walls may be sheathed with an appropriate sheathing product, and many types are available. Such walls may be panelized off-site or framed at the building site.
- The express framing building construction system provides several types of brackets for supporting joists and floor decking These brackets are placed on or near the top of the load bearing walls.
- In one embodiment of the present system, joist support angle brackets are affixed near the upper portion of parallel walls to support conventional joist constructions running between such walls. A second pair of walls perpendicular to the foregoing have decking support angles affixed near the top of such walls. The decking support angles are therefore parallel to the joists and perpendicular to the joist support angle brackets. Both the brackets and angles, in combination with the requisite joists, are capable of supporting the floor decking The floor decking is typically corrugated metal decking Additional bracing may be utilized to reinforce the wall, bracket and joist sub-assembly. Thereafter, the foregoing construction may be completed by pouring a concrete slab floor at any desired time.
- In another embodiment, the express framing building construction system utilizes a combination of unique bracket constructions including a suspended slab joist support bracket and a suspended slab deck support bracket. The suspended slab joist support brackets may be of an exterior-type or interior-type, depending on the requirements of the building under construction. In this context, the expression “suspended slab' refers to the fact that the poured concrete floor does not rest directly on top of the load bearing walls, as in conventional platform framing construction. Rather, in the express framing system, the slab floor is supported by the joists and decking in combination with the unique angles and brackets disclosed herein.
- In practice, floor joists are placed atop either the joist support angle brackets or into the stirrups of the suspended slab joist support brackets and fastened securely, such as by bolts that utilize pre-drilled slotted holes in the brackets or stirrups.
- Warp resisting or diaphragm bracing may be applied in diagonal or other patterns and fastened across or below the floor joists. Preferred bracing is comprised of reinforcing stiffened strapping as will be discussed below. The bracing web ends are fastened at each end and may be attached to light gauge steel clip angles or other conventional fasteners. Additionally, the bracing web may be intermittently fastened along its length to construction members requiring reinforcement. For example, it may be applied to the joist members to prevent twisting and swaying.
- Similarly, lateral bracing may be applied perpendicular to and across or below the bottom of the joists. Although the preferred lateral bracing is stiffened strapping, conventional hat channel may be used. The ends of the diaphragm bracing may be attached to light gauge steel clip angles.
- Thereafter, a roof or floor deck, usually a metal deck and particularly a steel deck, is installed over the joists. The decking is attached to the joists and to either the horizontal leg of the suspended slab deck support brackets or to the alternative decking support angle brackets.
- In general, each building story is constructed of exterior bearing walls, interior bearing walls, the floor system and the decking In the present invention, each story is a self-contained structural element capable of resisting all loads which it has been designed to carry or resist, as a component of the building as a whole. Once each story is framed with the present system, the next higher story can be constructed. This is accomplished by erecting the next higher set of walls directly above and resting on the upper load bearing surface of the walls of the preceding lower story. The process repeats itself until all stories of the building have been framed or erected.
- In such a system, scheduling the pouring of the concrete floor slabs is discretionary. The framing and erection of the building can be performed without interruption and independently of the need to pour and cure the concrete slab floors.
-
FIG. 1 is an illustration of a foundation upon which load bearing walls are to be erected. -
FIG. 2 depicts load bearing walls comprised of steel stud framing and sheathing panels erected on the foundation. -
FIG. 3 illustrates a suspended slab joist support bracket having an upside-down L-shape, and including a welded stirrup to receive a joist. -
FIG. 4 illustrates a suspended slab deck support bracket having a Z-shaped element, which receives the edges of the deck sheathing and forms a seal for containing the eventual poured slab. -
FIG. 5 is a detail of a joist support stirrup. -
FIG. 6 illustrates pairs of suspended slab joist support brackets installed opposite each other, atop parallel load bearing walls; and pairs of suspended slab deck support brackets installed perpendicular to the joist brackets, atop the remaining walls. -
FIG. 7 illustrates joist assemblies installed between the suspended slab joist support brackets. -
FIG. 8 illustrates diagonal or diaphragm bracing reinforcing the structure before a suspended slab deck is laid down and a slab floor is poured. -
FIG. 9 illustrates additional reinforcement with lateral bracing. -
FIG. 10 illustrates metal decking which will receive a poured slab installed atop the joists. InFIG. 10 , the metal decking is surrounded by two sets of parallel suspended slab joist brackets and, parallel to these, two other sets of parallel suspended slab deck support brackets, thereby creating a form or mold for a poured slab deck. -
FIG. 11 illustrates a second story of load bearing walls erected atop the first story prior to the first deck slab being poured.FIG. 11 also depicts the first slab deck or sheathing, suspended from the first story load bearing walls. -
FIGS. 12-13 illustrate construction details. -
FIG. 14 depicts a cross-section of stiffened reinforcement strapping, having arc-shaped flutes for added strength, and used for lateral or diagonal bracing.FIG. 14 a depicts a length of the stiffened reinforcement strapping having continuous arc-shaped flutes. -
FIG. 15 is a detail depicting the attachment of the stiffened bracing to a clip angle. -
FIG. 16 is a detail depicting installation of a double or interior type suspended joist saddle bracket installed atop an interior load bearing wall. -
FIG. 17 is a cross-section of an installed double or interior type suspended joist saddle bracket construction assembly. -
FIG. 18 is a perspective view of a joist support angle bracket. -
FIG. 19 is a perspective view of a reinforced joist support angle bracket. -
FIG. 20 is an elevation view of a joist support angle bracket installed on stud framing and securing a joist seen in cross-section. -
FIG. 21 is a cross-section of a joist support angle bracket installed on stud framing and securing a joist and decking assembly, also seen in cross-section. -
FIG. 22 is a cross-section of a decking support angle bracket installed on stud framing and securing a decking assembly, also seen in cross-section. -
FIG. 23 is a cross-section depiction of prior art platform framing. - The express framing construction system provides a method of erecting a building, and includes the steps of locating vertically extending and oppositely facing walls to form a set of joist supporting walls of a building, the joist supporting walls having upper load bearing surfaces; placing oppositely located rigid suspended slab joist supporting brackets on the wall upper surfaces; placing the ends of generally horizontal extending joists on the rigid suspended slab joist supporting brackets; and placing a sheet of slab decking on top of the joists. The decking is supported by the joists and the weight of the decking is borne by the joist supporting walls. In an alternative method, the suspended slab joist supporting brackets are replaced with joist support angle brackets affixed to load bearing elements of the joist supporting walls.
- The method may include the additional step of locating a pair of oppositely placed rigid suspended slab deck support brackets on top of a pair of vertically extending and oppositely facing walls which are perpendicular to the joist supporting walls and the suspended slab joist supporting brackets. Alternatively, the slab deck support brackets may be replaced with lengths of slab deck support angles attached to the upper region of the perpendicular walls.
- An additional step of bracing the wall and joist assemblies to reinforce and rigidify the assemblies and to inhibit relative twisting or warping by wind or other forces may be used. The bracing is preferably the reinforcing stiffened strapping described below.
- Thereafter, the method may continue with the additional step of pouring a layer of concrete or similar floor material on top of the decking to thereby form a floor for the building.
- The method works equally well with either exterior or interior load bearing walls.
- An interior load bearing wall will support symmetrical joist supporting brackets on opposite sides of the interior wall.
- The method may include the additional step of erecting a subsequent assembly of load bearing walls, suspended slab joist and deck support brackets and suspended slab decking prior to the pouring of one or more concrete slab floors. A building constructed in accordance with the foregoing method is thereby provided.
- In the express framing system, a building sub-assembly includes a lower set of vertically extending walls, an upper set of vertically extending walls, the upper set of walls resting on the lower set of walls, a bracket affixed to the lower walls, the bracket having a cantilever portion extending away from its corresponding lower wall panel, a horizontal joist extending from and having one end supported by the cantilever bracket portion, a generally horizontal decking lying atop and supported by the joist, whereby concrete may be poured at any time on the decking to form a concrete floor. This sub-assembly may include a second sub-assembly mounted on top of the first mentioned sub-assembly, thereby yielding two vertically spaced horizontal deckings, the respective walls of the two building sub-assemblies being coplanar, and whereby concrete may be poured on the two spaced horizontal deckings sequentially or simultaneously.
- The construction method of the present invention utilizes a number of unique components in combination with conventional building materials. The conventional components typically include light gauge steel stud walls, sheathing, floor and roof joists, steel roofing and floor decking, and miscellaneous light gauge steel framing accessories such as angles, fasteners, clips, etc. Fasteners are generally selected as appropriate from among conventional screws, rivets and nut, bolt and washer assemblies.
- In one embodiment, the first unique element utilized in the express framing system of this invention is a suspended slab joist support bracket. It may be of an exterior or interior type. This bracket is for the support of the floor joists which subsequently support the decking and poured slab. It is characterized herein as a “suspended slab” joist support bracket because, unlike conventional platform framing methods, the slab flooring is not installed atop the load bearing walls. Thus, the bracket supports or hangs the joists so that the load on the joist is eccentric to the centerline of the wall that is carrying the joist load. This bracket may form a continuous support for the floor joists and readily provides automatic “on center” distance locations for the placing of the joists.
- The eccentricity of the joist support allows the walls for successive stories to be placed on and fastened to the walls directly above and below each other. And unlike conventional platform framing mentioned above, construction of successive stories need not await the pouring and curing of concrete slab flooring. Rather, sufficient warp and twist resistance is provided by installation of the joist support brackets, the joists, the floor decking, and any bracing material which is utilized.
- The suspended slab
joist support bracket 8 ofFIG. 3 is an inverted L-shape having a horizontal and vertical leg with a formed “stirrup” welded to the vertical leg. The stirrup is located at the “on center” points of a load bearing wall and receives the floor joists. The stirrup is located below the horizontal leg of the bracket at a distance which equals the thickness of a subsequently poured concrete slab. The vertical face of the bracket acts as a leveling screed or pour stop to prevent the liquid slab concrete from exiting the desired area. The distance from the top of the bracket to the stirrup can be varied to achieve different results. Matching a desired slab depth with a specific stirrup location represents a typical application forbracket 8. - In this embodiment, the suspended slab
joist support bracket 8 is fastened through the vertical leg of the bracket to a track atop the conventional metal studs of a bearing wall. Fastening the bracket through the vertical leg allows the coplanar wall for the next story to rest on an upper load bearing surface that is flat and free from projections such as screws. The wall of the story above is fastened through its bottom track, the horizontal leg of the bracket and the top track of the wall below. The horizontal leg of the bracket is the same width as the metal stud bearing wall upon which it rests. - In this first embodiment, a second unique element of the express framing system is an interior-type slab joist support bracket. This bracket is used on interior load bearing walls. If this bracket is made as an integral unit, stirrups are welded on both sides of an inverted U-shaped element. It is preferred however, that instead of a single integral interior bracket, a pair of symmetrical half-units will be used as described below. The vertical legs of the bracket face downward, and the horizontal leg rests on top of the upper track of the bearing wall. The interior bracket is otherwise similar to the exterior joist support bracket.
- Also in this embodiment of the express framing building construction system, another unique element utilized is a suspended slab deck support bracket. These brackets are for the support of the metal decking at those of its perimeter edges which are perpendicular to those decking edges which are supported by the suspended slab deck support brackets. The bracket supports the edge of the metal decking and is located parallel to the direction of the floor joists. It forms a continuous support for the decking and also provides an automatic ledger for the slab, where no additional measuring is required.
- The suspended slab deck bracket is a Z-shaped steel element having upper horizontal, vertical and lower horizontal legs. An upper horizontal leg sits on top of the wall, the vertical leg equals the depth of the concrete slab, and the lower horizontal leg supports the metal decking. The horizontal leg that supports the decking is typically about 2 in. wide. The upper horizontal leg equals the width of the bearing wall. The vertical face of the bracket also acts as a pour stop to prevent the liquid slab concrete from exiting the desired area.
- The suspended slab deck bracket is fastened through the vertical leg of the bracket to the upper portion of the metal studs or top track of the bearing wall. Fastening the bracket through the vertical leg allows the wall for the next story to rest on a surface that is flat and free from projections such as screws. The wall of the story above is fastened through its bottom track, the horizontal leg of the bracket and the top track of the wall below. The upper horizontal leg of the bracket is the same width as the metal stud bearing wall upon which it rests. The suspended slab deck support brackets are installed on the walls that are parallel to the floor joists.
- In an alternative embodiment of the express framing building construction system, the suspended slab joist support brackets may be replaced with joint support angle brackets which are affixed near the top of the bearing walls which support the joists. In this embodiment, deck support angles may be utilized and affixed near the top of the perpendicular walls, to receive and support the floor decking Both such sets of brackets, in combination with the joist system and bracing, support the floor decking and the subsequently poured slab.
- In both of the foregoing embodiments, and in contrast to conventional platform framing, the decking is suspended from, rather than resting upon, the load bearing walls.
- Building constructions typically require the addition of reinforced bracing members. As currently used and produced, conventional flat light gauge steel strapping is quite elastic, unstable when handled improperly, and is subject to damage because it cannot support its own weight when held horizontally. Currently, it requires two carpenters to stretch flat strapping across floor and roof joists.
- A further unique element of the present system is stiffened strapping for lateral or diagonal bracing. Light gauge steel strapping may be stiffened by forming one or more continuous stiffening impressions, or beads, parallel to the long dimension of the strap. Stiffening impressions, such as flutes, enable the strapping to be easily handled. The flutes greatly add to the rigidity and structural properties of the strapping.
- The stiffened strapping provided herein may be used in a wide variety of applications requiring enhanced reinforcement. It is particularly useful in the subject express framing construction method where, when installed below the suspended joists and secured thereto, it serves to prevent swaying and twisting of the hanging joists.
- The stiffened strapping may be used for lateral or diagonal bracing and is preferably formed from a coil of steel, which is preferably galvanized steel conforming to the requirements of ASTM A 653, having a yield strength of 33 or 50 ksi and a minimum of G-60 galvanized coating. For convenience in handling, the steel coil is decoiled and flattened by conventional means before the stiffening impressions are imparted.
- The stiffening impressions may be applied to any length of coil but generally the dimensions of the strapping will be selected in accordance with the specified construction requirements and ease of handling. A typical installation will utilize 12 foot lengths of stiffened strapping having dimensions of about 2 in width and thickness of 54 mils (16 gauge). In other applications, lengths from about 2 in to 30 feet may be used as required and the width of the strapping may vary from about 1.5 in to 12 in while the thickness may vary from about 30 to 70 mils.
- One or more stiffening impressions are imparted to the web by conventional mechanical metal pressing, rolling or stamping. Hot or cold methods may be utilized as appropriate.
- The preferred stiffening impressions are flute-shaped impressions, but other shapes may be utilized depending upon the chosen methods of fabrication. It should be possible, for example, to create a v-shaped stiffening impression which ought to function similarly in appropriate applications. All such shapes and channels effective for stiffening the strapping are contemplated for use as the stiffening impressions. The preferred flute-shaped stiffening impressions are generally semi-circular in shape since an arc is readily impressed during fabrication.
- The flutes are generally centered along the length of the strapping, or symmetrically oriented from the center line when more than a single flute is utilized. It will be recognized, however, that the stiffening flutes may be offset from the center if a larger flat edge of the strapping is required for some other function, such as securing an edge along its length.
- A single stiffening impression such as a flute can be effective in some applications, especially less critical applications or where strapping lengths are minimized. Three or more stiffening impressions can be used for longer lengths of stiffened strapping or where applications will benefit from additional stiffening strength. In the subject express framing construction system, a pair of parallel flutes was impressed upon the stiffened strapping and these were found to be satisfactory.
- The stiffened strapping can be readily cut to order in the fabricator's shop and transported in flat bundles to a worksite. At the worksite, the stiffened strapping is readily installed using conventional fasteners including machine and metal screws, bolts, etc. Rivets could be utilized but are no longer a popular choice.
-
FIG. 1 illustrates a concrete ormasonry foundation 1A having aflat surface 1 upon which load bearing walls are to be erected. An outline of the location of an alternative steel beam bearing 2 is also indicated by the dotted lines. -
FIG. 2 depicts panelizedload bearing walls 5 comprised ofsteel stud framing 6 and sheathing panels erected onsurface 1 offoundation 1A. -
FIG. 3 illustrates a rigid suspended slabjoist support bracket 8 having an inverted L-shape, and includes a welded-thereto joist stirrup 9 to receive the joists. Thejoist stirrup 9 is generally U-shaped, as detailed inFIG. 5 . Thebracket 8 also includespre-drilled holes 10, while a rear edge ofbracket 8 is denoted as 11. The horizontal width of the top surface ofbracket 8 is denoted as 12 and matches the upper load bearing surface of a wall upon which it is installed. The downward width ofbracket 8 is denoted as 13 and varies with the desired depth of the poured slab flooring. In this figure, the on-center distance between later-installed studs is denoted as 14. The bracket is fastened to thee vertical studs with screws throughpre-drilled holes 10. -
FIG. 4 illustrates a rigid suspended slabdeck support bracket 20 which is generally Z-shaped, and which receives the edges of the deck sheathing and forms a seal for the later poured concrete slab. Slabdeck support bracket 20 includespre-drilled holes 21. The later-installed stud on-center distance is denoted as 22. A horizontal rear edge ofbracket 20 is denoted as 23. The slabdeck support bracket 20, placed atop a wall parallel to the joists, has a first or upper horizontal edge orwidth 24, avertical edge 25, and a second or lower horizontal edge orwidth 27.Deck support lip 26 lies in a horizontal plane. -
FIG. 5 is a detail of ajoist support stirrup 9 ofFIG. 3 .Reference numeral 9 denotes a joist stirrup which in this embodiment has typical dimensions of 4 in by 3 in by 2.5 in. Reference numeral 9 a denotes either of two vertical side portions, while 9 c denotes a flat, cantilever portion. Pre-drilled attachment holes 10 are in a vertical portion of 8, while thestirrup 9 is welded at 30 to provide a slab joist support. Crimped reinforcingribs 32 are provided on the outside walls ofstirrup 9. Pre-drilled,elongated holes 33 are provided at the bottom, flat portion of the stirrup. -
FIG. 6 illustrates several suspended slabjoist support brackets 8 installed in pairs opposite each other, atop parallel load bearing walls, and also includes several suspended slabdeck support brackets 20 installed perpendicular to the slab joist support brackets and atop the remaining walls which run lengthwise. -
FIG. 7 illustratesseveral joist assemblies 40 installed between the suspended slabjoist support brackets 8, the joist ends resting inrespective stirrups 9. Each joist may include a lower strut 40a such as may be utilized for supporting a suspended ceiling or to affix reinforcing bracing. The bracing may be stiffened strapping described herein. -
FIG. 8 illustrates several diagonal bracingmembers 55 reinforcing the structure before a deck and concrete slab are installed. Such bracing is preferably stiffened strapping which is fastened toconventional clip angle 50. -
FIG. 9 illustrates additional reinforcement with lateral bracing 60, the latter attached to respective pairs ofopposite walls 5. Again, the preferred bracing is stiffened strapping. -
FIG. 10 illustrates decking 65 which is usually corrugated metal decking and which is installed atop underlying joists and which will receive a poured slab on top thereof. The decking is peripherally surrounded byslab joist brackets 8 and slabdeck support brackets 20 to create a form or mold for the poured slab deck. The concrete may be poured at any convenient time ondecking 65. -
FIG. 11 illustrates the construction of a second story 67A atop a lower load bearingfirst story 67. The first and second stories are comprised ofwall sections Decking 65 is ready to receive concrete to form a poured slab deck. The illustrated second or upper story 67A utilizes steel stud framing 6A interior to the sheathing panels which together comprise the load bearing wall construction which supports any subsequent stories. -
FIG. 12 is a cross-section of the suspended slabjoist support bracket 8, taken along 12-12 ofFIG. 11 , installed betweenlower wall 70 and upper wall 70a and secured withscrew fasteners 71. For clarity, seams 75A and 76A are exaggerated.Fluted metal decking 65 supports pouredconcrete deck slab 66. An end of ajoist 40 is inserted intojoist stirrup 9 and secured with bolt, nut andwasher assembly 73. One end ofjoist 40 is supported by cantilever portion 9c ofstirrup 9. -
FIG. 13 is a cross-section detail of the suspendedslab deck support 20 installed between lowerlight gauge wall 72 and upper light gauge wall 72a and secured through wall tracks 77 and 78 withscrew fasteners 71.Seams 77A and 78A are exaggerated for clarity. It will be noted that the suspendedslab deck support 20 andwalls 72 and 72a depicted inFIG. 13 are perpendicular towalls 70 on 70a and suspendedslab joist support 8 illustrated inFIG. 12 . Also depicted inFIG. 13 isconcrete decking slab 66 poured atopmetal decking 65. -
FIG. 14 depicts a cross-section of a stiffened reinforcement strapping 80, the latter provided with continuous and parallel stiffening impressions which in this embodiment areflutes FIG. 8 and lateral bracing 60 inFIG. 9 . The strapping width in this figure has a width of about 2 inches.FIG. 14A is a perspective view of the stiffened reinforcement strapping 80, further illustrating its parallel strengthening flutes, 81 and 82.Holes 85 may be used to fasten the stiffened strapping. -
FIG. 15 is a detail depicting the attachment of lateral bracing 80 to clipangle 50. Diagonal bracing is similarly attached.Fasteners 71 pass through preformed openings to secure the bracing to the angle. Conventional fasteners, clip angles, screws and the like are selected as may be appropriate in a given application. -
FIG. 16 is a detail perspective depicting installation of an interior-type suspended slabjoist saddle bracket 83 installed atop an interiorload bearing wall 84. The saddle bracket may be a single, symmetrical unit or may be comprised of a pair of symmetrical half-units as illustrated inFIGS. 16 and 17 . In either case, joists hang on opposite sides of interiorload bearing wall 84. The joists are herein depicted withstruts 79 and lower joist tracks 40A. -
FIG. 17 is a cross-section showing symmetrical interior suspendedjoist saddle brackets 83 installed atop an interiorload bearing wall 84. It will be observed thatlower wall 84 andupper wall 84A ofFIG. 17 are substantially coplanar. That is, each lies in the same vertical plane. This also the case forwalls FIG. 12 , and forwalls FIG. 13 . InFIG. 17 ,joists 40 are secured tobrackets 83 by nut andbolt assemblies 73.Corrugated decking 65 and pouredslab 66 are shown.Bearing walls tracks screw fasteners 71. - In an alternative embodiment of the present invention, the suspended slab joist support brackets described above may be replaced with joist support angle brackets.
FIG. 18 is a perspective view of a joistsupport angle bracket 100 havingholes 102 for fastening a joist tobracket 100, typically via a bolt, nut and washer assembly. In the figure,bracket 100 also has holes for fastening the bracket to the top track of a bearing wall or stud.Holes 104 may receive bolts or other fasteners but will typically utilize screws for securingbrackets 100 to the track or studs. -
FIG. 19 is a perspective view of an alternative reinforced joistsupport angle bracket 101 additionally having reinforcingmember 101A. Reinforcingmember 101A is typically a metal wedge welded in placed or forged in the initial fabrication of the bracket. -
FIG. 20 is an elevation view of joistsupport angle bracket 100 installed withfasteners 140 on left and rightstud framing members fasteners 140 may be metal screws. In this figure, left and right portions of ajoist section support angle bracket 100 by nut, bolt andwasher assemblies - Construction details for installation of a joist support angle bracket and related assemblies are shown in
FIG. 21 . Joistsupport angle bracket 100, shown in cross-section, is installed on lower wallstud framing member 110 and secured thereon byfasteners 140. The vertical portion of this bracket may be a 4 in by 5 in flange which attaches to the studs with six 5/16th in screws. The horizontal joist ledger portion of the bracket can attach the joist seat with ½ in bolts which are 3½ in on-center. In this detail,joist members support angle bracket 100 bybolt 130 havingbolt head 138,washers corrugated decking 156 is shown atopjoist portion 154. In this figure,concrete decking slab 158 has been poured atopdeck sheathing 156. - In this construction,
lower framing member 110 is capped withupper rail 111 shown in cross-section and supports upper framingmember 112 and its associatedlower rail 113. These framing members are preferably metal framing studs having conventional framing hardware. These upper and lower members are securely fastened, as byscrews 114. In this figure,exaggerated seam 119 is shown only for clarity between the sections. In practice, the seam is eliminated when the upper and lower sections are secured together. Lower andupper sheathing panels Sheathing panels - Construction details for installation of a deck support angle and related assemblies are shown in
FIG. 22 .Deck support angle 160, shown in cross-section, is installed onlower wall 110′ and secured thereon byfasteners 145 which may be metal screws. In this detail, decking 162 is shown in cross-section. The suspended slab deck support angle is continuous conventional angle, e.g. 3 in by 3 in, trimmed to suitable lengths for ease of handling and effective for supporting the edge of the suspended decking and acting as a pour stop for the concrete floor. The decking is secured todeck support angle 160 byfastener 145. In this figure,concrete decking slab 158 has been poured atopdeck sheathing 162. In this construction, as inFIG. 21 ,lower framing member 110′ is capped withupper rail 111′ shown in cross-section and which supports upper framingmember 112′ and its associatedlower rail 113′. These upper and lower members are securely fastened, as byscrews 114. In this figure,exaggerated seam 147 is shown only for clarity between the sections. In practice, the seam is tight and essentially eliminated as the upper and lower sections are secured together. Lower andupper sheathing panels 116′ and 118′ are here depicted in cross section on the vertical wall panel opposite thedecking 162 anddeck support bracket 160. In this embodiment,sheathing panels 116′ and 118′ are gypsum board. Once again it will be understood that the concrete slab decking is poured up to the wall members, but not between them as is the case in prior art constructions. -
FIG. 23 is a cross-section of a prior art platform framing construction including exterior sheathing a, an upper load bearing wall b, a lower load bearing wall c, a concrete deck d, a joist hanger e, and a joist f. It is noteworthy that in such a construction, the poured slab floor d is located between the upper and lower load bearing walls b and c and therefore must be installed prior to construction of the upper walls.FIG. 23 shows that each concrete floor d must be poured and set prior to the formation of the next and, above, story. In stark contrast, the present invention permits all of the concrete floors to be poured at the same time, or as may be optimally desired. - The express framing system provides buildings comparable to those provided by other light gauge steel methods, such as the aforementioned platform framing technique. For example, such a building may have one or more load bearing quadrilaterals of about 100 ft by 100 ft. In such a building, an interior load bearing quadrilateral section might then be 50 ft by 100 ft. The typical height per story is 10 ft. The typical number of stories is 2 to 4, with 6 stories being the maximum for this type of light gauge steel mid-rise construction. Additionally, the joists run either lengthwise or widthwise, as the structure design dictates.
- Specifications for construction members and hardware are typical of light gauge steel framing techniques. The preferred grades of steel vary with the parts and application. For example, the specification for joists, joist brackets, decking hangers, decking, support fixtures and other rolled structural steel shapes is ASTM A572. The specification for structural steel plates and items made from such plates is ASTM A36. The specification for structural steel tubes is A500 Gr. B. The specification for cold formed light gauge steel, used for the stiffened strapping, is ASTM A653 with yield strength of 33 ksi or 50 ksi, and galvanized to a G-60 coating as per ASTM C955. The specification for bolts, joints, fittings, etc. is ASTM A325 TC, with hardened nuts & washers. In typical applications, any grade or type of concrete slab would be suitable.
Claims (32)
1. A method of erecting a building, comprising the steps of locating vertically extending and oppositely facing walls to form a set of joist supporting walls of a building, said joist supporting walls having upper, load bearing surfaces; placing oppositely located rigid suspended slab joist supporting brackets on said wall upper surfaces; placing the ends of generally horizontal extending joists on said rigid suspended slab joist supporting brackets;
and placing a sheet of slab decking on top of said joists, whereby said decking is supported by said joists and whereby the weight of said decking is borne by said joist supporting walls.
2. The method of claim 1 including the additional step of locating a pair of oppositely placed rigid suspended slab deck support brackets on top of a pair of vertically extending and oppositely facing walls which are perpendicular to said joist supporting walls and suspended slab joist supporting brackets.
3. The method of claim 1 including the additional step of bracing the wall and joist assemblies to reinforce and rigidify said assemblies and thereby inhibit relative twisting or warping by wind or other forces.
4. The method of claim 3 wherein said bracing is reinforcing stiffened strapping.
5. The method of claim 1 including the additional step of pouring a layer of concrete on top of said decking to thereby form a floor for the building.
6. The method of claim 1 wherein at least one joist supporting wall is an exterior load bearing wall.
7. The method of claim 1 wherein at least one joist supporting wall is an interior load bearing wall supporting symmetrical joist supporting brackets on opposite sides of said interior wall.
8. The method of claim 1 including the additional step of erecting a subsequent assembly of load bearing walls, suspended slab joist and deck support brackets and suspended slab decking prior to the pouring of one or more concrete slab floors.
9. A building constructed according to the method of claim 1 .
10. A method of erecting a building, including the steps of locating vertically extending and oppositely facing walls to form a set of joist supporting walls of a building, said joist supporting walls having upper load bearing locations for affixing oppositely located rigid joist support angle brackets on said walls, placing the ends of generally horizontal extending joists on said rigid joist support angle brackets, placing a sheet of suspended slab decking on top of said joists, whereby said decking is supported by said joists and whereby the weight of said decking is borne by said joist supporting walls.
11. The method of claim 10 including the additional step of locating a pair of oppositely placed rigid slab deck support angles parallel to said joists on vertically extending and oppositely facing walls which are perpendicular to said joist supporting walls and joist support angles.
12. The method of claim 10 including the additional step of bracing the wall and joist assemblies to reinforce and rigidify said assemblies and thereby inhibit relative twisting or warping by wind or other forces.
13. The method of claim 12 wherein said bracing is reinforcing stiffened strapping.
14. The method of claim 10 including the additional step of pouring a layer of concrete on top of said decking to thereby form a floor for the building.
15. The method of claim 10 wherein at least one joist supporting wall is an exterior load bearing wall.
16. The method of claim 10 wherein at least one joist supporting wall is an interior load bearing wall supporting symmetrical pairs of joist supporting angle brackets on opposite sides of said interior wall.
17. The method of claim 10 including the additional step of erecting a subsequent assembly of load bearing walls, joist support angle brackets, deck support angles and suspended slab decking prior to the pouring of one or more concrete slab floors.
18. A building constructed according to the method of claim 10 .
19. The method of claim 1 wherein said slab floor is eccentrically suspended from said load bearing walls by means of a cantilevered support bracket.
20. A method of producing stiffened strapping for use in construction methods requiring reinforcement, comprising the steps of de-coiling and flattening a work piece of unstiffened metal strapping and applying at least one stiffening impression upon the surface of said work piece, thereby forming a stiffening impression along the length of said work piece.
21. A method as in claim 20 wherein said stiffening impression is a flute-shaped impression having a concave arc-shaped impression on one surface of said stiffened strapping and a complementary convex arc-shaped impression on the opposite side of said stiffened strapping.
22. A method as in claim 20 wherein said stiffening impression is a v-shaped impression having a concave v-shaped impression on one surface of said stiffened strapping and a complementary convex v-shaped impression on the opposite side.
23. A method as in claim 20 wherein said stiffening impression is applied along the centerline of said stiffened strapping work piece.
24. A method as in claim 20 wherein two or more stiffening impressions are applied symmetrically along the centerline of said stiffened strapping work piece.
25. A method as in claim 24 wherein a pair of parallel stiffening flutes are symmetrically disposed from the center line along the length of said stiffened strapping.
26. A method as in claim 20 wherein one or more stiffening impressions are applied parallel to and offset from said centerline of said stiffened strapping work piece.
27. A method as in claim 20 wherein said stiffening impressions are mechanically applied to said work piece by devices selected from the group consisting of stamping, roll-forming and pressing devices.
28. A method as in claim 20 wherein said stiffened strapping is fabricated from a roll of steel strapping.
29. A method as in claim 20 wherein said steel strapping has a galvanized coating.
30. A method as in claim 20 wherein the stiffened strapping has a length of approximately 2 inches to 30 ft, a width of approximately 1.5 to 12 in and a thickness of approximately 30 to 70 mils.
31. A method as in claim 20 , including the additional steps of installing said stiffened strapping in a construction assembly requiring reinforcement; and fastening said stiffened strapping to said construction members to minimize unintended movement.
32. Stiffened strapping made in accordance with the method of claim 20 .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US13/568,091 US20120291378A1 (en) | 2005-09-01 | 2012-08-06 | Express framing system |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US71345505P | 2005-09-01 | 2005-09-01 | |
US11/469,528 US8234827B1 (en) | 2005-09-01 | 2006-09-01 | Express framing building construction system |
US13/568,091 US20120291378A1 (en) | 2005-09-01 | 2012-08-06 | Express framing system |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US11/469,528 Division US8234827B1 (en) | 2005-09-01 | 2006-09-01 | Express framing building construction system |
Publications (1)
Publication Number | Publication Date |
---|---|
US20120291378A1 true US20120291378A1 (en) | 2012-11-22 |
Family
ID=46583113
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US11/469,528 Expired - Fee Related US8234827B1 (en) | 2005-09-01 | 2006-09-01 | Express framing building construction system |
US13/568,091 Abandoned US20120291378A1 (en) | 2005-09-01 | 2012-08-06 | Express framing system |
Family Applications Before (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US11/469,528 Expired - Fee Related US8234827B1 (en) | 2005-09-01 | 2006-09-01 | Express framing building construction system |
Country Status (1)
Country | Link |
---|---|
US (2) | US8234827B1 (en) |
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103866856A (en) * | 2014-03-20 | 2014-06-18 | 北京工业大学 | Center support occlusion splicing system of assembly type steel structure with rigid-connection nodes |
CN105735648A (en) * | 2016-03-10 | 2016-07-06 | 中国五冶集团有限公司 | Multi-segment formwork set-up casting construction process of steel reinforced concrete coal hopper for house of main workshop of power plant |
CN109138428A (en) * | 2018-08-17 | 2019-01-04 | 中国人民解放军63926部队 | A kind of launching workplace diversion trench refractory concrete protective layer construction method |
US20190218811A1 (en) * | 2014-08-30 | 2019-07-18 | Innovative Building Technologies, Llc | Diaphragm to lateral support coupling in a structure |
US10676923B2 (en) | 2016-03-07 | 2020-06-09 | Innovative Building Technologies, Llc | Waterproofing assemblies and prefabricated wall panels including the same |
US10724228B2 (en) | 2017-05-12 | 2020-07-28 | Innovative Building Technologies, Llc | Building assemblies and methods for constructing a building using pre-assembled floor-ceiling panels and walls |
EP3757304A1 (en) | 2019-06-27 | 2020-12-30 | Proruper, Unipessoal, Lda | Modular construction system |
US10900224B2 (en) | 2016-03-07 | 2021-01-26 | Innovative Building Technologies, Llc | Prefabricated demising wall with external conduit engagement features |
US10961710B2 (en) | 2016-03-07 | 2021-03-30 | Innovative Building Technologies, Llc | Pre-assembled wall panel for utility installation |
CN112681331A (en) * | 2020-12-03 | 2021-04-20 | 中国建筑第八工程局有限公司 | Steel support and steel trestle integrated structure and construction method thereof |
US11054148B2 (en) | 2014-08-30 | 2021-07-06 | Innovative Building Technologies, Llc | Heated floor and ceiling panel with a corrugated layer for modular use in buildings |
US11060286B2 (en) | 2014-08-30 | 2021-07-13 | Innovative Building Technologies, Llc | Prefabricated wall panel for utility installation |
US11098475B2 (en) | 2017-05-12 | 2021-08-24 | Innovative Building Technologies, Llc | Building system with a diaphragm provided by pre-fabricated floor panels |
US11898351B2 (en) | 2018-10-10 | 2024-02-13 | Nucor Corporation | Joist tie used in structural decking systems and method of installing |
US11913180B1 (en) * | 2023-05-10 | 2024-02-27 | TX Bridge Robotics, INC. | Bridge construction method and bridge |
Families Citing this family (21)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US8234827B1 (en) * | 2005-09-01 | 2012-08-07 | Schroeder Sr Robert | Express framing building construction system |
US8272806B2 (en) * | 2008-01-22 | 2012-09-25 | Ford Contracting, Inc. | Panel connector |
US8661755B2 (en) * | 2008-01-24 | 2014-03-04 | Nucor Corporation | Composite wall system |
WO2011155992A1 (en) | 2010-06-08 | 2011-12-15 | Collins Arlan E | Lift-slab construction system and method for constructing multi-story buildings using pre-manufactured structures |
US8950132B2 (en) | 2010-06-08 | 2015-02-10 | Innovative Building Technologies, Llc | Premanufactured structures for constructing buildings |
CN103510618A (en) * | 2013-10-24 | 2014-01-15 | 华煜建设集团有限公司 | Cantilever beam support structure |
CN103790231A (en) * | 2014-01-24 | 2014-05-14 | 成都常民世纪建筑科技有限公司 | Light steel roof truss with continuous structural beams |
US11713576B2 (en) * | 2014-01-24 | 2023-08-01 | Ying Chun Hsieh | Three-dimensional lightweight steel framing system formed by bi-directional continuous double beams |
EP3186454B1 (en) | 2014-08-30 | 2021-01-20 | Innovative Building Technologies LLC | Prefabricated demising walls |
CN105593448B (en) * | 2014-08-30 | 2017-06-09 | 创新建筑科技公司 | Interface between floor panel and panelling track |
US9279244B1 (en) * | 2014-10-27 | 2016-03-08 | Travis Miller | Apparatus for supporting stay-in-place metal decking forms |
US9556606B2 (en) * | 2014-10-27 | 2017-01-31 | Travis Miller | Apparatus for supporting stay-in-place metal decking forms |
US10584485B2 (en) * | 2016-02-22 | 2020-03-10 | Vega Building Systems Llc | Constructing multi-story buildings using stacked structural steel wall trusses |
SG11201807193UA (en) | 2016-03-07 | 2018-09-27 | Innovative Building Technologies Llc | Floor and ceiling panel for slab-free floor system of a building |
US9932735B1 (en) * | 2017-05-02 | 2018-04-03 | Joey Biasucci | Header board bracket |
US10323428B2 (en) | 2017-05-12 | 2019-06-18 | Innovative Building Technologies, Llc | Sequence for constructing a building from prefabricated components |
US10487493B2 (en) | 2017-05-12 | 2019-11-26 | Innovative Building Technologies, Llc | Building design and construction using prefabricated components |
US10202759B2 (en) * | 2017-05-19 | 2019-02-12 | Hilti Aktiengesellschaft | Dynamic, fire-resistance-rated thermally insulating and sealing system having a F-rating of 120 min for use with curtain wall structures |
CN109811665A (en) * | 2019-02-03 | 2019-05-28 | 中交路桥华南工程有限公司 | The installation method of assembled heavy type steel corbel |
CA3145826A1 (en) * | 2019-07-15 | 2021-01-21 | Intelligent City Inc. | Facade panel with integrated window system |
GB202117649D0 (en) * | 2021-12-07 | 2022-01-19 | Sigmat Ltd | A floor tie |
Citations (84)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US136947A (en) * | 1873-03-18 | Improvement in floor-timber supports | ||
US526302A (en) * | 1894-09-18 | Continuous metal joist-support | ||
US529331A (en) * | 1894-11-13 | Hanger | ||
US1053127A (en) * | 1912-09-11 | 1913-02-11 | John F Golding | Process of constructing concrete floors and ceilings. |
US1789827A (en) * | 1926-10-18 | 1931-01-20 | P E Selby Inc | Building construction |
US1858701A (en) * | 1929-07-25 | 1932-05-17 | Armstrong Cork Co | Building construction |
US2272910A (en) * | 1940-04-22 | 1942-02-10 | Thomas J Boodell | Sheet metal building construction |
US2321221A (en) * | 1940-11-18 | 1943-06-08 | Irvin D Linehan | Joist anchoring bracket |
US3392499A (en) * | 1966-05-02 | 1968-07-16 | Ira J. Mcmanus | Steel joist connection |
US3420560A (en) * | 1966-05-23 | 1969-01-07 | Jerome E Pfahning | Masonry wall joist hanger |
US3513610A (en) * | 1966-02-26 | 1970-05-26 | Trent Concrete Ltd | Concrete structural member,framework structure,and casting method |
US3623755A (en) * | 1969-06-27 | 1971-11-30 | George D Ratliff Jr | Joist hanger |
US3675385A (en) * | 1970-02-16 | 1972-07-11 | Metallic Building Co | Method of constructing parking garage structures |
US3714304A (en) * | 1969-12-29 | 1973-01-30 | F Anderson | Building construction |
US3837135A (en) * | 1972-05-25 | 1974-09-24 | A Zachman | Combined joist and reinforcing bar holder and structure formed therewith |
US4014089A (en) * | 1975-02-21 | 1977-03-29 | Kajima Corporation | Method of connecting beams and columns of steel frame construction |
US4038796A (en) * | 1975-12-23 | 1977-08-02 | Eckel Industries, Inc. | Wall panel assembly |
US4074947A (en) * | 1974-08-12 | 1978-02-21 | Hitachi Metals, Ltd. | Fittings for connecting columns and beams |
US4075810A (en) * | 1976-05-06 | 1978-02-28 | Dominion Foundries And Steel, Limited | Metal wall construction for buildings |
US4078347A (en) * | 1976-05-06 | 1978-03-14 | Dominion Foundries And Steel, Limited | Metal wall construction for buildings |
US4223866A (en) * | 1977-05-10 | 1980-09-23 | Brown Company | Adjustable bracket |
US4276730A (en) * | 1979-07-02 | 1981-07-07 | Lewis David M | Building wall construction |
US4296048A (en) * | 1980-04-01 | 1981-10-20 | Sim William J | Support bracket for distribution panel for cooling towers and the like |
US4341051A (en) * | 1980-04-01 | 1982-07-27 | Sim William J | Building structure and process of beam assembly therein |
US4347015A (en) * | 1980-11-03 | 1982-08-31 | General Electric Company | Structural frame corner assembly for electrical switchboards and the like |
US4349491A (en) * | 1980-03-25 | 1982-09-14 | Eyden Everett A | Method for forming a concrete deck |
US4422792A (en) * | 1982-08-16 | 1983-12-27 | Simpson Strong-Tie Company, Inc. | Gusset metal ledger hanger |
US4527372A (en) * | 1983-04-26 | 1985-07-09 | Cyclops Corporation | High performance composite floor structure |
US4594017A (en) * | 1985-06-17 | 1986-06-10 | Altech Industries, Inc. | Joist hanger and blank therefor |
US4879856A (en) * | 1987-10-29 | 1989-11-14 | Bpb Industries Public Limited Company | Floor system |
US4893961A (en) * | 1989-06-05 | 1990-01-16 | Trus Joist Corporation | Joist hanger |
US4920725A (en) * | 1989-02-14 | 1990-05-01 | Truswal Systems Corporation | Self-gripping hanger device |
US4982548A (en) * | 1989-08-17 | 1991-01-08 | Abbey Jay E | Beam hanger for precast foundations |
US5058352A (en) * | 1990-10-01 | 1991-10-22 | Loiselle Scot D | Barrier system |
US5063718A (en) * | 1990-05-28 | 1991-11-12 | Al Nonis | Curtain wall for a building |
US5195293A (en) * | 1990-03-15 | 1993-03-23 | Digirolamo Edward R | Structural system for supporting a building utilizing light weight steel framing for walls and hollow core concrete slabs for floors and method of making same |
US5367853A (en) * | 1992-11-06 | 1994-11-29 | Bryan; Robert | Prefabricated deck system |
US5551135A (en) * | 1994-05-25 | 1996-09-03 | Powers, Iii; John | Method of fabricating a metal purlin and method of fabricating a building therewith |
US5887405A (en) * | 1994-09-22 | 1999-03-30 | Carranza-Aubry; Rene | Precast integral structure elements and procedure for the fast construction of buildings with such elements |
US5934036A (en) * | 1996-11-01 | 1999-08-10 | Gallagher, Jr.; Daniel P. | Insulated concrete slab assembly |
US5956910A (en) * | 1997-11-03 | 1999-09-28 | Sommerstein; Michael | Panel mounting structure |
US5979130A (en) * | 1996-10-10 | 1999-11-09 | Simpson Strong-Tie Company, Inc. | Connector with concave seat |
US6073405A (en) * | 1995-12-22 | 2000-06-13 | Icf Kaiser Engineers, Inc. | Fitting for effecting bolted connection between a beam and a column in a steel frame structure |
US6131358A (en) * | 1997-08-29 | 2000-10-17 | Wise; Michael A. | Joist hanger and installation method |
US6145268A (en) * | 1998-12-18 | 2000-11-14 | Korzen; Thomas G. | Apparatus and method for providing a reinforced roof truss |
US6311449B1 (en) * | 1999-08-06 | 2001-11-06 | Michael G. Morse | Securing decks to houses with “L”-shaped brackets |
US6332303B1 (en) * | 2000-02-28 | 2001-12-25 | Nic Engineering Co., Ltd. | Method of building underground structure |
US6397552B1 (en) * | 1999-07-23 | 2002-06-04 | Michael Bourque | Deck attachment bracket and method of attaching a deck to a building |
US20020078646A1 (en) * | 2000-10-16 | 2002-06-27 | Eaton Peter Francis | Suspended concrete flooring system and method |
US6463711B1 (en) * | 1999-08-09 | 2002-10-15 | United Steel Products Company, Inc. | Construction hanger |
US6470644B2 (en) * | 1998-10-19 | 2002-10-29 | Varco Pruden Technologies, Inc. | Roof bracket |
US6505450B1 (en) * | 1997-10-29 | 2003-01-14 | Reginald A. J. Locke | Masonry reinforcement system |
US20030033764A1 (en) * | 2001-08-20 | 2003-02-20 | Ting Raymond M.L. | Mullion splice joint design |
US6612087B2 (en) * | 2000-11-29 | 2003-09-02 | The Steel Network, Inc. | Building member connector allowing bi-directional relative movement |
US20040129845A1 (en) * | 2001-05-19 | 2004-07-08 | Whale Luke John Richard | Hanger device |
US20060016138A1 (en) * | 2005-07-22 | 2006-01-26 | Michael Blount | EZ bar |
US20060016139A1 (en) * | 2003-04-14 | 2006-01-26 | Beck John R | Wall and floor construction arrangements and methods |
US7055289B2 (en) * | 2003-04-14 | 2006-06-06 | Masonry Technology, Inc. | System and method for forming a structural connection |
US20060230697A1 (en) * | 2003-02-25 | 2006-10-19 | James Lupton | Deck structure |
US20060260261A1 (en) * | 2003-06-05 | 2006-11-23 | Jozef Cervenko | System for fasterning linings |
US20070186503A1 (en) * | 2006-02-10 | 2007-08-16 | Yoichi Homma | Construction framing system and method |
US20070204540A1 (en) * | 2006-03-03 | 2007-09-06 | Specified Technologies Inc. | Means and method for fireproof sealing between the peripheral edge of individual floors of a building and the exterior wall structure thereof |
US7299596B2 (en) * | 2004-04-21 | 2007-11-27 | John Hildreth | Framing system |
US20070289230A1 (en) * | 2006-06-15 | 2007-12-20 | Schroeder Robert Sr | Bracing For Shear Wall Construction |
US20080022624A1 (en) * | 2006-07-25 | 2008-01-31 | Hanson Courtney J | Joist support |
US20080115447A1 (en) * | 2004-08-12 | 2008-05-22 | Morse Michael G | Method of connecting post to joist |
US7389620B1 (en) * | 2004-08-19 | 2008-06-24 | Mcmanus Ira J | Composite pan for composite beam-joist construction |
US20080163568A1 (en) * | 2003-09-25 | 2008-07-10 | Shelton David R | Wooden member support retrofit system and method |
US7424793B1 (en) * | 2004-05-07 | 2008-09-16 | Thermafiber, Inc. | Interlocking curtain wall insulation system |
US20080236090A1 (en) * | 2007-04-02 | 2008-10-02 | Liberman Barnet L | Modular building structures |
US7497054B2 (en) * | 2001-06-06 | 2009-03-03 | Nippon Steel Corporation | Column-and-beam join structure |
US20090139176A1 (en) * | 2007-11-26 | 2009-06-04 | Schroeder Sr Robert | Slotted Tabbed Rim Track and Building Method |
US7716899B2 (en) * | 2003-04-14 | 2010-05-18 | Dietrich Industries, Inc. | Building construction systems and methods |
US7788878B1 (en) * | 2008-04-03 | 2010-09-07 | The Steel Network, Inc. | Device and method for bracing a wall structure |
US7827757B2 (en) * | 2005-02-28 | 2010-11-09 | Playcore Wisconsin, Inc. | Brackets and bracket system for assembling playground equipment |
US20100293872A1 (en) * | 2007-01-18 | 2010-11-25 | Stephen Kennedy | flooring panels and connectors |
US7845138B2 (en) * | 2004-06-11 | 2010-12-07 | Op-Deck Holdings B.V. | Method for the production of a building construction as well as formwork therefor |
US7992352B2 (en) * | 1999-12-21 | 2011-08-09 | Bonds Delton J | Modular building frame |
US8028494B2 (en) * | 2007-04-12 | 2011-10-04 | Denmay Steel | Sleeve connectors for metal girders |
US8209924B2 (en) * | 2009-11-12 | 2012-07-03 | The Foley Group, LLC | Connector system for securing an end portion of a steel structural member to a vertical cast concrete member |
US8234827B1 (en) * | 2005-09-01 | 2012-08-07 | Schroeder Sr Robert | Express framing building construction system |
US8234826B1 (en) * | 2006-06-15 | 2012-08-07 | Proffitt Jr Ray A | Hold down clip |
US8490341B2 (en) * | 2010-09-09 | 2013-07-23 | Michael Hatzinikolas | Self-releasing structural assembly |
US8490340B2 (en) * | 2010-09-09 | 2013-07-23 | Michael Hatzinikolas | Self-releasing structural assembly |
-
2006
- 2006-09-01 US US11/469,528 patent/US8234827B1/en not_active Expired - Fee Related
-
2012
- 2012-08-06 US US13/568,091 patent/US20120291378A1/en not_active Abandoned
Patent Citations (92)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US136947A (en) * | 1873-03-18 | Improvement in floor-timber supports | ||
US526302A (en) * | 1894-09-18 | Continuous metal joist-support | ||
US529331A (en) * | 1894-11-13 | Hanger | ||
US1053127A (en) * | 1912-09-11 | 1913-02-11 | John F Golding | Process of constructing concrete floors and ceilings. |
US1789827A (en) * | 1926-10-18 | 1931-01-20 | P E Selby Inc | Building construction |
US1858701A (en) * | 1929-07-25 | 1932-05-17 | Armstrong Cork Co | Building construction |
US2272910A (en) * | 1940-04-22 | 1942-02-10 | Thomas J Boodell | Sheet metal building construction |
US2321221A (en) * | 1940-11-18 | 1943-06-08 | Irvin D Linehan | Joist anchoring bracket |
US3513610A (en) * | 1966-02-26 | 1970-05-26 | Trent Concrete Ltd | Concrete structural member,framework structure,and casting method |
US3392499A (en) * | 1966-05-02 | 1968-07-16 | Ira J. Mcmanus | Steel joist connection |
US3420560A (en) * | 1966-05-23 | 1969-01-07 | Jerome E Pfahning | Masonry wall joist hanger |
US3623755A (en) * | 1969-06-27 | 1971-11-30 | George D Ratliff Jr | Joist hanger |
US3714304A (en) * | 1969-12-29 | 1973-01-30 | F Anderson | Building construction |
US3675385A (en) * | 1970-02-16 | 1972-07-11 | Metallic Building Co | Method of constructing parking garage structures |
US3837135A (en) * | 1972-05-25 | 1974-09-24 | A Zachman | Combined joist and reinforcing bar holder and structure formed therewith |
US4074947A (en) * | 1974-08-12 | 1978-02-21 | Hitachi Metals, Ltd. | Fittings for connecting columns and beams |
US4014089A (en) * | 1975-02-21 | 1977-03-29 | Kajima Corporation | Method of connecting beams and columns of steel frame construction |
US4038796A (en) * | 1975-12-23 | 1977-08-02 | Eckel Industries, Inc. | Wall panel assembly |
US4075810A (en) * | 1976-05-06 | 1978-02-28 | Dominion Foundries And Steel, Limited | Metal wall construction for buildings |
US4078347A (en) * | 1976-05-06 | 1978-03-14 | Dominion Foundries And Steel, Limited | Metal wall construction for buildings |
US4223866A (en) * | 1977-05-10 | 1980-09-23 | Brown Company | Adjustable bracket |
US4276730A (en) * | 1979-07-02 | 1981-07-07 | Lewis David M | Building wall construction |
US4349491A (en) * | 1980-03-25 | 1982-09-14 | Eyden Everett A | Method for forming a concrete deck |
US4296048A (en) * | 1980-04-01 | 1981-10-20 | Sim William J | Support bracket for distribution panel for cooling towers and the like |
US4341051A (en) * | 1980-04-01 | 1982-07-27 | Sim William J | Building structure and process of beam assembly therein |
US4347015A (en) * | 1980-11-03 | 1982-08-31 | General Electric Company | Structural frame corner assembly for electrical switchboards and the like |
US4422792A (en) * | 1982-08-16 | 1983-12-27 | Simpson Strong-Tie Company, Inc. | Gusset metal ledger hanger |
US4527372A (en) * | 1983-04-26 | 1985-07-09 | Cyclops Corporation | High performance composite floor structure |
US4594017A (en) * | 1985-06-17 | 1986-06-10 | Altech Industries, Inc. | Joist hanger and blank therefor |
US4879856A (en) * | 1987-10-29 | 1989-11-14 | Bpb Industries Public Limited Company | Floor system |
US4920725A (en) * | 1989-02-14 | 1990-05-01 | Truswal Systems Corporation | Self-gripping hanger device |
US4893961A (en) * | 1989-06-05 | 1990-01-16 | Trus Joist Corporation | Joist hanger |
US4982548A (en) * | 1989-08-17 | 1991-01-08 | Abbey Jay E | Beam hanger for precast foundations |
US5195293A (en) * | 1990-03-15 | 1993-03-23 | Digirolamo Edward R | Structural system for supporting a building utilizing light weight steel framing for walls and hollow core concrete slabs for floors and method of making same |
US5063718A (en) * | 1990-05-28 | 1991-11-12 | Al Nonis | Curtain wall for a building |
US5058352A (en) * | 1990-10-01 | 1991-10-22 | Loiselle Scot D | Barrier system |
US5367853A (en) * | 1992-11-06 | 1994-11-29 | Bryan; Robert | Prefabricated deck system |
US5551135A (en) * | 1994-05-25 | 1996-09-03 | Powers, Iii; John | Method of fabricating a metal purlin and method of fabricating a building therewith |
US5657596A (en) * | 1994-05-25 | 1997-08-19 | Powers, Iii; John | Fabricated building with metal purlins |
US5887405A (en) * | 1994-09-22 | 1999-03-30 | Carranza-Aubry; Rene | Precast integral structure elements and procedure for the fast construction of buildings with such elements |
US6073405A (en) * | 1995-12-22 | 2000-06-13 | Icf Kaiser Engineers, Inc. | Fitting for effecting bolted connection between a beam and a column in a steel frame structure |
US5979130A (en) * | 1996-10-10 | 1999-11-09 | Simpson Strong-Tie Company, Inc. | Connector with concave seat |
US5934036A (en) * | 1996-11-01 | 1999-08-10 | Gallagher, Jr.; Daniel P. | Insulated concrete slab assembly |
US6131358A (en) * | 1997-08-29 | 2000-10-17 | Wise; Michael A. | Joist hanger and installation method |
US6505450B1 (en) * | 1997-10-29 | 2003-01-14 | Reginald A. J. Locke | Masonry reinforcement system |
US5956910A (en) * | 1997-11-03 | 1999-09-28 | Sommerstein; Michael | Panel mounting structure |
US6470644B2 (en) * | 1998-10-19 | 2002-10-29 | Varco Pruden Technologies, Inc. | Roof bracket |
US6145268A (en) * | 1998-12-18 | 2000-11-14 | Korzen; Thomas G. | Apparatus and method for providing a reinforced roof truss |
US6354056B1 (en) * | 1998-12-18 | 2002-03-12 | Thomas G. Korzen | Apparatus and method for providing a reinforced roof truss |
US6817157B2 (en) * | 1999-07-23 | 2004-11-16 | Michael Bourque | Deck attachment bracket and method of attaching a deck to a building |
US6397552B1 (en) * | 1999-07-23 | 2002-06-04 | Michael Bourque | Deck attachment bracket and method of attaching a deck to a building |
US20020134042A1 (en) * | 1999-07-23 | 2002-09-26 | Michael Bourque | Deck attachment bracket and method of attaching a deck to a building |
US6311449B1 (en) * | 1999-08-06 | 2001-11-06 | Michael G. Morse | Securing decks to houses with “L”-shaped brackets |
US6463711B1 (en) * | 1999-08-09 | 2002-10-15 | United Steel Products Company, Inc. | Construction hanger |
US7992352B2 (en) * | 1999-12-21 | 2011-08-09 | Bonds Delton J | Modular building frame |
US6332303B1 (en) * | 2000-02-28 | 2001-12-25 | Nic Engineering Co., Ltd. | Method of building underground structure |
US20020078646A1 (en) * | 2000-10-16 | 2002-06-27 | Eaton Peter Francis | Suspended concrete flooring system and method |
US6612087B2 (en) * | 2000-11-29 | 2003-09-02 | The Steel Network, Inc. | Building member connector allowing bi-directional relative movement |
US20040129845A1 (en) * | 2001-05-19 | 2004-07-08 | Whale Luke John Richard | Hanger device |
US7497054B2 (en) * | 2001-06-06 | 2009-03-03 | Nippon Steel Corporation | Column-and-beam join structure |
US20030033764A1 (en) * | 2001-08-20 | 2003-02-20 | Ting Raymond M.L. | Mullion splice joint design |
US20060230697A1 (en) * | 2003-02-25 | 2006-10-19 | James Lupton | Deck structure |
US7055289B2 (en) * | 2003-04-14 | 2006-06-06 | Masonry Technology, Inc. | System and method for forming a structural connection |
US20060016139A1 (en) * | 2003-04-14 | 2006-01-26 | Beck John R | Wall and floor construction arrangements and methods |
US7856786B2 (en) * | 2003-04-14 | 2010-12-28 | Dietrich Industries, Inc. | Wall and floor construction arrangements and methods |
US7716899B2 (en) * | 2003-04-14 | 2010-05-18 | Dietrich Industries, Inc. | Building construction systems and methods |
US8091316B2 (en) * | 2003-04-14 | 2012-01-10 | Dietrich Industries, Inc. | Wall and floor systems |
US20060260261A1 (en) * | 2003-06-05 | 2006-11-23 | Jozef Cervenko | System for fasterning linings |
US20080163568A1 (en) * | 2003-09-25 | 2008-07-10 | Shelton David R | Wooden member support retrofit system and method |
US7299596B2 (en) * | 2004-04-21 | 2007-11-27 | John Hildreth | Framing system |
US7424793B1 (en) * | 2004-05-07 | 2008-09-16 | Thermafiber, Inc. | Interlocking curtain wall insulation system |
US7765753B1 (en) * | 2004-05-07 | 2010-08-03 | Thermafiber, Inc. | Interlocking curtain wall insulation system |
US7845138B2 (en) * | 2004-06-11 | 2010-12-07 | Op-Deck Holdings B.V. | Method for the production of a building construction as well as formwork therefor |
US20080115447A1 (en) * | 2004-08-12 | 2008-05-22 | Morse Michael G | Method of connecting post to joist |
US7389620B1 (en) * | 2004-08-19 | 2008-06-24 | Mcmanus Ira J | Composite pan for composite beam-joist construction |
US8225575B2 (en) * | 2005-02-28 | 2012-07-24 | Playcore Wisconsin, Inc. | Brackets and bracket system for assembling playground equipment |
US7827757B2 (en) * | 2005-02-28 | 2010-11-09 | Playcore Wisconsin, Inc. | Brackets and bracket system for assembling playground equipment |
US20060016138A1 (en) * | 2005-07-22 | 2006-01-26 | Michael Blount | EZ bar |
US8234827B1 (en) * | 2005-09-01 | 2012-08-07 | Schroeder Sr Robert | Express framing building construction system |
US20070186503A1 (en) * | 2006-02-10 | 2007-08-16 | Yoichi Homma | Construction framing system and method |
US20070204540A1 (en) * | 2006-03-03 | 2007-09-06 | Specified Technologies Inc. | Means and method for fireproof sealing between the peripheral edge of individual floors of a building and the exterior wall structure thereof |
US20070289230A1 (en) * | 2006-06-15 | 2007-12-20 | Schroeder Robert Sr | Bracing For Shear Wall Construction |
US8234826B1 (en) * | 2006-06-15 | 2012-08-07 | Proffitt Jr Ray A | Hold down clip |
US20080022624A1 (en) * | 2006-07-25 | 2008-01-31 | Hanson Courtney J | Joist support |
US20100293872A1 (en) * | 2007-01-18 | 2010-11-25 | Stephen Kennedy | flooring panels and connectors |
US20080236090A1 (en) * | 2007-04-02 | 2008-10-02 | Liberman Barnet L | Modular building structures |
US8028494B2 (en) * | 2007-04-12 | 2011-10-04 | Denmay Steel | Sleeve connectors for metal girders |
US20090139176A1 (en) * | 2007-11-26 | 2009-06-04 | Schroeder Sr Robert | Slotted Tabbed Rim Track and Building Method |
US7788878B1 (en) * | 2008-04-03 | 2010-09-07 | The Steel Network, Inc. | Device and method for bracing a wall structure |
US8209924B2 (en) * | 2009-11-12 | 2012-07-03 | The Foley Group, LLC | Connector system for securing an end portion of a steel structural member to a vertical cast concrete member |
US8490341B2 (en) * | 2010-09-09 | 2013-07-23 | Michael Hatzinikolas | Self-releasing structural assembly |
US8490340B2 (en) * | 2010-09-09 | 2013-07-23 | Michael Hatzinikolas | Self-releasing structural assembly |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103866856A (en) * | 2014-03-20 | 2014-06-18 | 北京工业大学 | Center support occlusion splicing system of assembly type steel structure with rigid-connection nodes |
US10975590B2 (en) * | 2014-08-30 | 2021-04-13 | Innovative Building Technologies, Llc | Diaphragm to lateral support coupling in a structure |
US11060286B2 (en) | 2014-08-30 | 2021-07-13 | Innovative Building Technologies, Llc | Prefabricated wall panel for utility installation |
US11054148B2 (en) | 2014-08-30 | 2021-07-06 | Innovative Building Technologies, Llc | Heated floor and ceiling panel with a corrugated layer for modular use in buildings |
US20190218811A1 (en) * | 2014-08-30 | 2019-07-18 | Innovative Building Technologies, Llc | Diaphragm to lateral support coupling in a structure |
US10676923B2 (en) | 2016-03-07 | 2020-06-09 | Innovative Building Technologies, Llc | Waterproofing assemblies and prefabricated wall panels including the same |
US10900224B2 (en) | 2016-03-07 | 2021-01-26 | Innovative Building Technologies, Llc | Prefabricated demising wall with external conduit engagement features |
US10961710B2 (en) | 2016-03-07 | 2021-03-30 | Innovative Building Technologies, Llc | Pre-assembled wall panel for utility installation |
CN105735648A (en) * | 2016-03-10 | 2016-07-06 | 中国五冶集团有限公司 | Multi-segment formwork set-up casting construction process of steel reinforced concrete coal hopper for house of main workshop of power plant |
US10724228B2 (en) | 2017-05-12 | 2020-07-28 | Innovative Building Technologies, Llc | Building assemblies and methods for constructing a building using pre-assembled floor-ceiling panels and walls |
US11098475B2 (en) | 2017-05-12 | 2021-08-24 | Innovative Building Technologies, Llc | Building system with a diaphragm provided by pre-fabricated floor panels |
CN109138428A (en) * | 2018-08-17 | 2019-01-04 | 中国人民解放军63926部队 | A kind of launching workplace diversion trench refractory concrete protective layer construction method |
US11898351B2 (en) | 2018-10-10 | 2024-02-13 | Nucor Corporation | Joist tie used in structural decking systems and method of installing |
EP3757304A1 (en) | 2019-06-27 | 2020-12-30 | Proruper, Unipessoal, Lda | Modular construction system |
CN112681331A (en) * | 2020-12-03 | 2021-04-20 | 中国建筑第八工程局有限公司 | Steel support and steel trestle integrated structure and construction method thereof |
US11913180B1 (en) * | 2023-05-10 | 2024-02-27 | TX Bridge Robotics, INC. | Bridge construction method and bridge |
Also Published As
Publication number | Publication date |
---|---|
US8234827B1 (en) | 2012-08-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US8234827B1 (en) | Express framing building construction system | |
US20050188638A1 (en) | Apparatus and method for composite concrete and steel floor construction | |
CA2358747C (en) | Ring beam/lintel system | |
US8499511B2 (en) | Precast composite structural floor system | |
US8516762B1 (en) | Composite floor systems and apparatus for supporting a concrete floor | |
US20080000177A1 (en) | Composite floor and composite steel stud wall construction systems | |
US8245480B2 (en) | Flush joist seat | |
US4144690A (en) | Concrete forming structures | |
US20070289230A1 (en) | Bracing For Shear Wall Construction | |
JP3866284B2 (en) | How to construct a suspended floor | |
US5881516A (en) | Bearing wall construction system wherein axial loads of walls do no pass through the floor construction | |
JP2001512198A (en) | Building panels used for building construction | |
US20030233801A1 (en) | Apparatus and method for composite concrete and steel floor construction | |
US8495846B2 (en) | Formwork assembly for fabricating composite structures including floor and roof structures | |
US20050066609A1 (en) | Preassembled roof and floor deck panel system | |
US7721497B2 (en) | Apparatus and method for composite concrete and steel floor construction | |
CA2592820A1 (en) | Composite floor and composite steel stud wall construction systems | |
RU2233367C1 (en) | Set for house building | |
JP2974025B1 (en) | Construction method of large span large beam upper frame | |
KR200296952Y1 (en) | Deck panel for reinforced concrete slab | |
KR200296951Y1 (en) | Deck panel for reinforced concrete slab | |
KR20040017560A (en) | Deck panel for reinforced concrete slab | |
JP2598008Y2 (en) | Floor structure and bundle of steel building balcony | |
Paoletti et al. | The Structural Procedures of the Advanced Envelope Systems | |
EP2340336B1 (en) | Joist hanger comprising a plurality of joist supports |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |