US20110162592A1 - Continuous steam generator - Google Patents

Continuous steam generator Download PDF

Info

Publication number
US20110162592A1
US20110162592A1 US13/062,738 US200913062738A US2011162592A1 US 20110162592 A1 US20110162592 A1 US 20110162592A1 US 200913062738 A US200913062738 A US 200913062738A US 2011162592 A1 US2011162592 A1 US 2011162592A1
Authority
US
United States
Prior art keywords
tubes
steam generator
flow medium
superheater
combustion chamber
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US13/062,738
Inventor
Martin Effert
Joachim Franke
Frank Thomas
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Siemens AG
Original Assignee
Siemens AG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Siemens AG filed Critical Siemens AG
Assigned to SIEMENS AKTIENGESELLSCHAFT reassignment SIEMENS AKTIENGESELLSCHAFT ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: FRANKE, JOACHIM, EFFERT, MARTIN, THOMAS, FRANK
Publication of US20110162592A1 publication Critical patent/US20110162592A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F22STEAM GENERATION
    • F22BMETHODS OF STEAM GENERATION; STEAM BOILERS
    • F22B37/00Component parts or details of steam boilers
    • F22B37/02Component parts or details of steam boilers applicable to more than one kind or type of steam boiler
    • F22B37/26Steam-separating arrangements
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F22STEAM GENERATION
    • F22BMETHODS OF STEAM GENERATION; STEAM BOILERS
    • F22B21/00Water-tube boilers of vertical or steeply-inclined type, i.e. the water-tube sets being arranged vertically or substantially vertically
    • F22B21/34Water-tube boilers of vertical or steeply-inclined type, i.e. the water-tube sets being arranged vertically or substantially vertically built-up from water tubes grouped in panel form surrounding the combustion chamber, i.e. radiation boilers
    • F22B21/341Vertical radiation boilers with combustion in the lower part
    • F22B21/343Vertical radiation boilers with combustion in the lower part the vertical radiation combustion chamber being connected at its upper part to a sidewards convection chamber
    • F22B21/345Vertical radiation boilers with combustion in the lower part the vertical radiation combustion chamber being connected at its upper part to a sidewards convection chamber with a tube bundle between an upper and a lower drum in the convection pass
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F22STEAM GENERATION
    • F22BMETHODS OF STEAM GENERATION; STEAM BOILERS
    • F22B29/00Steam boilers of forced-flow type
    • F22B29/06Steam boilers of forced-flow type of once-through type, i.e. built-up from tubes receiving water at one end and delivering superheated steam at the other end of the tubes

Definitions

  • the invention relates to a once-through (“continuous”) steam generator comprising a number of burners for fossil fuel, the surrounding wall thereof being completely or partially formed from steam generator tubes welded together in a gas-tight manner.
  • Said burners are disposed in a combustion chamber downstream of which a vertical gas duct is mounted above a horizontal gas duct on the hot gas side, a first part of the steam generator tubes being implemented as a system of evaporator tubes mounted upstream of a moisture separation system on the flow medium side, and a second part of the steam generator tubes being implemented as a system of superheater tubes mounted downstream of the moisture separation system on the flow medium side.
  • a fossil fired steam generator the energy of a fossil fuel is used to produce superheated steam which in a power plant, for example, can then supplied to a steam turbine for power generation.
  • steam generators are normally implemented as water tube boilers, i.e. the water supplied flows in a number of tubes which absorb energy in the form of radiant heat of the burner flames and/or by convection from the flue gas produced during combustion.
  • the steam generator tubes are usually welded together in a gas-tight manner to form the combustion chamber wall.
  • steam generator tubes disposed in the waste gas duct can also be provided.
  • Fossil fired steam generators can be categorized on the basis of a large number of criteria: based on the flow direction of the gas stream, steam generators can be subdivided, for example, into vertical and horizontal types. In the case of fossil fired steam generators of vertical design, a distinction is usually drawn between single-pass and two-pass boilers.
  • a horizontal gas duct leading into a vertical gas duct is mounted in an upper region downstream of the combustion chamber on the flue gas side.
  • the gas usually flows vertically from top to bottom. Therefore, in the two-pass boiler, multiple flow baffling of the flue gas takes place. Advantages of this design are, for example, the lower installed height and the resulting reduced manufacturing costs.
  • Steam generators may also be designed as natural circulation, forced circulation or once-through steam generators.
  • a once-through steam generator the heating of a number of evaporator tubes results in complete evaporation of the flow medium in the evaporator tubes in one pass.
  • the flow medium usually water
  • the flow medium is fed to superheater tubes downstream of the evaporator tubes where it is superheated.
  • this description is valid only at partial loads with subcritical pressure of water (P Kri ⁇ 221 bar) in the evaporator—at which there is no temperature at which water and steam can be present simultaneously and therefore also no phase separation is possible.
  • this representation will be used consistently in the following description.
  • the position of the evaporation end point i.e. the location at which the water content of the flow is completely evaporated, is variable and dependent on the operating mode.
  • the evaporation end point is, for example, in an end region of the evaporator tubes, so that the superheating of the evaporated flow medium begins even in the evaporator tubes.
  • a once-through steam generator is not subject to pressure limiting, so that it can be designed for main steam pressures well above the critical pressure of water.
  • a once-through steam generator of this kind is usually operated with a minimum flow of flow medium in the evaporator tubes in order to ensure reliable cooling of the evaporator tubes.
  • the pure mass flow through the evaporator is usually no longer sufficient to cool the evaporator tubes, so that an additional throughput of flow medium is superimposed in a circulating manner on the flow medium passing through the evaporator.
  • the operatively provided minimum flow of flow medium in the evaporator tubes is therefore not completely evaporated in the evaporator tubes during startup or light load operation, so that unevaporated flow medium, in particular a water-steam mixture, is still present at the end of the evaporator tubes during such an operating mode.
  • once-through steam generators are generally designed such that water is reliably prevented from entering the superheater tubes even during startup or light load operation.
  • the evaporator tubes are normally connected to the superheater tubes mounted downstream thereof via a moisture separation system.
  • the moisture separator is used to separate the water-steam mixture exiting the evaporator tubes during startup or light load operation into water and steam.
  • the steam is fed to the superheater tubes mounted downstream of the moisture separator, whereas the separated water is returned to the evaporator tubes e.g. via a circulating pump or can be drained off via a flash tank.
  • the above mentioned concept causes high temperature differences between evaporator tubes and superheater tubes: during cold starting, as yet unevaporated flow medium flows in the evaporator tubes at saturation temperature, while steam at higher temperature is still present in the superheater tubes.
  • the evaporator tubes are filled with cold feedwater, while the superheater tubes are still at operating temperature level. This can result in overloading and damage of the materials due to the differential thermal expansion.
  • the object of the invention is therefore to specify a once-through steam generator of the above mentioned type requiring comparatively low repair costs and having a comparatively long service life.
  • This object is achieved according to the invention by mounting superheater tubes in parallel contiguity with evaporator tubes immediately downstream of the moisture separation system on the flow medium side.
  • the invention is based on the idea that it would be possible to reduce repair costs and increase the service life of the once-through steam generator if damage caused by differential thermal expansion of welded-together steam generator tubes could be minimized.
  • the differential expansion is the result of high temperature differences between the steam generator tubes. Said temperature differences are caused by differential cooling of the steam generator tubes and different temperatures of the flow medium flowing therein and therefore occur in particular at the interface between welded-together evaporator and superheater tubes, as these exhibit a different throughput of flow medium with different temperatures through the intervening moisture separation system particularly during cold and hot starting.
  • the design means that an interface between parallel-welded evaporator and superheater tubes is typical.
  • the steam temperature in the superheater tubes welded parallel with the evaporator tubes must be minimized. This can be achieved by mounting said superheater tubes immediately downstream of the moisture separation system, so that there is no increase in the temperature of the flow medium flowing therein due to additional intervening superheater tubes. This consistently minimizes temperature differences as a cause of damage at the interface.
  • the combustion chamber wall of the once-through steam generator is formed from evaporator tubes and a sidewall of the horizontal gas duct is formed from superheater tubes, the superheater tubes adjacent to the combustion chamber being mounted directly downstream of the moisture separation system on the flow medium side.
  • the top of the once-through steam generator is found from superheater tubes which are disposed immediately downstream of the moisture separation system on the flow medium side.
  • the superheater tubes of the top are mounted parallel with other superheater tubes adjacent to the evaporator tubes. Due to the paralleling of the heating surfaces, such an arrangement is advantageous in respect of the pressure loss to be expected.
  • the advantages achieved with the invention are in particular that by mounting superheater tubes in parallel contiguity with evaporator tubes immediately downstream of the moisture separation system on the flow medium side, the temperature differences between said tubes are consistently minimized. As a result, the differential thermal expansion is minimized and damage and overloading are prevented, in turn resulting in fewer repairs and a longer service life of the once-through steam generator.
  • Such an arrangement is advantageous particularly in the case of once-through steam generators without circulating pump.
  • the absence of circulation results in lower inlet temperatures to the evaporator, smaller steam mass flows and an increase in the firing capacity required at startup.
  • Simulations have shown that particularly for these systems, impermissible temperature differences can occur at the interface between evaporator and superheater tubes if—as hitherto usual—the superheater tubes at the interface are mounted downstream of other superheater tubes, e.g. of the top. Mounting said superheater tubes directly downstream of the moisture separation system effectively prevents these temperature differences.
  • FIGURE schematically illustrates a once-through steam generator of two-pass design.
  • the once-through steam generator 1 comprises a combustion chamber 2 implemented as a vertical gas duct, downstream of which a horizontal gas duct 6 is disposed in an upper region 4 .
  • the horizontal gas duct 6 is connected to another vertical gas duct 8 .
  • a number of burners (not shown in greater detail) are provided which combust liquid or solid fuel in the combustion chamber.
  • the wall 12 of the combustion chamber 2 is formed of steam generator tubes welded together in a gas-tight manner into which a flow medium—usually water—is pumped by a pump (not shown in greater detail), said flow medium being heated by the heat produced by the burners.
  • the steam generator tubes can be oriented either spirally or vertically. In the case of a spiral arrangement, although comparatively greater design complexity is required, the resulting heating differences between parallel tubes are comparatively lower than with a vertically tubed combustion chamber 2 .
  • the once-through steam generator 1 shown also comprises a projection 14 forming a direct transition to the bottom 16 of the horizontal gas duct 6 and extending into the combustion chamber 2 .
  • the steam generator tubes of the combustion chamber 2 are designed as evaporator tubes.
  • the flow medium is first evaporated therein and fed via outlet headers 20 to the moisture separation system 22 .
  • the moisture separation system 22 not yet evaporated water is collected and drained off. This is particularly necessary in startup mode when a larger amount of flow medium must be pumped in to ensure reliable cooling of the evaporator tubes than can be evaporated in one evaporator tube pass.
  • the steam produced is fed to the inlet headers 24 of the downstream superheater tubes which form the top 26 of the once-through steam generator 1 and the walls of the horizontal gas duct 6 .
  • the transition from the sidewalls of the vertical gas duct to the sidewalls of the horizontal gas duct 6 constitutes the interface 18 between evaporator tubes of the combustion chamber wall 12 and superheater tubes in the walls of the horizontal gas duct 6 .
  • these superheater tubes are mounted directly downstream of the moisture separation system 22 via a connecting line 28 .
  • said superheater tubes are only subject to saturated steam and not higher-temperature superheated steam, thereby reducing the temperature.
  • the superheater tubes in the walls of the horizontal gas duct 6 are parallel to those of the top 26 and are flowed through from top to bottom. Thus, in the event of overfeeding of the moisture separation system 22 , unevaporated flow medium in the outlet headers 30 of the superheater tubes can be drained off and flow stagnation cannot occur.
  • the arrangement described minimizes the temperature differences at the interface 18 between the evaporator tubes of the combustion chamber wall 12 and the superheater tubes in the walls of the horizontal gas duct 6 , thereby enabling damage to be effectively prevented. This results in comparatively fewer repairs and a longer service life of the once-through steam generator 1 .

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)
  • Control Of Steam Boilers And Waste-Gas Boilers (AREA)
  • Air Supply (AREA)

Abstract

A continuous steam generator is provided. The continuous steam generator includes a number of burners for fossil fuels, the outside wall thereof being fully or partially formed from steam generator tubes welded together in a gas-tight manner. The burners are arranged in a combustion chamber, and a vertical gas duct is mounted downstream of the combustion chamber above a horizontal gas duct on the hot gas side. A first part of the steam generating tubes forms a system of evaporation tubes mounted upstream of a water separator system, on the flow medium side, and a second side, and a second part of the steam generating tubes forms a system of superheater tubes mounted downstream of the water separator system on the flow medium side. Superheater tubes adjacent and parallel to evaporation tubes are mounted directly downstream of the water separator system on the flow medium side.

Description

    CROSS REFERENCE TO RELATED APPLICATIONS
  • This application is the US National Stage of International Application No. PCT/EP2009/061468, filed Sep. 4, 2009 and claims the benefit thereof. The International Application claims the benefits of European Patent Office application No. 08015871.0 EP filed Sep. 9, 2008. All of the applications are incorporated by reference herein in their entirety.
  • FIELD OF INVENTION
  • The invention relates to a once-through (“continuous”) steam generator comprising a number of burners for fossil fuel, the surrounding wall thereof being completely or partially formed from steam generator tubes welded together in a gas-tight manner. Said burners are disposed in a combustion chamber downstream of which a vertical gas duct is mounted above a horizontal gas duct on the hot gas side, a first part of the steam generator tubes being implemented as a system of evaporator tubes mounted upstream of a moisture separation system on the flow medium side, and a second part of the steam generator tubes being implemented as a system of superheater tubes mounted downstream of the moisture separation system on the flow medium side.
  • BACKGROUND OF INVENTION
  • In a fossil fired steam generator, the energy of a fossil fuel is used to produce superheated steam which in a power plant, for example, can then supplied to a steam turbine for power generation. Particularly at the steam temperatures and pressures prevalent in a power plant environment, steam generators are normally implemented as water tube boilers, i.e. the water supplied flows in a number of tubes which absorb energy in the form of radiant heat of the burner flames and/or by convection from the flue gas produced during combustion.
  • In the region of the burners, the steam generator tubes are usually welded together in a gas-tight manner to form the combustion chamber wall. In other areas downstream of the combustion chamber on the flue gas side, steam generator tubes disposed in the waste gas duct can also be provided.
  • Fossil fired steam generators can be categorized on the basis of a large number of criteria: based on the flow direction of the gas stream, steam generators can be subdivided, for example, into vertical and horizontal types. In the case of fossil fired steam generators of vertical design, a distinction is usually drawn between single-pass and two-pass boilers.
  • In the case of a single-pass or tower boiler, the flue gas produced by combustion in the combustion chamber always flows vertically upward. All the heating surfaces disposed in the flue gas duct are located above the combustion chamber. Tower boilers offer a comparatively simple design and simple control of the stresses produced by the thermal expansion of the tubes. In addition, all the heating surfaces of the evaporator tubes disposed in the flue gas duct are horizontal and can therefore be completely dewatered, which may be desirable in frost-prone environments.
  • In the case of the two-pass boiler, a horizontal gas duct leading into a vertical gas duct is mounted in an upper region downstream of the combustion chamber on the flue gas side. In said second vertical gas duct, the gas usually flows vertically from top to bottom. Therefore, in the two-pass boiler, multiple flow baffling of the flue gas takes place. Advantages of this design are, for example, the lower installed height and the resulting reduced manufacturing costs.
  • Steam generators may also be designed as natural circulation, forced circulation or once-through steam generators. In a once-through steam generator, the heating of a number of evaporator tubes results in complete evaporation of the flow medium in the evaporator tubes in one pass. Once evaporated, the flow medium—usually water—is fed to superheater tubes downstream of the evaporator tubes where it is superheated. Strictly speaking, this description is valid only at partial loads with subcritical pressure of water (PKri≈221 bar) in the evaporator—at which there is no temperature at which water and steam can be present simultaneously and therefore also no phase separation is possible. However, for the sake of clarity, this representation will be used consistently in the following description.
  • The position of the evaporation end point, i.e. the location at which the water content of the flow is completely evaporated, is variable and dependent on the operating mode. During full load operation of a once-through steam generator of this kind, the evaporation end point is, for example, in an end region of the evaporator tubes, so that the superheating of the evaporated flow medium begins even in the evaporator tubes.
  • In contrast to a natural or forced circulation steam generator, a once-through steam generator is not subject to pressure limiting, so that it can be designed for main steam pressures well above the critical pressure of water.
  • During light load operation or at startup, a once-through steam generator of this kind is usually operated with a minimum flow of flow medium in the evaporator tubes in order to ensure reliable cooling of the evaporator tubes. For this purpose, particularly at low loads of e.g. less than 40% of the design load, the pure mass flow through the evaporator is usually no longer sufficient to cool the evaporator tubes, so that an additional throughput of flow medium is superimposed in a circulating manner on the flow medium passing through the evaporator. The operatively provided minimum flow of flow medium in the evaporator tubes is therefore not completely evaporated in the evaporator tubes during startup or light load operation, so that unevaporated flow medium, in particular a water-steam mixture, is still present at the end of the evaporator tubes during such an operating mode.
  • However, as the superheater tubes mounted downstream of the evaporator tubes of the once-through steam generator and usually not receiving flow medium until it has flowed through the combustion chamber walls are not designed for a flow of unevaporated flow medium, once-through steam generators are generally designed such that water is reliably prevented from entering the superheater tubes even during startup or light load operation. To achieve this, the evaporator tubes are normally connected to the superheater tubes mounted downstream thereof via a moisture separation system. The moisture separator is used to separate the water-steam mixture exiting the evaporator tubes during startup or light load operation into water and steam. The steam is fed to the superheater tubes mounted downstream of the moisture separator, whereas the separated water is returned to the evaporator tubes e.g. via a circulating pump or can be drained off via a flash tank.
  • However, particularly in startup mode, the above mentioned concept causes high temperature differences between evaporator tubes and superheater tubes: during cold starting, as yet unevaporated flow medium flows in the evaporator tubes at saturation temperature, while steam at higher temperature is still present in the superheater tubes. During hot starting, on the other hand, the evaporator tubes are filled with cold feedwater, while the superheater tubes are still at operating temperature level. This can result in overloading and damage of the materials due to the differential thermal expansion.
  • SUMMARY OF INVENTION
  • The object of the invention is therefore to specify a once-through steam generator of the above mentioned type requiring comparatively low repair costs and having a comparatively long service life.
  • This object is achieved according to the invention by mounting superheater tubes in parallel contiguity with evaporator tubes immediately downstream of the moisture separation system on the flow medium side.
  • The invention is based on the idea that it would be possible to reduce repair costs and increase the service life of the once-through steam generator if damage caused by differential thermal expansion of welded-together steam generator tubes could be minimized. The differential expansion is the result of high temperature differences between the steam generator tubes. Said temperature differences are caused by differential cooling of the steam generator tubes and different temperatures of the flow medium flowing therein and therefore occur in particular at the interface between welded-together evaporator and superheater tubes, as these exhibit a different throughput of flow medium with different temperatures through the intervening moisture separation system particularly during cold and hot starting.
  • Particularly in the case of once-through steam generators of the two-pass type, the design means that an interface between parallel-welded evaporator and superheater tubes is typical. In order to minimize as far as possible the temperature differences between evaporator and superheater tubes, the steam temperature in the superheater tubes welded parallel with the evaporator tubes must be minimized. This can be achieved by mounting said superheater tubes immediately downstream of the moisture separation system, so that there is no increase in the temperature of the flow medium flowing therein due to additional intervening superheater tubes. This consistently minimizes temperature differences as a cause of damage at the interface.
  • In an advantageous embodiment, the combustion chamber wall of the once-through steam generator is formed from evaporator tubes and a sidewall of the horizontal gas duct is formed from superheater tubes, the superheater tubes adjacent to the combustion chamber being mounted directly downstream of the moisture separation system on the flow medium side. This effectively minimizes the temperature differences at the vertical interface between evaporator tubes of the combustion chamber and superheater tubes of the horizontal gas duct in the case of the two-pass boiler.
  • Advantageously, the top of the once-through steam generator is found from superheater tubes which are disposed immediately downstream of the moisture separation system on the flow medium side. This means that the superheater tubes of the top are mounted parallel with other superheater tubes adjacent to the evaporator tubes. Due to the paralleling of the heating surfaces, such an arrangement is advantageous in respect of the pressure loss to be expected.
  • In a once-through steam generator in which superheater tubes in parallel contiguity with evaporator tubes are disposed vertically, these are advantageously designed such that the flow medium flows through the superheater tubes from top to bottom. This means that, in the event of overfeeding of the moisture separation system resulting in unevaporated flow medium being applied to the superheater tubes, this can be drained off at the outlet header of the superheater tubes, thereby enabling any flow stagnation to be effectively prevented.
  • The advantages achieved with the invention are in particular that by mounting superheater tubes in parallel contiguity with evaporator tubes immediately downstream of the moisture separation system on the flow medium side, the temperature differences between said tubes are consistently minimized. As a result, the differential thermal expansion is minimized and damage and overloading are prevented, in turn resulting in fewer repairs and a longer service life of the once-through steam generator.
  • Such an arrangement is advantageous particularly in the case of once-through steam generators without circulating pump. The absence of circulation results in lower inlet temperatures to the evaporator, smaller steam mass flows and an increase in the firing capacity required at startup. Simulations have shown that particularly for these systems, impermissible temperature differences can occur at the interface between evaporator and superheater tubes if—as hitherto usual—the superheater tubes at the interface are mounted downstream of other superheater tubes, e.g. of the top. Mounting said superheater tubes directly downstream of the moisture separation system effectively prevents these temperature differences.
  • BRIEF DESCRIPTION OF THE DRAWINGS
  • An exemplary embodiment of the invention will now be explained in greater detail with reference to the accompanying drawings in which the FIGURE schematically illustrates a once-through steam generator of two-pass design.
  • DETAILED DESCRIPTION OF INVENTION
  • The once-through steam generator 1 according to the FIGURE comprises a combustion chamber 2 implemented as a vertical gas duct, downstream of which a horizontal gas duct 6 is disposed in an upper region 4. The horizontal gas duct 6 is connected to another vertical gas duct 8.
  • In the lower region 10 of the combustion chamber 2, a number of burners (not shown in greater detail) are provided which combust liquid or solid fuel in the combustion chamber. The wall 12 of the combustion chamber 2 is formed of steam generator tubes welded together in a gas-tight manner into which a flow medium—usually water—is pumped by a pump (not shown in greater detail), said flow medium being heated by the heat produced by the burners. In the lower region 10 of the combustion chamber 2, the steam generator tubes can be oriented either spirally or vertically. In the case of a spiral arrangement, although comparatively greater design complexity is required, the resulting heating differences between parallel tubes are comparatively lower than with a vertically tubed combustion chamber 2.
  • To improve flue gas flow, the once-through steam generator 1 shown also comprises a projection 14 forming a direct transition to the bottom 16 of the horizontal gas duct 6 and extending into the combustion chamber 2.
  • The steam generator tubes of the combustion chamber 2 are designed as evaporator tubes. The flow medium is first evaporated therein and fed via outlet headers 20 to the moisture separation system 22. In the moisture separation system 22, not yet evaporated water is collected and drained off. This is particularly necessary in startup mode when a larger amount of flow medium must be pumped in to ensure reliable cooling of the evaporator tubes than can be evaporated in one evaporator tube pass. The steam produced is fed to the inlet headers 24 of the downstream superheater tubes which form the top 26 of the once-through steam generator 1 and the walls of the horizontal gas duct 6. The transition from the sidewalls of the vertical gas duct to the sidewalls of the horizontal gas duct 6 constitutes the interface 18 between evaporator tubes of the combustion chamber wall 12 and superheater tubes in the walls of the horizontal gas duct 6.
  • In addition to the two-pass boiler shown in the FIGURE, other configurations for fossil fired boilers are self-evidently also possible.
  • In order to prevent damage due to differential thermal expansion caused by temperature differences at the interface 18 between the evaporator tubes of the combustion chamber wall 12 and the superheater tubes in the walls of the horizontal gas duct 6, these superheater tubes are mounted directly downstream of the moisture separation system 22 via a connecting line 28. As a result, said superheater tubes are only subject to saturated steam and not higher-temperature superheated steam, thereby reducing the temperature.
  • The superheater tubes in the walls of the horizontal gas duct 6 are parallel to those of the top 26 and are flowed through from top to bottom. Thus, in the event of overfeeding of the moisture separation system 22, unevaporated flow medium in the outlet headers 30 of the superheater tubes can be drained off and flow stagnation cannot occur.
  • The arrangement described minimizes the temperature differences at the interface 18 between the evaporator tubes of the combustion chamber wall 12 and the superheater tubes in the walls of the horizontal gas duct 6, thereby enabling damage to be effectively prevented. This results in comparatively fewer repairs and a longer service life of the once-through steam generator 1.

Claims (5)

1.-4. (canceled)
5. A continuous steam generator, comprising:
a plurality of burners for fossil fuel;
a plurality of steam generator tubes;
a combustion chamber;
a vertical gas duct;
a horizontal gas duct; and
a moisture separation system,
wherein a surrounding wall of the plurality of burners is completely or partially formed from steam generator tubes welded together in a gas-tight manner,
wherein the plurality of burners are disposed in the combustion chamber downstream of which the vertical gas duct is mounted above the horizontal gas duct on a hot gas side,
wherein a first part of the plurality of steam generator tubes is implemented as a system of evaporator tubes mounted upstream of a moisture separation system on a flow medium side, and
wherein a second part of the steam generator tubes is implemented as a system of superheater tubes mounted downstream of the moisture separation system on the flow medium side, and
wherein a plurality of superheater tubes in parallel contiguity with the plurality of evaporator tubes are mounted immediately downstream of the moisture separation system on the flow medium side.
6. The continuous steam generator as claimed in claim 5,
wherein a combustion chamber wall is formed from the plurality of evaporator tubes and a sidewall of the horizontal gas duct is formed from the plurality of superheater tubes, and
wherein the plurality of superheater tubes adjacent to the combustion chamber is mounted immediately downstream of the moisture separation system on the flow medium side.
7. The continuous steam generator as claimed in claim 5, wherein a top of the once-through steam generator is formed from the plurality of superheater tubes which are mounted immediately downstream of the moisture separation system on the flow medium side.
8. The continuous steam generator as claimed in claim 5, wherein vertically disposed superheater tubes in parallel contiguity with the plurality of evaporator tubes are designed such that the flow medium flows through the plurality of superheater tubes from top to bottom.
US13/062,738 2008-09-09 2009-09-04 Continuous steam generator Abandoned US20110162592A1 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
EP08015871A EP2182278A1 (en) 2008-09-09 2008-09-09 Continuous-flow steam generator
EP08015871.0 2008-09-09
PCT/EP2009/061468 WO2010029022A2 (en) 2008-09-09 2009-09-04 Continuous steam generator

Publications (1)

Publication Number Publication Date
US20110162592A1 true US20110162592A1 (en) 2011-07-07

Family

ID=41820262

Family Applications (1)

Application Number Title Priority Date Filing Date
US13/062,738 Abandoned US20110162592A1 (en) 2008-09-09 2009-09-04 Continuous steam generator

Country Status (7)

Country Link
US (1) US20110162592A1 (en)
EP (2) EP2182278A1 (en)
JP (1) JP5345217B2 (en)
CN (1) CN102149970B (en)
AU (1) AU2009290944B2 (en)
DK (1) DK2324287T3 (en)
WO (1) WO2010029022A2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110197830A1 (en) * 2008-09-09 2011-08-18 Brueckner Jan Continuous steam generator
US9671105B2 (en) * 2013-08-06 2017-06-06 Siemens Aktiengesellschaft Continuous flow steam generator with a two-pass boiler design
US9920924B2 (en) * 2016-04-05 2018-03-20 The Babcock & Wilcox Company High temperature sub-critical boiler with steam cooled upper furnace and start-up methods

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102009024587A1 (en) * 2009-06-10 2010-12-16 Siemens Aktiengesellschaft Flow evaporator
CN114576607B (en) * 2022-03-09 2023-05-23 东方电气集团东方锅炉股份有限公司 System and method for realizing steam-water flow of supercritical boiler ceiling wall-covering

Citations (72)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2032368A (en) * 1930-04-22 1936-03-03 Babcock & Wilcox Co High pressure boiler
US2048393A (en) * 1936-03-16 1936-07-21 Kroger Rudolf Triple service water heater and boiler
US2170345A (en) * 1935-12-18 1939-08-22 Babcock & Wilcox Co Vapor generator
US2170343A (en) * 1935-12-18 1939-08-22 Babcock & Wilcox Co Vapor generator
US2201618A (en) * 1933-11-13 1940-05-21 W D La Mont Inc Steam generator
US2201620A (en) * 1933-11-13 1940-05-21 W D La Mont Inc High speed steam producing apparatus
US2617394A (en) * 1949-12-30 1952-11-11 Comb Eng Superheater Inc Boiler
US2834324A (en) * 1953-02-12 1958-05-13 Babcock & Wilcox Co Vapor generator with high temperature pendent superheater platens
US2869517A (en) * 1953-09-26 1959-01-20 Sulzer Ag Once through steam generating plant
US2921565A (en) * 1955-12-16 1960-01-19 Babcock & Wilcox Co Steam generating and superheating unit with downshot burners and gas recirculation temperature control
US2946187A (en) * 1958-05-28 1960-07-26 Foster Wheeler Corp Gas and steam cycle power plant having twin supercharged vapor generators
US2947288A (en) * 1957-08-20 1960-08-02 Kohlenscheidungs Gmbh Radiant tubular heat exchanger
US2952975A (en) * 1957-11-15 1960-09-20 Babcock & Wilcox Co Vapor generating and superheating unit
US2960972A (en) * 1954-05-24 1960-11-22 Babcock & Wilcox Co Apparatus for vapor generating and superheating with recirculated gas flow control of reheat
US2980081A (en) * 1958-02-11 1961-04-18 Atomic Energy Authority Uk Apparatus for the exchange of heat between fluids
US2982267A (en) * 1956-07-11 1961-05-02 Sulzer Ag High pressure steam plant
US3038453A (en) * 1957-02-07 1962-06-12 Combustion Eng Apparatus and method for controlling a forced flow once-through steam generator
US3072109A (en) * 1958-05-28 1963-01-08 Foster Wheeler Corp Supercharged vapor generator
US3267908A (en) * 1965-08-03 1966-08-23 Sulzer Ag Steam generator with flue gas return
US3280559A (en) * 1963-09-26 1966-10-25 Babcock & Wilcox Ltd Ship propulsion power plant
US3288117A (en) * 1965-12-01 1966-11-29 Combustion Eng Arrangement of tube circuits in supercritical forced through-flow vapor generator
US3312198A (en) * 1965-12-23 1967-04-04 Combustion Eng Steam generator having improved steam heating sections arranged for parallel flow
US3338219A (en) * 1965-09-09 1967-08-29 Frederick W Riehl Steam generating boiler or steam power plant
US3530836A (en) * 1967-07-13 1970-09-29 Sulzer Ag Forced through-flow steam generator
US3769941A (en) * 1970-12-31 1973-11-06 Sulzer Ag Steam generator
US3841270A (en) * 1972-11-01 1974-10-15 Westinghouse Electric Corp Flow restrictor for an evaporator
US3946566A (en) * 1974-12-16 1976-03-30 Combustion Engineering, Inc. Turbine start-up system
US3955358A (en) * 1974-08-08 1976-05-11 Westinghouse Electric Corporation Combined cycle electric power plant and a heat recovery steam generator with improved fluid level control therefor
US3965675A (en) * 1974-08-08 1976-06-29 Westinghouse Electric Corporation Combined cycle electric power plant and a heat recovery steam generator having improved boiler feed pump flow control
US3974644A (en) * 1974-08-08 1976-08-17 Westinghouse Electric Corporation Combined cycle electric power plant and heat recovery steam generator having improved multi-loop temperature control of the steam generated
US4020797A (en) * 1975-05-07 1977-05-03 Ofag Ofenbau-Und Feuerungstechnik Ag Process and apparatus for using waste heat of refuse burning installations
US4031404A (en) * 1974-08-08 1977-06-21 Westinghouse Electric Corporation Combined cycle electric power plant and a heat recovery steam generator having improved temperature control of the steam generated
US4262636A (en) * 1978-10-03 1981-04-21 Sulzer Brothers Limited Method of starting a forced-flow steam generator
US4290390A (en) * 1978-12-22 1981-09-22 Sulzer Brothers Limited Steam generator
US4377134A (en) * 1981-08-03 1983-03-22 Combustion Engineering, Inc. Steam temperature control with overfire air firing
US4418652A (en) * 1981-09-15 1983-12-06 Sulzer Brothers Limited Steam generator having a superheater tube bank
US4430962A (en) * 1980-12-23 1984-02-14 Sulzer Brothers Ltd. Forced flow vapor generator plant
US4444154A (en) * 1981-04-23 1984-04-24 Sulzer Brothers Limited Steam generator with fluidized bed firing
US4465021A (en) * 1981-08-22 1984-08-14 Deutsche Babcock Aktiengesellschaft Steam generator with a main boiler and a fluidized bed furnace
US4501127A (en) * 1980-10-29 1985-02-26 Ruhrgas Aktiengesellschaft Heating system incorporating an absorption-type heat pump and methods for the operation thereof
US4552099A (en) * 1984-10-25 1985-11-12 Westinghouse Electric Corp. Anticipatory boiler feedpump suction head controller system
US4574744A (en) * 1983-12-23 1986-03-11 Firma Carl Still Gmbh & Co. Kg Waste heat boiler system, and method of generating superheated high pressure steam
US5293842A (en) * 1992-03-16 1994-03-15 Siemens Aktiengesellschaft Method for operating a system for steam generation, and steam generator system
US5529021A (en) * 1992-05-04 1996-06-25 Siemens Aktiengesellschaft Forced once-through steam generator
US5762031A (en) * 1997-04-28 1998-06-09 Gurevich; Arkadiy M. Vertical drum-type boiler with enhanced circulation
US5787844A (en) * 1995-03-06 1998-08-04 Ahlstrom Machinery Oy Economizer system
US5839396A (en) * 1995-02-09 1998-11-24 Siemens Aktiengesellschaft Method and apparatus for starting up a continuous-flow steam generator
US5950574A (en) * 1996-12-17 1999-09-14 Babcock-Hitachi Kabushiki Kaisha Boiler
US5979370A (en) * 1994-09-01 1999-11-09 Siemens Aktiengesellschaft Continuous-flow steam generator
US5983639A (en) * 1995-03-02 1999-11-16 Siemens Aktiengesellschaft Method and system for starting up a continuous flow steam generator
US6019070A (en) * 1998-12-03 2000-02-01 Duffy; Thomas E. Circuit assembly for once-through steam generators
US6105369A (en) * 1999-01-13 2000-08-22 Abb Alstom Power Inc. Hybrid dual cycle vapor generation
US6192837B1 (en) * 1997-04-23 2001-02-27 Siemens Aktiengesellschaft Once-through steam generator and method for starting up a once-through steam generator
US6253714B1 (en) * 1999-09-08 2001-07-03 Bbp Energy Gmbh Steam generator
US20020000208A1 (en) * 1998-12-18 2002-01-03 Joachim Franke Fossil fuel-fired continuous-flow steam generator
US20020017251A1 (en) * 1999-03-31 2002-02-14 Eberhard Wittchow Fossil-fired continuous-flow steam generator
US20020026906A1 (en) * 1999-01-18 2002-03-07 Joachim Franke Fossil-fired steam generator
US20020026905A1 (en) * 1999-01-18 2002-03-07 Joachim Franke Fossil-fuel-fired steam generator
US20020157618A1 (en) * 1998-06-10 2002-10-31 Joachim Franke Fossil-fuel-fired once-through steam generator
US6536380B1 (en) * 1999-06-24 2003-03-25 Siemens Aktiengesellschaft Fossil-fuel heated steam generator, comprising dentrification device for heating gas
US6715450B1 (en) * 1999-03-31 2004-04-06 Siemens Aktiengesellschaft Fossil-fuel fired continuous-flow steam generator
US20040219079A1 (en) * 2003-01-22 2004-11-04 Hagen David L Trifluid reactor
US20050120715A1 (en) * 1997-12-23 2005-06-09 Christion School Of Technology Charitable Foundation Trust Heat energy recapture and recycle and its new applications
US20070283906A1 (en) * 2006-06-07 2007-12-13 Albrecht Melvin J Circulation system for sliding pressure steam generator
US20080115743A1 (en) * 2005-02-16 2008-05-22 Siemens Aktiengesellschaft Continuous Steam Generator
US20080190382A1 (en) * 2005-02-16 2008-08-14 Jan Bruckner Steam Generator in Horizontal Constructional Form
US20110011090A1 (en) * 2008-02-15 2011-01-20 Rudolf Kral Method for starting a continuous steam generator
US20110197830A1 (en) * 2008-09-09 2011-08-18 Brueckner Jan Continuous steam generator
US20110203536A1 (en) * 2008-09-09 2011-08-25 Martin Effert Continuous steam generator
US20110232286A1 (en) * 2010-03-29 2011-09-29 Hitachi, Ltd. Boiler Apparatus
US20130186089A1 (en) * 2010-10-04 2013-07-25 Jan Brückner Continuous flow steam generator having an integrated reheater
US20140123914A1 (en) * 2012-11-08 2014-05-08 Vogt Power International Inc. Once-through steam generator

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6256905U (en) * 1985-09-24 1987-04-08
DE3863153D1 (en) * 1987-09-21 1991-07-11 Siemens Ag METHOD FOR OPERATING A CONTINUOUS STEAM GENERATOR.
JPH0631286Y2 (en) * 1988-07-14 1994-08-22 石川島播磨重工業株式会社 Boiler furnace wall
JPH05644Y2 (en) * 1988-07-28 1993-01-11
JPH08110005A (en) * 1994-10-06 1996-04-30 Ishikawajima Harima Heavy Ind Co Ltd Seal structure for ceiling enclosure of boiler
DE19702133A1 (en) * 1997-01-22 1997-12-11 Siemens Ag Flow-type steam generator e.g for Benson-boiler
EP1710498A1 (en) * 2005-04-05 2006-10-11 Siemens Aktiengesellschaft Steam generator

Patent Citations (80)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2032368A (en) * 1930-04-22 1936-03-03 Babcock & Wilcox Co High pressure boiler
US2201618A (en) * 1933-11-13 1940-05-21 W D La Mont Inc Steam generator
US2201620A (en) * 1933-11-13 1940-05-21 W D La Mont Inc High speed steam producing apparatus
US2170345A (en) * 1935-12-18 1939-08-22 Babcock & Wilcox Co Vapor generator
US2170343A (en) * 1935-12-18 1939-08-22 Babcock & Wilcox Co Vapor generator
US2048393A (en) * 1936-03-16 1936-07-21 Kroger Rudolf Triple service water heater and boiler
US2617394A (en) * 1949-12-30 1952-11-11 Comb Eng Superheater Inc Boiler
US2834324A (en) * 1953-02-12 1958-05-13 Babcock & Wilcox Co Vapor generator with high temperature pendent superheater platens
US2869517A (en) * 1953-09-26 1959-01-20 Sulzer Ag Once through steam generating plant
US2960972A (en) * 1954-05-24 1960-11-22 Babcock & Wilcox Co Apparatus for vapor generating and superheating with recirculated gas flow control of reheat
US2921565A (en) * 1955-12-16 1960-01-19 Babcock & Wilcox Co Steam generating and superheating unit with downshot burners and gas recirculation temperature control
US2982267A (en) * 1956-07-11 1961-05-02 Sulzer Ag High pressure steam plant
US3038453A (en) * 1957-02-07 1962-06-12 Combustion Eng Apparatus and method for controlling a forced flow once-through steam generator
US2947288A (en) * 1957-08-20 1960-08-02 Kohlenscheidungs Gmbh Radiant tubular heat exchanger
US2952975A (en) * 1957-11-15 1960-09-20 Babcock & Wilcox Co Vapor generating and superheating unit
US2980081A (en) * 1958-02-11 1961-04-18 Atomic Energy Authority Uk Apparatus for the exchange of heat between fluids
US3072109A (en) * 1958-05-28 1963-01-08 Foster Wheeler Corp Supercharged vapor generator
US2946187A (en) * 1958-05-28 1960-07-26 Foster Wheeler Corp Gas and steam cycle power plant having twin supercharged vapor generators
US3280559A (en) * 1963-09-26 1966-10-25 Babcock & Wilcox Ltd Ship propulsion power plant
US3267908A (en) * 1965-08-03 1966-08-23 Sulzer Ag Steam generator with flue gas return
US3338219A (en) * 1965-09-09 1967-08-29 Frederick W Riehl Steam generating boiler or steam power plant
US3288117A (en) * 1965-12-01 1966-11-29 Combustion Eng Arrangement of tube circuits in supercritical forced through-flow vapor generator
US3312198A (en) * 1965-12-23 1967-04-04 Combustion Eng Steam generator having improved steam heating sections arranged for parallel flow
US3530836A (en) * 1967-07-13 1970-09-29 Sulzer Ag Forced through-flow steam generator
US3769941A (en) * 1970-12-31 1973-11-06 Sulzer Ag Steam generator
US3841270A (en) * 1972-11-01 1974-10-15 Westinghouse Electric Corp Flow restrictor for an evaporator
US4031404A (en) * 1974-08-08 1977-06-21 Westinghouse Electric Corporation Combined cycle electric power plant and a heat recovery steam generator having improved temperature control of the steam generated
US3955358A (en) * 1974-08-08 1976-05-11 Westinghouse Electric Corporation Combined cycle electric power plant and a heat recovery steam generator with improved fluid level control therefor
US3965675A (en) * 1974-08-08 1976-06-29 Westinghouse Electric Corporation Combined cycle electric power plant and a heat recovery steam generator having improved boiler feed pump flow control
US3974644A (en) * 1974-08-08 1976-08-17 Westinghouse Electric Corporation Combined cycle electric power plant and heat recovery steam generator having improved multi-loop temperature control of the steam generated
US3946566A (en) * 1974-12-16 1976-03-30 Combustion Engineering, Inc. Turbine start-up system
US4020797A (en) * 1975-05-07 1977-05-03 Ofag Ofenbau-Und Feuerungstechnik Ag Process and apparatus for using waste heat of refuse burning installations
US4262636A (en) * 1978-10-03 1981-04-21 Sulzer Brothers Limited Method of starting a forced-flow steam generator
US4290390A (en) * 1978-12-22 1981-09-22 Sulzer Brothers Limited Steam generator
US4501127A (en) * 1980-10-29 1985-02-26 Ruhrgas Aktiengesellschaft Heating system incorporating an absorption-type heat pump and methods for the operation thereof
US4430962A (en) * 1980-12-23 1984-02-14 Sulzer Brothers Ltd. Forced flow vapor generator plant
US4444154A (en) * 1981-04-23 1984-04-24 Sulzer Brothers Limited Steam generator with fluidized bed firing
US4377134A (en) * 1981-08-03 1983-03-22 Combustion Engineering, Inc. Steam temperature control with overfire air firing
US4465021A (en) * 1981-08-22 1984-08-14 Deutsche Babcock Aktiengesellschaft Steam generator with a main boiler and a fluidized bed furnace
US4418652A (en) * 1981-09-15 1983-12-06 Sulzer Brothers Limited Steam generator having a superheater tube bank
US4574744A (en) * 1983-12-23 1986-03-11 Firma Carl Still Gmbh & Co. Kg Waste heat boiler system, and method of generating superheated high pressure steam
US4668344A (en) * 1983-12-23 1987-05-26 Firma Carl Still Gmbh & Co. Kg Method for cooling coke and generating superheated high pressure steam
US4552099A (en) * 1984-10-25 1985-11-12 Westinghouse Electric Corp. Anticipatory boiler feedpump suction head controller system
US5293842A (en) * 1992-03-16 1994-03-15 Siemens Aktiengesellschaft Method for operating a system for steam generation, and steam generator system
US5529021A (en) * 1992-05-04 1996-06-25 Siemens Aktiengesellschaft Forced once-through steam generator
US5979370A (en) * 1994-09-01 1999-11-09 Siemens Aktiengesellschaft Continuous-flow steam generator
US5839396A (en) * 1995-02-09 1998-11-24 Siemens Aktiengesellschaft Method and apparatus for starting up a continuous-flow steam generator
US5983639A (en) * 1995-03-02 1999-11-16 Siemens Aktiengesellschaft Method and system for starting up a continuous flow steam generator
US5787844A (en) * 1995-03-06 1998-08-04 Ahlstrom Machinery Oy Economizer system
US5950574A (en) * 1996-12-17 1999-09-14 Babcock-Hitachi Kabushiki Kaisha Boiler
US6192837B1 (en) * 1997-04-23 2001-02-27 Siemens Aktiengesellschaft Once-through steam generator and method for starting up a once-through steam generator
US5762031A (en) * 1997-04-28 1998-06-09 Gurevich; Arkadiy M. Vertical drum-type boiler with enhanced circulation
US20050120715A1 (en) * 1997-12-23 2005-06-09 Christion School Of Technology Charitable Foundation Trust Heat energy recapture and recycle and its new applications
US20080155985A1 (en) * 1997-12-23 2008-07-03 Gaudencio Aquino Labrador Heat Energy Recapture And Recycle And Its New Applications
US6557499B2 (en) * 1998-06-10 2003-05-06 Siemens Aktiengesellschaft Fossil-fuel-fired once-through steam generator
US20020157618A1 (en) * 1998-06-10 2002-10-31 Joachim Franke Fossil-fuel-fired once-through steam generator
US6019070A (en) * 1998-12-03 2000-02-01 Duffy; Thomas E. Circuit assembly for once-through steam generators
US6446580B2 (en) * 1998-12-18 2002-09-10 Siemens Aktiengesellschaft Fossil fuel-fired continuous-flow steam generator
US20020000208A1 (en) * 1998-12-18 2002-01-03 Joachim Franke Fossil fuel-fired continuous-flow steam generator
US6105369A (en) * 1999-01-13 2000-08-22 Abb Alstom Power Inc. Hybrid dual cycle vapor generation
US20020026906A1 (en) * 1999-01-18 2002-03-07 Joachim Franke Fossil-fired steam generator
US20020026905A1 (en) * 1999-01-18 2002-03-07 Joachim Franke Fossil-fuel-fired steam generator
US6446584B1 (en) * 1999-01-18 2002-09-10 Siemens Aktiengesellschaft Fossil-fuel-fired steam generator
US6499440B2 (en) * 1999-01-18 2002-12-31 Siemens Aktiengesellschaft Fossil-fired steam generator
US20020017251A1 (en) * 1999-03-31 2002-02-14 Eberhard Wittchow Fossil-fired continuous-flow steam generator
US6715450B1 (en) * 1999-03-31 2004-04-06 Siemens Aktiengesellschaft Fossil-fuel fired continuous-flow steam generator
US6481386B2 (en) * 1999-03-31 2002-11-19 Siemens Aktiengellschaft Fossil-fired continuous-flow steam generator
US6536380B1 (en) * 1999-06-24 2003-03-25 Siemens Aktiengesellschaft Fossil-fuel heated steam generator, comprising dentrification device for heating gas
US6253714B1 (en) * 1999-09-08 2001-07-03 Bbp Energy Gmbh Steam generator
US20040219079A1 (en) * 2003-01-22 2004-11-04 Hagen David L Trifluid reactor
US20080115743A1 (en) * 2005-02-16 2008-05-22 Siemens Aktiengesellschaft Continuous Steam Generator
US20080190382A1 (en) * 2005-02-16 2008-08-14 Jan Bruckner Steam Generator in Horizontal Constructional Form
US20070283906A1 (en) * 2006-06-07 2007-12-13 Albrecht Melvin J Circulation system for sliding pressure steam generator
US7587996B2 (en) * 2006-06-07 2009-09-15 Babcock & Wilcox Power Generation Group, Inc. Circulation system for sliding pressure steam generator
US20110011090A1 (en) * 2008-02-15 2011-01-20 Rudolf Kral Method for starting a continuous steam generator
US20110197830A1 (en) * 2008-09-09 2011-08-18 Brueckner Jan Continuous steam generator
US20110203536A1 (en) * 2008-09-09 2011-08-25 Martin Effert Continuous steam generator
US20110232286A1 (en) * 2010-03-29 2011-09-29 Hitachi, Ltd. Boiler Apparatus
US20130186089A1 (en) * 2010-10-04 2013-07-25 Jan Brückner Continuous flow steam generator having an integrated reheater
US20140123914A1 (en) * 2012-11-08 2014-05-08 Vogt Power International Inc. Once-through steam generator

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110197830A1 (en) * 2008-09-09 2011-08-18 Brueckner Jan Continuous steam generator
US9267678B2 (en) * 2008-09-09 2016-02-23 Siemens Aktiengesellschaft Continuous steam generator
US9671105B2 (en) * 2013-08-06 2017-06-06 Siemens Aktiengesellschaft Continuous flow steam generator with a two-pass boiler design
US9920924B2 (en) * 2016-04-05 2018-03-20 The Babcock & Wilcox Company High temperature sub-critical boiler with steam cooled upper furnace and start-up methods

Also Published As

Publication number Publication date
CN102149970A (en) 2011-08-10
EP2324287B1 (en) 2016-11-02
JP2012502250A (en) 2012-01-26
WO2010029022A3 (en) 2010-05-27
JP5345217B2 (en) 2013-11-20
EP2182278A1 (en) 2010-05-05
EP2324287A2 (en) 2011-05-25
DK2324287T3 (en) 2017-02-06
WO2010029022A2 (en) 2010-03-18
AU2009290944B2 (en) 2014-04-17
CN102149970B (en) 2016-08-03
AU2009290944A1 (en) 2010-03-18

Similar Documents

Publication Publication Date Title
US7628124B2 (en) Steam generator in horizontal constructional form
CN102889570B (en) Tower-type boiler with primary reheater and secondary reheater
RU2310121C2 (en) Steam generator
US9267678B2 (en) Continuous steam generator
AU2009290944B2 (en) Continuous steam generator
AU2009290998B2 (en) Continuous steam generator
RU2217654C2 (en) Parallel-current steam generator operating on fossil fuel
RU2396486C1 (en) Reactor feed water circuit with fluidised bed and reactor with fluidised bed with such feed water circuit
KR101663850B1 (en) Continuous evaporator
CA2368972C (en) Fossil-fired continuous-flow steam generator
US5901669A (en) Variable pressure once-through steam generator upper furnace having non-split flow circuitry
US8851023B2 (en) Continuous steam generator
KR20140003372A (en) Forced-flow steam generator
AU2011287836B2 (en) Forced-flow steam generator
US7243619B2 (en) Dual pressure recovery boiler
CA2546375A1 (en) Continuous steam generator
Basu et al. Forced Circulation for Supercritical or Subcritical Boilers

Legal Events

Date Code Title Description
AS Assignment

Owner name: SIEMENS AKTIENGESELLSCHAFT, GERMANY

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:EFFERT, MARTIN;FRANKE, JOACHIM;THOMAS, FRANK;SIGNING DATES FROM 20110217 TO 20110221;REEL/FRAME:025916/0381

STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION