US20030167727A1 - Building construction method - Google Patents
Building construction method Download PDFInfo
- Publication number
- US20030167727A1 US20030167727A1 US10/093,194 US9319402A US2003167727A1 US 20030167727 A1 US20030167727 A1 US 20030167727A1 US 9319402 A US9319402 A US 9319402A US 2003167727 A1 US2003167727 A1 US 2003167727A1
- Authority
- US
- United States
- Prior art keywords
- framework
- construction method
- building construction
- pile
- building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
- E02D27/14—Pile framings, i.e. piles assembled to form the substructure
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/24—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/58—Connections for building structures in general of bar-shaped building elements
- E04B1/5825—Connections for building structures in general of bar-shaped building elements with a closed cross-section
- E04B1/5837—Connections for building structures in general of bar-shaped building elements with a closed cross-section of substantially circular form
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/24—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
- E04B1/2403—Connection details of the elongated load-supporting parts
- E04B2001/2406—Connection nodes
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/24—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
- E04B1/2403—Connection details of the elongated load-supporting parts
- E04B2001/2451—Connections between closed section profiles
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/24—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
- E04B1/2403—Connection details of the elongated load-supporting parts
- E04B2001/2457—Beam to beam connections
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/24—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
- E04B1/2403—Connection details of the elongated load-supporting parts
- E04B2001/2463—Connections to foundations
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/24—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
- E04B2001/2481—Details of wall panels
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/24—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
- E04B2001/2484—Details of floor panels or slabs
Definitions
- the invention relates to a construction method suitable for constructing low-rise buildings.
- the object of the invention is to provide a construction method that facilitates the construction of low-rise buildings at a relatively low cost.
- the building construction method of this invention includes the steps of:
- each of the pile connecting beams having opposite ends connected to the lateral beam connecting parts of the pile connectors on the upper pile portions of an adjacent pair of the piles, and
- FIG. 1 is a flow diagram of the preferred embodiment of the building construction method according to this invention.
- FIGS. 2 to 11 illustrate how a building is constructed according to the preferred embodiment of the method shown in FIG. 1.
- the preferred embodiment of the building construction method according to this invention is shown to comprise the steps of:
- a ground surface 10 of a building site is divided into a plurality of polygonal areas 100 , and a plurality of pile holes 11 are formed in the ground surface 10 .
- Each of the pile holes 11 is disposed in a respective corner of one of the polygonal areas 100 .
- each of the pile holes 11 is then filled with concrete 13 such that the piles 12 have lower pile portions 121 ′ that are fixed in the pile holes 11 , and upper pile portions 121 that protrude upwardly and outwardly from the concrete 13 in the respective one of the pile holes 11 .
- each of the piles 12 is made of quenched steel and has a roughened periphery 122 for secure engagement with the concrete 13 in the respective one of the pile holes 11 .
- trenches 11 ′ are formed in the ground surface 10 along boundaries of the polygonal areas 100 such that the upper pile portions 121 of the piles 12 are disposed in the trenches 11 ′.
- a plurality of pile connectors 14 are mounted on the upper pile portions 121 of the piles 12 such that the pile connectors 14 have lateral beam connecting parts 141 that are disposed in the trenches 11 ′, and vertical framework connecting parts 142 that project upwardly from the ground surface 10 .
- a plurality of pile connecting beams 20 are subsequently installed in the trenches 11 ′. Each of the pile connecting beams 20 (only one is shown in FIG.
- each of the pile connecting beams 20 includes a first beam member 201 and a second beam member 202 , each of which has an insert end 203 retained in the lateral beam connecting part 141 of one of the pile connectors 14 , and a coupling end 204 coupled to the other of the first and second beam members 201 , 202 .
- the first and second beam members 201 , 202 are preferably made of quenched steel. Referring to FIG.
- each of the pile connecting beams 20 further includes a beam coupler 41 , which has a first sleeve 412 secured to the coupling end 204 of the first beam member 201 , a second sleeve 413 secured to the coupling end 204 of the second beam member 202 , and a third sleeve 411 threadedly engaging the second sleeve 413 and urging the first sleeve 412 to abut tightly against the second sleeve 413 .
- a concrete ground floor structure is formed on the ground surface 10 on top of each of the polygonal areas 100 .
- the concrete ground floor structure is formed by laying a ground floor grid 15 on the ground surface 10 on top of each of the polygonal areas 100 , and by applying a layer of concrete 31 to embed the ground floor grid 15 therein and to form a ground floor surface of the ground floor structure 300 .
- FIGS. 3 and 4 a building framework is erected in the following manner:
- Lower ends 4011 of a plurality of framework columns 401 are connected to the vertical framework connecting parts 142 of the pile connectors 14 .
- a plurality of framework connectors 50 are mounted on upper ends 4012 of the framework columns 401 .
- a plurality of framework beams 402 are then installed.
- Each of the framework beams 402 has opposite ends 4021 connected to the framework connectors 50 on the upper ends 4012 of an adjacent pair of the framework columns 401 .
- the lower ends 4011 of a plurality of framework columns 401 are connected to the framework connectors 50 on the upper ends 4012 of the framework columns 401 of the lower frame structure.
- a plurality of framework connectors 50 are mounted on upper ends 4012 of the framework columns 401 of the upper framework structure.
- a plurality of framework beams 402 are then installed.
- Each of the framework beams 402 has opposite ends connected to the framework connectors 50 on the upper ends 4012 of an adjacent pair of the framework columns 401 of the upper frame structure.
- each of the framework columns 401 and the framework beams 402 includes a first beam member 201 and a second beam member 202 , each of which has a coupling end 204 coupled to the other of the first and second beam members 201 , 202 .
- the first and second beam members 201 , 202 are preferably made of quenched steel.
- Each of the framework columns 401 and the framework beams 402 further includes a beam coupler 41 , which has a first sleeve 412 secured to the coupling end 204 of the first beam member 201 , a second sleeve 413 secured to the coupling end 204 of the second beam member 202 , and a third sleeve 411 threadedly engaging the second sleeve 413 and urging the first sleeve 412 to abut tightly against the second sleeve 413 .
- each of the vertical wall grids 60 is secured to an adjacent pair of the framework columns 401 and to an adjacent pair of the framework beams 402 .
- each of the vertical wall grids 60 is one of a channel beam grid, an H-beam grid and an I-beam grid, and is made of quenched steel.
- each of the vertical wall grids 60 is welded to L-shaped braces 43 that are fixed on the framework columns 401 and the framework beams 402 of the building framework. As shown in FIG.
- each of the vertical wall grids 60 is welded to channel supports 43 ′ that are fixed on the framework columns 401 and the framework beams 402 of the building framework.
- the pre-cast vertical slabs 70 are then mounted on opposite sides of the vertical wall grids 60 by high-impact nailing. Insulating material (not shown) can be further installed in the space confined by opposite pairs of the pre-cast vertical slabs 70 for sound insulation purposes.
- concrete 64 can be poured into a concrete pouring space confined by the pre-cast vertical slabs 70 on the opposite sides of the vertical wall grids 60 .
- each of the vertical wall grids 60 is formed with a plurality of holes 63 in horizontal parts 62 thereof so that the concrete 64 can pass through the holes 63 for enhancing the engagement among the aforesaid wall constituting components.
- each of the horizontal floor grids 60 ′ is one of a channel beam grid, an H-beam grid and an I-beam grid, and is made of quenched steel.
- each of the horizontal floor grids 60 ′ is welded to L-shaped braces 43 that are fixed on the framework beams 402 of the building framework.
- each of the horizontal floor grids 60 ′ is welded to channel supports 43 ′ that are fixed on the framework beams 402 of the building framework.
- the pre-cast horizontal slabs 70 ′ are mounted on a lower side of the horizontal floor grids 60 ′ by high-impact nailing. Concrete 65 is then poured on top of the pre-cast horizontal slabs 70 ′ to embed the horizontal floor grids 60 ′ therein and to form an upper floor surface. As shown in FIG. 11, in a further embodiment, the pre-cast horizontal slabs 70 ′ are mounted on opposite sides of the horizontal floor grids 60 ′ by high-impact nailing. Similar to the walls 80 of FIG. 8, insulating material (not shown) can be further installed in the space confined by opposite pairs of the pre-cast horizontal slabs 70 ′ for sound insulation purposes.
- electrical wiring and water distribution pipes can be disposed in the space confined by the opposite pairs of the pre-cast horizontal and vertical slabs 70 ′, 70 .
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
A building construction method includes the steps of forming pile holes, installing piles, installing pile connecting beams, forming a concrete ground floor structure, erecting a building framework, forming walls on the building framework, and forming floors on the building framework. The construction method facilitates the construction of low-rise buildings at a relatively low cost.
Description
- The invention relates to a construction method suitable for constructing low-rise buildings.
- The object of the invention is to provide a construction method that facilitates the construction of low-rise buildings at a relatively low cost.
- Accordingly, the building construction method of this invention includes the steps of:
- (a) dividing a ground surface of a building site into a plurality of polygonal areas, and forming a plurality of pile holes in the ground surface, each of the pile holes being disposed in a respective corner of one of the polygonal areas;
- (b) installing a pile in each of the pile holes, and filling each of the pile holes with concrete such that the piles have lower pile portions that are fixed in the pile holes, and upper pile portions that protrude upwardly and outwardly from the concrete in the respective one of the pile holes;
- (c) forming trenches in the ground surface along boundaries of the polygonal areas such that the upper pile portions of the piles are disposed in the trenches,
- mounting a plurality of pile connectors on the upper pile portions of the piles such that the pile connectors have lateral beam connecting parts that are disposed in the trenches, and vertical framework connecting parts that project upwardly from the ground surface,
- installing a plurality of pile connecting beams in the trenches, each of the pile connecting beams having opposite ends connected to the lateral beam connecting parts of the pile connectors on the upper pile portions of an adjacent pair of the piles, and
- filling the trenches with concrete to embed the lateral beam connecting parts of the pile connectors and the pile connecting beams therein;
- (d) forming a concrete ground floor structure on the ground surface on top of each of the polygonal areas;
- (e) erecting a building framework including the sub-step of forming a lower frame structure by
- connecting lower ends of a plurality of framework columns to the vertical framework connecting parts of the pile connectors,
- mounting a plurality of framework connectors on upper ends of the framework columns, and
- installing a plurality of framework beams, each having opposite ends connected to the framework connectors on the upper ends of an adjacent pair of the framework columns;
- (f) forming walls on the building framework by mounting pre-cast vertical slabs thereon; and
- (g) forming floors on the building framework by mounting pre-cast horizontal slabs thereon.
- Other features and advantages of the present invention will become apparent in the following detailed description of the preferred embodiments with reference to the accompanying drawings, of which:
- FIG. 1 is a flow diagram of the preferred embodiment of the building construction method according to this invention; and
- FIGS.2 to 11 illustrate how a building is constructed according to the preferred embodiment of the method shown in FIG. 1.
- Referring to FIG. 1, the preferred embodiment of the building construction method according to this invention is shown to comprise the steps of:
- (a) Forming pile holes11:
- With further reference to FIG. 2, a
ground surface 10 of a building site is divided into a plurality ofpolygonal areas 100, and a plurality ofpile holes 11 are formed in theground surface 10. Each of thepile holes 11 is disposed in a respective corner of one of thepolygonal areas 100. - (b) Installing piles12:
- With further reference to FIG. 3, after installing a pile12 in each of the
pile holes 11, each of thepile holes 11 is then filled with concrete 13 such that the piles 12 havelower pile portions 121′ that are fixed in thepile holes 11, andupper pile portions 121 that protrude upwardly and outwardly from the concrete 13 in the respective one of thepile holes 11. Preferably, each of the piles 12 is made of quenched steel and has a roughenedperiphery 122 for secure engagement with the concrete 13 in the respective one of thepile holes 11. - (c) Installing pile connecting beams20:
- Referring to FIGS. 2 and 3,
trenches 11′ are formed in theground surface 10 along boundaries of thepolygonal areas 100 such that theupper pile portions 121 of the piles 12 are disposed in thetrenches 11′. A plurality ofpile connectors 14 are mounted on theupper pile portions 121 of the piles 12 such that thepile connectors 14 have lateralbeam connecting parts 141 that are disposed in thetrenches 11′, and verticalframework connecting parts 142 that project upwardly from theground surface 10. A plurality ofpile connecting beams 20 are subsequently installed in thetrenches 11′. Each of the pile connecting beams 20 (only one is shown in FIG. 3) has opposite ends connected to the lateralbeam connecting parts 141 of thepile connectors 14 on theupper pile portions 121 of an adjacent pair of the piles 12. Thetrenches 11′ are then filled with concrete to embed the lateralbeam connecting parts 141 of thepile connectors 14 and thepile connecting beams 20 therein. - Preferably, the lateral
beam connecting part 141 of each of thepile connectors 14 is tubular, and each of thepile connecting beams 20 includes afirst beam member 201 and asecond beam member 202, each of which has aninsert end 203 retained in the lateralbeam connecting part 141 of one of thepile connectors 14, and acoupling end 204 coupled to the other of the first andsecond beam members second beam members pile connecting beams 20 further includes abeam coupler 41, which has afirst sleeve 412 secured to thecoupling end 204 of thefirst beam member 201, asecond sleeve 413 secured to thecoupling end 204 of thesecond beam member 202, and athird sleeve 411 threadedly engaging thesecond sleeve 413 and urging thefirst sleeve 412 to abut tightly against thesecond sleeve 413. - (d) Forming a concrete ground floor structure:
- A concrete ground floor structure is formed on the
ground surface 10 on top of each of thepolygonal areas 100. Referring once again to FIG. 3, the concrete ground floor structure is formed by laying aground floor grid 15 on theground surface 10 on top of each of thepolygonal areas 100, and by applying a layer ofconcrete 31 to embed theground floor grid 15 therein and to form a ground floor surface of theground floor structure 300. - (e) Erecting a building framework:
- Referring to FIGS. 3 and 4, a building framework is erected in the following manner:
- (e1) Forming a lower frame structure:
-
Lower ends 4011 of a plurality offramework columns 401 are connected to the verticalframework connecting parts 142 of thepile connectors 14. A plurality offramework connectors 50 are mounted onupper ends 4012 of theframework columns 401. A plurality offramework beams 402 are then installed. Each of theframework beams 402 hasopposite ends 4021 connected to theframework connectors 50 on theupper ends 4012 of an adjacent pair of theframework columns 401. - (e2) Forming an upper frame structure:
- The
lower ends 4011 of a plurality offramework columns 401 are connected to theframework connectors 50 on theupper ends 4012 of theframework columns 401 of the lower frame structure. A plurality offramework connectors 50 are mounted onupper ends 4012 of theframework columns 401 of the upper framework structure. A plurality offramework beams 402 are then installed. Each of theframework beams 402 has opposite ends connected to theframework connectors 50 on theupper ends 4012 of an adjacent pair of theframework columns 401 of the upper frame structure. - The sub-step of forming the upper frame structure is repeated until a required number of stories is obtained, as shown in FIG. 5.
- Referring again to FIG. 4, similar to the
pile connecting beam 20, each of theframework columns 401 and theframework beams 402 includes afirst beam member 201 and asecond beam member 202, each of which has acoupling end 204 coupled to the other of the first andsecond beam members second beam members framework columns 401 and theframework beams 402 further includes abeam coupler 41, which has afirst sleeve 412 secured to thecoupling end 204 of thefirst beam member 201, asecond sleeve 413 secured to thecoupling end 204 of thesecond beam member 202, and athird sleeve 411 threadedly engaging thesecond sleeve 413 and urging thefirst sleeve 412 to abut tightly against thesecond sleeve 413. - (f) Forming
walls 80 on the building framework: - Referring to FIGS.6 to 8, a plurality of
vertical wall grids 60 are installed on the building framework. Each of thevertical wall grids 60 is secured to an adjacent pair of theframework columns 401 and to an adjacent pair of theframework beams 402. Preferably, each of thevertical wall grids 60 is one of a channel beam grid, an H-beam grid and an I-beam grid, and is made of quenched steel. In the embodiment shown in FIG. 6, each of thevertical wall grids 60 is welded to L-shaped braces 43 that are fixed on theframework columns 401 and theframework beams 402 of the building framework. As shown in FIG. 7, in a modified embodiment, each of thevertical wall grids 60 is welded to channel supports 43′ that are fixed on theframework columns 401 and theframework beams 402 of the building framework. The pre-castvertical slabs 70 are then mounted on opposite sides of thevertical wall grids 60 by high-impact nailing. Insulating material (not shown) can be further installed in the space confined by opposite pairs of the pre-castvertical slabs 70 for sound insulation purposes. As shown in FIG. 9, in yet another embodiment, concrete 64 can be poured into a concrete pouring space confined by the pre-castvertical slabs 70 on the opposite sides of thevertical wall grids 60. Preferably, each of thevertical wall grids 60 is formed with a plurality ofholes 63 inhorizontal parts 62 thereof so that the concrete 64 can pass through theholes 63 for enhancing the engagement among the aforesaid wall constituting components. - (g) Forming
floors 90 on the building framework: - Referring to FIGS. 6 and 7, a plurality of
horizontal floor grids 60′ are installed on the framework beams 402 of the building framework. Preferably, each of thehorizontal floor grids 60′ is one of a channel beam grid, an H-beam grid and an I-beam grid, and is made of quenched steel. In the embodiment of FIG. 6, each of thehorizontal floor grids 60′ is welded to L-shapedbraces 43 that are fixed on the framework beams 402 of the building framework. As shown in FIG. 7, in a modified embodiment, each of thehorizontal floor grids 60′ is welded to channel supports 43′ that are fixed on the framework beams 402 of the building framework. Referring to FIG. 10, the pre-casthorizontal slabs 70′ are mounted on a lower side of thehorizontal floor grids 60′ by high-impact nailing.Concrete 65 is then poured on top of the pre-casthorizontal slabs 70′ to embed thehorizontal floor grids 60′ therein and to form an upper floor surface. As shown in FIG. 11, in a further embodiment, the pre-casthorizontal slabs 70′ are mounted on opposite sides of thehorizontal floor grids 60′ by high-impact nailing. Similar to thewalls 80 of FIG. 8, insulating material (not shown) can be further installed in the space confined by opposite pairs of the pre-casthorizontal slabs 70′ for sound insulation purposes. - In the embodiments of FIGS.8 to 11, electrical wiring and water distribution pipes can be disposed in the space confined by the opposite pairs of the pre-cast horizontal and
vertical slabs 70′, 70. - While the present invention has been described in connection with what is considered the most practical and preferred embodiments, it is understood that this invention is not limited to the disclosed embodiments but is intended to cover various arrangements included within the spirit and scope of the broadest interpretation so as to encompass all such modifications and equivalent arrangements.
Claims (30)
1. A building construction method, comprising the steps of:
(a) dividing a ground surface of a building site into a plurality of polygonal areas, and forming a plurality of pile holes in the ground surface, each of the pile holes being disposed in a respective corner of one of the polygonal areas;
(b) installing a pile in each of the pile holes, and filling each of the pile holes with concrete such that the piles have lower pile portions that are fixed in the pile holes, and upper pile portions that protrude upwardly and outwardly from the concrete in the respective one of the pile holes;
(c) forming trenches in the ground surface along boundaries of the polygonal areas such that the upper pile portions of the piles are disposedin the trenches,
mounting a plurality of pile connectors on the upper pile portions of the piles such that the pile connectors have lateral beam connecting parts that are disposed in the trenches, and vertical framework connecting parts that project upwardly from the ground surface,
installing a plurality of pile connecting beams in the trenches, each of the pile connecting beams having opposite ends connected to the lateral beam connecting parts of the pile connectors on the upper pile portions of an adjacent pair of the piles, and
filling the trenches with concrete to embed the lateral beam connecting parts of the pile connectors and the pile connecting beams therein;
(d) forming a concrete ground floor structure on the ground surface on top of each of the polygonal areas;
(e) erecting a building framework including the sub-step of forming a lower frame structure by
connecting lower ends of a plurality of framework columns to the vertical framework connecting parts of the pile connectors,
mounting a plurality of framework connectors on upper ends of the framework columns, and
installing a plurality of framework beams, each having opposite ends connected to the framework connectors on the upper ends of an adjacent pair of the framework columns;
(f) forming walls on the building framework by mounting pre-cast vertical slabs thereon; and
(g) forming floors on the building framework by mounting pre-cast horizontal slabs thereon.
2. The building construction method as claimed in claim 1 , wherein the piles are made of quenched steel.
3. The building construction method as claimed in claim 1 , wherein each of the piles has a roughened periphery for secure engagement with the concrete in the respective one of the pile holes.
4. The building construction method as claimed in claim 1 , wherein the lateral beam connecting part of each of the pile connectors is tubular, and each of the pile connecting beams includes a first beam member and a second beam member, each of which has an insert end retained in the lateral beam connecting part of one of the pile connectors, and a coupling end coupled to the other of the first and second beam members.
5. The building construction method as claimed in claim 4 , wherein each of the pile connecting beams further includes a beam coupler having
a first sleeve secured to the coupling end of the first beam member,
a second sleeve secured to the coupling end of the second beam member, and
a third sleeve threadedly engaging the second sleeve and urging the first sleeve to abut tightly against the second sleeve.
6. The building construction method as claimed in claim 4 , wherein the first and second beam members are made of quenched steel.
7. The building construction method as claimed in claim 1 , wherein said step (d) includes the sub-steps of laying a ground floor grid on the ground surface on top of each of the polygonal areas, and applying a layer of concrete to embed the ground floor grid therein and to form a ground floor surface of the ground floor structure.
8. The building construction method as claimed in claim 1 , wherein said step (e) further includes the sub-step of forming an upper frame structure by
connecting lower ends of a plurality of framework columns to the framework connectors on the upper ends of the framework columns of the lower frame structure,
mounting a plurality of framework connectors on upper ends of the framework columns of the upper framework structure, and
installing a plurality of framework beams, each having opposite ends connected to the framework connectors on the upper ends of an adjacent pair of the framework columns of the upper frame structure.
9. The building construction method as claimed in claim 8 , wherein the sub-step of forming the upper frame structure is repeated until a required number of stories is obtained.
10. The building construction method as claimed in claim 8 , wherein each of the framework columns and the framework beams includes a first beam member and a second beam member, each of which has a coupling end coupled to the other of the first and second beam members.
11. The building construction method as claimed in claim 10 , wherein each of the framework columns and the framework beams further includes a beam coupler having
a first sleeve secured to the coupling end of the first beam member,
a second sleeve secured to the coupling end of the second beam member, and
a third sleeve threadedly engaging the second sleeve and urging the first sleeve to abut tightly against the second sleeve.
12. The building construction method as claimed in claim 10 , wherein the first and second beam members are made of quenched steel.
13. The building construction method as claimed in claim 8 , wherein said step (f) includes the sub-step of installing a plurality of vertical wall grids on the building framework, each of the vertical wall grids being secured to an adjacent pair of the framework columns and to an adjacent pair of the framework beams.
14. The building construction method as claimed in claim 13 , wherein the pre-cast vertical slabs are mounted on opposite sides of the vertical wall grids.
15. The building construction method as claimed in claim 14 , wherein the pre-cast vertical slabs are nailed to the vertical wall grids.
16. The building construction method as claimed in claim 13 , wherein said step (f) further includes the sub-step of pouring concrete into a concrete pouring space confined by the pre-cast vertical slabs on the opposite sides of the vertical wall grids.
17. The building construction method as claimed in claim 13 , wherein each of the vertical wall grids is welded to L-shaped braces on the framework columns and the framework beams of the building framework.
18. The building construction method as claimed in claim 13 , wherein each of the vertical wall grids is welded to channel supports on the framework columns and the framework beams of the building framework.
19. The building construction method as claimed in claim 13 , wherein each of the vertical wall grids is one of a channel beam grid, an H-beam grid and an I-beam grid.
20. The building construction method as claimed in claim 13 , wherein each of the vertical wall grids is made of quenched steel.
21. The building construction method as claimed in claim 8 , wherein said step (g) includes the sub-step of installing a plurality of horizontal floor grids on the framework beams of the building framework.
22. The building construction method as claimed in claim 21 , wherein the pre-cast horizontal slabs are mounted on a lower side of the horizontal floor grids.
23. The building construction method as claimed in claim 22 , wherein the pre-cast horizontal slabs are nailed to the horizontal floor grids.
24. The building construction method as claimed in claim 22 , wherein said step (f) further includes the sub-step of pouring concrete on top of the pre-cast horizontal slabs to embed the horizontal floor grids therein and to form an upper floor surface.
25. The building construction method as claimed in claim 21 , wherein the pre-cast horizontal slabs are mounted on opposite sides of the horizontal floor grids.
26. The building construction method as claimed in claim 25 , wherein the pre-cast horizontal slabs are nailed to the horizontal floor grids.
27. The building construction method as claimed in claim 21 , wherein each of the horizontal floor grids is welded to L-shaped braces on the framework beams of the building framework.
28. The building construction method as claimed in claim 21 , wherein each of the horizontal floor grids is welded to channel supports on the framework beams of the building framework.
29. The building construction method as claimed in claim 21 , wherein each of the horizontal floor grids is one of a channel beam grid, an H-beam grid and an I-beam grid.
30. The building construction method as claimed in claim 21 , wherein each of the horizontal floor grids is made of quenched steel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US10/093,194 US20030167727A1 (en) | 2002-03-07 | 2002-03-07 | Building construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US10/093,194 US20030167727A1 (en) | 2002-03-07 | 2002-03-07 | Building construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
US20030167727A1 true US20030167727A1 (en) | 2003-09-11 |
Family
ID=27787939
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US10/093,194 Abandoned US20030167727A1 (en) | 2002-03-07 | 2002-03-07 | Building construction method |
Country Status (1)
Country | Link |
---|---|
US (1) | US20030167727A1 (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2007060291A1 (en) * | 2005-11-23 | 2007-05-31 | Rautaruukki Oyj | Foundation arrangement |
US20080072529A1 (en) * | 2003-03-07 | 2008-03-27 | Morgan Buildings | Hinged support column |
CN104499715A (en) * | 2014-12-08 | 2015-04-08 | 江苏中南建筑产业集团有限责任公司 | Template overhanging construction method for floor system with composite structure by utilizing profiled steel beams |
CN104878926A (en) * | 2015-06-16 | 2015-09-02 | 中建八局第三建设有限公司 | Suspended template system construction method and turnover brackets |
IT201700042061A1 (en) * | 2017-04-14 | 2018-10-14 | Nicola Panizza | FORM FOR THE REALIZATION OF A BUILDING UNIT |
CN114164963A (en) * | 2021-09-30 | 2022-03-11 | 航天建筑设计研究院有限公司 | Shear force wall building structure |
Citations (33)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2571337A (en) * | 1948-01-28 | 1951-10-16 | James H Burnham | Boat dock and the like |
US2625815A (en) * | 1943-10-23 | 1953-01-20 | Eric A Black | Adjustable anchorage |
US2726866A (en) * | 1953-06-18 | 1955-12-13 | Nally Duke Howe | Knock-down platform construction |
US2780935A (en) * | 1951-12-11 | 1957-02-12 | Roy W Rumble | Method of making a floor slab |
US2801716A (en) * | 1952-03-19 | 1957-08-06 | Nat Steel Corp | Foundation unit and building including same |
US3848377A (en) * | 1973-02-09 | 1974-11-19 | M Mori | Mat foundation |
US4074537A (en) * | 1977-05-18 | 1978-02-21 | John Peter Gronlie | Dock bracket |
US4107889A (en) * | 1976-03-01 | 1978-08-22 | Gonsalves, Santucci, Inc. | Foundation system |
US4124963A (en) * | 1977-02-08 | 1978-11-14 | Tadayasu Higuchi | Method for forming a continuous footing |
US4485598A (en) * | 1979-02-05 | 1984-12-04 | Eustachio Guardiani | Prefabricated elements and rooms for the quick construction of buildings and building works in general |
US4538386A (en) * | 1984-09-04 | 1985-09-03 | Ohio State Home Services, Inc. | Drainage system and method |
US4653239A (en) * | 1984-04-12 | 1987-03-31 | Randa Wallace H | Pre-engineered building and method of assembling same |
US4683689A (en) * | 1985-07-05 | 1987-08-04 | Loggy Albert D | Modular reinforced building structure and method |
US4886399A (en) * | 1987-02-12 | 1989-12-12 | Pidgeon John T | Method of constructing a foundation for buildings |
US5067289A (en) * | 1990-06-28 | 1991-11-26 | Ouderkirk Dale L | Foundation system for manufactured housing |
US5096333A (en) * | 1990-04-27 | 1992-03-17 | Jeanne Bassett | Foundation repair method and apparatus |
US5103613A (en) * | 1990-08-30 | 1992-04-14 | Satoru Kinoshita | Foundation for wooden house |
US5224799A (en) * | 1990-10-03 | 1993-07-06 | Parker Alton F | Permanently installed building foundation form |
US5367845A (en) * | 1993-02-09 | 1994-11-29 | Hartling; Robert H. | System for building a structure |
US5685114A (en) * | 1995-03-20 | 1997-11-11 | Tanaka Masakatsu Design Office Co., Ltd. | Structural member, floor structure, and roof structure for wooden building and a method of building with the same |
US5733470A (en) * | 1993-09-24 | 1998-03-31 | Siroflex Of America, Inc. | Mold for casting ground covering |
US5735090A (en) * | 1995-08-08 | 1998-04-07 | Papke; William | Modular foundation construction and method |
US5755064A (en) * | 1996-03-26 | 1998-05-26 | Bay Apartment Communities, Inc. | Carport enclosure with one or more garage doors |
US5848507A (en) * | 1997-08-21 | 1998-12-15 | Malton Equipment Company | Enclosure with externally mounted adjustable foundations |
US5934036A (en) * | 1996-11-01 | 1999-08-10 | Gallagher, Jr.; Daniel P. | Insulated concrete slab assembly |
US6168031B1 (en) * | 1998-12-03 | 2001-01-02 | Fulterer Usa, Inc. | Hanging file support apparatus |
US6205720B1 (en) * | 1997-12-24 | 2001-03-27 | Daryl R. Wolfrum | Foundation panel and method of assembly |
US6314693B1 (en) * | 1998-09-03 | 2001-11-13 | Sanders Pre-Cast Concrete Systems. | Building foundation using pre-cast concrete elements |
US6322045B1 (en) * | 1997-08-04 | 2001-11-27 | Chris Andros | Rapid forming system for tilt-up pre-cast concrete wall panels (tilt panel screed system-tipss) |
US6332303B1 (en) * | 2000-02-28 | 2001-12-25 | Nic Engineering Co., Ltd. | Method of building underground structure |
US6341459B1 (en) * | 2000-03-08 | 2002-01-29 | Bobby L. Bates | Method and apparatus for expedited construction of a building |
US6370835B1 (en) * | 1999-06-15 | 2002-04-16 | Robust Building Systems, Inc. | Method and apparatus for low cost housing construction |
US6540445B1 (en) * | 2001-03-01 | 2003-04-01 | Eldon Boyd Evans, Jr. | Concrete silt fence |
-
2002
- 2002-03-07 US US10/093,194 patent/US20030167727A1/en not_active Abandoned
Patent Citations (33)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2625815A (en) * | 1943-10-23 | 1953-01-20 | Eric A Black | Adjustable anchorage |
US2571337A (en) * | 1948-01-28 | 1951-10-16 | James H Burnham | Boat dock and the like |
US2780935A (en) * | 1951-12-11 | 1957-02-12 | Roy W Rumble | Method of making a floor slab |
US2801716A (en) * | 1952-03-19 | 1957-08-06 | Nat Steel Corp | Foundation unit and building including same |
US2726866A (en) * | 1953-06-18 | 1955-12-13 | Nally Duke Howe | Knock-down platform construction |
US3848377A (en) * | 1973-02-09 | 1974-11-19 | M Mori | Mat foundation |
US4107889A (en) * | 1976-03-01 | 1978-08-22 | Gonsalves, Santucci, Inc. | Foundation system |
US4124963A (en) * | 1977-02-08 | 1978-11-14 | Tadayasu Higuchi | Method for forming a continuous footing |
US4074537A (en) * | 1977-05-18 | 1978-02-21 | John Peter Gronlie | Dock bracket |
US4485598A (en) * | 1979-02-05 | 1984-12-04 | Eustachio Guardiani | Prefabricated elements and rooms for the quick construction of buildings and building works in general |
US4653239A (en) * | 1984-04-12 | 1987-03-31 | Randa Wallace H | Pre-engineered building and method of assembling same |
US4538386A (en) * | 1984-09-04 | 1985-09-03 | Ohio State Home Services, Inc. | Drainage system and method |
US4683689A (en) * | 1985-07-05 | 1987-08-04 | Loggy Albert D | Modular reinforced building structure and method |
US4886399A (en) * | 1987-02-12 | 1989-12-12 | Pidgeon John T | Method of constructing a foundation for buildings |
US5096333A (en) * | 1990-04-27 | 1992-03-17 | Jeanne Bassett | Foundation repair method and apparatus |
US5067289A (en) * | 1990-06-28 | 1991-11-26 | Ouderkirk Dale L | Foundation system for manufactured housing |
US5103613A (en) * | 1990-08-30 | 1992-04-14 | Satoru Kinoshita | Foundation for wooden house |
US5224799A (en) * | 1990-10-03 | 1993-07-06 | Parker Alton F | Permanently installed building foundation form |
US5367845A (en) * | 1993-02-09 | 1994-11-29 | Hartling; Robert H. | System for building a structure |
US5733470A (en) * | 1993-09-24 | 1998-03-31 | Siroflex Of America, Inc. | Mold for casting ground covering |
US5685114A (en) * | 1995-03-20 | 1997-11-11 | Tanaka Masakatsu Design Office Co., Ltd. | Structural member, floor structure, and roof structure for wooden building and a method of building with the same |
US5735090A (en) * | 1995-08-08 | 1998-04-07 | Papke; William | Modular foundation construction and method |
US5755064A (en) * | 1996-03-26 | 1998-05-26 | Bay Apartment Communities, Inc. | Carport enclosure with one or more garage doors |
US5934036A (en) * | 1996-11-01 | 1999-08-10 | Gallagher, Jr.; Daniel P. | Insulated concrete slab assembly |
US6322045B1 (en) * | 1997-08-04 | 2001-11-27 | Chris Andros | Rapid forming system for tilt-up pre-cast concrete wall panels (tilt panel screed system-tipss) |
US5848507A (en) * | 1997-08-21 | 1998-12-15 | Malton Equipment Company | Enclosure with externally mounted adjustable foundations |
US6205720B1 (en) * | 1997-12-24 | 2001-03-27 | Daryl R. Wolfrum | Foundation panel and method of assembly |
US6314693B1 (en) * | 1998-09-03 | 2001-11-13 | Sanders Pre-Cast Concrete Systems. | Building foundation using pre-cast concrete elements |
US6168031B1 (en) * | 1998-12-03 | 2001-01-02 | Fulterer Usa, Inc. | Hanging file support apparatus |
US6370835B1 (en) * | 1999-06-15 | 2002-04-16 | Robust Building Systems, Inc. | Method and apparatus for low cost housing construction |
US6332303B1 (en) * | 2000-02-28 | 2001-12-25 | Nic Engineering Co., Ltd. | Method of building underground structure |
US6341459B1 (en) * | 2000-03-08 | 2002-01-29 | Bobby L. Bates | Method and apparatus for expedited construction of a building |
US6540445B1 (en) * | 2001-03-01 | 2003-04-01 | Eldon Boyd Evans, Jr. | Concrete silt fence |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20080072529A1 (en) * | 2003-03-07 | 2008-03-27 | Morgan Buildings | Hinged support column |
US7574841B2 (en) * | 2003-03-07 | 2009-08-18 | Morton Buildings | Method of erecting a wall having a vertically adjustable hinged support column |
WO2007060291A1 (en) * | 2005-11-23 | 2007-05-31 | Rautaruukki Oyj | Foundation arrangement |
CN104499715A (en) * | 2014-12-08 | 2015-04-08 | 江苏中南建筑产业集团有限责任公司 | Template overhanging construction method for floor system with composite structure by utilizing profiled steel beams |
CN104878926A (en) * | 2015-06-16 | 2015-09-02 | 中建八局第三建设有限公司 | Suspended template system construction method and turnover brackets |
IT201700042061A1 (en) * | 2017-04-14 | 2018-10-14 | Nicola Panizza | FORM FOR THE REALIZATION OF A BUILDING UNIT |
CN114164963A (en) * | 2021-09-30 | 2022-03-11 | 航天建筑设计研究院有限公司 | Shear force wall building structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101574253B1 (en) | A method for construction using a twin wall structure using a PC panel | |
EP2646632B1 (en) | A multi-storey apartment building and method of constructing such building | |
US20220064946A1 (en) | Insulated concrete form construction method and system | |
JP5496732B2 (en) | Construction method for reinforced concrete buildings | |
KR20190022132A (en) | Top-down method using precast-concrete colum | |
US20030167727A1 (en) | Building construction method | |
JP4976938B2 (en) | Seismic reinforcement structure | |
RU108473U1 (en) | SEISMIC RESISTANT BUILDING | |
JP6855296B2 (en) | Building foundation structure and its construction method | |
JP7160357B2 (en) | Method for manufacturing a structure with wall modules | |
JP3185129B2 (en) | Column-integrated column base fixed foundation structure and its construction method | |
CN212453065U (en) | Assembled building frame structure member | |
JP5270255B2 (en) | Foundation reinforcement method for existing wooden houses | |
KR102172651B1 (en) | Simple pool construction method | |
JP3641227B2 (en) | Construction method of underground structure | |
JPS6043500B2 (en) | How to build a basement | |
JP2003105861A (en) | Medium-rise and high-rise building using hfc column and hfc beam or the like | |
JP2004060310A (en) | Wooden earthquake-proof construction using earthquake-proof core | |
KR20130022656A (en) | Hybrid building construction method combining dry type and wet type | |
JP2897663B2 (en) | How to build underground structures | |
CN110984367A (en) | Assembly type building frame structure member and construction method thereof | |
JPH04330119A (en) | Building foundation constructing method | |
JP5467935B2 (en) | Mixed structure unit type building and construction method of mixed structure unit type building | |
KR20210017645A (en) | Underground structure using strut and method construturing the same | |
CN109235648B (en) | Steel grating plate building structure and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |