US1279150A - Method of building levees and embankments. - Google Patents

Method of building levees and embankments. Download PDF

Info

Publication number
US1279150A
US1279150A US5577915A US5577915A US1279150A US 1279150 A US1279150 A US 1279150A US 5577915 A US5577915 A US 5577915A US 5577915 A US5577915 A US 5577915A US 1279150 A US1279150 A US 1279150A
Authority
US
United States
Prior art keywords
levee
pit
points
embankments
embankment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US5577915A
Inventor
Arsene Perrilliat
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to US5577915A priority Critical patent/US1279150A/en
Application granted granted Critical
Publication of US1279150A publication Critical patent/US1279150A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like

Definitions

  • My invention relates to a method of building levees and embankments particularly designed for use in cases where the material for constructing the levee or embankment, or enlarging an old one, must be taken from an extremely wide and shallow borrow-pit by means of an excavator of the rotating derrick-boom type.
  • levee L which, in this particular illustration. is in the nature of a levee to be enlarged to the extent indicated at E and the material therefor must be excavated from a wide pit extending from the levee to the extreme right of the drawing.
  • T he method of building a levee or embankment which consists in excavating progressively at a series of points, in a di rectiontransverse to the line ofthe levee or embankment, the remoter portion of a berrow-pit; depositing, in a corresponding progressive manner, the material thus excavated at an intermediate point of the pit; then excavating at a series of points also in the said transverse direction and progressively, the nearer portion of said pit including the above mentioned material, and

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

A. PERRILLIAT. METHODOF BUILDING LEVEES AND EMBANKMENTS.
APPUCATION FILED OCT. 14. I915- Patsnted Sept. 17, 1918.
ARSENE PERRILLIAT, OF NEW ORLEANS, LOUISIANA.
METHOD OF BUILDING LEVEES AND EMBANKMENTS.
Application filed October 14, 1915.
To all whom it may concern:
Be it known that I, Ansimn PERRILLIAT, a citizen of the United States, residing at New Orleans, Orleans parish, State of Louisiana, have invented certain new and useful Improvements in Methods of Building Levees and Embankments, the following being a full, clear, and exact disclosure of the one form of my invention which I at present deem preferable.
For a detailed description of the present form of my invention, reference may be had to the following specification and to the accompanying drawings, which illustrate my invention.
My invention relates to a method of building levees and embankments particularly designed for use in cases where the material for constructing the levee or embankment, or enlarging an old one, must be taken from an extremely wide and shallow borrow-pit by means of an excavator of the rotating derrick-boom type.
Referring to the drawing, 1 haveindicated at the left of the figure a levee L which, in this particular illustration. is in the nature of a levee to be enlarged to the extent indicated at E and the material therefor must be excavated from a wide pit extending from the levee to the extreme right of the drawing.
I first station an excavator X of the aforesaid type at the point A which is at a distance from the outer edge of the pit about equal to the radius of action of the machine. From this point A the excavator is moved from time to time, first along a straight route toward the levee up to a point A then backward along a diagonal route to the point A and so on to thesuccessive points A*, A A, etc., as far as may be desired. This zig-zag path of travel of the excavator I have indicated by the parallel lines bounding the two sides of the path and showing the width of path required by the excavator. The distance between the centers of each of the straight parallel portions of the aforesaid route is equal to the horizontal reach of the excavator less one-half the width of the required trackway.
In the travel of the excavator from A to A it first excavates, while still at the station A along the extreme right-hand edge of the borrow-pit area bounded by the four points a a a ,.a and dumps the ma- Specification of Letters Patent.
Patented Sept. 17, 1918.
Serial No. 55,779.
terial therefrom along the extreme right hand edge;of the dumping area bounded by the four points (Z al (Z (Z It then proceeds to excavate progressively from right to left within the said excavation area, leaving untouched however its diagonal track from A toward A and dumps the material progressively.from right to left over the said dumping area. When that has been completed the excavator is moved along the diagonal path from station A to station A It then excavates from right to left over a second excavation area bounded by the four points a a a (i leaving untouched however its own path toward station A and deposits the material progressively from right toleft over the second dumping area bounded by the four points (Z (Z (Z (F. In addition ,it excavates it. own path behind it which had been left while it was excavating in the first area. In like manner the machine is moved. next, to station A from which it is moved step by ste,
to station A while it digs within the third excavation'area bounded by the fourpoints a 0. a a and deposits the n'iaterial in the third dun'iping area (Z (Z cl, (Z .This creates a temporary pile of material covering the several dumping areas. When this has been continued as far as desired, the excavator is moved across the lower end of the temporary pile to the station 13 near the line to which the completed levee will reach. will excavate progressively, but in this case from left to right, over the areaembraced by the four points 0 c 0 0 including the third dumping area aforesaid and depositing the material on that part of the levee-extension between the four points Z Z Z Z It will be observed that the temporary dump aforesaid has been 'established on an area which is to be subsequently excavated and that part of the material which has to be twice handled includes only that from the farther part of the pit while its second handling occurs in connection with the excavation of the nearer part of the pit. The machine then proceeds with its operations and is gradually brought to station B respecting however its track ahead of it and digging up its track behind it. From 13 the excavator is moved diagonally from B to B where it begins to excavate, progressing from left to right,
From this station E the machine ceeds in a' the area within the points 0 0 0 0 including the dump (Z cl, (Z and to deposit the sameon the levee Within the area Z Z Z lflbut leaving its trackwayahead and digging up its trackway behind. like manner the final areac c 0 0 including the first dumping area aforesaid, is excavated and delivered on the area Z Z Z Z of the levee.
It will be now apparent that by this method a very wide and shallow borrowpit may be utilized to build the levee, without resort to other apparatus than an ordinary excavator having aworking radius of practicable length.
hile I have described the operation as progressing from right to left, or, from left to right, such description is only illustrative, since, in either case the progress may be in the opposite direction. The essential feature is that the excavation proline transverse to the line'of the levee or embankment, progressing either toward it or away from it, and from the end 'of one series of such transverse exc'ai' ations the. machine is moved to the beginning of the next series.
1 WVhat I claim as new and desire to secure by Letters Patent is:
1'. T he method of building a levee or embankment. which consists in excavating progressively at a series of points, in a di rectiontransverse to the line ofthe levee or embankment, the remoter portion of a berrow-pit; depositing, in a corresponding progressive manner, the material thus excavated at an intermediate point of the pit; then excavating at a series of points also in the said transverse direction and progressively, the nearer portion of said pit including the above mentioned material, and
Copies of this patent may be obtained for finally depositing the material last excavated on the levee or embankment.
2. The method of building a levee or embankment, which consists in excavating progressively at a series of points, in a direction transverse to the line of the levee or embankment, the remoter portion of a borrow-pit; depositing the excavated material progressively on an intermediate unexcavated area of the pit and in a line parallel with the levee or embankment, then excavating at a series of points, also in the said transverse direction and progressively, the nearer portion of said pit including the material above mentioned, and finally depositing the material last excavated on the levee or embankment.
3. The method of building a levee or embankment, which consists in excavating in on a succeeding portion of the pit in a direction parallel with the levee or embank- 1 ment; then excavating in a similar series of arcs the nearer portion of the pit, including the material previously excavated, and depositing the material on the levee or embankment. p
In witness whereof I have hereunto set my hand, this fourth day of October, 1915.
ARSENE PER-RILLIAT.
five cents each, by addressing the Commissioner of Patents, Washington, I) C. i
US5577915A 1915-10-14 1915-10-14 Method of building levees and embankments. Expired - Lifetime US1279150A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US5577915A US1279150A (en) 1915-10-14 1915-10-14 Method of building levees and embankments.

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US5577915A US1279150A (en) 1915-10-14 1915-10-14 Method of building levees and embankments.

Publications (1)

Publication Number Publication Date
US1279150A true US1279150A (en) 1918-09-17

Family

ID=3346745

Family Applications (1)

Application Number Title Priority Date Filing Date
US5577915A Expired - Lifetime US1279150A (en) 1915-10-14 1915-10-14 Method of building levees and embankments.

Country Status (1)

Country Link
US (1) US1279150A (en)

Similar Documents

Publication Publication Date Title
Tyulenev et al. The method of coal losses reducing at mining by shovels
AU2018308953A1 (en) Zero-gangue-discharge short-wall face pillar-free mining method
US1279150A (en) Method of building levees and embankments.
Katsubin et al. Selection of Excavating Equipment for the Outpacing Development of the Coal-bearing Zone
US10648331B2 (en) Method of strip mining
CN105626076A (en) High-efficiency mining method of dragline saw-tooth type working bench
Litvin et al. Coal-bearing zone transformation into a coalless one at the open pit
RU2247241C1 (en) Method for extraction of mineral resources
US776125A (en) Ditching-machine.
AU709808B1 (en) Strip mining overburden removal method
US1644288A (en) Method of excavating
US539604A (en) Excavator and conveyer
US1279151A (en) Method of building levees and embankments.
Pells et al. A tale of two spillways
Erdem, B.*, Duran, Z.* & ï¿ ½elebi A model for direct dragline casting in a dipping coal-seam
US892538A (en) Excavating-machine.
Krishna et al. Case Study on Dragline
RU2106494C1 (en) Method for handling overburden earth
US832371A (en) Ship channel or canal.
Oakes Failure of Masonry and Rock Ledge Cofferdam at Louisville and Portland Canal
Kolovos “Best Practice” Concepts for a Fast-Track Lignite Mine Opening
Hamza Geotechnics of the Suez Canal Construction: 150 Years Old, but Nearly Four Millennia in the Making
SU1300084A1 (en) Method of constructing a dam of locally available materials
RU2108462C1 (en) Method of overburden operations
SU1122828A1 (en) Method of combination mining of seam deposits