TWM262522U - Assembly structure for column and foundation bolt of building - Google Patents

Assembly structure for column and foundation bolt of building Download PDF

Info

Publication number
TWM262522U
TWM262522U TW93207398U TW93207398U TWM262522U TW M262522 U TWM262522 U TW M262522U TW 93207398 U TW93207398 U TW 93207398U TW 93207398 U TW93207398 U TW 93207398U TW M262522 U TWM262522 U TW M262522U
Authority
TW
Taiwan
Prior art keywords
foundation
column
template
bolts
pillar
Prior art date
Application number
TW93207398U
Other languages
Chinese (zh)
Inventor
Shian-Tsuen Lu
Original Assignee
Shian-Tsuen Lu
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shian-Tsuen Lu filed Critical Shian-Tsuen Lu
Priority to TW93207398U priority Critical patent/TWM262522U/en
Publication of TWM262522U publication Critical patent/TWM262522U/en

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Description

M262522 四、創作說明〇) 【新型所屬之技術領域j 指一 =ΐ 作係為一種建築物柱體與基礎螺检之構造’尤 用於、鱼1 ^加基礎螺检與柱體間之結合強度,使基礎螺栓 構造。、"月時更具穩固性及安全性之柱體與基礎螺栓之 【先前技術】 構成ΐ驟概尤;鋼筋混泥土建築)之結構及其 Ϊ至後拆卸模板而形成粗胚,以此步驟逐-由 成。此ί 復對整體建物施以粉飾作業而 所示),若欲於^ =頂樓概會形成柱體(如第一圖 俨1 η她而微 ;、0设鋼構建物隔間時’則需再於哕括 體10知面鑽入基礎螺栓u :幻而再於。亥柱 拴11與柱體10之結合方★甘弟—圖所不),由於基礎螺 鑽孔,嗣將基礎螺栓:為柱體10成型後再於端面 而使其結固,由於基礎庄入填料(強化水泥等) 中,此結固方式之連結體10成型後再植入其 之鋼構建物隔間高度、^、 义,因此,一般所加設 結構安全(請參閱第三圖所_Ρ所限制,以維持建築物的 建物之外,一般於地面上 除了建築物頂樓的鋼構 11與柱體1 〇間之結固性合=鋼構廠房,其基礎螺栓 【新型内容】 良亦會有上述同樣問題產生者。 本案創作之目的即在於 之間因結合性不良所造成之:柱體10與基礎螺栓11 故而提供-種可增加基 M262522 四、創作說明(2) 礎螺栓與柱體間 更具穩固性及安 有關本案創 造特徵’兹謹再 詳細說明如下: 本案創作主 該柱體20 ( 筋2 1直立預紮於 以法定間距圍束 鉤於主筋),請 設有螺紋3 1,末 之基礎螺栓30置 屬支撐條33連接 、鐵絲綁固等方 未灌漿之主筋2 1 釘設模板,而將 泥渡,俟泥將乾 圖所示)。— 【實施方式】 藉由上述構 架置主筋2 1之間 同一體,又尤其 检30與柱體20之 枉體2 0上加設之 及若干基礎 所示)之構 ),再將直 筋末端須以 圖,該基礎 成彎折端3 2 干主筋2 1内 主筋2 1或箍 數量之基礎 距離主筋2 1 模板之中, ,而得一柱 螺栓3 0, 成係先將 立之若干 1 3 5 度彎 螺栓30之 ’可將預 ,再藉由 筋22 (可 螺栓3 0被 適當尺寸 又在模板 體20者( 其中: 若干主 主筋21 折而扣 頂端係 定數量 若干金 為焊接 架置於 之四週 内澆灌 如第七 之結合強度,使基礎螺栓用於連結鋼骨時 全性之柱體與基礎螺栓之構造。 作,達倉“乍目的所運用之技術手段及其構 配&第四圖至第八圖所示之較佳實施例, 要包含柱體2 〇 請參閱第四圖 樓板(或地面 箍筋2 2 (該箍 參閱第五、六 端則彎折而形 於柱體20之若 基礎螺栓30及 式),使預定 之間,復另於 主筋2 1包圍在 固後拆卸模板 造’由於基礎螺栓3 0係於柱體2 〇灌漿前即 ,復進行灌漿後,基礎螺栓3 〇與柱體2 〇形 基礎螺栓30下方設有彎折部32,嗣基礎螺 間則具有極佳之結合強度;由是,當欲於 鋼構建物隔間時,由於基礎螺栓3〇與柱體M262522 IV. Creation instructions 0) [Technical field to which the new type belongs refers to the structure of a building pillar and basic screw inspection ', especially for the combination of fish 1 ^ plus basic screw inspection and cylinder The strength makes the foundation bolt structure. 、 &Quot; Most stable and safe pillars and foundation bolts [prior technology], the structure of the structure is simple; reinforced concrete construction) and the structure is removed afterwards to form a rough embryo. Step-by-step. This figure shows that the whole building is whitewashed. If you want to make a pillar on the top floor (as shown in the first picture, 1 and 1), you need to set up a steel structure compartment. Then drill into the foundation bolt u on the knowing surface of the bracket 10: The magic bolt and then again. The combination of the Haizhu bolt 11 and the pillar 10 ★ Gandi—not shown in the figure), due to the drilling of the foundation screw, the foundation bolt: After the pillar 10 is formed, it is consolidated on the end face. Since the foundation is embedded in the filler (reinforced cement, etc.), the joint 10 of this consolidation method is implanted into the steel structure compartment height, ^ Therefore, generally, the added structure is safe (please refer to the restriction in _P in the third figure to maintain the building's structures, and it is generally on the ground except for the steel structure 11 and the pillar 10 of the top floor of the building. The combination of solidity = steel structure workshop, its foundation bolts [new content] The same problems as above will occur. The purpose of the creation of this case is caused by the poor bonding between the pillars 10 and the foundation bolts 11 Therefore, provide-a kind can increase the base M262522 Fourth, the creation instructions (2) more between the base bolt and the column Stability and safety related to the characteristics of this case's creation are hereby explained in detail as follows: The author of this case is the column 20 (ribs 21 are pre-stretched and tied to the main ribs with a legal spacing around the beam), please have threads 3 1 at the end The foundation bolts 30 are the main ribs 2 1 that are not grouted, such as the connection of the support bar 33 and the iron wire binding, and the template is nailed, and the mud will be crossed, and the mud will be dry. — [Embodiment] By using the above structure to set the same body between the main ribs 21, and especially check the structure of the carcass 20 and the base 20 (shown on the base 20 and some of the basic structures), and then straight end According to the figure, the foundation is a bent end 3 2 dry main reinforcement 2 1 inner main reinforcement 2 1 or the number of hoop bases in the template from the main reinforcement 2 1, and a column bolt 3 0 is obtained. 3 5 degree bent bolts 30 'can be pre-made, and then by the ribs 22 (can be bolts 30 are appropriately sized and then in the template body 20 (of which: several main main ribs 21 fold and the top of the buckle is fixed a number of gold for the welding frame Placed in the surrounding area, it is irrigated with the bonding strength of seventh, so that the foundation bolt is used to connect the steel column and the foundation bolt structure when it is used to connect the steel frame. The preferred embodiment shown in the fourth to eighth figures, including the column 2 〇 Please refer to the fourth figure floor (or the floor stirrup 2 2 (this hoop is bent and shaped at the fifth and sixth ends) If the base bolt 30 and the type of the column 20), make it between the predetermined and the main rib 2 1 pack After the solidification, the formwork is dismantled. Because the foundation bolt 30 is tied to the column 20 before the grouting, that is, after the grouting is repeated, the base bolt 30 and the pillar 20 are provided with a bent portion 32 below the foundation bolt 30. The foundation screw has excellent bonding strength; therefore, when the steel structure compartment is intended, the foundation bolt 30 and the column

第7頁 M262522Page 7 M262522

四、創作說明(3) 20間具有極佳之結合強度’嗣鋼構建物之高度、面積即可 大為放寬而不會有安全上的顧慮。另外,本案柱體與美礎 螺栓之結合構造除了運用於建築物頂樓的鋼構建物之^卜, 亦可以相同的技術手段運用於地面上所構築之鋼構廠房者 以上之所 體與基礎 強度,使 •,是以, 顯著的進 為本案創 之要件, 外,本案 舉凡依本 作之申請 構造,確 拴應用於 較於習知 實用性, 研發而成 提出申請 揭示之構 之構造所 圍。 從 本案柱 之結合 安全性 確具有 構造確 型專利 另 施例, 於本創 螺栓之 基礎螺 本案相 步性及 作人所 爰依法 以上所 案創作 專利範 平乂狂】: 可增加 連結鋼 柱體與 且其運 ,嗣本 ,並祈 造,乃 作之等 基礎螺 骨時更 基礎螺 用之技 案創作 賜專利 為本創 效變化 栓與柱體間 具穩固性、及 拴之構造, 術手段及其 誠已符合新 權為禱。 作較佳之實 ’仍應含蓋4. Creation instructions (3) The 20 rooms with excellent bonding strength can be greatly relaxed in height and area without any safety concerns. In addition, in addition to the steel structure used in the roof of the building, the combined structure of the pillar and the foundation bolt in this case can also be applied to the strength and foundation strength of the steel structure factory built on the ground by the same technical means. , •• is based on the significant advancement of this case. In addition, the application structure based on the application made in this case is indeed applied to the structure of the structure disclosed by the application that is developed and applied to the application. . From the combined safety of the pillars in this case, there is another example of a structure-confirmed patent. The phasedness of the foundation screw of the original bolt and the author's creation of the patent according to the above case. Fan Ping's crazy]: can increase the connection of steel pillars The body and its movements, copying and praying, are the basic screw snails and other basic screw snails. The patent creation is based on the effect of changing the stability between the bolt and the column, and the structure of the bolt. The technical means and sincerity have been in accord with the new right to pray. To be better ’should still cover

M262522 圖式簡單說明 .第一圖 第二圖 第三圖 第四圖 第五圖 第六圖 第七圖 第八圖 一般建物之頂頭示意簡圖。 習知柱體與基礎螺栓之結合構造圖。 習知柱體建構鋼骨建物之示意圖。 本案創作之柱體成型圖(一)。 本案創作之柱體成型圖(二)。 本案創作之柱體成型圖(三)。 本案創作之柱體成型圖(四)。 本案創作之柱體建構鋼骨建物之示意圖 圖式中元件號數之說明: 【習知部份】 10 柱體 11 基礎螺栓 【本案部份】 20 柱體 21 主筋 22 箍筋 30 基礎螺栓 31 螺紋 32 彎折端 33 金屬支撐條M262522 Schematic description. First picture Second picture Third picture Fourth picture Fifth picture Fifth picture Sixth picture Seventh picture Eighth picture A schematic diagram of the head of a general building. Know the combination structure diagram of column and foundation bolt. Schematic diagram of the construction of steel skeleton structures in conventional columns. Column forming drawing (1) created in this case. Column forming drawing created in this case (2). Shaped drawing of the cylinder created in this case (3). Formed drawing of the cylinder created in this case (4). Schematic illustration of the components of the steel structure in the column structure created in this case: [Learning section] 10 Column 11 Foundation bolt [Part of the case] 20 Column 21 Main rib 22 Hoop 30 Base bolt 31 Thread 32 Bent end 33 Metal support bar

第9頁Page 9

Claims (1)

M262522 五、申請專利範圍 一種建築物柱體與基礎螺栓之結合構造,其主要包含 柱體及若干基礎螺栓;其t,該柱體之構成係^將若 筋直立預紮於樓板(或地面),再將直立之若干主筋以法 定間距及角度圍束箍筋,另於距離主筋適當尺寸之四週釘 設模板,而將主筋包圍在模板之t,復在模板内洗灌泥聚 ,俟泥將乾涸後拆卸模板,而得一柱體,其特徵乃在於: 该基礎螺栓之頂端為螺紋端,末端則彎折而形成’資折端, 可將預定數量之基礎螺栓於灌漿前置於主筋内,再藉由若 干金屬支撐條連接基礎螺栓及主筋或箍筋,其連結^式可 為焊接、鐵絲綁固方式,使預定數量之基礎螺栓被架置於 未灌漿之主筋之間,當柱體成型後,基礎螺栓被穩固& 合於柱體内。M262522 5. Scope of patent application A combined structure of a building pillar and a foundation bolt, which mainly includes a pillar and a number of foundation bolts; t, the composition of the pillar ^ will be if the ribs stand upright on the floor (or the ground) Then, the main bars that are upright are bound with hoop bars at a legal interval and angle, and a template is nailed around the appropriate size from the main bars, and the main bars are enclosed at t of the template, and then washed and filled with mud in the template. After drying out, the template is disassembled to obtain a cylinder, which is characterized in that the top end of the foundation bolt is a threaded end, and the end is bent to form a 'finished end'. A predetermined number of foundation bolts can be placed in the main reinforcement before grouting. Then, the base bolts and main bars or stirrups are connected by a plurality of metal support bars. The connection method can be welding, wire bonding, so that a predetermined number of base bolts are placed between the main bars without grouting, and when the columns are After forming, the foundation bolts are stabilized & fit into the column.
TW93207398U 2004-05-12 2004-05-12 Assembly structure for column and foundation bolt of building TWM262522U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW93207398U TWM262522U (en) 2004-05-12 2004-05-12 Assembly structure for column and foundation bolt of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW93207398U TWM262522U (en) 2004-05-12 2004-05-12 Assembly structure for column and foundation bolt of building

Publications (1)

Publication Number Publication Date
TWM262522U true TWM262522U (en) 2005-04-21

Family

ID=36122580

Family Applications (1)

Application Number Title Priority Date Filing Date
TW93207398U TWM262522U (en) 2004-05-12 2004-05-12 Assembly structure for column and foundation bolt of building

Country Status (1)

Country Link
TW (1) TWM262522U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8522507B2 (en) 2009-06-24 2013-09-03 Mitsubishi Heavy Industries, Ltd. Concrete platform production process, concrete platform, and connecting member

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8522507B2 (en) 2009-06-24 2013-09-03 Mitsubishi Heavy Industries, Ltd. Concrete platform production process, concrete platform, and connecting member
TWI409400B (en) * 2009-06-24 2013-09-21 Mitsubishi Heavy Ind Ltd A method for manufacturing a concrete frame, a concrete frame, and a connecting material

Similar Documents

Publication Publication Date Title
CN206737116U (en) Node dry and wet Hybrid connections assembled integral concrete frame structure
JP2001507769A (en) Elastic fiber reinforced composite structural member
CN102330432A (en) Panel-type framework prestressed anchor rod flexible support structure and construction method thereof
CN103741817A (en) Enhancement method of X-shaped reinforcing bars for improving seismic resistance of special-shaped column nodes
CN104480922B (en) Space truss formwork system and construction method thereof
CN107143065A (en) Prefabricated load bearing concrete wall panel combining structure and construction method
CN104929278A (en) Assembly type dense column hollow shear wall structure
CN106284844A (en) A kind of concrete-filled double skin steel tube superposed column and preparation method thereof
CN110107075B (en) Large-span step-by-step cantilever inclined strut structure based on pull-up and pull-down embedded structure and construction method thereof
CN209211748U (en) A kind of structure node of assembled ceiling radiating system
CN208105474U (en) A kind of assembly node of upper and lower interior wall and floor
TWM262522U (en) Assembly structure for column and foundation bolt of building
CN208105473U (en) A kind of assembly node of upper and lower self-heat conserving external wall and floor
CN210483031U (en) Reinforced concrete crossed inclined column construction template
CN106906945A (en) The installation method of insulating light wall slab, light-weight building structure and light-weight building structure
CN108301562A (en) Assembly concrete-filled steel tube column-isolated footing-concrete collar tie beam cross connecting node
CN208023734U (en) Assembly concrete-filled steel tube column-isolated footing-concrete collar tie beam linear type connecting node
CN113482036A (en) Column base structure of reinforced concrete and construction method thereof
TWM428213U (en) Prefabricated cross-beam structure
CN206903060U (en) The concrete composite beam of strap end portion shaped steel
CN207130992U (en) Between a kind of precast stair
CN105715069B (en) A kind of method of rapid reinforcement Reinforced Concrete Columns
CN105756366B (en) A kind of method of rapid reinforcement armored concrete corner post
TWI755188B (en) Construction method of reinforced concrete structure by replacing part of steel bars with section steel
JP2008223461A (en) Construction method for high-floor type building, foundation column and sill

Legal Events

Date Code Title Description
MM4K Annulment or lapse of a utility model due to non-payment of fees