TW202417718A - Architecture system and method for constructing the same - Google Patents

Architecture system and method for constructing the same Download PDF

Info

Publication number
TW202417718A
TW202417718A TW111139483A TW111139483A TW202417718A TW 202417718 A TW202417718 A TW 202417718A TW 111139483 A TW111139483 A TW 111139483A TW 111139483 A TW111139483 A TW 111139483A TW 202417718 A TW202417718 A TW 202417718A
Authority
TW
Taiwan
Prior art keywords
precast
steel bars
connection structure
steel bar
connection
Prior art date
Application number
TW111139483A
Other languages
Chinese (zh)
Other versions
TWI808911B (en
Inventor
尹衍樑
曹昌盛
王瑞禎
陳智軒
Original Assignee
潤弘精密工程事業股份有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 潤弘精密工程事業股份有限公司 filed Critical 潤弘精密工程事業股份有限公司
Priority to TW111139483A priority Critical patent/TWI808911B/en
Application granted granted Critical
Publication of TWI808911B publication Critical patent/TWI808911B/en
Publication of TW202417718A publication Critical patent/TW202417718A/en

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Communication Control (AREA)

Abstract

The instant disclosure provides an architecture system which includes a right and a left precast connection structure each positioned on a precast column. The beam structures of the right and the left precast connection structures are positioned adjacent to each other and connected to each other through a precast beam structure and an on-site connection structure. A first end of the precast beam structure is directly coupled to the right precast connection structure. A number of beam steels are embedded in the precast beam structure and protrudes outward from a second end of the precast beam structure. The on-site connection structure includes: a number of stationary couplers embedded at an end surface of the beam structure of the left precast connection structure; a number of connection rods connected to the stationary couplers; a confined structure telescoping the beam steels of the precast beam structure; and a number of movable couplers with one end connected to one of the corresponding connection rods and with the other end connected with one of the corresponding beam steels of the precast beam structure.

Description

建築系統及其建造方法Building system and construction method thereof

本發明實施例關於提供一種建築系統及其建造方法。Embodiments of the present invention provide a building system and a construction method thereof.

常見的建築工法包括RC(鋼筋混凝土)結構、SC(鋼骨梁柱外面包覆混凝土做防火披覆使用)結構以及SRC(鋼骨鋼筋混凝土)結構等。RC(鋼筋混凝土)結構又可區分為現場澆置混凝土的傳統場鑄工法以及近年發展具有結構品質優異、施工安全迅速、營建成本經濟合理等優點的預鑄工法。預鑄工法係於預鑄廠或工地周邊,以標準化的作業流程及模組化的模具,施工鋼筋結構並澆置混凝土,快速大量生產精密的柱體、梁體、板體等的預鑄構件。藉由精確的搬運管理及組裝作業,將在預鑄廠內或工地周邊生產完成的預鑄構件於工地現場組合。藉此,工地現場中的工作量可以降低、減少人力及施工時間,進而有效縮短工期,並確保施工品質。此外,預鑄施工法亦可減少或避免在外牆鷹架上施工,大幅提高了施工安全性。Common construction methods include RC (reinforced concrete) structure, SC (concrete coated on the outside of steel beams and columns for fireproofing) structure and SRC (reinforced concrete) structure. RC (reinforced concrete) structure can be divided into the traditional on-site casting method of pouring concrete on site and the precast method developed in recent years with advantages such as excellent structural quality, safe and rapid construction, and economical and reasonable construction cost. The precast method is to construct the steel structure and pour concrete in a precast factory or around the construction site with standardized operation processes and modular molds, and quickly mass-produce precise precast components such as columns, beams, and plates. Through precise transportation management and assembly operations, the precast components produced in the precast factory or around the construction site are assembled on site. In this way, the workload on the construction site can be reduced, manpower and construction time can be reduced, thereby effectively shortening the construction period and ensuring the construction quality. In addition, the precast construction method can also reduce or avoid construction on the external wall scaffolding, greatly improving construction safety.

基於各種工法有其優缺點,混和式的建築工法也逐漸被採用。舉例而言,以預鑄柱工法搭配傳統場鑄工法建築住宅類型建案可發揮其各自的優缺點,其中利用預鑄柱工法施工建築物外圍的梁柱主結構,輔以傳統場鑄工法施作建築物內圍較瑣碎的時工細節通常可以在品質、工時,以及成品各方面達到最佳的性價比。有鑑於此類建築物的發展,如何在利用最少施工步驟以達到最大產量且提供最佳品質的製造此類梁柱結構的方法,以及依此方法所製成的梁柱結構是業界所企盼的。Since each construction method has its own advantages and disadvantages, mixed construction methods are gradually being adopted. For example, the combination of precast column construction method and traditional field casting construction method in residential construction projects can give play to their respective advantages and disadvantages. The use of precast column construction method to construct the main beam and column structure of the building's periphery, supplemented by the traditional field casting method to construct the more intricate construction details of the building's interior, can usually achieve the best cost-effectiveness in terms of quality, labor time, and finished products. In view of the development of such buildings, how to use the least construction steps to achieve the maximum output and provide the best quality of the manufacturing method of such beam and column structure, and the beam and column structure manufactured by this method are what the industry is looking forward to.

本發明之一實施例提供一種建築系統,其包括:二個預鑄柱;一右側第二預鑄連接結構及一左側第二預鑄連接結構,各自包括固定於該二個預鑄柱之一者之一預鑄連接頭、及自該預鑄連接頭之側邊水平延伸之一梁結構,其中該右側第二預鑄連接結構之該梁結構與該左側第二預鑄連接結構之該梁結構相鄰設置,且該右側第二預鑄連接結構包括複數個第一梁鋼筋埋設於其中;一預鑄梁結構,具有相對設置且分別面對該右側第二預鑄連接結構及該左側第二預鑄連接結構之一第一端及一第二端,且包括:複數個第二梁鋼筋埋設於該預鑄梁結構當中並自該預鑄梁結構之該第二端延伸而出;以及複數個鋼筋續接器,設置於該預鑄梁結構之該第一端並經構形以將該右側第二預鑄連接結構之該複數個第一梁鋼筋連結至該預鑄梁結構之該複數個第二梁鋼筋;以及一場鑄接續結構,包括:複數個固定鋼筋續接器,埋設於該左側第二預鑄連接結構之該梁結構之一端面中;複數個連接鋼筋,連接至該複數個固定鋼筋續接器;一圍束結構,套設於該預鑄梁結構之該複數個第二梁鋼筋;以及複數個可移動鋼筋續接器,其每一者之一端連接該複數個連接鋼筋之相應的一者,其每一者之另一端連接該預鑄梁結構之該複數個第二梁鋼筋之相應的一者。An embodiment of the present invention provides a building system, which includes: two precast columns; a right second precast connection structure and a left second precast connection structure, each including a precast connection head fixed to one of the two precast columns, and a beam structure extending horizontally from the side of the precast connection head, wherein the beam structure of the right second precast connection structure and the left second precast connection structure are connected to each other. The beam structures of the structure are arranged adjacent to each other, and the right second precast connection structure includes a plurality of first beam steel bars embedded therein; a precast beam structure has a first end and a second end which are arranged opposite to each other and face the right second precast connection structure and the left second precast connection structure respectively, and includes: a plurality of second beam steel bars embedded in the precast beam structure and extending from the precast beam structure The second end of the precast beam structure extends outward; and a plurality of steel bar connectors disposed at the first end of the precast beam structure and configured to connect the plurality of first beam steel bars of the right second precast connection structure to the plurality of second beam steel bars of the precast beam structure; and a field cast connection structure, including: a plurality of fixed steel bar connectors, embedded in the beam structure of the left second precast connection structure an end surface; a plurality of connecting steel bars connected to the plurality of fixed steel bar extenders; a restraining structure sleeved on the plurality of second beam steel bars of the precast beam structure; and a plurality of movable steel bar extenders, each of which has one end connected to a corresponding one of the plurality of connecting steel bars and the other end connected to a corresponding one of the plurality of second beam steel bars of the precast beam structure.

在上述實施例中,該圍束結構包括複數個彼此以一預定距離間隔之封閉式箍筋。In the above-mentioned embodiment, the confinement structure includes a plurality of closed stirrups spaced apart from each other by a predetermined distance.

在上述實施例中,該複數個固定鋼筋續接器每一者之一端部係暴露於該左側第二預鑄連接結構之梁結構之該端面且包括一內螺紋結構;並且該複數個連接鋼筋每一者之一端部包括一外螺紋結構,經由該內螺紋結構與該外螺紋結構之嚙合,該複數個連接鋼筋螺紋連接至該複數個固定鋼筋續接器。In the above embodiment, one end of each of the plurality of fixed steel bar connectors is exposed to the end surface of the beam structure of the left second precast connection structure and includes an internal thread structure; and one end of each of the plurality of connecting steel bars includes an external thread structure, and the plurality of connecting steel bars are threadedly connected to the plurality of fixed steel bar connectors through the engagement of the internal thread structure with the external thread structure.

在上述實施例中,該場鑄接續結構之該複數個可移動鋼筋續接器中填充有砂漿材料,以固接該複數個連接鋼筋與該複數個第二梁鋼筋。In the above embodiment, the plurality of movable steel bar connectors of the field-cast connection structure are filled with mortar material to fix the plurality of connecting steel bars and the plurality of second beam steel bars.

在上述實施例中,該複數個連接鋼筋之長度係小於或等於該複數個第二梁鋼筋之自由端與該左側第二預鑄連接結構之梁結構之端面之間隔距離。In the above embodiment, the length of the plurality of connecting steel bars is less than or equal to the spacing distance between the free ends of the plurality of second beam steel bars and the end surface of the beam structure of the left second precast connecting structure.

本發明之另一實施例提供一種建築系統之建造方法,其包括:提供二個預鑄柱;吊設一右側第二預鑄連接結構及一左側第二預鑄連接結構於該二個預鑄柱之上,其各自包括固定於該二個預鑄柱之一者之一預鑄連接頭、及自該預鑄連接頭之側邊水平延伸之一梁結構;將該右側第二預鑄連接結構之該預鑄連接頭及該左側第二預鑄連接結構之該預鑄連接頭分別固定於該二個預鑄柱之頂端,使該右側第二預鑄連接結構之該梁結構與該左側第二預鑄連接結構之該梁結構相鄰設置;以及提供一預鑄梁結構,並將該預鑄梁結構吊設以及定位於該右側第二預鑄連接結構之該梁結構及該左側第二預鑄連接結構之該梁結構之間;將該右側第二預鑄連接結構之該梁結構之複數個第一梁鋼筋連結至該預鑄梁結構之複數個第二梁鋼筋;以及施作一場鑄接續結構於該預鑄梁結構與該左側第二預鑄連接結構之梁結構之間。Another embodiment of the present invention provides a construction method of a building system, which includes: providing two precast columns; hanging a right second precast connection structure and a left second precast connection structure on the two precast columns, each of which includes a precast connection head fixed to one of the two precast columns, and a beam structure extending horizontally from the side of the precast connection head; fixing the precast connection head of the right second precast connection structure and the precast connection head of the left second precast connection structure to the top ends of the two precast columns respectively, so that the right second precast connection structure The beam structure of the cast connection structure is arranged adjacent to the beam structure of the second precast connection structure on the left side; a precast beam structure is provided, and the precast beam structure is suspended and positioned between the beam structure of the second precast connection structure on the right side and the beam structure of the second precast connection structure on the left side; a plurality of first beam steel bars of the beam structure of the second precast connection structure on the right side are connected to a plurality of second beam steel bars of the precast beam structure; and a field casting connection structure is constructed between the precast beam structure and the beam structure of the second precast connection structure on the left side.

在上述實施例中,施作該場鑄接續結構之步驟包括:(A) 埋設複數個固定鋼筋續接器於該左側第二預鑄連接結構之梁結構之一端面中;(B) 提供並將複數個連接鋼筋連接至該左側第二預鑄連接結構中之該複數個固定鋼筋續接器;(C)套設一圍束結構於該預鑄梁結構之該複數個第二梁鋼筋上;以及(D) 將複數個可移動鋼筋續接器每一者之一端連接該複數個連接鋼筋之相應的一者,並將該複數個可移動鋼筋續接器每一者之另一端連接該預鑄梁結構之該複數個第二梁鋼筋之相應的一者。In the above-mentioned embodiment, the steps of constructing the field-cast connection structure include: (A) embedding a plurality of fixed steel bar connectors in an end face of the beam structure of the left second precast connection structure; (B) providing and connecting a plurality of connecting steel bars to the plurality of fixed steel bar connectors in the left second precast connection structure; (C) sleeved a restraining structure on the plurality of second beam steel bars of the precast beam structure; and (D) connecting one end of each of a plurality of movable steel bar connectors to a corresponding one of the plurality of connecting steel bars, and connecting the other end of each of the plurality of movable steel bar connectors to a corresponding one of the plurality of second beam steel bars of the precast beam structure.

在上述實施例中,步驟(D)包括:將該複數個可移動鋼筋續接器預先分別套設於該預鑄梁結構之該複數個第二梁鋼筋,此時可移動鋼筋續接器之兩端均位於該該複數個第二梁鋼筋上;待該預鑄梁結構定位完成使得該複數個第二梁鋼筋對齊該複數個連接鋼筋後,將該複數個可移動鋼筋續接器朝向該複數個連接鋼筋移動。In the above embodiment, step (D) includes: pre-installing the plurality of movable steel bar connectors on the plurality of second beam steel bars of the pre-cast beam structure, respectively, at which time both ends of the movable steel bar connectors are located on the plurality of second beam steel bars; after the pre-cast beam structure is positioned so that the plurality of second beam steel bars are aligned with the plurality of connecting steel bars, the plurality of movable steel bar connectors are moved toward the plurality of connecting steel bars.

在上述實施例中,所述方法進一步包括將該圍束結構由一未展開狀態轉換成一展開狀態,其中在該未展開狀態下該複數個連接鋼筋未被該圍束結構所圍繞,且在該展開狀態下該複數個連接鋼筋以及該複數個可移動鋼筋續接器被該圍束結構所圍繞。In the above embodiment, the method further includes converting the restraining structure from an undeployed state to an deployed state, wherein in the undeployed state the plurality of connecting steel bars are not surrounded by the restraining structure, and in the deployed state the plurality of connecting steel bars and the plurality of movable steel bar connectors are surrounded by the restraining structure.

在上述實施例中,所述方法進一步包括將一砂漿材料注入至該複數個可移動鋼筋續接器中,以使該複數個可移動鋼筋續接器與該複數個第二梁鋼筋及該複數個連接鋼筋固接,並形成混凝土結構使其包覆該場鑄接續結構。In the above embodiment, the method further includes injecting a mortar material into the plurality of movable steel bar connectors to fix the plurality of movable steel bar connectors to the plurality of second beam steel bars and the plurality of connecting steel bars, and forming a concrete structure to cover the field-cast connection structure.

為更清楚了解本創作之特徵、內容與優點及其所能達成之功效,茲將本創作配合附圖,並以實施例之表達形式詳細說明如下,而其中所使用之圖式,其主旨僅為示意及輔助說明書之用,故不應就所附之圖式的比例與配置關係解讀、侷限本創作的申請專利範圍。In order to better understand the features, contents and advantages of this invention and the effects it can achieve, this invention is described in detail as follows with accompanying drawings and in the form of embodiments. The drawings used therein are only for illustration and auxiliary description. Therefore, the proportions and configurations of the attached drawings should not be interpreted to limit the scope of the patent application of this invention.

本揭露中的用語「一」或「一種」係用以敘述本創作之元件及成分。此術語僅為了敘述方便及給予本創作之基本觀念。此敘述應被理解為包括一種或至少一種,且除非明顯地另有所指,表示單數時亦包括複數。於申請專利範圍中和「包含」一詞一起使用時,該用語「一」可意謂一個或超過一個。此外,本揭露中的用語「或」其意同「及/或」。The terms "a" or "an" in this disclosure are used to describe the elements and components of this invention. This term is only for the convenience of description and to give the basic concept of this invention. This description should be understood to include one or at least one, and unless otherwise clearly indicated, the singular also includes the plural. When used with the word "including" in the scope of the patent application, the term "a" can mean one or more than one. In addition, the term "or" in this disclosure means "and/or".

除非另外規定,否則諸如「上方」、「下方」、「向上」、「左邊」、「右邊」、「向下」、「本體」、「底座」、「垂直」、「水平」、「側」、「較高」、「下部」、「上部」、「上方」、「下面」等空間描述係關於圖中所展示之方向加以指示。應理解,本揭露中所使用之空間描述僅出於說明之目的,且本揭露中所描述之結構之實際實施可以任何相對方向在空間上配置,此限制條件不會改變本發明實施例之優點。舉例來說,在一些實施例之描述中,提供「在」另一元件「上」之一元件可涵蓋前一元件直接在後一元件上(例如,與後一元件實體接觸)的狀況以及一或複數個介入元件位於前一元件與後一元件之間的狀況。又或者,在一些實施例之描述中,位於「左側」之元件可與位於「右側」之元件之位置互換。Unless otherwise specified, spatial descriptions such as "above", "below", "upward", "left", "right", "downward", "body", "base", "vertical", "horizontal", "side", "higher", "lower", "upper", "above", "below", etc. are indicated with respect to the directions shown in the figures. It should be understood that the spatial descriptions used in the present disclosure are for illustrative purposes only, and the actual implementation of the structures described in the present disclosure can be spatially arranged in any relative direction, and this limitation does not change the advantages of the embodiments of the present invention. For example, in the description of some embodiments, providing an element "on" another element can cover the situation where the previous element is directly on the latter element (for example, in physical contact with the latter element) and the situation where one or more intervening elements are located between the previous element and the latter element. Alternatively, in the description of some embodiments, the position of the element located on the "left side" and the element located on the "right side" may be interchanged.

如本揭露中所使用,術語「大致」、「實質上」、「實質的」及「約」用以描述及考慮微小之變化。當與事件或情形結合使用時,該等術語可意指事件或情形明確發生之情況以及事件或情形極近似於發生之情況。As used in this disclosure, the terms "substantially," "substantial," "substantial," and "approximately" are used to describe and take into account minor variations. When used in conjunction with an event or circumstance, these terms may mean both the situation where the event or circumstance definitely occurred and the situation where the event or circumstance closely approximates to occurring.

本揭露以下內容中,包括「預鑄」之元件名稱(例如:預鑄角柱、預鑄邊柱、預鑄連接結構、預鑄梁結構等)所對應之結構係採用「預鑄工法」製造之建築結構,其係於預鑄廠或工地周邊,以標準化的作業流程及模組化的模具,施工鋼筋結構,例如鋼筋籠,構築模板並澆置混凝土,快速大量生產高精密度且高品質均一性的柱體、梁體、板體等的結構體構件。隨後,於工地現場中藉由精確的搬運管理及組裝作業,將生產完成之結構體構件於工地現場組合。另一方面,包括「場鑄」之元件名稱(例如:場鑄接續結構等)所對應之結構係採用傳統「場鑄工法」之建築結構,其係於工地現場施工鋼筋結構、構築模板並澆置混凝土所完成之結構。In the following contents of this disclosure, the names of components including "precast" (e.g., precast corner columns, precast side columns, precast connection structures, precast beam structures, etc.) correspond to building structures manufactured using the "precast method", which is to construct steel structures such as steel cages, build templates and pour concrete in a precast factory or around the construction site with standardized operation processes and modular molds, and quickly mass-produce high-precision and high-quality uniformity columns, beams, plates, etc. Structure components. Subsequently, the completed structural components are assembled on the construction site through precise transportation management and assembly operations. On the other hand, the names of components that include "site cast" (for example: site cast joint structure, etc.) correspond to structures that use the traditional "site cast method" to build structures. They are structures that are completed on site by constructing steel structures, building formwork, and pouring concrete.

根據本發明之一實施例,本發明之建築系統之單一樓層的外圍建築系統係採梁柱預鑄結構,內部建築系統之部分結構可採梁柱預鑄結構或以傳統場鑄工法製造。外圍建築系統包括多個預鑄角柱、多個預鑄邊柱、多個預鑄連接結構、至少一預鑄梁結構、及至少一場鑄接續結構。內部建築系統則可選擇地包括一或多個預鑄梁柱結構並以傳統場鑄工法製造剩餘之梁柱結構,或是所有梁柱結構皆以傳統場鑄工法製造。According to one embodiment of the present invention, the outer perimeter construction system of a single floor of the construction system of the present invention adopts a precast beam-column structure, and part of the structure of the inner perimeter construction system can adopt a precast beam-column structure or be manufactured by a traditional field casting method. The outer perimeter construction system includes a plurality of precast corner columns, a plurality of precast side columns, a plurality of precast connection structures, at least one precast beam structure, and at least one field cast connection structure. The inner perimeter construction system can optionally include one or more precast beam-column structures and manufacture the remaining beam-column structures by a traditional field casting method, or all beam-column structures are manufactured by a traditional field casting method.

圖1展示之本發明之一實施例中的建築系統1之示意圖。建築系統1之單一樓層之外圍建築系統10包括四個預鑄角柱11、八個預鑄邊柱13、多個預鑄連接結構(例如:四個第一預鑄連接結構15及八個第二預鑄連接結構17)、二個預鑄梁結構20、及二個場鑄接續結構30。建築系統1之內部建築系統40則是部分採梁柱預鑄結構,並以傳統場鑄工法製造剩餘之梁柱結構,其中包括二個場鑄柱結構41、多個場鑄梁結構42、二個內部預鑄柱結構43及二個內部預鑄連接結構44、45。FIG1 shows a schematic diagram of a building system 1 in an embodiment of the present invention. The outer peripheral building system 10 of a single floor of the building system 1 includes four precast corner columns 11, eight precast side columns 13, a plurality of precast connection structures (e.g., four first precast connection structures 15 and eight second precast connection structures 17), two precast beam structures 20, and two field-cast connection structures 30. The inner building system 40 of the building system 1 is partially precast beam-column structures, and the remaining beam-column structures are manufactured by conventional field-casting methods, including two field-cast column structures 41, a plurality of field-cast beam structures 42, two inner precast column structures 43, and two inner precast connection structures 44, 45.

根據本揭露之部分實施例,建築系統1之施工方法說明如下:According to some embodiments of the present disclosure, the construction method of the building system 1 is described as follows:

建築系統1之施工方法包括定位外圍建築系統10之預鑄柱結構及內部建築系統40之預鑄柱結構。舉例而言,在圖1所展示之實施例中,在對建築系統1之各樓層進行建造時,首先將該樓層之外圍建築系統10之四個預鑄角柱11放置於建築系統1之角隅,並將該樓層之外圍建築系統10之二個預鑄邊柱13放置於每二個預鑄角柱11之間。並且,將該樓層之內部建築系統40之二個內部預鑄柱結構43排列於該等預鑄角柱11及預鑄邊柱13所包圍之區域內。預鑄角柱11、預鑄邊柱13及內部預鑄柱結構43可各自具有建築系統1之單一樓層之高度,並藉由吊車(圖未示)垂直吊放於工地現場。在其他實施例中,預鑄角柱11、預鑄邊柱13及內部預鑄柱結構43可定位於已完成建造之下方樓層之預鑄連接結構之上。關於預鑄角柱、預鑄邊柱及內部預鑄柱結構與預鑄連接結構之連接方法請參見2022年10月17日申請之中華民國發明專利申請案第111139260號,該案之全部內容以引用方式併入本揭露中。The construction method of the building system 1 includes positioning the precast column structure of the peripheral building system 10 and the precast column structure of the internal building system 40. For example, in the embodiment shown in FIG. 1 , when constructing each floor of the building system 1, firstly, four precast corner columns 11 of the peripheral building system 10 of the floor are placed at the corners of the building system 1, and two precast side columns 13 of the peripheral building system 10 of the floor are placed between every two precast corner columns 11. In addition, two internal precast column structures 43 of the internal building system 40 of the floor are arranged in the area surrounded by the precast corner columns 11 and the precast side columns 13. The precast corner columns 11, precast side columns 13, and the internal precast column structure 43 can each have a height of a single floor of the building system 1, and can be vertically suspended on the construction site by a crane (not shown). In other embodiments, the precast corner columns 11, precast side columns 13, and the internal precast column structure 43 can be positioned on the precast connection structure of the completed lower floor. For the connection method of the precast corner columns, precast side columns, and the internal precast column structure with the precast connection structure, please refer to the Republic of China invention patent application No. 111139260 filed on October 17, 2022, the entire contents of which are incorporated by reference into this disclosure.

如圖2所示,預鑄角柱11包括管狀的複數個續接結構112垂直埋設於其中。續接結構112之一端部暴露於預鑄角柱11之頂表面111並經構形以允許垂直鋼筋9***其中並與其接合。相似地,預鑄邊柱13包括管狀的複數個續接結構132垂直埋設於其中。續接結構132之一端部暴露於預鑄邊柱13之頂表面131並經構形以允許垂直鋼筋9(未展示於圖2)***其中並與其接合。As shown in FIG. 2 , the precast corner column 11 includes a plurality of tubular connecting structures 112 vertically embedded therein. One end of the connecting structure 112 is exposed to the top surface 111 of the precast corner column 11 and is configured to allow the vertical steel bar 9 to be inserted therein and engaged therewith. Similarly, the precast side column 13 includes a plurality of tubular connecting structures 132 vertically embedded therein. One end of the connecting structure 132 is exposed to the top surface 131 of the precast side column 13 and is configured to allow the vertical steel bar 9 (not shown in FIG. 2 ) to be inserted therein and engaged therewith.

在預鑄柱結構定位完成後,建築系統1之施工方法更包括將預鑄連接結構固定設置於對應之預鑄柱結構之上,並在水平方向上對預鑄連接結構進行耦接。舉例而言,如圖3所示,該等預鑄連接結構中的第一預鑄連接結構15係藉由吊車(圖未示)吊放於預鑄角柱11之上。第一預鑄連接結構15包括一第一預鑄連接頭150及二個彼此大致垂直的第一梁結構151、152。第一預鑄連接頭150設置於預鑄角柱11上方,並經構形以其底部連接預鑄角柱11以及以其兩個相鄰側邊與該二個彼此大致垂直的第一梁結構151、152連接。複數個穿孔155垂直穿設第一預鑄連接頭150,當第一預鑄連接頭150吊放於預鑄角柱11之上時,如圖3所示,垂直鋼筋9穿過穿孔155,並自第一預鑄連接頭150之頂表面1503突出向上延伸。After the precast column structure is positioned, the construction method of the building system 1 further includes fixing the precast connection structure on the corresponding precast column structure and coupling the precast connection structure in the horizontal direction. For example, as shown in FIG3 , the first precast connection structure 15 among the precast connection structures is suspended on the precast corner column 11 by a crane (not shown). The first precast connection structure 15 includes a first precast connection head 150 and two first beam structures 151, 152 that are substantially perpendicular to each other. The first precast connection head 150 is disposed above the precast corner column 11 and is configured to be connected to the precast corner column 11 at its bottom and to be connected to the two first beam structures 151, 152 that are substantially perpendicular to each other at its two adjacent sides. A plurality of through holes 155 are vertically formed through the first precast connection head 150. When the first precast connection head 150 is suspended on the precast corner column 11, as shown in FIG. 3, the vertical steel bar 9 passes through the through holes 155 and protrudes upward from the top surface 1503 of the first precast connection head 150.

如圖2所示,垂直鋼筋9係在第一預鑄連接結構15吊放於預鑄角柱11之上之前即預先固定設置於預鑄角柱11之上,並在第一預鑄連接頭150經由吊放的下降過程中,使複數個垂直鋼筋9分別穿設複數個穿孔155。在一些實施例中,垂直鋼筋9係在第一預鑄連接結構15吊放於預鑄角柱11之上之後,方***穿孔155內並與預鑄角柱11內之續接結構132接合。在一些實施例中,如圖3A所示,第一預鑄連接頭150包括複數個箍筋156用以圍束設置於穿孔155中的垂直鋼筋。As shown in FIG2 , the vertical steel bars 9 are pre-fixed on the precast corner column 11 before the first precast connection structure 15 is suspended on the precast corner column 11, and the plurality of vertical steel bars 9 are respectively penetrated by the plurality of through holes 155 during the lowering process of the first precast connection head 150. In some embodiments, the vertical steel bars 9 are inserted into the through holes 155 and connected with the connecting structure 132 in the precast corner column 11 after the first precast connection structure 15 is suspended on the precast corner column 11. In some embodiments, as shown in FIG3A , the first precast connection head 150 includes a plurality of stirrups 156 for enclosing the vertical steel bars disposed in the through holes 155.

如圖4所示,二個第一梁結構151、152分別連結第一預鑄連接頭150上相互垂直之二個側表面1501、1502。換言之,二個第一梁結構151、152分別自第一預鑄連接頭150之相互垂直之二個側表面1501、1502向外延伸。如圖3A所示,每一第一梁結構151、152分別具有複數個梁鋼筋153、154,其一端設置於第一預鑄連接頭150內並自第一預鑄連接頭150向外沿水平方向延伸。複數個梁鋼筋153、154位於第一預鑄連接頭150內之端部包含具較大寬度之錨定頭1532、1542。藉由錨定頭1532、1542之設置可增加梁鋼筋153、154與第一預鑄連接頭150之間的連結強度。第一梁結構151、152之梁鋼筋153、154在第一預鑄連接頭150中位於不同高度,彼此互不干涉。As shown in FIG4 , the two first beam structures 151, 152 are respectively connected to two mutually perpendicular side surfaces 1501, 1502 of the first precast connection head 150. In other words, the two first beam structures 151, 152 extend outward from the two mutually perpendicular side surfaces 1501, 1502 of the first precast connection head 150. As shown in FIG3A , each of the first beam structures 151, 152 has a plurality of beam steel bars 153, 154, one end of which is disposed in the first precast connection head 150 and extends outward from the first precast connection head 150 in a horizontal direction. The ends of the plurality of beam steel bars 153, 154 located in the first precast connection head 150 include anchor heads 1532, 1542 with a larger width. The anchor heads 1532 and 1542 can increase the connection strength between the beam steel bars 153 and 154 and the first precast joint 150. The beam steel bars 153 and 154 of the first beam structures 151 and 152 are located at different heights in the first precast joint 150 and do not interfere with each other.

如圖3A所示,第一梁結構151之一端面1511係預先埋設有複數個鋼筋續接器60於其中。鋼筋續接器60為管狀且具有一第一開口61及一第二開口62,分別位於鋼筋續接器60之相對二端,並與鋼筋續接器60內部之中空通道連通。第二開口62與梁鋼筋153之末端1531固接。第一開口61暴露於第一梁結構151之端面1511並經構形以允許另一梁結構之梁鋼筋(未展示於圖3A)***其中並與其接合。如圖7E至圖7H所示,一第一貫穿孔63及一第二貫穿孔64分別相鄰第一開口61及第二開口62貫穿鋼筋續接器60之壁面,並經構形以連接用於輸送砂漿材料之漿料管線。關於漿料管線之供應方式將於下方關於圖7D至圖7I之描述中詳細說明。As shown in FIG3A , a plurality of rebar connectors 60 are pre-embedded in one end face 1511 of the first beam structure 151. The rebar connector 60 is tubular and has a first opening 61 and a second opening 62, which are located at two opposite ends of the rebar connector 60 and communicate with the hollow passage inside the rebar connector 60. The second opening 62 is fixedly connected to the end 1531 of the beam rebar 153. The first opening 61 is exposed to the end face 1511 of the first beam structure 151 and is configured to allow the beam rebar (not shown in FIG3A ) of another beam structure to be inserted therein and joined thereto. As shown in Figures 7E to 7H, a first through hole 63 and a second through hole 64 respectively penetrate the wall of the rebar connector 60 adjacent to the first opening 61 and the second opening 62, and are configured to connect to a slurry pipeline for conveying mortar material. The supply method of the slurry pipeline will be described in detail in the description of Figures 7D to 7I below.

繼續參照圖4,在第一預鑄連接結構15定位施工完成後,繼續第二預鑄連接結構17之定位施工。在一實施例中,第二預鑄連接結構17包括一第二預鑄連接頭170及二個第二梁結構171、172。第二預鑄連接頭170設置於預鑄邊柱13上方,並經構形以其底部連接預鑄邊柱13且以其兩相對側與二個彼此大致平行且對齊之第二梁結構171、172連接。換言之,二個第二梁結構171、172分別自第二預鑄連接頭170之相對之二個側表面1701、1702向外延伸。相似於第一梁結構151、152,第二梁結構171、172也分別具有複數個梁鋼筋(圖4僅展示第二梁結構172之梁鋼筋174),其一端設置於第二預鑄連接頭170內並自第二預鑄連接頭170向外沿水平方向延伸。第二梁結構171之梁鋼筋之末端係固定於位於端面1711之鋼筋續接器60中,且第二梁結構172之梁鋼筋174之末端自第二梁結構172之端面1721延伸而出。複數個穿孔175垂直穿設第二預鑄連接頭170。穿孔175經構形以允許垂直鋼筋(未展示於圖4)穿設,進而將第二預鑄連接頭170固定於預鑄邊柱13之上。第二預鑄連接結構17進一步包括複數個梁鋼筋179,其一端設置於第二預鑄連接頭170內並自第二預鑄連接頭170之側表面1703向外沿水平方向延伸。第二預鑄連接頭170之側表面1703面向建築物內部,並位於側表面1701、1702之間。梁鋼筋179經構形以連接場鑄梁結構42(參圖1)。Continuing to refer to FIG. 4 , after the positioning construction of the first precast connection structure 15 is completed, the positioning construction of the second precast connection structure 17 is continued. In one embodiment, the second precast connection structure 17 includes a second precast connection head 170 and two second beam structures 171, 172. The second precast connection head 170 is disposed above the precast side column 13, and is configured to connect the precast side column 13 with its bottom and to connect with two second beam structures 171, 172 that are substantially parallel and aligned with each other at its two opposite sides. In other words, the two second beam structures 171, 172 extend outward from two opposite side surfaces 1701, 1702 of the second precast connection head 170, respectively. Similar to the first beam structures 151 and 152, the second beam structures 171 and 172 also have a plurality of beam steel bars (FIG. 4 only shows the beam steel bar 174 of the second beam structure 172), one end of which is disposed in the second precast connection head 170 and extends outwardly from the second precast connection head 170 in a horizontal direction. The end of the beam steel bar of the second beam structure 171 is fixed in the steel bar connector 60 located at the end surface 1711, and the end of the beam steel bar 174 of the second beam structure 172 extends out from the end surface 1721 of the second beam structure 172. A plurality of through holes 175 are vertically penetrated through the second precast connection head 170. The through hole 175 is configured to allow vertical steel bars (not shown in FIG. 4 ) to pass through, thereby fixing the second precast connection head 170 to the precast side column 13. The second precast connection structure 17 further includes a plurality of beam steel bars 179, one end of which is disposed in the second precast connection head 170 and extends horizontally outward from the side surface 1703 of the second precast connection head 170. The side surface 1703 of the second precast connection head 170 faces the interior of the building and is located between the side surfaces 1701 and 1702. The beam steel bars 179 are configured to connect the field-cast beam structure 42 (see FIG. 1 ).

參照圖4-6,第二預鑄連接結構17與預鑄邊柱13定位並與第一預鑄連接結構15對接之施工步驟說明如下:首先,先將第二預鑄連接結構17吊放至預鑄邊柱13之頂表面130之上之一偏移位置。如圖4所示,在此偏移位置上,第二梁結構172之端面1721與第一梁結構151之端面1511間隔一既定距離,且第二預鑄連接頭170係與預鑄邊柱13之頂表面130偏移設置,使第二預鑄連接頭170未完全覆蓋預鑄邊柱13之頂表面130。接著,沿圖4之箭頭所示之方向,對第二預鑄連接結構17執行一橫向移動施工。在橫向移動施工中,第二預鑄連接結構17朝向第一預鑄連接結構15移動,使固定於第一梁結構151內之鋼筋續接器60套設第二梁結構172之梁鋼筋174,並使第二梁結構172之端面1721相鄰第一梁結構151之端面1511設置。在完成上述橫向移動之施工後,如圖5所示,第二預鑄連接頭170對齊預鑄邊柱13之頂表面130,且第二預鑄連接頭170完全覆蓋預鑄邊柱13之頂表面130。接著,如圖6所示,在第二預鑄連接頭170對齊預鑄邊柱13之頂表面130之後,將垂直鋼筋9***第二預鑄連接頭170上之穿孔175內並使其與預鑄邊柱13內之續接結構132(參圖3)接合。Referring to Figures 4-6, the construction steps of positioning the second precast connection structure 17 with the precast side column 13 and docking with the first precast connection structure 15 are described as follows: First, the second precast connection structure 17 is suspended to an offset position above the top surface 130 of the precast side column 13. As shown in Figure 4, at this offset position, the end surface 1721 of the second beam structure 172 is spaced a predetermined distance from the end surface 1511 of the first beam structure 151, and the second precast connection head 170 is offset from the top surface 130 of the precast side column 13, so that the second precast connection head 170 does not completely cover the top surface 130 of the precast side column 13. Then, along the direction indicated by the arrow in Figure 4, a lateral movement construction is performed on the second precast connection structure 17. During the lateral movement construction, the second precast connection structure 17 moves toward the first precast connection structure 15, so that the steel bar connector 60 fixed in the first beam structure 151 is sleeved with the beam steel bar 174 of the second beam structure 172, and the end surface 1721 of the second beam structure 172 is arranged adjacent to the end surface 1511 of the first beam structure 151. After the above-mentioned lateral movement construction is completed, as shown in FIG. 5, the second precast connection head 170 is aligned with the top surface 130 of the precast side column 13, and the second precast connection head 170 completely covers the top surface 130 of the precast side column 13. Next, as shown in FIG. 6 , after the second precast connection head 170 is aligned with the top surface 130 of the precast side column 13 , the vertical steel bar 9 is inserted into the through hole 175 on the second precast connection head 170 and engaged with the connecting structure 132 (see FIG. 3 ) in the precast side column 13 .

在一實施例中,砂漿材料(圖未示)係填充於預鑄連接頭(例如:第一預鑄連接結構15、第二預鑄連接結構17)與預鑄柱(例如:預鑄角柱11、預鑄邊柱13)之間並且填充於垂直鋼筋9穿設之穿孔5之部分空間中,以固定預鑄連接頭、預鑄柱及垂直鋼筋。關於預鑄連接頭、預鑄柱及垂直鋼筋之連接方法請參見2022年6月30日申請之中華民國發明專利申請案第111124472號,該案之全部內容以引用方式併入本揭露中。In one embodiment, mortar material (not shown) is filled between the precast connection head (e.g., the first precast connection structure 15, the second precast connection structure 17) and the precast column (e.g., the precast corner column 11, the precast side column 13) and filled in part of the space of the through hole 5 through which the vertical steel bar 9 is penetrated to fix the precast connection head, the precast column and the vertical steel bar. For the connection method of the precast connection head, the precast column and the vertical steel bar, please refer to the Republic of China invention patent application No. 111124472 filed on June 30, 2022, the entire contents of which are incorporated into this disclosure by reference.

在一實施例中,相鄰之預鑄梁結構之續接方法,參照圖7A-7C,說明如後。如圖7A-7C所示,複數個漿料管線70係埋設於第一梁結構151鄰近端面1511之區域,並經構形以供應砂漿材料至埋設於第一梁結構151內部之鋼筋續接器60,或是經構形以允許少部分多餘砂漿材料自埋設於第一梁結構151內部之鋼筋續接器60流出。如圖7B所示,每一漿料管線70具有一第一端71及一第二端72。漿料管線70之第一端71係連結於鋼筋續接器60。又,如圖7A所示,漿料管線70之第二端72係暴露於第一梁結構151之側表面1512與上表面1513之上,以允許一傳輸管連接或允許來自鋼筋續接器60之少部分多餘砂漿材料對外排出。In one embodiment, the method of connecting adjacent precast beam structures is described below with reference to FIGS. 7A-7C. As shown in FIGS. 7A-7C, a plurality of slurry pipelines 70 are buried in the area adjacent to the proximal end surface 1511 of the first beam structure 151, and are configured to supply mortar material to the steel bar connector 60 buried inside the first beam structure 151, or are configured to allow a small amount of excess mortar material to flow out of the steel bar connector 60 buried inside the first beam structure 151. As shown in FIG. 7B, each slurry pipeline 70 has a first end 71 and a second end 72. The first end 71 of the slurry pipeline 70 is connected to the steel bar connector 60. 7A, the second end 72 of the slurry pipeline 70 is exposed on the side surface 1512 and the upper surface 1513 of the first beam structure 151 to allow a transmission pipe to be connected or to allow a small amount of excess mortar material from the rebar connector 60 to be discharged to the outside.

在一些實施例中,如圖7C所示,在鋼筋續接器60具有第一貫穿孔63及第二貫穿孔64之實施例中,鋼筋續接器60之第一貫穿孔63及第二貫穿孔64之每一者皆流體連接漿料管線70,以接收來自漿料管線70之砂漿材料或以自其內部排出砂漿材料至漿料管線70。因此,複數個漿料管線70的數量為鋼筋續接器60之第一貫穿孔63及第二貫穿孔64之數量之總和。漿料管線70可以具一定硬度以防止在第一梁結構151之混凝土定形期間受壓縮而變形但同時允許彎折之材料所製成。舉例而言,漿料管線70可由多層PVC塑膠軟管交疊設置而成。In some embodiments, as shown in FIG. 7C , in an embodiment where the rebar connector 60 has a first through hole 63 and a second through hole 64, each of the first through hole 63 and the second through hole 64 of the rebar connector 60 is fluidly connected to a slurry pipeline 70 to receive mortar material from the slurry pipeline 70 or to discharge mortar material from the inside thereof to the slurry pipeline 70. Therefore, the number of the plurality of slurry pipelines 70 is the sum of the number of the first through hole 63 and the second through hole 64 of the rebar connector 60. The slurry pipeline 70 may be made of a material having a certain hardness to prevent deformation due to compression during the concrete setting period of the first beam structure 151 but allowing bending at the same time. For example, the slurry pipeline 70 may be formed by overlapping multiple layers of PVC plastic hoses.

圖7D-7I展示建築系統1之第一預鑄連接結構15之第一梁結構151與第二預鑄連接結構17之第二梁結構172之續接方法之示意圖。如圖7D所示,第一梁結構151與第二梁結構172之續接方法包括將第一梁結構151之端面1511相鄰第二梁結構172之端面1721設置,以定義一間隙G於其間。7D-7I show schematic diagrams of a method for connecting the first beam structure 151 of the first precast connection structure 15 and the second beam structure 172 of the second precast connection structure 17 of the building system 1. As shown in FIG7D , the method for connecting the first beam structure 151 and the second beam structure 172 includes placing the end surface 1511 of the first beam structure 151 adjacent to the end surface 1721 of the second beam structure 172 to define a gap G therebetween.

接著,如圖7D所示,將間隙G左右兩側及下方以一密封元件92密封。在此實施例中,密封元件92為一板模,其貼附於第一梁結構151及第二梁結構172之側表面及底表面以部分密封間隙G。在另一實施例中,密封元件92為封膜氣胎。封膜氣胎可在一未充氣之情況下放入間隙G的四周,接著再將氣體填充進入封膜氣胎,以部分密封間隙G。在又一實施例中,間隙G之上方並未為密封元件92所覆蓋。Next, as shown in FIG. 7D , the left and right sides and the bottom of the gap G are sealed with a sealing element 92. In this embodiment, the sealing element 92 is a plate mold, which is attached to the side surface and the bottom surface of the first beam structure 151 and the second beam structure 172 to partially seal the gap G. In another embodiment, the sealing element 92 is a sealing film pneumatic tire. The sealing film pneumatic tire can be placed around the gap G in an uninflated state, and then gas is filled into the sealing film pneumatic tire to partially seal the gap G. In another embodiment, the top of the gap G is not covered by the sealing element 92.

接著,如圖7D、7E所示,經由灌漿管道70將一砂漿材料93(例如無收縮砂漿)填充至間隙G中。砂漿材料93可由一傳輸管95供應,其中傳輸管95可連接至第一梁結構151之側表面1512上排列於最下方之漿料管線70,以供應砂漿材料93至排列於第一梁結構151最下方且緊鄰側表面1512之鋼筋續接器60內部。並且,如圖7E所示,傳輸管95所連接之漿料管線70係流體連接至所述鋼筋續接器60之第二貫穿孔64。亦即,傳輸管95連接至鋼筋續接器60較為遠離間隙G之一側。為清楚說明,以下內容以「上游鋼筋續接器60’」稱此流體連接傳輸管95且排列於第一梁結構151最下方並緊鄰側表面1512(參圖7B)之鋼筋續接器。Next, as shown in FIGS. 7D and 7E , a mortar material 93 (e.g., non-shrinkage mortar) is filled into the gap G through the grouting pipe 70. The mortar material 93 may be supplied by a transmission pipe 95, wherein the transmission pipe 95 may be connected to the mortar pipeline 70 arranged at the bottom on the side surface 1512 of the first beam structure 151, so as to supply the mortar material 93 to the inside of the steel bar connector 60 arranged at the bottom of the first beam structure 151 and adjacent to the side surface 1512. Furthermore, as shown in FIG. 7E , the mortar pipeline 70 connected to the transmission pipe 95 is fluidically connected to the second through hole 64 of the steel bar connector 60. That is, the transmission pipe 95 is connected to a side of the rebar connector 60 that is farther from the gap G. For clarity, the following content refers to the rebar connector 60' that is connected to the fluid transmission pipe 95 and is arranged at the bottom of the first beam structure 151 and close to the side surface 1512 (see FIG. 7B ).

如圖7E所示,當傳輸管95供應砂漿材料93時,砂漿材料93自漿料管線70經由上游鋼筋續接器60’之第二貫穿孔64進入上游鋼筋續接器60’內部。隨著砂漿材料93持續供應,砂漿材料93在上游鋼筋續接器60’與梁鋼筋153之間的空隙向上流動、以及上游鋼筋續接器60’與梁鋼筋174之間的空隙流動,進而填滿上游鋼筋續接器60’之內部。當上游鋼筋續接器60’內部為砂漿材料93所填滿後,少量砂漿材料93自連接上游鋼筋續接器60’之第一貫穿孔63之漿料管線70排出,其餘砂漿材料93則經由連通至間隙G之第一開口61自上游鋼筋續接器60’流出。As shown in Fig. 7E, when the transmission pipe 95 supplies the mortar material 93, the mortar material 93 enters the interior of the upstream steel bar connector 60' through the second through hole 64 of the upstream steel bar connector 60' from the mortar pipeline 70. As the mortar material 93 is continuously supplied, the mortar material 93 flows upward in the gap between the upstream steel bar connector 60' and the beam steel bar 153, and flows in the gap between the upstream steel bar connector 60' and the beam steel bar 174, thereby filling the interior of the upstream steel bar connector 60'. When the interior of the upstream rebar connector 60' is filled with the mortar material 93, a small amount of the mortar material 93 is discharged from the mortar pipeline 70 connected to the first through hole 63 of the upstream rebar connector 60', and the remaining mortar material 93 flows out of the upstream rebar connector 60' through the first opening 61 connected to the gap G.

如圖7F所示,隨著砂漿材料93持續自傳輸管95供應至上游鋼筋續接器60’內並流向間隙G,由於間隙G為密封元件92所部分封閉,故砂漿材料93將經由其餘鋼筋續接器60之第一開口61進入至各個鋼筋續接器60內,並在該些鋼筋續接器60與梁鋼筋153之間的空隙向上流動、以及鋼筋續接器60與梁鋼筋174之間的空隙向上流動。並且,如圖7G所示,當個別鋼筋續接器60為砂漿材料93充分填充時,鋼筋續接器60內的砂漿材料93將自連結至對應之鋼筋續接器60之漿料管線70之第二端72排出第一梁結構151外部。在本實施例中,傳輸管95僅經由單一漿料管線70供應砂漿材料,因此施工人員可藉由觀察砂漿材料自各個漿料管線70流出之情況,進而確認砂漿材料在鋼筋續接器60之填充狀況。舉例而言,如圖7F及7G上方展示之箭頭所示,當砂漿材料自連結位於第一梁結構151上方之鋼筋續接器60之漿料管線70之第二端72流出時,即表示位於第一梁結構151最上方之鋼筋續接器60內部已充分填充砂漿材料。As shown in FIG. 7F , as the mortar material 93 is continuously supplied from the transmission pipe 95 to the upstream rebar connector 60′ and flows toward the gap G, since the gap G is partially closed by the sealing element 92, the mortar material 93 will enter each rebar connector 60 through the first opening 61 of the remaining rebar connectors 60, and flow upward in the gaps between the rebar connectors 60 and the beam rebar 153, and flow upward in the gaps between the rebar connectors 60 and the beam rebar 174. Furthermore, as shown in FIG. 7G , when the individual rebar connectors 60 are fully filled with the mortar material 93, the mortar material 93 in the rebar connector 60 will be discharged from the second end 72 of the mortar pipeline 70 connected to the corresponding rebar connector 60 to the outside of the first beam structure 151. In this embodiment, the transmission pipe 95 only supplies the mortar material through a single mortar pipeline 70, so the construction personnel can confirm the filling status of the mortar material in the rebar connector 60 by observing the mortar material flowing out from each mortar pipeline 70. For example, as shown by the arrows shown above in FIGS. 7F and 7G , when the mortar material flows out from the second end 72 of the mortar pipeline 70 connected to the rebar connector 60 located above the first beam structure 151 , it means that the interior of the rebar connector 60 located at the top of the first beam structure 151 has been fully filled with the mortar material.

在一實施例中,隨著砂漿材料依序自連接不同鋼筋續接器60之漿料管線70排出,但一或多個漿料管線70之第二端72未有砂漿材料排出時,此時可判定未有砂漿材料排出之漿料管線70所連接之鋼筋續接器60並未充分填充砂漿材料。此時,施工人員可進一步將傳輸管95***該未有砂漿材料排出之漿料管線70,逐一朝可能未充分填充砂漿材料之鋼筋續接器60供應砂漿材料。在鋼筋續接器60具有第一貫穿孔63及第二貫穿孔64之實施例中,施工人員可以藉由觀察砂漿材料是否由連接相同鋼筋續接器60之另一漿料管線70排出,進而判斷該鋼筋續接器60是否已充分填充砂漿材料。In one embodiment, as mortar material is sequentially discharged from the mortar pipelines 70 connected to different rebar connectors 60, if no mortar material is discharged from the second ends 72 of one or more mortar pipelines 70, it can be determined that the rebar connectors 60 connected to the mortar pipelines 70 from which no mortar material is discharged are not fully filled with mortar material. At this time, the construction personnel can further insert the transmission pipe 95 into the mortar pipelines 70 from which no mortar material is discharged, and supply mortar material to the rebar connectors 60 that may not be fully filled with mortar material one by one. In the embodiment where the rebar connector 60 has the first through hole 63 and the second through hole 64, the construction personnel can judge whether the rebar connector 60 is fully filled with mortar material by observing whether the mortar material is discharged from another mortar pipeline 70 connected to the same rebar connector 60.

參照圖7H,在完成砂漿材料之填充程序後,第一梁結構151與第二梁結構172之續接方法進一步包括將多個塞子94***漿料管線70暴露於第一梁結構151表面之第二端72,以防止砂漿材料在凝固前自鋼筋續接器60內流出。在一實施例中,塞子94是在所有鋼筋續接器60皆充分填充有砂將材料後才***至漿料管線70之一端。在另一實施例中,塞子94是在確認個別鋼筋續接器60已充分填充有砂將材料時即***至連結該鋼筋續接器60之漿料管線70之第二端72中。7H , after the filling process of the mortar material is completed, the method of connecting the first beam structure 151 and the second beam structure 172 further includes inserting a plurality of plugs 94 into the second end 72 of the mortar pipeline 70 exposed to the surface of the first beam structure 151 to prevent the mortar material from flowing out of the rebar connector 60 before solidification. In one embodiment, the plug 94 is inserted into one end of the mortar pipeline 70 after all the rebar connectors 60 are fully filled with the mortar material. In another embodiment, the plug 94 is inserted into the second end 72 of the mortar pipeline 70 connecting the rebar connector 60 when it is confirmed that the individual rebar connector 60 has been fully filled with the mortar material.

如圖7H所示,第一梁結構151之端面1511之中心進一步包括複數個溝槽157((請同時參圖3))形成於其上。在砂漿材料93填充間隙G之過程中,部分砂漿材料93將流入溝槽157內。當砂漿材料93凝固後,位於溝槽157內之砂漿材料93形成朝第一梁結構151內部延伸之多個接合結構,其進步一增強第一梁結構151與第二梁結構172之續接強度。As shown in FIG. 7H , the center of the end surface 1511 of the first beam structure 151 further includes a plurality of grooves 157 (see FIG. 3 ) formed thereon. During the process of the mortar material 93 filling the gap G, part of the mortar material 93 will flow into the groove 157. After the mortar material 93 solidifies, the mortar material 93 in the groove 157 forms a plurality of joint structures extending toward the inside of the first beam structure 151, which further enhances the joint strength between the first beam structure 151 and the second beam structure 172.

在砂漿材料充分填充鋼筋續接器後,第一梁結構151與第二梁結構172之續接方法進一步包括將塞子94移除,並貼附裝飾面板91(例如:石材)於第一梁結構151及第二梁結構172之外表面之上。裝飾面板91係設置於建築系統之最外圍,用於裝飾建築系統之外觀。在一實施例中,如圖7A所示,在第一梁結構151及第二梁結構172未填充砂漿材料前,第一梁結構151之上表面1513及第二梁結構172之上表面1723之部分區域即預先貼附有裝飾面板91,但裝飾面板91未覆蓋設置有漿料管線70之第二端72之區域。並且,如圖7I所示,在第一梁結構151及第二梁結構172之間以及其鄰近區域填充砂漿材料後,第一梁結構151之上表面1513或第二梁結構172之上表面1723上設置有漿料管線70之第二端72之區域才進一步覆蓋有裝飾面板91。裝飾面板91可利用例如黏著劑之材料貼附於第一梁結構151或第二梁結構172之上。透過預先將大部分裝飾面板91貼附於預鑄結構之上,而僅在工地現場後貼部分區域之裝飾面板91之施作方法,可有效縮短工地現場之施工時間。After the mortar material is fully filled in the steel bar connector, the method of connecting the first beam structure 151 and the second beam structure 172 further includes removing the plug 94 and attaching a decorative panel 91 (e.g., stone) on the outer surface of the first beam structure 151 and the second beam structure 172. The decorative panel 91 is arranged at the outermost periphery of the building system and is used to decorate the appearance of the building system. In one embodiment, as shown in FIG. 7A, before the first beam structure 151 and the second beam structure 172 are filled with mortar material, the decorative panel 91 is pre-attached to a portion of the upper surface 1513 of the first beam structure 151 and the upper surface 1723 of the second beam structure 172, but the decorative panel 91 does not cover the area where the second end 72 of the slurry pipeline 70 is arranged. Furthermore, as shown in FIG. 7I , after the mortar material is filled between the first beam structure 151 and the second beam structure 172 and the adjacent areas, the area on the upper surface 1513 of the first beam structure 151 or the upper surface 1723 of the second beam structure 172 where the second end 72 of the mortar pipeline 70 is disposed is further covered with the decorative panel 91. The decorative panel 91 can be attached to the first beam structure 151 or the second beam structure 172 using a material such as an adhesive. By attaching most of the decorative panel 91 to the precast structure in advance and only attaching the decorative panel 91 in a part of the area on the construction site, the construction time on the construction site can be effectively shortened.

應當理解的是,上述實施例中,用於連接梁結構之鋼筋續接器與梁鋼筋之設置位置係可彼此互換,並不侷限於上述實施例所述之樣態。舉例而言,第一梁結構151之端面1511可包括多個梁鋼筋向外沿水平方向延伸,而第二梁結構172之端面1721可包括多個預先設置之鋼筋續接器。第一梁結構151與第二梁結構172對接時,第二梁結構172之鋼筋續接器套設第一梁結構151之梁鋼筋,並藉由如圖7A-7I之方式填充砂漿材料,以固定第一梁結構151與第二梁結構172。It should be understood that in the above-mentioned embodiments, the steel bar connectors and the beam steel bars used to connect the beam structures can be interchanged with each other and are not limited to the forms described in the above-mentioned embodiments. For example, the end surface 1511 of the first beam structure 151 may include a plurality of beam steel bars extending outward in the horizontal direction, and the end surface 1721 of the second beam structure 172 may include a plurality of pre-set steel bar connectors. When the first beam structure 151 and the second beam structure 172 are butt-joined, the steel bar connector of the second beam structure 172 is sleeved with the beam steel bars of the first beam structure 151, and mortar material is filled in the manner as shown in Figures 7A-7I to fix the first beam structure 151 and the second beam structure 172.

繼續參照圖8,位於圖1下方之第一預鑄連接結構15及第二預鑄連接結構17同樣以如圖2-6之實施例所描述之方法分別定位於預鑄角柱11及預鑄邊柱13之上,並且以如圖7D-7I之實施例所描述之方法彼此進行對接,進而形成圖9之建築結構。如圖9所示,由於位於建築系統單一側邊之第一預鑄連接結構15係先定位於預鑄角柱11之上,隨後二個第二預鑄連接結構17才定位於預鑄邊柱13之上,因此,二個第二預鑄連接結構17之間具有一緩衝空間,以允許圖9所示之右側第二預鑄連接結構17被預先執行如圖4所展示之橫向移動施工。接著,如圖10所示,建築系統1進一步包括一預鑄梁結構20及一場鑄接續結構30以連結相鄰之二個預鑄連接結構(例如:圖10所示之右側第二預鑄連接結構17及左側第二預鑄連接結構17)之梁結構。Continuing with reference to FIG8 , the first precast connection structure 15 and the second precast connection structure 17 located at the bottom of FIG1 are respectively positioned on the precast corner column 11 and the precast side column 13 using the method described in the embodiment of FIGS. 2-6 , and are connected to each other using the method described in the embodiment of FIGS. 7D-7I , thereby forming the building structure of FIG9 . As shown in FIG. 9 , since the first precast connection structure 15 located on a single side of the building system is first positioned on the precast corner column 11, and then the two second precast connection structures 17 are positioned on the precast side columns 13, there is a buffer space between the two second precast connection structures 17 to allow the second precast connection structure 17 on the right side shown in FIG. 9 to be pre-moved horizontally as shown in FIG. 4 . Next, as shown in FIG. 10 , the building system 1 further includes a precast beam structure 20 and a field-cast connecting structure 30 to connect the beam structures of two adjacent precast connecting structures (for example, the right second precast connecting structure 17 and the left second precast connecting structure 17 shown in FIG. 10 ).

參照圖10,其係預鑄梁結構20及場鑄接續結構30放置於二個第二預鑄連接結構17之間之結構***圖,並展示二個相鄰之預鑄連接結構17藉由預鑄梁結構20及場鑄接續結構30進行續接之方法。預鑄梁結構20大致具有長形之形狀,具有相對的第一端201以及第二端202,並包括複數個梁鋼筋21埋設於其中(參圖12)。梁鋼筋21係沿預鑄梁結構20之長度方向上延伸,且其一端自預鑄梁結構20之第二端202向外伸出。預鑄梁結構20之第一端201係預先埋設有複數個鋼筋續接器60於其中。鋼筋續接器60係經構形以將自第二預鑄連接結構17之第二梁結構171向外沿水平方向延伸之梁鋼筋173連結至預鑄梁結構20內之梁鋼筋21。為清楚描述之目的,以下說明中以梁鋼筋21稱做「第一梁鋼筋」,且梁鋼筋173稱做「第二梁鋼筋」。在一實施例中,預鑄梁結構205之本體的長度L2係小於所欲對接之二個相鄰之預鑄連接結構之端面之間隔距離L1。預鑄梁結構205之本體的長度L2係指預鑄梁結構205之第一端201至第一梁鋼筋21之自由端之距離。Referring to FIG. 10 , it is an exploded view of a structure in which a precast beam structure 20 and a field-cast connecting structure 30 are placed between two second precast connecting structures 17, and shows a method of connecting two adjacent precast connecting structures 17 by means of the precast beam structure 20 and the field-cast connecting structure 30. The precast beam structure 20 is generally in an elongated shape, has a first end 201 and a second end 202 opposite to each other, and includes a plurality of beam steel bars 21 embedded therein (see FIG. 12 ). The beam steel bars 21 extend along the length direction of the precast beam structure 20, and one end thereof extends outward from the second end 202 of the precast beam structure 20. The first end 201 of the precast beam structure 20 is pre-embedded with a plurality of steel bar connectors 60. The steel bar connector 60 is configured to connect the beam steel bar 173 extending outwardly in the horizontal direction from the second beam structure 171 of the second precast connection structure 17 to the beam steel bar 21 in the precast beam structure 20. For the purpose of clear description, the beam steel bar 21 is referred to as the "first beam steel bar" and the beam steel bar 173 is referred to as the "second beam steel bar" in the following description. In one embodiment, the length L2 of the body of the precast beam structure 205 is less than the spacing distance L1 between the end faces of the two adjacent precast connection structures to be connected. The length L2 of the body of the precast beam structure 205 refers to the distance from the first end 201 of the precast beam structure 205 to the free end of the first beam steel bar 21.

預鑄梁結構20與二個相鄰之預鑄連接結構17之第一者(圖10右方之第二預鑄連接結構17)之對接方法說明如下:首先,將預鑄梁結構20吊放至二個第二預鑄連接結構17之二個第二梁結構171之間。接著,對預鑄梁結構20執行一橫向移動施工。在橫向移動過程中,預鑄梁結構20朝向預鑄連接結構17之第一者(圖10右方)移動,使預鑄梁結構20內之鋼筋連接器60套設於預鑄連接結構17之第一者(圖10右方)之第二梁鋼筋173,並且使第二梁結構171之端面173鄰接預鑄梁結構20之第一端201,如圖11所示。接著,執行相似於上述圖7D-7I中所描述之二個梁結構續接之方法,以完成鑄連接結構17之第一者(圖10右方)與預鑄梁結構20之對接施工。The method of connecting the precast beam structure 20 with the first of the two adjacent precast connection structures 17 (the second precast connection structure 17 on the right side of FIG. 10 ) is described as follows: First, the precast beam structure 20 is suspended between the two second beam structures 171 of the two second precast connection structures 17. Then, the precast beam structure 20 is subjected to a lateral movement operation. During the lateral movement, the precast beam structure 20 moves toward the first precast connection structure 17 (right side of FIG. 10 ), so that the steel bar connector 60 in the precast beam structure 20 is sleeved on the second beam steel bar 173 of the first precast connection structure 17 (right side of FIG. 10 ), and the end face 173 of the second beam structure 171 is adjacent to the first end 201 of the precast beam structure 20, as shown in FIG. 11 . Then, a method similar to the above-mentioned method of connecting two beam structures described in FIGS. 7D-7I is performed to complete the butt connection construction between the first precast connection structure 17 (right side of FIG. 10 ) and the precast beam structure 20.

如圖12所示,場鑄接續結構30係經構形以將預鑄梁結構20與預鑄連接結構17之第二者(圖10左方之第二預鑄連接結構17)進行對接。在一實施例中,場鑄接續結構30包括複數個固定鋼筋續接器31、複數個連接鋼筋32、複數個圍束結構34、及複數個可移動鋼筋續接器35。圖12A顯示場鑄接續結構30、預鑄梁結構20、預鑄連接結構17三者結合之***圖。在一實施例中,固定鋼筋續接器31預先埋設於第二預鑄連接結構17之第二者(圖10左方)中,且包括之一端部311暴露於預鑄連接結構17之端面1711。固定鋼筋續接器31之端部311之內壁面可包括內螺紋結構312,連接鋼筋32其一端部321包括外螺紋結構322。經由固定鋼筋續接器31之內螺紋結構312與連接鋼筋32之外螺紋結構322之嚙合,連接鋼筋32螺紋連接至固定鋼筋續接器31。在一實施例中,連接鋼筋32之長度L5係小於或等於第二梁鋼筋21之自由端與預鑄連接結構17之端面1711之間隔距離L6。因此,如圖12A所示,當連接鋼筋32的外螺紋結構322與固定鋼筋續接器31之內螺紋結構312嚙合之後,連接鋼筋32與第二梁鋼筋21相隔一間距。可移動鋼筋續接器35為管狀,並且經構形以可移動的方式套設於第一梁鋼筋21以及連接鋼筋32之上。複數個圍束結構圍束結構34套設於預鑄梁結構20之第二梁鋼筋21及可移動鋼筋續接器35外側,用以圍束第二梁鋼筋21。圍束結構34可選自複數個箍筋、一或多個彈簧結構、或其他可環繞於第一梁鋼筋21外側並可由一未展開狀態(如圖13所示)轉換成一展開狀態(如圖14所示)之類似結構。在未展開狀態下,連接鋼筋32未被圍束結構34所圍繞。在展開狀態下,連接鋼筋32被圍束結構34所圍繞。As shown in FIG12 , the field-cast connection structure 30 is configured to connect the precast beam structure 20 with the second of the precast connection structures 17 (the second precast connection structure 17 on the left side of FIG10 ). In one embodiment, the field-cast connection structure 30 includes a plurality of fixed steel bar connectors 31, a plurality of connecting steel bars 32, a plurality of confinement structures 34, and a plurality of movable steel bar connectors 35. FIG12A shows an exploded view of the field-cast connection structure 30, the precast beam structure 20, and the precast connection structure 17. In one embodiment, the fixed steel bar connector 31 is pre-buried in the second of the second pre-cast connection structures 17 (left side of FIG. 10 ), and includes an end portion 311 exposed to the end surface 1711 of the pre-cast connection structure 17. The inner wall surface of the end portion 311 of the fixed steel bar connector 31 may include an internal thread structure 312, and the end portion 321 of the connecting steel bar 32 includes an external thread structure 322. The connecting steel bar 32 is threadedly connected to the fixed steel bar connector 31 through the engagement of the internal thread structure 312 of the fixed steel bar connector 31 and the external thread structure 322 of the connecting steel bar 32. In one embodiment, the length L5 of the connecting steel bar 32 is less than or equal to the distance L6 between the free end of the second beam steel bar 21 and the end surface 1711 of the precast connection structure 17. Therefore, as shown in FIG12A, after the outer thread structure 322 of the connecting steel bar 32 is engaged with the inner thread structure 312 of the fixed steel bar connector 31, the connecting steel bar 32 is spaced apart from the second beam steel bar 21. The movable steel bar connector 35 is tubular and is configured to be movably mounted on the first beam steel bar 21 and the connecting steel bar 32. A plurality of restraining structures The restraining structures 34 are sleeved on the second beam reinforcement 21 of the precast beam structure 20 and the outer side of the movable reinforcement connector 35 to restrain the second beam reinforcement 21. The restraining structures 34 can be selected from a plurality of stirrups, one or more spring structures, or other similar structures that can surround the outer side of the first beam reinforcement 21 and can be converted from an unexpanded state (as shown in FIG. 13) to an expanded state (as shown in FIG. 14). In the unexpanded state, the connecting reinforcement 32 is not surrounded by the restraining structures 34. In the expanded state, the connecting reinforcement 32 is surrounded by the restraining structures 34.

預鑄梁結構20經由場鑄接續結構30與預鑄連接結構17之第二者(圖10左方)之對接方法說明如下:首先,將場鑄接續結構30之可移動鋼筋續接器35與圍束結構34套設於第一梁鋼筋21上。如圖10所示,場鑄接續結構30之可移動鋼筋續接器35與圍束結構34係預先設置於預鑄梁結構20之第一梁鋼筋21上,並連同預鑄梁結構20一同吊放至二個相鄰之第二預鑄連接結構17之間。接著,如圖12所示,在預鑄梁結構20與二個相鄰之第二預鑄連接結構之17第一者(圖10右方)對接完成後,將連接鋼筋32連接至第二預鑄連接結構之17第二者(圖10左方)之固定鋼筋續接器31。接著,如圖13所示,移動可移動鋼筋續接器35,使其一端之開口套設於第一梁鋼筋21,且其另一端之開口套設於連接鋼筋32。接著,如圖13A所示,供應砂漿材料37至可移動鋼筋續接器35中,以使可移動鋼筋續接器35與第一梁鋼筋21及連接鋼筋32固接。接著,如圖14所示,移動圍束結構34,使圍束結構34均勻分布於第二預鑄連接結構之17第二者與預鑄梁結構20之間。最後,經由模板環繞場鑄接續結構30並澆置混凝土於其中,以形成混凝土結構覆蓋包覆包含圍束結構34之場鑄接續結構30。混凝土結構可在當層樓之預鑄連接結構皆完成對接後,再包覆場鑄接續結構30。或者,混凝土結構可在移動圍束結構34後即進行施作。關於形成混凝土結構之詳細方法將於後方關於圖19之實施例進一步說明。The method of connecting the precast beam structure 20 with the second precast connection structure 17 (left side of FIG. 10) via the field-cast connection structure 30 is described as follows: First, the movable steel bar connector 35 and the restraining structure 34 of the field-cast connection structure 30 are sleeved on the first beam steel bar 21. As shown in FIG. 10, the movable steel bar connector 35 and the restraining structure 34 of the field-cast connection structure 30 are pre-set on the first beam steel bar 21 of the precast beam structure 20, and are hoisted together with the precast beam structure 20 between two adjacent second precast connection structures 17. Next, as shown in FIG12, after the precast beam structure 20 and the first of the two adjacent second precast connection structures 17 (the right side of FIG10) are connected, the connection steel bar 32 is connected to the fixed steel bar connector 31 of the second of the second precast connection structure 17 (the left side of FIG10). Next, as shown in FIG13, the movable steel bar connector 35 is moved so that the opening at one end is sleeved on the first beam steel bar 21, and the opening at the other end is sleeved on the connection steel bar 32. Next, as shown in FIG13A, mortar material 37 is supplied to the movable steel bar connector 35 so that the movable steel bar connector 35 is fixedly connected to the first beam steel bar 21 and the connection steel bar 32. Next, as shown in FIG14 , the restraining structure 34 is moved so that the restraining structure 34 is evenly distributed between the second precast connection structure 17 and the precast beam structure 20. Finally, the field-cast connection structure 30 is surrounded by a template and concrete is poured therein to form a concrete structure covering the field-cast connection structure 30 including the restraining structure 34. The concrete structure can cover the field-cast connection structure 30 after all the precast connection structures of the current floor are connected. Alternatively, the concrete structure can be constructed immediately after the restraining structure 34 is moved. The detailed method for forming the concrete structure will be further described later with respect to the embodiment of FIG19 .

在上述圖10所示之實施例中,場鑄接續結構30之固定鋼筋續接器31係埋設於圖面顯示之左側第二預鑄連接結構17內,且圖面顯示之右側第二預鑄連接結構17有梁鋼筋173向外突出並與預鑄梁結構20耦接,但本揭露並不僅此為限。在另一實施中,預鑄梁結構20之方向對調,場鑄接續結構30之固定鋼筋續接器31係埋設於圖面顯示之右側第二預鑄連接結構17中,且圖面顯示之左側第二預鑄連接結構17有梁鋼筋173向外突出並與預鑄梁結構20耦接。In the embodiment shown in FIG. 10 above, the fixed steel bar connector 31 of the field-cast connection structure 30 is embedded in the second pre-cast connection structure 17 on the left side shown in the drawing, and the second pre-cast connection structure 17 on the right side shown in the drawing has a beam steel bar 173 protruding outward and coupled with the pre-cast beam structure 20, but the present disclosure is not limited to this. In another embodiment, the direction of the pre-cast beam structure 20 is reversed, and the fixed steel bar connector 31 of the field-cast connection structure 30 is embedded in the second pre-cast connection structure 17 on the right side shown in the drawing, and the second pre-cast connection structure 17 on the left side shown in the drawing has a beam steel bar 173 protruding outward and coupled with the pre-cast beam structure 20.

在建築系統1單邊之預鑄連接結構定位完成且對接後,接著透過類似的施工方式,將該樓層剩餘的預鑄連接結構進行定位並對接。如圖16所示,預鑄梁結構20及場鑄接續結構30形成於建築系統1上相對設置之側邊(下文稱左側邊及右側邊)上。建築系統1上垂直於所述左側邊及右側邊之另外二個側邊(下文稱前側邊與後側邊)並未有預鑄梁結構20及場鑄接續結構30設置。在一實施例中,在建造建築系統1之左側邊及右側邊的過程中,定位於二個預鑄角柱11之上的二個第一預鑄連接結構15係早於定位於二個預鑄邊柱預鑄邊柱13之上的二個第二預鑄連接結構17施工,在二個第二預鑄連接結構17之間施工需要現場施作的工程,例如陽台,之後進而使用預鑄梁結構20及場鑄接續結構30連接二個第二預鑄連接結構17。相對的,在建造建築系統1之前側邊與後側邊的過程中,省略設置預鑄梁結構20及場鑄接續結構30於其中。After the precast connection structure on one side of the building system 1 is positioned and connected, the remaining precast connection structure of the floor is then positioned and connected through a similar construction method. As shown in Figure 16, the precast beam structure 20 and the field-cast connection structure 30 are formed on the opposite sides (hereinafter referred to as the left side and the right side) of the building system 1. The other two sides of the building system 1 that are perpendicular to the left side and the right side (hereinafter referred to as the front side and the rear side) do not have the precast beam structure 20 and the field-cast connection structure 30 set. In one embodiment, during the construction of the left and right sides of the building system 1, the two first precast connection structures 15 located on the two precast corner columns 11 are constructed earlier than the two second precast connection structures 17 located on the two precast side columns 13, and the works that need to be constructed on site, such as a balcony, are constructed between the two second precast connection structures 17, and then the precast beam structure 20 and the on-site cast connecting structure 30 are further used to connect the two second precast connection structures 17. In contrast, during the construction of the front and rear sides of the building system 1, the precast beam structure 20 and the on-site cast connecting structure 30 are omitted.

然而應當理解的是,本揭露並不僅限於上述實施例,外圍建築系統可在單一側邊上設置有預鑄梁結構20及場鑄接續結構30,其餘側邊並未設置預鑄梁結構20及場鑄接續結構30。在其他實施例中,在如圖6所示之左側邊之第一預鑄連接結構15與第二預鑄連接結構17完成對接後,沿一順時針方向依序對接其餘預鑄連接結構,最後才經由如圖10所示之預鑄梁結構20及場鑄接續結構30完成外圍建築系統10。However, it should be understood that the present disclosure is not limited to the above-mentioned embodiments, and the peripheral building system may be provided with a precast beam structure 20 and a field-cast connecting structure 30 on a single side, and the remaining sides are not provided with a precast beam structure 20 and a field-cast connecting structure 30. In other embodiments, after the first precast connecting structure 15 and the second precast connecting structure 17 on the left side as shown in FIG6 are connected, the remaining precast connecting structures are connected in sequence along a clockwise direction, and finally the peripheral building system 10 is completed through the precast beam structure 20 and the field-cast connecting structure 30 as shown in FIG10.

在一實施例中,經由預鑄梁結構20及場鑄接續結構30進行對接之二個相鄰的預鑄連接結構(例如:二個第二預鑄連接結構17),其二個梁結構(例如:第二梁結構171、172)具有不同之長度。舉例而言,如圖11所示,二個第二梁結構中相鄰預鑄梁結構20或場鑄接續結構30之一者(例如:第二梁結構171)的長度,係小於另一者(例如:第二梁結構172)的長度。藉由縮小預鑄連接結構之長度,將有利於預鑄連接結構之運送,並降低預鑄連接結構之重量。In one embodiment, two adjacent precast connection structures (e.g., two second precast connection structures 17) connected via a precast beam structure 20 and a field-cast connection structure 30 have two beam structures (e.g., second beam structures 171, 172) of different lengths. For example, as shown in FIG. 11, the length of one of the adjacent precast beam structures 20 or field-cast connection structures 30 (e.g., second beam structure 171) of the two second beam structures is shorter than the length of the other (e.g., second beam structure 172). By reducing the length of the precast connection structure, it is convenient to transport the precast connection structure and reduce the weight of the precast connection structure.

在完成建築系統1之外圍建築系統10之建造步驟後,建築系統1之施工方法進一步包括施工內部建築系統40之二個場鑄柱結構41。在一實施例中,二個場鑄柱結構41係設置於下一樓層之二個場鑄柱結構(圖未示)之上。在一實施例中,場鑄柱結構41是在預鑄角柱11、預鑄邊柱13及內部預鑄柱結構43之吊放作業之前、之後或期間於工地現場進行場鑄建造。After completing the construction step of the outer building system 10 of the building system 1, the construction method of the building system 1 further includes constructing two field-cast column structures 41 of the inner building system 40. In one embodiment, the two field-cast column structures 41 are arranged on the two field-cast column structures (not shown) of the next floor. In one embodiment, the field-cast column structures 41 are field-cast on site at the construction site before, after or during the hanging operation of the precast corner columns 11, the precast side columns 13 and the inner precast column structures 43.

如圖17所示,建築系統1之施工方法進一步包括定位二個內部預鑄連接結構44、45於二個內部預鑄柱結構43之上,其中內部預鑄連接結構44係早於內部預鑄連接結構45定位於內部預鑄柱結構43之上。如圖16所示,複數個垂直鋼筋9係在內部預鑄連接結構44吊放於內部預鑄柱結構43之上之前即預先固定於內部預鑄柱結構43之上,並在內部預鑄連接結構44經由吊裝的下降過程中,使複數個垂直鋼筋9分別穿過內部預鑄連接結構44內部之複數個穿孔。並且,在內部預鑄連接結構44吊放於內部預鑄柱結構43之上之後,再執行如圖4所展示之橫向移動施工,將內部預鑄連接結構45定位於另一內部預鑄柱結構43並使其與內部預鑄連接結構44對接,如圖17所示。As shown in FIG17 , the construction method of the building system 1 further includes positioning two internal precast connection structures 44 and 45 on two internal precast column structures 43, wherein the internal precast connection structure 44 is positioned on the internal precast column structure 43 before the internal precast connection structure 45. As shown in FIG16 , a plurality of vertical steel bars 9 are pre-fixed on the internal precast column structure 43 before the internal precast connection structure 44 is suspended on the internal precast column structure 43, and during the lowering process of the internal precast connection structure 44 through the lifting, the plurality of vertical steel bars 9 pass through the plurality of through holes inside the internal precast connection structure 44. Furthermore, after the internal precast connection structure 44 is suspended on the internal precast column structure 43, the lateral movement construction as shown in FIG. 4 is performed to position the internal precast connection structure 45 on another internal precast column structure 43 and connect it with the internal precast connection structure 44, as shown in FIG. 17 .

如圖17所示,內部預鑄連接結構44包括一內部預鑄連接頭440及二個內部預鑄梁結構441、442。內部預鑄連接頭440設置於內部預鑄柱結構43之上方。二個內部預鑄梁結構441、442設置於內部預鑄連接頭440之二個垂直之相鄰側表面。複數個梁鋼筋自內部預鑄連接頭440未設置內部預鑄梁結構之側表面向外沿水平方向延伸。內部預鑄連接結構45包括一內部預鑄連接頭450及一內部預鑄梁結構。內部預鑄連接頭450設置於另一預鑄柱結構43之上方。內部預鑄梁結構451設置於內部預鑄連接頭450相鄰梁結構441之側表面。複數個梁鋼筋自內部預鑄連接頭450未設置內部預鑄梁結構之側表面向外沿水平方向延伸。As shown in FIG. 17 , the internal precast connection structure 44 includes an internal precast connection head 440 and two internal precast beam structures 441, 442. The internal precast connection head 440 is disposed above the internal precast column structure 43. The two internal precast beam structures 441, 442 are disposed on two vertical adjacent side surfaces of the internal precast connection head 440. A plurality of beam steel bars extend outward in a horizontal direction from the side surface of the internal precast connection head 440 where the internal precast beam structure is not disposed. The internal precast connection structure 45 includes an internal precast connection head 450 and an internal precast beam structure. The internal precast connection head 450 is disposed above another precast column structure 43. The internal precast beam structure 451 is disposed on the side surface of the internal precast connection head 450 adjacent to the beam structure 441. A plurality of beam steel bars extend outward in a horizontal direction from the side surface of the internal precast connection head 450 where the internal precast beam structure is not disposed.

如圖18所示,在完成建築系統1之內部預鑄連接頭440之定位後,則施工內部建築系統40之內部梁結構42。內部梁結構42係連結於二個相鄰內部柱結構41之二者之間。或者,內部梁結構42係連結於內部柱結構41與預鑄連接頭440、450之間。或者,內部梁結構42係連結於內部預鑄連接結構44、45與外圍建築系統10之第二預鑄連接結構17之間。As shown in FIG. 18 , after the positioning of the internal precast connection head 440 of the building system 1 is completed, the internal beam structure 42 of the internal building system 40 is constructed. The internal beam structure 42 is connected between two adjacent internal column structures 41. Alternatively, the internal beam structure 42 is connected between the internal column structure 41 and the precast connection heads 440, 450. Alternatively, the internal beam structure 42 is connected between the internal precast connection structures 44, 45 and the second precast connection structure 17 of the peripheral building system 10.

建築系統1之外圍建築系統10先完成後才施工內部建築系統40,且內部建築系統40中之內部梁結構42係以場鑄方式施工,這樣的施工方式無須在建築系統1之外圍搭設施工架且可降低建築系統之建造成本,並增加建造程序上的靈活性。The outer building system 10 of the building system 1 is completed first before the inner building system 40 is constructed, and the inner beam structure 42 in the inner building system 40 is constructed by on-site casting. This construction method does not require the construction scaffolding to be set up outside the building system 1 and can reduce the construction cost of the building system and increase the flexibility of the construction process.

參照圖19,其展示建築系統1之一樓層之平面圖。在一實施例中,場鑄接續結構30係相鄰建築系統1之一對外敞開並向外延伸之平台46設置。在施工場鑄接續結構30時,施工人員可站立於平台46移動並定位可移動鋼筋續接器35(圖14)及透過模板的設置以及澆置混凝土於其中以形成混凝土結構36,使其包覆場鑄接續結構30。由於施工人員沒有暴露於建築系統1外部之風險,故無須額外搭設施工架。又,如圖19所示,建築系統1包括二個天井48、49,其中天井48之面積較天井49之面積大。由於相鄰天井48之內部建築系統40包括部分預鑄梁結構(例如:如圖17所示之內部預鑄梁結構441、442、451),且位於天井48兩側需以場鑄方式施工之內部梁結構42係相鄰建築系統1之一對外敞開並向外延伸之平台47設置,故天井48內也可不必搭設施工架。另一方面,由於位於天井49兩側需以場鑄方式施工之內部梁結構42係相鄰建築系統1之一對外敞開之平台47設置,故天井49內也可不必搭設施工架。Referring to FIG. 19 , a plan view of a floor of the building system 1 is shown. In one embodiment, the site-cast joint structure 30 is provided on a platform 46 adjacent to the building system 1 that is open to the outside and extends outward. When the site-cast joint structure 30 is constructed, the construction personnel can stand on the platform 46 to move and position the movable steel bar connector 35 ( FIG. 14 ) and form a concrete structure 36 by setting a template and pouring concrete therein so as to cover the site-cast joint structure 30. Since the construction personnel are not exposed to the risk of the outside of the building system 1, there is no need to set up an additional construction frame. In addition, as shown in FIG. 19 , the building system 1 includes two patios 48 and 49, wherein the area of the patio 48 is larger than the area of the patio 49. Since the internal building system 40 of the adjacent patio 48 includes a part of the precast beam structure (e.g., the internal precast beam structures 441, 442, and 451 shown in FIG. 17), and the internal beam structures 42 located on both sides of the patio 48 that need to be constructed by on-site casting are provided on a platform 47 of the adjacent building system 1 that is open to the outside and extends outward, it is not necessary to set up a construction frame in the patio 48. On the other hand, since the internal beam structures 42 located on both sides of the patio 49 that need to be constructed by on-site casting are provided on a platform 47 of the adjacent building system 1 that is open to the outside, it is not necessary to set up a construction frame in the patio 49.

藉由上述配置,建築系統1在施工過程中可將施工架之使用量降至最低,進而減少建築系統1之建造成本並避免產生不必要之建築廢棄物。By means of the above configuration, the building system 1 can reduce the usage of the construction scaffolding to a minimum during the construction process, thereby reducing the construction cost of the building system 1 and avoiding the generation of unnecessary construction waste.

參照圖20,其展示建築系統1’之一樓層之平面圖。建築系統1與建築系統1’相同或相似之元件以相同符號表示,且其結構特徵將不再描述。建築系統1與建築系統1’之差異在於兩者的外圍建築系統的結構略有不同,其中如圖19及圖20所示,建築系統1’以預鑄連接結構15’、17’、19取代結構不同之建築系統1之預鑄連接結構15、17,且建築系統1’進一步包括多個預鑄梁結構25。預鑄連接結構15’係透過預鑄梁結構25與預鑄連接結構17’或預鑄連接結構19而連接。二個預鑄連接結構17’係經由預鑄梁結構20及場鑄接續結構30而連接。二個預鑄連接結構19係彼此直接耦接。在一實施例中,預鑄連接結構15’、17’、19及預鑄梁結構25係以相似於圖2-6及圖7A-7I所揭露之方式彼此進行連接,預鑄連接結構17’係以相似於圖10-14所揭露之方式進行連接,為簡化說明在此即不再重複。Referring to FIG. 20 , a plan view of one floor of the building system 1′ is shown. The same or similar elements of the building system 1 and the building system 1′ are indicated by the same symbols, and their structural features will not be described again. The difference between the building system 1 and the building system 1′ is that the structures of the peripheral building systems of the two are slightly different. As shown in FIG. 19 and FIG. 20 , the building system 1′ replaces the precast connection structures 15 and 17 of the building system 1 with different structures with precast connection structures 15′, 17′, and 19, and the building system 1′ further includes a plurality of precast beam structures 25. The precast connection structure 15′ is connected to the precast connection structure 17′ or the precast connection structure 19 through the precast beam structure 25. The two precast connection structures 17' are connected via the precast beam structure 20 and the field cast connection structure 30. The two precast connection structures 19 are directly coupled to each other. In one embodiment, the precast connection structures 15', 17', 19 and the precast beam structure 25 are connected to each other in a manner similar to that disclosed in Figures 2-6 and 7A-7I, and the precast connection structure 17' is connected in a manner similar to that disclosed in Figures 10-14, which will not be repeated here for simplicity of description.

在一實施例中,建築系統1’之預鑄連接結構15’、17’、19上水平延伸之梁結構的長度係較建築系統1之預鑄連接結構15、17上水平延伸之梁結構的長度短,藉此增加預鑄連接結構15’、17’、19運送之便利性。在一實施例中,建築系統1’之預鑄連接結構15’之梁結構151’、152’分別具有長度L3、L4。長度L3、L4係至少大於1公尺,以使梁結構151’、152’與相鄰結構之對接位置係位於預鑄連接結構15’之塑鉸(plastic hinge)區之外,以強化預鑄連接結構15’之結構強度。In one embodiment, the length of the horizontally extending beam structure on the precast connection structure 15', 17', 19 of the building system 1' is shorter than the length of the horizontally extending beam structure on the precast connection structure 15, 17 of the building system 1, thereby increasing the convenience of transportation of the precast connection structure 15', 17', 19. In one embodiment, the beam structures 151', 152' of the precast connection structure 15' of the building system 1' have lengths L3 and L4, respectively. The lengths L3 and L4 are at least greater than 1 meter, so that the connection position of the beam structures 151', 152' and the adjacent structure is located outside the plastic hinge area of the precast connection structure 15', so as to enhance the structural strength of the precast connection structure 15'.

本揭露實施例提供一種建築系統其施工方法,其至少包括以下技術優點:(1)藉由預鑄工法施工外圍建築系統的大部分結構,僅在部分區塊使用場鑄接續結構,有助於建築系統之製造流程標準化,減少施工程序上可變因數,進而提升建築品質;(2)藉由預鑄結構的使用,增加建造速度並提升工地環境整潔;及(3)藉由將場鑄之施作地點設置於陽台等場域,避免施工架之使用,有助減少生產成本並降低環境衝擊。The disclosed embodiments provide a construction method for a building system, which has at least the following technical advantages: (1) by using a precast method to construct most of the structure of the peripheral building system, only using a site-cast connecting structure in some areas, it is helpful to standardize the manufacturing process of the building system, reduce variable factors in the construction process, and thus improve the quality of the building; (2) by using precast structures, the construction speed is increased and the site environment is improved; and (3) by setting the site casting construction site in a balcony or other place, the use of a construction scaffold is avoided, which helps to reduce production costs and reduce environmental impact.

以上所述之實施例僅係為說明本創作之技術思想及特點,其目的在使熟習此項技藝之人士能夠瞭解本創作之內容並據以實施,當不能以之限定本創作之專利範圍,依本創作所揭示之精神所作之均等變化或修飾,仍應涵蓋在本創作之專利範圍內。The embodiments described above are only for illustrating the technical ideas and features of the present invention, and their purpose is to enable people familiar with this art to understand the content of the present invention and implement it accordingly. They cannot be used to limit the patent scope of the present invention. Equivalent changes or modifications made according to the spirit revealed by the present invention should still be covered by the patent scope of the present invention.

1:建築系統 9:垂直鋼筋 10:外圍建築系統 11:預鑄角柱 13:預鑄邊柱 15:預鑄連接結構/第一預鑄連接結構 15’:預鑄連接結構 17:預鑄連接結構/第二預鑄連接結構 17’:預鑄連接結構 19:預鑄連接結構 20:預鑄梁結構 21:梁鋼筋/第一梁鋼筋 25:預鑄梁結構 30:場鑄接續結構 31:固定鋼筋續接器 32:連接鋼筋 34:圍束結構 35:可移動鋼筋續接器 36:混凝土結構 37:砂漿材料 40:內部建築系統 41:內部柱結構 42:內部梁結構 43:內部預鑄柱結構 44:內部預鑄連接結構 45:內部預鑄連接結構 46:平台 47:平台 48:天井 49:天井 60:鋼筋續接器 61:第一開口 62:第二開口 63:第一貫穿孔 64:第二貫穿孔 70:漿料管道 71:第一端 72:第二端 91:裝飾面板 92:密封元件 93:砂漿材料 94:塞子 111:頂表面 112:續接結構 131:頂表面 132:續接結構 150:第一預鑄連接頭 151:第一梁結構 152:第一梁結構 153:梁鋼筋 154:梁鋼筋 155:穿孔 157:溝槽 170:第二預鑄連接頭 171:第二梁結構 172:第二梁結構 173:梁鋼筋/第二梁鋼筋 174:梁鋼筋 175:穿孔 179:梁鋼筋 201:端面 202:端面 311:端部 312:內螺紋結構 321:端部 322:外螺紋結構 440:內部預鑄連接頭 441:內部預鑄梁結構 442:內部預鑄梁結構 450:內部預鑄連接頭 451:內部預鑄梁結構 1501:側表面 1502:側表面 1503:頂表面 1511:端面 1512:側表面 1513:上表面 1532:錨定頭 1542:錨定頭 1701:側表面 1702:側表面 1703:側表面 1711:端面 1721:端面 1721:端面 1722:側表面 1723:上表面 G:間隙 L1:距離 L2:長度 L3:長度 L4:長度 L5:長度 L6:間隔距離 1: Building system 9: Vertical steel bars 10: Peripheral building system 11: Precast corner columns 13: Precast side columns 15: Precast connection structure/first precast connection structure 15’: Precast connection structure 17: Precast connection structure/second precast connection structure 17’: Precast connection structure 19: Precast connection structure 20: Precast beam structure 21: Beam steel bars/first beam steel bars 25: Precast beam structure 30: Field cast connection structure 31: Fixed steel bar connector 32: Connecting steel bars 34: Enclosure structure 35: Movable steel bar connector 36: Concrete structure 37: Mortar material 40: Internal building system 41: Internal column structure 42: Internal beam structure 43: Internal precast column structure 44: Internal precast connection structure 45: Internal precast connection structure 46: Platform 47: Platform 48: Patio 49: Patio 60: Rebar connector 61: First opening 62: Second opening 63: First through-hole 64: Second through-hole 70: Mortar pipe 71: First end 72: Second end 91: Decorative panel 92: Sealing element 93: Mortar material 94: Plug 111: Top surface 112: Connection structure 131: Top surface 132: Continuation structure 150: First precast joint 151: First beam structure 152: First beam structure 153: Beam reinforcement 154: Beam reinforcement 155: Perforation 157: Groove 170: Second precast joint 171: Second beam structure 172: Second beam structure 173: Beam reinforcement/Second beam reinforcement 174: Beam reinforcement 175: Perforation 179: Beam reinforcement 201: End face 202: End face 311: End face 312: Internal thread structure 321: End face 322: External thread structure 440: Internal precast joint 441: Internal precast beam structure 442: Internal precast beam structure 450: Internal precast connector 451: Internal precast beam structure 1501: Side surface 1502: Side surface 1503: Top surface 1511: End surface 1512: Side surface 1513: Top surface 1532: Anchor head 1542: Anchor head 1701: Side surface 1702: Side surface 1703: Side surface 1711: End surface 1721: End surface 1721: End surface 1722: Side surface 1723: Top surface G: Gap L1: Distance L2: Length L3: Length L4: Length L5: Length L6: Spacing distance

圖1展示本發明之一實施例中的建築系統之示意圖。FIG. 1 shows a schematic diagram of a building system in one embodiment of the present invention.

圖2展示本發明上述實施例中的建築系統之製造方法之示意圖一。FIG. 2 shows a schematic diagram of the manufacturing method of the building system in the above embodiment of the present invention.

圖3展示本發明上述實施例中的建築系統之製造方法之示意圖二。FIG. 3 shows a second schematic diagram of the manufacturing method of the building system in the above embodiment of the present invention.

圖3A展示本發明上述實施例中的第一預鑄連接結構之部分結構之俯視圖。FIG. 3A is a top view showing a partial structure of the first pre-cast connection structure in the above embodiment of the present invention.

圖4展示本發明上述實施例中的建築系統之製造方法之示意圖三。FIG. 4 shows a third schematic diagram of the manufacturing method of the building system in the above embodiment of the present invention.

圖5展示本發明上述實施例中的建築系統之製造方法之示意圖四。FIG. 5 shows a fourth schematic diagram of the manufacturing method of the building system in the above-mentioned embodiment of the present invention.

圖6展示本發明上述實施例中的建築系統之製造方法之示意圖五。FIG. 6 shows a fifth schematic diagram of the manufacturing method of the building system in the above-mentioned embodiment of the present invention.

圖7A展示本發明上述實施例中的建築系統之二個對接之預鑄梁結構之示意圖。FIG. 7A is a schematic diagram showing two butted precast beam structures of the building system in the above-mentioned embodiment of the present invention.

圖7B展示本發明上述實施例中的建築系統之一預鑄梁結構在垂直預鑄梁結構之延伸方向上之斷面圖。FIG7B shows a cross-sectional view of a precast beam structure of the building system in the above-mentioned embodiment of the present invention in the extension direction perpendicular to the precast beam structure.

圖7C展示本發明上述實施例中的建築系統之二個對接之預鑄梁結構在平行預鑄梁結構之延伸方向上之斷面圖。FIG. 7C shows a cross-sectional view of two butted precast beam structures of the building system in the above-mentioned embodiment of the present invention in the extension direction parallel to the precast beam structures.

圖7D-7I展示本發明上述實施例中的建築系統之二個預鑄梁結構之對接方法之示意圖。7D-7I are schematic diagrams showing a method for docking two precast beam structures of the building system in the above-mentioned embodiment of the present invention.

圖8展示本發明上述實施例中的建築系統之製造方法之示意圖六。FIG8 shows a sixth schematic diagram of the manufacturing method of the building system in the above-mentioned embodiment of the present invention.

圖9展示本發明上述實施例中的建築系統之製造方法之示意圖七。FIG. 9 shows a seventh schematic diagram of the manufacturing method of the building system in the above-mentioned embodiment of the present invention.

圖10展示本發明上述實施例中的建築系統之製造方法之示意圖八。FIG. 10 is a schematic diagram showing an eighth method for manufacturing the building system in the above-mentioned embodiment of the present invention.

圖11展示本發明上述實施例中的建築系統之製造方法之示意圖九。FIG. 11 is a ninth schematic diagram showing a method for manufacturing a building system according to the above-mentioned embodiment of the present invention.

圖12展示本發明上述實施例中的建築系統之製造方法之示意圖十。FIG. 12 is a schematic diagram showing a tenth method for manufacturing the building system in the above-mentioned embodiment of the present invention.

圖12A顯示本發明上述實施例中之場鑄接續結構、預鑄梁結構、預鑄連接結構三者結合之***圖。FIG. 12A shows an exploded view of the field-cast connection structure, the pre-cast beam structure, and the pre-cast connection structure in the above-mentioned embodiment of the present invention.

圖13展示本發明上述實施例中的建築系統之製造方法之示意圖十一。FIG. 13 is a schematic diagram showing the eleventh method for manufacturing the building system in the above-mentioned embodiment of the present invention.

圖13A展示本發明上述實施例中的建築系統之製造方法之示意圖十二。FIG. 13A is a twelfth schematic diagram showing a method for manufacturing a building system in the above-mentioned embodiment of the present invention.

圖14展示本發明上述實施例中的建築系統之製造方法之示意圖十三。FIG. 14 is a thirteenth schematic diagram showing a method for manufacturing a building system in the above-mentioned embodiment of the present invention.

圖15展示本發明上述實施例中的建築系統之製造方法之示意圖十四。FIG. 15 is a schematic diagram showing a fourteenth method for manufacturing the building system in the above-mentioned embodiment of the present invention.

圖16展示本發明上述實施例中的建築系統之製造方法之示意圖十五。FIG. 16 is a schematic diagram showing the fifteenth method for manufacturing the building system in the above-mentioned embodiment of the present invention.

圖17展示本發明上述實施例中的建築系統之製造方法之示意圖十六。FIG. 17 is a schematic diagram showing a sixteenth method for manufacturing the building system in the above-mentioned embodiment of the present invention.

圖18展示本發明上述實施例中的建築系統之製造方法之示意圖十七。FIG. 18 is a seventeenth schematic diagram showing a method for manufacturing a building system in the above-mentioned embodiment of the present invention.

圖19展示本發明另一實施例中的建築系統之一平面示意圖。FIG. 19 is a schematic plan view showing a building system in another embodiment of the present invention.

圖20展示本發明之又一實施例中的建築系統之一平面示意圖。FIG. 20 shows a schematic plan view of a building system in another embodiment of the present invention.

11:預鑄角柱 11: Pre-cast corner columns

13:預鑄邊柱 13: Pre-cast side columns

15:預鑄連接結構/第一預鑄連接結構 15: Pre-cast connection structure/first pre-cast connection structure

17:預鑄連接結構/第二預鑄連接結構 17: Pre-cast connection structure/second pre-cast connection structure

20:預鑄梁結構 20: Precast beam structure

21:梁鋼筋/第一梁鋼筋 21: Beam reinforcement/first beam reinforcement

30:場鑄接續結構 30: Field cast connection structure

31:固定鋼筋續接器 31:Fixed steel bar connector

34:圍束結構 34: Enclosure structure

35:可移動鋼筋續接器 35: Movable steel bar connector

60:鋼筋續接器 60: Steel bar connector

150:第一預鑄連接頭 150: First pre-cast connector

151:第一梁結構 151: First beam structure

152:第一梁結構 152: First beam structure

170:第二預鑄連接頭 170: Second pre-cast connector

171:第二梁結構 171: Second beam structure

172:第二梁結構 172: Second beam structure

173:梁鋼筋/第二梁鋼筋 173: Beam reinforcement/Second beam reinforcement

201:端面 201: End face

202:端面 202: End face

1711:端面 1711: End face

L1:距離 L1: Distance

L2:長度 L2: Length

Claims (10)

一種建築系統,包括: 二個預鑄柱; 一右側第二預鑄連接結構及一左側第二預鑄連接結構,各自包括固定於該二個預鑄柱之一者之一預鑄連接頭、及自該預鑄連接頭之側邊水平延伸之一梁結構,其中該右側第二預鑄連接結構之該梁結構與該左側第二預鑄連接結構之該梁結構相鄰設置,且該右側第二預鑄連接結構包括複數個第一梁鋼筋埋設於其中; 一預鑄梁結構,具有相對設置且分別面對該右側第二預鑄連接結構及該左側第二預鑄連接結構之一第一端及一第二端,且包括: 複數個第二梁鋼筋埋設於該預鑄梁結構當中並自該預鑄梁結構之該第二端延伸而出;以及 複數個鋼筋續接器,設置於該預鑄梁結構之該第一端並經構形以將該右側第二預鑄連接結構之該複數個第一梁鋼筋連結至該預鑄梁結構之該複數個第二梁鋼筋;以及 一場鑄接續結構,包括: 複數個固定鋼筋續接器,埋設於該左側第二預鑄連接結構之該梁結構之一端面中; 複數個連接鋼筋,連接至該複數個固定鋼筋續接器; 一圍束結構,套設於該預鑄梁結構之該複數個第二梁鋼筋;以及 複數個可移動鋼筋續接器,其每一者之一端連接該複數個連接鋼筋之相應的一者,其每一者之另一端連接該預鑄梁結構之該複數個第二梁鋼筋之相應的一者。 A building system, comprising: Two precast columns; A right-side second precast connection structure and a left-side second precast connection structure, each comprising a precast connection head fixed to one of the two precast columns, and a beam structure extending horizontally from the side of the precast connection head, wherein the beam structure of the right-side second precast connection structure and the beam structure of the left-side second precast connection structure are arranged adjacent to each other, and the right-side second precast connection structure comprises a plurality of first beam steel bars embedded therein; A precast beam structure, having a first end and a second end arranged opposite to each other and facing the right-side second precast connection structure and the left-side second precast connection structure, respectively, and comprising: A plurality of second beam steel bars are embedded in the precast beam structure and extend from the second end of the precast beam structure; and A plurality of steel bar connectors are disposed at the first end of the precast beam structure and are configured to connect the plurality of first beam steel bars of the right second precast connection structure to the plurality of second beam steel bars of the precast beam structure; and A field-cast connection structure, comprising: A plurality of fixed steel bar connectors, embedded in an end face of the beam structure of the left second precast connection structure; A plurality of connecting steel bars, connected to the plurality of fixed steel bar connectors; A binding structure, sleeved on the plurality of second beam steel bars of the precast beam structure; and A plurality of movable steel bar connectors, each of which has one end connected to a corresponding one of the plurality of connecting steel bars, and each of which has the other end connected to a corresponding one of the plurality of second beam steel bars of the precast beam structure. 如請求項1所述之建築系統,其中該圍束結構包括複數個彼此以一預定距離間隔之封閉式箍筋。A building system as described in claim 1, wherein the confining structure includes a plurality of closed stirrups spaced a predetermined distance from each other. 如請求項1至3任一項所述之建築系統,其中該複數個固定鋼筋續接器每一者之一端部係暴露於該左側第二預鑄連接結構之梁結構之該端面且包括一內螺紋結構;並且 該複數個連接鋼筋每一者之一端部包括一外螺紋結構,經由該內螺紋結構與該外螺紋結構之嚙合,該複數個連接鋼筋螺紋連接至該複數個固定鋼筋續接器。 A construction system as described in any one of claims 1 to 3, wherein one end of each of the plurality of fixed steel bar connectors is exposed to the end surface of the beam structure of the left second precast connection structure and includes an internal thread structure; and one end of each of the plurality of connecting steel bars includes an external thread structure, and the plurality of connecting steel bars are threadedly connected to the plurality of fixed steel bar connectors through the engagement of the internal thread structure with the external thread structure. 如請求項1至3任一項所述之建築系統,其中該場鑄接續結構之該複數個可移動鋼筋續接器中填充有砂漿材料,以固接該複數個連接鋼筋與該複數個第二梁鋼筋。A construction system as described in any one of claims 1 to 3, wherein the plurality of movable steel bar connectors of the cast-in-place joint structure are filled with mortar material to fix the plurality of connecting steel bars and the plurality of second beam steel bars. 如請求項1至3任一項所述之建築系統,其中該複數個連接鋼筋之長度係小於或等於該複數個第二梁鋼筋之自由端與該左側第二預鑄連接結構之梁結構之端面之間隔距離。A building system as described in any one of claims 1 to 3, wherein the length of the plurality of connecting steel bars is less than or equal to the spacing distance between the free ends of the plurality of second beam steel bars and the end surface of the beam structure of the left second precast connecting structure. 一種建築系統之建造方法,包括: 提供二個預鑄柱; 吊設一右側第二預鑄連接結構及一左側第二預鑄連接結構於該二個預鑄柱之上,其各自包括固定於該二個預鑄柱之一者之一預鑄連接頭、及自該預鑄連接頭之側邊水平延伸之一梁結構; 將該右側第二預鑄連接結構之該預鑄連接頭及該左側第二預鑄連接結構之該預鑄連接頭別固定於該二個預鑄柱之頂端,使該右側第二預鑄連接結構之該梁結構與該左側第二預鑄連接結構之該梁結構相鄰設置;以及 提供一預鑄梁結構,並將該預鑄梁結構吊設以及定位於該右側第二預鑄連接結構之該梁結構及該左側第二預鑄連接結構之該梁結構之間; 將該右側第二預鑄連接結構之該梁結構之複數個第一梁鋼筋連結至該預鑄梁結構之複數個第二梁鋼筋;以及 施作一場鑄接續結構於該預鑄梁結構與該左側第二預鑄連接結構之梁結構之間。 A construction method of a building system, comprising: providing two precast columns; hanging a right second precast connection structure and a left second precast connection structure on the two precast columns, each of which includes a precast connection head fixed to one of the two precast columns, and a beam structure extending horizontally from the side of the precast connection head; fixing the precast connection head of the right second precast connection structure and the precast connection head of the left second precast connection structure to the top ends of the two precast columns, respectively, so that the beam structure of the right second precast connection structure and the beam structure of the left second precast connection structure are arranged adjacent to each other; and A precast beam structure is provided, and the precast beam structure is suspended and positioned between the beam structure of the second precast connection structure on the right side and the beam structure of the second precast connection structure on the left side; A plurality of first beam steel bars of the beam structure of the second precast connection structure on the right side are connected to a plurality of second beam steel bars of the precast beam structure; and A field casting connection structure is constructed between the precast beam structure and the beam structure of the second precast connection structure on the left side. 如請求項6所述之方法,其中施作該場鑄接續結構之步驟包括: (A) 埋設複數個固定鋼筋續接器於該左側第二預鑄連接結構之該梁結構之一端面中; (B) 提供並將複數個連接鋼筋連接至該左側第二預鑄連接結構中之該複數個固定鋼筋續接器; (C) 套設一圍束結構於該預鑄梁結構之該複數個第二梁鋼筋上;以及 (D) 將複數個可移動鋼筋續接器每一者之一端連接該複數個連接鋼筋之相應的一者,並將該複數個可移動鋼筋續接器每一者之另一端連接該預鑄梁結構之該複數個第二梁鋼筋之相應的一者。 The method as described in claim 6, wherein the steps of constructing the field-cast connection structure include: (A) embedding a plurality of fixed steel bar connectors in one end face of the beam structure of the left second precast connection structure; (B) providing and connecting a plurality of connecting steel bars to the plurality of fixed steel bar connectors in the left second precast connection structure; (C) sleeve a restraining structure on the plurality of second beam steel bars of the precast beam structure; and (D) One end of each of the plurality of movable steel bar connectors is connected to a corresponding one of the plurality of connecting steel bars, and the other end of each of the plurality of movable steel bar connectors is connected to a corresponding one of the plurality of second beam steel bars of the precast beam structure. 如請求項7所述之方法,其中步驟(D)包括: 將該複數個可移動鋼筋續接器預先分別套設於該預鑄梁結構之該複數個第二梁鋼筋,此時可移動鋼筋續接器之兩端均位於該該複數個第二梁鋼筋上;以及 待該預鑄梁結構定位完成使得該複數個第二梁鋼筋對齊該複數個連接鋼筋後,將該複數個可移動鋼筋續接器朝向該複數個連接鋼筋移動。 The method as described in claim 7, wherein step (D) comprises: Preliminarily sleeve the plurality of movable steel bar connectors on the plurality of second beam steel bars of the precast beam structure, wherein both ends of the movable steel bar connectors are located on the plurality of second beam steel bars; and After the precast beam structure is positioned so that the plurality of second beam steel bars are aligned with the plurality of connecting steel bars, the plurality of movable steel bar connectors are moved toward the plurality of connecting steel bars. 如請求項8所述之方法,進一步包括將該圍束結構由一未展開狀態轉換成一展開狀態,其中在該未展開狀態下該複數個連接鋼筋未被該圍束結構所圍繞,且在該展開狀態下該複數個連接鋼筋以及該複數個可移動鋼筋續接器被該圍束結構所圍繞。The method as described in claim 8 further includes converting the restraining structure from an undeployed state to a deployed state, wherein in the undeployed state the plurality of connecting steel bars are not surrounded by the restraining structure, and in the deployed state the plurality of connecting steel bars and the plurality of movable steel bar connectors are surrounded by the restraining structure. 如請求項9所述之方法,更包括將一砂漿材料注入至該複數個可移動鋼筋續接器中,以使該複數個可移動鋼筋續接器與該複數個第二梁鋼筋及該複數個連接鋼筋固接,並形成混凝土結構使其包覆該場鑄接續結構。The method as described in claim 9 further includes injecting a mortar material into the plurality of movable steel bar connectors to fix the plurality of movable steel bar connectors to the plurality of second beam steel bars and the plurality of connecting steel bars, and forming a concrete structure to cover the field-cast connection structure.
TW111139483A 2022-10-18 2022-10-18 Architecture system and method for constructing the same TWI808911B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
TW111139483A TWI808911B (en) 2022-10-18 2022-10-18 Architecture system and method for constructing the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
TW111139483A TWI808911B (en) 2022-10-18 2022-10-18 Architecture system and method for constructing the same

Publications (2)

Publication Number Publication Date
TWI808911B TWI808911B (en) 2023-07-11
TW202417718A true TW202417718A (en) 2024-05-01

Family

ID=88149530

Family Applications (1)

Application Number Title Priority Date Filing Date
TW111139483A TWI808911B (en) 2022-10-18 2022-10-18 Architecture system and method for constructing the same

Country Status (1)

Country Link
TW (1) TWI808911B (en)

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWM248822U (en) * 2004-01-14 2004-11-01 Runhorn Pretech Eng Co Ltd Semi-precast beam-column joint
TWI736482B (en) * 2020-12-03 2021-08-11 潤弘精密工程事業股份有限公司 Construction method of architectural structure

Also Published As

Publication number Publication date
TWI808911B (en) 2023-07-11

Similar Documents

Publication Publication Date Title
WO2019206193A1 (en) Prefabricated wall panel, connection structure thereof and construction method therefor
CN1821501B (en) Column-beam attaching tectosome of architecture and method of attaching the same
KR101903628B1 (en) Precast Double Wall Structure with Enhanced Seismic Performance and Construction method thereof
KR20140110490A (en) Half precast concrete column manufacturing method using prefabricated PC panels and constructing method using the same
JPH08302892A (en) Precast structural member comprising reinforced concrete column and steel beam, and method for constructing structure using the same
CN211143393U (en) Frame for preparing assembly type concrete core-filled wall and assembly type concrete core-filled wall
KR102621195B1 (en) The Integrated PC double wall structure with improved productivit
JP7411749B2 (en) How to construct a concrete building
TWI808911B (en) Architecture system and method for constructing the same
CN106639146A (en) Autoclaved aerated block lintel and construction method thereof
TW202417712A (en) Architecture system and method for constructing the same
TW202419719A (en) Architecture structure and method for constructing the same
CN110593437B (en) Construction method of assembled shear wall
JP2004082571A (en) Method for manufacturing precast concrete structural component
KR20010090294A (en) Precast concrete structure for variable plan of apartment house
TWI848871B (en) Column structure and architecture system having the same
TWI818874B (en) Beam-column structure and method for assembling the same
CN218405908U (en) Invisible stand column structure
TWI816580B (en) Beam-column structure and method for fabricating the same and architecture system having the same
JPH08144425A (en) Prefabricated member of mixed structure and construction method of mixed structure
TWI844505B (en) Architecture system
TWI798122B (en) Beam-column structure and method for assembling the same
CN109680811B (en) Prefabricated steel column node connection structure for assembled building and construction method thereof
CN209958816U (en) Parcel formula reinforcing apparatus
CN117702946B (en) Assembled wall and construction method thereof