SU730941A1 - Method of erecting the framework of building - Google Patents
Method of erecting the framework of building Download PDFInfo
- Publication number
- SU730941A1 SU730941A1 SU772526301A SU2526301A SU730941A1 SU 730941 A1 SU730941 A1 SU 730941A1 SU 772526301 A SU772526301 A SU 772526301A SU 2526301 A SU2526301 A SU 2526301A SU 730941 A1 SU730941 A1 SU 730941A1
- Authority
- SU
- USSR - Soviet Union
- Prior art keywords
- floor
- slab
- floors
- slabs
- lifting
- Prior art date
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
(54) СПОСОБ МОНТАЖА КАРКАСА ЗДАНИЯ(54) METHOD OF INSTALLATION OF FRAME BUILDING
1one
Изобретение относитс к строительству, в частности к способам монтажа каркаса зданий, возводимых методом подъема этажей и перекрытий.The invention relates to the construction, in particular to methods for mounting a frame of buildings erected by the method of lifting floors and ceilings.
Известен способ монтажа каркаса зданий возводимых методом подъема, предусматриваюш .ий следующую последовательность операций: изготовление и подъем кровельной плиты посредством гибких т г с захватами на уровень, необходимый дл изготовлени следующих плит пакета, с подвеской по периметру кровельной плиты защитного экрана 1.The known method of mounting the frame of buildings erected by the method of lifting involves the following sequence of operations: manufacturing and raising the roofing plate by means of flexible grids with grips to the level required to manufacture the following plates of the package, with suspension around the perimeter of the roofing plate of the protective screen 1.
Наиболее близким техническим решением вл етс способ монтажа каркаса здани , имеющего пакет междуэтажных плит перекрытий из бетонной и тому подобной смеси дл зданий, возводимых методом подъема этажей и перекрытий, включающий установку колонн нескольких этажей, изготовление плит перекрытий этажей и кровельной плиты на заданной отметке и последующий подъем кровельной плиты и плит перекрытий этажей на заданные отметки посредством гибких т г с захватами и подвеска по периметру кровельной плиты защитного экрана 2.The closest technical solution is the method of mounting a building frame that has a package of interfloor floor slabs of concrete and the like for buildings erected by the method of lifting floors and ceilings, including installing columns of several floors, manufacturing floor slabs and a roofing slab at a given point and then the rise of the roofing slab and floor slabs to predetermined elevations by means of flexible joints with grippers and a suspension around the perimeter of the roofing slab of the protective screen 2.
Недостатками этого способа вл ютс значительные сроки возведени здани , особенно при строительстве в первом и втором климатических районах, поскольку не совмещены процессы изготовлени пакета плит перекрытий и их подъема, а также сложность бетонировани плит перекрытий, требующа изготовлени специальной металлической опалубки по всей площади плиты и специальной установки дл нагнетани бетонной смеси, а также значительного расхода энергии дл обеспечени твердени бетона. Кроме того, при такой последовательности возведени создаютс технологические простои подъемного оборудовани .The disadvantages of this method are the considerable time needed to build a building, especially during construction in the first and second climatic regions, since the manufacturing processes for the production of a package of floor plates and their lifting are not combined, as well as the complexity of concreting floor slabs, requiring the manufacture of special metal formwork installations for injecting concrete as well as significant energy consumption to ensure concrete hardening. In addition, with such a sequence of construction, technological downtime of the lifting equipment is created.
Цель изобретени - уменьщение срока возведени каркаса при строительстве зданий методом подъема этажей и перекрытий в первом и втором климатических районах за счет совмещени процессов изготовлени плит, их подъема и обустройства возвденных этажей при упрощении процесса бетонировани .The purpose of the invention is to reduce the period of construction of the frame during the construction of buildings by lifting floors and ceilings in the first and second climatic regions by combining the processes of slab production, lifting them and arranging the raised floors while simplifying the process of concreting.
Указанна цель достигаетс тем, что в способе монтажа каркаса здани , имеющего пакет междуэтажных плит перекрытий из бетонной и тому подобной смеси дл здаНИИ , возводимых методом подъема этажей и перекрытий, включающем установку колонн нескольких этажей, изготовление плит перекрытий этажей и кровельной илиты на заданной отметке и последующий подъем кровельной плиты и плит перекрытий этажей на заданные отметки посредством гибких т г с захватами, и подвеску по периметру кровельной плиты защитного экрана, на заданной отметке изготавливают плиты перекрытий первого, второй этажей и кровельную плиту, после чего последнюю поднимают ка высоту этажа и на верхней поверхности плиты второго эатажа бетонируют плиту перекрыти третьего этажа, после чего поднимают пакет плит на отметку второго этажа затем на верхней поверхности пакета бетонируют плиту четвертого этажа, поднимают плиты второго, третьего и четвертого этажей на отметку второго этажа, бетонируют на верхней поверхности плиту следующего этажа , поднимают пакет плит этажей и кровельную плиту на отметку следующего этажа, после чего процесс повтор ют.This goal is achieved by the fact that in the method of mounting a building frame that has a package of interfloor floor slabs of concrete and the like mixture for a building constructed by the method of lifting floors and ceilings, including the installation of columns of several floors, the manufacture of floor slabs and roofing at a given elevation and the subsequent lifting of the roofing slab and floor slabs to the specified elevations by means of flexible tg with grippers, and a suspension around the perimeter of the roofing slab of the protective screen was made at the predetermined elevation floor slabs of the first, second floors and roofing slab are worn, after which the last one is raised to the height of the floor and the third floor slab is concreted on the upper surface of the second floor slab, then the plate stack is raised to the second floor then the fourth floor slab is concrete, the slabs of the second, third and fourth floors are raised to the mark of the second floor, concreted on the upper surface of the slab of the next floor, the package of the slabs of floors and the roofing slab is raised to the mark of the next floor and then the process is repeated.
На фиг. 1 показано изготовление пакета плит перекрытий первого, второго этажей и кровельной плиты; на фиг. 2 - установка кровельной плиты на отметку второго этажа и подвеска к ней по периметру защитного экрана с бортовой опалубкой, а на верхней -поверхности плиты второго этажа бетонирование плиты перекрыти третьего этажа; на фиг. 3 - подъем кровельной плиты на отметку третьего этажа и бетонирование плиты третьего этажа; на фиг. 4 - подъем пакета из трех плит на отметку второго этажа, а на верхней поверхности плиты третьего этажа бетонирование плиты четвертого этажа; на фиг. 5 - подъем кровельной . плиты на отметку четвертого этажа и бетонирование плиты четвертого этажа; на фиг. 6 - подъем пакета из трех плит на отметку третьего этажа, а на верхней поверхности плиты четвертого этажа бетонирование плиты п того этажа. Плита первого этажа установлена на проектную отметку; на фиг. 7 - промежуточный этап совмещени процессов изготовлени плит перекрытий их подъема и обустройства нижних этажей.FIG. 1 shows the manufacture of a package of floor slabs of the first, second floors and a roofing slab; in fig. 2 - installation of the roofing slab on the mark of the second floor and suspension to it around the perimeter of the protective screen with side formwork, and on the upper surface of the slab of the second floor concreting of the third floor slab; in fig. 3 - raising the roofing slab to the mark of the third floor and concreting the slab of the third floor; in fig. 4 - raising a package of three plates to the mark of the second floor, and concreting the plate of the fourth floor on the upper surface of the plate of the third floor; in fig. 5 - roof lifting. slabs to the level of the fourth floor and concreting of the slab of the fourth floor; in fig. 6 - raising a package of three plates to the mark of the third floor, and concreting the plate of the fifth floor on the upper surface of the plate of the fourth floor. The slab of the first floor is set at the design mark; in fig. 7 is an intermediate stage of combining the processes of manufacturing the floor slabs of their lifting and arranging the lower floors.
Способ осуществл ют следующим образом .The method is carried out as follows.
Изготавливают пакет плит перекрытий дл двух первых этажей (плиты 1 и 2 первого и второго этажей) и кровельную плиту 3, при заранее установленных колоннах 4 и шахты 5. После чего устанавливают подъемники 6, кровельную плиту 3 поднимают на отметку второго этажа и подвещивают к ней по периметру защитный экран 7 с нижней бортовой опалубкой 8 с возможностью самосто тельного ее вертикального перемещени , а на верхней поверхности плиты второго этажа 2 бетонируют плиту 9 перекрыти третьего этажа, после чего поднимают пакет из трех плит на отметку второго этажа, затем на верхней поверхности пакетаA stack of floor slabs is made for the first two floors (plates 1 and 2 of the first and second floors) and roofing slab 3, with pre-installed columns 4 and shafts 5. Then they install the lifts 6, the roof slab 3 is raised to the mark of the second floor and illuminated to it along the perimeter, a protective screen 7 with a lower side formwork 8 with the possibility of independent vertical movement, and on the upper surface of the slab of the second floor 2 concrete block 9 of the third floor, then lift a package of three plates to the mark in orogo floor, then on the top surface of the package
J бетонируют плиту 10 четвертого этажа, поднимают плиты второго, третьего и четвертого этажей, бетонируют на верхней поверхности плиту 11 следующего п того этажа, поднимают пакет плит перекрытий этажей и кровельную плиту на отметку следующегоJ concrete slab 10 of the fourth floor, raise the slabs of the second, third and fourth floors, concrete in the upper surface slab 11 of the next fifth floor, raise the stack of floor slabs and the roof slab to the next level
0 этажа, после чего процесс повтор ют.0 floors, after which the process is repeated.
Предлагаемый способ предусматривает одновременный подъем трех плит пакетов и тем самым сокращает сроки монтажа каркаса . При этом не требуетс расхода энергии на твердение бетонируемой плиты, так как пока плита дойдет до своей 1троектной отметки , она полностью набирает свою прочность.The proposed method provides for the simultaneous lifting of three plates of packages and thereby reduces the time of installation of the frame. It does not require energy consumption for the hardening of the concrete slab, as until the slab reaches its 1 design mark, it fully gains its strength.
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU772526301A SU730941A1 (en) | 1977-10-11 | 1977-10-11 | Method of erecting the framework of building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU772526301A SU730941A1 (en) | 1977-10-11 | 1977-10-11 | Method of erecting the framework of building |
Publications (1)
Publication Number | Publication Date |
---|---|
SU730941A1 true SU730941A1 (en) | 1980-04-30 |
Family
ID=20725662
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
SU772526301A SU730941A1 (en) | 1977-10-11 | 1977-10-11 | Method of erecting the framework of building |
Country Status (1)
Country | Link |
---|---|
SU (1) | SU730941A1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4691485A (en) * | 1982-11-30 | 1987-09-08 | Epitestudomanyi Intezet & Konnyuipari Szerelo es Epito Vallalat | Apparatus and process for the construction of monolithic ceilings |
RU2759467C1 (en) * | 2021-04-28 | 2021-11-15 | Публичное акционерное общество "Федеральная гидрогенерирующая компания - РусГидро" | Method for automated installation of the power structure of a gravitational energy storage device and a set of devices for its implementation |
-
1977
- 1977-10-11 SU SU772526301A patent/SU730941A1/en active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4691485A (en) * | 1982-11-30 | 1987-09-08 | Epitestudomanyi Intezet & Konnyuipari Szerelo es Epito Vallalat | Apparatus and process for the construction of monolithic ceilings |
RU2759467C1 (en) * | 2021-04-28 | 2021-11-15 | Публичное акционерное общество "Федеральная гидрогенерирующая компания - РусГидро" | Method for automated installation of the power structure of a gravitational energy storage device and a set of devices for its implementation |
WO2022231457A1 (en) * | 2021-04-28 | 2022-11-03 | Публичное акционерное общество "Федеральная гидрогенерирующая компания - РусГидро" | Method for installing a supporting structure for a gravitational energy storage device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105839784B (en) | Assembled jacking type construction techniques | |
SU730941A1 (en) | Method of erecting the framework of building | |
JPH01256636A (en) | Construction method of building | |
SU552395A1 (en) | The method of construction of high-rise buildings | |
SU962548A1 (en) | Method of erecting high-rise buildings with rigidity core by the method of floor-lifting | |
SU1048093A1 (en) | Method of erecting multistorey building by floor-rising technique | |
SU1278431A1 (en) | Method of assembling skeleton for building | |
SU831942A1 (en) | Method of lifting the floors and ceilings of multistorey building | |
SU421752A1 (en) | METHOD OF BUILDING BUILDING | |
GB1293689A (en) | Improvements in or relating to methods of building | |
RU93010838A (en) | METHOD OF CONSTRUCTION OF MONOLITHIC BUILDING AND MOBILE FORMWORK FOR ITS IMPLEMENTATION | |
SU1087638A1 (en) | Method of erecting structures by hoisting | |
SU1126676A1 (en) | Method for erecting manystoried building by jacking-up floors | |
SU773229A1 (en) | Method of erecting a building from monolithic concrete | |
RU2116414C1 (en) | Method for erection of sectional-and-monolithic buildings | |
SU1682472A1 (en) | Strip foundation | |
SU718586A1 (en) | Method of erecting multistorey building floors | |
SU1240852A1 (en) | Process for erecting multistorey skeleton building by floor-lifting method | |
SU737600A1 (en) | Method of making a floor in sliding form | |
SU1534170A1 (en) | Method of assembling a building in a raising process | |
SU775254A1 (en) | Multistorey building erecting method | |
SU1024575A1 (en) | Method of erecting a building | |
SU1557295A1 (en) | Method of erecting multistorey building by method of storey lifting | |
RU2026941C1 (en) | Method of the building erection by means of hoisting | |
GB982503A (en) | Improvements relating to multi-storey building construction |