SU706530A1 - Trenching method - Google Patents

Trenching method

Info

Publication number
SU706530A1
SU706530A1 SU782582420A SU2582420A SU706530A1 SU 706530 A1 SU706530 A1 SU 706530A1 SU 782582420 A SU782582420 A SU 782582420A SU 2582420 A SU2582420 A SU 2582420A SU 706530 A1 SU706530 A1 SU 706530A1
Authority
SU
USSR - Soviet Union
Prior art keywords
excavator
trenching
open
horizontal
mineral deposits
Prior art date
Application number
SU782582420A
Other languages
Russian (ru)
Inventor
Борис Нусимович Тартаковский
Вадим Викторович Млинарич
Original Assignee
Институт Геотехнической Механики Ан Украинской Сср
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Институт Геотехнической Механики Ан Украинской Сср filed Critical Институт Геотехнической Механики Ан Украинской Сср
Priority to SU782582420A priority Critical patent/SU706530A1/en
Application granted granted Critical
Publication of SU706530A1 publication Critical patent/SU706530A1/en

Links

Landscapes

  • Earth Drilling (AREA)

Description

(54) СПОСОБ ПРОЖ)ДКИ ТРАНШЕЙ(54) METHOD OF PROJECT) DKI TRANCHES

Изобретение относитс  к горной промышленности и может быть использовано при открытой разработке месторождений полезных ископаемых дл  проходки траншей . Известен способ проходки траншей при открытой разработке месторождений полезных ископаемьис, включающий поэта ную проходку траншей l. -Известен также способ проходки тран шей при открытой разработке месторождений полезных ископаемых, включающий взрывание массива пород и выемку горной массы горизонтальными сло ми 2. Однако оба известных способа характеризуютс  недостаточной эффективностью из-за невозможности применени  экскаватора . Целью изобретени   вл етс  повышение эффективности проходки траншей с применением экскаватора. Поставленна  цель достигаетс  тем, что каждый горизонтальный слой раздел ют по диагонали на две клиновидные заходки, при этом горную массу верхне заходки переэкскавируют вниз по направлению движени  экскаватора по наклонной рабочей площадке, а горную массу нижней заходки размещают позади экскаватора при его обратном движении по горизонтальной площадке. На фиг. 1, 2 и 3 представлены схемы последовательной проходки траншей. Способ заключаетс  в следующем. После взрывани  горной массы на участке транщеи экскаватором 1 проход т наклонную заходку 2, при этом горную массу 3 переэкскаввруют вниз по трассе дл  создани  требуемого профил  и предохранительного вала ниже акска- ватора. Наклонную заходку проход т шириной , позвол ющей создать горизонтальную площадку 4 дл  полного разворота экскаватора. После его разворота проход т горизонтальную заходку до основани  5 нарезаемой транщеи, при атом горную массу 6 размещают позади экскаватора . В заключительной стадии производ т зачистку основани  крутой траншеи. В дальнейшем операции повтор ютс .The invention relates to the mining industry and can be used in the open-pit mining of mineral deposits for trenching. There is a method of trenching in the open-pit mining of mineral deposits, which includes poetry trenching l. - A method of excavating a trench is also known in open pit mining of mineral deposits, including blasting an array of rocks and excavating rock mass with horizontal layers 2. However, both known methods are characterized by insufficient efficiency due to the impossibility of using an excavator. The aim of the invention is to increase the efficiency of trenching using an excavator. The goal is achieved by dividing each horizontal layer diagonally into two wedge-shaped stoppers, while the upper stowage rock mass is re-excavated downward in the direction of movement of the excavator along the inclined working site, and the lower stowage rock mass is placed behind the excavator when it is moving backward along the horizontal platform . FIG. 1, 2, and 3 show sequential trenching schemes. The method is as follows. After the rock mass is detonated at the site of the trench by excavator 1, an inclined stowage 2 is performed, while the mountain mass 3 is excavated down the road to create the required profile and safety shaft below the axle shaft. The sloping fit extends in width to create a horizontal platform 4 for a full turn of the excavator. After its reversal, a horizontal approach to the base 5 of the tranche being cut is performed, with the atom a mountain mass 6 is placed behind the excavator. In the final stage, the base of the steep trench is cleaned up. Further operations are repeated.

Фо|эмула И 3обре тени Fo | emule And 3 obre shade

Способ проходки траншей при откры- той разработке месторождений полезных ископаемых, включающий взрывание массива пород и выемку горной массы гс рнзойтальньши сло ми, о т л и ч а ю щ и и с   тем, что, с целью повышени  эффективности проходки траншей с применением экскаватора, каждый горизонтальный слой раздел ют по диагонали на две клиновидные заходки, при этом горную массу верхней заходки переэкскавируют вниз по направлению движени  экскаватора,по наклонной рабочей плоцидке , а горную массу нижней заходки размешают позади экскаватора при его обратном движении по горизонтальной площадке.The method of trenching in the open-pit mining of mineral deposits, including blasting an array of rocks and excavation of rock mass in layers, is carried out in layers, so that, in order to increase the efficiency of trenching using an excavator, each horizontal layer is diagonally divided into two wedge-shaped stoppers, while the mountain mass of the upper winding is re-excavated downwards in the direction of movement of the excavator along the inclined working platform, and the mountain mass of the lower winding is stirred behind the excavator When its return movement the horizontal platform.

Источники информации, прин тые во внимание при экспертизеSources of information taken into account in the examination

1.Симаков П. Т. и др. Опыт проектировани  и строительства скипового подъеника на Сибайском карьере. - Торный журнал , 1975, N 1О, с. 21-22.1. Simakov, P. T., et al. Experience in designing and building a skip lift at the Sibay open pit. - Torn journal, 1975, N 1O, p. 21-22.

2.Нрвс идов М. Г. Технологи  открытой разработки месторождений полезных ископаемых. Ч. 2, М., Недра, 1971,2. Nrvs idov M. G. Technologists of open-cast mining of mineral deposits. Part 2, M., Nedra, 1971,

с. 34 (прототип). with. 34 (prototype).

(put-l(put-l

Фиг.зFig.z

SU782582420A 1978-02-20 1978-02-20 Trenching method SU706530A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU782582420A SU706530A1 (en) 1978-02-20 1978-02-20 Trenching method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU782582420A SU706530A1 (en) 1978-02-20 1978-02-20 Trenching method

Publications (1)

Publication Number Publication Date
SU706530A1 true SU706530A1 (en) 1979-12-30

Family

ID=20750103

Family Applications (1)

Application Number Title Priority Date Filing Date
SU782582420A SU706530A1 (en) 1978-02-20 1978-02-20 Trenching method

Country Status (1)

Country Link
SU (1) SU706530A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2534297C1 (en) * 2013-04-09 2014-11-27 Федеральное государственное бюджетное учреждение науки Институт горного дела Уральского отделения Российской академии наук (ИГД УрО РАН) Method of making steep trench
RU2614835C2 (en) * 2015-06-01 2017-03-29 Федеральное государственное бюджетное учреждение науки Институт горного дела Уральского отделения Российской академии наук (ИГД УрО РАН) Method of arrangement of semi-steep trench

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2534297C1 (en) * 2013-04-09 2014-11-27 Федеральное государственное бюджетное учреждение науки Институт горного дела Уральского отделения Российской академии наук (ИГД УрО РАН) Method of making steep trench
RU2614835C2 (en) * 2015-06-01 2017-03-29 Федеральное государственное бюджетное учреждение науки Институт горного дела Уральского отделения Российской академии наук (ИГД УрО РАН) Method of arrangement of semi-steep trench

Similar Documents

Publication Publication Date Title
SU706530A1 (en) Trenching method
RU2425220C1 (en) Method for formation of steeply inclined transport access track
RU2224107C1 (en) Process of opencast-underground mining of mineral resources
RU2114307C1 (en) Method for opencast mining of flooded mineral deposits
RU2099524C1 (en) Combined method of mining of formation of steeply dipping coal seams
SU1323716A1 (en) Method of remining mineral deposits
SU1083662A1 (en) Method of mining steep-slope ore-bodies
Gogolewska Surface and underground mining technology
SU812922A1 (en) Method of consolidating slopes
SU1122828A1 (en) Method of combination mining of seam deposits
RU2290510C1 (en) Open underground method for extracting formations of mineral resources
RU2187647C1 (en) Method of softening of surface layer of opencast benches in seasonal ground freezing
SU825964A1 (en) Method of working thick steeply-inclined ore bodies
RU2091583C1 (en) Method of mining of mineral upper horizons
SU1033741A1 (en) Method of open-cast mining of steep deposits
SU639995A1 (en) Method of shoring slopes
SU1458574A1 (en) Method of mining ore bodies
SU732531A1 (en) Method for open mining of mineral deposits
SU912934A1 (en) Method of strip mining of mineral deposits
SU861606A1 (en) Method of mining thin steeply deeping veins
Buchan, IF, Baars, LF & Northcote Opencast coal mining at Kriel Colliery
SU885556A1 (en) Method of stripping the working levels of a mine pit
SU866190A1 (en) Method of working a mine face by bucket-wheel excavator
RU1768754C (en) Method for opencast mining of water-bearing deposits
SU620603A1 (en) Method of bis-development of steep orebodies