SU1613661A1 - Utilization steam-gas plant - Google Patents

Utilization steam-gas plant Download PDF

Info

Publication number
SU1613661A1
SU1613661A1 SU884482273A SU4482273A SU1613661A1 SU 1613661 A1 SU1613661 A1 SU 1613661A1 SU 884482273 A SU884482273 A SU 884482273A SU 4482273 A SU4482273 A SU 4482273A SU 1613661 A1 SU1613661 A1 SU 1613661A1
Authority
SU
USSR - Soviet Union
Prior art keywords
gas
stage
regenerative
heater
network
Prior art date
Application number
SU884482273A
Other languages
Russian (ru)
Inventor
Игорь Андреевич Аксенцов
Юрий Петрович Зайков
Алексей Дмитриевич Кондратьев
Николай Михайлович Шапин
Original Assignee
Районное Энергетическое Управление "Челябэнерго"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Районное Энергетическое Управление "Челябэнерго" filed Critical Районное Энергетическое Управление "Челябэнерго"
Priority to SU884482273A priority Critical patent/SU1613661A1/en
Application granted granted Critical
Publication of SU1613661A1 publication Critical patent/SU1613661A1/en

Links

Landscapes

  • Engine Equipment That Uses Special Cycles (AREA)

Abstract

Изобретение относитс  к теплоэнергетике и промышленной теплотехнике. С целью повышени  экономичности и мощности газообразное топливо по газопроводу 2 через дроссель 3 направл ют в котел 4, а по газопроводу 1 - на вход теплообменника 5 с двум  ступен ми 11 и 13 подогрева. После этого газ расшир ют в газовой турбине 6, а затем подают в газоподогреватель 10 с трем  ступен ми 14,17 и 18 подогрева, после чего его также направл ют в котел 4. Это позвол ет увеличить выработку электроэнергии газовой турбины 6 и повысить экономичность котла 4.The invention relates to a power system and industrial heat engineering. In order to increase the economy and power, the gaseous fuel through gas pipeline 2 through throttle 3 is directed to boiler 4, and through gas pipeline 1 to the inlet of heat exchanger 5 with two heating stages 11 and 13. After that, the gas is expanded in the gas turbine 6, and then fed to the gas preheater 10 with three preheating stages 14,17 and 18, after which it is also sent to the boiler 4. This allows an increase in the electricity generation of the gas turbine 6 and increases the efficiency of the boiler four.

Description

Изобретение относится к теплоэнергетике и промышленной теплотехнике, а именно к парогазовым утилизационным установкам, преимущественно работающим при имеющемся избыточном давлении газа в газо- Е проводах, к энергетическим котлам.The invention relates to a power system and industrial heat engineering, in particular to combined cycle gas recovery plants, which are mainly operated at the existing excess gas pressure in the gas-E wires, to power boilers.

Целью изобретения является повышение экономичности и мощности,The aim of the invention is to increase efficiency and power,

На чертеже представлена схема парогазовой утилизационной установки. 1The drawing shows a diagram of a combined cycle gas recovery plant. 1

Установка содержит по меньшей мере два газопровода 1 и 2, Газопровод 2 подключен через дроссель 3 к энергетическому котлу 4, а газопровод 1 через теплообменник 5 - к входу газовой турбины 6, выхлопной 1 патрубок 7 которой соединен с газопроводом 2 за дросселем 3, и паровую турбину 8 с регенеративным отбором 9. На участке газопровода 2 между выхлопным патрубком 7 газовой турбины 6 и дросселем 3 размещен 2 газоподогреватель 10. Теплообменник 5 выполнен двухступенчатым, причем первая по ходу газа ступень 11 соединена с трубопроводом 12 обратной сетевой воды, а вторая по ходу газа ступень 13 - с регенеративным 2 отбором 9 паровой турбины 8. Газоподогреватель 10 выполнен трехступенчатым, причем первая по ходу газа ступень 14 подключена к трубопроводу 15 циркуляционной воды из конденсатора 16, вторая по 3 ходу газа ступень 17 подключена к трубопроводу 12 обратной сетевой воды до сетевого подогревателя (не показан), а третья по ходу газа ступень 18 - к регенеративному отбору 9 паровой турбины 8. 3The installation contains at least two gas pipelines 1 and 2, a gas pipeline 2 is connected through an inductor 3 to a power boiler 4, and a gas pipeline 1 through a heat exchanger 5 is connected to an inlet of a gas turbine 6, an exhaust 1 of which 7 is connected to a gas pipeline 2 behind an orifice 3, and a steam a turbine 8 with regenerative selection 9. On the gas pipeline section 2 between the exhaust pipe 7 of the gas turbine 6 and the throttle 3 there are 2 gas heaters 10. The heat exchanger 5 is made two-stage, and the first stage 11 along the gas is connected to the return network water pipe 12, and the second stage 13 in the gas path with regenerative 2 extraction 9 of the steam turbine 8. The gas heater 10 is made in three stages, the first stage 14 in the gas direction connected to the circulation water pipe 15 from the condenser 16, the second stage 17 in the gas direction 3 connected to the pipeline 12 return network water to the network heater (not shown), and the third step 18 in the course of gas - to regenerative selection 9 of the steam turbine 8. 3

Парогазовая утилизационная установка работает следующим образом.Combined cycle utilization plant operates as follows.

Газообразное топливо для энергетического котла 4 со среднегодовой температурой 2-10°С перед подачей в котел 4 4 направляют в газопроводы 1 и 2, один поток направляют по газопроводу 2 через дроссель 3, а второй поток - по газопроводу 1 на вход теплообменника 5, в котором повышают его температуру до 140-200°С за 4 счет нагрева в ступенях 11 и 13 обратной сетевой водой и паром регенеративного отбора 9 паровой турбины 8 соответственно, после чего подают его на вход газовой турбины 6. Из выходного патрубка 7 последней охлажденный газ подают в газопо5 догреватель 10, в трех ступенях которого 14, 17 и 18 соответственно нагревают газ циркуляционной водой, обратной сетевой водой и паром регенеративного отбо--, ра 9 до 40-50°С.Gaseous fuel for power boiler 4 with an average annual temperature of 2-10 ° C before being fed to boiler 4 4 is sent to gas pipelines 1 and 2, one stream is sent through gas pipeline 2 through throttle 3, and the second stream is sent through gas pipeline 1 to the inlet of heat exchanger 5, which increases its temperature to 140-200 ° C due to 4 heating in steps 11 and 13 with reverse network water and steam of regenerative selection 9 of the steam turbine 8, respectively, after which it is supplied to the inlet of the gas turbine 6. From the outlet pipe 7 of the last, cooled gas is supplied in gas5 heater 10 in which three stages 14, 17 and 18 respectively heat the gas circulating water feedback mains water and steam regenerative otbo--, pa 9 to 40-50 ° C.

После газоподогревателя 10 газ подмешивают к газу после дросселя 3 и подают на вход котла 4. В зависимости от давления газа, его температуры и расхода, а также от давления пара в регенеративном отборе 5 9, может быть выбрано оптимальное соотношение расходов потоков газа, направляемых по газопроводам 1 и 2.After the gas heater 10, the gas is mixed with gas after the inductor 3 and fed to the inlet of the boiler 4. Depending on the gas pressure, its temperature and flow rate, as well as on the vapor pressure in regenerative selection 5 9, the optimal ratio of gas flow rates directed along gas pipelines 1 and 2.

Claims (1)

Формула изобретенияClaim Парогазовая утилизационная установка, содержащая паровую турбину с регенеративными отборами, к выходу которой подключены последовательно по воде конденсатор с трубопроводами циркуляционной воды и регенеративные подогреватели, трубопровод обратной сетевой воды, подключенный к входу сетевого подогревателя, газовую утилизационнуютурбину и по меньшей мере два газопровода, один из которых через дроссель подключен к энергетическому котлу, а другой - к входу газовой утилизационной турбины, на выходном патрубке которой размещен газоподогреватель, отличающаяся тем, что, с целью повышения экономичности и мощности перед газовой утилизационной турбиной дополнительно размещен двухступенчатый теплообменник, первая ступень которого соединена с трубопроводом обратной сетевой воды до сетевого подогревателя, а вторая - с регенеративным отбором паровой турбины,*а газоподогреватель выполнен трехступенчатым, при этом первая ступень его подключена к трубопроводу циркуляционной воды, вторая ступень - к трубопроводу-обратной сетевой воды, а третья ступень - к регенеративному отбору.A combined cycle gas recovery plant comprising a steam turbine with regenerative extraction, to the outlet of which a condenser with circulating water pipelines and regenerative heaters are connected in series through water, a return network water pipeline connected to the input of the network heater, a gas recovery turbine and at least two gas pipelines, one of which through a throttle connected to an energy boiler, and the other to the inlet of a gas recovery turbine, at the outlet of which a gas heater is located evatel, characterized in that, in order to increase efficiency and power, a two-stage heat exchanger is additionally placed in front of the gas recovery turbine, the first stage of which is connected to the return network water pipeline to the network heater, and the second - with regenerative extraction of the steam turbine *, and the gas heater is made of three-stage, at the same time, its first stage is connected to the circulation water pipeline, the second stage to the return water network pipe, and the third stage to regenerative selection.
SU884482273A 1988-09-13 1988-09-13 Utilization steam-gas plant SU1613661A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU884482273A SU1613661A1 (en) 1988-09-13 1988-09-13 Utilization steam-gas plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU884482273A SU1613661A1 (en) 1988-09-13 1988-09-13 Utilization steam-gas plant

Publications (1)

Publication Number Publication Date
SU1613661A1 true SU1613661A1 (en) 1990-12-15

Family

ID=21399090

Family Applications (1)

Application Number Title Priority Date Filing Date
SU884482273A SU1613661A1 (en) 1988-09-13 1988-09-13 Utilization steam-gas plant

Country Status (1)

Country Link
SU (1) SU1613661A1 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
3ысин В.А. Комбинированные парогазовые установки и циклы. М.-Л.: Госэнергоиз- дат, 1962, С.52, рис. 2-14. *

Similar Documents

Publication Publication Date Title
US5623822A (en) Method of operating a waste-to-energy plant having a waste boiler and gas turbine cycle
US6497102B2 (en) Method for supplementing a saturated steam generation system having at least one steam turbine set, and steam power plant supplemented using the method
US6256978B1 (en) Power generation in a combination power plant with a gas turbine and a steam turbine
US20070017207A1 (en) Combined Cycle Power Plant
RU99113947A (en) MIXED TYPE POWER PLANT WITH GAS AND STEAM TURBINES
JP2757290B2 (en) Gas / steam turbine combined facility with coal gasification facility
US4702081A (en) Combined steam and gas turbine plant
RU2650232C1 (en) Combined-cycle cogeneration plant
KR20000010927A (en) Gas and steam turbine equipment and operating method thereof
US3461667A (en) Method and apparatus for mixing gas and steam in a gas turbine plant
DK0657687T3 (en) Device for improving the efficiency of a power plant or the like
MXPA04006872A (en) Feedwater heater.
RU2326246C1 (en) Ccpp plant for combined heat and power production
SU1613661A1 (en) Utilization steam-gas plant
RU2115000C1 (en) Combination boiler house
HUT69893A (en) Combined gas- and steam turbine for servicing electric energy
Abdel-Moneim et al. Exergy analysis of a combined gas/steam turbine cycle with a supercharged boiler
RU2078229C1 (en) Steam-and-gas plant
CN112594019B (en) Energy cascade efficient utilization system of supercritical coal-fired generator set
RU2031213C1 (en) Steam-gas power plant
SU1617161A1 (en) District heating steam-gas plant
RU2163703C1 (en) Centralized heat supply system
RU2139430C1 (en) Combined-cycle plant
RU2053374C1 (en) Method of preheating of feed water
RU2079672C1 (en) Method of regeneration of steam heat in steam-gas cycles