SU1017762A1 - Method of straightening a river bed - Google Patents

Method of straightening a river bed Download PDF

Info

Publication number
SU1017762A1
SU1017762A1 SU823378757A SU3378757A SU1017762A1 SU 1017762 A1 SU1017762 A1 SU 1017762A1 SU 823378757 A SU823378757 A SU 823378757A SU 3378757 A SU3378757 A SU 3378757A SU 1017762 A1 SU1017762 A1 SU 1017762A1
Authority
SU
USSR - Soviet Union
Prior art keywords
channel
pioneer
river
trench
flow
Prior art date
Application number
SU823378757A
Other languages
Russian (ru)
Inventor
Николай Константинович Голубев
Нинель Рачиковна Стеценко
Давид Лазаревич Меламут
Василий Алексеевич Нешин
Original Assignee
Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Гидротехники И Мелиорации Им.А.Н.Костякова
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Гидротехники И Мелиорации Им.А.Н.Костякова filed Critical Всесоюзный Ордена Трудового Красного Знамени Научно-Исследовательский Институт Гидротехники И Мелиорации Им.А.Н.Костякова
Priority to SU823378757A priority Critical patent/SU1017762A1/en
Application granted granted Critical
Publication of SU1017762A1 publication Critical patent/SU1017762A1/en

Links

Landscapes

  • Revetment (AREA)

Abstract

СПОСОБ ВЬШРАВЛЕНйЯ РУСЛА РЕКИ, включающий направление воды из в3весенесущего потока реки с русловыми мезоформами в размываемую пионерную траншею с входным участком , выполненным в виде раструба, и одновременное стеснение и перекрытие русла реки ниже пионерной траншеи намывом грунта в поток, о тл и чающий с   тем, что, с целью повьвиени  эффективности за счет сохранени  пропускной способности пионерной.траншеи и ускорени  перекрыти  русла, на входном участке пионерной траншеи сооружают донный неразмываемый порог высотой, превышающей высоту русловых мёзрформ,. а стеснение русла реки осуществл ют с противоположноговходу пионер- .§ ной траншеи берега под острый сл углом к динамической оси потока реки. с:A METHOD FOR IMPROVING THE RIVER BED, including the direction of water from the spring flow of the river with channel mezoforms to the eroded pioneer trench with a bell-shaped entrance section, and the ostrich and overlapping of the river below the pioneer trench all the way to the flow of a channel, and the channel is covered by a sink. that, in order to improve efficiency by preserving the capacity of the pioneer tranche and accelerating the blocking of the channel, at the entrance of the pioneer trench, a bottom non-erasable threshold is constructed with a height exceeding the common height of the channel mezrform ,. Constriction of the riverbed is carried out from the opposite path of the pioneer. trench of the coast at a sharp angle to the dynamic axis of the river flow. with:

Description

лl

Изобретение относитс  к технологии производства гидромеханизированных русловыправительных работ, например при отводе потока от размываемог берега в спр мл ющее русло.The invention relates to a process for the production of hydromechanized channeling works, for example, when diverting a stream from a washed-out shore to a closed channel.

Известен способ отвода потока дл  постройки канала, при котором размыв пионерной траншеи безнапорным взвесенесущим потоком осуществл ют с отделением насыщенных продуктами размыва придонных слоев потока и направлением их через боковые отвод щие каналы в естественные емкости.A known method of diverting a stream to build a channel in which the pioneer trench is washed out with a free-flowing suspended flow is carried out with separation of the bottom layers of the stream saturated with products and directed through the side discharge channels to natural tanks.

При этом дл  разделени  потока используют поверхностные струенаправл ющке системы, которые устанавливают перёд боковыми отвод щими .каналами 1. In this case, for the separation of the flow, surface strapping systems are used, which are installed in front of the side discharge channels 1.

Недостатком данного способа  вл етс  то, что при отводе потока, содержащего донные наносы с русловыми мезоформами, происходит заиление входного участка канала и сниже ние эффективности размыва: участков пионерной траншеи за счет неполного пропуска наносов в отвод щие каналы. Кроме того,монтаж и установка струенаправл ющих систем - достаточно трудоемкие операции, а эксплуатаци  их требует обслуживающего персонала и определенных .затрат.The disadvantage of this method is that when a stream containing bottom sediments with channel meso forms is diverted, the channel inlet section becomes silted and the erosion efficiency decreases: areas of the pioneer trench due to incomplete passage of sediment into the discharge channels. In addition, the installation and installation of streamlining systems is quite time-consuming operations, and their operation requires maintenance personnel and certain costs.

Известен также сп.особ выправлени  русла реки, включаюйщй направление воды из взвесенесущего потока реки с русловыми мезоформами в размываемую пионерную траншею с входным участком выполненным в виде раструба, и одновременное стеснение и перекрытие русла реки ниже пионерной траншеи намывом грунта в поток ЗThe method of straightening the river bed is also known, including the direction of water from the river's weighing stream with channel meso-forms into the eroded pioneer trench with a bell-shaped entrance section, and the simultaneous constraint and overlapping of the river channel below the pioneer trench by pouring all the soil into the stream 3

Недостатком этого способа  вл етс  заиление поступающими из реки русловыми мезоформами входного участка пионерной траншеи, дл  сохранени  пропускной способности которой требуетс  выполнение земснар дами дноуглубительных работ.The disadvantage of this method is the sedimentation of the riverbed mesoforms coming from the river from the entrance section of the pioneer trench, in order to preserve the carrying capacity of which the dredging works are required.

Цель изобретени  - повышение эффективности, за счет сохранени  пропускной способности пионерной тра.ншеи и ускорени  перекрыти  русла.The purpose of the invention is to increase efficiency by maintaining the throughput of the pioneer trap and speeding up the overlapping of the channel.

Цель достигаетс  тем, что на входном участке пионерной траншеи сооружают.донный неразмываемый порог высотой, превышающей высоту русловых мезоформ, а стеснение русла реки осуществл ют с противоположного входу пионерной траншеи берега под острым углом к динамической оси потока реки.The goal is achieved by constructing a non-erasable bottom threshold at the entrance of the pioneer trench to a height greater than the height of the channel mesoforms, and restricting the flow of the riverbed from the pioneer bank trench opposite the entrance at an acute angle to the dynamic axis of the river flow.

На фиг. 1 изображен план русла реки в процессе осуществлени  способа; на фиг. 2 - разрез А-А на фиг. 1. .FIG. 1 shows a riverbed plan in the process of implementation of the method; in fig. 2 shows section A-A in FIG. one. .

Способ осуществл ют следую(цим образом.The method is carried out as follows.

Предварительно по трассе спр мл ющего русла 1 разрабатывают пионерную траншею 2/ входной участок которой выполн ют .в виде раструба с донным земл ным неразмываемым порогом 3, высотой „ , превышающей высоту Ji русловых мезоформ 4, с посто нным поперечным сечением и с увеличивающейс  глубиной в сторону потока.в пионерной траншее 2. Мезоформы - это крупные печаные гр ды, соизмеримые с размерами речного &усла . Дальнейша  разработка спр мл ющего русла 1 до проектного сечени  осуществл етс  безнапорным размывом пионерной траншеи2 путем направлени  воды в нее }гз реки 5. Одновременно производ т стеснение и перекрытие русла реки 5 возведением в нем перемычки б земснар дами 7 грунта в-поток. При этом стеснение русла реки 5-осуществл ют ниже по течению от пионерной траншеи 2 с противоположного ее входу берега реки 5 под острым углом к динс1мической оси 8 потока/ которай наблюдалась до стеснени  русла рекиPreliminary, along the route of the distributing channel 1, a pioneer trench 2 is developed / the entrance section of which is made in the form of a socket with a ground bottom non-erasable threshold 3 with a height, exceeding the height Ji of the channel meso-forms 4 with a constant cross section and with increasing depth to the side of the stream. in the pioneer trench 2. Mesoforms are large peppered ridges commensurate with the size of the river & Further development of the spreading channel 1 to the design section is carried out by means of the unconstrained erosion of the pioneer trench 2 by directing water into it} in the river 5. At the same time, the river channel is constrained and overlaid with a jumper in dredger 7 of the in-flow soil. At the same time, the riverbed 5 is constrained downstream from the pioneer trench 2 from the bank of the river 5 opposite to its entrance at an acute angle to the flow direction axis 8, which was observed to the riverbed

5.Таким образом, при отводе потока в спр мл ющее русло 1 по предлагаемому способу придонные струи потока реки 5 не попадают в пионерную траншею 2, а направл ютс  ниже по течению к створу возведени  перемычки5. Thus, when diverting the stream to the spreading channel 1 according to the proposed method, the bottom streams of the river stream 5 do not enter the pioneer trench 2, but are directed downstream to the construction site of the jumper

6.При этом русловые мезоформы 4 перемещаютс  по руслу реки 5, не заил ют входной участок пионерной тран шеи 2, что способствует сохранению ее пропускной способности. Сте,снение реки 5 с- противоположного входу пионерной траншеи 2 берега и под острым углом к динамической оси потока реки 5 создает благопри тные гидравлические услови  дл  перемещени  меэоформ 4 по руслу реки 5 и осаждени  в зоне перемычки 6, не допуска  их поступлени  в пионерную траншею 2. 6. At the same time, the channel mesoforms 4 move along the channel of the river 5, they do not cover the entrance section of the pioneer tranche of neck 2, which helps to preserve its carrying capacity. The ste, removal of the river 5 from the opposite of the entrance of the pioneer trench 2 of the bank and at an acute angle to the dynamic axis of the stream of the river 5 creates favorable hydraulic conditions for moving meeoform 4 along the riverbed 5 and settling in the zone of the bridge 6, preventing it from entering the pioneer trench 2

Это позвол ет повысить интенсивность размыва пионерной траншеи, а также ускорить перекрытие русла за счет дополнительного насыщени  наносами перекрываемого потока реки и направлени  мезоформ в зону намыва перемычки .This makes it possible to increase the intensity of erosion of the pioneer trench, as well as to accelerate the overlapping of the channel due to the additional saturation of the overflow of the river with sediments and the direction of the mesoforms to the zone of alluvial jumpers.

Claims (1)

СПОСОБ ВЫПРАВЛЕНИЯ РУСЛА РЕКИ, включающий направление воды из взвесенесущего потока реки с русловыми мезоформами в размываемую пионерную траншею с входным участком, выполненным в виде раструба, и одновременное стеснение и перекрытие русла реки ниже пионерной траншеи намывом грунта в поток, о тл и чаю щ и й с я тем, что, с целью повьииения эффективности за счет сохранения пропускной способности пионерной.траншеи и ускорения перекрытия русла, на входном участке пионерной траншеи сооружают донный неразмываемый порог высотой, превышающей высоту русловых мёзоформ, а стеснение русла реки Осуществляют с противоположного входу пионер- . g ной траншеи берега под острый j углом к Динамической оси потока С/ реки. м м Λ ьоMETHOD FOR RECTING A RIVER BED, including the direction of water from a suspension stream of a river with channel mesoforms into a washable pioneer trench with an inlet section made in the form of a bell, and at the same time constraining and blocking the river channel below the pioneer trench by flooding the soil into the flow, with the fact that, in order to improve efficiency by maintaining the capacity of the pioneer trench and to accelerate the overlap of the channel, a bottom indelible threshold is constructed at the entrance of the pioneer trench with a height exceeding you hundred channel mesoforms, and oppression of the river bed Carry out from the opposite entrance pioneer. g of the trench of the shore at an acute j angle to the Dynamic axis of the C / river flow. m m Λ b
SU823378757A 1982-01-07 1982-01-07 Method of straightening a river bed SU1017762A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU823378757A SU1017762A1 (en) 1982-01-07 1982-01-07 Method of straightening a river bed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU823378757A SU1017762A1 (en) 1982-01-07 1982-01-07 Method of straightening a river bed

Publications (1)

Publication Number Publication Date
SU1017762A1 true SU1017762A1 (en) 1983-05-15

Family

ID=20991257

Family Applications (1)

Application Number Title Priority Date Filing Date
SU823378757A SU1017762A1 (en) 1982-01-07 1982-01-07 Method of straightening a river bed

Country Status (1)

Country Link
SU (1) SU1017762A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109356097A (en) * 2018-11-29 2019-02-19 中国电建集团成都勘测设计研究院有限公司 The water discharge tunnel makeup of the imports for ditch water process

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
1. Авторское свидетельство СССР 629280, кл. Е 02 .В 5/02, 1975. 2. Меламут Д.Л. и др. Защита берегов Амударьи с помощью средств гидромеханизации:- Гидротехника и мелиораци , 1977, 5, с. 17 (прототип) . *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109356097A (en) * 2018-11-29 2019-02-19 中国电建集团成都勘测设计研究院有限公司 The water discharge tunnel makeup of the imports for ditch water process
CN109356097B (en) * 2018-11-29 2023-09-19 中国电建集团成都勘测设计研究院有限公司 A drainage tunnel import structure for ditch water treatment

Similar Documents

Publication Publication Date Title
KR101334192B1 (en) Early rainwater filtration and skimming device
DeBano et al. ENHANCEMENT OF RIPARIAN ECOSYSTEMS WITH CHANNEL STRUCTURES 1
CN109056633A (en) A kind of hazards control system and method for flood control and anti-mud-rock flow
US3997444A (en) Sewage settling tank
RU2665072C1 (en) Method of reservoir water area localization of pollutants entering reservoir from tributaries and drains
US3693796A (en) Method and apparatus for removal of particles from suspension
SU1017762A1 (en) Method of straightening a river bed
US3817383A (en) Apparatus for removing particulate matter
KR0171912B1 (en) Purifying apparatus
US2672982A (en) Solids retention apparatus for streams
KR101181324B1 (en) Water treatment system
JPH08170359A (en) Earth and sand filter device
CN106013007A (en) Water-sand separation building applicable to linear chute spillway
SU35078A1 (en) Device to protect the reservoir from sediment
JP2003227149A (en) River water reservoir facility outside of river course in flood
SU836280A1 (en) Sand and gravel trap
SU1055826A1 (en) Earth-fill hydraulic structure
US2727623A (en) Material distributing system for mining dredges
KR101006852B1 (en) System for improving water quality of river
SU889784A1 (en) Method of erecting hydraulically filled structures in water ducts
SU1010182A1 (en) Method of storing tails of concentration mills
SU1198144A1 (en) Arrangement for controlling deformation of bed part of canals
SU1114728A1 (en) Method for hydraulically filling structures
SU836279A1 (en) Method of closing river flows
SU1444462A1 (en) Method of straightening river path