Prior art keywords
foam
fire
mine
pipe
formwork
Prior art date
Application number
RU2008119799/22U
Other languages
Russian (ru)
Inventor
Андрей Васильевич Кондаков
Василий Маркович Кондаков
Алексей Егорович Чуприков
Дарья Васильевна Агеева
Original Assignee
Общество с ограниченной ответственностью "Кузбассгорноспасатель" (ООО "Кузбассгорноспасатель")
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Общество с ограниченной ответственностью "Кузбассгорноспасатель" (ООО "Кузбассгорноспасатель") filed Critical Общество с ограниченной ответственностью "Кузбассгорноспасатель" (ООО "Кузбассгорноспасатель")
Priority to RU2008119799/22U priority Critical patent/RU76978U1/en
Application granted granted Critical
Publication of RU76978U1 publication Critical patent/RU76978U1/en

Links

Landscapes

  • Fire-Extinguishing By Fire Departments, And Fire-Extinguishing Equipment And Control Thereof (AREA)

Abstract

Использование: Полезная модель относится к горному делу и может быть использована при тушении подземных пожаров, преимущественно в куполах горных выработок. Цель: Повышение эффективности профилактики и тушения пожаров в куполах горных уклонных выработок. Сущность: Устройство для тушения пожаров в наклонной горной выработке, содержащее пеногенератор и расположенный под ним воздушно-пенный ствол с плоскоструйным насадком, при этом образующуюся пену средней кратности транспортируют потоком на поверхность струи низкократной пены в аварийную зону, при этом зона эндогенного пожара горной выработки изолирована двойной быстровозводимой опалубкой 12 и 19, со стороны действующей выработки установлена проемная труба 2 и подсоединена к ней пеногенераторная установка 5, со стороны изолированного пространства внутри опалубки под проемной трубой 2 установлена поперек выработки перфорированная труба 3 с выводом патрубка 4 в действующую выработку, от дополнительного напорного патрубка проемной трубы 5 рукав 14 соединен на пожарную пику 15, внедренную в пожарный купол 16 горной выработки, и произведено заполнение пенной пробкой 17 пространства двойной перемычки с вытеснением пожарных газов из купола 16 горной выработки и двойной изолирующей опалубки 12 и 19 за пределы аварийного участка, а транспортирование пенной пробки 17 обеспечивают на почвенном слое 1 гидрофобного эмульгатора. Положительный эффект: Повышение эффективности, безопасности и надежности производства горноспасательных работ при ликвидации эндогенного пожара в куполах горных выработок.Use: The utility model relates to mining and can be used to extinguish underground fires, mainly in mining domes. Purpose: Improving the effectiveness of the prevention and suppression of fires in domes of mountain deviations. SUBSTANCE: device for extinguishing fires in an inclined mining, containing a foam generator and an air-foamy barrel with a plane-jet nozzle located beneath it, while the resulting medium-foam foam is transported by a stream onto the surface of a low-foam foam jet into the emergency zone, while the zone of the endogenous mine fire is isolated double prefabricated formwork 12 and 19, from the side of the working mine, an opening pipe 2 is installed and a foam generator 5 is connected to it, from the side of the insulated of the space inside the formwork, under the opening pipe 2, a perforated pipe 3 is installed across the working with the outlet of the pipe 4 to the working output, from the additional pressure pipe of the opening pipe 5, the sleeve 14 is connected to the fire lance 15, embedded in the fire dome 16 of the mine working, and the foam tube 17 is filled the space of the double bridge with the displacement of fire gases from the dome 16 of the mine and the double insulating formwork 12 and 19 outside the emergency section, and the transportation of the foam plug 17 is provided by indigenous layer 1 of a hydrophobic emulsifier. Positive effect: Improving the efficiency, safety and reliability of mining operations during the elimination of endogenous fire in the domes of mine workings.

Description

Полезная модель устройства относится к горному долгу и может быть использована при тушении подземных пожаров, преимущественно в куполах горных выработок.A useful model of the device relates to mining duty and can be used to extinguish underground fires, mainly in domes of mine workings.

Известен способ тушения пожара в куполе горной выработки, включающий введение в купол перфорированных труб для отсоса через низ пожарных газов, выжигание горючих компонентов и утилизацию продуктов сгорания, создание в аварийном участке пенной барьерной пробки. (Патент РФ №2136889, кл. Е21F 5/00, 1999).A known method of extinguishing a fire in a dome of mining, including introducing perforated pipes into the dome for suction through the bottom of the fire gases, burning combustible components and disposing of combustion products, creating a foam barrier plug in the emergency section. (RF patent No. 2136889, class E21F 5/00, 1999).

Недостаток известного способа заключается в сложности его реализации вследствие наличия ряда уникального оборудования (парашютная перемычка, воздухонепроницаемое перекрытие, газификатор, камера дожигания и др.) Таким же недостатком обладает установка для возведения изолирующей перемычки по свидетельству РФ на полезную модель №17569, кл. Е21F 5/00, 2000.The disadvantage of this method lies in the difficulty of its implementation due to the presence of a number of unique equipment (parachute bridge, airtight ceiling, gasifier, afterburner, etc.). The installation for erecting an isolation bridge according to the RF certificate for utility model No. 17569, cl. E21F 5/00, 2000.

Цель полезной модели - повышение эффективности профилактики и тушения пожаров в куполах горных уклонных выработок.The purpose of the utility model is to increase the effectiveness of the prevention and suppression of fires in domes of mountain deviations.

Это достигается тем, что в устройстве для тушения пожаров в уклонной горной выработке, содержащем пеногенератор и расположенный под ним воздушно-пенный ствол с плоскоструйным насадком, при этом образующуюся пену средней кратности транспортируют потоком на поверхность струи низкократной пены в аварийную зону, зона эндогенного пожара горной выработки изолирована двойной быстровозводимой опалубкой, со стороны действующей выработки установлена проемная труба и подсоединена к ней пеногенераторная установка, со стороны This is achieved by the fact that in a device for extinguishing fires in an inclined mine working area containing a foam generator and an air-foamy barrel with a flat-jet nozzle located beneath it, the resulting foam of medium multiplicity is transported by a stream onto the surface of a low-level foam jet into the emergency zone, the endogenous mountain fire zone the workings are insulated with a double quick-erected formwork, on the side of the active workout an opening pipe is installed and a foam generator is connected to it, on the side

изолированного пространства внутри опалубки под проемной трубой установлена поперек выработки перфорированная труба с выводом патрубка в действующую выработку, от дополнительного напорного патрубка проемной трубы рукав соединен на пожарную пику, внедренную в пожарный купол горной выработки, и произведено заполнение пенной пробкой пространства двойной перемычки с вытеснением пожарных газов из купола горной выработки и двойной изолирующей опалубки за пределы аварийного участка.an perforated pipe was installed across the working area under the opening pipe across the working hole, with a pipe outlet into the working output, from the additional pressure pipe opening of the opening pipe, the hose was connected to a fire lance embedded in the mining fire dome, and a foam plug filled the double bridge space with fire gas displacement from a mining dome and double insulating formwork beyond the emergency site.

Предложенная совокупность отличительных признаков полезной модели обладает полезным свойством, которое заключается в полной изоляции аварийного участка от действующих выработок и ликвидации опасности выброса из купола продуктов горения, вредных газов, при этом обеспечивается безопасность работ по ликвидации пожара.The proposed set of distinguishing features of the utility model has a useful property, which consists in the complete isolation of the emergency section from existing workings and the elimination of the danger of the emission of combustion products and harmful gases from the dome, while ensuring the safety of fire suppression.

На рисунке изображена технологическая схема по реализации устройства в действии.The figure shows the technological scheme for the implementation of the device in action.

Технологическая схема поясняется следующими основными позициями: 1 - слой пены гидрофобного эмульгатора, 2 - проемная труба изоляционной перемычки; 3 - перфорированный отрезок трубы по почве горной выработки; 4 - патрубок подачи гидрофобного эмульгатора, 5 - установка напорная пеногенераторная "Экран"; 6 - рукав подачи раствора пенообразователя; 7 - емкость пенообразователя; 8 - рукав подачи сжатого газа: 9 - патрубок отвода от пожарно-оросительного трубопровода; 10 - пожарно-оросительный трубопровод; 11 - растяжка раскрепляющая; 12 - опалубка быстровозводимая "Парус"; 13 - пена высокократная; 14 - рукав подачи потока инертной пены на пожарную пику; 15 - пика пожарная; 16 - очаг пожара купола горной выработки; 17 - пенная пробка внутриопалубочного пространства; 18 - внутриопалубочное пространство аварийного участка; 19 - двойная опалубка аварийного участка; 20 - изолированное пространство; 21 - проемная труба сброса жидкой дисперсной фазы.The technological scheme is illustrated by the following main positions: 1 - a layer of foam of a hydrophobic emulsifier, 2 - an opening pipe of an insulating bridge; 3 - perforated pipe section on the soil of a mine; 4 - a nozzle for supplying a hydrophobic emulsifier, 5 - a foam pressure-generating unit "Screen"; 6 - a hose for supplying a foaming agent solution; 7 - the capacity of the foaming agent; 8 - sleeve for supplying compressed gas: 9 - pipe branch from the fire-irrigation pipeline; 10 - fire and irrigation pipeline; 11 - stretching unfastening; 12 - prefabricated formwork "Sail"; 13 - high-foam; 14 - sleeve supply flow of inert foam to the fire peak; 15 - fire peak; 16 - fire center dome mining; 17 - foam plug vnutriopalubnogo space; 18 - intra deck space emergency site; 19 - double formwork of the emergency section; 20 - isolated space; 21 - aperture pipe discharge of the liquid dispersed phase.

Полезная модель устройства работает следующим образом.A useful model of the device operates as follows.

При возникновении эндогенного пожара вследствие самовозгорания угля в разрушенном массиве закрепного пространства, а именно в куполе горной выработки на границах пожара наклонной выработки (уклоне) возводят двойную перемычку быстровозводимой опалубкой 12 и 19 "Парус" (конструкция РосНИИГД) с установкой проемной трубы 2 и перфорированного отрезка трубы 3. Одновременно с этим в купол 16 горной выработки внедряют пожарную пику 15 с подсоединением ее рукавом 14 к дополнительному патрубку проемной трубы 2, к которой подсоединяют пеногенераторную напорную установку "Экран" с соответствующим подключением через отводной патрубок 9 к пожарно-оросительному трубопроводу 10, а рукавом 8 к подземному газификатору азота, например "КОМБИ" (комплект оборудования механизации и безопасной изоляции - конструкция РосНИИГД), который также имеет в своем составе резервуар с хладоном 114В2, который можно использовать при подаче пены в купол горной выработки для флегматизации взрыва (выброса).In the event of an endogenous fire due to spontaneous combustion of coal in the destroyed mass of the fixed space, namely, in the dome of the mine working at the borders of the fire of an inclined mine (slope), a double bridge is erected with the quick-release formwork 12 and 19 “Sail” (design of RosNIIGD) with the installation of the opening pipe 2 and perforated section pipes 3. At the same time, fire peak 15 is introduced into the dome 16 of the mine working with its sleeve 14 connected to an additional branch pipe of the opening pipe 2 to which the foam generator is connected “Ekran” pressure head installation with a corresponding connection through the branch pipe 9 to the fire-irrigation pipe 10, and by a sleeve 8 to an underground nitrogen gasifier, for example, “COMBI” (a set of mechanization equipment and safe insulation - design of RosNIIGD), which also includes a tank with Freon 114B2, which can be used when supplying foam to the dome of a mine for phlegmatization of an explosion (discharge).

Работу пеногенератора 5 и подачу гидрофобного эмульгатора через патрубок 4 на перфорированную трубу 3 производят одновременно Первоначальную подачу инертной пены предпочтительно производить при вводе в инертную пену дополнительного флегматизатора, например хладона 114В2 из резервуара газификатора "КОМБИ". Слой инертной пены одновременно поступает на заполнение (вытеснение) объема очага пожара в куполе 16 горной выработки и создание пенной пробки 17 в пространстве между опалубками 12 и 19. При этом инертная пена 13 легко транспортируется на слое 1 гидрофобного эмульгатора, в качестве которого используют, например инертную пыль. Жидкая дисперсная фаза (синерезис пены) вместе с низкократной пеной 1 сбрасывается через проемные трубы 21 за опалубку 19 в изолированное пространство 20 горной выработки. После вытеснения пожарных газов через воздухопроницаемую опалубку и выдержки на охлаждение очага по времени, со стороны действующей выработки производят контроль изолированного пространства купола 16 The operation of the foam generator 5 and the supply of the hydrophobic emulsifier through the pipe 4 to the perforated pipe 3 is carried out simultaneously. The initial supply of inert foam is preferably carried out by introducing an additional phlegmatizer into the inert foam, for example Freon 114B2 from the COMBI gasifier reservoir. A layer of inert foam simultaneously enters to fill (displace) the volume of the fire in the dome 16 of the mine and create a foam plug 17 in the space between the formwork 12 and 19. In this case, the inert foam 13 is easily transported on the layer 1 of a hydrophobic emulsifier, which is used, for example inert dust. The liquid dispersed phase (foam syneresis) together with low-level foam 1 is discharged through the opening pipes 21 by the formwork 19 into the isolated space 20 of the mine working. After the displacement of fire gases through breathable formwork and exposure to the cooling of the hearth in time, from the side of the existing production, the isolated space of the dome is controlled 16

горной выработки через проем трубы пожарной пики 15, после чего пространство купола 16 заполняется быстротвердеющим материалом или пенопластом.mining through the opening of the pipe of the fire lance 15, after which the space of the dome 16 is filled with quick-hardening material or foam.

Предлагаемое техническое решение полезной модели обеспечивает повышение эффективности и безопасности горноспасательных работ, сократил, время воздействия на очаг пожара в уклонной выработке шахты.The proposed technical solution of the utility model provides an increase in the efficiency and safety of mine rescue operations, and reduces the time of exposure to the fire in a mine deviation.

Claims (1)

Устройство тушения пожара в уклонной горной выработке, содержащее пеногенератор и расположенный под ним воздушно-пенный ствол с плоскоструйным насадком, отличающееся тем, что со стороны действующей выработки установлена проемная труба - опалубка перемычки и к ней подсоединена напорная пеногенераторная установка, со стороны изолированного пространства внутри опалубки под проемной трубой установлена поперек выработки перфорированная труба с выводом пенного патрубка в действующую выработку, от дополнительного напорного патрубка проемной трубы, расположенного на стороне изолированного пространства, подсоединен рукав на пожарную пику, внедренную в пожарный купол горной выработки, которой производится заполнение пенной инертной пробкой пространства за двойной перемычкой с последующим вытеснением пожарных газов из купола горной выработки и двойной изолирующей опалубки за пределы аварийного участка.
Figure 00000001
Fire extinguishing device in a sloping mine working area, containing a foam generator and an air-foamy barrel with a flat jet nozzle located under it, characterized in that an opening pipe is installed on the side of the working mine - a lintel formwork and a pressure-generating foam generator is connected to it, from the side of the isolated space inside the formwork a perforated pipe is installed under the opening pipe across the outlet with the foam nozzle being withdrawn to the existing opening, from the additional discharge nozzle I connected a pipe located on the side of the isolated space, a sleeve for the fire lance embedded in the fire dome of the mine, which is filled with an inert foam plug in the space behind the double bridge, followed by the expulsion of the fire gases from the dome of the mine and the double insulating formwork outside the emergency section.
Figure 00000001
RU2008119799/22U 2008-05-19 2008-05-19 FIRE EXTINGUISHING DEVICE IN SLOPING MINING RU76978U1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2008119799/22U RU76978U1 (en) 2008-05-19 2008-05-19 FIRE EXTINGUISHING DEVICE IN SLOPING MINING

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2008119799/22U RU76978U1 (en) 2008-05-19 2008-05-19 FIRE EXTINGUISHING DEVICE IN SLOPING MINING

Publications (1)

Publication Number Publication Date
RU76978U1 true RU76978U1 (en) 2008-10-10

Family

ID=39928198

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2008119799/22U RU76978U1 (en) 2008-05-19 2008-05-19 FIRE EXTINGUISHING DEVICE IN SLOPING MINING

Country Status (1)

Country Link
RU (1) RU76978U1 (en)

Similar Documents

Publication Publication Date Title
CN111734474B (en) Method and equipment for preventing and controlling fire in high-emergence area of coal mine by curing deoxidized clay foam
RU76978U1 (en) FIRE EXTINGUISHING DEVICE IN SLOPING MINING
RU2199667C2 (en) Procedure preventing and suppressing endogenous fires in developed space
CN103691082A (en) Colloid-inhibiting inert foam preparation device and process for preventing coal spontaneous combustion
RU30842U1 (en) Fire extinguishing device in deviation mining
RU2136889C1 (en) Method for fire suppression in dome of mine working
RU2143296C1 (en) General-purpose end locking device of fire-fighting pipeline
Morris A review of experiences on the use of inert gases in mine fires
RU32529U1 (en) Underground fire extinguishing complex
RU30162U1 (en) Complex of isolation and extinguishing of underground fires in hard-to-reach places of mines
RU2094614C1 (en) Active fire-prevention stopping
RU2222699C2 (en) Fire-extinguishing method for endogenous fires into loosened coal massifs
CN106609677A (en) A gas extraction and discharge construction method
RU2061876C1 (en) Device for remote isolation of mine working
SU708061A2 (en) Inflatable partition
RU16936U1 (en) EXTINGUISHING FIRE EXTINGUISHING DEVICE
SU605030A1 (en) Method of fire fighting in mines
RU35656U1 (en) Fire train for the construction of insulating jumpers in the mine
RU35838U1 (en) Energy train for insulating work in mines
RU32197U1 (en) Underground Fire Isolation and Extinguishing System
SU872775A1 (en) Method of creating ice partition and destroying same
RU79944U1 (en) HEADER FOAM GENERATOR UNIT FOR PRODUCING COMBINED INERT FOAM
RU47976U1 (en) HEADER FOAM GENERATOR UNIT FOR PRODUCING COMBINED INERT FOAM
RU2086770C1 (en) Method for isolating and suppressing fire in steep underground working
RU25044U1 (en) INSTALLATION OF INSULATION AND EXTINGUISHING OF UNDERGROUND FIRE IN DIFFICULT ACCESSIBLE MINES

Legal Events

Date Code Title Description
MM1K Utility model has become invalid (non-payment of fees)

Effective date: 20120520