RU133867U1 - TWO-TIER TWO-LEVEL UNIT FOR TEMPORAL DRILLING OF OIL AND GAS WELLS - Google Patents

TWO-TIER TWO-LEVEL UNIT FOR TEMPORAL DRILLING OF OIL AND GAS WELLS Download PDF

Info

Publication number
RU133867U1
RU133867U1 RU2013126996/03U RU2013126996U RU133867U1 RU 133867 U1 RU133867 U1 RU 133867U1 RU 2013126996/03 U RU2013126996/03 U RU 2013126996/03U RU 2013126996 U RU2013126996 U RU 2013126996U RU 133867 U1 RU133867 U1 RU 133867U1
Authority
RU
Russia
Prior art keywords
block
installation
drilling
receiving bridge
bridge
Prior art date
Application number
RU2013126996/03U
Other languages
Russian (ru)
Inventor
Сергей Геннадьевич Бабин
Ренат Фагилевич Миниханов
Андрей Михайлович Бедняков
Original Assignee
Общество с ограниченной ответственностью "Генерация инжиниринг"
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Общество с ограниченной ответственностью "Генерация инжиниринг" filed Critical Общество с ограниченной ответственностью "Генерация инжиниринг"
Priority to RU2013126996/03U priority Critical patent/RU133867U1/en
Application granted granted Critical
Publication of RU133867U1 publication Critical patent/RU133867U1/en

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

1. Двухъярусная двухэшелонная установка для кустового бурения нефтяных и газовых скважин, содержащая вышечно-лебедочный блок и функциональные блоки, скомпонованные в два эшелона, в одном из которых расположен блок циркуляционной системы, а в другом - насосный блок, при этом установка имеет приемный мост со стеллажами для буровых и обсадных труб и направляющие, отличающаяся тем, что установка выполнена двухъярусной, в нижнем ярусе расположены функциональные блоки, а над ними, в верхнем ярусе - приемный мост со стеллажами для буровых и обсадных труб, над приемным мостом расположен грузоподъемный кран для перемещения труб к приемному мосту блоку в направлении, параллельном направляющим.2. Установка по п.1, отличающаяся тем, что в эшелоне блока циркуляционной системы расположен блок дополнительных емкостей бурового раствора.3. Установка по п.1, отличающаяся тем, что в эшелоне насосного блока расположен блок приготовления раствора.4. Установка по п.1, отличающаяся тем, что в начале и конце эшелоне блока циркуляционной системы расположены два независимых друг от друга тепловых модуля.5. Установка по п.1, отличающаяся тем, что стеллажи приемного моста расположены над функциональными блоками, а грузоподъемный кран приемного моста расположен над насосным блоком.1. A two-tier two-level installation for cluster drilling of oil and gas wells, containing a derrick and winch block and functional blocks arranged in two echelons, one of which has a circulation system block, and the other has a pump block, and the installation has a receiving bridge with shelving for drill and casing pipes and guides, characterized in that the installation is two-tiered, functional blocks are located in the lower tier, and above them, in the upper tier, there is a receiving bridge with racks for drilling and casing s pipes, located above the receiving bridge crane to move the pipe to a receiving unit bridge in a direction parallel napravlyayuschim.2. Installation according to claim 1, characterized in that in the echelon of the circulating system block there is a block of additional drilling fluid reservoirs. Installation according to claim 1, characterized in that in the echelon of the pump unit there is a solution preparation unit. Installation according to claim 1, characterized in that at the beginning and end of the echelon of the circulating system unit there are two independent from each other thermal modules. Installation according to claim 1, characterized in that the racks of the receiving bridge are located above the functional blocks, and the lifting crane of the receiving bridge is located above the pump unit.

Description

Полезная модель относится к нефтегазовому оборудованию, и может быть использована для кустового бурения разведочных и эксплуатационных нефтяных и газовых скважин.The utility model relates to oil and gas equipment, and can be used for cluster drilling of exploration and production oil and gas wells.

Для этих целей используют оборудование, содержащее комплексы, предназначенные для выполнения взаимосвязанных функций, называемые функциональными блоками. Так, комплекс для спускоподъемных операций называется вышечно-лебедочный блок, для подачи и хранения труб - приемный мост, для обеспечения циркуляции бурового раствора - блок циркуляционной системы, включающий блок приготовления, очистки и хранения бурового раствора, для подачи бурового раствора - насосный блок, для электроснабжения и управления - блок электрооборудования. Есть еще блоки оборудования для обогрева установки, для транспортировки блоков и модулей, их выравнивания, и другие.For these purposes, use equipment containing systems designed to perform interrelated functions, called functional blocks. So, a complex for hoisting operations is called a hoist block, for supplying and storing pipes - a receiving bridge, for ensuring circulation of a drilling fluid - a block of a circulation system, including a block for preparing, cleaning and storing a drilling fluid, for supplying a drilling fluid - a pump block, power supply and control - electrical equipment block. There are also blocks of equipment for heating the installation, for transporting blocks and modules, leveling them, and others.

Традиционная компоновка блоков оборудования для бурения скважин включает вышечно-лебедочный блок и расположенные за ним последовательно, то есть в «эшелон», функциональные блоки, за исключением приемного моста, стоящего отдельно на земле. Так известна кустовая буровая установка (RU 83280, публ. 27.05.2009 г.) [1], включающая вышечно-лебедочный блок с механизмом перемещения и функциональные блоки с укрытием, а именно: блок циркуляционной системы, насосный блок с буровыми насосами, компрессорный блок, блок электрооборудования, а также блок цементирования скважин и блок обогрева установки. Каждый из функциональных блоков выполнен в виде модулей, содержащих рамы с технологическим оборудованием, модули установлены на двух параллельных направляющих. Система обогрева буровой установки выполнена в виде двух парогенераторов и двух теплогенераторов, связанных трубопроводами с модулями буровой установки. Один из теплогенераторов и один из парогенераторов установлены в вышечно-лебедочном блоке, а другой теплогенератор и другой парогенератор расположены на модуле, установленном между насосным блоком и модулем блока цементировочного насосного агрегата, содержащегося в комплексе оборудования для цементирования скважин.The traditional layout of the blocks of equipment for drilling wells includes a tower block and located behind it sequentially, that is, in the "echelon", functional blocks, with the exception of the receiving bridge, which is separately on the ground. The well-known cluster drilling rig (RU 83280, published May 27, 2009) [1], which includes a derrick and winch block with a movement mechanism and functional blocks with a shelter, namely: a circulation system block, a pump block with mud pumps, a compressor block , electrical equipment unit, as well as cementing unit for wells and heating unit. Each of the functional blocks is made in the form of modules containing frames with technological equipment, the modules are installed on two parallel guides. The heating system of the drilling rig is made in the form of two steam generators and two heat generators connected by pipelines to the modules of the drilling rig. One of the heat generators and one of the steam generators are installed in the winch block, and the other heat generator and the other steam generator are located on the module installed between the pump block and the block module of the cementing pump unit contained in the complex of well cementing equipment.

При такой компоновке основных функциональных блоков оборудования, приемный мост со стеллажами для буровых труб расположен на земле сбоку от эшелона. Направление подачи труб в этом случае перпендикулярно направлению движения установки. При перемещении установки к другой скважине, расположенный таким образом приемный мост приходится демонтировать. Буровая установка с традиционной одноэшелонной компоновкой функциональных блоков занимает большие площади, требует длительного времени на передвижение от одной скважины до другой, требует демонтажа приемного моста при перемещении. Есть и другие недостатки, а именно, значительная длина коммуникаций и связанные с этим потери тепла. Кроме того, работа на мостках приемного моста не механизирована, цикл подачи трубы на устье занимает длительное время.With this arrangement of the main functional blocks of the equipment, the receiving bridge with racks for drill pipes is located on the ground side of the train. The pipe feed direction in this case is perpendicular to the direction of installation movement. When moving the installation to another well, the receiving bridge located in this way has to be dismantled. A drilling rig with a traditional single-layered arrangement of functional blocks occupies large areas, requires a long time to move from one well to another, and requires dismantling the receiving bridge when moving. There are other disadvantages, namely, the significant length of communications and the associated heat loss. In addition, the work on the bridges of the receiving bridge is not mechanized, the pipe feeding cycle at the mouth takes a long time.

Одним из современных направлений в разработке установок для кустового бурения скважин является создание для них более компактных компоновочных схем. Так известна буровая установка (RU 2426854, публ. 20.08.2011 г.) [2], в которой функциональные блоки, выполненные в виде модулей с технологическим оборудованием, скомпонованы в два эшелона с возможностью изменения их взаимного положения. Вся компоновка модулей установлена на четырех направляющих. Компоновка блоков в два эшелона позволяет сократить длины коммуникаций и оптимизировать проходы для удобства обслуживания установки.One of the modern directions in the development of installations for cluster drilling of wells is the creation of more compact layout schemes for them. So the well-known drilling rig (RU 2426854, publ. 08/20/2011) [2], in which functional blocks, made in the form of modules with technological equipment, are arranged in two echelons with the possibility of changing their relative position. The whole layout of the modules is installed on four rails. The arrangement of blocks in two echelons allows to reduce the length of communications and optimize walkways for ease of maintenance.

Приемный мост в известной компоновке смонтирован между рядами модулей оборудования и соединен с вышечно-лебедочным блоком, а стеллажи приемного моста для буровых труб могут быть установлены в любой из рядов компоновки с возможностью соединения с приемным мостом. При таком расположении приемного моста и его стеллажей неизбежны сложности с подачей труб на приемный мост. Доставлять трубы к приемному мосту и стеллажам придется автокраном, т.к. направляющие под модули с оборудованием будут мешать проезду автомобилей. Следует иметь ввиду, что при расположении стеллажей приемного моста между модулями с оборудованием, путь трубы от автомашины до рабочей площадки будет идти по сложной траектории с несколькими изменениями направления движения, и будет достаточно долгим. При подаче на скважину труба должна пройти несколько этапов с поворотами, каждый из которых нужно механизировать, что приведет к увеличению времени спуско-подъемных операций и к повышению сложности и числа механизмов. Могут возникнуть сложности, обусловленные нехваткой вылета стрелы крана для подачи труб к стеллажам.The receiving bridge in the known layout is mounted between the rows of equipment modules and is connected to the winch block, and the receiving bridge racks for drill pipes can be installed in any of the series with the possibility of connecting to the receiving bridge. With this arrangement of the receiving bridge and its racks, difficulties with feeding pipes to the receiving bridge are inevitable. It will be necessary to deliver pipes to the receiving bridge and racks with a truck crane, as guides for modules with equipment will interfere with the passage of cars. It should be borne in mind that when the racks of the receiving bridge are located between the equipment modules, the pipe path from the car to the work platform will follow a complex path with several changes in the direction of movement, and will be quite long. When applying to the well, the pipe must go through several stages with turns, each of which must be mechanized, which will lead to an increase in the time of tripping operations and to increase the complexity and number of mechanisms. Difficulties may arise due to the lack of crane boom extension for feeding pipes to the racks.

Кроме того, при таком расположении приемного моста, поперек него пройдут все трубные и кабельные коммуникации. Это усложняет монтаж, обслуживание и ремонт оборудования, увеличивает длину коммуникаций, и приводит к снижению надежности. При размещении стеллажей приемного моста в модулях разрешенного к перевозке транспортного габарита над стеллажами крайне мало места для работы персонала на мостках. При увеличении габарита возникнут сложности перевозки модулей, при применении съемных крыш - дополнительные монтажные операции и усложнение конструкций.In addition, with such an arrangement of the receiving bridge, all pipe and cable communications will pass across it. This complicates the installation, maintenance and repair of equipment, increases the length of communications, and leads to a decrease in reliability. When placing racks of the receiving bridge in the modules of the transport gauge allowed for transportation over the racks, there is extremely little space for staff to work on the bridges. With an increase in size, there will be difficulties in transporting modules, with the use of removable roofs, additional installation operations and complication of structures.

Известной компоновке блоков оборудования присущи еще следующие недостатки. На указанной в описании к RU 2426854 площади, занимаемой установкой, невозможно разместить более шести емкостей с буровым раствором, одна из которых предназначена для его приготовления. Таким образом, суммарный объем емкостей составит не более 250 куб.м, что соответствует установкам класса 250 т. Эта установка менее производительна по сравнению с заявленной. Условная глубина бурения, обеспечиваемая объемом раствора в известной установке, составляет 4 км, тогда как в заявленной - более 5 км. В известную двухэшелонную компоновку не вписывается система обогрева, что, как и в одноэшелонной установке, предполагает обогрев от котельной и прокладки трассы до нее. Монтаж трассы от котельной в городке бурильщиков до буровой установки приведет к необходимости дополнительных площадей, увеличению длины коммуникаций, увеличению теплопотерь от трассы.The well-known layout of the equipment units inherent in the following disadvantages. It is impossible to place more than six tanks with drilling fluid in the area indicated in the description of RU 2426854, one of which is intended for its preparation. Thus, the total capacity of the tanks will be no more than 250 cubic meters, which corresponds to installations of the class of 250 tons. This installation is less productive than the declared one. The conditional drilling depth provided by the solution volume in the known installation is 4 km, while in the claimed one it is more than 5 km. The heating system does not fit into the well-known two-level layout, which, as in the single-level installation, involves heating from the boiler room and laying the route to it. Installation of the route from the boiler house in the town of drillers to the drilling rig will lead to the need for additional space, an increase in the length of communications, and an increase in heat loss from the route.

Известна кустовая буровая установка (RU 2467146, публ. 20.12.2012 г.) [4], функциональные блоки которой скомпонованы в два эшелона и установлены на 4-х направляющих. Установка содержит блок емкостей для бурового раствора, установленный в одном ряду с блоком циркуляционной системы (ЦС) и компрессорным блоком. В другом ряду от вышечно-лебедочного блока последовательно установлены блок цементирования скважин, блок буровых насосов (НБ) и приемный мост для буровых труб. Предусмотрен и другой вариант расположения блоков в рядах: от вышечно-лебедочного блока последовательно установлены приемный мост для буровых труб, блок буровых насосов и блок цементирования скважин. Блок электрооборудования в этой компоновке может быть установлен между блоком цементирования скважин и блоком буровых насосов. В такой компоновке блок приготовления бурового раствора находится в эшелоне циркуляционной системы, что затрудняет проезд автомашины с реагентами для приготовления к блоку, т.к. при бурении «в амбар» т.е. при наличии рядом с буровой открытого котлована для сброса отработанной породы (шлама) между буровой и амбаром на автомобиле не проехать. Кроме того, через приемный мост идут все коммуникации между ЦС и НБ. Для перегрузки труб на стеллажи необходим автокран, а блок дополнительных емкостей необходимо размещать в стороне от установки.Known cluster drilling rig (RU 2467146, publ. December 20, 2012) [4], the functional blocks of which are arranged in two echelons and installed on 4 rails. The installation contains a block of tanks for drilling fluid, installed in a row with the block of the circulation system (CA) and the compressor block. In a different row from the tower block, a well cementing block, a block of mud pumps (LB) and a receiving bridge for drill pipes are installed in series. There is another option for arranging blocks in rows: a receiving bridge for drill pipes, a block of drilling pumps, and a cementing unit for wells are sequentially installed from the derrick winch block. The electrical unit in this arrangement can be installed between the well cementing unit and the mud pump unit. In this arrangement, the mud preparation unit is located in the echelon of the circulation system, which makes it difficult for a vehicle with reagents to prepare for the unit to travel, because when drilling "into a barn" ie if there is an open foundation pit near the rig to discharge spent rock (sludge) between the rig and the barn, do not drive a car. In addition, all communications between the CA and the NB go through the receiving bridge. To reload the pipes on the shelves, a truck crane is required, and the block of additional tanks must be placed away from the installation.

Задачей заявленного технического решения является создание компактной и надежной компоновочной схемы расположения оборудования для кустового бурения скважин при снижении времени спуско-подъемных операций, упрощении монтажа, обслуживания и ремонта, увеличении объема бурильного раствора.The objective of the claimed technical solution is to create a compact and reliable layout arrangement of equipment for cluster drilling while reducing the time of tripping operations, simplifying installation, maintenance and repair, increasing the volume of drilling fluid.

Для решения поставленной задачи установка для кустового бурения нефтяных и газовых скважин содержит вышечно-лебедочный блок и функциональные блоки, скомпонованные в два эшелона, в одном из которых расположен блок циркуляционной системы, а в другом - насосный блок, установка имеет приемный мост со стеллажами для буровых и обсадных труб и направляющие. Установка отличается тем, что выполнена двухъярусной, в нижнем ярусе расположены функциональные блоки, а над ними, в верхнем ярусе - приемный мост со стеллажами для буровых и обсадных труб, над приемным мостом расположен грузоподъемный кран для перемещения труб к приемному мосту блоку в направлении, параллельном направляющим.To solve this problem, a unit for cluster drilling of oil and gas wells contains a tower hoist and functional blocks arranged in two echelons, in one of which there is a circulation system block and in the other a pump block, the installation has a receiving bridge with racks for drilling and casing and guides. The installation is characterized in that it is made in two tiers, functional blocks are located in the lower tier, and above them, in the upper tier, there is a receiving bridge with racks for drill and casing pipes, a lifting crane is located above the receiving bridge to move the pipes to the receiving bridge in the direction parallel to guides.

В эшелоне блока циркуляционной системы расположен блок дополнительных емкостей бурового раствора, а в эшелоне насосного блока - блок приготовления раствора.A block of additional drilling fluid reservoirs is located in the echelon of the circulating system unit, and in the echelon of the pumping unit is the mud preparation unit.

В начале и конце эшелоне блока циркуляционной системы расположены два независимых друг от друга тепловых модуля.At the beginning and end of the echelon of the circulation system block, two independent thermal modules are located.

Стеллажи приемного моста расположены над функциональными блоками, а грузоподъемный кран приемного моста расположен над насосным блоком.The racks of the receiving bridge are located above the functional blocks, and the lifting crane of the receiving bridge is located above the pumping block.

Двухярусность заявленной установки для кустового бурения скважин позволяет сочетать компактность двухэшелонного расположения функциональных блоков с таким расположением приемного моста со стеллажами для буровых труб и расположенного над ним грузоподъемного крана, которое без дополнительных механизмов ориентировки труб может перемещать трубы к вышечно-лебедочному блоку в направлении, параллельном направлению движения установки. В этом случае повороты трубы при подаче и разгрузке исключены.The two-tier of the claimed installation for cluster drilling of wells allows you to combine the compactness of the two-level arrangement of functional blocks with the location of the receiving bridge with racks for drill pipes and a crane located above it, which without additional pipe orientation mechanisms can move the pipes to the mast winch block in a direction parallel to installation movements. In this case, pipe turns during feeding and unloading are excluded.

Приемный мост, расположенный параллельно движению установки над блоками оборудования нижнего яруса, принимает буровые трубы прямо с транспорта, стоящего параллельно направляющим, что сокращает площади для размещения, а также путь трубы от стеллажа до рабочей площадки и время спуско-подъемных операций. Применение встроенного грузоподъемного крана избавляет от необходимости применять отдельный автокран при разгрузке транспорта с трубами. Более того, такое расположение приемного моста позволяет полностью механизировать подачу труб. Нехватка вылета стрелы для подачи труб к вышечно-лебедочному блоку в этом случае исключена.The receiving bridge, located parallel to the movement of the installation above the lower tier equipment units, receives drill pipes directly from vehicles that are parallel to the guides, which reduces the area for placement, as well as the pipe path from the rack to the work platform and the time of tripping. The use of an integrated crane eliminates the need to use a separate truck crane when unloading vehicles with pipes. Moreover, this arrangement of the receiving bridge allows you to fully mechanize the flow of pipes. The lack of the boom extension for feeding pipes to the winch block is excluded in this case.

Размещенный в эшелоне циркуляционной системы блок дополнительных емкостей для бурового раствора позволяет увеличить его полезный объем без увеличения площади, занимаемой установкой. А блок приготовления бурового раствора, размещенный в эшелоне насосного блока, не затрудняет проезд к нему автомашины с реагентами.A block of additional tanks for drilling mud located in the echelon of the circulation system allows to increase its useful volume without increasing the area occupied by the installation. A drilling fluid preparation unit, located in the echelon of the pump unit, does not impede the passage of vehicles with reagents to it.

Система воздушного обогрева с двумя мощными независимыми тепловыми модулями позволяет создать комфортные климатические условия и ускорить запуск буровой установки в строй после монтажа.An air heating system with two powerful independent thermal modules allows you to create comfortable climatic conditions and accelerate the launch of the rig after installation.

Расположение грузоподъемного крана приемного моста над насосным блоком позволяет использовать этот кран, в том числе, для извлечения и замены насосного оборудования. Расположение стеллажей приемного моста над функциональными блоками, а грузоподъемного крана приемного моста - над насосным блоком, позволяет создать единое просторное помещение, называемое трубным цехом не ограничивая установку в запасе трубы. В заявленной установке предусмотрено размещение до 5 километров обсадной трубы диаметром 178 мм, т.е. полного запаса трубы на условную глубину бурения станка г/п 320 т. При таком размещении стеллажей возможна механизация подачи и раскатывания трубы по стеллажам.The location of the load-lifting crane of the receiving bridge above the pump unit allows the use of this crane, including for removing and replacing pumping equipment. The location of the racks of the receiving bridge over the functional units, and the lifting crane of the receiving bridge over the pump unit, allows you to create a single spacious room, called the pipe shop without restricting the installation in stock pipe. The claimed installation provides for the placement of up to 5 kilometers of casing with a diameter of 178 mm, i.e. the total supply of the pipe to the nominal drilling depth of the machine tool with a loading capacity of 320 tons. With this arrangement of racks, mechanization of the supply and rolling of the pipe into racks is possible.

Таким образом, новый технический результат, достигаемый заявленным решением, заключается в повышении эффективности использования двухэшелонного расположения функциональных блоков установки для кустового бурения скважин, при повышении эффективности работы ее приемного моста.Thus, the new technical result achieved by the claimed solution is to increase the efficiency of using the two -chelon arrangement of the functional units of the installation for cluster drilling of wells, while increasing the efficiency of its receiving bridge.

Полезная модель иллюстрируется следующими рисунками. На фиг.1 изображен общий вид установки; на фиг.2 - то же, без укрытия функциональных блоков и приемного моста; на фиг.3 - двухэшелонное расположение функциональных блоков оборудования.The utility model is illustrated by the following figures. Figure 1 shows a General view of the installation; figure 2 is the same, without sheltering the functional blocks and the receiving bridge; figure 3 - two-echelon arrangement of the functional blocks of the equipment.

Установка содержит вышечно-лебедочный блок 1, снабженный механизмом перемещения и выравнивания (не показан). Один из эшелонов нижнего яруса установки содержит блок циркуляционной системы, содержащий блок очистки бурового раствора 2 и блок емкостей для хранения бурового раствора 3. В этом же эшелоне, называемом эшелоном циркуляционной системы (далее ЦС), расположены блок дополнительных емкостей для бурового раствора 4 и блоки обогрева 5 и 6, стоящие в начале и конце эшелона. В другом эшелоне, называемом эшелоном насосного блока (далее НБ), расположены насосный блок 8 с буровыми насосами (не показаны), блок приготовления бурового раствора 9, блок электрооборудования 10. Приемный мост 11 с встроенным грузоподъемным краном 13 расположен вторым ярусом поверх эшелонов насосного блока и циркуляционной системы. В верхнем ярусе установки смонтирован приемный мост 11 со стеллажами хранения труб 12, который служит для выполнения операций, связанных с подачей бурильных и обсадных труб на буровую площадку и хранением запаса труб. Над приемным мостом 11 смонтирован грузоподъемный кран 13. Все блоки, включая приемный мост и стеллажи, имеют жесткое утепленное укрытие 14.The installation comprises a tower hoist 1 equipped with a movement and leveling mechanism (not shown). One of the echelons of the lower tier of the installation contains a circulating system unit containing a drilling fluid cleaning unit 2 and a block of reservoirs for storing drilling fluid 3. In the same echelon, called a circulating system echelon (hereinafter CC), there are a block of additional reservoirs for drilling mud 4 and blocks heating 5 and 6, standing at the beginning and end of the train. In another echelon, called the echelon of the pump unit (hereinafter NB), there are a pump unit 8 with mud pumps (not shown), a mud preparation unit 9, an electrical equipment unit 10. A receiving bridge 11 with an integrated crane 13 is located on the second tier over the echelons of the pump unit and circulation system. In the upper tier of the installation, a receiving bridge 11 with pipe storage racks 12 is mounted, which serves to perform operations related to the supply of drill and casing pipes to the drilling site and storage of pipe stock. A load-lifting crane 13 is mounted above the receiving bridge 11. All units, including the receiving bridge and racks, have a rigid insulated shelter 14.

Функциональные блоки выполнены в виде соединенных с коммуникациями модулей. Система коммуникаций включает трубопроводы пара, воды, воздуха, бурового раствора и другие. Соединение всех коммуникаций установки осуществляется при монтаже. Блоки соединены коммуникациями таким образом, чтобы свести к минимуму работы по монтажу, осуществляемые на площадке месторождения.Function blocks are made in the form of modules connected to communications. The communication system includes pipelines of steam, water, air, drilling mud and others. The connection of all communications of the installation is carried out during installation. The blocks are connected by communications in such a way as to minimize installation work carried out at the field site.

Кабельные и трубные гидравлические трассы проложены в силовых металлоконструкциях с помощью специальных лотков и не требуют прокладки после монтажа. Основные кабельные трассы проложены под эшелонами в лотках, смонтированных на балках механизма перемещения. Время монтажа комплекса сокращено за счет максимальной готовности модулей и их компоновки в два ряда, прокладки кабелей в лотках, применения быстроразъемных соединений кабельных и трубных трасс, жестких быстромонтируемых укрытий.Cable and pipe hydraulic routes are laid in power metal structures using special trays and do not require laying after installation. The main cable routes are laid under the trains in trays mounted on the beams of the movement mechanism. The installation time of the complex is reduced due to the maximum availability of the modules and their arrangement in two rows, the laying of cables in the trays, the use of quick-disconnect connections of cable and pipe routes, rigid quick-mounted shelters.

Установка смонтирована на по четырех направляющих 15.The installation is mounted on four guides 15.

Заявленная установка работает следующим образом. Автомобиль с трубами, связанными в пачку, подъезжает, встает параллельно эшелону насосного блока, останавливается в зоне работы крана 13. Оператор, управляя краном с пульта, поднимает пачку труб параллельно направлению движению буровой установки на уровень стеллажей 12. Далее возможна выгрузка (раскатывание) на стеллажи для подачи труб или для их хранения. Раскатывание трубы на стеллажах трубы механизировано. Передача труб со стеллажей на рабочую площадку и обратно на стеллажи, полностью механизирована. Система подачи работает на сжатом воздухе, гидравлика исключена для повышения надежности системы и отказа от дорогих рабочих жидкостей.The claimed installation works as follows. A car with pipes connected in a pack drives up, stands parallel to the echelon of the pump unit, stops in the area of crane operation 13. The operator, controlling the crane from the console, raises the pipe stack parallel to the direction of movement of the drilling rig to the level of racks 12. Further, unloading (rolling) is possible racks for feeding pipes or for storing them. Pipe rolling on pipe racks is mechanized. The transfer of pipes from the racks to the work platform and back to the racks is fully mechanized. The feed system operates on compressed air, hydraulics are excluded to increase the reliability of the system and the rejection of expensive working fluids.

При необходимости извлечь части бурового насоса для ремонта или замены трубы со стеллажей снимаются или сдвигаются на другую половину, часть крыши насосного блока снимается при помощи крана 13, насос извлекается и подается наружу на транспорт. Необходимости в автокране нет, транспорт задействован только на время погрузки-разгрузки.If necessary, remove parts of the mud pump for repair or replacement of pipes from the shelves are removed or shifted to the other half, part of the roof of the pump unit is removed using a crane 13, the pump is removed and fed outside to the vehicle. There is no need for a truck crane, transport is involved only during loading and unloading.

В процессе бурения установку перемещают при помощи встроенного механизма перемещения по направляющим 15 от одной скважины куста к другой.During drilling, the installation is moved using the built-in movement mechanism along the guides 15 from one well of the bush to another.

Таким образом, заявленная двухярусная установка для кустового бурения скважин с двухэшелонным расположением функциональных блоков технологического оборудования, является компактной и надежной, позволяет снизить время спуско-подъемных операций, упростить и ускорить монтаж, обслуживание и ремонт оборудования, увеличить объем бурового раствора. В совокупности это позволяет сэкономить значительные средства на бурение скважин по сравнению с аналогами.Thus, the claimed two-tier installation for cluster drilling of wells with a two-echelon arrangement of functional units of technological equipment is compact and reliable, it allows to reduce the time of tripping, simplify and speed up the installation, maintenance and repair of equipment, increase the volume of drilling fluid. Together, this saves significant funds for drilling wells compared to peers.

Claims (5)

1. Двухъярусная двухэшелонная установка для кустового бурения нефтяных и газовых скважин, содержащая вышечно-лебедочный блок и функциональные блоки, скомпонованные в два эшелона, в одном из которых расположен блок циркуляционной системы, а в другом - насосный блок, при этом установка имеет приемный мост со стеллажами для буровых и обсадных труб и направляющие, отличающаяся тем, что установка выполнена двухъярусной, в нижнем ярусе расположены функциональные блоки, а над ними, в верхнем ярусе - приемный мост со стеллажами для буровых и обсадных труб, над приемным мостом расположен грузоподъемный кран для перемещения труб к приемному мосту блоку в направлении, параллельном направляющим.1. A two-tier two-level installation for cluster drilling of oil and gas wells, containing a derrick and winch block and functional blocks arranged in two echelons, one of which has a circulation system block, and the other has a pump block, and the installation has a receiving bridge with shelving for drill and casing pipes and guides, characterized in that the installation is two-tiered, functional blocks are located in the lower tier, and above them, in the upper tier, there is a receiving bridge with racks for drilling and casing s pipes, located above the receiving bridge crane to move the pipe to a receiving unit bridge in a direction parallel to the guide. 2. Установка по п.1, отличающаяся тем, что в эшелоне блока циркуляционной системы расположен блок дополнительных емкостей бурового раствора.2. Installation according to claim 1, characterized in that in the echelon of the circulating system block there is a block of additional drilling fluid reservoirs. 3. Установка по п.1, отличающаяся тем, что в эшелоне насосного блока расположен блок приготовления раствора.3. Installation according to claim 1, characterized in that in the echelon of the pump unit is located the block for the preparation of the solution. 4. Установка по п.1, отличающаяся тем, что в начале и конце эшелоне блока циркуляционной системы расположены два независимых друг от друга тепловых модуля.4. Installation according to claim 1, characterized in that at the beginning and end of the echelon of the circulating system unit there are two independent from each other thermal modules. 5. Установка по п.1, отличающаяся тем, что стеллажи приемного моста расположены над функциональными блоками, а грузоподъемный кран приемного моста расположен над насосным блоком.
Figure 00000001
5. Installation according to claim 1, characterized in that the racks of the receiving bridge are located above the functional blocks, and the lifting crane of the receiving bridge is located above the pump block.
Figure 00000001
RU2013126996/03U 2013-06-13 2013-06-13 TWO-TIER TWO-LEVEL UNIT FOR TEMPORAL DRILLING OF OIL AND GAS WELLS RU133867U1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
RU2013126996/03U RU133867U1 (en) 2013-06-13 2013-06-13 TWO-TIER TWO-LEVEL UNIT FOR TEMPORAL DRILLING OF OIL AND GAS WELLS

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
RU2013126996/03U RU133867U1 (en) 2013-06-13 2013-06-13 TWO-TIER TWO-LEVEL UNIT FOR TEMPORAL DRILLING OF OIL AND GAS WELLS

Publications (1)

Publication Number Publication Date
RU133867U1 true RU133867U1 (en) 2013-10-27

Family

ID=49447086

Family Applications (1)

Application Number Title Priority Date Filing Date
RU2013126996/03U RU133867U1 (en) 2013-06-13 2013-06-13 TWO-TIER TWO-LEVEL UNIT FOR TEMPORAL DRILLING OF OIL AND GAS WELLS

Country Status (1)

Country Link
RU (1) RU133867U1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2672892C2 (en) * 2016-04-29 2018-11-20 Мухтар Зуфарович Валитов Cluster driller
RU2693981C1 (en) * 2018-04-16 2019-07-08 Акционерное Общество "Урало-Сибирская Промышленная Компания" Two environmental-friendly drilling rig in arctic design

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2672892C2 (en) * 2016-04-29 2018-11-20 Мухтар Зуфарович Валитов Cluster driller
RU2693981C1 (en) * 2018-04-16 2019-07-08 Акционерное Общество "Урало-Сибирская Промышленная Компания" Two environmental-friendly drilling rig in arctic design

Similar Documents

Publication Publication Date Title
US20190218868A1 (en) Wellbore drilling system
US20110240371A1 (en) Drilling Station
CN106794889B (en) Seabed drilling operation ship
CN205259938U (en) Anchor rod drilling carriage of four arms group
CN107553687B (en) The house 3D printer
US20220025708A1 (en) Electrically-powered drilling rig and method for operating thereof
CN104005583A (en) Gantry-type three-dimensional parking system and parking and pick-up method thereof
EP2173964A1 (en) Drilling tower device and drilling machine system
RU133867U1 (en) TWO-TIER TWO-LEVEL UNIT FOR TEMPORAL DRILLING OF OIL AND GAS WELLS
CN204532126U (en) Supporting platform module drilling machine
US8381480B2 (en) Dual offset derrick
RU116558U1 (en) COMPACT SPEED DRILLING RIG
US10086917B2 (en) Drilling vessel and method for operating a drilling vessel adapted to run large diameter casing strings
CN201953323U (en) Novel catwalk for module drilling machine of marine oil drilling platform
NO320287B1 (en) Well system and method for forming a well system
CN216892336U (en) Unmanned well head platform that stays with formula of salvaging well repair area
RU2693981C1 (en) Two environmental-friendly drilling rig in arctic design
RU97160U1 (en) COMPACT ECHELON OF A DRILL DRILLING RIG
CN210313200U (en) Hoisting system for installing shaft pressure steel pipe
RU83280U1 (en) PIT DRILLING RIG
CA2738196C (en) Drilling rig for deep well drilling
CN105178875A (en) Quick moving and assembling rig
CN108798560A (en) A kind of dynamic rathole is unloaded upright post system and column method of unloading offline
US10711539B1 (en) Modular drilling rig having pipe lifting capability and ventilation therein
CN104653114A (en) Integrated petroleum drill base

Legal Events

Date Code Title Description
MM9K Utility model has become invalid (non-payment of fees)

Effective date: 20170614