NO20170041A1 - Combined module handling and Crane system. - Google Patents

Combined module handling and Crane system. Download PDF

Info

Publication number
NO20170041A1
NO20170041A1 NO20170041A NO20170041A NO20170041A1 NO 20170041 A1 NO20170041 A1 NO 20170041A1 NO 20170041 A NO20170041 A NO 20170041A NO 20170041 A NO20170041 A NO 20170041A NO 20170041 A1 NO20170041 A1 NO 20170041A1
Authority
NO
Norway
Prior art keywords
crane
module handling
pedestal
guide tracks
cursor
Prior art date
Application number
NO20170041A
Other languages
Norwegian (no)
Other versions
NO343492B1 (en
Inventor
Ivar Bjørnevik
Original Assignee
Rolls Royce Marine As
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rolls Royce Marine As filed Critical Rolls Royce Marine As
Priority to NO20170041A priority Critical patent/NO343492B1/en
Priority to PCT/NO2018/050006 priority patent/WO2018132016A1/en
Publication of NO20170041A1 publication Critical patent/NO20170041A1/en
Publication of NO343492B1 publication Critical patent/NO343492B1/en

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/18Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
    • B66C23/36Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes mounted on road or rail vehicles; Manually-movable jib-cranes for use in workshops; Floating cranes
    • B66C23/52Floating cranes
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/16Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes with jibs supported by columns, e.g. towers having their lower end mounted for slewing movements
    • B66C23/163Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes with jibs supported by columns, e.g. towers having their lower end mounted for slewing movements where only part of the column rotates, i.e. at least the bottom part is fixed
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B27/00Arrangement of ship-based loading or unloading equipment for cargo or passengers
    • B63B27/10Arrangement of ship-based loading or unloading equipment for cargo or passengers of cranes
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B1/00Control systems of elevators in general
    • B66B1/02Control systems without regulation, i.e. without retroactive action
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/04Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
    • B66C13/06Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for minimising or preventing longitudinal or transverse swinging of loads
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C7/00Runways, tracks or trackways for trolleys or cranes
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C7/00Runways, tracks or trackways for trolleys or cranes
    • B66C7/12Devices for changing direction of travel or for transferring from one runway to another; Crossings; Combinations of tracks of different gauges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B25/00Tracks for special kinds of railways
    • E01B25/30Tracks for magnetic suspension or levitation vehicles
    • E01B25/32Stators, guide rails or slide rails
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B27/00Arrangement of ship-based loading or unloading equipment for cargo or passengers
    • B63B27/30Arrangement of ship-based loading or unloading equipment for transfer at sea between ships or between ships and off-shore structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Ocean & Marine Engineering (AREA)
  • Automation & Control Theory (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Jib Cranes (AREA)
  • Control And Safety Of Cranes (AREA)

Abstract

Combined module handling and crane system on a vessel (10), comprising a crane pedestal (22) placed on a deck (12) of the vessel (10), wherein said crane pedestal (22) is equipped with a top mounted and swingable crane (20), and a side mounted and vertically skidable module handling support cursor (30).Combined module handling and crane system on a vessel (10), comprising a crane pedestal (22) placed on a deck (12) of the vessel (10), said crane pedestal (22) is equipped with a top mounted and swingable crane (20), and a side mounted and vertically skidable module handling support cursor (30).

Description

TITLE: Combined module handling and crane system.
Field of the invention
The present invention relates to a combined module handling and crane system on a vessel.
Background of the invention.
Handling of modules offshore can have several challenges, different operations and the present invention will increase the choice and flexibility of how to handle different structures from the ship, through stacking together different modules and installing them in a more efficient way than the industry today do. The present invention will be a great step in simplification of the number of needed systems onboard a vessel to be able to compete on a series of different jobs on one vessel instead of the need for several specialized vessels, without compromising the functionality of the job to be done. Also installing running tools and do maintenance on the subsea structures can be handled in a good way by the intervention
Objects of the present invention
The crane is widely used in the marked and also ideas of using module handling in crane positions are presented by other suppliers, but the combination of crane and module handling system in the same unit is new. This combination will give a unique flexibility in building, testing and installing equipment, where all or parts of the work could be done with the crane or with the module handling system.
An object is therefore to provide a new and improved combination of a crane and a module handling system.
Summary of the invention
A combined module handling and crane system on a vessel, according to the present invention, comprises a crane pedestal placed on a deck of the vessel, wherein said crane pedestal is equipped with a top mounted and swingable crane, and a side mounted and vertically skidable module handling support cursor.
The support cursor can be skidable on upright guide tracks on the crane pedestal, in where the support cursor is elevated and lowered on said guide tracks.
The support cursor may be a vertically skidable support platform for carrying subsea equipment for assembly of modules on deck and module installation or intervention subsea.
The crane pedestal can comprise a fixed lower part with a plurality of guide tracks, said guide tracks being placed upright and with a fixed distance on or around the lower part of the crane pedestal.
The crane pedestal may further comprise a swingable upper part with a plurality of guide tracks, said guide tracks being placed in a similar manner upright and with a fixed distance on or around the upper part of the crane pedestal.
The vertically skidable module handling support cursor can travel from a first pair of guide tracks on the crane pedestal's fixed lower part to a pair of guide tracks on the crane pedestal's swingable upper part, and after rotation of the swingable upper part of the crane pedestal and alignment of the guide tracks on the swingable upper part with a second pair of guide tracks on the lower part, the module handling support cursor can travel down on said second pair of guide tracks. The movement pattern may of course be reversed.
The second pair of guide tracks on the crane pedestal's fixed lower part can be aligned and connected with a pair of guide tracks mounted vertically on a hull side of the vessel, and the module handling cursor can be deployed on the guide tracks on the hull side of the vessel to the water level or through the splash zone.
The top mounted crane is preferable placed on top of the swingable upper part of the crane pedestal.
The crane pedestal, with the top mounted crane and the side mounted and vertically skidable module handling support cursor, is swingable about a central rotation point.
The crane pedestal can be equipped with one or more guide wire winches and a rope routing sheave for deployment or retrieval of subsea equipment to the ocean floor. The crane pedestal may further be equipped with a cursor winch for vertical movement of the skidable module handling support cursor.
The swingable upper part can be mounted on a slewing ring to the fixed lower part of the crane pedestal. It is also possible that the crane is mounted on a slewing ring on the swingable upper part of the crane pedestal.
Description of the diagrams
Embodiments of the present invention will now be described, by way of example only, with reference to the following diagrams wherein:
Figure 1 shows a combined module handling and crane system on a vessel, with a module handling system in a lower building position.
Figure 2 shows the combined module handling and crane system, with the module handling system in an upper building position.
Figure 3 shows the combined module handling and crane system, with the module handling system in an upper installation position.
Figure 4 shows the combined module handling and crane system, with the module handling system in a lower installation position.
Figure 5 shows a module handling support cursor, being part of the combined module handling and crane system
Figure 6 shows an upper part of a crane pedestal and a crane, being part of the combined module handling and crane system.
Description of preferred embodiments of the invention
The present invention relates to a combined module handling and crane system on a vessel 10. The vessel 10 is only partially shown in the drawings. Rails 16 for normal movement of modules and equipment can be placed on a deck 12 of the vessel 10, along with equipment for assembly of modules on the deck 12. On the same deck 12 is a pedestal 22 with a crane 20 placed. The crane 20 can be of any type of lifting crane, and the crane is only schematically shown in the drawings.
The pedestal 22 is equipped with a top mounted and swingable crane 20, and a side mounted and vertically skidable module handling support cursor 30. Said pedestal further comprises a fixed lower part 22b and a swingable or rotatable upper part 22a. The upper part 22a can be mounted to the lower part 22b on a slewing ring, to allow rotation of the upper part 22a in relation to the lower part 22b.
The lower fixed part 22b of the pedestal 22 comprises a plurality of tracks 40 placed upright, preferably at least two pair of tracks 40. As shown in for instance figure 1 there is a first pair of tracks 40 facing the deck 12 of the vessel 10, which the support cursor 30 is connected to, and a second pair of tracks 40 facing the hull side 14 of the vessel 10. The lower fixed part 22b may comprise further pair of tracks 40 on the sides not visible on the drawings. The tracks 40 are placed with a fixed distance to each other.
The upper swingable part 22a of the pedestal 22 also comprises several tracks 42 placed upright, at least one pair of tracks. Said tracks 42 on the upper part 22a are placed with the same fixed distance as the pair of tracks 40 on the lower part 22b, and thus the tracks 42 on the upper part 22a are aligned with the pair of tracks 40 on the lower part 22b when the upper part 22a is rotated in correct position. Another pair of tracks 44 can be placed upright on the hull side 14 of the vessel, in where the tracks 44 on the hull side 14 are placed with the same fixed distance as the pair of tracks 40 on the lower part 22b, thus being are aligned with the pair of tracks 40 on the lower part 22b.
The crane pedestal 22 may further be equipped with a guide wire winch 24 and a rope routing sheave 26 for deployment of subsea equipment to the ocean floor. The guide wire winch 24 and the rope routing sheave 26 are preferable mounted on the upper swingable part 22a. The crane pedestal 22 may further be equipped with a separate cursor winch for vertical movement of the skidable module handling support cursor 30. The cursor winch is likewise preferable mounted on the upper swingable part 22a.
The upper part 22a of the pedestal 22 can be mounted on a slewing ring to the fixed lower part 22b in order to be able to rotate. It is also possible that the crane 20 is mounted to the upper part 22b of the pedestal 22 by a slewing ring. An advantage is that the crane 20 can swing without moving/swinging the cursor 30.
MHS – module handling system comprises the module handling support cursor 30 which is a vertically skidable support platform to support subsea equipment for module building and assembly of modules on deck and module installation or intervention subsea, i.e. to support subsea structure during assembly/testing/ stacking, handling around crane pedestal and through splash zone. The main function for the cursor is to avoid the stack pendulum movement due to the vessel motion and to ensure a safe handling of the stack from deck and through splash zone.
The support cursor 30 can travel from the tracks 40 on the fixed lower part 22b of the pedestal 22 and to the tracks 42 on the upper part 22a on the pedestal 22. The support cursor can also travel from the tracks 42 on the upper part 22a of the pedestal 22 and to the tracks 44 on the hull side 14 of the vessel 10.The movement pattern may of course be reversed.
The tracks 40,42,44 can be of any kind of guide tracks, and the support cursor 30 can be equipped with wheels, rollers, or other rolling or gliding units.
Figures 1-4 show a typical movement pattern of the support cursor 30. In figure 1 the module handling system, i.e. the cursor 30, is parked in a lower building position. In figure 2 the cursor 30 has moved on the tracks 40 on the lower part 22b to the tracks 42 on the upper part 22a of the pedestal 22 and is in an upper building position. In figure 3 the upper part 22a of pedestal 22 has rotated 90° and the cursor 30 is in an upper installation position. Figure 4 shows the module handling system in a lower installation position, in where the support cursor 30 has traveled from the tracks 42 on the upper part 22, past the tracks 42 on the lower part 22b of the pedestal 22, and down the tracks 44 on the hull side 14 of the vessel 10 for performing module installation or intervention subsea. The crane 20 may assist in any part of the operation.
The present invention has integrated several known function into the same device. During normal crane operations the cursor system may be parked in building position. Module building and testing position. Module installation or other operations done from a tower.
During normal crane operations the crane has full operation ability as a normal crane, and can perform lifting from deck, pallet or other vessel. Use the normal crane swing to position the lifted equipment. Normal crane launch through splash zone. Normal installation to sea bottom, and retrieval opposite than above.
Module building position is shown in figure 1 and 2. During module installation a building and or testing location is often required to assemble sub-modules to running tools. One or more dedicated position to build/stack together modules using the cursor 30 along the crane pedestal 22. Skidding of modules to this position is possible, for instance on the rails 16 on the deck 12 of the vessel 10. Potential for testing of modules prior to installations may be applied. Building can be done with crane winch or dedicated cursor winch.
Module installation is shown in figure 3 and 4. Normal module handling lift operations, installing the stacked object from pick up point from pallet on deck 12. Lifting the module from the pallet supported by the cursor 30. Swinging the module to it's overside position (still using the cursor 30 to secure the load). Deploy the module through the splash zone supported with the cursor 30. Cursor supported installations over side of the vessel. Guide wires may be integrated and used if required. Module installation can be done with the crane winch or with separate main winch.
The module handling system, i.e. the cursor 30, can also be used for well intervention and plug and abandonment work.

Claims (14)

Claims
1. Combined module handling and crane system on a vessel (10), comprising a crane pedestal (22) placed on a deck (12) of the vessel (10), wherein said crane pedestal (22) is equipped with a top mounted and swingable crane (20), and a side mounted and vertically skidable module handling support cursor (30).
2. Combined module handling and crane system according to claim 1, wherein the support cursor (30) is skidable on upright guide tracks (40,42) on the crane pedestal (22).
3. Combined module handling and crane system according to claim 2, wherein the support cursor (30) is elevated and lowered on said guide tracks (40,42).
4. Combined module handling and crane system according to claim 1, wherein the support cursor (30) is a vertically skidable support platform for carrying subsea equipment for assembly of modules on deck (12) and module installation or intervention subsea.
5. Combined module handling and crane system according to claim 1, wherein said crane pedestal (22) comprises a fixed lower part (22b) with a plurality of guide tracks (40), said guide tracks (40) being placed upright and with a fixed distance on the lower part (22b) of the crane pedestal (22).
6. Combined module handling and crane system according to claim 1, wherein said crane pedestal (22) comprises a swingable upper part (22a) with a plurality of guide tracks (42), said guide tracks (42) being placed upright and with a fixed distance on the upper part (22a) of the crane pedestal (22).
7. Combined module handling and crane system according to claim 5 and 6, wherein the vertically skidable module handling support cursor (30) can travel from a first pair of guide tracks (40) on the crane pedestal's (22) fixed lower part (22b) to a pair of guide tracks (42) on the crane pedestal's (22) swingable upper part (22a), and after rotation of the swingable upper part (22a) of the crane pedestal (22) and alignment of the guide tracks (42) on the swingable upper part (22a) with a second pair of guide tracks (40) on the lower part (22b), the module handling support cursor (30) can travel down on said second pair of guide tracks (40).
8. Combined module handling and crane system according to claim 7, wherein said second pair of guide tracks (40) on the crane pedestal's (22) fixed lower part (22b) are aligned and connected with a pair of guide tracks (44) mounted vertically on a hull side (14) of the vessel (10), and the module handling cursor (30) can be deployed on the guide tracks (44) on the hull side (14) of the vessel (10) to the water level or through the splash zone.
9. Combined module handling and crane system according to claim 6, wherein the top mounted crane (20) is placed on top of the swingable upper part (22a) of the crane pedestal (20).
10. Combined module handling and crane system according to claim 1, wherein the crane pedestal (22), with the top mounted crane (20) and the side mounted and vertically skidable module handling support cursor (30), is swingable about a central rotation point.
11. Combined module handling and crane system according to claim 1, wherein the crane pedestal (22) is equipped with one or more guide wire winches (24) and a rope routing sheave (26) for deployment or retrieval of subsea equipment to the ocean floor.
12. Combined module handling and crane system according to claim 1, wherein the crane pedestal (22) is equipped with a cursor winch for vertical movement of the skidable module handling support cursor (30).
13. Combined module handling and crane system according to claim 1, wherein said crane pedestal (22) comprises a fixed lower part (22b) and a swingable upper part (22a) mounted on a slewing ring.
14. Combined module handling and crane system according to claim 1, wherein said crane pedestal (22) comprises a fixed lower part (22b) and a swingable upper part (22a), in where the crane (20) is mounted on a slewing ring on the swingable upper part (22a).
NO20170041A 2017-01-10 2017-01-10 Combined module handling and Crane system. NO343492B1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
NO20170041A NO343492B1 (en) 2017-01-10 2017-01-10 Combined module handling and Crane system.
PCT/NO2018/050006 WO2018132016A1 (en) 2017-01-10 2018-01-09 Combined module handling and crane system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
NO20170041A NO343492B1 (en) 2017-01-10 2017-01-10 Combined module handling and Crane system.

Publications (2)

Publication Number Publication Date
NO20170041A1 true NO20170041A1 (en) 2018-07-11
NO343492B1 NO343492B1 (en) 2019-03-25

Family

ID=62840224

Family Applications (1)

Application Number Title Priority Date Filing Date
NO20170041A NO343492B1 (en) 2017-01-10 2017-01-10 Combined module handling and Crane system.

Country Status (2)

Country Link
NO (1) NO343492B1 (en)
WO (1) WO2018132016A1 (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016175652A1 (en) * 2015-04-28 2016-11-03 Itrec B.V. Offshore vessel, marine pipeline installation system and method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016175652A1 (en) * 2015-04-28 2016-11-03 Itrec B.V. Offshore vessel, marine pipeline installation system and method

Also Published As

Publication number Publication date
NO343492B1 (en) 2019-03-25
WO2018132016A1 (en) 2018-07-19

Similar Documents

Publication Publication Date Title
CN100537348C (en) Offshore platform integral constructing and hoisting method and special-purpose hoisting machine for the same
CN111807239B (en) Crane, vessel comprising such a crane and method for erecting a longitudinal structure
CN104527937B (en) Marine wind turbine whole machine is transported with installing special purpose ship and method
US4269542A (en) Jack-up rig for marine drilling
US10870467B2 (en) Offshore material handling system and material handling method
CN202765242U (en) Accommodation ladder device for arriving at or leaving fixed offshore platform
US9359047B2 (en) Mobile barge and method of operation of mobile barge
US20150217838A1 (en) Method for lowering and hoisting of a load to or from an ocean floor
CN101870435B (en) Overturned hoisting method for helicopter platform
EP3442895B1 (en) Deck hoist tractor, rescue chute and tote tank
CN103174093A (en) Mounting device and mounting method of steel box girder in support zone
US8757954B1 (en) Maritime transfer system
US9945114B2 (en) System and method for the rapid installation of a portable building in a confined vertically inaccessible location
CN104234636A (en) Installation method for self-elevating platform derrick
KR101592922B1 (en) Electrical telescopic system for accommodation ladder
US9695565B2 (en) Jackup pedestal crane installation and operation, movable along a guide
NO20170041A1 (en) Combined module handling and Crane system.
CN107487724B (en) Non-crane-assisted large floating crane arm support mounting device and mounting method
NO20181130A1 (en) Kombinert modulhåndtering- og kransystem
US11560205B2 (en) Lifting system for a floating vessel
US20180099843A1 (en) Drilling, plug, abandonment, and decommissioning
CN106379495A (en) Wharf pile foundation underwater maintenance operation device with self-propulsion capability
CN105883614A (en) Method for hoisting gantry crane main beam through single equipment in eccentrically loaded mode
CN206125353U (en) Pier pile foundation underwater maintenance operation device with self -navigation ability
CN103626041A (en) Crane for wharf construction and component erection method thereof

Legal Events

Date Code Title Description
CHAD Change of the owner's name or address (par. 44 patent law, par. patentforskriften)

Owner name: KONGSBERG MARITIME CM AS, NO

MM1K Lapsed by not paying the annual fees