Prior art keywords
slope
drainage plate
fixing
greening
plate
Prior art date
Application number
KR1020200119052A
Other languages
Korean (ko)
Inventor
김범진
Original Assignee
김범진
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김범진 filed Critical 김범진
Priority to KR1020200119052A priority Critical patent/KR20220036623A/en
Publication of KR20220036623A publication Critical patent/KR20220036623A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/202Securing of slopes or inclines with flexible securing means
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G24/00Growth substrates; Culture media; Apparatus or methods therefor
    • A01G24/10Growth substrates; Culture media; Apparatus or methods therefor based on or containing inorganic material
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G24/00Growth substrates; Culture media; Apparatus or methods therefor
    • A01G24/20Growth substrates; Culture media; Apparatus or methods therefor based on or containing natural organic material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/122Flexible prefabricated covering elements, e.g. mats, strips
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0085Geotextiles
    • E02D2300/0089Geotextiles non-woven

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Inorganic Chemistry (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Cultivation Of Plants (AREA)

Abstract

The present invention relates to a slope greening construction method of a cut slope area, wherein a problem of slope greening loss is resolved by providing a drainage function. The method comprises the following steps of: installing a drainage plate on a surface of the cut slope area or the slope surface; installing a fixing net body on an upper surface of the drainage plate; fixing the drainage plate and the fixing net body by using a fixing pin; and installing a slope greening member. The drainage plate is formed with an uneven protrusion protruding from a bottom surface vertically and horizontally, and allows running water to pass through a space between the ground and the drainage plate.

Description

사면절개구역의 사면녹화 시공방법{Construction Methods For Slope Tree-Planting For Slope Area By Cutting}Construction Methods For Slope Tree-Planting For Slope Area By Cutting}

본 발명은 사면녹화 시공방법에 관한 것이며, 좀 더 구체적으로는 배수기능을 가짐으로써 사면녹화의 유실 문제를 해소한 사면절개구역의 사면녹화 시공방법에 관한 것이다. The present invention relates to a slope greening construction method, and more particularly, to a slope greening construction method in a slope incision area, which has a drainage function, thereby solving the problem of slope greening loss.

우리나라는 산악지형이 많다보니 각종 건설이나 토목시공에 의해 절개구역이 많이 생기게 된다. 사면절개구역은 사태의 위험을 갖고 있는 것이어서 이러한 사고를 방지하기 위하여 다양한 시공법이 존재해 왔었다. 사태의 방지를 위한 것과는 별도로 사면절개구역은 미관상 좋지 못하기 때문에 사면녹화작업을 시행하기도 한다. 특히 도심지에 있는 사면절개구역은 녹화작업이 더욱 필요시 된다. Since Korea has a lot of mountainous terrain, many incision areas are created by various constructions or civil engineering works. Since the slope incision area has a risk of avalanche, various construction methods have existed to prevent such accidents. Apart from the prevention of avalanche, slope greening work is sometimes implemented because the slope incision area is not aesthetically pleasing. In particular, the slope incision area in the city center requires more greening work.

사면녹화의 방법중 하나로서 녹생토를 이용하는 방법이 있다. 녹생토 시공방법은 사면녹화를 암반지역과 같이 흙이 없는 지역에 하수슬러지를 두껍게 뿌림으로써 그로 하여금 흙과 거름 역할을 하도록 하여 풀이 잘 생육하도록 하는 방식이다. 녹생토의 고정을 위하여 코아넷 또는 철망을 사면에 미리 고정시킨다. As one of the methods of reforestation, there is a method using green soil. The green soil construction method is a method of thickly sprinkling sewage sludge in an area without soil such as a bedrock area by greening the slope, allowing it to act as soil and manure so that weeds can grow well. For fixing the green soil, fix the corenet or wire mesh on the slope in advance.

그러나 척박한 사면의 특성상 녹생토가 완전히 정착하기 이전에 사면과 녹생토 사이에 빗물이 스며드는 경우에는 녹생토가 유실되는 경우가 종종 생긴다. 그러면 절개사면 아래 부분이 흘러내린 사면녹화에 의해 덮여지게 되며, 공사했던 구간은 위에서 아래로 길게 도랑이 패이게 됨으로써 재공사를 하여야 했다. However, due to the nature of the barren slope, green soil is often lost if rainwater seeps between the slope and green soil before the green soil is completely settled. Then, the lower part of the incised slope will be covered by the flowing greening, and the section that was constructed had to be reconstructed as a long trench was dug from top to bottom.

비단 녹생토 뿐만 아니라 다른 형태의 사면녹화 공법에도 위와 같은 문제가 상존하였다. The above problem existed not only in silk green soil, but also in other types of slope reforestation methods.

대한민국 특허출원 제10-2017-0052092호Korean Patent Application No. 10-2017-0052092 대한민국 특허출원 제10-2019-0089077호Korean Patent Application No. 10-2019-0089077

위와 같은 문제에 대하여 본 발명은 사면절개구역이나 법면에 사면녹화를 시공할 때에 있어서 사면녹화와 지면 사이에 흐르는 유수 때문에 사면녹화가 쓸려나가는 것을 방지할 수 있는 방법을 제공하는 것을 목적으로 한다. In response to the above problems, the present invention aims to provide a method for preventing the slope greening from being washed away due to the running water flowing between the slope greening and the ground when the slope greening is constructed on the slope incision area or on the slope.

위와 같은 목적은, 사면절개구역 또는 법면의 표면에 배수판을 설치하는 단계; 상기 배수판의 상면에 고정망체를 설치하는 단계; 고정핀을 이용하여 상기 배수판과 고정망체를 고정하는 단계; 사면녹화부재를 설치하는 단계를 포함하되;The above purpose, the steps of installing a drainage plate on the surface of the slope incision area or slope; Installing a fixed mesh body on the upper surface of the drain plate; fixing the drain plate and the fixing net body using a fixing pin; including installing a slope greening member;

상기 배수판은 저면에 요철돌기가 종횡으로 돌출 형성되는 것으로서, 유수가 지면과 배수판 사이의 공간을 통해 흐를 수 있도록 하는 것을 특징으로 하는 사면절개구역의 사면녹화 시공방법에 의해 달성된다. The drainage plate is achieved by the slope greening construction method of the slope incision area, characterized in that the uneven projections are formed on the bottom surface to protrude vertically and horizontally, and the running water can flow through the space between the ground and the drainage plate.

본 발명의 다른 특징에 의하면, 상기 배수판은 0.5 ~ 2.0mm의 일정한 두께로 되어 있음으로써 저면에는 종횡으로 요철돌기가 마련되고 상면에는 종횡으로 요홈이 마련되는 것일 수 있다. According to another feature of the present invention, since the drain plate has a constant thickness of 0.5 to 2.0 mm, the bottom surface may be provided with vertical and horizontal concavo-convex projections and the upper surface may be provided with vertical and horizontal grooves.

본 발명의 또 다른 특징에 의하면, 상기 배수판의 저면에는 부직포로 된 정착시트가 접착 고정되는 것일 수 있다. According to another feature of the present invention, a fixing sheet made of a non-woven fabric may be adhesively fixed to the bottom surface of the drain plate.

여기서 상기 정착시트는 평판 형태로서 상기 배수판의 요철돌기에 접착 고정될 수 있다. Here, the fixing sheet may be adhesively fixed to the uneven projections of the drain plate in the form of a flat plate.

본 발명에 의하면, 상기 사면녹화부재는 중량비로서 제지화이바 15%, 톱밥 15%, 수피 20%, 유기질비료 25%, 황토 23%, 및 미생물 2%으로 구성되는 것일 수 있다. According to the present invention, the slope greening member may be composed of 15% paper fiber, 15% sawdust, 20% bark, 25% organic fertilizer, 23% loess, and 2% microorganisms by weight.

또한 본 발명에 의하면, 상기 사면녹화부재는 중량비로서 제지화이바 30%, 발효하수 10%, 유지질비료 20%, 톱밥(또는 수피) 10%, 및 마사토 30%로 구성되는 것일 수 있다. Also, according to the present invention, the slope greening member may be composed of 30% paper fiber, 10% fermented sewage, 20% oil and fat fertilizer, 10% sawdust (or bark), and 30% Masato by weight ratio.

위와 같은 구성에 의하면, 절개사면 또는 법면과 사면녹화 사이에 배수판이 개입되어 있게 되며 따라서 절개사면 또는 법면의 상면을 따라 흐르는 의한 유수는 배수판의 요철돌기 사이에 마련되는 통로를 통해 흐름으로써 녹생토와 같은 사면녹화부재를 유실시키지 않게 된다. According to the above configuration, the drainage plate is interposed between the incised slope or the slope and the greening, and therefore the running water flowing along the incised slope or the upper surface of the slope flows through the passage provided between the uneven projections of the drainage plate, so that it is like green soil. The slope greening material is not lost.

도 1은 본 발명의 실시예에 의한 사면녹화의 시공방법에 의한 절개사면의 단면구성도이다.
도 2는 본 발명의 실시예에 의한 사면녹화의 시공방법에 의한 절개사면의 상세 단면도이다.
도 3은 본 발명의 실시예에 의한 사면녹화의 시공방법에 의한 분해 사시도이다.
도 4는 본 발명의 실시예에 의한 사면녹화의 시공방법에 의한 배수판의 설치상태를 도시하는 평면도이다.
1 is a cross-sectional configuration diagram of a cut slope by the construction method of slope greening according to an embodiment of the present invention.
2 is a detailed cross-sectional view of a cut slope by the construction method of slope greening according to an embodiment of the present invention.
3 is an exploded perspective view of the construction method of slope greening according to an embodiment of the present invention.
4 is a plan view showing the installation state of the drainage board according to the construction method of slope greening according to an embodiment of the present invention.

이하, 명세서에 첨부된 도면을 동시에 참조하여 본 발명의 실시예를 상세하게 설명한다. Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings in the specification.

본 발명의 실시예에 의한 사면녹화 시공방법은 사면절개구역 또는 법면의 표면에 배수판(20)을 설치하는 단계; 상기 배수판(20)의 상면에 고정망체(30)를 설치하는 단계; 고정핀(40)을 이용하여 상기 배수판(20)과 고정망체(30)를 고정하는 단계; 및 사면녹화부재(50)를 설치하는 단계를 포함한다. A slope greening construction method according to an embodiment of the present invention comprises the steps of installing a drainage plate 20 on the surface of a slope incision area or a slope; Installing a fixing net body 30 on the upper surface of the drain plate 20; fixing the drain plate 20 and the fixing net body 30 using a fixing pin 40; and installing the slope greening member 50 .

본 발명에 의하면 기존의 시공방법에 대하여 절개사면(E)에 먼저 배수판(20)을 포설하는 단계가 추가된 것이다. 절개사면(E)은 토사, 암반, 축대, 콘크리트 또는 숏크리트 등 제한이 없다. According to the present invention, the step of first installing the drainage plate 20 on the incised slope E is added to the existing construction method. The incision slope (E) is not limited by soil, rock, shaft, concrete or shotcrete.

배수판(20)은 베이스판(21) 및 베이스판(21)의 저면에 종횡으로 돌출 형성되는 요철돌기(22)를 포함한다. 배수판(20)은 유수가 절개사면(E)과 배수판(20) 사이의 배수공간(23)을 통해 흐를 수 있도록 하는 부재이다. 배수판(20)은 도 2 내지 도 3에 도시된 바와 같이 얇은 합성수지 재질로 되어 있다. 배수판(20)은 계란판과 유사한 구성으로 되어 있다. 즉 그의 단면이 파형으로 되어 있다. The drain plate 20 includes a base plate 21 and an uneven protrusion 22 protruding vertically and horizontally from a bottom surface of the base plate 21 . The drain plate 20 is a member that allows running water to flow through the drain space 23 between the incision slope E and the drain plate 20 . The drain plate 20 is made of a thin synthetic resin material as shown in FIGS. 2 to 3 . The drain plate 20 has a configuration similar to that of an egg plate. That is, its cross section is wavy.

배수판(20)은 0.5 ~ 2.0mm의 일정한 두께(T)로 되어 있음으로써 저면에는 종횡으로 요철돌기(22)가 마련되고 상면에는 종횡으로 요홈이 마련되는 것일 수 있다. 요홈은 요철돌기에 의해 만들어진 것이다. 요철돌기(22)의 높이는 10 ~ 30mm가 될 수 있다. Since the drain plate 20 has a constant thickness (T) of 0.5 to 2.0 mm, it may be that the concave-convex projections 22 are provided on the bottom surface vertically and horizontally, and the grooves are provided on the upper surface vertically and horizontally. The groove is made by the concavo-convex projections. The height of the concavo-convex projections 22 may be 10 to 30 mm.

본 발명의 다른 실시예에 의하면 배수판(20)에는 식물의 뿌리가 생장할 수 있도록 하며, 물이 상하로 통할 수 있도록 통기공(미도시됨)이 마련될 수 있다. 이 통기공 요철돌기(22)에 의한 배수공간(23) 보다는 작은 직경으로 타공되며 사면을 따라 흐르는 유수가 배수공간(23)을 통해서만 흐를 수 있도록 유도하기 위함이다. 통기공은 더 바람직하게는 요철돌기(22)의 중간 부분에 마련될 수 있다. 식물의 뿌리가 요철돌기(22)를 통해 직접 지표면에 닿을 수 있도록 하기 위함이다.According to another embodiment of the present invention, the drainage plate 20 may be provided with vent holes (not shown) to allow the roots of plants to grow and to allow water to pass vertically. This vent hole is perforated with a smaller diameter than the drainage space 23 by the concavo-convex projections 22 and is intended to induce the flowing water flowing along the slope to flow only through the drainage space 23 . More preferably, the ventilation hole may be provided in the middle portion of the concavo-convex protrusion 22 . This is so that the root of the plant can directly contact the ground surface through the bumps 22 .

배수판(20)은 도 4에 도시된 것처럼 절개사면을 따라 세로방향으로 길게 설치될 수 있다. 배수판(20)은 롤형태로 제공될 수 있으며 작업자는 배수판(20)을 펼쳐서 설치하면 된다. 배수판의 폭(W)은 1 ~ 2m가 될 수 있고, 길이(L)는 수십미터일 수 있다. 배수판(20)은 도면상 좌우방향으로 약간씩 포개지도록 설치될 수 있다. The drain plate 20 may be installed long in the longitudinal direction along the cut slope as shown in FIG. 4 . The drain plate 20 may be provided in the form of a roll, and the operator may install the drain plate 20 by spreading it. The width (W) of the drain plate may be 1 to 2 m, and the length (L) may be several tens of meters. The drain plate 20 may be installed to be slightly overlapped in the left and right directions in the drawing.

본 발명의 다른 실시예에 의하면, 배수판(20)의 저면에는 부직포로 된 정착시트(10)가 접착 고정될 수 있다. 이 정착시트(10)는 배수판(20)이 지면에서 미끌어지지 않고 잘 정착해있도록 하기 위한 것이다. 정착시트(10)는 단면이 "U" 형태로 되어 있고, 2 ~ 5mm의 두께로 되어 있을 수 있다. 정착시트(10)는 배수판(20)과 절개사면(E)과의 사이에 마찰력을 높인다. According to another embodiment of the present invention, the fixing sheet 10 made of a non-woven fabric may be adhesively fixed to the bottom surface of the drain plate 20 . The fixing sheet 10 is for the drain plate 20 to be well fixed without sliding on the ground. The fixing sheet 10 may have a “U” cross-section and a thickness of 2 to 5 mm. The fixing sheet 10 increases the frictional force between the drain plate 20 and the incised slope E.

여기서 정착시트(10)는 평평한 시트 형태로서 배수판(20)의 요철돌기(22)에 접착으로 고정될 수 있다. 정착시트(10)와 배수판(20)은 접착된 상태에서 일체로 절개사면(E)에 포설된다. 정착시트(10)가 절개사면(E)에 밀착되는 경우에 지표면으로 흐르는 물은 정작시트(10)와 배수판(20) 사이의 매수공간(23)을 따라 흐르게 된다. Here, the fixing sheet 10 may be fixed to the concave-convex projections 22 of the drain plate 20 by adhesive in the form of a flat sheet. The fixing sheet 10 and the drain plate 20 are integrally installed on the cut-off slope E in an adhered state. When the fixing sheet 10 is in close contact with the cut-off slope E, water flowing to the ground flows along the purchase space 23 between the main sheet 10 and the drain plate 20 .

배수판(20) 위에는 고정망체(30)를 덮어 배수판(20)을 고정시킨다. 고정망체(30)는 PVC가 코팅된 철망으로 되어 있을 수도 있고 코아넷(또는 야자매트)이 될 수도 있다. 고정망체(30)는 사면녹화부재(50)를 절개사면(E)에 고정시키기 위한 사전작업으로 시행된다. 즉 슬러지 형태의 사면녹화부재(50)가 흘러내리지 않고 경사면에 고정될 수 있도록 하는 수단이다. A fixing net body 30 is covered on the drain plate 20 to fix the drain plate 20 . The fixed mesh body 30 may be made of a PVC-coated wire mesh or may be a core net (or a palm mat). The fixing net body 30 is implemented as a pre-work for fixing the slope greening member 50 to the incised slope (E). That is, it is a means for allowing the slope greening member 50 in the form of sludge to be fixed to the inclined surface without flowing down.

이후 고정핀(40)을 이용하여 고정망체(30)와 배수판(20)을 절개사면(E)에 고정시킨다. 고정핀(40)의 설치간격은 경사도, 지표면의 물성, 배수판(20)의 무게 등 여러 상황에 따라서 결정된다. Thereafter, the fixing net body 30 and the drain plate 20 are fixed to the incision slope E using the fixing pins 40 . The installation interval of the fixing pins 40 is determined according to various circumstances, such as inclination, physical properties of the ground surface, and the weight of the drain plate 20 .

이후 소정의 장비를 이용하여 사면녹화부재(50)를 타설한다. 사면녹화부재(50)는 7 ~ 10cm 의 두께로 타설된다. 사용 장비는 발전기, 취부기(믹서) 및 콤프레셔를 포함할 수 있다. 사면녹화(50)는 습식공사용과 건식공사용으로 구분될 수 있다. Thereafter, the slope greening member 50 is poured using predetermined equipment. The slope greening member 50 is poured with a thickness of 7 to 10 cm. Equipment used may include a generator, an injector (mixer) and a compressor. The slope greening 50 may be divided into wet construction and dry construction.

습식공사용 사면녹화부재는 중량비로서 제지화이바 15%, 톱밥 15%, 수피 20%, 유기질비료 25%, 황토 23%, 및 미생물 2%로 구성되는 것일 수 있다. 또한 건식공사용 사면녹화는 중량비로서 제지화이바 30%, 발효하수 10%, 유지질비료 20%, 톱밥(또는 수피) 10%, 및 마사토 30%로 구성되는 것일 수 있다. 여기서 언급된 각 중량비율은 ±10% 범위에서 조정이 가능하다. The slope greening member for wet construction may be composed of 15% paper fiber, 15% sawdust, 20% bark, 25% organic fertilizer, 23% loess, and 2% microorganisms by weight. In addition, slope greening for dry construction may be composed of 30% of paper fiber, 10% of fermented sewage, 20% of oil and fat fertilizer, 10% of sawdust (or bark), and 30% of Masato as a weight ratio. Each weight ratio mentioned here can be adjusted in the range of ±10%.

그리고 전술한 사면녹화부재의 성분에 영양제 또는 보습제로서 테라코템이 적정량 더 포함될 수 있으며, 피트모스가 혼합 사용될 수도 있다. In addition, an appropriate amount of Terracottem as a nutrient or moisturizing agent may be further included in the components of the above-mentioned slope greening member, and peat moss may be mixed and used.

이상에서 설명된 것들은 본 발명의 기술적 사상에 의거한 몇가지 예시에 불과하다. 당업자는 청구범위를 통해 표현되는 본 발명의 기술적 사상의 범위를 넘지 않는 선에서 예시된 바를 활용하여 다양한 변형실시를 할 수 있을 것이다. 예를 들어 위에 설명된 모든 실시예들은 당업자에 의해 자유롭게 조합되어 실시될 수 있으며 어떠한 조합이든지 본 발명의 권리범위에 포함된다고 해석되어야 한다. What has been described above is only a few examples based on the technical idea of the present invention. Those skilled in the art will be able to make various modifications using the illustrated bar without going beyond the scope of the technical spirit of the present invention expressed through the claims. For example, all embodiments described above can be freely combined and implemented by those skilled in the art, and any combination should be construed as being included in the scope of the present invention.

10 : 정착시트 20 : 배수판
21 : 베이스판 22 : 요철돌기
23 : 배수공간 30 : 고정망체
40 : 고정핀 50 : 사면녹화부재
E : 절개사면
10: fixing sheet 20: drain plate
21: base plate 22: uneven projection
23: drainage space 30: fixed mesh body
40: fixing pin 50: slope greening member
E: incision slope

Claims (6)

사면절개구역 또는 법면의 표면에 배수판을 설치하는 단계; 상기 배수판의 상면에 고정망체를 설치하는 단계; 고정핀을 이용하여 상기 배수판과 고정망체를 고정하는 단계; 사면녹화부재를 설치하는 단계를 포함하되;
상기 배수판은 저면에 요철돌기가 종횡으로 돌출 형성되는 것으로서, 유수가 지면과 배수판 사이의 공간을 통해 흐를 수 있도록 하는 것을 특징으로 하는 사면절개구역의 사면녹화 시공방법.
Installing a drainage plate on the surface of the slope incision area or slope; Installing a fixed mesh body on the upper surface of the drain plate; fixing the drain plate and the fixing net body using a fixing pin; including installing a slope greening member;
The drainage plate is a slope greening construction method of a slope incision area, characterized in that the uneven projections are formed on the bottom surface to protrude vertically and horizontally, and the running water can flow through the space between the ground and the drainage plate.
제1항에 있어서,
상기 배수판은 0.5 ~ 2.0mm의 일정한 두께로 되어 있음으로써 저면에는 종횡으로 요철돌기가 마련되고 상면에는 종횡으로 요홈이 마련되는 것을 특징으로 하는 사면절개구역의 사면녹화 시공방법.
According to claim 1,
The drainage plate has a constant thickness of 0.5 to 2.0 mm, so that the vertical and horizontal uneven projections are provided on the bottom surface and the vertical and horizontal grooves are provided on the upper surface.
제1항에 있어서,
상기 배수판의 저면에는 부직포로 된 정착시트가 접착 고정되되;
상기 정착시트는 평평한 시트 형태로서 상기 배수판의 요철돌기에 접착 고정되는 것을 특징으로 하는 사면절개구역의 사면녹화 시공방법.
According to claim 1,
A fixing sheet made of a non-woven fabric is adhesively fixed to the bottom surface of the drain plate;
The fixing sheet is in the form of a flat sheet and is adhesively fixed to the uneven projections of the drainage plate.
제1항에 있어서,
상기 배수판에는 식물의 뿌리가 생장할 수 있도록 하며, 물이 상하로 통할 수 있도록 통기공이 마련되는 것을 특징으로 하는 사면절개구역의 사면녹화 시공방법.
According to claim 1,
A method for greening a slope in a slope incision area, characterized in that the drainage plate is provided with ventilation holes to allow the roots of plants to grow and to allow water to pass vertically.
제1항에 있어서,
상기 사면녹화부재는 중량비로서 제지화이바 15%, 톱밥 15%, 수피 20%, 유기질비료 25%, 황토 23%, 및 미생물 2%으로 구성되는 것을 특징으로 하는 사면절개구역의 사면녹화 시공방법.
According to claim 1,
The slope greening member is a slope greening construction method of a slope incision area, characterized in that it consists of 15% of paper fiber, 15% of sawdust, 20% of bark, 25% of organic fertilizer, 23% of loess, and 2% of microorganisms as a weight ratio.
제1항에 있어서,
상기 사면녹화부재는 중량비로서 제지화이바 30%, 발효하수 10%, 유지질비료 20%, 톱밥(또는 수피) 10%, 및 마사토 30%로 구성되는 것을 특징으로 하는 사면절개구역의 사면녹화 시공방법.
According to claim 1,
The slope greening member is a slope greening construction method of a slope incision area, characterized in that it consists of 30% of paper fiber, 10% of fermented sewage, 20% of oil and fat fertilizer, 10% of sawdust (or bark), and 30% of Masato as a weight ratio .
KR1020200119052A 2020-09-16 2020-09-16 Construction Methods For Slope Tree-Planting For Slope Area By Cutting KR20220036623A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020200119052A KR20220036623A (en) 2020-09-16 2020-09-16 Construction Methods For Slope Tree-Planting For Slope Area By Cutting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020200119052A KR20220036623A (en) 2020-09-16 2020-09-16 Construction Methods For Slope Tree-Planting For Slope Area By Cutting

Publications (1)

Publication Number Publication Date
KR20220036623A true KR20220036623A (en) 2022-03-23

Family

ID=80963625

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020200119052A KR20220036623A (en) 2020-09-16 2020-09-16 Construction Methods For Slope Tree-Planting For Slope Area By Cutting

Country Status (1)

Country Link
KR (1) KR20220036623A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102666757B1 (en) * 2023-05-02 2024-05-17 두한종합건설 주식회사 Soundproof tunnel including vegetation part

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20170052092A (en) 2015-11-03 2017-05-12 한전케이피에스 주식회사 Sealing device for drive shaft of debris filter and installation method thereof
KR20190089077A (en) 2017-01-26 2019-07-29 미쓰비시덴키 가부시키가이샤 Survey control device and survey method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20170052092A (en) 2015-11-03 2017-05-12 한전케이피에스 주식회사 Sealing device for drive shaft of debris filter and installation method thereof
KR20190089077A (en) 2017-01-26 2019-07-29 미쓰비시덴키 가부시키가이샤 Survey control device and survey method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102666757B1 (en) * 2023-05-02 2024-05-17 두한종합건설 주식회사 Soundproof tunnel including vegetation part

Similar Documents

Publication Publication Date Title
KR101101281B1 (en) Mat for planting tree on sloop
KR20220036623A (en) Construction Methods For Slope Tree-Planting For Slope Area By Cutting
KR102051838B1 (en) Slope Vegetation Method using Embossing
KR100648884B1 (en) Sand and gardening plant loss preventive constructure of an rock incline
JP4703776B1 (en) Water shielding greening sheet
JP3121174B2 (en) Rainwater storage type planting ground
KR100678348B1 (en) Tree pot and method of plant
KR200254952Y1 (en) Device for suppling water of tree
KR100549498B1 (en) Construction assembly breast wall pul lek establishment structure
JPH093831A (en) Green belt and water-retaining tool for the green belt
JP2008289393A (en) Fiber structure into which culture soil is put
KR200142764Y1 (en) A protection block structure of the earth cut slope
KR20020015185A (en) Planting belts construction method for street trees
JP2002235327A (en) Greening system, greening method thereby and corner member used therefor
JP5177605B1 (en) Weed suppression and replenishment type vegetation greening mat body
KR200251406Y1 (en) A member for preventing earth of a retaining wall from being washed away
JP3516612B2 (en) Planting structure and planting structure of slope
JP3090799U (en) Laying piers for greening slopes
KR20110127776A (en) Construction method for stabilizing slope for soil-flow and greening
JP2012120462A (en) Ground unit for greening
CN214143117U (en) Garden road structure
KR200262840Y1 (en) Embankment Block and Building Method Thereof
JP4767116B2 (en) Revegetation structure of the constructed wall with the machin block
KR200185860Y1 (en) Concrete block for constructing greening vegetation foundation
JP2003082670A (en) Construction of slope face

Legal Events

Date Code Title Description
J301 Trial decision

Free format text: TRIAL NUMBER: 2021101001012; TRIAL DECISION FOR APPEAL AGAINST DECISION TO DECLINE REFUSAL REQUESTED 20210422

Effective date: 20220330