KR20220000803A KR1020210012023A KR20210012023A KR20220000803A KR 20220000803 A KR20220000803 A KR 20220000803A KR 1020210012023 A KR1020210012023 A KR 1020210012023A KR 20210012023 A KR20210012023 A KR 20210012023A KR 20220000803 A KR20220000803 A KR 20220000803A
Authority
KR
South Korea
Prior art keywords
pile
leader
coupled
drilling
bit
Prior art date
Application number
KR1020210012023A
Other languages
Korean (ko)
Other versions
KR102637552B1 (en
Inventor
박인수
Original Assignee
박인수
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 박인수 filed Critical 박인수
Priority to KR1020210012023A priority Critical patent/KR102637552B1/en
Publication of KR20220000803A publication Critical patent/KR20220000803A/en
Application granted granted Critical
Publication of KR102637552B1 publication Critical patent/KR102637552B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/26Placing by using several means simultaneously
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/02Placing by driving
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/06Dredgers; Soil-shifting machines mechanically-driven with digging screws
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/02Drilling rigs characterised by means for land transport with their own drive, e.g. skid mounting or wheel mounting
    • E21B7/027Drills for drilling shallow holes, e.g. for taking soil samples or for drilling postholes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0038Production methods using an auger, i.e. continuous flight type

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Paleontology (AREA)
  • Geology (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Mechanical Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

Disclosed is a pile construction apparatus capable of simultaneous achievement of hole-boring and vibrating. The pile construction apparatus capable of simultaneous achievement of hole-boring and vibrating comprises a hole-boring machine and a vibrating machine. The hole-boring machine includes: an auger ascending and descending along a leader; a screw coupled to a lower portion of the auger; and a casing formed in a column shape and provided below the auger so that the screw is positioned inside. The vibrating machine includes: a pile fixing unit for fixing a cast; a vibration generating unit for providing vibration to the pile fixing unit; and a support unit coupled to at least one of the pile fixing unit and the vibration generating unit to ascend and descend in a vertical direction. The vibrating machine descends and bores a second pile hole in a process in which the vibrating machine descends and inserts the cast into a first pile hole. Therefore, the time required for pile construction can be reduced.

Description

천공 및 항타 작업의 동시수행이 가능한 파일 시공장치{File construction apparatus capable of simultaneous achievement of hole-boring and vibrating}File construction apparatus capable of simultaneous achievement of hole-boring and vibrating}

본 발명의 일 실시예는 파일 시공장치에 관한 것으로, 더욱 상세하게는, 파일을 삽입하기 위한 파일 파일공의 천공작업과 파일을 파일공에 삽입하는 항타작업을 동시에 실시할 수 있도록 함으로써 파일 시공에 소요되는 시간을 절감할 수 있는 천공 및 항타 작업의 동시수행이 가능한 파일 시공장치에 관련된다.One embodiment of the present invention relates to a pile construction apparatus, and more specifically, by allowing the drilling of the pile for inserting the file and the driving operation of inserting the file into the pile at the same time to be performed at the same time, It relates to a pile construction device capable of simultaneously performing drilling and driving work that can reduce the time required.

일반적으로 철근 콘크리트 구조물이나 그 밖의 건축물 등을 축조할 경우에, 건축물 지반의 기초를 견고하게 하기 위하여 PHC, 강관파일, H형 빔, 시트파일 등을 지반에 일정 간격으로 박아서 매설하는 방법으로 기초 공사를 실시하고 있는바, 이러한 파일 등의 시공은 구조물 및 건축물 등을 축조하는 데 있어서 매우 중요하다.In general, when constructing reinforced concrete structures or other buildings, PHC, steel pipe piles, H-beams, sheet piles, etc. are driven into the ground at regular intervals to make the foundation of the building solid. Since construction is being carried out, the construction of such piles is very important in constructing structures and buildings.

기초공사에서 파일을 시공하는 방법으로 타설시공법과 굴삭시공법 등이 사용되고 있다. 타설시공법은 기중기에 수직으로 설치한 리더의 상부에 설치된 권양로프를 이용하여 중량체의 해머를 상승시켰다가 낙하시켜서 파일을 타설하거나, 컴프레셔의 압축공기를 이용하여 해머를 상승시켰다가 하강시키면서 파일을 타설하여 지반에 삽입 설치하는 공법인데, 이러한 시공법들은 해머로서 파일 상단을 타설시 타격음과 진동이 크게 발생하는 문제 점으로 인해 그 사용에 제약이 많이 따른다. As a method of constructing piles in foundation construction, the pouring construction method and the excavation construction method are used. The pouring construction method uses a lifting rope installed on the upper part of the leader installed vertically in the crane to raise the hammer of the heavy body and then drop it to place the pile, or use the compressed air of the compressor to raise the hammer and then lower the pile while lowering it. It is a construction method of pouring and inserting into the ground, and these construction methods have a lot of restrictions on their use due to the problem of large impact sound and vibration when pouring the top of the pile as a hammer.

굴착시공법은 오거(Auger) 머신에 장착된 스크류를 회전시켜서 지반을 굴착하여 파일공을 형성시킨 후 스크류를 역회전시켜서 굴착된 파일공에서 빼낸 다음, 천공된 파일공의 흙더미가 무너지는 등의 붕괴를 방지하기 위해 리더가 작동하여 별도로 구비되는 시트파일을 인양하고, 바이브레이터를 이용하여 파일공에 시트파일(SHEET PILE : 강널말뚝) 등의 파일을 삽입시키는 공법으로, 타설시공법의 문제점을 해결하기 위한 대안으로 사용되고 있다. 여기서, 시트파일은 재질이 주강제이고 그 단면은 대체로 ㄷ자형을 가지면서 개방된 양단이 외측으로 벌어진 사다리꼴 모양을 이루고 있으며, 또한 사다리꼴 모양을 이루도록 외측을 향해 벌어진 양단에는 서로 이웃한 것끼리 대칭상으로 결합될 수 있는 구조로 이루어진다. 따라서, 다수의 시트파일들이 일직선상으로 연결되는 구조로 지반에 타입 설치되거나 또는 일직선상으로 연결되게 하면서 타입 설치하다가 원하는 각도로 방향을 틀어서 타입 설치될 수 있고, 또는 원형을 이루도록 타입 설치될 수 있으며, 이와 같은 시트파일은 콘크리트 건축물을 건설할 때 또는 물막이 연속벽을 구축할 때 및 교량이나 고가도로 등의 교각을 구축할 때와 같이 주로 도로·호안·항만 및 하천공사에서 무소음 무진동 공법으로 지반에 압입되는데 많이 사용되고 있다.In the excavation construction method, the screw mounted on the Auger machine is rotated to excavate the ground to form a pile hole, and then the screw is rotated reversely to remove it from the excavated pile hole, and then the soil pile of the drilled pile hole collapses. In order to prevent this, a leader operates to lift a separately provided sheet pile, and a vibrator is used to insert a file such as a sheet pile (SHEET PILE: steel pile) into the pile hole. being used as an alternative. Here, the material of the sheet pile is cast steel, and the cross section is generally U-shaped and both ends open to form a trapezoidal shape, and the adjacent ones are symmetrical at both ends that open outward to form a trapezoidal shape. It has a structure that can be combined with Therefore, a plurality of sheet piles may be type-installed on the ground in a structure in which they are connected in a straight line, or may be type-installed by turning the direction at a desired angle while being type-installed while being connected in a straight line, or may be type-installed to form a circle. , these sheet piles are press-fitted into the ground by a noise-free and vibration-free method mainly in road, shore, harbor, and river construction, such as when constructing concrete structures, when constructing continuous water walls, and when constructing piers such as bridges or overpasses. It is used a lot.

그러나 이와 같은 종래의 굴착시공법에 의하면, 오거 스크류를 이용한 천공 작업과 리더를 통한 시트파일의 인양 및 바이브레이터를 이용한 시트파일의 근입 작업이 각각 별개로 진행되고, 번갈아가면서 반복적으로 행해짐에 따라 하나의 파일공을 천공하고 시트파일을 근입하는 데 많은 작업 공정과 함께 장비가 복잡해져 시공작업을 복잡하게 하였다. 나아가 작업장의 효율적 사용을 어렵게 하여 이에 따른 공기(工期)가 증가되어 공사비 증가는 물론 작업 효율이 저하되는 문제점이 있었다.However, according to such a conventional excavation construction method, the drilling operation using the auger screw, the lifting of the sheet pile through the leader, and the insertion operation of the sheet pile using the vibrator are performed separately, and as they are repeatedly performed alternately, one pile In drilling the ball and inserting the sheet pile, the equipment was complicated along with many work processes, complicating the construction work. Furthermore, it made it difficult to use the workplace efficiently, which resulted in an increase in air (工期), which resulted in an increase in construction cost as well as a decrease in work efficiency.

본 발명의 일 측면은, 천공작업과 항타작업을 동시에 실시할 수 있도록 함으로써 파일 시공에 소요되는 시간을 절감할 수 있는 천공 및 항타 작업의 동시수행이 가능한 파일 시공장치를 제공할 수 있다.One aspect of the present invention may provide a pile construction apparatus capable of simultaneously performing drilling and driving, which can reduce the time required for pile construction by allowing the drilling operation and the driving operation to be performed at the same time.

본 발명의 예시적인 실시예에 따른 천공 및 항타 작업의 동시수행이 가능한 파일 시공장치는, 상기 리더를 따라 승강하는 오거; 상기 오거의 하방에 결합되는 스크류; 및 기둥 형상으로 이루어져 상기 스크류가 내측에 위치되도록 상기 오거의 하방에 구비되는 케이싱;을 포함하는 천공기와, 타설물을 고정하는 파일고정부; 상기 파일고정부에 진동을 제공하는 진동발생부; 및 상기 파일고정부 및 상기 진동발생부 중 적어도 하나에 결합되어 수직방향으로 승강하는 지지부;를 포함하는 항타기를 포함하고, 상기 항타기가 하강하면서 상기 타설물을 제1 파일공에 삽입하는 과정에서 상기 천공기가 하강하면서 제2 파일공을 천공하게 구성될 수 있다.A pile construction apparatus capable of simultaneously performing drilling and driving work according to an exemplary embodiment of the present invention includes: an auger that ascends and descends along the leader; a screw coupled to a lower portion of the auger; and a casing provided under the auger so that the screw is positioned inside the auger and formed in a column shape; a perforator including a; a vibration generating unit providing vibration to the pile fixing unit; and a supporting part coupled to at least one of the pile fixing part and the vibration generating part to ascend and descend in a vertical direction. As the perforator descends, it may be configured to perforate the second pile hole.

이때, 상기 지지부는 상기 케이싱에 구비되는 케이싱레일에 결합되어 상기 케이싱레일을 따라 승강할 수 있다.In this case, the support part may be coupled to a casing rail provided in the casing to ascend and descend along the casing rail.

또한, 상기 리더의 상하방향과 평행한 가상의 직선을 회전축으로 하여 상기 케이싱이 회전되어 상기 케이싱레일의 위치가 변화될 수 있다.In addition, the casing is rotated by using an imaginary straight line parallel to the vertical direction of the leader as a rotation axis to change the position of the casing rail.

또한, 상기 스크류의 중심축을 기준으로 상기 케이싱이 회전되어 상기 케이싱레일의 위치가 변화될 수 있다.In addition, the casing is rotated with respect to the central axis of the screw to change the position of the casing rail.

또한, 상기 리더의 일면에 구비되는 리더레일을 따라 승강하는 제1 가이드, 상기 제1 가이드 상의 한 점을 지나면서 상기 리더의 상하방향과 평행한 가상의 직선을 회전축으로 하여 상기 케이싱이 회동가능하게 결합될 수 있다.In addition, a first guide that ascends and descends along a leader rail provided on one surface of the leader, and a virtual straight line parallel to the vertical direction of the leader as it passes through a point on the first guide, the casing is rotatable can be combined.

또한, 상기 항타기는 상기 리더의 상하방향과 평행한 가상의 선을 축으로 회전가능하게 상기 지지대에 결합될 수 있다.In addition, the driving machine may be rotatably coupled to the support about an imaginary line parallel to the vertical direction of the leader.

또한, 상기 지지부는 상기 리더에 구비되는 리더보조레일에 결합되어 상기 리더보조레일을 따라 승강하고, 상기 지지부 상의 한 점을 지나면서 상기 리더의 상하방향과 평행한 가상의 직선을 회전축으로 하여 상기 진동발생부 또는 상기 파일고정부가 회동가능하게 결합될 수 있다.In addition, the support unit is coupled to the leader auxiliary rail provided in the leader, ascends and descends along the leader auxiliary rail, passes a point on the support unit, and uses an imaginary straight line parallel to the vertical direction of the leader as a rotation axis to vibrate the vibration. The generating unit or the pile fixing unit may be rotatably coupled.

또한, 상기 리더에 결합되는 보조리더를 더 포함하고, 상기 지지부는 상기 보조리더에 구비되는 보조리더레일에 결합되어 상기 보조리더레일을 따라 승강하고, 상기 리더 상의 한 점을 지나면서 상기 리더와 평행한 가상의 선을 축으로 하여 상기 보조리더가 회동 가능하도록 상기 리더와 상기 보조리더가 결합될 수 있다.In addition, it further includes an auxiliary leader coupled to the leader, wherein the support part is coupled to the auxiliary leader rail provided in the auxiliary leader to ascend and descend along the auxiliary leader rail, passing a point on the leader and parallel to the leader The leader and the sub-reader may be coupled to each other so that the sub-reader is rotatable about an imaginary line as an axis.

또한, 상기 스크류의 하부에 결합되는 비트를 더 포함하되, 상기 비트는 장축과 단축을 가지며, 상기 비트의 장축이 상기 파일고정부를 향하도록 상기 비트가 위치된 제1 상태에서 상기 천공기가 상승하면, 인접된 타설물에 상기 비트가 접촉되고, 상기 비트의 장축이 상기 파일고정부를 향하지 않는 상태에서 상기 천공기가 상승하면, 인접된 타설물에 상기 비트가 접촉되지 않는 것일 수 있다.In addition, further comprising a bit coupled to the lower portion of the screw, wherein the bit has a long axis and a short axis, and when the perforator rises in the first state in which the bit is positioned so that the long axis of the bit faces the pile fixing part , When the bit is in contact with the adjacent cast and the perforator rises in a state where the long axis of the bit does not face the pile fixing part, the bit may not come into contact with the adjacent cast.

또한, 상기 파일고정부에는 제1 시트파일을 파지하는 제1 파지부 및 상기 제1 파지부로부터 이격되어 구비되며 제2 시트파일을 파지하는 제2 파지부가 구비될 수 있다.In addition, the file fixing part may be provided with a first gripping part for gripping the first sheet pile and a second gripping part spaced apart from the first gripping part and gripping the second sheet file.

또한, 상기 진동발생부 또는 상기 파일고정부가 상기 지지부 상에서 수평방향으로 이동가능하게 결합될 수 있다.In addition, the vibration generating part or the pile fixing part may be movably coupled in the horizontal direction on the support part.

본 발명의 일 실시예에 따르면, 파일을 삽입하기 위한 파일 파일공의 천공작업과 파일을 파일공에 삽입하는 항타작업을 동시에 실시할 수 있도록 함으로써 파일 시공에 소요되는 시간을 절감할 수 있다는 유용한 효과가 제공될 수 있다.According to an embodiment of the present invention, a useful effect that it is possible to reduce the time required for the construction of the pile by allowing the drilling operation of the pile hole for inserting the file and the driving operation of inserting the file into the pile hole at the same time may be provided.

또한, 본 발명의 일 실시예에 따르면, 시트파일의 설치방향, 시트파일의 설치위치 등을 손쉽게 조절하면서도 시공 효율성을 개선할 수 있다는 유용한 효과가 제공될 수 있다.In addition, according to an embodiment of the present invention, it is possible to provide a useful effect of improving the construction efficiency while easily adjusting the installation direction of the sheet pile, the installation position of the sheet pile, and the like.

도 1은 본 발명의 일 실시예에 따른 천공 및 항타 작업의 동시수행이 가능한 파일 시공장치가 적용된 건설장비를 설명하기 위한 도면이고,
도 2는 본 발명의 일 실시예에 따른 작동원리를 설명하기 위한 평면 개념도이고,
도 3은 본 발명의 일 실시예에 따른 작동원리를 설명하기 위한 측면 개념도이고,
도 4는 본 발명의 다른 실시예에 따른 작동원리를 설명하기 위한 측면 개념도이고,
도 5는 본 발명의 일 실시예에 따른 작동원리를 설명하기 위한 평면 개념도이고,
도 6은 본 발명의 다른 실시예에 따른 작동원리를 설명하기 위한 평면 개념도이고,
도 7는 본 발명의 또 다른 실시예에 따른 작동원리를 설명하기 위한 평면 개념도이고,
도 8은 본 발명의 일 실시예에 따른 시공과정을 설명하기 위한 도면이다.
1 is a view for explaining construction equipment to which a pile construction device capable of simultaneously performing drilling and driving work is applied according to an embodiment of the present invention;
2 is a plan conceptual view for explaining the operating principle according to an embodiment of the present invention,
3 is a side conceptual diagram for explaining the operating principle according to an embodiment of the present invention,
4 is a side conceptual view for explaining the operating principle according to another embodiment of the present invention,
5 is a plan conceptual view for explaining the principle of operation according to an embodiment of the present invention,
6 is a plan conceptual view for explaining the operating principle according to another embodiment of the present invention,
7 is a plan conceptual view for explaining the operating principle according to another embodiment of the present invention,
8 is a view for explaining a construction process according to an embodiment of the present invention.

본 발명의 이점 및 특징, 그리고 그것들을 달성하는 방법은 첨부되는 도면들과 함께 상세하게 후술되어 있는 실시예들을 참조하면 명확해질 것이다. 그러나 본 발명은 이하에서 개시되는 실시예들에 한정되는 것이 아니라 서로 다른 다양한 형태로 구현될 수 있다. 본 실시예들은 본 발명의 개시가 완전하도록 하고, 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에게 발명의 범주를 완전하게 알려주기 위해 제공될 수 있다. 명세서 전문에 걸쳐 동일 참조 부호는 동일 구성 요소를 지칭한다.Advantages and features of the present invention, and a method of achieving them, will become apparent with reference to the embodiments described below in detail in conjunction with the accompanying drawings. However, the present invention is not limited to the embodiments disclosed below and may be implemented in various different forms. The present embodiments may be provided so as to complete the disclosure of the present invention and to completely inform those of ordinary skill in the art to the scope of the present invention. Like reference numerals refer to like elements throughout.

본 명세서에서 사용된 용어들은 실시예들을 설명하기 위한 것이며 본 발명을 제한하고자 하는 단계는 아니다. 본 명세서에서, 단수형은 문구에서 특별히 언급하지 않는 한 복수형도 포함한다. 명세서에서 사용되는 '포함한다(comprise)' 및/또는 '포함하는(comprising)'은 언급된 구성요소, 단계, 동작 및/또는 소자는 하나 이상의 다른 구성요소, 단계, 동작 및/또는 소자의 존재 또는 추가를 배제하지 않는다.The terms used herein are for the purpose of describing the embodiments and are not intended to limit the present invention. In this specification, the singular also includes the plural unless specifically stated otherwise in the phrase. As used herein, 'comprise' and/or 'comprising' means that a referenced component, step, operation and/or element is the presence of one or more other components, steps, operations and/or elements. or addition is not excluded.

이하에서는 첨부된 도면을 참조하여 본 발명의 구성 및 작용효과를 더욱 상세하게 설명한다.Hereinafter, the configuration and effect of the present invention will be described in more detail with reference to the accompanying drawings.

도 1은 본 발명의 일 실시예에 따른 천공 및 항타 작업의 동시수행이 가능한 파일 시공장치가 적용된 건설장비를 설명하기 위한 도면이고, 도 2는 본 발명의 일 실시예에 따른 작동원리를 설명하기 위한 평면 개념도이고, 도 3은 본 발명의 일 실시예에 따른 작동원리를 설명하기 위한 측면 개념도이고, 도 4는 본 발명의 다른 실시예에 따른 작동원리를 설명하기 위한 측면 개념도이고, 도 5는 본 발명의 일 실시예에 따른 작동원리를 설명하기 위한 평면 개념도이고, 도 6은 본 발명의 다른 실시예에 따른 작동원리를 설명하기 위한 평면 개념도이고, 도 7는 본 발명의 또 다른 실시예에 따른 작동원리를 설명하기 위한 평면 개념도이고, 도 8은 본 발명의 일 실시예에 따른 시공과정을 설명하기 위한 도면이다.1 is a view for explaining a construction equipment to which a pile construction apparatus capable of simultaneously performing drilling and driving work according to an embodiment of the present invention is applied, and FIG. 2 is a view for explaining the operating principle according to an embodiment of the present invention 3 is a side conceptual diagram for explaining the operating principle according to an embodiment of the present invention, FIG. 4 is a side conceptual diagram for explaining the operating principle according to another embodiment of the present invention, and FIG. 5 is It is a plan conceptual diagram for explaining the operating principle according to an embodiment of the present invention, Figure 6 is a plan conceptual diagram for explaining the operating principle according to another embodiment of the present invention, Figure 7 is another embodiment of the present invention It is a plan conceptual diagram for explaining the principle of operation according to the present invention, and FIG. 8 is a view for explaining a construction process according to an embodiment of the present invention.

도면을 참조하면, 본 발명의 일 실시예에 따른 천공 및 항타 작업의 동시수행이 가능한 파일 시공장치는 리더(110), 천공기(200) 및 항타기(300)를 포함한다.Referring to the drawings, the pile construction apparatus capable of simultaneously performing drilling and driving work according to an embodiment of the present invention includes a leader 110 , a drilling machine 200 and a driving machine 300 .

일 실시예에서, 리더(110)는 천공기(200), 항타기(300) 등의 장비를 상승시키거나 하강시키는 과정이 안정적으로 수행될 수 있도록 지지하는 역할을 수행한다. 이때, 리더(110)는 차체(1)에 결합되어 이송 가능할 수 있고, 차체(1)와 리더(110) 사이에 붐(2)이 개입될 수 있다.In one embodiment, the leader 110 serves to support so that the process of raising or lowering equipment such as the perforator 200 and the driving machine 300 can be stably performed. In this case, the leader 110 may be coupled to the vehicle body 1 to be transportable, and the boom 2 may be interposed between the vehicle body 1 and the leader 110 .

일 실시예에서, 천공기(200)는 오거(210), 스크류(220) 및 케이싱(230)을 포함하고, 더 나아가, 케이싱 결합부(215), 케이싱레일(231), 비트(240), 제1 가이드(250), 제2 가이드(260), 가이드부(270) 등을 더 포함할 수 있다. 천공기(200)는 하강하면서 파일공을 천공하는 기능을 수행하고, 상승하여 파일공으로부터 분리된다. 오거(210)는 스크류(220)를 회전시키는데, 스크류(220)의 회전에 의하여 파일공이 천공되며, 케이싱(230)은 천공된 파일공이 무너지지 않도록 지지하는 기능을 수행한다. 한편, 스크류(220)의 하단부에는 비트(240)가 결합될 수 있고, 이러한 비트(240)에 의하여 단단한 암반에 대한 천공도 가능해진다.In one embodiment, the perforator 200 includes an auger 210, a screw 220 and a casing 230, and furthermore, a casing coupling portion 215, a casing rail 231, a bit 240, the first It may further include a first guide 250 , a second guide 260 , a guide part 270 , and the like. The perforator 200 performs a function of perforating the pile hole while descending, and is separated from the pile hole by ascending. The auger 210 rotates the screw 220, the pile hole is perforated by the rotation of the screw 220, and the casing 230 performs a function of supporting the perforated pile hole so as not to collapse. On the other hand, a bit 240 may be coupled to the lower end of the screw 220 , and it is also possible to perforate the hard rock by the bit 240 .

일 실시예에서, 오거(210)는 리더(110)를 따라 승강할 수 있고, 오거(210)의 하방에는 스크류(220)가 구비되어 오거(210)의 승강과정에서 스크류(220)도 함께 승강될 수 있다.In one embodiment, the auger 210 can be raised and lowered along the leader 110 , and a screw 220 is provided below the auger 210 , so that the screw 220 is also raised and lowered during the lifting process of the auger 210 . can be

일 실시예에서, 케이싱(230)은 기둥형상으로 이루어지고, 그 내부에 스크류(220)가 위치하여 회전될 수 있다. 이 케이싱(230)은 오거(210)에 직접 결합될 수 있다. 또한, 오거(210)에 구비되는 케이싱 결합부(215)에 케이싱(230)이 결합고정될 수도 있다. 한편, 케이싱 결합부(215)는 케이싱(230)을 회전시킬 수 있다. 이때 회전축은 스크류(220)의 회전축과 동일할 수 있다.In one embodiment, the casing 230 is formed in a column shape, and the screw 220 is positioned therein and can be rotated. This casing 230 may be coupled directly to the auger 210 . In addition, the casing 230 may be coupled and fixed to the casing coupling portion 215 provided in the auger 210 . Meanwhile, the casing coupling part 215 may rotate the casing 230 . In this case, the rotation axis may be the same as the rotation axis of the screw 220 .

일 실시예에서, 천공기(200)는 리더(110)에 구비된 리더레일(111)을 따라서 승강할 수 있다. 예컨대, 리더레일(111)에 접촉되고, 리더레일(111)에 의하여 상하방향으로 가이드되는 제1 가이드(250)에 천공기(200)가 결합됨으로써 천공기(200)가 리더(110)를 따라 승강할 수 있다. 이때, 제1 가이드(250)는 오거(210), 케이싱 결합부(215), 케이싱(230) 중 어느 하나 또는 둘 이상에 결합될 수 있다. 다만, 오거(210)가 가장 상부에 있고, 오거(210) 자체는 회전될 필요가 없는 반면에, 케이싱(230)이나 케이싱 결합부(215)는 오거(210) 하방에 구비되고, 필요에 따라서는 케이싱(230)이 회전되거나 케이싱 결합부(215)가 회전될 수도 있으므로 오거(210)에 제1 가이드(250)가 결합되는 것이 가장 바람직할 수 있다.In an embodiment, the perforator 200 may be raised and lowered along the leader rail 111 provided in the leader 110 . For example, as the perforator 200 is coupled to the first guide 250 that is in contact with the leader rail 111 and is guided in the vertical direction by the leader rail 111 , the perforator 200 moves up and down along the leader 110 . can In this case, the first guide 250 may be coupled to any one or two or more of the auger 210 , the casing coupling portion 215 , and the casing 230 . However, the auger 210 is at the top, and the auger 210 itself does not need to be rotated, whereas the casing 230 or the casing coupling part 215 is provided below the auger 210, and as needed. Since the casing 230 may be rotated or the casing coupling portion 215 may be rotated, it may be most preferable that the first guide 250 is coupled to the auger 210 .

일 실시예에서, 제1 가이드(250)와 천공기(200) 사이에 제2 가이드(260)가 구비될 수 있다. 제2 가이드(260)는 제1 가이드(250) 상의 한 점을 중심으로 회동가능하게 결합될 수 있다. 그리고, 제2 가이드(260)가 천공기(200)에 결합될 수 있으며, 그 결과, 제1 가이드(250) 상의 한 점을 지나면서 리더(110)의 상하방향과 평행한 가상의 직선을 회전축으로 하여 케이싱(230)이 회동 가능해진다.In one embodiment, the second guide 260 may be provided between the first guide 250 and the perforator 200 . The second guide 260 may be rotatably coupled to a point on the first guide 250 . And, the second guide 260 may be coupled to the perforator 200, and as a result, a virtual straight line parallel to the vertical direction of the leader 110 while passing a point on the first guide 250 as a rotation axis Thus, the casing 230 is rotatable.

일 실시예에서, 항타기(300)는 파일고정부(310), 진동발생부(320) 및 지지부(330)를 포함하고, 더 나아가 회전가이드(340)를 더 포함할 수 있다. 파일고정부(310)는 시트파일 등의 파일을 파지해서 고정하는 기능을 수행하고, 진동발생부(320)는 파일고정부(310)에 진동을 제공하여 시트파일이 파일공 내부로 원활하게 삽입될 수 있도록 하는 기능을 수행한다. 지지부(330)의 일측은 진동발생부(320) 및 파일고정부(310) 중 적어도 하나 이상에 결합될 수 있다.In one embodiment, the driving machine 300 includes a pile fixing unit 310 , a vibration generating unit 320 and a support unit 330 , and further may further include a rotation guide 340 . The pile fixing unit 310 performs a function of holding and fixing the file such as a sheet file, and the vibration generating unit 320 provides vibration to the pile fixing unit 310 so that the sheet file is smoothly inserted into the pile hole. functions that make it possible. One side of the support part 330 may be coupled to at least one of the vibration generating part 320 and the pile fixing part 310 .

일 실시예에서, 지지부(330)는 천공기(200)에 결합될 수 있고, 천공기(200)를 따라서 지지부(330)가 상승하거나 하강할 수 있다. 예컨대, 케이싱(230)의 일면에 케이싱레일(231)이 구비되고, 이 케이싱레일(231)에 지지부(330)가 슬라이딩 가능하게 결합될 수 있다. 이와 같이, 본 발명의 일 실시예에 따르면, 지지부(330)가 리더(110) 상에서 승강할 수 있게 되고, 그 결과 천공기(200)가 승강되지 않는 상태에서도 항타기(300)가 승강될 수 있고, 항타기(300)의 승강 동작을 통해서 시트파일을 다른 시트파일과 끼워 맞추는 등의 위치조절 작업의 효율성이 향상될 수 있다.In an embodiment, the support 330 may be coupled to the perforator 200 , and the support 330 may ascend or descend along the perforator 200 . For example, a casing rail 231 is provided on one surface of the casing 230 , and the support part 330 may be slidably coupled to the casing rail 231 . As such, according to an embodiment of the present invention, the support 330 can be lifted on the leader 110, and as a result, the driving machine 300 can be lifted even in a state in which the perforator 200 is not lifted, Through the lifting operation of the driving machine 300, the efficiency of the position adjustment operation, such as fitting the seat pile with another sheet pile, can be improved.

일 실시예에서, 리더(110)의 상하방향과 평행한 가상의 직선을 회전축으로 하여 천공기(200)가 회전될 수 있다. 일 실시예에서, 천공기(200)의 회전축은 스크류(220)의 회전축과 동일할 수 있다. 다른 실시예에서, 천공기(200)의 회전축은 제1 가이드(250) 상의 한 점을 지나면서 리더(110)의 상하방향과 평행한 가상의 직선일 수 있다. 일 예로써 도 5에 예시된 제1 가이드(250)상에서 제2 가이드(260)가 회전되는 점을 지나면서 리더(110)의 상하방향에 평행한 가상의 직선이 천공기(200)의 회전축일 수 있다.In one embodiment, the perforator 200 may be rotated using an imaginary straight line parallel to the vertical direction of the leader 110 as a rotation axis. In one embodiment, the axis of rotation of the perforator 200 may be the same as the axis of rotation of the screw 220 . In another embodiment, the rotation axis of the perforator 200 may be a virtual straight line parallel to the vertical direction of the leader 110 while passing a point on the first guide 250 . As an example, an imaginary straight line parallel to the vertical direction of the leader 110 while passing the point at which the second guide 260 is rotated on the first guide 250 illustrated in FIG. 5 may be the rotation axis of the perforator 200 . have.

이와 같이, 천공기(200)가 회전됨에 따라 항타기(300)의 위치가 조절될 수 있고, 그 결과 시트파일의 연결작업이나 천공작업을 진행하면서 차체나 리더(110) 자체를 이동시키지 않아도 시트파일의 위치를 세밀하고 편리하게 조절할 수 있게 된다.In this way, as the perforator 200 is rotated, the position of the driving machine 300 can be adjusted, and as a result, the seat pile is connected without moving the vehicle body or the leader 110 itself while performing the connection work or the perforation work of the sheet pile. The position can be precisely and conveniently adjusted.

일 실시예에서, 천공기(200)에서 케이싱(230)이 상하방향으로 길이가 긴 반면에, 오거(210)나 케이싱 결합부(215)는 케이싱(230)에 비해서는 상하방향의 길이가 상대적으로 짧은 편이다. 따라서, 케이싱(230)에 케이싱레일(231)이 구비되고, 이 케이싱레일(231)을 따라 지지부(330)가 승강할 수 있도록 결합될 경우, 천공기(200)가 정지되어 있는 상태에서 항타기(300)의 상승 및 하강 가능한 범위가 가장 커질 수 있다.In one embodiment, the casing 230 in the perforator 200 has a long length in the vertical direction, whereas the auger 210 or the casing coupling portion 215 has a length in the vertical direction relative to that of the casing 230 . It is rather short. Accordingly, when the casing rail 231 is provided on the casing 230 and the support part 330 is coupled to be elevated along the casing rail 231, the perforator 200 is stopped while the driving machine 300 ) may have the largest possible rise and fall range.

일 실시예에서, 리더(110)의 상하방향과 평행한 가상의 선을 회전축으로 하여 항타기(300)가 회전될 수 있도록 하면서 항타기(300)가 결합될 수 있다. 예컨대, 지지부(330) 상의 한 점을 지나면서 리더(110)의 상하방향과 평행한 가상의 직선을 회전축으로 하여 진동발생부(320) 또는 파일고정부(310)가 회동가능하게 결합될 수 있다.In one embodiment, the driving machine 300 may be coupled while allowing the driving machine 300 to be rotated using an imaginary line parallel to the vertical direction of the leader 110 as a rotation axis. For example, the vibration generating unit 320 or the pile fixing unit 310 may be rotatably coupled to a rotation axis using an imaginary straight line parallel to the vertical direction of the leader 110 as it passes through a point on the support unit 330 . .

일 실시예에서, 지지부(330)와 진동발생부(320) 사이 또는 지지부(330)와 파일고정부(310) 사이에 회전가이드(340)가 구비될 수 있다. 회전가이드(340)는 지지부(330) 상의 한 점을 중심으로 회동가능하게 결합될 수 있다. 그리고, 회전가이드(340)가 진동발생부(320) 또는 파일고정부(310)에 결합될 수 있으며, 그 결과, 지지부(330) 상의 한 점을 지나면서 리더(110)의 상하방향과 평행한 가상의 직선을 회전축으로 하여 케이싱(230)이 회동 가능해진다.In one embodiment, the rotation guide 340 may be provided between the support part 330 and the vibration generating part 320 or between the support part 330 and the pile fixing part 310 . The rotation guide 340 may be rotatably coupled around a point on the support 330 . In addition, the rotation guide 340 may be coupled to the vibration generating unit 320 or the pile fixing unit 310 , and as a result, while passing a point on the support unit 330 , parallel to the vertical direction of the leader 110 . The casing 230 is rotatable by using an imaginary straight line as a rotation axis.

이와 같이, 항타기(300)가 회전됨에 따라 시트파일의 위치가 조절될 수 있고, 그 결과 시트파일의 연결작업이나 천공작업을 진행하면서 차체나 리더(110) 자체를 이동시키지 않아도 시트파일의 위치를 세밀하고 편리하게 조절할 수 있게 된다.In this way, as the driving machine 300 rotates, the position of the seat pile can be adjusted, and as a result, the position of the seat pile can be adjusted without moving the vehicle body or the leader 110 itself while performing the connection or drilling of the sheet pile. It can be controlled precisely and conveniently.

일 실시예에서, 지지부(330)는 리더(110)에 결합될 수 있고, 리더(110)를 따라서 지지부(330)가 상승하거나 하강할 수 있다. 예컨대, 리더(110)의 일면에 리더보조레일(112)이 구비되고, 이 리더보조레일(112)에 지지부(330)가 슬라이딩 가능하게 결합될 수 있다. 이와 같이, 본 발명의 일 실시예에 따르면, 천공기(200)와는 별도로 지지부(330)가 리더(110) 상에서 승강할 수 있게 되고, 그 결과 천공기(200)가 승강되지 않는 상태에서도 항타기(300)의 승강이 가능해지고, 항타기(300)의 승강 동작을 통해서 시트파일을 다른 시트파일과 끼워 맞추는 등의 위치조절 작업의 효율성이 향상될 수 있다. 이때, 천공기(200)가 승강 가능하게 결합되는 리더레일(111)은 리더(110)의 다른 면에 구비될 수 있다.In an embodiment, the support 330 may be coupled to the leader 110 , and the support 330 may ascend or descend along the leader 110 . For example, a leader auxiliary rail 112 is provided on one surface of the leader 110 , and the support 330 may be slidably coupled to the leader auxiliary rail 112 . As such, according to an embodiment of the present invention, the support 330 is able to ascend and descend on the leader 110 separately from the perforator 200, and as a result, even in a state in which the perforator 200 does not elevate, the driving machine 300. is possible, and the efficiency of the position adjustment operation such as fitting the seat pile with another sheet pile through the lifting operation of the driving machine 300 can be improved. At this time, the leader rail 111 to which the perforator 200 is hoistably coupled may be provided on the other surface of the leader 110 .

일 실시예에서, 항타기(300)가 회전될 수 있으며, 지지부(330)와 회전가이드(340)의 결합관계 등은 전술한 바 있으므로 중복설명을 생략한다.In one embodiment, the driving machine 300 may be rotated, and the coupling relationship between the support part 330 and the rotation guide 340 has been described above, and thus a redundant description will be omitted.

일 실시예에서, 보조리더(120)가 리더(110)에 결합되고, 지지부(330)는 보조리더(120)에 결합되어 보조리더(120)를 따라서 지지부(330)가 상승하거나 하강할 수 있다. 예컨대, 리더(110)의 일면에 리더레일(111)이 구비되고, 리더(110)의 타면에 보조리더(120)가 결합되며, 보조리더(120)의 일면에 보조리더레일(121)이 구비되고, 이 보조리더레일(121)에 지지부(330)가 슬라이딩 가능하게 결합될 수 있다. 이와 같이, 본 발명의 일 실시예에 따르면, 천공기(200)와는 별도로 지지부(330)가 보조리더(120) 상에서 승강할 수 있게 되고, 그 결과 천공기(200)가 승강되지 않는 상태에서도 항타기(300)의 승강이 가능해지고, 항타기(300)의 승강동작을 통해서 시트파일을 다른 시트파일과 끼워 맞추는 등의 위치조절 작업의 효율성이 향상될 수 있다. 이때, 천공기(200)가 승강 가능하게 결합되는 리더레일(111)은 리더(110)의 다른 면에 구비될 수 있다.In an embodiment, the auxiliary reader 120 is coupled to the leader 110 , and the support unit 330 is coupled to the auxiliary reader 120 so that the support unit 330 may rise or fall along the auxiliary leader 120 . . For example, the leader rail 111 is provided on one surface of the leader 110 , the auxiliary reader 120 is coupled to the other surface of the leader 110 , and the auxiliary leader rail 121 is provided on one surface of the auxiliary reader 120 . and the support part 330 may be slidably coupled to the auxiliary leader rail 121 . As such, according to an embodiment of the present invention, the support 330 can be raised and lowered on the auxiliary leader 120 separately from the perforator 200, and as a result, the perforator 200 is not lifted even in a state where the driving machine 300 is not lifted. ) becomes possible, and the efficiency of the position adjustment operation such as fitting the seat pile with another sheet pile through the lifting operation of the driving machine 300 can be improved. At this time, the leader rail 111 to which the perforator 200 is hoistably coupled may be provided on the other surface of the leader 110 .

일 실시예에서, 보조리더(120)가 회전가능하게 리더(110)에 결합되고, 그 결과 항타기(300)가 회전될 수 있다. 이때, 리더(110) 상의 한 점을 지나면서 리더(110)와 평행한 가상의 선을 축으로 하여 회동될 수 있도록 보조리더(120)가 리더(110)에 결합될 수 있다. 이를 위하여 보조리더가이드(130)가 리더(110)와 보조리더(120) 사이에 개입될 수 있다.In one embodiment, the auxiliary leader 120 is rotatably coupled to the leader 110, as a result, the driving machine 300 can be rotated. At this time, the auxiliary reader 120 may be coupled to the leader 110 so that it can rotate about a virtual line parallel to the leader 110 as it passes through a point on the leader 110 . To this end, the auxiliary leader guide 130 may be interposed between the leader 110 and the auxiliary reader 120 .

일 실시예에서, 진동발생부(320) 또는 파일고정부(310)가 지지부(330) 상에서 수평방향으로 이동가능하게 결합될 수 있다. 예컨대, 도 5 및 도 6을 참조하면, 회전가이드(340)가 지지부(330) 상에 결합되는 위치가 수평방향으로 조정될 수 있으며, 더 나아가 회전가이드(340)가 지지부(330) 상에서 슬라이딩 가능하게 결합될 수 있다. 여기서 회전가이드(340)가 지지부(330)상의 한 점을 축으로 해서 회전되지 않으면서 회전가이드(340)가 수평방향으로 위치를 변경할 수도 있다. 즉, 회전가이드(340)에 해당되는 부분이 수평이동 가능할 뿐 회전되지 않는 실시예도 가능하다는 것이다.In an embodiment, the vibration generating unit 320 or the pile fixing unit 310 may be movably coupled to the support unit 330 in the horizontal direction. For example, referring to FIGS. 5 and 6 , the position at which the rotation guide 340 is coupled on the support part 330 can be adjusted in the horizontal direction, and further, the rotation guide 340 can be slidably on the support part 330 . can be combined. Here, while the rotation guide 340 is not rotated about a point on the support 330 as an axis, the position of the rotation guide 340 may be changed in the horizontal direction. That is, an embodiment in which the portion corresponding to the rotation guide 340 is horizontally movable but not rotated is also possible.

지지부(330)와 진동발생부(320) 또는 지지부(330)와 파일고정부(310) 사이의 위치관계는 전술한 다른 실시예에도 비슷한 원리로 적용될 수 있다.The positional relationship between the support part 330 and the vibration generating part 320 or the support part 330 and the pile fixing part 310 may be applied in a similar principle to the other embodiments described above.

이에 따라, 시트파일의 크기가 달라지거나, 파일공의 직경이 달라지는 경우에 진동발생부(320) 또는 파일고정부(310)를 수평방향으로 이동시킴으로써 그 변화에 효율적으로 대응할 수 있게 된다.Accordingly, when the size of the sheet pile changes or the diameter of the pile hole changes, by moving the vibration generating unit 320 or the pile fixing unit 310 in the horizontal direction, it is possible to efficiently respond to the change.

도 2를 참조하면, 일 실시예에서, 비트(240)는 장축(241)과 단축(242)을 가지도록 형성될 수 있다. 이때, 비트(240)의 장축(241)이 파일고정부(310)를 향하도록 비트(240)가 위치된 제1 상태에서 천공기(200)가 상승하면, 인접된 타설물에 비트(240)가 접촉되고, 비트(240)의 장축(241)이 파일 고정부를 향하지 않는 상태에서 천공기(200)가 상승하면, 인접된 타설물에 비트(240)가 접촉되지 않는 형상으로 비트(240)가 구현될 수 있다. 예컨대, 전체적으로 직사각형 형상을 갖는 비트(240)의 경우, 길이가 가장 긴 장축이 비트(240)의 회전범위의 직경(240R)과 동일하고, 결과적으로 제2 파일공(12)의 직경과 장축(241)의 길이가 같아진다. 본 실시예에 따른 천공 및 항타 작업의 동시수행이 가능한 파일 시공장치에서는 파일공 천공이 완료된 후 천공기(200)를 상승시키기 전에 비트(240)의 장축이 시트파일 방향, 즉 파일고정부(310) 방향을 향하지 않도록 비트(240)를 회전시킨 뒤 천공기(200)를 상승시킴으로써, 천공기(200)의 상승과정에서 비트(240)가 인접된 시트파일에 접촉되지 않게 할 수 있다.Referring to FIG. 2 , in one embodiment, the bit 240 may be formed to have a major axis 241 and a minor axis 242 . At this time, when the perforator 200 rises in the first state in which the bit 240 is positioned so that the long axis 241 of the bit 240 faces the pile fixing part 310, the bit 240 in the adjacent casting When the perforator 200 rises in a state where the long axis 241 of the bit 240 does not face the pile fixing part, the bit 240 is implemented in a shape in which the bit 240 does not contact the adjacent casting. can be For example, in the case of the bit 240 having a generally rectangular shape, the longest major axis is the same as the diameter 240R of the rotation range of the bit 240, and as a result, the diameter and the major axis of the second pile hole 12 ( 241) is the same length. In the pile construction apparatus capable of simultaneously performing drilling and driving work according to this embodiment, the long axis of the bit 240 is in the sheet pile direction, that is, the pile fixing part 310 before raising the drilling machine 200 after the pile drilling is completed. By rotating the bit 240 so as not to face the direction and then raising the perforator 200, the bit 240 may not contact the adjacent sheet pile in the process of raising the perforator 200.

종래의 일반적인 비트(240)는 전체적으로 원형 형상으로 이루어지는 것이 통상적이었다. 그리고, 비트(240)는 케이싱(230)의 직경보다 큰 직경으로 이루어지는 것이 일반적이었다. 예컨대, 케이싱(230)은 457mm, 508mm, 560mm 등의 직경을 가질 수 있으며, 이 각각의 케이싱(230) 직경에 대하여, 460mm, 512mm, 570mm 등의 직경으로 이루어지는 비트(240)가 스크류(220)에 결합될 수 있다는 것이다. 본 발명의 일 실시예에 따르면, 제1 파일공(11)으로의 제1 시트파일(21)의 삽입 과정과 제2 파일공(12)의 천공과정이 동시에 진행되는데, 종래의 일반적인 원형 비트(240)를 사용할 경우, 천공기(200)를 상승시키는 과정에서 비트(240)가 제1 시트파일(21)에 걸려서 상승되지 못하거나 제1 시트파일(21)을 손상시키면서 상승되는 상황이 발생될 수 있다. 본 발명의 일 실시예에 따르면, 비트(240)가 장축(241)과 단축(242)을 갖도록 형성되므로, 충분한 직경의 파일공을 형성할 수 있으면서도, 천공기(200)의 상승 과정에서 인접 시트파일을 손상시키거나 인접 시트파일에 걸려서 비트(240)가 상승되지 못하는 상황이 발생되지 않는다.The conventional general bit 240 is generally made of a circular shape as a whole. And, it is common that the bit 240 has a larger diameter than the diameter of the casing 230 . For example, the casing 230 may have a diameter of 457 mm, 508 mm, 560 mm, etc., for each casing 230 diameter, a bit 240 having a diameter of 460 mm, 512 mm, 570 mm, etc. is a screw 220 that it can be coupled to According to an embodiment of the present invention, the insertion process of the first sheet pile 21 into the first pile hole 11 and the drilling process of the second pile hole 12 are carried out at the same time, and a conventional general circular bit ( 240), in the process of raising the perforator 200, the bit 240 is caught on the first sheet pile 21 and cannot be lifted, or a situation may occur that rises while damaging the first sheet pile 21. have. According to an embodiment of the present invention, since the bit 240 is formed to have a major axis 241 and a minor axis 242, it is possible to form a pile hole of sufficient diameter, while the adjacent sheet pile in the process of rising of the perforator 200 A situation in which the bit 240 cannot be raised due to damage to or caught in an adjacent sheet pile does not occur.

일 실시예에서, 케이싱(230)의 하부에 가이드부(270)가 구비될 수 있다. 이때, 가이드부(270)는 인접한 시트파일(예컨대, 도 3에서 제1 시트파일(21))에 슬라이딩 가능하게 결합될 수 있다. 한편, 제1 시트파일(21)의 일단이 기초 시트파일(20)의 일단에 끼워 맞춰진 상태로 제1 시트파일(21)의 삽입과정이 진행될 수 있다. 이에 따라, 제1 시트파일(21)의 삽입과 동시에 이루어지는 제2 파일공(12)의 천공 과정에서, 제1 시트파일(21)은 기초 시트파일(20)에 의하여 삽입방향이 가이드되고, 케이싱(230)의 하강방향은 제1 시트파일(21)에 의하여 삽입방향이 가이드될 수 있다.In one embodiment, the guide part 270 may be provided under the casing 230 . In this case, the guide part 270 may be slidably coupled to an adjacent sheet pile (eg, the first sheet pile 21 in FIG. 3 ). On the other hand, the insertion process of the first sheet pile 21 may proceed in a state where one end of the first sheet pile 21 is fitted to one end of the basic sheet pile 20 . Accordingly, in the drilling process of the second pile hole 12 made simultaneously with the insertion of the first sheet pile 21, the insertion direction of the first sheet pile 21 is guided by the basic sheet pile 20, and the casing In the descending direction of the 230 , the insertion direction may be guided by the first sheet pile 21 .

도 8을 참조하면, 본 발명의 일 실시예에 따른 천공 및 항타 작업의 동시수행이 가능한 파일 시공장치를 이용하여 시트파일을 삽입하는 기초공사는 다음과 같이 진행될 수 있다.Referring to FIG. 8 , the foundation construction for inserting the sheet pile using the pile construction apparatus capable of simultaneously performing drilling and driving work according to an embodiment of the present invention may be performed as follows.

먼저, 기초 파일공(10)을 형성하여 기초 시트파일(20)을 삽입한다. 이때, 기초 시트파일(20)의 상부를 파일고정부(310)로 파지시켜서 기초 시트파일(20)을 항타기(300)에 고정한 뒤 기초 시트파일(20)을 기초 파일공(10) 상방에 정위치시킨다. 이때, 제1 파일공(11)이 형성될 위치에 천공기(200)를 위치시킬 수 있다. 이 과정에서 천공기(200)를 회전시키거나 항타기(300)를 회전시킴으로써 천공기(200)와 항타기(300)의 정위치를 잡는 과정이 효율적으로 진행될 수 있다. 또한, 진동발생부(320) 또는 파일고정부(310)를 지지부(330) 상에서 수평이동시키는 방식으로 정밀한 위치제어가 가능하다.First, the foundation pile hole 10 is formed and the foundation sheet pile 20 is inserted. At this time, the upper part of the foundation sheet pile 20 is held by the pile fixing part 310 to fix the basic sheet pile 20 to the driving machine 300 and then the foundation sheet pile 20 is fixed to the foundation pile hole 10 above. place it In this case, the perforator 200 may be positioned at a position where the first pile hole 11 is to be formed. In this process, by rotating the drilling machine 200 or rotating the driving machine 300 , the process of holding the correct positions of the drilling machine 200 and the driving machine 300 can be performed efficiently. In addition, precise position control is possible by horizontally moving the vibration generating unit 320 or the pile fixing unit 310 on the support unit 330 .

다음으로, 스크류(220)와 비트(240)를 회전시켜서 제1 파일공(11)을 천공하는 동시에 진동발생부(320)를 작동시켜서 기초 시트파일(20)을 기초 파일공(10)으로 삽입한다. Next, by rotating the screw 220 and the bit 240 to drill the first pile hole 11 and at the same time operate the vibration generating unit 320 to insert the foundation sheet pile 20 into the foundation pile hole (10) do.

다음으로, 기초 시트파일(20)을 파일고정부(310)에서 분리하고 천공기(200)와 항타기(300)를 상승시킨다. 이때, 비트(240)의 장축(241)이 기초 시트파일(20)을 향하지 않도록 조정한 뒤 천공기(200)를 상승시킨다.Next, the base sheet pile 20 is separated from the pile fixing part 310 and the perforator 200 and the driving machine 300 are raised. At this time, after adjusting so that the long axis 241 of the bit 240 does not face the base sheet pile 20, the perforator 200 is raised.

다음으로, 파일고정부(310)에 제1 시트파일(21)을 파지시키고 제1 시트파일(21)의 일측면 하단부가 기초 시트파일(20)의 일측면 상단부에 맞물려지도록 하면서 제1 시트파일(21)을 제1 파일공(11) 상에 정위치시킨다. 이 과정에서 천공기(200) 역시 제2 파일공(12)이 천공될 위치로 정위치된다. 이 과정에서 천공기(200)를 회전시키거나 항타기(300)를 회전시킴으로써 천공기(200)와 항타기(300)의 정위치를 잡는 과정이 효율적으로 진행될 수 있다. 또한, 진동발생부(320) 또는 파일고정부(310)를 지지부(330) 상에서 수평이동시키는 방식으로 정밀한 위치제어가 가능하다.Next, the first sheet pile while holding the first sheet pile 21 in the pile fixing unit 310 and engaging the lower end of one side of the first sheet pile 21 with the upper end of one side of the base sheet pile 20 (21) is placed on the first pile hole (11). In this process, the perforator 200 is also positioned at a position where the second pile hole 12 is to be perforated. In this process, by rotating the drilling machine 200 or rotating the driving machine 300 , the process of holding the correct positions of the drilling machine 200 and the driving machine 300 can be performed efficiently. In addition, precise position control is possible by horizontally moving the vibration generating unit 320 or the pile fixing unit 310 on the support unit 330 .

다음으로, 스크류(220)와 비트(240)를 회전시켜서 제2 파일공(12)을 천공하는 동시에 진동발생부(320)를 작동시켜서 제1 시트파일(21)을 제1 파일공(11)으로 삽입한다. Next, by rotating the screw 220 and the bit 240 to drill the second pile hole 12 and at the same time operate the vibration generating unit 320 to move the first sheet pile 21 to the first pile hole 11 . insert into

다음으로, 제1 시트파일(21)을 파일고정부(310)에서 분리하고 천공기(200)와 항타기(300)를 상승시킨다. 이때, 비트(240)의 장축이 기초 시트파일(20)을 향하지 않도록 조정한 뒤 천공기(200)를 상승시킨다.Next, the first sheet pile 21 is separated from the pile fixing part 310 and the perforator 200 and the driving machine 300 are raised. At this time, the long axis of the bit 240 is adjusted so as not to face the base sheet pile 20, and then the perforator 200 is raised.

다음으로, 제2 파일공(12)에 대한 제2 시트파일(22)의 삽입, 제3 파일공(13)의 천공이 전술한 바와 비슷한 방식으로 수행될 수 있다.Next, the insertion of the second sheet pile 22 into the second pile hole 12 and the drilling of the third pile hole 13 may be performed in a manner similar to that described above.

한편, 시트파일들은 방향이 뒤집히면서 파일공에 삽입된다. 예컨대, 도 8에서 기초 시트파일(20)은 도면상 상방향을 향해서 열린 ㄷ자 모양으로 배치되고, 제1 시트파일(21)은 도면상 하방향을 향해서 열린 ㄷ자 모양으로 배치되며, 제2 시트파일(22)은 다시 도면상 상방향을 향해서 열린 ㄷ자 모양으로 배치된다. 일 실시예에서, 파일고정부(310)에는 시트파일을 파지할 수 있는 파지부가 2개 구비될 수 있다. 예컨대, 도 8을 기준으로 제1 시트파일(21)이 파지되는 파지부와 제2 시트파일(22)이 파지되는 파지부가 서로 이격된 위치에 각각 구비될 수 있다는 것이다. 이에 따라, 시트파일의 교체 과정에서 항타기(300)의 위치 변동을 최소화할 수 있게 된다.On the other hand, the sheet piles are inserted into the pile ball while the direction is reversed. For example, in FIG. 8, the basic sheet pile 20 is arranged in a U-shape opened toward the top on the drawing, and the first sheet pile 21 is disposed in a U-shape opened toward the bottom on the drawing, and the second sheet pile (22) is again arranged in a U-shape that opens upward in the drawing. In one embodiment, the pile fixing unit 310 may be provided with two holding units capable of holding the sheet pile. For example, with reference to FIG. 8 , the gripping part by which the first sheet pile 21 is gripped and the gripping part by which the second sheet pile 22 is gripped may be provided at positions spaced apart from each other. Accordingly, it is possible to minimize the position change of the driving machine 300 in the replacement process of the seat pile.

이상과 같이 구성된 본 발명의 일 실시예에 따른 천공 및 항타 작업의 동시수행이 가능한 파일 시공장치는 파일을 삽입하기 위한 파일 파일공의 천공작업과 파일을 파일공에 삽입하는 항타작업을 동시에 실시할 수 있도록 함으로써 파일 시공에 소요되는 시간을 절감할 수 있고, 시트파일의 설치방향, 시트파일의 설치위치 등을 손쉽게 조절하면서도 시공 효율성을 개선할 수 있다. 또한, 종래에는 파일공을 천공하고 스크류(220)를 파일공에서 빼낸 뒤 시트파일을 인양해서 파일공에 삽입하는 방식으로 작업이 진행되었고, 이 과정에서 파일공 내부로 흙이나 자갈 등이 유입됨에 따라 요구되는 정심도 까지 시트파일이 삽입되지 않거나, 삽입과정에 많은 시간이 소요되는 문제가 있었다. 그러나, 본 발명의 일 실시예에 따른 천공 및 항타 작업의 동시수행이 가능한 파일 시공장치는 제1 파일공으로 제1 시트파일을 삽입하는 동시에 제1 파일공에 인접한 위치에 제2 파일공이 천공되므로, 제1 파일공 내부에 존재하는 흙이나 자갈 등의 방해물이 제2 파일공 쪽으로 이동될 수 있으며, 그 결과 제1 파일공에 대한 제1 시트파일의 삽입과정이 종래보다 쉽고 신속하게 진행될 수 있다.The pile construction apparatus capable of simultaneously performing drilling and driving work according to an embodiment of the present invention configured as described above performs the drilling operation of the pile pile hole for inserting the file and the driving operation of inserting the file into the pile hole at the same time. By doing so, the time required for pile construction can be reduced, and construction efficiency can be improved while easily adjusting the installation direction of the sheet pile and the installation position of the sheet pile. In addition, in the prior art, the work was carried out in such a way that, after drilling a pile hole and removing the screw 220 from the pile hole, the sheet pile was lifted and inserted into the pile hole, in this process, soil or gravel was introduced into the pile hole. There was a problem that the sheet file was not inserted up to the required precision, or that the insertion process took a lot of time. However, the pile construction apparatus capable of simultaneously performing drilling and driving work according to an embodiment of the present invention inserts the first sheet pile into the first pile hole and at the same time, the second pile hole is drilled at a position adjacent to the first pile hole, Obstacles such as soil or gravel existing inside the first pile hole may be moved toward the second pile hole, and as a result, the insertion process of the first sheet pile into the first pile hole may be performed more easily and quickly than in the prior art.

10 : 기초 파일공
11 : 제1 파일공
12 : 제2 파일공
13 : 제3 파일공
20 : 기초 시트파일
21 : 제1 시트파일
22 : 제2 시트파일
110 : 리더
111: 리더레일
112 : 리더보조레일
120 : 보조리더
121 : 보조리더레일
130 : 보조리더가이드
200 : 천공기
210 : 오거
215 : 케이싱 결합부
220 : 스크류
230 : 케이싱
231 : 케이싱레일
240 : 비트
250 : 제1 가이드
260 : 제2 가이드
270 : 가이드부
300 : 항타기
310 : 파일고정부
320 : 진동발생부
330 : 지지부
340 : 회전가이드
10: basic pile ball
11: first file ball
12: second file ball
13: 3rd file ball
20: basic sheet file
21: first sheet file
22: second sheet file
110 : leader
111: leader rail
112: leader auxiliary rail
120: auxiliary leader
121: auxiliary leader rail
130: auxiliary leader guide
200: perforator
210 : Auger
215: casing coupling part
220: screw
230: casing
231: casing rail
240: bit
250: first guide
260: second guide
270: guide part
300: driving
310: pile fixing part
320: vibration generating unit
330: support
340: rotation guide

Claims (7)

리더, 천공기 및 항타기를 포함하는 천공 및 항타 작업의 동시수행이 가능한 파일 시공장치에 있어서,
상기 천공기는,
상기 리더를 따라 승강하는 오거;
상기 오거의 하방에 결합되는 스크류; 및
기둥 형상으로 이루어져 상기 스크류가 내측에 위치되도록 상기 오거의 하방에 구비되는 케이싱;을 포함하고,
상기 항타기는,
타설물을 고정하는 파일고정부;
상기 파일고정부에 진동을 제공하는 진동발생부; 및
상기 파일고정부 및 상기 진동발생부 중 적어도 하나에 결합되어 수직방향으로 승강하는 지지부;를 포함하되,
상기 항타기가 하강하면서 상기 타설물을 제1 파일공에 삽입하는 과정에서 상기 천공기가 하강하면서 제2 파일공을 천공하는 것을 특징으로 하는 천공 및 항타 작업의 동시수행이 가능한 파일 시공장치.
In the pile construction device capable of simultaneously performing drilling and driving work including a leader, a drilling machine and a driving machine,
The perforator is
an auger ascending and descending along the leader;
a screw coupled to a lower portion of the auger; and
A casing formed in a column shape and provided below the auger so that the screw is positioned inside; and
The cruiser is
Pile fixing unit for fixing the cast;
a vibration generating unit for providing vibration to the pile fixing unit; and
Including; a support part coupled to at least one of the pile fixing part and the vibration generating part to ascend and descend in a vertical direction;
A pile construction apparatus capable of simultaneously performing drilling and driving work, characterized in that the drilling machine descends and drills the second pile hole while the drilling machine descends in the process of inserting the cast object into the first pile hole while the driving machine descends.
청구항 1에 있어서,
상기 항타기는 상기 리더의 상하방향과 평행한 가상의 선을 축으로 회전가능하게 상기 지지대에 결합되는 것을 특징으로 하는 천공 및 항타 작업의 동시수행이 가능한 파일 시공장치.
The method according to claim 1,
The driving machine is a pile construction device capable of simultaneously performing drilling and driving work, characterized in that it is coupled to the support rotatably about a virtual line parallel to the vertical direction of the leader.
청구항 1에 있어서,
상기 지지부는 상기 리더에 구비되는 리더보조레일에 결합되어 상기 리더보조레일을 따라 승강하고,
상기 지지부 상의 한 점을 지나면서 상기 리더의 상하방향과 평행한 가상의 직선을 회전축으로 하여 상기 진동발생부 또는 상기 파일고정부가 회동가능하게 결합되는 것을 특징으로 하는 천공 및 항타 작업의 동시수행이 가능한 파일 시공장치.
The method according to claim 1,
The support part is coupled to the leader auxiliary rail provided in the leader and ascends and descends along the leader auxiliary rail,
Simultaneous performance of drilling and driving work is possible, characterized in that the vibration generating part or the pile fixing part is rotatably coupled to a rotation axis using an imaginary straight line parallel to the vertical direction of the leader while passing a point on the support part file construction equipment.
청구항 1에 있어서,
상기 리더에 결합되는 보조리더를 더 포함하고,
상기 지지부는 상기 보조리더에 구비되는 보조리더레일에 결합되어 상기 보조리더레일을 따라 승강하고,
상기 리더 상의 한 점을 지나면서 상기 리더와 평행한 가상의 선을 축으로 하여 상기 보조리더가 회동 가능하도록 상기 리더와 상기 보조리더가 결합되는 것을 특징으로 하는 천공 및 항타 작업의 동시수행이 가능한 파일 시공장치.
The method according to claim 1,
Further comprising an auxiliary leader coupled to the leader,
The support part is coupled to an auxiliary leader rail provided in the auxiliary leader and ascends and descends along the auxiliary leader rail;
A file capable of simultaneously performing drilling and driving work, characterized in that the leader and the auxiliary leader are combined so that the auxiliary leader can rotate about an imaginary line parallel to the leader while passing a point on the leader construction device.
청구항 1에 있어서,
상기 스크류의 하부에 결합되는 비트를 더 포함하되,
상기 비트는 장축과 단축을 가지며, 상기 비트의 장축이 상기 파일고정부를 향하도록 상기 비트가 위치된 제1 상태에서 상기 천공기가 상승하면, 인접된 타설물에 상기 비트가 접촉되고, 상기 비트의 장축이 상기 파일고정부를 향하지 않는 상태에서 상기 천공기가 상승하면, 인접된 타설물에 상기 비트가 접촉되지 않는 것을 특징으로 하는 천공 및 항타 작업의 동시수행이 가능한 파일 시공장치.
The method according to claim 1,
Further comprising a bit coupled to the lower portion of the screw,
The bit has a long axis and a short axis, and when the perforator rises in the first state in which the bit is positioned so that the long axis of the bit faces the pile fixing part, the bit comes into contact with an adjacent casting, When the drilling machine rises in a state where the long axis does not face the pile fixing part, the pile construction apparatus capable of simultaneously performing drilling and driving work, characterized in that the bit does not come into contact with the adjacent casting.
청구항 1에 있어서,
상기 파일고정부에는 제1 시트파일을 파지하는 제1 파지부 및 상기 제1 파지부로부터 이격되어 구비되며 제2 시트파일을 파지하는 제2 파지부가 구비되는 것을 특징으로 하는 천공 및 항타 작업의 동시수행이 가능한 파일 시공장치.
The method according to claim 1,
Simultaneous drilling and driving operation, characterized in that the pile fixing part is provided with a first gripping part for gripping the first sheet pile and a second gripping part spaced apart from the first gripping part and gripping the second sheet pile. A file construction device that can be carried out.
청구항 1항 내지 청구항 6 중 어느 한 항에 있어서,
상기 진동발생부 또는 상기 파일고정부가 상기 지지부 상에서 수평방향으로 이동가능하게 결합되는 것을 특징으로 하는 천공 및 항타 작업의 동시수행이 가능한 파일 시공장치.
7. The method according to any one of claims 1 to 6,
Pile construction apparatus capable of simultaneously performing drilling and driving work, characterized in that the vibration generating part or the pile fixing part is coupled to be movable in the horizontal direction on the support part.
KR1020210012023A 2020-06-26 2021-01-28 File construction apparatus capable of simultaneous achievement of hole-boring and vibrating KR102637552B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020210012023A KR102637552B1 (en) 2020-06-26 2021-01-28 File construction apparatus capable of simultaneous achievement of hole-boring and vibrating

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR1020200078597A KR102215187B1 (en) 2020-06-26 2020-06-26 File construction apparatus capable of simultaneous achievement of hole-boring and vibrating
KR1020210012023A KR102637552B1 (en) 2020-06-26 2021-01-28 File construction apparatus capable of simultaneous achievement of hole-boring and vibrating

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR1020200078597A Division KR102215187B1 (en) 2020-06-26 2020-06-26 File construction apparatus capable of simultaneous achievement of hole-boring and vibrating

Publications (2)

Publication Number Publication Date
KR20220000803A true KR20220000803A (en) 2022-01-04
KR102637552B1 KR102637552B1 (en) 2024-02-19

Family

ID=74560613

Family Applications (2)

Application Number Title Priority Date Filing Date
KR1020200078597A KR102215187B1 (en) 2020-06-26 2020-06-26 File construction apparatus capable of simultaneous achievement of hole-boring and vibrating
KR1020210012023A KR102637552B1 (en) 2020-06-26 2021-01-28 File construction apparatus capable of simultaneous achievement of hole-boring and vibrating

Family Applications Before (1)

Application Number Title Priority Date Filing Date
KR1020200078597A KR102215187B1 (en) 2020-06-26 2020-06-26 File construction apparatus capable of simultaneous achievement of hole-boring and vibrating

Country Status (1)

Country Link
KR (2) KR102215187B1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102671627B1 (en) 2023-11-06 2024-06-03 주식회사 엠케이건설산업 Prevention of dislocation and safety fixation when entering the casing of drilling equipment according to ground strength
CN117248828B (en) * 2023-11-15 2024-02-20 西昌学院 Foundation pile drilling equipment for building foundation construction

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61282516A (en) * 1985-06-07 1986-12-12 Kazuharu Fujito Construction work for underground continuous wall
KR20120016737A (en) * 2010-08-17 2012-02-27 백남진 Ground boring system
KR101723512B1 (en) * 2016-10-05 2017-04-05 (유)나라기초건설 Pile construction apparatus for drilling and piling
KR101808960B1 (en) * 2016-10-26 2017-12-13 박인수 Sheet pile construction apparatus using multi-axled auger screw
KR102016516B1 (en) * 2017-07-02 2019-08-30 김오중 Piercer with adjustable hammer position

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61282516A (en) * 1985-06-07 1986-12-12 Kazuharu Fujito Construction work for underground continuous wall
KR20120016737A (en) * 2010-08-17 2012-02-27 백남진 Ground boring system
KR101723512B1 (en) * 2016-10-05 2017-04-05 (유)나라기초건설 Pile construction apparatus for drilling and piling
KR101808960B1 (en) * 2016-10-26 2017-12-13 박인수 Sheet pile construction apparatus using multi-axled auger screw
KR102016516B1 (en) * 2017-07-02 2019-08-30 김오중 Piercer with adjustable hammer position

Also Published As

Publication number Publication date
KR102637552B1 (en) 2024-02-19
KR102215187B1 (en) 2021-02-15

Similar Documents

Publication Publication Date Title
AU2010253666B2 (en) Method and apparatus for drilling large-diameter hole in ground
KR102299439B1 (en) File construction apparatus capable of simultaneous achievement of hole-boring work and vibrating
KR20220000803A (en) File construction apparatus capable of simultaneous achievement of hole-boring and vibrating
CN101736755A (en) Clean water hole pile foundation constructing method
CN111734309A (en) Guiding device for construction of SMW method pile, and SMW method pile construction equipment and method
WO2023109014A1 (en) Construction apparatus and construction method for steel pipe pile in bare rock riverbed
CN111042104A (en) Method for constructing diaphragm wall at existing underground structure
KR20170142353A (en) Stone quarrying equipment and method for quarrying stone using the same
JP2018024988A (en) Excavation method od sediment and excavator
KR101615810B1 (en) Sheet Pile Construction Apparatus For Perforating and Pile Driver Work
JP2779389B2 (en) Rotary press-in device for steel pipe piles for settlement settlement
JP4635725B2 (en) Pile construction system
JP3451275B2 (en) Deep foundation excavator
KR102586201B1 (en) File construction apparatus
KR101044485B1 (en) Casing for deep depth filing hole
JP3946992B2 (en) Rock drilling system in caisson method.
JP4064984B2 (en) Drilling method of hole in low head space
JP2000008369A (en) Earth retaining wall forming method in pit excavating construction method
JP2019132088A (en) Excavation method
JP2813061B2 (en) Excavation method of continuous underground wall and its excavator
JP3836712B2 (en) Drilling rig
KR20170100498A (en) Metfhod and device for constructing a foundation, and foundation
CN117307034A (en) Drilling tool for reinforced concrete bored pile
KR101696890B1 (en) Rotatable auger drill
JPH03125722A (en) Caisson settling method and dredging device therefor

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant