KR20160085609A - Dual crane spreader beam system for module lifting fpso and the ship or offshore platform including the same - Google Patents

Dual crane spreader beam system for module lifting fpso and the ship or offshore platform including the same Download PDF

Info

Publication number
KR20160085609A
KR20160085609A KR1020150002824A KR20150002824A KR20160085609A KR 20160085609 A KR20160085609 A KR 20160085609A KR 1020150002824 A KR1020150002824 A KR 1020150002824A KR 20150002824 A KR20150002824 A KR 20150002824A KR 20160085609 A KR20160085609 A KR 20160085609A
Authority
KR
South Korea
Prior art keywords
hook
crane
wire
pin joint
tension bar
Prior art date
Application number
KR1020150002824A
Other languages
Korean (ko)
Other versions
KR101678520B1 (en
Inventor
조동현
강민제
이철우
Original Assignee
대우조선해양 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 대우조선해양 주식회사 filed Critical 대우조선해양 주식회사
Priority to KR1020150002824A priority Critical patent/KR101678520B1/en
Publication of KR20160085609A publication Critical patent/KR20160085609A/en
Application granted granted Critical
Publication of KR101678520B1 publication Critical patent/KR101678520B1/en

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/62Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means comprising article-engaging members of a shape complementary to that of the articles to be handled
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B73/00Building or assembling vessels or marine structures, e.g. hulls or offshore platforms
    • B63B9/00
    • B63B9/06
    • B63B2009/00
    • B63B2009/06

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Ocean & Marine Engineering (AREA)
  • Jib Cranes (AREA)

Abstract

The present invention relates to a dual offshore crane spreader beam system for mounting an FPSO module which can maximize lifting capacity of a crane by offsetting horizontal load generated in the crane when a heavy object is lifted using two cranes. The dual offshore crane spreader beam system includes: multiple hook beams wherein a hook connected to a dual crane by a wire is connected to a hook pin joint; a compression beam which connects the hook beam and a hook beam by an upper pin joint; a wire connected to a lower part of the hook beam; a tension bar controlling the horizontal load by being connected to a lower end of the wire; and a link plate connecting a module by being connected to both ends of the tension bar by a lower pin joint.

Description

FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템 및 이를 가지는 선박 또는 해양구조물{DUAL CRANE SPREADER BEAM SYSTEM FOR MODULE LIFTING FPSO AND THE SHIP OR OFFSHORE PLATFORM INCLUDING THE SAME}TECHNICAL FIELD [0001] The present invention relates to a dual-beam crane spreader beam system for mounting an FPSO module, and a ship or an offshore structure having the same.

본 발명은 FPSO 모듈 듀얼 탑재용 해상 크레인 스프레더 빔 시스템에 관한 것으로서, 보다 상세하게는 두 대의 크레인을 이용한 고중량물의 인양 시 크레인에 발생되는 수평 하중을 상쇄시켜 크레인의 인양 하중을 최대화할 수 있도록 하는 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템에 관한 것이다.The present invention relates to a floating crane spreader beam system for dual loading on an FPSO module, and more particularly, to a crane spreading beam system for loading a crane by maximizing a lifting load of a crane by canceling a horizontal load generated in a crane when lifting a heavy object using two cranes The present invention relates to a dual overhead crane spreader beam system for mounting an FPSO module.

일반적으로 최근 들어, 공업화와 산업화가 가속화함에 따라 천연자원(석유, 천연가스 등)의 사용량이 점차 증가하고 있으며, 매장량이 한정된 천연자원의 안정적인 생산과 공급이 대단히 중요한 문제로 떠오르고 있다.In recent years, as industrialization and industrialization have accelerated, the use of natural resources (petroleum, natural gas, etc.) is gradually increasing, and stable production and supply of natural resources with limited reserves are becoming very important.

이들 중 FPSO(부유식 원유/가스 생산저장하역설비: FLATING PRODUCTION STORAGE AND OFFLOADING)는 현재 유전에서 원유를 생산하기 위해 사용되고 있으며, LNG FPSO는 근래 들어 유전의 고갈 및 청정연료에 대한 수요의 증가로 인해 그 개발이 활발히 이루어지고 있다.Among them, FPSO (Floating Production Storage and Offloading Facility) is currently being used to produce crude oil from oilfields, and LNG FPSO has been used in recent years due to depletion of oilfields and increased demand for clean fuel The development is being actively carried out.

상기와 같은 FPSO는 심해저 유전 개발에 있어서 해상에 부유한 상태로 원유나 천연 가스를 정제, 저장 및 하역할 수 있어 부유식 해상 정유공장이라고 할 수 있다.The above-mentioned FPSO can be said to be a floating marine refinery because it can refine, store and unload crude oil or natural gas floating in the sea in the development of the deep sea water oil field.

이를 위해, 상기 FPSO에는 가스압축공정, 주수, 또는 가스주입시스템 등과 같은 원유 생산설비가 설치되며, 분리된 원유는 화물창에 보관되었다가 하역시스템을 통하여 셔틀탱커로 이송되는 구조를 갖는다.To this end, the FPSO is equipped with a crude oil production facility such as a gas compression process, a sump or a gas injection system, and the separated crude oil is stored in a cargo hold and then transferred to the shuttle tanker through the cargo system.

이와 같은 상기 FPSO의 선체 상부에는 상부모듈(TOPSIDE MODULE)이라 불리는 상부 원유정제설비가 마련되어 원유/가스를 효율적으로 생산하기 위한 여러 단계의 공정을 거치게 된다.An upper crude oil refining facility called TOPSIDE MODULE is provided on the upper portion of the FPSO so as to perform various steps for efficiently producing crude oil / gas.

이러한 공정에는 분리, 수처리(WATER TREATMENT), 수분제거(DEHYDRATION), 압축을 포함하는 가스처리(GAS TREATMENT) 등이 포함된다.Such processes include separation, water treatment, dehydration, gas treatment including compression, and the like.

상기 상부모듈은 FPSO의 선체와 달리 여러 곳에서 별도로 나뉘어 제작되는데, 상부모듈의 구조는 선박의 경우와 달리 강판(STEEL PLATE)보다 관상(TUBULAR) 구조로 이루어진다.Unlike the FPSO hull, the upper module is divided into several parts. The upper module has a tubular structure rather than a steel plate.

이와 같은 상부모듈은 제각기 2,000 ~ 3,000톤의 중량을 갖는 10~16개의 모듈 형태로 설계, 제작된 후 해상 크레인을 통해 FPSO의 선체 위에 설치된다.These upper modules are designed and manufactured in the form of 10 ~ 16 modules each weighing 2,000 ~ 3,000 tons, and then installed on the hull of the FPSO through a floating crane.

최근 FPSO 및 F-LNG 모듈은 4,000톤 이상의 대형 모듈이 만들어지고 있는 추세이다.Recently, FPSO and F-LNG modules have been making large modules of 4,000 tons or more.

이를 위해 해상 크레인은 상부모듈을 인양하여 FPSO의 선체 위로 상부모듈을 운반해 상부모듈을 정해진 위치에 탑재시키게 된다.For this purpose, the floating crane lifts the upper module and carries the upper module over the hull of the FPSO, and loads the upper module at the predetermined position.

FPSO 모듈 중량이 약 4,000톤 이상 되기 때문에 기존의 3,600톤 해상크레인으로는 리프팅 수용능력을 초과하게 되며, 4개의 리프팅 포인트를 가진 탑사이드 모듈을 리프팅하기 위한 빔(beam) 개발의 필요성이 인식된다.Since the FPSO module weighs more than 4,000 tons, the existing 3,600-ton offshore cranes exceed the lifting capacity and the need to develop a beam to lift the topside module with four lifting points is recognized.

통상 1대의 해상 크레인에는 4개의 후크(hook)가 있고 2대의 크레인 사용시 8개의 후크를 가지게 된다.Normally, one marine crane has four hooks, and two marine cranes have eight hooks.

도 1 내지 도 3은 종래의 탑사이드 모듈을 탑재하기 위한 스프레더 빔을 도시한 정면도이다.1 to 3 are front views showing a spreader beam for mounting a conventional top side module.

도 1 내지 도 3에서와 같이 종래 기술의 해상 크레인(10)에 와이어(W)로 연결되는 스프레더 빔(20)은 구조적으로 모듈(30)의 하중에 맞추기 위해 과다한 크기 및 과중량의 구조를 가지게 됨으로써 스프레더 빔(20)에 큰 벤딩(bending)이 발생되며 수평 하중 발생시 상쇄시키기 어려운 문제점과 함께 8개의 후크(21)에 원하는 하중을 발생시킬 수 없는 문제점이 있었다.1 to 3, the spreader beam 20 connected with the wire (W) to the conventional floating crane 10 has a structure of excessive size and overweight in order to structurally match the load of the module 30 There is a problem that a large bending is generated in the spreader beam 20 and it is difficult to cancel the horizontal load when the horizontal load is generated and a desired load can not be generated in the eight hooks 21. [

또한, 종래에는 해상 크레인 폭에 비해 리프팅 포인트가 좁아서 예각으로 인한 수평 하중이 발생하게 되는데, 수평 하중은 전체 크레인 후크 로드(hook load)에 영향을 미치게 되며, 수평 하중에 의해 원하는 하중을 만들 수가 없어 해상 크레인 인양 하중에 영향을 주게 되는 문제점이 있었다.In addition, in the past, the lifting point is narrower than the marine crane width, so that a horizontal load is generated due to an acute angle. The horizontal load affects the hook load of the entire crane, and a desired load can not be created by the horizontal load There is a problem that the lifting load of the marine crane is influenced.

본 발명은 상기한 문제점을 해결하기 위하여 안출한 것으로, 그 목적은 와이어 및 스프레더 빔 구조가 연결되는 다수의 포인트에 한 개의 핀조인트(pin joint)를 구현시켜 각각의 후크에 원하는 하중을 발생시킬 수 있음으로 크레인의 최대 인양 리프팅 수용능력(capacity)을 가질 수 있어 FPSO 탑사이드 모듈을 리프팅할 수 있도록 하는 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템 및 이를 가지는 선박 또는 해양구조물을 제공함에 있다.SUMMARY OF THE INVENTION The present invention has been made in order to solve the problems described above, and it is an object of the present invention to provide a pin joint in a plurality of points to which a wire and a spreader beam structure are connected, Which is capable of lifting a maximum lift lifting capacity of a crane to allow a lifting of the FPSO top side module, and a ship or an offshore structure having the dual split crane spreader beam system.

상기한 목적을 달성하기 위한 본 발명의 일 측면에 따르면, FPSO 탑사이드 모듈을 탑재하기 위해 크레인으로 리프팅하는 스프레더 빔 시스템에 있어서, 크레인에 설치되는 복수의 후크 빔; 상기 후크 빔 사이의 하부에 연결되는 컴프레션 빔; 상기 후크 빔의 하부에 연결되는 와이어; 상기 와이어의 하부 끝단에 연결되어 수평 하중을 제어하게 되는 텐션바; 및 상기 텐션바의 양끝단에 설치되어 모듈을 연결하는 링크플레이트를 포함할 수 있다.According to an aspect of the present invention, there is provided a spreader beam system for lifting a crane by a crane for mounting an FPSO topside module, comprising: a plurality of hook beams installed on a crane; A compression beam coupled to a lower portion between the hook beams; A wire connected to a lower portion of the hook beam; A tension bar connected to a lower end of the wire to control a horizontal load; And a link plate provided at both ends of the tension bar for connecting the modules.

본 실시예에 따른 후크 빔은, 스프레더 빔을 크레인에 와이어로 연결시킬 수 있도록 양쪽에 후크가 설치될 수 있다.The hook beam according to the present embodiment can be provided with hooks on both sides so as to connect the spreader beam to the crane with a wire.

또한, 상기 후크는 후크 빔에 후크핀조인트로 연결될 수 있다.The hook may also be connected to the hook beam by a hook pin joint.

또한, 상기 후크 빔의 양쪽 하부에는 컴프레션 빔을 안정적으로 지지할 수 있도록 지지부재가 설치될 수 있다.In addition, support members may be provided on both sides of the hook beam to stably support the compression beam.

상기 후크 빔의 하부 전후에는 와이어가 걸어질 수 있도록 풀리(쉬브)가 설치될 수 있다.A pulley (sheave) may be installed on the front and rear of the lower portion of the hook beam so that the wire can be hooked.

본 실시예에 따른 컴프레션 빔은, 상기 양쪽의 후크 빔 사이에 후크 빔의 하측에서 수평으로 설치될 수 있다.The compression beam according to this embodiment can be installed horizontally below the hook beam between the two hook beams.

상기 컴프레션 빔은 후크 빔과 상부핀조인트로 연결될 수 있다.The compression beam may be connected to the hook beam by an upper pin joint.

본 실시예에 따른 와이어는, 상기 좌우측 각각의 후크 빔의 중앙 하부에 연결되고 텐션바의 양쪽에 연결되면서 경사지게 설치될 수 있다.The wires according to the present embodiment may be connected to the lower center of each of the right and left hook beams and be inclined while being connected to both sides of the tension bar.

본 실시예에 따른 텐션바는, 상기 후크 빔에 연결되는 와이어를 연결시키며 모듈을 걸게 되는 링크플레이트와 하부핀조인트로 연결될 수 있다.The tension bar according to the present embodiment may be connected to a link plate and a lower pin joint that connect the wires connected to the hook beams and to which the modules are hooked.

또한, 상기 텐션바는 와이어가 경사지게 연결될 수 있도록 컴프레션 빔 보다 가볍고 짧은 길이로 이루어질 수 있다.In addition, the tension bar can be made lighter and shorter in length than the compression beam so that the wire can be tilted.

또한, 상기 텐션바의 양끝단 전후에는 와이어가 걸어질 수 있도록 풀리(쉬브)가 설치될 수 있다.In addition, a pulley (sheave) may be installed at both ends of the tension bar so that the wire can be hooked.

또한, 상기 텐션바는 컴프레션 빔과 수평상태로 설치될 수 있다.In addition, the tension bar may be installed horizontally with the compression beam.

본 실시예에 따른 링크플레이트는, 상기 텐션바의 양끝단에 하부핀조인트로 연결되며, 모듈 상부에 설치된 패드아이를 연결구로 연결시킬 수 있다.
The link plate according to the present embodiment is connected to both ends of the tension bar by a lower pin joint, and the pad eye provided at the upper portion of the module can be connected to the connection hole.

본 발명의 다른 일 측면에 따르면, 상기한 고중량물의 모듈을 인양하기 위한 듀얼 크레인에 복수의 후크 빔이 연결되되 후크 빔을 상부핀조인트로 컴프레션 빔에 연결되고 양쪽의 후크 빔에 와이어를 텐션바와 연결하며 텐션바에 탑사이드 모듈을 연결하는 링크플레이트를 설치하여 듀얼 크레인을 이용하여 모듈을 인양 시 크레인에 발생되는 수평 하중을 상쇄시켜 크레인의 수용능력을 최대화할 수 있도록 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템을 가지는 선박 또는 해양구조물을 제공할 수 있다.According to another aspect of the present invention, a plurality of hook beams are connected to a dual crane for lifting the heavy-weight module, and the hook beam is connected to the compression beam by an upper pin joint, And a link plate for connecting the topside module to the tension bar. This dual crane spreader for mounting the FPSO module to maximize the capacity of the crane by canceling the horizontal load generated by the crane when lifting the module with dual cranes A ship or an ocean structure having a beam system can be provided.

이와 같이 본 발명의 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템에 따르면, 크레인 폭에 비해 리프팅 포인트가 좁아 예각이 발생하고 수평하중이 발생되었던 것을 핀조인트로 연결되는 스프레더 빔을 듀얼 크레인에 설치하여 고중량물의 모듈을 인양하게 됨으로써 수평하중을 상쇄시켜 수평하중에 영향을 받지 않기 때문에 크레인의 인양 가능 하중을 극대화할 수 있는 효과를 갖는다.As described above, according to the dual-beam crane spreader beam system for mounting an FPSO module of the present invention, a spreading beam is narrowed due to a small lifting point compared with a crane width, and a horizontal load is generated. Since the load module is lifted, horizontal load is canceled and it is not influenced by horizontal load. Therefore, it is possible to maximize lifting load of the crane.

도 1 내지 도 3은 종래의 탑사이드 모듈을 탑재하기 위한 스프레더 빔의 실시예를 도시한 정면도이다.
도 4는 본 발명에 따른 듀얼 해상 크레인 스프레더 빔 시스템을 도시한 정면도이다.
도 5는 본 발명에 따른 듀얼 해상 크레인 스프레더 빔 시스템의 후크 빔과 컴프레션 빔의 연결상태를 도시한 측면도이다.
도 6은 본 발명에 따른 듀얼 해상 크레인 스프레더 빔 시스템의 텐션바와 링크플레이트의 연결상태를 도시한 측면도이다.
1 to 3 are front views showing an embodiment of a spreader beam for mounting a conventional top side module.
4 is a front view showing a dual-wing crane spreader beam system according to the present invention.
5 is a side view showing a connection state of a compression beam and a hook beam of a dual-wing crane spreader beam system according to the present invention.
FIG. 6 is a side view showing a connection state of a tension plate and a link plate of a dual-wing crane spreader beam system according to the present invention.

이하, 첨부된 도면을 참조하여 본 발명의 일 실시예를 상세히 설명하면 다음과 같다.
Hereinafter, an embodiment of the present invention will be described in detail with reference to the accompanying drawings.

도 4는 본 발명에 따른 듀얼 해상 크레인 스프레더 빔 시스템을 도시한 정면도이며, 도 5는 본 발명에 따른 듀얼 해상 크레인 스프레더 빔 시스템의 후크 빔과 컴프레션 빔의 연결상태를 도시한 측면도이고, 도 6은 본 발명에 따른 듀얼 해상 크레인 스프레더 빔 시스템의 텐션바와 링크플레이트의 연결상태를 도시한 측면도이다.FIG. 4 is a front view showing a dual-beam crane spreader beam system according to the present invention, FIG. 5 is a side view showing a connection state of a hook beam and a compression beam of a dual-beam crane spreader beam system according to the present invention, FIG. 6 is a side view showing a connection state of a tension plate and a link plate of a dual marine crane spreader beam system according to the present invention. FIG.

도 4 내지 도 6에 도시된 바와 같이 본 발명의 일 측면에 따른 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템은, 후크 빔(200)과, 컴프레션 빔(300)과, 와이어(W)와, 텐션바(400)와, 링크플레이트(500)를 포함하게 된다.4 to 6, a dual-beam crane spreader beam system for mounting an FPSO module according to an aspect of the present invention includes a hook beam 200, a compression beam 300, a wire W, A bar 400, and a link plate 500.

본 실시예의 후크 빔(200)은, 듀얼 크레인에 설치되며 스프레더 빔 시스템을 크레인(100)에 와이어(W)로 연결시킬 수 있도록 양쪽에 후크(210)가 설치되어지게 된다.The hook beam 200 of the present embodiment is installed in a dual crane and hooks 210 are installed on both sides so that the spreader beam system can be connected to the crane 100 by a wire W. [

또한, 상기 후크(210)는 후크 빔(200)에 후크핀조인트(600)로 연결되어지게 된다. In addition, the hook 210 is connected to the hook beam 200 by a hook pin joint 600.

즉, 상기 후크(210)와 후크 빔(200)을 후크핀조인트(600)로 연결하게 됨으로써 후크(210)와 후크 빔(200)의 회전 및 기울어짐이 가능하게 되어 모멘트(moment)를 상쇄시킬 수 있게 된다.That is, by connecting the hook 210 and the hook beam 200 with the hook pin joint 600, it is possible to rotate and tilt the hook 210 and the hook beam 200 to cancel the moment .

또한, 상기 후크 빔(200)의 양쪽 하부에는 컴프레션 빔(300)을 안정적으로 지지할 수 있도록 지지부재(220)가 설치되어지게 된다.A support member 220 is installed on both sides of the hook beam 200 to stably support the compression beam 300.

또한, 상기 후크 빔(200)의 하부 전,후에는 크레인(100)에 연결되는 와이어(W)가 연결될 수 있도록 풀리(쉬브)(P)가 설치되어지게 된다.In addition, a pulley (sheave) P is installed before and after the hook beam 200 so that the wire W connected to the crane 100 can be connected.

상기에서 후크 빔(200)은 8개의 후크(210)를 4개의 FPSO 탑사이드 모듈(700)을 리프팅 연결하기 위해 두 개의 후크(210)를 한 개로 모아주게 된다.The hook beam 200 collects the two hooks 210 into one for lifting and connecting the four hooks 210 to the four FPSO topside modules 700.

이에 두 개의 후크(210) 센터에서 하중이 발생하기 때문에 항상 두 개의 후크(210)가 동일한 하중이 발생하게 된다.Therefore, since the load is generated at the center of the two hooks 210, the same load is always generated by the two hooks 210.

본 실시예의 컴프레션 빔(300)은, 상기 후크 빔(200) 하부에 연결되며 좌,우측의 후크 빔(200)을 서로 연결하게 된다.The compression beam 300 of the present embodiment is connected to the lower portion of the hook beam 200 and connects the left and right hook beams 200 to each other.

이때, 상기 컴프레션 빔(300)은, 상기 후크 빔(200)과 후크 빔(200) 사이에 수평으로 설치되어지게 된다,At this time, the compression beam 300 is installed horizontally between the hook beam 200 and the hook beam 200,

상기 컴프레션 빔(300)은 후크 빔(200)의 하부에 상부핀조인트(610)로 연결되어지게 된다.The compression beam 300 is connected to the lower portion of the hook beam 200 by an upper pin joint 610.

상기에서 일 예로 69m 지점까지 벌어지는 후크(210)가 25 ~ 40m의 FPSO 모듈(700)을 들기 위해서는 수평하중이 발생하게 됨에 따라 상기 컴프레션 빔(300)으로 복수의 후크 빔(200)을 연결하게 되어 수평 하중을 상쇄시킬 수 있게 된다.For example, in order to lift the FPSO module 700 of 25 to 40 m, the hook 210 extending up to the point of 69 m generates a horizontal load, so that the plurality of the hook beams 200 are connected to the compression beam 300 The horizontal load can be canceled.

또한, 상기 와이어(W)가 걸린 후크 빔(200)의 풀리(쉬브)(P)에서 수평하중이 발생하는 부분과 컴프레션 빔(300)을 동일한 상부핀조인트(610)를 만들어 수평 하중이 추가 모멘트를 만들지 않게 상쇄시키게 된다.A portion of the pulley (sheave) P of the hook beam 200 on which the wire W is hooked generates a horizontal load and the compression beam 300 are formed in the same upper pin joint 610, Is canceled.

즉, 상기 후크 빔(200) 구조와 와이어(W)가 걸리는 풀리(쉬브)(P) 및 컴프레션 빔(300)이 연결되는 구조를 한 개의 핀조인트(pin joint)인 상부핀조인트(610)를 이용하여 연결시키게 되어 수평 하중이 크레인(100)에 전달되지 않게 된다.That is, the structure in which the structure of the hook beam 200 is connected to the pulley (sheave) P and the compression beam 300 to which the wire W is hooked is defined as an upper pin joint 610 which is a pin joint So that the horizontal load is not transmitted to the crane 100.

이에 상기 상부핀조인트(610)의 한 개의 핀조인트가 수평력이 발생시키는 우력을 없애기 때문에 수평력으로 인해 크레인(100) 용량이 영향을 받지 않게 된다.Accordingly, since the single pin joint of the upper pin joint 610 eliminates the force generated by the horizontal force, the capacity of the crane 100 is not affected by the horizontal force.

본 실시예의 와이어(W)는, 상기 후크 빔(200)에 설치되는 풀리(쉬브)(P)와 텐션바(400)에 연결되어 후크 빔(200)과 텐션바(400)를 연결시키게 된다.The wire W of the present embodiment is connected to a tension bar 400 connected to a pulley (sheave) P provided on the hook beam 200 and connects the hook beam 200 and the tension bar 400.

상기 와이어(W)는 컴프레션 빔(300)의 양쪽에 연결되는 후크 빔(200)의 풀리(쉬브)(P)에 걸어지면서 텐션바(400)의 양쪽 각각에 연결되어 와이어(W)가 안쪽으로 경사지게 설치되어지게 된다.The wire W is hooked on a pulley (sheave) P of a hook beam 200 connected to both sides of the compression beam 300 and is connected to both sides of the tension bar 400 so that the wire W is moved inward It is installed at an inclined angle.

본 실시예의 텐션바(400)는, 상기 와이어(W)의 하부 끝단에 연결되어 구조적으로 발생하는 수평 하중을 제어할 수 있게 된다.The tension bar 400 of the present embodiment is connected to the lower end of the wire W so that the horizontal load generated by the structure can be controlled.

상기 텐션바(400)의 양끝단 전,후에는 후크 빔(200)의 풀리(쉬브)(P)에 걸어지는 와이어(W)가 연결될 수 있도록 풀리(쉬브)(P)가 설치되어지게 된다.A pulley (sheave) P is installed so that a wire W to be hooked to a pulley (sheave) P of the hook beam 200 can be connected before and after the both ends of the tension bar 400.

상기 텐션바(400)는 후크 빔(200)에 연결되는 와이어(W)를 연결시키고 모듈(700)을 걸게 되는 링크플레이트(500)와 하부핀조인트(620)로 연결되어지게 된다.The tension bar 400 is connected to the link plate 500 and the lower pin joint 620 through which the wire W connected to the hook beam 200 is connected and the module 700 is hooked.

또한, 상기 텐션바(400)는 와이어(W)가 안쪽으로 경사지게 연결될 수 있도록 컴프레션 빔(300) 보다 짧은 길이로 이루어지게 된다.The tension bar 400 is shorter than the compression beam 300 so that the wire W can be inclined inward.

상기에서 풀리(쉬브)(P)와 링크플레이트(500) 및 텐션바(400)를 하부핀조인트(620)의 동일한 핀(pin)에 연결하게 되어 모멘트를 상쇄시킬 수 있게 된다.The sheave P, the link plate 500, and the tension bar 400 are connected to the same pin of the lower pin joint 620, so that the moment can be canceled.

본 실시예의 링크플레이트(500)는, 상기 텐션바(400)의 양끝단에 설치되어 고중량물의 모듈(700)을 연결하게 된다.The link plate 500 of the present embodiment is installed at both ends of the tension bar 400 to connect the module 700 of a heavy weight.

상기 링크플레이트(500)는 텐션바(400)의 양끝단에 하부핀조인트(620)로 연결되어지게 된다.The link plate 500 is connected to both ends of the tension bar 400 by a lower pin joint 620.

또한, 상기 링플레이트(500)에는 모듈(700)을 리프팅하기 위해 모듈(700) 상부에 설치된 패드아이(710)를 연결시킬 수 있도록 연결구(510)가 결합되어지게 된다.
The ring 510 is coupled to the ring plate 500 so as to connect the pad eye 710 installed on the module 700 to lift the module 700.

본 발명의 다른 일 측면에 따르면, 전술한 2기의 크레인(100)에 와이어(W)로 연결되는 후크(210)가 후크핀포인트(600)로 후크 빔(200)에 설치되고 후크 빔(200)과 후크 빔(200)을 한 개의 핀조인트(pin joint)인 상부핀조인트(610)로 컴프레션 빔(300)에 연결하며 상기 후크 빔(200)에 텐션바(400)가 와이어(W)로 연결되고 상기 텐션바(400)에 하부핀조인트(620)로 고중량물의 모듈(700)을 걸기 위한 링크플레이트(500)가 설치되는 스프레더 빔 시스템을 크레인(100)에 설치하여 2대의 크레인(100)을 이용한 고중량물의 모듈(700) 인양 시 크레인(100)에 발생되는 수평 하중을 상쇄시켜 크레인(100) 인양 하중을 최대화할 수 있도록 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템을 가지는 선박 또는 해양구조물에 적용되어지게 된다.According to another aspect of the present invention, a hook 210 connected by a wire W to the above-described two crane 100 is installed in the hook beam 200 with a hook pin point 600, and the hook beam 200 And the hook beam 200 are connected to the compression beam 300 by an upper pin joint 610 which is a pin joint and the tension bar 400 is fixed to the hook beam 200 by a wire W A spreader beam system is connected to the tension bar 400 and a link plate 500 for fastening the module 700 of a heavy weight to the lower pin joint 620 is installed in the crane 100, A heavy marine crane having a spreader beam system for mounting the FPSO module in order to maximize the lifting load of the crane 100 by canceling the horizontal load generated in the crane 100 during lifting To be applied to the structure.

즉, 크레인(100)에 와이어(W)로 후크(210)가 연결되면서 후크(210)가 후크 빔(200)에 후크핀조인트(600)로 연결되며 후크 빔(200)과 컴프레션 빔(300)이 상부핀조인트(610)로 연결되고 후크 빔(200)에 와이어(W)로 연결되는 텐션바(400)와 링크플레이트(500)가 하부핀조인트(620)의 동일한 핀(pin)으로 연결되어짐으로써 와이어(W) 및 스프레더 빔 시스템의 연결 포인트에 한 개의 핀조인트를 구현시켜 수평 하중의 발생이 상쇄되어짐에 따라 각각의 후크(210)에 원하는 하중을 발생시킬 수 있어 크레인 최대 인양 수용능력(capacity)으로 FPSO 모듈을 리프링할 수 있는 모든 선박 또는 해양구조물에 적용할 수 있게 된다.
That is, when the hook 210 is connected to the crane 100 by the wire W, the hook 210 is connected to the hook beam 200 by the hook pin joint 600 and the hook beam 200 and the compression beam 300 are connected, The tension bar 400 and the link plate 500 connected by the upper pin joint 610 and connected to the hook beam 200 by the wire W are connected to the same pin of the lower pin joint 620 A single pin joint is implemented at the connection points of the wire W and the spreader beam system to generate a desired load on each of the hooks 210 as the horizontal load is canceled, ) To be applicable to any ship or offshore structure capable of re-FPSO modules.

상기와 같이 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템에 따르면, 듀얼 크레인(100)에 와이어(W)로 연결되는 후크(210)가 후크 빔(200)에 후크핀조인트(600)로 연결되어 후크 빔(200)이 회전 및 기울어짐이 가능하여 모멘트(moment)를 상쇄시킬 수 있게 된다.According to the dual floating crane spreader beam system for mounting the FPSO module as described above, the hook 210 connected to the dual cranes 100 by the wire W is connected to the hook beam 200 by the hook pin joint 600, The beam 200 can be rotated and tilted so that the moment can be canceled.

그리고, 상기 두 개의 후크(210)가 센터에서 하중이 발생하기 때문에 두 개의 후크(210)에 항상 동일한 하중이 발생하게 된다.Since the two hooks 210 generate a load at the center, the same load is always generated in the two hooks 210. [

이에 상기 후크 빔(200)과 후크(210)가 후크핀조인트(600)로 연결됨으로써 모멘트를 상쇄시켜 크레인(100)의 부하율에 영향을 주지 않게 된다.Thus, the hook beam 200 and the hook 210 are connected to each other by the hook pin joint 600, thereby canceling the moment and not affecting the load factor of the crane 100.

또한, 상기 후크 빔(200)이 컴프레션 빔(300)에 연결되면서 상부핀조인트(610)로 연결됨으로써 수평 하중이 추가 모멘트를 만들지 않게 상쇄시켜 수평 하중이 크레인(100)에 전달되지 않게 된다.Further, the hook beam 200 is connected to the compression beam 300 and connected to the upper pin joint 610, so that the horizontal load is canceled so as not to generate an additional moment, so that the horizontal load is not transmitted to the crane 100.

이와 함께, 상기 모듈(700)을 걸기 위한 링크플레이트(500)가 텐션바(400)와 하부핀조인트(620)로 연결되며 상기 텐션바(400)가 후크 빔(200)에 연결되는 와이어(W)에 연결되어 상기 와이어(W)와 링크플레이트(500) 및 텐션바(400)를 하부핀조인트(620)의 동일한 핀에 연결하여 모멘트를 상쇄시킬 수 있게 된다.A link plate 500 for hooking the module 700 is connected by a tension bar 400 and a lower pin joint 620 and the tension bar 400 is connected to a wire W So that the moment W can be canceled by connecting the wire W, the link plate 500, and the tension bar 400 to the same pin of the lower pin joint 620.

따라서, 본 발명은 스프레더 빔 시스템이 한 개의 핀조인트로 각각 연결되어지게 됨으로써 모멘트를 최소화시킬 수 있고 스프레더 빔 시스템 내에서 수평 하중을 상쇄시켜 크레인의 전체 인양 하중에 영향을 주지 않게 된다.
Accordingly, the present invention minimizes the moment by connecting the spreader beam system to each pin joint, and does not affect the overall lifting load of the crane by offsetting the horizontal load in the spreader beam system.

이상에서와 같이 본 발명은 상술한 특정의 바람직한 실시예에 한정되지 아니하며, 청구범위에서 청구하는 본 발명의 요지를 벗어남이 없이 당해 발명이 속하는 기술분야에서 통상의 지식을 가진 자라면 누구든지 다양한 변형실시가 가능한 것은 물론이고, 그와 같은 변경은 청구범위 기재의 범위 내에 있게 된다.As described above, the present invention is not limited to the above-described specific preferred embodiments, and any person skilled in the art can make various modifications without departing from the gist of the present invention. It is to be understood that such changes and modifications are intended to fall within the scope of the appended claims.

100 : 크레인
200 : 후크 빔
210 : 후크
220 : 지지부재
300 : 컴프레션 빔
400 : 텐션바
500 : 링크플레이트
510 : 연결구
600 : 후크핀조인트
610 : 상부핀조인트
620 : 하부핀조인트
700 : 모듈
710 : 패드아이
W : 와이어
P : 풀리(쉬브)
100: Crane
200: Hook beam
210: Hook
220: Support member
300: Compression beam
400: tension bar
500: Link plate
510: connector
600: Hook pin joint
610: upper pin joint
620: Lower pin joint
700: Module
710: Pad Eye
W: Wire
P: Pulley (sheve)

Claims (14)

FPSO 모듈을 탑재하기 위해 해상 크레인으로 리프팅하는 스프레더 빔 시스템으로서,
상기 해상 크레인에 와이어로 연결되는 후크가 핀조인트로 연결되는 복수의 후크 빔;
상기 후크 빔과 후크 빔을 핀조인트로 연결하는 컴프레션 빔;
상기 후크 빔의 하부에 연결되는 와이어;
상기 와이어의 하부 끝단에 연결되어 수평 하중을 제어하는 텐션바; 및
상기 텐션바의 양끝단에 핀조인트로 연결되어 모듈을 연결하는 링크플레이트;
를 포함하는 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템.
A spreader beam system for lifting to a floating crane for mounting an FPSO module,
A plurality of hook beams to which hooks connected by wires to the overhead crane are connected by pin joints;
A compression beam connecting the hook beam and the hook beam with a pin joint;
A wire connected to a lower portion of the hook beam;
A tension bar connected to a lower end of the wire to control a horizontal load; And
A link plate connected to both ends of the tension bar by pin joints to connect the modules;
Dual float crane spreader beam system with FPSO module.
제 1 항에 있어서,
상기 후크는,
상기 후크 빔에 후크핀조인트로 연결되는 것을 특징으로 하는 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템.
The method according to claim 1,
The hook
And the hook beam is connected to the hook beam by a hook pin joint.
제 1 항에 있어서,
상기 후크 빔의 양쪽 하부에는 컴프레션 빔을 안정적으로 지지할 수 있도록 지지부재가 설치되는 것을 특징으로 하는 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템.
The method according to claim 1,
Wherein a support member is installed on both sides of the hook beam to stably support the compression beam. ≪ RTI ID = 0.0 > 15. < / RTI >
제 1 항에 있어서,
상기 후크 빔의 하부 전,후에는 와이어가 걸어질 수 있도록 풀리(쉬브)가 설치되는 것을 특징으로 하는 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템.
The method according to claim 1,
And a pulley (sheave) is installed so that a wire can be hooked before and after the hook beam. [5] The dual-beam crane spreader beam system according to claim 1,
제 1 항에 있어서,
상기 컴프레션 빔은,
상기 후크 빔과 후크 빔 사이의 하측에서 수평으로 설치되는 것을 특징으로 하는 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템.
The method according to claim 1,
The compression beam,
And a horizontal beam is installed horizontally below the hook beam and between the hook beam and the hook beam.
제 1 항에 있어서,
상기 컴프레션 빔은,
상기 후크 빔과 한 개의 핀조인트인 상부핀조인트로 연결되는 것을 특징으로 하는 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템.
The method according to claim 1,
The compression beam,
Wherein the hook beam is connected to the hook beam by an upper pin joint, which is a pin joint, and a dual beam crane spreader beam system for mounting the FPSO module.
제 1 항에 있어서,
상기 와이어는,
각각의 후크 빔 중앙 하부에 연결되고 텐션바의 양쪽에 연결되면서 경사지게 설치되는 것을 특징으로 하는 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템.
The method according to claim 1,
The wire
Wherein each of the hook beams is connected to the lower portion of the center of the hook beam and is connected to both sides of the tension bar, and is inclined to the dual beam crane spreader beam system for mounting on the FPSO module.
제 1 항에 있어서,
상기 텐션바는,
상기 후크 빔에 연결되는 와이어를 연결시키며 모듈을 걸게 되는 링크플레이트와 하부핀조인트로 연결되는 것을 특징으로 하는 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템.
The method according to claim 1,
The tension bar,
And a link plate and a lower pin joint which are connected to each other by a wire connected to the hook beam and connected to the module, and connected by a lower pin joint.
제 1 항에 있어서,
상기 텐션바는,
상기 와이어가 경사지게 연결될 수 있도록 컴프레션 빔 보다 짧은 길이로 설치되는 것을 특징으로 하는 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템.
The method according to claim 1,
The tension bar,
Wherein the wire is installed at a shorter length than the compression beam so that the wire can be connected in an inclined manner.
제 1 항에 있어서,
상기 텐션바의 양끝단 전,후에는 와이어가 걸어질 수 있도록 풀리(쉬브)가 설치되는 것을 특징으로 하는 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템.
The method according to claim 1,
And a pulley (sheave) is installed so that the wire can be hooked before and after the both ends of the tension bar.
제 1 항에 있어서,
상기 텐션바는,
상기 컴프레션 빔과 수평상태로 설치되는 것을 특징으로 하는 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템.
The method according to claim 1,
The tension bar,
Wherein the compression beam is installed horizontally with respect to the compression beam.
제 1 항에 있어서,
상기 링크플레이트는,
상기 텐션바의 양끝단에 하부핀조인트로 연결되는 것을 특징으로 하는 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템.
The method according to claim 1,
Wherein the link plate comprises:
Wherein the tension bar is connected to both ends of the tension bar by a lower pin joint. ≪ RTI ID = 0.0 > 18. < / RTI >
제 1 항에 있어서,
상기 링크플레이트에는 모듈 상부에 설치된 패드아이를 연결시킬 수 있도록 연결구가 결합되는 것을 특징으로 하는 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템.
The method according to claim 1,
Wherein the coupling plate is coupled to the link plate so as to connect the pad eye provided on the upper part of the module to the dual ported crane spreader beam system.
제 1 항 내지 제 13 항 중 어느 한 항에 기재된 고중량물의 모듈을 인양하기 위한 크레인에 한 개의 핀조인트로 연결되어 수평 하중을 상쇄시켜 크레인 인양 가능 하중을 최대화할 수 있도록 FPSO 모듈 탑재용 듀얼 해상 크레인 스프레더 빔 시스템을 가지는 선박 또는 해양구조물.A dual-walled FPSO module for mounting a heavy-duty module according to any one of claims 1 to 13 on a crane for hoisting a crane lifting load by canceling a horizontal load by a single pin joint Ship or offshore structure with crane spreader beam system.
KR1020150002824A 2015-01-08 2015-01-08 Dual crane spreader beam system for module lifting fpso and the offshore platform including the same KR101678520B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020150002824A KR101678520B1 (en) 2015-01-08 2015-01-08 Dual crane spreader beam system for module lifting fpso and the offshore platform including the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020150002824A KR101678520B1 (en) 2015-01-08 2015-01-08 Dual crane spreader beam system for module lifting fpso and the offshore platform including the same

Publications (2)

Publication Number Publication Date
KR20160085609A true KR20160085609A (en) 2016-07-18
KR101678520B1 KR101678520B1 (en) 2016-11-22

Family

ID=56679671

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020150002824A KR101678520B1 (en) 2015-01-08 2015-01-08 Dual crane spreader beam system for module lifting fpso and the offshore platform including the same

Country Status (1)

Country Link
KR (1) KR101678520B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018084709A1 (en) * 2016-11-07 2018-05-11 Heerema Marine Contractors Nederland Se A method of handing over a load, and an arrangement to hand over a load
CN114184320A (en) * 2021-11-23 2022-03-15 大连船舶重工集团有限公司 FPSO unloading system weighing test tool and test method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20180063574A (en) * 2016-12-02 2018-06-12 김성국 Method, Apparatus and Computer-Readable Medium for determining sales price of used car for dealing a used car on P2P using machine learning

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003252563A (en) * 2002-03-07 2003-09-10 Oriental Construction Co Ltd Method of dismantling concrete structure and lifting sling used in dismantling
JP2008213995A (en) * 2007-03-01 2008-09-18 Kito Corp Cargo-handling/carrying hoisting accessory, and cargo-handling/carrying device equipped with the same and cargo-handling/carrying method
JP2014073908A (en) * 2012-10-05 2014-04-24 Jfe Steel Corp Slinging suspension jig

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003252563A (en) * 2002-03-07 2003-09-10 Oriental Construction Co Ltd Method of dismantling concrete structure and lifting sling used in dismantling
JP2008213995A (en) * 2007-03-01 2008-09-18 Kito Corp Cargo-handling/carrying hoisting accessory, and cargo-handling/carrying device equipped with the same and cargo-handling/carrying method
JP2014073908A (en) * 2012-10-05 2014-04-24 Jfe Steel Corp Slinging suspension jig

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2018084709A1 (en) * 2016-11-07 2018-05-11 Heerema Marine Contractors Nederland Se A method of handing over a load, and an arrangement to hand over a load
NL2017736B1 (en) * 2016-11-07 2018-05-23 Heerema Marine Contractors Nl A method of handing over a load, and an arrangement to hand over a load.
GB2572872A (en) * 2016-11-07 2019-10-16 Heerema Marine Contractors Nl A method of handing over a load, and an arrangement to hand over a load
US10710845B2 (en) 2016-11-07 2020-07-14 Heerema Marine Contractors Nederland Se Method of handing over a load, and an arrangement to hand over a load
GB2572872B (en) * 2016-11-07 2021-12-08 Heerema Marine Contractors Nl A method of handing over a load, and an arrangement to hand over a load
CN114184320A (en) * 2021-11-23 2022-03-15 大连船舶重工集团有限公司 FPSO unloading system weighing test tool and test method
CN114184320B (en) * 2021-11-23 2024-04-19 大连船舶重工集团有限公司 FPSO unloading system weighing test tool and test method

Also Published As

Publication number Publication date
KR101678520B1 (en) 2016-11-22

Similar Documents

Publication Publication Date Title
CN103781698B (en) Anchor cable tensioning method
US7011473B2 (en) Method for underwater transportation and installation or removal of objects at sea
US8235228B2 (en) Method and apparatus for deep water deployment operations
US20120156003A1 (en) Method and apparatus for supporting a load
KR101678520B1 (en) Dual crane spreader beam system for module lifting fpso and the offshore platform including the same
CN104284857A (en) Heavy lifting apparatus and method
CN102815373A (en) Hybrid deep water mooring system
KR20140030476A (en) Divided erection method of flare tower
US5028194A (en) Marine crane improvement
EP2888193A1 (en) Method for lowering and hoisting of a load to or from an ocean floor
WO2019069076A1 (en) A semi submersible vessel
JP6752682B2 (en) How to install a suspended load by a crane vessel
KR20160001236U (en) Hanging type mono rail series connection apparatus and offshore structure having the connection apparatus
CN105947910A (en) Lifting process of upper structure of FPSO crane
WO2015199611A1 (en) A method of supporting a chain stopper on a vessel, a chain stopper assembly for a vessel, and a vessel
KR20160005887A (en) Floating crane rigging system
WO2013073950A1 (en) Vessel and method for towing a heavy load under water
CN208500119U (en) A kind of boom hoisting of A font cantilever crane
AU2013332507B2 (en) Midwater arch system
US4359011A (en) Boat mooring system for a platform structure
KR20150109728A (en) Method for loading large block of ship
US10710845B2 (en) Method of handing over a load, and an arrangement to hand over a load
KR20230083564A (en) Dismantling apparatus for upper plate structure of system scaffold and dismantling method of upper plate structure of system scaffold usiing the same
KR101695487B1 (en) Loading method of structure and crane-linking apparatus for the same
CN105857528A (en) Hoisting method for A-type liquid cargo tank

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20191119

Year of fee payment: 4