KR20160012512A - Bearing plate structure and construction method for buoyancy protection anchor using the same - Google Patents

Bearing plate structure and construction method for buoyancy protection anchor using the same Download PDF

Info

Publication number
KR20160012512A
KR20160012512A KR1020140094058A KR20140094058A KR20160012512A KR 20160012512 A KR20160012512 A KR 20160012512A KR 1020140094058 A KR1020140094058 A KR 1020140094058A KR 20140094058 A KR20140094058 A KR 20140094058A KR 20160012512 A KR20160012512 A KR 20160012512A
Authority
KR
South Korea
Prior art keywords
anchor
hole
pressure plate
anchor body
concrete
Prior art date
Application number
KR1020140094058A
Other languages
Korean (ko)
Other versions
KR101596245B1 (en
Inventor
김덕형
Original Assignee
도원에프앤지(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 도원에프앤지(주) filed Critical 도원에프앤지(주)
Priority to KR1020140094058A priority Critical patent/KR101596245B1/en
Publication of KR20160012512A publication Critical patent/KR20160012512A/en
Application granted granted Critical
Publication of KR101596245B1 publication Critical patent/KR101596245B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Road Paving Structures (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to a bearing plate structure and a construction method for a buoyancy anchor using the same. The bearing plate structure (100) of a buoyancy anchor comprises: a lower bearing plate (110) coming in contact with the ground, and having a through hole (111) to be connected to a bored hole (1); an upper bearing plate (120) formed on an upper part of the lower bearing plate (110) at intervals, and having an anchoring hole (121) in order for an anchor body (20) inserted into the bored hole (1) to be inserted and mounted; and a spacer member (130) installed between the lower bearing plate (110) and the upper bearing plate (120) to maintain a gap between the lower bearing plate (110) and the upper bearing plate (120). The bearing plate structure is able to reduce construction time and costs by preventing unnecessary construction by finishing a work of the buoyancy anchor by placing a construction company of the buoyancy anchor once.

Description

지압판 구조물 및 이를 이용한 부력앵커의 시공방법{BEARING PLATE STRUCTURE AND CONSTRUCTION METHOD FOR BUOYANCY PROTECTION ANCHOR USING THE SAME}BACKGROUND OF THE INVENTION 1. Field of the Invention [0001] The present invention relates to a buckling plate structure,

본 발명은 토목 분야에 관한 것으로서, 상세하게는 부력앵커에 관한 것이다.Field of the Invention [0002] The present invention relates to a civil engineering field, and more particularly to a buoyancy anchor.

부력앵커란, 부력이 발생하는 지반에 설치되는 구조물의 부유(상향력)를 방지하도록, 연직방향의 파일구조로 설치되는 기초구조물을 의미한다.Buoyant anchor means a foundation structure installed in a vertical pile structure to prevent floating (upward force) of a structure installed on the ground where buoyancy is generated.

도 1 내지 9는 종래의 부력앵커의 시공방법의 공정도이다.1 to 9 are process drawings of a conventional buoyancy anchor construction method.

설계심도까지 천공 홀(1)을 형성하고(도 1), 천공 홀(1)에 앵커체(20)를 삽입한 후(도 2), 그라우트(G)를 실시하여 앵커체(20)의 하부를 지중에 고정한다(도 3). 이들 공정은 부력앵커의 시공업체가 시공한다.The anchor body 20 is inserted into the perforation hole 1 (Fig. 2), and then the grout G is applied to form the perforation hole 1 (Fig. 1) (Fig. 3). These processes are carried out by the construction company of the buoyant anchor.

앵커체(20)의 상단이 노출되도록 버림 콘크리트(2)를 타설하고(도 4), 버림 콘크리트(2)의 상부에 철근(3)을 배근한 후(도 5), 기초콘크리트(4)를 타설한다(도 6). 이들 공정은 본 구조물의 시공업체가 시공한다.4), the reinforced concrete 3 is placed on the upper part of the abandoned concrete 2 (FIG. 5), and then the foundation concrete 4 is poured (See Fig. 6). These processes are carried out by the contractor of this structure.

기초 콘크리트(4)의 양생 후, 앵커체(20)의 상단이 노출되도록 판 구조의 지압판(10)을 설치하고(도 7), 노출된 앵커체(20)의 상단을 상부로 긴장하여 콘 등의 정착부재에 의해 지압판(10)에 정착하며, 보호캡(21)을 설치한 후(도 8), 보호캡(21) 및 지압판(10)의 노출부위를 몰탈 채움(5)에 의해 마감한다(도 9). 이들 공정은 부력앵커의 시공업체가 시공한다.After the curing of the foundation concrete 4, the plate 10 of the anchor structure 20 is installed to expose the upper end of the anchor body 20 (Fig. 7), and the upper end of the exposed anchor body 20 is tensed upward, The protection cap 21 and the exposed portion of the pressure plate 10 are closed by mortar filling 5 after the protective cap 21 is installed (Fig. 9). These processes are carried out by the construction company of the buoyant anchor.

이러한 종래의 공법은 다음과 같은 문제가 있었다.Such conventional methods have the following problems.

첫째, 부력앵커의 시공과 본 구조물의 시공은 서로 다른 시공업체에 의해 이루어지는데, 상술한 바와 같이 서로 다른 시공업체가 지속적으로 번갈아 투입되면서 작업이 이루어져야 하므로, 시공이 번거롭고 작업대기시간이 증대하여, 결국 공사기간 및 비용의 증대를 초래한다.First, the construction of the buoyant anchor and the construction of the present structure are performed by different construction companies. As described above, since different construction companies must be continuously put on each other, the construction is troublesome and the waiting time is increased, Resulting in an increase in construction period and cost.

둘째, 기초 콘크리트(4)의 양생 후, 비로소 앵커체(20)를 긴장하여 정착할 수 있으므로, 공사기간이 증대하고 비효율적이다.Secondly, after the curing of the foundation concrete 4, the anchor body 20 can be fixed by tilting, so that the construction period is increased and it is inefficient.

본 발명은 상기와 같은 문제점을 해결하기 위하여 도출된 것으로서, 부력앵커의 시공업체의 1회 투입에 의해 부력앵커 작업이 종료되도록 함으로써, 번거로운 시공을 방지하여 공사기간 및 비용을 줄일 수 있도록 하는 지압판 구조물 및 이를 이용한 부력앵커의 시공방법을 제시하는 것을 그 목적으로 한다.SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems, and it is an object of the present invention to provide a buckling anchor structure which can prevent a troublesome construction by reducing buoyancy anchor work by one- And an object of the present invention is to provide a method of constructing a buoyant anchor using the same.

상기 과제의 해결을 위하여, 본 발명은 지면에 면접촉하도록 형성됨과 아울러, 천공 홀(1)과 연통하도록 관통공(111)이 형성된 하부 지압판(110); 상기 하부 지압판(110)의 상부에 이격하여 형성됨과 아울러, 상기 천공 홀(1)에 삽입된 앵커체(20)가 삽입 및 정착되도록 정착공(121)이 형성된 상부 지압판(120); 상기 하부 지압판(110) 및 상부 지압판(120)의 간격을 유지하도록, 상기 하부 지압판(110) 및 상부 지압판(120)의 사이에 설치된 간격부재(130);를 포함하는 부력앵커의 지압판 구조물(100)을 제시한다.In order to solve the above-described problems, the present invention provides a pantograph, comprising: a lower bearing plate 110 formed to be in surface contact with a ground surface and having a through hole 111 to communicate with the perforation hole 1; An upper pressure plate 120 spaced from the upper portion of the lower pressure plate 110 and having a fixing hole 121 formed therein to insert and fix the anchor body 20 inserted into the perforation hole 1; And a spacing member 130 provided between the lower and upper pressure plates 110 and 120 to maintain a gap between the lower and upper pressure plates 110 and 120. The buck- ).

상기 하부 지압판(110) 및 상부 지압판(120)은 상호 동일한 면적을 갖도록 형성된 것이 바람직하다.It is preferable that the lower and upper pressure plates 110 and 120 have the same area.

상기 관통공(111)은 상기 하부 지압판(110)의 중앙부에 형성되고, 상기 정착공(121)은 상기 상부 지압판(120)의 중앙부에 형성된 것이 바람직하다.The through hole 111 may be formed at a central portion of the lower pressure plate 110 and the fixing hole 121 may be formed at a central portion of the upper pressure plate 120.

상기 간격부재(130)는 복수가 상기 관통공(111) 및 정착공(121)을 중심으로 방사대칭구조로 설치된 것이 바람직하다.It is preferable that a plurality of the spacing members 130 are provided in a radially symmetric structure with the through holes 111 and the fixing holes 121 as a center.

본 발명은 상기 지압판 구조물(100)을 이용한 부력앵커의 시공방법으로서, 지반에 천공 홀(1)을 형성하는 천공단계; 상기 천공 홀(1)에 상기 앵커체(20)를 삽입하는 앵커체 삽입단계; 상기 천공 홀(1)에 그라우트(G)를 주입하는 그라우팅 단계; 상기 앵커체(20)의 상단이 상기 관통공(111) 및 정착공(121)을 관통하여 상부로 노출되도록, 지면에 상기 지압판 구조물(100)을 설치하는 지압판 구조물 설치단계; 상기 앵커체(20)를 긴장하여 상기 정착공(121)에 정착하는 앵커체 정착단계; 상기 지면에 버림 콘크리트(2)를 타설하는 버림 콘크리트 타설단계; 상기 버림 콘크리트(2)의 상부에 철근(3)의 배근을 실시하는 배근단계; 상기 지압판 구조물(100)이 매몰되도록, 상기 버림 콘크리트(2)의 상부에 기초 콘크리트(4)를 타설하는 기초 콘크리트 타설단계;를 포함하는 것을 특징으로 하는 부력앵커의 시공방법을 제시한다.The present invention relates to a buoyant anchor construction method using the above-mentioned pavement plate structure 100, comprising: a boring step of forming a perforation hole 1 in a ground; Inserting the anchor body (20) into the perforation hole (1); A grouting step of injecting a grout (G) into the perforation hole (1); A step of installing the pressure plate structure 100 on the ground so that an upper end of the anchor body 20 passes through the through hole 111 and the fixing hole 121 and is exposed upward; Fixing the anchor body (20) to the fixing hole (121) by tightening the anchor body (20); Placing the abandoned concrete (2) on the ground; A step of laying the reinforcing bars (3) on the upper part of the abandoned concrete (2); And a foundation concrete pouring step of pouring the foundation concrete (4) on the top of the abandoned concrete (2) so that the padding structure (100) is buried.

상기 앵커체 정착단계와 상기 버림 콘크리트 타설단계의 사이에는, 상기 정착공(121)을 통해 상부로 노출된 상기 앵커체(20)의 상단을 보호하도록, 상기 지압판 구조물(100)의 상부 지압판(120)의 상부에 보호캡(21)을 설치하는 보호캡 설치단계;를 더 포함하는 것이 바람직하다.An upper plate (120) of the pressure plate structure (100) is disposed between the anchor body fixing step and the abandoned concrete pouring step to protect the upper end of the anchor body (20) exposed upward through the fixing hole And a protection cap mounting step of installing a protection cap on an upper portion of the protection cap.

상기 버림 콘크리트 타설단계는, 상기 지압판 구조물(100)의 하부 지압판(110)이 매몰되고, 상기 상부 지압판(120)은 노출되도록 상기 버림 콘크리트(2)를 타설하는 것이 바람직하다.It is preferable that the abandoned concrete pouring step includes placing the abandoned concrete 2 so that the lower pressure plate 110 of the pressure plate structure 100 is buried and the upper pressure plate 120 is exposed.

상기 배근단계는, 배근되는 상기 철근(3)과 상기 지압판 구조물(100)의 간격부재(130) 또는 상부 지압판(120)을 상호 결합하는 것이 바람직하다.It is preferable that the reinforcing step 3 and the gap member 130 or the upper supporting plate 120 of the supporting plate structure 100 are coupled to each other.

본 발명은 부력앵커의 시공업체의 1회 투입에 의해 부력앵커 작업이 종료되도록 함으로써, 번거로운 시공을 방지하여 공사기간 및 비용을 줄일 수 있도록 하는 지압판 구조물 및 이를 이용한 부력앵커의 시공방법을 제시한다.The present invention proposes a construction method of a buckyard anchor that uses a buoyancy anchor to finish construction of a buoyant anchor by one time of a construction worker to prevent troublesome construction and reduce construction period and cost.

도 1 내지 9는 종래의 부력앵커의 시공방법의 공정도.
도 10은 본 발명에 의한 지압판 구조물의 일실시예의 사시도.
도 11 이하는 본 발명에 의한 부력앵커의 시공방법의 일실시예의 공정도.
1 to 9 are process drawings of a conventional buoyancy anchor construction method.
10 is a perspective view of an embodiment of a platen according to the present invention.
Fig. 11 is a process diagram of an embodiment of a buoyancy anchor construction method according to the present invention.

이하, 첨부도면을 참조하여 본 발명의 실시예에 관하여 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 10에 도시된 바와 같이, 본 발명에 의한 지압판 구조물(100)은 기본적으로, 지면에 면접촉하도록 형성됨과 아울러, 천공 홀(1)과 연통하도록 관통공(111)이 형성된 하부 지압판(110); 하부 지압판(110)의 상부에 이격하여 형성됨과 아울러, 천공 홀(1)에 삽입된 앵커체(20)가 삽입 및 정착되도록 정착공(121)이 형성된 상부 지압판(120); 하부 지압판(110) 및 상부 지압판(120)의 간격을 유지하도록, 하부 지압판(110) 및 상부 지압판(120)의 사이에 설치된 간격부재(130);를 포함하여 구성된다.10, the piping structure 100 according to the present invention basically comprises a lower pressure plate 110 formed to be in surface contact with the paper surface and having a through hole 111 to communicate with the perforation hole 1, ; An upper support plate 120 spaced apart from the upper portion of the lower support plate 110 and having a fixing hole 121 formed therein for inserting and fixing the anchor member 20 inserted into the perforation hole 1; And a spacing member 130 provided between the lower and upper pressure plates 110 and 120 to maintain a gap between the lower and upper pressure plates 110 and 120. [

도 11 이하를 참조하여 본 발명에 의한 부력앵커 시공방법의 공정을 설명하면 다음과 같다.The process of the buoyancy anchor construction method according to the present invention will be described with reference to FIG.

지반에 천공 홀(1)을 형성하고(도 11), 천공 홀(1)에 앵커체(20)를 삽입한 후(도 12), 천공 홀(1)에 그라우트(G)를 주입하여 앵커체(20)의 하부를 고정한다(도 13).The grout G is injected into the perforation hole 1 after the perforation hole 1 is formed on the ground (Fig. 11) and the anchor body 20 is inserted into the perforation hole 1 (FIG. 13).

앵커체(20)의 상단이 지압판 구조물(100)의 관통공(111) 및 정착공(121)을 관통하여 상부로 노출되도록, 지면에 지압판 구조물(100)을 설치한 후, 앵커체(20)를 긴장하여 정착공(121)에 정착한다(도 14).The anchor body 20 is installed on the ground so that the upper end of the anchor body 20 is exposed through the through hole 111 and the fixing hole 121 of the support structure 100, And is fixed on the fixing hole 121 (Fig. 14).

이때, 정착공(121)을 통해 상부로 노출된 앵커체(20)의 상단을 보호하도록, 지압판 구조물(100)의 상부 지압판(120)의 상부에 보호캡(21)을 설치한다(도 15).At this time, the protection cap 21 is installed on the upper part of the upper pressure plate 120 of the pressure plate structure 100 to protect the upper end of the anchor body 20 exposed upward through the fixing hole 121 (FIG. 15) .

여기까지의 공정은 모두 부력앵커의 시공업체가 시공하며, 이것으로 당해 업체의 역할은 종료된다.All of the processes up to this point are carried out by the construction company of buoyancy anchor, and the role of the company is terminated.

이후, 지면에 버림 콘크리트(2)를 타설하는데(도 16), 지압판 구조물(100)의 하부 지압판(110)이 매몰되고, 상부 지압판(120)은 노출되도록 버림 콘크리트(2)를 타설하여야 추후 기초 콘크리트(4)와 상부 지압판(120)의 일체구조를 이루기 위하여 바람직하다.Thereafter, the abandoned concrete 2 is laid on the ground (FIG. 16), the lower pressure plate 110 of the pressure plate structure 100 is buried, and the abandoned concrete 2 is laid so that the upper pressure plate 120 is exposed. It is preferable to form the integral structure of the concrete 4 and the upper pressure plate 120.

버림 콘크리트(2)의 상부에 철근(3)의 배근을 실시하는데(도 17), 배근되는 철근(3)과 지압판 구조물(100)의 간격부재(130) 또는 상부 지압판(120)을 상호 결합하는 것이 구조의 일체화 측면에서 바람직하다.17), the reinforcing bars 3 to be laid and the spacing member 130 or the upper pressure plate 120 of the paving structure 100 are joined to each other Is preferable in terms of the integration of the structure.

지압판 구조물(100)이 매몰되도록, 버림 콘크리트(2)의 상부에 기초 콘크리트(4)를 타설한다(도 18).The foundation concrete 4 is laid on the top of the abandoned concrete 2 so that the paving structure 100 is buried (Fig. 18).

이들 공정은 모두 본 구조물의 시공업체가 시공한다.All these processes are carried out by the contractor of this structure.

즉, 본 발명에 의한 부력앵커의 시공방법은 앵커체(20)의 매립, 그라우팅, 지압판 구조물(100)의 설치, 앵커체(20)의 긴장 및 정착공정까지를 부력앵커의 시공업체가 연속적인 1회 시공에 의해 완료하도록 하고, 이후 버림 콘크리트(2)의 타설, 철근(3)의 배근, 기초 콘크리트(4)의 타설 공정을 모두 본 구조물의 시공업체가 시공하도록 하므로, 종래와 같이 부력앵커의 시공업체와 본 구조물의 시공업체가 번갈아 투입되는 번거로운 시공을 방지함으로써 공사기간 및 비용을 줄일 수 있다는 효과가 있다.That is, the method of constructing the buoyancy anchor according to the present invention is a method in which the buoyancy anchor construction contractor continuously processes the anchor body 20 for embedding, grouting, installation of the padding structure 100, The construction worker of the present structure is allowed to complete the installation of the abandoned concrete 2, the placing of the reinforcing bars 3, and the placing of the foundation concrete 4, so that the buoyant anchor It is possible to reduce construction time and cost by preventing troublesome construction where the construction company of the building and the construction company of the structure are alternately inputted.

또한 종래와 같이 기초 콘크리트(4)의 양생 후, 비로소 앵커체(20)를 긴장하여 정착하는 것이 아니라, 지압판 구조물(100)의 설치 후 곧바로 앵커체(20)를 긴장하여 정착할 수 있으므로, 공사기간이 단축되고 효율적인 시공이 가능하다는 효과가 있다..Since the anchor body 20 can be fixed and fixed immediately after the installation of the padding structure 100, instead of tensioning and fixing the anchor body 20 only after the curing of the base concrete 4 as in the prior art, It has the effect of shortening the period and enabling efficient construction.

종래의 공법에서 부력앵커의 시공업체와 본 구조물의 시공업체가 번갈아 투입되어야 하는 이유는, 판형 구조의 지압판(10)을 기초 콘크리트(4)에 의해 고정하고, 이러한 상태에서 앵커체(20)를 긴장하여 지압판(10)에 정착하는 방식을 취하였기 때문이다(도 5 내지 7).In the conventional method, the construction company of the buoyancy anchor and the construction company of the structure should be alternately inserted because the plate-like structure 10 is fixed by the foundation concrete 4, and the anchor body 20 So that it is taut and fixed on the pressure plate 10 (Figs. 5 to 7).

본 발명에 의한 공법에서는, 종래와 같이 판형 구조의 지압판(10)을 적용하는 것이 아니라, 하부 지압판(110), 상부 지압판(120), 간격부재(130)에 의해 구성되는 지압판 구조물(100)을 적용하므로, 기초 콘크리트(4)가 타설되지 않은 상태라 하더라도 앵커체(20)를 긴장하여 상부 지압판(120)에 정착할 수 있고, 이후 철근의 배근 및 기초 콘크리트(4)의 타설에 의해 지압판 구조물(100)과 기초 콘크리트(4)이 일체구조를 이루도록 하므로 충분한 구조적 안정성을 얻을 수 있다.The method according to the present invention does not apply the plate-shaped pressure plate 10 as in the prior art but applies the pressure plate structure 100 composed of the lower pressure plate 110, the upper pressure plate 120, It is possible to fix the anchor body 20 to the upper pressure plate 120 even if the foundation concrete 4 is not poured and then to fix the anchor body 20 to the upper pressure plate 120. Then, (100) and the foundation concrete (4) have a unified structure, sufficient structural stability can be obtained.

한편, 위 실시예에서는 그라우팅 후 지압판 구조물(100)의 설치 및 앵커체(20)의 긴장, 정착작업을 하고, 이후, 버림 콘크리트(2)를 타설하는 실시예에 관하여 설명하였는데, 그라우팅 후 먼저 버림 콘크리트(2)를 타설하고, 그 위에 지압판 구조물(100)의 설치 및 앵커체(20)의 긴장, 정착작업을 할 수도 있다.In the above embodiment, an example in which the post-grouting concrete structure 100 is installed and the anchor body 20 is tensed and fixed, and then the shrink concrete 2 is laid is described. However, after the grouting, The concrete 2 may be laid, and the tread structure 100 and the anchor body 20 may be tensioned and fixed thereon.

이하, 지압판 구조물(100)의 구체적 구성에 관한 실시예에 대하여 설명한다(도 10).Hereinafter, an embodiment relating to a concrete construction of the paving structure 100 will be described (FIG. 10).

상부 지압판(120)은 콘(쐐기부재) 등의 정착부재에 의해 앵커체(20)의 긴장력을 간격부재(130)에 전달하고, 간격부재(130)는 위 긴장력을 하부 지압판(110)에 전달하며, 하부 지압판(110)은 지면에 면접촉하도록 형성되어 위 긴장력을 지반에 전달한다.The upper support plate 120 transmits a tension force of the anchor body 20 to the spacing member 130 by a fixing member such as a cone (wedge member), and the spacing member 130 transmits the upper tensioning force to the lower pressure plate 110 And the lower pressure plate 110 is formed to be in surface contact with the ground so as to transmit the upper tension force to the ground.

따라서 상부 지압판(120), 하부 지압판(110), 간격부재(130)는 앵커체(20)의 긴장력을 감안하여 각각 안정된 부재력을 갖도록 설계되어야 한다.Therefore, the upper support plate 120, the lower support plate 110, and the spacing member 130 should be designed to have a stable member force in consideration of the tension of the anchor body 20.

상부 지압판(120), 하부 지압판(110)의 형상은 현장별로 구조 검토에 의해 결정되며, 사각형, 원형, 마름모 등의 구조를 취할 수 있다.The shapes of the upper and lower pressure plates 120 and 110 are determined according to the structure of each site, and may take the form of a square, a circle, a rhombus, or the like.

구체적으로, 상부 지압판(120)과 하부 지압판(110)은 상호 동일한 면적을 갖도록 형성되고, 관통공(111)은 하부 지압판(110)의 중앙부에 형성되고, 정착공(121)은 상부 지압판(120)의 중앙부에 형성되며, 간격부재(130)는 복수가 관통공(111) 및 정착공(121)을 중심으로 방사대칭구조로 설치된 구조를 취하는 것이 지면에 대하여 앵커체(20)의 긴장력을 안정적으로 전달하기 위하여 바람직하다.The through holes 111 are formed at the center of the lower pressure plate 110 and the fixing holes 121 are formed at the upper end of the upper pressure plate 120. The upper and lower pressure plates 120, And the spacing member 130 has a structure in which a plurality of through holes 111 and a fixing hole 121 are provided in a radially symmetric structure with respect to the ground so that the tension force of the anchor body 20 can be stably Lt; / RTI >

간격부재(130)의 단면 및 수량 역시 현장별로 구조 검토에 의해 결정된다.The cross-section and quantity of the spacing member 130 are also determined by site-specific structure review.

이상은 본 발명에 의해 구현될 수 있는 바람직한 실시예의 일부에 관하여 설명한 것에 불과하므로, 주지된 바와 같이 본 발명의 범위는 위의 실시예에 한정되어 해석되어서는 안 될 것이며, 위에서 설명된 본 발명의 기술적 사상과 그 근본을 함께 하는 기술적 사상은 모두 본 발명의 범위에 포함된다고 할 것이다.It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit or scope of the invention as defined in the appended claims. It is to be understood that both the technical idea and the technical spirit of the invention are included in the scope of the present invention.

1 : 천공 홀 2 : 버림 콘크리트
3 : 철근 4 : 기초 콘크리트
20 : 앵커체 21 : 보호캡
100 : 지압판 구조물 110 : 하부 지압판
111 : 관통공 120 : 상부 지압판
121 : 정착공 130 : 간격부재
1: Perforated hole 2: Discarded concrete
3: Reinforced concrete 4: Foundation concrete
20: anchor body 21: protective cap
100: a scaffold structure 110: a lower scaffold
111: Through hole 120: Upper plate
121: Fixing hole 130:

Claims (9)

지면에 면접촉하도록 형성됨과 아울러, 천공 홀(1)과 연통하도록 관통공(111)이 형성된 하부 지압판(110);
상기 하부 지압판(110)의 상부에 이격하여 형성됨과 아울러, 상기 천공 홀(1)에 삽입된 앵커체(20)가 삽입 및 정착되도록 정착공(121)이 형성된 상부 지압판(120);
상기 하부 지압판(110) 및 상부 지압판(120)의 간격을 유지하도록, 상기 하부 지압판(110) 및 상부 지압판(120)의 사이에 설치된 간격부재(130);를
포함하는 부력앵커의 지압판 구조물(100).
A lower pressure plate 110 formed to be in surface contact with the paper surface and having a through hole 111 to communicate with the perforation hole 1;
An upper pressure plate 120 spaced from the upper portion of the lower pressure plate 110 and having a fixing hole 121 formed therein to insert and fix the anchor body 20 inserted into the perforation hole 1;
A spacing member 130 provided between the lower and upper pressure plates 110 and 120 to maintain a gap between the lower and upper pressure plates 110 and 120;
(100) comprising a buoyant anchor.
제1항에 있어서,
상기 하부 지압판(110) 및 상부 지압판(120)은 상호 동일한 면적을 갖도록 형성된 것을 특징으로 하는 부력앵커의 지압판 구조물(100).
The method according to claim 1,
Wherein the lower pressure plate 110 and the upper pressure plate 120 are formed to have the same area as the buoyancy plate 100 of the buoyancy anchor.
제1항에 있어서,
상기 관통공(111)은 상기 하부 지압판(110)의 중앙부에 형성되고, 상기 정착공(121)은 상기 상부 지압판(120)의 중앙부에 형성된 것을 특징으로 하는 부력앵커의 지압판 구조물(100).
The method according to claim 1,
Wherein the through hole 111 is formed at a central portion of the lower pressure plate 110 and the fixing hole 121 is formed at a central portion of the upper pressure plate 120.
제3항에 있어서,
상기 간격부재(130)는 복수가 상기 관통공(111) 및 정착공(121)을 중심으로 방사대칭구조로 설치된 것을 특징으로 하는 부력앵커의 지압판 구조물(100).
The method of claim 3,
Wherein a plurality of spacers (130) are installed in a radially symmetric configuration about the through-holes (111) and the fusing holes (121).
제1항 내지 제4항 중 어느 한 항의 지압판 구조물(100)을 이용한 부력앵커의 시공방법으로서,
지반에 천공 홀(1)을 형성하는 천공단계;
상기 천공 홀(1)에 상기 앵커체(20)를 삽입하는 앵커체 삽입단계;
상기 천공 홀(1)에 그라우트(G)를 주입하는 그라우팅 단계;
상기 앵커체(20)의 상단이 상기 관통공(111) 및 정착공(121)을 관통하여 상부로 노출되도록, 지면에 상기 지압판 구조물(100)을 설치하는 지압판 구조물 설치단계;
상기 앵커체(20)를 긴장하여 상기 정착공(121)에 정착하는 앵커체 정착단계;
상기 지면에 버림 콘크리트(2)를 타설하는 버림 콘크리트 타설단계;
상기 버림 콘크리트(2)의 상부에 철근(3)의 배근을 실시하는 배근단계;
상기 지압판 구조물(100)이 매몰되도록, 상기 버림 콘크리트(2)의 상부에 기초 콘크리트(4)를 타설하는 기초 콘크리트 타설단계;를
포함하는 것을 특징으로 하는 부력앵커의 시공방법.
A method of constructing a buoyant anchor using the paving structure (100) of any one of claims 1 to 4,
Forming a perforation hole (1) in the ground;
Inserting the anchor body (20) into the perforation hole (1);
A grouting step of injecting a grout (G) into the perforation hole (1);
A step of installing the pressure plate structure 100 on the ground so that an upper end of the anchor body 20 passes through the through hole 111 and the fixing hole 121 and is exposed upward;
Fixing the anchor body (20) to the fixing hole (121) by tightening the anchor body (20);
Placing the abandoned concrete (2) on the ground;
A step of laying the reinforcing bars (3) on the upper part of the abandoned concrete (2);
Placing a foundation concrete (4) on an upper part of the abandoned concrete (2) so that the paving structure (100) is buried;
Wherein the buoyant anchor is formed of a metal.
제5항에 있어서,
상기 앵커체 정착단계와 상기 버림 콘크리트 타설단계의 사이에는,
상기 정착공(121)을 통해 상부로 노출된 상기 앵커체(20)의 상단을 보호하도록, 상기 지압판 구조물(100)의 상부 지압판(120)의 상부에 보호캡(21)을 설치하는 보호캡 설치단계;를 더 포함하는 것을 특징으로 하는 부력앵커의 시공방법.
6. The method of claim 5,
Between the anchor body fixing step and the abandoned concrete pouring step,
A protection cap is installed to protect the upper end of the anchor body 20 exposed through the fixing hole 121 at the upper portion of the upper pressure plate 120 of the pressure plate structure 100 The method of claim 1, further comprising:
제5항에 있어서,
상기 버림 콘크리트 타설단계는,
상기 지압판 구조물(100)의 하부 지압판(110)이 매몰되고, 상기 상부 지압판(120)은 노출되도록 상기 버림 콘크리트(2)를 타설하는 것을 특징으로 하는 부력앵커의 시공방법.
6. The method of claim 5,
The method of claim 1,
Wherein the lower pavement plate 110 of the pavement structure 100 is buried and the pavement concrete 2 is poured to expose the upper pavement plate 120.
제5항에 있어서,
상기 배근단계는,
배근되는 상기 철근(3)과 상기 지압판 구조물(100)의 간격부재(130) 또는 상부 지압판(120)을 상호 결합하는 것을 특징으로 하는 부력앵커의 시공방법.
6. The method of claim 5,
In the step of laying,
Wherein the reinforcing bars (3) and the spacing member (130) or the upper supporting plate (120) of the supporting plate structure (100) are joined to each other.
제1항 내지 제4항 중 어느 한 항의 지압판 구조물(100)을 이용한 부력앵커의 시공방법으로서,
지반에 천공 홀(1)을 형성하는 천공단계;
상기 천공 홀(1)에 상기 앵커체(20)를 삽입하는 앵커체 삽입단계;
상기 천공 홀(1)에 그라우트(G)를 주입하는 그라우팅 단계;
상기 지면에 버림 콘크리트(2)를 타설하는 버림 콘크리트 타설단계;
상기 앵커체(20)의 상단이 상기 관통공(111) 및 정착공(121)을 관통하여 상부로 노출되도록, 상기 버림 콘크리트(2)의 상면에 상기 지압판 구조물(100)을 설치하는 지압판 구조물 설치단계;
상기 앵커체(20)를 긴장하여 상기 정착공(121)에 정착하는 앵커체 정착단계;
상기 버림 콘크리트(2)의 상부에 철근(3)의 배근을 실시하는 배근단계;
상기 지압판 구조물(100)이 매몰되도록, 상기 버림 콘크리트(2)의 상부에 기초 콘크리트(4)를 타설하는 기초 콘크리트 타설단계;를
포함하는 것을 특징으로 하는 부력앵커의 시공방법.
A method of constructing a buoyant anchor using the paving structure (100) of any one of claims 1 to 4,
Forming a perforation hole (1) in the ground;
Inserting the anchor body (20) into the perforation hole (1);
A grouting step of injecting a grout (G) into the perforation hole (1);
Placing the abandoned concrete (2) on the ground;
The upper surface of the anchor body 20 is exposed through the through hole 111 and the fixing hole 121 so that the upper surface of the lower concrete 2 is installed on the upper surface of the anchor sheet 20, step;
Fixing the anchor body (20) to the fixing hole (121) by tightening the anchor body (20);
A step of laying the reinforcing bars (3) on the upper part of the abandoned concrete (2);
Placing a foundation concrete (4) on an upper part of the abandoned concrete (2) so that the paving structure (100) is buried;
Wherein the buoyant anchor is formed of a metal.
KR1020140094058A 2014-07-24 2014-07-24 Construction method for buoyancy protection anchor KR101596245B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020140094058A KR101596245B1 (en) 2014-07-24 2014-07-24 Construction method for buoyancy protection anchor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020140094058A KR101596245B1 (en) 2014-07-24 2014-07-24 Construction method for buoyancy protection anchor

Publications (2)

Publication Number Publication Date
KR20160012512A true KR20160012512A (en) 2016-02-03
KR101596245B1 KR101596245B1 (en) 2016-02-22

Family

ID=55355540

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020140094058A KR101596245B1 (en) 2014-07-24 2014-07-24 Construction method for buoyancy protection anchor

Country Status (1)

Country Link
KR (1) KR101596245B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101954755B1 (en) 2018-07-19 2019-06-17 주식회사 서웅이엔씨 Pressure sleeve for preventing buoyancy and buoyancy anchor construction method using the same

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100832101B1 (en) * 2007-02-01 2008-05-29 주식회사 삼우기초기술 Supporting device for a ground anchor fixing equipment
JP2009257006A (en) * 2008-04-18 2009-11-05 Masashi Sasaki Ground anchor construction method
KR20110121043A (en) * 2010-04-30 2011-11-07 주식회사 다모이엔씨 Pile foundation and method for constucting the same

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100832101B1 (en) * 2007-02-01 2008-05-29 주식회사 삼우기초기술 Supporting device for a ground anchor fixing equipment
JP2009257006A (en) * 2008-04-18 2009-11-05 Masashi Sasaki Ground anchor construction method
KR20110121043A (en) * 2010-04-30 2011-11-07 주식회사 다모이엔씨 Pile foundation and method for constucting the same

Also Published As

Publication number Publication date
KR101596245B1 (en) 2016-02-22

Similar Documents

Publication Publication Date Title
US9783949B2 (en) Soil anchor footing
CN103912000B (en) Construction method for reusable composite-material soil nailing wall supporting face plate
KR101212240B1 (en) Structure for underground downward extension of structural remodeling and methode thereof
US20220380996A1 (en) Methods for constructing tensionless concrete pier foundations and foundations constructed thereby
US9683347B2 (en) Systems and methods to reinforce excavation walls
KR101598275B1 (en) Method of construction of line type supports at large section tunnel having low flat rate
KR101013778B1 (en) Structure construction method to pile using support appratus
KR20180137268A (en) Aseismatic Reinforcement Steel Frame with Friction Slip Brace and Aseismatic Reinforcement Method using thereof
KR101596245B1 (en) Construction method for buoyancy protection anchor
JP3198237U (en) Reinforcing equipment for concrete structures
JP6632290B2 (en) Steel column leg structure and steel column leg construction method
KR101993609B1 (en) Earth retaining structure using concrete block for the anchorage of anchor pc-strands and construction method thereof
JP6283906B2 (en) Prop foundation
KR20130121271A (en) Assemblies for supporting earth anchor of soil retaining wall and soil retaining wall constructing method using the same
KR20150010421A (en) Cap beam assembly
KR20060048843A (en) Reinforcement structure for a foundation pile
KR101534058B1 (en) Soil retaining wall for load support and constructing method thereof
KR101198871B1 (en) Transverse supporting apparatus for standing underground retaining walls being given the earth pressure of backfill
JP5852475B2 (en) Pile foundation reconstruction method
JP5056534B2 (en) Structure installation method for water gradient floor
KR20090003933A (en) Retaining wall using panel and constructing method thereof
KR20040051182A (en) Temporary soil sheathing using prestress and pile thereof
KR100980623B1 (en) Foundation anchorage and method for anchoraging micro pile using the same
AU2013200425B2 (en) Soil Anchor Footing
KR101397403B1 (en) Building extension method using modular unit fixed to roof slab concrete

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20190218

Year of fee payment: 4