KR20130099581A - Stanchion integrated scaffolding stage bracket - Google Patents

Stanchion integrated scaffolding stage bracket Download PDF

Info

Publication number
KR20130099581A
KR20130099581A KR1020120021200A KR20120021200A KR20130099581A KR 20130099581 A KR20130099581 A KR 20130099581A KR 1020120021200 A KR1020120021200 A KR 1020120021200A KR 20120021200 A KR20120021200 A KR 20120021200A KR 20130099581 A KR20130099581 A KR 20130099581A
Authority
KR
South Korea
Prior art keywords
bracket
support
scaffold
scaffolding
hole
Prior art date
Application number
KR1020120021200A
Other languages
Korean (ko)
Inventor
홍원표
황호진
Original Assignee
에스티엑스조선해양 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 에스티엑스조선해양 주식회사 filed Critical 에스티엑스조선해양 주식회사
Priority to KR1020120021200A priority Critical patent/KR20130099581A/en
Publication of KR20130099581A publication Critical patent/KR20130099581A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/06Consoles; Brackets
    • E04G5/062Consoles; Brackets specially adapted for attachment to building walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/08Scaffold boards or planks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/14Railings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Ladders (AREA)

Abstract

In the bracket for supporting the scaffold of the scaffolding, the support is hingedly coupled to the scaffolding bracket, and when the scaffold is installed, the rail is vertically rotated to install the railing. When dismantling the scaffolding, the support is rotated horizontally and folded on the scaffolding bracket, and the support bracket is integrated with the scaffolding bracket, which completes the installation of the scaffolding by installing the scaffolding, thereby reducing the work time and facilitating the management of the components of the scaffolding.
The present invention, the bracket support is fixedly attached to the structure; A footrest bracket coupled to the bracket support part and extending in a direction perpendicular to the structure to have a footrest installed at an upper portion thereof; The support is coupled to the outside of the scaffold bracket to be installed to extend the installation for a long time; is integrally formed by the hinge, the support is easy to install and store as the scaffold bracket and the folding can be combined.

Description

Support integrated scaffolding stage bracket

The present invention relates to a support integrated footrest bracket.

In detail, the present invention, in the bracket for supporting the scaffolding of the scaffold, the support bracket is hingedly coupled to the scaffolding bracket, the installation of the handrail by vertically rotating the support coupled to the scaffolding bracket when the scaffold is installed When dismantling the scaffold, the support is rotated horizontally, folded to the foot bracket, completes the installation of the foot bracket through the installation of the foot bracket to shorten the working time, and easy to manage the scaffold component bracket. .

Scaffolding is a temporary construction used for aerial work and is used as a material carrier or a worker's passage. To install the scaffolding, first install a scaffolding bracket to which the scaffold is installed, install a support for the handrail installation on the scaffolding bracket, and then install the scaffold and railing to complete the scaffold.

However, the above method requires more time because the installation process is made in two stages, and the scaffold bracket and the support are configured separately, so that components of the scaffold are not easily managed, and the support is used during installation and dismantling of the scaffold. There is a risk of falling.

Conventional technology, there is a construction scaffolding safety scaffolding and its manufacturing and installation method (application number: 10-2010-0124599), Figure 1 shows the technique. The above technique is to prevent the fall by attaching the auxiliary scaffold between the scaffolding and the scaffolding pipe, but the height of the auxiliary scaffold needs to install additional railings.

There is also a scaffold for scaffolding (application number: 10-2006-0004917), and Fig. 2 shows the above technique. The above technology is a structure that is coupled to the scaffolding and the scaffolding frame, one side of the scaffolding can be opened and closed by the hinge rotation, but because there is no railing to prevent the fall must be installed a separate railing.

The present invention has been made to solve the above problems.

Accordingly, the present invention, in the bracket for supporting the scaffolding of the scaffold, the support bracket is hingedly coupled to the scaffolding bracket, the installation of the handrail by vertically rotating the support coupled to the scaffold bracket when the scaffold is installed When dismantling the scaffold, the support is rotated horizontally and folded on the scaffold bracket, which completes the installation of the scaffold bracket to complete the installation of the scaffold, thereby shortening the working time and providing an integrated scaffold bracket for easy scaffold component management. There is a purpose.

In order to achieve the above object, the present invention has the following configuration.

The present invention, the bracket support is fixedly attached to the structure; A footrest bracket coupled to the bracket support part and extending in a direction perpendicular to the structure to have a footrest installed at an upper portion thereof; The support is coupled to the outside of the scaffold bracket to be installed to extend for a long time to install the handrail; is formed integrally by the hinge, so that the support is easy to install and store as the scaffold bracket and the folding can be combined .

Here, the scaffold bracket is a hinge hole for hinge coupling with the support, a horizontal fixing hole is formed in the hinge hole spaced apart in the longitudinal direction of the scaffold bracket, spaced in the width direction of the scaffold bracket in the hinge hole to form a vertical fixing hole Thus, the fixing is maintained by the support fixing hole and the fixing pin in the horizontal fixing hole and vertical fixing hole.

In addition, the support is a hinge hole formed in a position corresponding to the hinge hole of the foot bracket, the support hole is formed by being spaced apart in the longitudinal direction of the support from the hinge hole, the foot rest by engaging with the horizontal fixing hole and the vertical fixing hole of the foot bracket It is folded horizontally or vertically with the bracket.

As described above, the present invention, in the bracket for supporting the scaffolding of the scaffolding, the support bracket is hingedly coupled to the scaffolding bracket, the following effects are obtained.

If the footrest bracket is installed, the support rail can be vertically rotated so that the railing can be immediately installed, so that a separate supporter installation process is omitted, thereby reducing work time.

In addition, since the support integrated scaffold bracket according to the present invention has a structure in which the scaffold bracket and the support are integrated, there is no fear that the support falls during the installation and dismantling of the scaffold, so that the work can be carried out safely and easily, and the worker is loaded on the vehicle. And it is easy to transport to the site and also easy to store in the warehouse after dismantling the scaffold.

In particular, it is possible to efficiently manage the components of the scaffold to prevent the loss or loss of components due to poor management, thereby reducing maintenance costs.

1 is a perspective view of a conventional construction scaffolding safety scaffold and its manufacturing and installation method.
Figure 2 is a perspective view of a scaffold for the prior art.
Figure 3 is a front view of the support integrated unit footrest bracket installed state according to the present invention.
Figure 4 is a part of the support integral footrest bracket according to the present invention.
5 is a front view of a horizontal state and a vertical state of the support integrated scaffold bracket according to the present invention.
Figure 6a is a front view, a side view, a plan view, a bottom view of a horizontal state of the support integrated scaffold bracket according to the present invention.
Figure 6b is a front view, a side view of the vertical state of the support integrated scaffold bracket according to the present invention.

Embodiments of the present invention will now be described in detail with reference to the accompanying drawings.

Figure 3 is a front view of the support integrated scaffold bracket according to the present invention is installed, Figure 4 is a part view of the integrated support scaffold bracket according to the present invention, Figure 5 is a vertical state and vertical of the support integrated scaffold bracket according to the present invention 6A is a front view, a side view, a plan view, and a bottom view of a horizontal state of a support integrated footrest bracket according to the present invention, and FIG. 6B is a front view and a side view of a vertical state of a support integrated footrest bracket according to the present invention. to be.

Referring to the drawings, the support integrated scaffold bracket according to the present invention, in the bracket for supporting the scaffolding of the scaffold, is composed of the scaffold bracket 100, the support 200, the hinge 300, the fixing pin 400.

In the present invention, since the support is hinged to the scaffold bracket so that the hinge can be pivoted, the weight of the worker, the tool, and the materials applied to the scaffold and the railing are considered, and the scaffold is frequently installed and dismantled, so that the mechanical properties and chemicals Although a metal material having excellent properties is applied, the material of the fixing pin 400 is superior in mechanical properties to the material of the fixing pin 400 because the load of the support pin 200 is large.

Here, the scaffolding bracket 100 is a bracket for supporting the scaffolding of the scaffold installed for the aerial work, one side of the scaffolding bracket 100 is formed with a hinge hole 110 is installed hinge (300) support ( 200 is hinge-coupled, the horizontal fixing hole 120 is inserted into the fixing pin 400 for maintaining the horizontal state of the support 200 is spaced in the longitudinal direction of the foot bracket 100 in the hinge hole 110 And a vertical fixing hole 130 into which the fixing pin 400 is inserted to maintain the vertical state of the support 200 is spaced apart from the hinge hole 110 in the width direction of the scaffold bracket 100. On the other side of the scaffold bracket 100, an installation hole 140 is installed to be installed on the bracket mounting table 10 installed in the structure.

In addition, the support 200 is hinged to one side of the scaffold bracket 100, extends in the longitudinal direction for the handrail installation, so that the handrail is installed by pivoting vertically of the scaffold bracket 100 when the scaffold is installed. When dismantling the scaffold, the bracket 100 is rotated horizontally and folded on the scaffold bracket 100.

As such, since the scaffolding bracket 100 and the support 200 are integrated, the possibility of the support 200 falling down when the scaffold is installed and dismantled is eliminated, so that the work proceeds safely and easily, and when folded, the size is reduced. It is so small that it can be easily loaded on the vehicle and transported to the site, and also easily stored in a warehouse after dismantling the scaffold, thus preventing damage and loss due to mismanagement.

Here, the support 200 is a hinge hole 210 is installed on one side of the hinge 300 is installed for the hinge rotation, the fixing hole formed to be spaced apart in the longitudinal direction of the support 200 in the hinge hole 210 The fixing pin 400 is inserted to maintain the horizontal state or the vertical state 220.

In addition, the support 200 includes a handrail bracket 230, which is a space where the handrail is installed for handrail installation, and the number of handrails to be installed is equally spaced in large numbers in consideration of falling of a worker, a work tool, and materials. Install it to prevent safety accidents.

In particular, in order to prevent the loss of the fixing pin 400 may be connected to the support 200 by connecting a chain or string.

Referring to FIG. 3, the procedure of installing the scaffold using the support integrated scaffold bracket of the present invention is as follows.

First, the scaffold bracket 100 is fixed to the bracket mounting table 10 installed in the structure through the mounting hole 140 formed at the other side of the scaffold bracket 100.

After pulling out the fixing pin 400 inserted into the fixing hole 220 of the support 200 which is folded in the scaffold bracket 100 and the horizontal state is maintained, the support 200 is rotated vertically, and the fixing pin When the 400 is inserted into the fixing hole 220, the vertical state of the support 200 is maintained by penetrating through the vertical fixing hole 130 of the scaffold bracket 100.

In consideration of the size and safety of the scaffolding, two or more scaffolding brackets 100 are installed as described above, and the handrail bracket 230 of the support 200 pivoted vertically also includes a plurality of handrails.

Disassembly is performed in the reverse order of the above.

10: bracket mounting bracket 100: scaffolding bracket
110: hinge hole 120: horizontal
130: vertical fixing hole 140: mounting hole
200: support 210: hinge ball
220: support fixing hole 230: handrail bracket
300: hinge 400: fixed pin

Claims (3)

A bracket support part 10 fixedly attached to the structure;
A footrest bracket (100) coupled to the bracket support portion (10) and extending in a direction perpendicular to the structure to have a footrest installed thereon;
Is coupled to the outside of the scaffold bracket 100 is a support (200) is installed to extend long to install a railing;
It is integrally formed by the hinge 300, the support 200 is a stand-alone foot bracket, characterized in that to facilitate the installation and storage as the foot bracket bracket 100 and foldable.
According to claim 1, wherein the scaffold bracket 100
Hinge hole 110 for hinge coupling with the support 200, and the horizontal fixing hole 120 is formed in the hinge hole 110 in the longitudinal direction of the foot bracket 100 is formed, the hinge hole 110 A vertical fixing hole 130 is formed to be spaced apart in the width direction of the scaffold bracket 100 in the), the support fixing hole 220 and the fixing pin 400 in the horizontal fixing hole 120 and the vertical fixing hole 130 The fixed stand footrest brackets, characterized in that the fixing is maintained by.
The method of claim 1, wherein the support 200
The hinge hole 210 formed at a position corresponding to the hinge hole 110 of the footrest bracket 100 and the support hole fixing hole 220 are formed to be spaced apart from the hinge hole 210 in the longitudinal direction of the support 200. Support plate integrated scaffold bracket, characterized in that to be folded horizontally or vertically with the scaffold bracket 100 by engaging with the horizontal fixing hole 120 and the vertical fixing hole (130) of the scaffold bracket (100).

KR1020120021200A 2012-02-29 2012-02-29 Stanchion integrated scaffolding stage bracket KR20130099581A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020120021200A KR20130099581A (en) 2012-02-29 2012-02-29 Stanchion integrated scaffolding stage bracket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020120021200A KR20130099581A (en) 2012-02-29 2012-02-29 Stanchion integrated scaffolding stage bracket

Publications (1)

Publication Number Publication Date
KR20130099581A true KR20130099581A (en) 2013-09-06

Family

ID=49450863

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020120021200A KR20130099581A (en) 2012-02-29 2012-02-29 Stanchion integrated scaffolding stage bracket

Country Status (1)

Country Link
KR (1) KR20130099581A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101995334B1 (en) * 2017-12-27 2019-07-03 삼성중공업(주) Device for setting up a scaffolding on the block of a hull
US11585106B2 (en) * 2016-04-08 2023-02-21 Peri Se Side protector, ceiling formwork system having at least one such side protector, and method for erecting such a side protector

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11585106B2 (en) * 2016-04-08 2023-02-21 Peri Se Side protector, ceiling formwork system having at least one such side protector, and method for erecting such a side protector
KR101995334B1 (en) * 2017-12-27 2019-07-03 삼성중공업(주) Device for setting up a scaffolding on the block of a hull

Similar Documents

Publication Publication Date Title
KR101654483B1 (en) The building is equipped with safety scaffold equipment
US9803384B2 (en) Safety barrier netting system
US20100025563A1 (en) Formwork system
CN101341306A (en) System for saving and evacuating persons, which is applied to buildings
CN102168484B (en) External hanging scaffold and application method thereof
KR20130099581A (en) Stanchion integrated scaffolding stage bracket
JP2006348579A (en) Scaffolding board capable of being used as both staircase and ladder
JP5594678B2 (en) Scaffolding material for storage tank
CN105926918A (en) Foldable elevator shaft operation steel platform device and erecting method
FI126773B (en) Vertical support structure for guardrail construction in roofing
CN111527302B (en) Method for building a tower, tower segment, supply structure and tower
KR101346702B1 (en) Structure with supporter and safe rail for mold
US2883241A (en) Scaffolding accessory
IES20100326A2 (en) An advanced guard rail
JP2008095373A (en) Moving scaffold and its temporary construction method
KR101743587B1 (en) Lateral pressure supporter of double insulated wall form
KR102027845B1 (en) Foldable scaffold frame
RU141467U1 (en) WALL BRACKET
KR200288007Y1 (en) Rail railing (scaffolding) clamping device in the construction site.
JP3347283B2 (en) Assembling scaffolding equipment for skewing moving transfer equipment
KR100825186B1 (en) Safety net foundation framework
CN220014275U (en) Temporary protective fence for side edges of multi-layer stairs
JP2014234685A (en) Cloth material in temporary building
JP2019081636A (en) Ladder apparatus for elevator pit
KR102230963B1 (en) Variable Type boarding box of high place works car

Legal Events

Date Code Title Description
WITN Withdrawal due to no request for examination