KR20120106037A KR1020110023863A KR20110023863A KR20120106037A KR 20120106037 A KR20120106037 A KR 20120106037A KR 1020110023863 A KR1020110023863 A KR 1020110023863A KR 20110023863 A KR20110023863 A KR 20110023863A KR 20120106037 A KR20120106037 A KR 20120106037A
Authority
KR
South Korea
Prior art keywords
thumb pile
installation
anchor body
thumb
pile
Prior art date
Application number
KR1020110023863A
Other languages
Korean (ko)
Other versions
KR101386275B1 (en
Inventor
이기호
Original Assignee
이기호
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이기호 filed Critical 이기호
Priority to KR1020110023863A priority Critical patent/KR101386275B1/en
Publication of KR20120106037A publication Critical patent/KR20120106037A/en
Application granted granted Critical
Publication of KR101386275B1 publication Critical patent/KR101386275B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/80Ground anchors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Foundations (AREA)

Abstract

PURPOSE: A temporary sheathing structure and an installation method thereof are provided to reduce weight applied to an anchor body by removing waling. CONSTITUTION: A temporary sheathing structure comprises an H-pile(110), a guide frame(120), horizontal connecting plates(130), a forepoling and retaining plate(140), a soil retaining plate(150), and anchor bodies(160). The plurality of H-pile comprises a pair of plates and is installed under the ground. The pair of plate is connected through a connection rib(112). Anchor holes are bored longitudinally through the plates. The guide frame forms a vertical passage(121). The horizontal connecting plates connect the H-piles. The forepoling and retaining plate is inserted in the guide frame and slid down through the self-weight. The retaining plate is inserted between the H-piles.

Description

가설 흙막이 구조물 및 그 설치방법{Reformed sheet plate and the method of installation of the same} Reformed sheet plate and the method of installation of the same}

본 발명은 가설 흙막이 구조물 및 그 설치방법에 관한 것으로, 상세하게는 각종 지하 굴착 공사를 하고자 할 때, 일정한 길이로 제작된 H형 엄지말뚝을 굴착 공사와 병행하여 측벽 지중에 삽입하고, 상기 H형 엄지말뚝을 먼저 시공한 앵커체로 고정한 다음, 상기 H형 엄지말뚝 사이에 토류판을 삽입하여 굴착 내부로 지반의 붕괴나 토사 유입을 방지하도록 하되, 특히 띠장이나 받침대, 브래킷(Bracket), 스티프너(Stiffner), 홈메우기 등을 생략하여 구조를 간단히 함으로써 효율적으로 굴착공사를 시행할 수 있도록 하는 가설 흙막이 구조물 및 그 설치방법에 관한 것이다.The present invention relates to a temporary earthquake structure and a method for installing the same. Specifically, when various underground excavation work is to be carried out, an H-type thumb pile manufactured to a certain length is inserted in parallel with an excavation work and inserted into the sidewall underground, and the H-type The thumb pile is fixed with the anchor body first constructed, and then the earth plate is inserted between the H-shaped thumb piles to prevent the collapse of the ground or the inflow of soil into the excavation, in particular, a belt, a pedestal, a bracket, a stiffner The present invention relates to a temporary earthquake structure and a method of installing the same, which simplify the structure by omitting a groove filling and the like, thereby enabling an efficient excavation work.

일반적으로 지하구조물을 구축하는 방법에는 지하구조물이 축조되는 지반에 흙막이 공사를 한 다음 지반을 굴착하면서 흙막이를 지지할 수 있는 가시설물을 설치하고 토사를 전부 반출한 뒤 맨 아래층에서부터 구조물을 축조해 올라가는 순타설공법과, 흙막이를 시공하고 1층 구조물을 축조한 뒤 그 구조물을 흙막이용 버팀대로 이용하여 상부에서 하부로 지반을 굴착하면서 구조물을 축조해 내려가는 역타설 공법이 있다.In general, the construction of underground structures involves the construction of earthquakes on the ground where the underground structures are constructed, and then installs the temporary facilities that can support the earthquakes while excavating the ground, and then removes all the soil and builds the structure from the bottom floor. There is a net pouring method and a reverse pouring method that constructs a 1-story structure, and then builds the structure by digging the ground from the top to the bottom using the structure as a brace for the structure.

한편, 건축물의 기초 등을 지하에 구축하기 위한 지반 굴착 공사에서 주변 지반의 안정 및 지하수의 차수를 목적으로 하는 흙막이 공사가 선행되어야 한다.On the other hand, in the ground excavation work to build the foundation of the building, etc., the earthquake construction for the purpose of stabilization of the surrounding ground and the order of the groundwater should be preceded.

특히, 용적률 확보 및 지가 상승 등의 요인으로 인해 도심지의 한정된 대지상의 굴착공사는 대지경계선에 인접하여 시공되고 있으며, 좁은 토지를 효율적으로 활용하는 방안으로 지하굴착 심도를 더욱 깊게 시공하며, 대지경계선에 인접하여 시공하는 경우에는 기존시설물이나 인접건물을 보호하기 위해 흙막이 벽의 설치가 요구된다. In particular, due to factors such as securing a floor area ratio and rising land prices, limited excavation work in urban areas is being constructed adjacent to the land boundary line, and the underground excavation depth is further deepened to efficiently utilize the narrow land. In the case of adjacent construction, it is required to install the retaining wall to protect existing facilities or adjacent buildings.

이러한 흙막이 벽의 시공방법은 엄지말뚝을 지중에 설치하고 지하로 굴착해 내려가면서 토류판을 끼워 설치하는 방법, 쉬트파일의 조인트부를 맞물려 지중에 널말뚝을 설치한 강제 널말뚝 방법, 소일시멘트 기둥을 연속해서 만들고 그 속에 보강재를 삽입하여 콘크리트재를 타설하는 방법, 땅속에 벽체구멍을 파고 철근 틀을 삽입하여 콘크리트를 타설하는 방법 등이 있다. The construction method of the earthen wall is to install the thumb pile in the ground and excavate and install the earth plate while going down the ground, the steel plate pile method in which the pile pile is installed in the ground by engaging the joint part of the sheet pile, and the soil cement column is made continuously. There is a method of placing concrete material by inserting reinforcement in it, or digging a wall hole in the ground, and placing concrete by inserting a reinforcing frame.

본 발명의 배경기술은 상기 엄지말뚝을 지중에 설치하고, 지하로 굴착해 내려가면서 토류판을 끼워 설치하는 방법에 해당된다.The background art of the present invention corresponds to a method of installing the thumb pile in the ground and installing the earth plate while digging down into the basement.

또한, 흙막이 벽의 자립을 위한 지보구조에는 자립식, 앵커체, 버팀대, 레이커(Racker), 케이블 타이(Cable Tie) 등이 있다. In addition, the support structure for the self-support of the retaining wall includes a self-supporting type, anchor body, brace, Racker, Cable Tie.

종래에 주로 시공한 흙막이 벽체는 지상에서 수평으로 일정거리마다 지중에 수직 천공하여 홀(Hole)을 만들고 홀에 엄지말뚝을 박고 지하방향으로 굴착해 내려가면서 엄지말뚝 사이에 토류판을 끼워서 흙막이 벽체를 형성한다.Conventionally constructed mud wall is vertically perforated at a certain distance horizontally from the ground to make a hole (Hole) to form a mud wall by sandwiching the earth plate between the thumb pile while drilling the thumb pile in the hole and going down the underground direction do.

또한, 흙막이 벽체의 지보구조는 흙막이 벽체에 작용하는 토압을 계산하여 지하로 일정한 간격의 단을 만들고, 상기 각 단마다 엄지말뚝에 띠장 받침대를 설치하여 수평으로 나란하게 띠장을 설치한 후, 버팀대를 설치하거나, 흙막이 벽체의 지중에 앵커체를 설치하여 강결시켰다.In addition, the support structure of the retaining wall is to calculate the earth pressure acting on the retaining wall to create a step at a constant distance underground, and to install the bands horizontally and side by side by installing a band rest on the thumb pile for each step. Or anchored in the ground of the retaining wall to harden.

상기 버팀대 및 앵커체는 엄지말뚝과 토류판으로 구성된 흙막이 벽체 후방의 토압이 띠장에 작용하여 띠장에서 전달되는 반력을 지지하는 압축재, 또는 인장재의 역할을 하였다. 즉 흙막이 벽체의 토압은 토류판에서 엄지말뚝으로, 엄지말뚝에서 띠장으로, 띠장에서 버팀대 또는 앵커체로 전달되는 지보구조로 되어 있다.The brace and the anchor body acted as a compressive material or tension member supporting the reaction force transmitted from the strip by the earth pressure of the rear wall of the earth wall consisting of the thumb pile and the earth plate acts on the strip. In other words, the earth pressure of the retaining wall is a support structure that is transmitted from the earth plate to the thumb pile, from the thumb pile to the belt, and from the belt to the prop or anchor.

토류판 및 띠장, 앵커체를 각 단마다 설치하면서 최종굴착 심도까지 굴착이 완료되면 지하 구조물을 단계적으로 시공하고, 구조물과 흙막이 벽체 사이를 흙으로 되메우기하며, 흙막이 구조물(토류판, 띠장, 버팀대, 앵커체)의 해체를 병행하여 지상으로 올라와 최종 엄지말뚝을 지상에서 인발 해체하였다.When the excavation is completed to the final excavation depth by installing the earth plate, the belt and the anchor body at each stage, construct the underground structure step by step, backfill the soil between the structure and the wall of the earth, and make the earthen structure (earth plate, belt, brace, anchor body) ) Dismantled in parallel to the ground to remove the final thumb pile from the ground.

그러나 이러한 종래의 기술은 엄지말뚝의 설치를 위해 대형천공기로 지반을 천공하고, 크레인으로 엄지말뚝을 천공 홀에 박고, 엄지말뚝의 해체할 경우 인발기를 사용해야 한다. 또한, 엄지말뚝 및 띠장의 이음, 띠장 받침대, 스티프너, 홈메우기, 브래킷 등의 제작과 설치를 위해 발전기를 필요로 하는 등의 작업공정이 복잡하고, 작업 준비로 인해 공사비가 증가할 뿐만 아니라 장비로 인한 소음 및 비산먼지가 발생하고, 안전사고의 위험성이 높다.However, such a conventional technique is to drill the ground with a large perforator for the installation of the thumb pile, to put the thumb pile into the drilling hole with a crane, and to use the pull-out when dismantling the thumb pile. In addition, the work process, such as the need for a generator for the manufacture and installation of thumb piles and strips, strip holders, stiffeners, grooves, and brackets, is complicated, and the cost of construction increases as well as equipment. Noise and scattering dust are generated and the risk of safety accident is high.

따라서 이러한 문제점을 해소하기 위하여 본 발명의 주목적은 엄지말뚝을 일정한 길이로 제작하여 대형장비(천공기, 크레인, 인발기, 발전기)를 사용하지 않고, 굴착장비(굴삭기)만으로 흙막이 벽체의 시공이 가능하도록 하여 신속하고 안전하게 시공할 수 있을 뿐만 아니라, 이로 인하여 소음이나 진동 및 비산 먼지를 최소화하기 위한 가설 흙막이 구조물 및 그 설치방법을 제공하는 데 있다.Therefore, in order to solve this problem, the main purpose of the present invention is to make the thumb pile to a certain length so that the construction of the retaining wall only by excavating equipment (excavator) without using large equipment (perforator, crane, drawing machine, generator). In addition to the construction can be quickly and safely, to provide a temporary block structure and installation method for minimizing noise, vibration and scattering dust.

본 발명의 다른 목적은 띠장을 생략하여 띠장 무게만큼 앵커체에 작용하는 하중을 줄이고, 띠장 폭 만큼 굴착량의 감소는 물론, 띠장과 관련된 받침대, 스티프너, 홈메우기, 브래킷 등의 제작 및 설치 등을 생략하여 공사비를 크게 절감 시킬 수 있도록 하는 가설 흙막이 구조물 및 그 설치방법을 제공하는 데 있다. Another object of the present invention is to reduce the load acting on the anchor body by the weight of the belt length by omitting the length of the belt, reduce the amount of excavation by the width of the length of the belt, as well as the manufacture and installation of the base, stiffeners, grooves, brackets, etc. It is to provide a temporary block structure and installation method that can be omitted to greatly reduce the construction cost.

따라서 상기한 목적을 달성하기 위하여 토류판과 엄지말뚝으로 구성된 흙막이 벽체와 앵커체의 연결매체인 띠장을 생략하기 위해 띠장위에 설치되는 브래킷을 엄지말뚝과 일체화 시켜 흙막이 벽체에 작용하는 토압이 띠장을 통하지 않고 직접 앵커체로 전달되도록 하는 본 발명의 가설 흙막이 구조물은 일정한 길이의 한 쌍의 플레이트 사이를 연결리브로 연결하고 플레이트를 전후로 관통하는 앵커체의 강선을 삽입하는 앵커공을 천공하고 앵커공 전면에 부착되는 브래킷으로 결합된 엄지말뚝과, 상기 엄지말뚝의 플레이트의 내부 면에 결합하여 수직으로 통로를 형성하는 가이드프레임과, 상기 엄지말뚝을 횡으로 연결하여 결합하는 수평연결대와, 상기 가이드프레임에 삽입하여 자중에 의해 하부로 슬라이딩하는 쏠장토류판과, 상기 엄지말뚝과 엄지말뚝 사이에 끼워 조립하는 토류판 및 상기 엄지말뚝의 앵커공을 통하여 지중에 설치하여 엄지말뚝을 지지하는 앵커체로 구성함을 그 기술적 구성상의 기본 특징으로 한다.Therefore, in order to achieve the above object, the earth pressure acting on the earth wall is not integrated with the thumb pile by integrating the earth wall and the anchor wall consisting of the earth plate and the thumb pile and the anchor, which is the connecting medium of the anchor body. Hypothetical earth structure of the present invention to be directly delivered to the anchor body without connecting a pair of plates of a certain length connected by a connecting rib and punctures the anchor hole for inserting the steel wire of the anchor body penetrating back and forth through the plate and attached to the anchor hole front A thumb pile coupled with a bracket, a guide frame coupled to the inner surface of the plate of the thumb pile to form a vertical passage, a horizontal connecting rod connecting the thumb pile laterally, and inserted into the guide frame Sole soil plate sliding by the lower portion, and the thumb pile That through the toryupan and the anchor hole of the thumb peg assembly sandwiched between the support piles installed in the ground anchor body configured for supporting a thumb piles shall be based on the feature that the technical configuration.

본 발명의 가설 흙막이 구조물의 설치방법은 엄지말뚝의 조립 방법에 따라 위아래를 맞이음하는 일자형과 겹쳐 이음 하는 계단형으로 구분되며, 일정한 길이로 제작된 엄지말뚝을 한단으로 하여 흙막이 구조물을 완성하며 한단, 한단 지하로 굴착한다.The installation method of the temporary earthquake structure according to the present invention is divided into a step shape overlapping with a straight line that meets the upper and lower sides according to the assembly method of the thumb pile, and the earthquake structure is completed by completing the end of the earthquake structure with a single end made of a constant length. , Excavate underground.

시공방법은 흙막이 벽체의 설치라인의 내측으로 사면안정을 이루는 경사법면(1:1)을 유지하며 앵커체 설치 위치까지 경사법면(1:1)을 제외한 굴착단면 전부를 1차 굴착하고, 엄지말뚝을 경사법면(1:1)에 매입하기 위한 2차 굴착은 가능한 좁은 폭으로 경사법면(1:1)에 굴착하되, 주변토사의 붕괴 및 유실을 방지하기 위하여 첫째 단에선 쏠장토류판을 자립식으로 설치하고, 둘째 단 부터는 엄지말뚝에 삽입된 쏠장토류판을 내리며 굴착한다.The construction method maintains the sloped surface (1: 1) which makes the slope stability inside the installation line of the retaining wall, and excavates all the excavated sections except the sloped surface (1: 1) to the anchor body installation position. 2nd excavation for embedding on the sloped surface (1: 1) should be excavated to the sloped surface (1: 1) with the narrowest possible width, but in order to prevent the collapse and loss of surrounding soil, From the second stage, excavate by lowering the soil plate inserted in the thumb pile.

그 다음, 2차 굴착된 경사법면(1:1)의 측벽에 앵커체 홀(Hole)을 천공하여 앵커체를 지중에 설치하고, 쏠장토류판이 삽입된 엄지말뚝을 앵커체와 조립하여 설치한 다음, 좌우 엄지말뚝을 수평연결대로 연결하고, 엄지말뚝 배면을 시멘트 모르타르로 충진하고, 좌우 엄지말뚝 사이에 토류판을 끼우며 엄지말뚝 선단까지 3차 굴착하여 한 단의 흙막이 구조물을 완성한다.Then, the anchor body hole (Hole) is drilled on the sidewall of the second excavated inclined surface (1: 1), and the anchor body is installed in the ground, and the thumb pile into which the sole soil plate is inserted is assembled with the anchor body. Connect the left and right thumb piles with a horizontal connection, fill the back of the thumb pile with cement mortar, insert a earth plate between the left and right thumb piles, and excavate three times to the tip of the thumb pile to complete the structure of one stage.

이러한 흙막이 구조물의 완성을 반복하며 원하는 심도까지 안전하게 굴착하는 것을 그 기술적 구성의 기본 특징으로 한다.Repeating the completion of the structure of the earth block and the excavation safely to the desired depth is the basic feature of the technical configuration.

이러한 본 발명의 가설 흙막이 구조물 및 그 설치방법은 브래킷을 부착하여 일정한 길이로 제작한 엄지말뚝을 바둑판 모양으로 측벽 지중에 설치하는 각각의 앵커체와 조립하고, 좌우 엄지말뚝을 수평연결대로 결합한 다음, 상기의 좌우 엄지말뚝 사이에 토류판을 끼워 흙막이 구조물을 완성하는 것으로 굴착장비로 시공이 가능하여 기존방식과는 엄지말뚝의 시공방법이 달라지고, 띠장이 생략된다.The construction of the temporary earthquake structure and the installation method of the present invention is assembled with each anchor body installed in the side wall in the form of a checkerboard to the thumb pile made of a fixed length by attaching a bracket, combining the left and right thumb piles with a horizontal connection, The earthquake plate is sandwiched between the left and right thumb piles to complete the structure of the earth block, and thus the construction of the thumb pile is different from the existing method.

따라서 기존방식의 엄지말뚝 시공을 위해 필요한 대형장비 진입로와 대형천공기 및 크레인, 인발기 등이 불필요 하게 되고, 기존방식 대비 띠장이 생략됨에 따라 강재 수량이 줄고, 그 무게만큼 앵커체에 작용되는 하중이 줄며, 띠장 폭 만큼 굴착량의 감소는 물론, 띠장과 관련된 받침대, 스티프너, 홈메우기, 브래킷 등의 제작설치가 생략 되어 발전기도 불필요 하게 된다.Therefore, large equipment access road, large perforator, crane, drawing machine, etc., which are necessary for the construction of the thumb pile of the conventional method are unnecessary, and the amount of steel is reduced as the length of the belt is omitted, and the load acting on the anchor body by the weight is reduced. It reduces the amount of excavation by the width of the length of the belt, as well as eliminates the installation and installation of the pedestal, stiffeners, grooves, brackets, etc. related to the belt.

이로 인하여 소음이나 진동 및 비산먼지의 발생이 최소화되고, 신속하고 안전하게 흙막이 공사를 시행할 수 있을 뿐만 아니라 공사비를 크게 줄일 수 있도록 하는 효과가 있다.This minimizes the occurrence of noise, vibration, and scattering dust, and enables the construction of the screening of the earthquake quickly and safely as well as greatly reducing the construction cost.

도 1 은 본 발명에 따른 일자형 가설 흙막이 구조물 및 그 설치방법을 설명하기 위한 정면도.
도 2 는 본 발명에 따른 일자형 가설 흙막이 구조물 및 그 설치방법을 설명하기 위한 단면도.
도 3 은 본 발명에 따른 일자형 가설 흙막이 구조물 및 그 설치방법을 설명하기 위한 평면도.
도 4 는 본 발명에 따른 일자형 가설 흙막이 구조물 및 그 설치방법을 설명하기 위한 사시도.
도 5 는 본 발명에 따른 계단형 가설 흙막이 구조물 및 그 설치방법을 설명하기 위한 정면도.
도 6 은 본 발명에 따른 계단형 가설 흙막이 구조물 및 그 설치방법을 설명하기 위한 단면도.
도 7 은 본 발명에 따른 계단형 가설 흙막이 구조물 및 그 설치방법을 설명하기 위한 평면도.
도 8 은 본 발명에 따른 계단형 가설 흙막이 구조물 및 그 설치방법을 설명하기 위한 사시도.
1 is a front view for explaining a linear construction temporary structure and the installation method according to the present invention.
Figure 2 is a cross-sectional view for explaining the construction of a straight temporary soil structure and its installation method according to the invention.
Figure 3 is a plan view for explaining the linear construction temporary structure and the installation method according to the invention.
Figure 4 is a perspective view for explaining the construction of a linear construction temporary structure according to the invention and its installation method.
Figure 5 is a front view for explaining the stepped temporary construction structure and installation method according to the present invention.
Figure 6 is a cross-sectional view for explaining the stepped temporary construction structure and installation method according to the present invention.
Figure 7 is a plan view for explaining a stepped temporary structure and installation method according to the present invention.
Figure 8 is a perspective view for explaining a stepped temporary construction structure and installation method according to the present invention.

이하, 첨부된 도면을 참조하면서 본 발명의 실시 예를 상세하게 설명하면 다음과 같다. Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1 내지 도 5 에 나타낸 바와 같이, 본 발명의 가설 흙막이 구조물(100)은 다수를 일정간격으로 지중에 수직으로 설치하되 한 쌍의 플레이트(111) 사이를 연결리브(112)로 연결하고 플레이트(111)를 전후로 관통하는 앵커공(114)을 천공하며 앵커공(114)의 전면에 브래킷(125)을 부착한 엄지말뚝(110)과, 상기 엄지말뚝(110)의 플레이트(111)의 내부 면에 결합하여 수직으로 통로(121)를 형성하는 가이드프레임(120)과, 상기 엄지말뚝(110)을 횡으로 연결하여 결합하는 수평연결대(130)와, 상기 가이드프레임(120)에 삽입하여 자중에 의해 하부로 슬라이딩하는 쏠장토류판(140)과, 상기 엄지말뚝(110)과 엄지말뚝(110) 사이에 끼워 조립하는 토류판(150), 및 상기 엄지말뚝(110)의 앵커공(114)을 통하여 지중에 설치하여 엄지말뚝(110)을 지지하는 앵커체(160)로 구성한다.As shown in Figures 1 to 5, the temporary earthquake structure 100 of the present invention is installed vertically in the ground at regular intervals a large number of plates (111) between the connecting ribs 112 and the plate ( The thumb pile 110 having the anchor hole 114 penetrating back and forth through the 111 and attached the bracket 125 to the front of the anchor hole 114, and the inner surface of the plate 111 of the thumb pile 110 A guide frame 120 coupled to the vertical to form a passage 121, a horizontal connecting rod 130 connecting the thumb pile 110 laterally, and inserted into the guide frame 120 to the weight thereof. Underground through the anchor plate 114 of the cock plate earth plate 140, sliding between the thumb pile 110 and the thumb pile 110, and the anchor pile 114 of the thumb pile 110 to slide downward by It is installed in the anchor body 160 to support the thumb pile 110.

상기 엄지말뚝(110)은 한 쌍의 플레이트(111)를 전, 후로 형성하고 그 사이에 연결리브(112)로 연결하여 일체화하되 연결리브(112)를 한 쌍으로 형성하여 중앙에 수직으로 공간(113)이 형성한다.The thumb pile 110 is formed by a pair of plates 111 before and after, and connected by connecting ribs 112 therebetween to integrate, but forming a pair of connecting ribs 112 in a vertical space in the center ( 113) forms.

여기서, 엄지말뚝(110)의 앵커공(114)은 연결리브(112)의 사이 공간(113)을 통하여 한 쌍의 플레이트(111)를 전후로 앵커체(160)의 기울기에 맞게 천공하며, 앵커체(160)의 강선과 접촉되지 않을 만큼의 구멍크기가 확보되어야 한다.Here, the anchor hole 114 of the thumb pile 110 is drilled in accordance with the inclination of the anchor body 160 through the space 113 between the connecting ribs 112 back and forth, the anchor body 160, anchor body The hole size should be secured so as not to contact the steel wire of 160.

더불어, 엄지말뚝(110)의 플레이트(111)의 좌우측에 절곡편(117)을 형성하여 이를 코너에 설치하므로 토류판(150)을 원활하게 가이드 하도록 함이 바람직하다.In addition, since the bending piece 117 is formed on the left and right sides of the plate 111 of the thumb pile 110 and installed at the corner, it is preferable to guide the earth plate 150 smoothly.

나아가, 일자형의 엄지말뚝(110) 상단에는 연결고리(116)를 부착하고, 하단에는 연결홈(115)을 형성하여 결합을 용이하도록 하며, 계단형의 엄지말뚝(110)의 전면에는 체결공(123)을 형성하고, 배면에는 체결공(123)에 삽입하는 연결고리(124)를 부착하여 용이하게 결합할 수 있도록 함이 이상적이다.Furthermore, the upper side of the thumb pile 110 is attached to the connecting ring 116, the lower end to form a connection groove 115 to facilitate the coupling, the fastening hole (in the front of the stepped thumb pile 110) It is ideal to form a 123, the rear surface is attached to the connecting ring 124 to be inserted into the fastening hole 123 to be easily coupled.

상기 가이드프레임(120)은 엄지말뚝(110)의 플레이트(111)의 내면에 결합하여 수직으로 통로(121)를 형성하되 측방으로 다수개의 세팅공(122)을 수직선상으로 천공하여 통로(121)에 삽입되는 쏠장토류판(140)을 못이나 나사 등의 고정수단(123)으로 위치를 세팅할 수 있도록 한다.The guide frame 120 is coupled to the inner surface of the plate 111 of the thumb pile 110 to form a passage (121) vertically, but a plurality of setting holes (122) in the side perforated in a vertical line passage (121) The cocked earth plate 140 is inserted into it so that the position can be set by fixing means 123 such as nails or screws.

상기 수평연결대(130)는 직각으로 절곡하여 지지력을 향상시키되 양단을 좌우 엄지말뚝(110)에 체결수단(131)으로 체결한다. The horizontal connector 130 is bent at a right angle to improve the support force, but fasten both ends to the left and right thumb pile 110 by the fastening means 131.

상기 쏠장토류판(140)과 토류판(150)의 재질이나 크기는 이를 한정하거나 제한하는 것은 아니다.The material or size of the sole earth plate 140 and the earth plate 150 is not limited or limited thereto.

상기 앵커체(160)는 지반의 특성에 따라 다양한 앵커체를 선택적으로 사용할 수 있다.The anchor body 160 may selectively use various anchor bodies according to the characteristics of the ground.

이러한 본 발명의 가설 흙막이 구조물(100)의 설치방법은 엄지말뚝(110)의 조립 방법에 따라 위아래를 맞이음하는 일자형(도1~4))과 겹쳐 이음 하는 계단형(도5~8)으로 구분되며, 일정한 길이로 제작된 엄지말뚝을 한단으로 하여 흙막이 구조물(100)을 완성하며 한단씩 지하로 순차적 굴착을 시행한다.The installation method of the temporary earthquake structure 100 of the present invention is a stepped type (Figs. 5 to 8) overlapped with a straight type (Figs. 1 to 4) to face up and down according to the assembly method of the thumb pile 110. It is divided, and the end of the earthquake structure (100) by using the end of the thumb pile made of a certain length is carried out sequential excavation underground one by one.

일자형(도1~4)의 시공방법은 엄지말뚝(110)의 선단 아래를 굴착하여 위아래의 엄지말뚝(110)을 맞이음하는 방법으로 그 상세는 흙막이 벽체 설치라인의 내측으로 사면안정을 이루는 경사법면(1:1)을 유지하며 앵커체(160) 설치 위치까지 경사법면(1:1)을 제외한 굴착단면 전부를 1차 굴착하고, 엄지말뚝(110)을 경사법면(1:1)에 설치하기 위한 2차 굴착은 가능한 좁은 폭으로 경사법면(1:1)에 굴착하되, 주변토사의 붕괴 및 유실을 방지하기 위하여 첫째 단에선 쏠장토류판(140)을 자립식으로 설치하고, 둘째 단 부터는 엄지말뚝(110)에 삽입된 쏠장토류판(140)을 내리며 굴착하되, 지질에 따라 앵커체(160)를 기준으로 두 번에 나눠 굴착하고, 2차 굴착된 공간에 앵커체(160) 홀을 천공하여 앵커체(160)를 지중에 설치하며, 쏠장토류판(140)이 삽입된 엄지말뚝(110)을 앵커체(160)와 조립하여 설치한 다음, 상기와 동일 방법으로 설치된 좌우 엄지말뚝(110)을 수평연결대(130)로 연결하고, 엄지말뚝(110) 배면에 발생될 수 있는 공극을 시멘트 모르타르로 충진한 후, 양생되면 엄지말뚝(110)의 앵커공(114)으로 삽입한 앵커체(160)를 브래킷(125)위에서 강결시키고, 동일 방법으로 설치된 좌우 엄지말뚝(110) 사이에 토류판(150)을 끼우며 엄지말뚝(110) 선단까지 3차 굴착하여 한 단의 흙막이 구조물(100)을 완성하며, 이와 같은 설치방법을 반복하며 원하는 심도까지 안전하게 굴착하는 것이다.The construction method of the straight type (Fig. 1 to 4) is a method of digging below the tip of the thumb pile 110 to meet the thumb pile 110 above and below. Maintain the surface (1: 1) and excavate all the excavated sections except the slope method (1: 1) to the anchor body 160 installation position, and install the thumb pile 110 on the slope method (1: 1). Secondary excavation is to be excavated on the slope method (1: 1) as narrow as possible, but in order to prevent the collapse and loss of the surrounding soil, the first step is to install the sole soil plate 140 in a self-supporting manner, and from the second end Excavate the grounding soil plate 140 inserted into the pile 110, excavated in two times based on the anchor body 160 according to the geology, and drilled the anchor body 160 holes in the second excavated space The anchor body 160 is installed in the ground, and the thumb pile 110 into which the shoot soil plate 140 is inserted is the anchor body 160. After installing and assembled, and then connected to the left and right thumb pile 110 in the same manner as the horizontal connection 130, filling the voids that may be generated on the back of the thumb pile 110 with cement mortar, curing When the anchor body 160 inserted into the anchor hole 114 of the thumb pile 110 is tightened on the bracket 125, the earth plate 150 between the left and right thumb pile 110 is installed in the same way, the thumb pile (110) the third end excavation to complete the one-stage earthquake structure 100, repeating the installation method like this is to safely excavate to the desired depth.

엄지말뚝(110)의 설치를 용이하게 하기위해 엄지말뚝(110) 상단에 연결고리(116)를 부착하고, 하단에 연결홈(115)을 설치함이 바람직하나 이를 한정하는 것은 아니다.In order to facilitate installation of the thumb pile 110, it is preferable to attach the connection ring 116 to the top of the thumb pile 110, and to install the connection groove 115 at the bottom, but is not limited thereto.

쏠장토류판(140)의 길이는 엄지말뚝의 길이보다 10~20cm 적게 제작하여 엄지말뚝과 앵커체의 조립시 철거가 용이하도록 하며, 가이드프레임(120)에 다수개의 세팅공(122)을 천공하여 못 또는 나사로 쏠장토류판(140)의 이동을 조절할 수 있도록 한다.The length of the sole soil plate 140 is 10 to 20 cm less than the length of the thumb pile to facilitate the dismantling of the thumb pile and the anchor body, a plurality of setting holes 122 in the guide frame 120 can not be drilled Or to adjust the movement of the shoot earth plate 140 with a screw.

엄지말뚝(110)의 배면 공극을 시멘트 모르타르로 충진하기 전에 앵커체(160) 아래의 엄지말뚝(110) 주변은 양질의 토사로 되메우기 하여 토류판(150)이 끼워지는 홈에 몰 탈이 채워지지 않도록 하며, 앵커체(160) 위의 엄지말뚝(110) 주변은 스펀지로 엄지말뚝(110)과 굴착법면 사이의 틈을 막아 시멘트 몰 탈이 흘러나오지 않도록 한다.Before filling the back voids of the thumb pile 110 with cement mortar, the surroundings of the thumb pile 110 under the anchor body 160 are filled with high quality soil so that the mortar is not filled in the groove into which the earth plate 150 is fitted. And, around the thumb pile 110 on the anchor body 160 to prevent the cement mortar flow out of the gap between the thumb pile 110 and the excavation surface with a sponge.

계단형(도5~8)의 시공방법은 엄지말뚝(110)의 전면 플레이트(111)를 따라 아래를 굴착하여 위아래의 엄지말뚝(110)을 겹쳐 이음 하는 방법으로 그 외 상세는 일자형(도1~4)의 동일하며, 엄지말뚝(110)의 설치를 용이하게 하기위해 엄지말뚝(110) 전면 플레이트(111)에 체결공(123)을 천공하고, 후면 플레이트에 연결고리(124)를 부착하며, 쏠장토류판(140)의 제작설치 및 엄지말뚝(110) 배면의 충진 방법은 일자형과 동일하다.Construction method of step type (Figs. 5 to 8) is to excavate the bottom along the front plate 111 of the thumb pile 110 to overlap the upper and lower thumb pile 110, and other details are straight (Fig. 1). 4) is the same, and to facilitate the installation of the thumb pile 110, puncture the fastening hole 123 to the thumb plate 110, the front plate 111, and attach the connecting ring 124 to the rear plate , Manufacture and installation of the cocking earth plate 140 and the filling method of the back of the thumb pile 110 is the same as the straight.

100 : 흙막이 구조물 110 : 엄지말뚝
111 : 플레이트 112 : 연결리브
113 : 공간 114 : 앵커공
115 : 연결홈 116 : 연결고리
117 : 절곡편 120 : 가이드프레임
121 : 통로 122 : 세팅공
123 : 체결공 124 : 연결고리
125 : 브래킷 130 : 수평연결대
131 : 체결수단 140 : 쏠장토류판
150 : 토류판 160 : 앵커체
100: earth structure 110: thumb pile
111: plate 112: connecting rib
113: space 114: anchor ball
115: connecting groove 116: connecting ring
117: bending 120: guide frame
121: passage 122: setting hole
123: fastener 124: connecting ring
125: bracket 130: horizontal connection
131: fastening means 140: cocked earth plate
150: earth plate 160: anchor body

Claims (13)

다수를 일정간격으로 지중에 설치하되 한 쌍의 플레이트(111) 사이를 연결리브(112)로 연결하고 플레이트(111)를 전후로 관통하는 앵커공(114)을 천공한 엄지말뚝(110)과,
상기 엄지말뚝(110)의 플레이트(111)의 내부 면에 결합하여 수직으로 통로(121)를 형성하는 가이드프레임(120)과,
상기 엄지말뚝(110)을 횡으로 연결하여 결합하는 수평연결대(130)와,
상기 가이드프레임(120)의 삽입하여 자중에 의해 하부로 슬라이딩하는 쏠장토류판(140)과,
상기 엄지말뚝(110)과 엄지말뚝(110) 사이에 끼워 조립하는 토류판(150), 및
상기 엄지말뚝(110)의 앵커체(160)로 구성한 것을 특징으로 하는 가설 흙막이 구조물.
Thumb pile 110, which is installed in the ground at regular intervals, but connected between a pair of plates 111 with connecting ribs 112 and perforated anchor holes 114 penetrating back and forth through the plate 111,
A guide frame 120 coupled to an inner surface of the plate 111 of the thumb pile 110 to form a passage 121 vertically;
A horizontal connector 130 for connecting the thumb pile 110 to the side;
Shooting earth plate 140 and sliding of the guide frame 120 by the lower portion by the insertion of its own weight,
An earth plate 150 assembled between the thumb pile 110 and the thumb pile 110, and
Temporary earthquake structure, characterized in that consisting of the anchor body 160 of the thumb pile 110.
제 1 항에 있어서,
상기 엄지말뚝(110)은 한 쌍의 플레이트(111)를 전, 후로 형성하고 그 사이에 연결리브(112)로 연결하여 일체화하되 연결리브(112)를 한 쌍으로 형성하여 중앙에 수직으로 공간(113)이 형성하며, 엄지말뚝(110)의 앵커공(114)은 연결리브(112)의 사이 공간(113)을 통하여 플레이트(111)를 전후로 앵커체(160)의 기울기에 알맞게 앵커공(114)을 천공하고 앵커공(114)의 전면에 부착되는 브래킷(125)을 부착하여 구성한 것을 특징으로 하는 가설 흙막이 구조물.
The method of claim 1,
The thumb pile 110 is formed by a pair of plates 111 before and after, and connected by connecting ribs 112 therebetween to integrate, but forming a pair of connecting ribs 112 in a vertical space in the center ( 113 is formed, the anchor hole 114 of the thumb pile 110 is anchored to the inclination of the anchor body 160 back and forth around the plate 111 through the space 113 between the connecting ribs (112). Temporary earthquake structure, characterized in that the perforated and configured by attaching a bracket (125) attached to the front of the anchor hole (114).
제 1 항에 있어서,
상기 엄지말뚝(110)의 플레이트(111)의 좌우측에 절곡편(117)을 형성하여 코너 부분에서 토류판(150)을 원활하게 가이드 하도록 구성한 것을 특징으로 하는 가설 흙막이 구조물.
The method of claim 1,
Temporary earthquake structure, characterized in that the bending piece 117 is formed on the left and right sides of the plate 111 of the thumb pile 110 to guide the earth plate 150 at the corner portion smoothly.
제 1 항에 있어서,
상기 엄지말뚝(110) 상단에는 하단의 연결홈(115)에 삽입하는 연결고리(116)를 형성하고, 하단에는 연결홈(115)을 설치하여 엄지말뚝(110) 위아래를 맞이음시켜 일자형으로 용이하게 결합할 수 있도록 구성한 것을 특징으로 하는 가설 흙막이 구조물.
The method of claim 1,
On the top of the thumb pile 110 is formed a connecting ring 116 to be inserted into the connection groove 115 of the lower, and the connection groove 115 is installed at the lower end to the top and bottom of the thumb pile 110, easy to straight Temporary earthquake structure, characterized in that configured to be configured to combine.
제 1항에 있어서,
상기 엄지말뚝(110)의 전면에는 체결공(123)을 형성하고, 배면에는 체결공(123)에 삽입하는 연결고리(124)를 부착하여 엄지말뚝(110)의 상하부를 중첩시켜 계단형으로 용이하게 결합할 수 있도록 구성한 것을 특징으로 하는 가설 흙막이 구조물.
The method of claim 1,
A fastening hole 123 is formed on the front of the thumb pile 110, and a connecting ring 124 inserted into the fastening hole 123 is attached to the back of the thumb pile 110 to easily overlap the upper and lower portions of the thumb pile 110 in a stepped manner. Temporary earthquake structure, characterized in that configured to be configured to combine.
제 1 항에 있어서,
상기 가이드프레임(120)은 엄지말뚝(110)의 플레이트(111)의 내면에 결합하여 수직으로 통로(121)를 형성하되 측방으로 다수개의 세팅공(122)을 천공하여 쏠장토류판(140)의 이동을 조절하도록 구성을 특징으로 하는 가설 흙막이 구조물.
The method of claim 1,
The guide frame 120 is coupled to the inner surface of the plate 111 of the thumb pile 110 to form a passage (121) vertically, but by drilling a plurality of setting holes 122 to the side to move the shoot earth plate 140 Temporary earthquake structure, characterized in that the configuration to adjust.
흙막이 구조물(100) 설치라인의 내측으로 사면안정을 이루는 경사법면을 유지하며 무지보로 앵커체(160) 설치 위치까지 1차 굴착하는 단계와,
상기 1차 굴착이 완료되면 아래단의 엄지말뚝(110)의 설치를 위해 위단의 엄지말뚝(110)의 선단 아래를 위단의 엄지말뚝(110)에 삽입한 쏠장토류판(140)을 자중으로 아래로 내려 주변 토사의 붕괴나 유실을 방지하며 경사법면을 2차 굴착하는 단계와,
상기 2차 굴착이 완료되면 2차 굴착된 공간의 벽체에 앵커체(160) 홀을 천공하여 앵커체(160)를 지중에 설치하는 단계와,
상기 앵커체(160)의 설치가 완료되면 앵커체(160)에 쏠장토류판(140)을 삽입한 엄지말뚝(110)을 조립하는 단계와,
상기 동일한 방법으로 설치된 좌우 엄지말뚝(110)을 수평연결대(130)로 연결하여 고정하는 단계와,
상기 엄지말뚝(110) 사이에 토류판(150)을 끼우며 엄지말뚝(110) 선단까지 3차 굴착하여 흙막이 구조물(100)을 완성하는 단계를 포함하는 것을 특징으로 하는 가설 흙막이 구조물의 설치방법.
Maintaining the inclined surface forming the slope stability to the inside of the earthquake structure 100 installation line and the first excavation to the anchoring body 160 installation position without a beam;
When the first excavation is completed, the sole soil plate 140 inserted below the tip of the upper thumb pile 110 to the thumb pile 110 of the upper end for installation of the thumb pile 110 of the lower end under its own weight. Secondly excavating the sloped surface to prevent collapse or loss of surrounding soil;
When the secondary excavation is completed, drilling the anchor body 160 hole in the wall of the secondary excavated space to install the anchor body 160 in the ground,
When the installation of the anchor body 160 is completed, assembling the thumb pile 110 into which the anchor earth plate 140 is inserted into the anchor body 160;
Connecting the left and right thumb piles 110 installed in the same manner to fix the horizontal connecting rods 130;
Inserting the earth plate (150) between the thumb pile 110, the excavation to the tip of the thumb pile 110 to the third end excavation installation method of the temporary construction of the clam structure, characterized in that it comprises the step of completing the clam structure (100).
제 7 항에 있어서,
상기 수평연결대(130)의 연결이 완료되면 엄지말뚝(110) 배면의 공극을 시멘트 모르타르를 충진하는 단계와,
상기 모르타르가 양생되면 엄지말뚝(110)의 브래킷(125) 위에서 앵커체(160)를 강결시키는 단계를 더 포함하여 구성한 것을 특징으로 하는 특징으로 하는 가설 흙막이 구조물의 설치방법.
The method of claim 7, wherein
When the connection of the horizontal connector 130 is completed, filling the cement mortar in the voids on the back of the thumb pile 110,
When the mortar is cured, the installation method of the temporary soil structure, characterized in that configured to further comprise the step of strengthening the anchor body on the bracket (125) of the thumb pile (110).
제 7 항 또는 제 8 항에 있어서,
상기 앵커체(160)의 설치 후 엄지말뚝(110)을 조립단계는 엄지말뚝(110)을 맞이음하되, 엄지말뚝(110)의 연결홈(115)에 연결고리(116)를 끼워 위아래의 엄지말뚝(110)을 일자형으로 설치하는 것을 포함하여 특징으로 하는 가설 흙막이 구조물의 설치방법.
9. The method according to claim 7 or 8,
After the installation of the anchor body 160, the thumb pile 110 is assembled to the thumb pile 110, but the connecting ring 116 into the connecting groove 115 of the thumb pile 110, the thumb up and down The installation method of the temporary earthquake structure characterized in that the installation of the pile 110 in a straight line.
제 7 항 또는 제 8 항에 있어서,
상기 앵커체(160)의 설치 후 엄지말뚝(110)을 조립단계는 위아래의 엄지말뚝(110)을 중첩시켜 겹쳐 이음하되 엄지말뚝(110)의 체결공(123)에 연결고리(124)를 끼워 위아래의 엄지말뚝(110)을 계단형으로 설치하는 것을 포함하여 특징으로 하는 가설 흙막이 구조물의 설치방법.
9. The method according to claim 7 or 8,
Assembling the thumb pile 110 after the installation of the anchor body 160 by overlapping the upper and lower thumb pile 110, the connection ring 124 is inserted into the fastening hole 123 of the thumb pile 110 The installation method of the temporary earthquake structure, characterized in that the installation of the upper and lower thumb pile 110 in a staircase.
제 7 항에 있어서,
상기 앵커체(160)를 지중에 설치하는 단계는 엄지말뚝(110)의 앵커공(114)으로 앵커체(160)를 삽입하여 조립하되, 엄지말뚝(110)의 브래킷(125)위에서 앵커체(160)의 강선을 인장하여 강결시키는 것을 특징으로 하는 가설 흙막이 구조물의 설치방법.
The method of claim 7, wherein
The step of installing the anchor body 160 in the ground is assembled by inserting the anchor body 160 into the anchor hole 114 of the thumb pile 110, the anchor body on the bracket 125 of the thumb pile 110 ( 160) The installation method of the temporary earthquake structure, characterized in that for tightening the steel wire.
제 7 항에 있어서,
상기 쏠장토류판(140)의 길이를 엄지말뚝(110)의 길이보다 적게 제작하여 엄지말뚝(110)과 앵커체(160)의 조립시 철거가 용이하도록 하고, 가이드프레임(120)에 다수의 세팅공(122)을 천공하여 못 또는 나사로 쏠장토류판(140)의 이동을 조절할 수 있도록 하는 것을 특징으로 하는 가설 흙막이 구조물의 설치방법.
The method of claim 7, wherein
Making the length of the shoot earth plate 140 less than the length of the thumb pile 110 to facilitate the removal of the thumb pile 110 and the anchor body 160, a plurality of setting holes in the guide frame 120 Method of installation of a temporary earthquake structure, characterized in that for drilling 122 to control the movement of the shoot earth plate 140 with a nail or screw.
제 8 항에 있어서,
상기 엄지말뚝(110)의 배면의 공극에 모르타르 충진 전에 앵커체(160) 아래의 엄지말뚝(110) 주변은 양질의 토사로 되메우기 하여 토류판이 끼워지는 홈에 모르타르가 채워지지 않도록 하고, 앵커체(160) 위의 엄지말뚝(110) 주변에는 스펀지나 발포제로 엄지말뚝(110)과 굴착법면 사이의 틈을 막아 시멘트 모르타르가 흘러나오지 않도록 하는 것을 특징으로 하는 가설 흙막이 구조물의 설치방법.
The method of claim 8,
Before filling the mortar in the air gap on the back of the thumb pile 110, the thumb pile 110 around the anchor body 160 under the anchor body 160 is filled with high-quality earth and sand so that the mortar is not filled in the groove into which the earth plate is inserted. 160) The installation method of the temporary soil structure, characterized in that the cement mortar to prevent the gap between the thumb pile 110 and the excavation surface with a sponge or foaming agent around the thumb pile (110).
KR1020110023863A 2011-03-17 2011-03-17 Reformed sheet plate and the method of installation of the same KR101386275B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110023863A KR101386275B1 (en) 2011-03-17 2011-03-17 Reformed sheet plate and the method of installation of the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110023863A KR101386275B1 (en) 2011-03-17 2011-03-17 Reformed sheet plate and the method of installation of the same

Publications (2)

Publication Number Publication Date
KR20120106037A true KR20120106037A (en) 2012-09-26
KR101386275B1 KR101386275B1 (en) 2014-04-17

Family

ID=47112809

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110023863A KR101386275B1 (en) 2011-03-17 2011-03-17 Reformed sheet plate and the method of installation of the same

Country Status (1)

Country Link
KR (1) KR101386275B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20170035321A (en) * 2015-09-21 2017-03-30 주식회사 울산기초 Retaining wall construction method and retaining wall structure by the method
CN108149696A (en) * 2018-02-12 2018-06-12 山东大学 The composite supporting construction and construction method that a kind of gib soil nail wall is combined with permanent anti-float anchor rod
CN111270679A (en) * 2020-03-18 2020-06-12 长江勘测规划设计研究有限责任公司 Construction method and structure of foundation pit fender pile opening excavation processing structure
CN113832991A (en) * 2021-08-20 2021-12-24 上海市政工程设计研究总院(集团)有限公司 Reverse construction method of pile plate wall
CN117090231A (en) * 2023-10-20 2023-11-21 广东省冶金建筑设计研究院有限公司 Ecological protector of highway rock slope

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100969996B1 (en) 2008-02-25 2010-07-15 코오롱건설주식회사 Soil retaining method for two rows pile using earth anchor
KR100882831B1 (en) 2008-08-22 2009-02-10 문동춘 Reformed sheet plate and the method of installation of the same
KR100907904B1 (en) 2009-03-05 2009-07-16 이석용 Movable Temporary Temper Structure

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20170035321A (en) * 2015-09-21 2017-03-30 주식회사 울산기초 Retaining wall construction method and retaining wall structure by the method
CN108149696A (en) * 2018-02-12 2018-06-12 山东大学 The composite supporting construction and construction method that a kind of gib soil nail wall is combined with permanent anti-float anchor rod
CN108149696B (en) * 2018-02-12 2019-09-13 山东大学 A kind of construction method for the composite supporting construction that gib soil nail wall is combined with permanent anti-float anchor rod
CN111270679A (en) * 2020-03-18 2020-06-12 长江勘测规划设计研究有限责任公司 Construction method and structure of foundation pit fender pile opening excavation processing structure
CN113832991A (en) * 2021-08-20 2021-12-24 上海市政工程设计研究总院(集团)有限公司 Reverse construction method of pile plate wall
CN117090231A (en) * 2023-10-20 2023-11-21 广东省冶金建筑设计研究院有限公司 Ecological protector of highway rock slope
CN117090231B (en) * 2023-10-20 2024-01-19 广东省冶金建筑设计研究院有限公司 Ecological protector of highway rock slope

Also Published As

Publication number Publication date
KR101386275B1 (en) 2014-04-17

Similar Documents

Publication Publication Date Title
KR101640795B1 (en) Furlable earth retaining structure for provisional facilities and construction method thereof
KR101179778B1 (en) Method for constructing underground structure
KR100855098B1 (en) Strut structure as temporary system using a vertical truss at the end and the method thereof
KR101241566B1 (en) Method for Constructing Cap Beam Combined Wale For Retaining Wall
KR101386275B1 (en) Reformed sheet plate and the method of installation of the same
KR20140055639A (en) A execution method of architecture beam
KR20130085353A (en) Construction method for retaining wall and construction apparatus for thereof and retaining wall structure
KR101149895B1 (en) Reinforcement block for pillar of tunnel
KR101096664B1 (en) Construction method of approaching duel tunnel and pressing unit of pillar using the same
KR101682510B1 (en) Construction method of retaining wall to secure safety using PC panel and permanent anchor
KR100831332B1 (en) Underground retaining wall for public works and method for constructing the same
KR20140013497A (en) Method for constructing block type reinforced retaining wall in cut site
KR20200124949A (en) Anchor Tension way sheathing structure and sheathing method of construction
KR101021915B1 (en) A method for constructing cut-off temporary structure for sheathing work
KR20080025219A (en) Underground outer wall construction method using deck-plate and deck-plate for constructing underground outer wall
JP2015183366A (en) Structure and construction method for banking structure
KR101021913B1 (en) A method for constructing cut-off temporary structure for sheathing work
KR101221084B1 (en) Temporary pile using bending restoring force and temporary structure construction method therewith
KR101297679B1 (en) Self-supporting Temporary Structure Using Steel Wire And Method Of The Same
KR100984040B1 (en) Method of reinforced earth retaining wall for cutting face through double reinforcing execution
KR20040031451A (en) Prestressed scaffolding method
KR100967496B1 (en) Device for constructing an underground structure
KR102289576B1 (en) Top-down type underground structure construction method using earth support plate
KR101744378B1 (en) Method for Constructing Retaining Wall
KR101809554B1 (en) Structure using key-block and sheetfile

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
AMND Amendment
E601 Decision to refuse application
AMND Amendment
E90F Notification of reason for final refusal
AMND Amendment
X701 Decision to grant (after re-examination)
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee