KR20120010370A - Non-power-failure power distribution method using wire-changing device and bypasscable - Google Patents

Non-power-failure power distribution method using wire-changing device and bypasscable Download PDF

Info

Publication number
KR20120010370A
KR20120010370A KR1020100071855A KR20100071855A KR20120010370A KR 20120010370 A KR20120010370 A KR 20120010370A KR 1020100071855 A KR1020100071855 A KR 1020100071855A KR 20100071855 A KR20100071855 A KR 20100071855A KR 20120010370 A KR20120010370 A KR 20120010370A
Authority
KR
South Korea
Prior art keywords
phase
wire
cable
work
bypass
Prior art date
Application number
KR1020100071855A
Other languages
Korean (ko)
Other versions
KR101122499B1 (en
Inventor
권세원
Original Assignee
대원전기 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 대원전기 주식회사 filed Critical 대원전기 주식회사
Priority to KR1020100071855A priority Critical patent/KR101122499B1/en
Priority to PCT/KR2011/003996 priority patent/WO2012015160A1/en
Publication of KR20120010370A publication Critical patent/KR20120010370A/en
Application granted granted Critical
Publication of KR101122499B1 publication Critical patent/KR101122499B1/en

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/02Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for overhead lines or cables

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)
  • Electric Cable Installation (AREA)

Abstract

PURPOSE: A wire-changing device and a method for distributing uninterruptible power using a by-pass cable are provided to expand an operating area of an uninterruptible power by widely utilizing an uninterruptible method according to the working skill and taste of an expert in uninterruptible power supply. CONSTITUTION: A wire-changing device(10) is arranged in one side of a long pole at a column. A separate by-pass cable(20) is installed on the ground. A first phase(A) among extra-high voltage three phases is bypassed. The first phase among three phases is formed into a diagonal line shape by separating a jumper line of a wire on the first phase bypassed among extra-high voltage three phases three phases. The operation on the first phase is completed by dividing a terminal cable of the cable arranged. A by-pass cable, which is arranged at the second phase among three phases, is bypassed to a second phase in either side of an operation section on the second phase. An operation process of the second phase is repetitively performed on a third phase(C). The uninterruptible task of an extra-high voltage three phase is safely operated by removing an arranged by-pass cable.

Description

Non-power-failure power distribution method using wire-changing device and bypasscable}

The present invention, in the replacement and relocation of the distribution line connected to each pole and change of transition place, by installing the wire lead mechanism in each pole, the sequential electricity between the new and old wire by the bypass cable installed on the ground or pole It is possible to replace the electric wires, replace electric poles, move electric poles and change the transition site by uninterrupting by disconnecting and connecting them. Improved workability by allowing replacement and relocation by uninterruptible power, but by the applicant of the present invention, the patent application No.0407376, "Uninterrupted power distribution method using wire transfer mechanism in electric pole" and patent registration of pre-registered It is made by applying the "Uninterruptible power distribution method of single phase line using a processing temporary line" by the arc.

In response to the surge in electric power demand, electric power facilities have been expanded in response. As the demand for electric quality of electric power users increases, the momentary power failure is also subject to civil complaints. Increasingly, uninterrupted construction methods are being performed in which the construction is performed without disconnecting the power for high quality power supply during power distribution construction.

Existing uninterrupted power distribution works consist of a transformer transformer method, a bypass cable method, and a switchgear method for construction.Bypass cable method is a cable car and a work section necessary for a cable car and work section. Equipment, mobile transformer car, live bucket truck, and air port for live work, and install bypass cable to bypass power supply, replace and relocate distribution line, and remove bypass cable again. Construction is complete.

In addition, in order to reduce the capacity of the distribution line to 5,000 KVA or less, the distribution line having a capacity of more than 5,000 KVA is less than 5,000 KVA at the time of applying the existing bypass cable method. Wastes a lot of time and labor costs when switching power loads to other distribution lines, and there is a serious problem in the system operation of an effective distribution line, and in particular, uninterrupted work on upper distribution lines of two or more lines is needed. There is a problem that construction is impossible with the current uninterrupted construction method.

Therefore, a lot of construction manpower is required for the electric power distribution work, and a lot of special high voltage connection points are created to install the bypass cable, which is standardized at 50m, in the 200 ~ 300m section. By repeating installation and dismantling frequently, waste of labor cost and damage of bypass cable are accelerated, which is a more dangerous threat to safety, and in case of safety accident or sudden power failure, to secure electricity quality at high cost. Contrary to the purpose, more civil complaints, economic loss and casualties can be brought, as well as unstable operation of the distribution line system due to excessive load transfer work and the uninterruptible method work of the upper line of the distribution line of two or more lines.

In order to solve the problems described above, the inventor of the present invention uses a wire transfer mechanism and a wire twisted pair mechanism in Jeonju to secure a working space between the old and new wires and the relocation wire in Jeonju, as in 2001 Patent Application No. 32587. The uninterrupted operation of two or more upper distribution lines without switching power is provided by providing a method to replace and relocate new power lines with an uninterruptible uninterruptible power without using a separate bypass cable. It is possible to improve the power quality and also to use the mobile transformer car construction method except when replacing the transformer, which enables safe construction at low cost, and does not interfere with pedestrians' walking or passing through the vehicle even when it is under construction. Wire transfer mechanism in an electric pole and uninterrupted power using the same Bar has devised a major laws.

However, by using the electric wire transfer mechanism and wire twisted wire mechanism in the above pole, the new wire can be replaced and relocated by separating the electric wire between the old and new wires while securing the working space between the old and new wires in Jeonju. This is a method of installing and removing wires and twisted wires for each wire to be replaced and relocated.However, by repeating the wire reworking process in the process of replacing and rewiring a large number of wires with one wire. There was a problem that a lot of time and manpower was consumed in the work.

Accordingly, the applicant of the present invention, as in Patent Registration No. 407376, in the uninterruptible power distribution method using a wire transfer mechanism in the electric pole that cuts electricity of the demolition wire without a power failure by a bypass by the connection of the installation wire and the demolition wire, Install the wires on only one side and transfer only one wire to the other side, and then replace the wires by the uninterrupted power distribution method in which the corresponding replacement wires are transferred, but the remaining replacement wires use the reverse wires as bypass cables without any separate wire process. By repeating the installation process of wire twisted wire installation, the installation wire installation, the demolition wire removal process and the uninterrupted connection method by bypass, it is necessary to install and wire the wire once and for the replacement and relocation of new and old wires. To minimize the time and manpower required for work by replacing and relocating multiple wires An uninterruptible power distribution method using a wire transfer mechanism in a pole was proposed.

However, the uninterruptible power distribution method as described above has a problem that it is difficult to separate the side of the electric wires when a building, a street lamp, a signboard, a roadside tree, or a guard tree are adjacent to each other in order to separate the electric wires on one pole on the electric pole in a downtown area. Have

In addition, if it is impossible to separate the wires to the side due to the site conditions, the existing distribution method, which is complicated and requires a lot of work time and a large number of workers, must be applied as it is.

The present invention is to solve the problems as described above, by using the "Uninterrupted power distribution method using electric wire transfer mechanism in the electric pole in accordance with the prior registration No. 10-0407376" sideways the one-phase wire on the electric pole in the metropolitan city area When it is difficult to be separated for safety due to the side of buildings, street lamps, signs, protective water, etc., in case of separation, it is impossible to separate one phase wire to the side in the field condition or for the safety of work in the field conditions. An uninterruptible power supply that completes three-phase work by sequential separation and connection of electricity one by one by using cable and wire that temporarily installs one of three phases of bypass cable and installs one phase among bypass cables. Development of "Uninterrupted Power Distribution Method Using Wire Transfer Mechanism and Bypass Cable", which enables wire replacement, Jeonju replacement and relocation work It aims to provide a more mature uninterrupted process according to the skills and preferences of workers in the field.

The present invention for achieving the object as described above, one phase of the bypass cable is installed in the ground or the main phase by using the wire transfer mechanism to the ground or main phase by using a cable and wire to temporarily transmit the phase of electricity It is made by working with new technology developed to allow uninterrupted electric wire replacement, electric pole replacement and relocation work for jijangjeon pole that completes three phase work by separate connection.

The present invention, the uninterruptible power distribution method using the wire transfer mechanism in the downtown area of the metropolitan area when the wire to be moved to the side by installing the transfer mechanism in the Jeonju when the work distance is less than the distance from the building, signboard or streetlight, etc. In some cases, the above-mentioned problems can be solved through the ground or air laying of the bypass cable according to such a case and necessary work conditions, and the selection and utilization of the uninterruptible method is widely available depending on the work proficiency and taste of the uninterruptible major. It is possible to improve safety by improving the scope of uninterruptible work and psychological stability of workers, and it is effective in reducing power outage and improving the power quality due to the expansion of work range.

1 is a state diagram that the bypass cable is installed from the power distribution method according to the present invention
2 is a state diagram in which the first phase of the three-phase line is removed from the power distribution method according to the present invention
3 is a state diagram in which the second phase of the three-phase line is removed from the power distribution method according to the present invention
4 is a state diagram in which the third phase of the three-phase line is removed from the power distribution method according to the present invention
5 is an exemplary view illustrating a construction in which a bypass cable is installed and installed in FIG. 4.
6 is a view illustrating a construction for a work section having a transformer column from the distribution method according to the present invention
7 is an exemplary view illustrating a construction in which a bypass cable is installed and installed in FIG. 6.
8 is an exemplary view showing the construction of a work section having a branch column from the distribution method according to the present invention
9 is an exemplary view illustrating a construction in which a bypass cable is installed and installed in FIG. 8.

The terms and words used in the present specification and claims should not be construed as limited to ordinary or dictionary meanings and the inventor may properly define the concept of the term to describe its invention in the best possible way And should be construed in accordance with the principles and meanings and concepts consistent with the technical idea of the present invention.

Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings.

1 is a state diagram in which the bypass cable is installed from the power distribution method according to the present invention, Figure 2 is a state diagram in which the first phase of the three-phase line is removed from the power distribution method according to the present invention, Figure 3 is from the power distribution method according to the present invention Figure 4 is a state diagram in which the second phase of the three-phase line is removed, Figure 4 is a state diagram in which the third phase of the three-phase line is removed from the power distribution method according to the present invention.

The present invention, the uninterrupted power distribution method using the existing bypass cable method and wire unwired method and other uninterrupted method as an uninterrupted method in order to reduce the work outage for maintenance of new power distribution facilities, replacement of electric poles and relocation to the trouble pole. Is actively used and applied.

Such the present invention is invented for the application of a wider and safer method according to the skill and field conditions of the operator in the field by using the existing bypass cable method and wire wire method.

Example 1

Special high voltage power distribution equipment wired with long poles and electric wires In order to perform uninterrupted work from poles, wire poles are installed on one side of pole poles, and the wires that carry out uninterrupted work by securing a safe work space by transferring the first high voltage side to the side. Instead of the existing uninterruptible power distribution method work process using the wire mechanism, after installing the known wire wire mechanism 10 proposed by the patent registration No. 407376 on one side of the pole in the column as shown in Figure 1, Wire of the first phase (A) bypassed among the extra-high voltage 3 phases as shown in FIG. Separate the jumper wires to make the first phase (A) of the three phases oblique and secure the working space to complete wire stranding and long wire work.

Then, the first phase (A) jumper wire is compressed and the terminal cable of the installed cable is disconnected to complete the first phase (A) work, and in the second phase (B) work of the three phases, the already installed bypass After bypassing the cable 20 to the second phase B of the three phases on both sides of the work section, as shown in FIG. 3, the jumper wire of the second phase B is separated to make a diagonal line. The work of the second phase (B) is completed by compressing the jumper wire of the second phase (B) and disconnecting the terminal cable of the installed cable.

In addition, as shown in FIG. 4, the third phase C repeatedly performs the work process of the second phase B in the third phase C, and removes the installed bypass cable 30 to obtain a special high pressure 3. This is done by safely performing an uninterruptible operation.

Example 2

When there is a work disturbance on the ground as shown in FIG.

In the case of uninterrupted work of the extra-high voltage distribution equipment wired with the poles and wires, if the river or road and various work obstructions are located on the ground within the work section, the bypass cable 20 is wired as shown in FIG. Jumper of the wire of the first phase (A) bypassed among the three high pressure phases after bypassing the first phase (A) of the three high pressure phases by installing it on the column near the neutral line through the two wire mechanism (10). Separate the wires and make the first phase (A) of the three phases oblique to secure the working space to complete wire stranded and long wire work.

Then, the first phase (A) jumper wire is compressed and the terminal cable of the installed cable is disconnected to complete the first phase (A) work, and in the second phase (B) work of the three phases, the already installed bypass After the cable 20 is bypassed to the second phase B of the three phases on both sides of the work section, the jumper wire of the second phase B is separated to make a diagonal line, and the wire stranding and the long wire work are performed. The jumper wire of (B) is compressed and the terminal cable of the installed cable is separated to complete the work of the second phase (B).

In addition, the third phase (C) repeatedly performs the work process of the second phase (B) in the third phase (C), and safely removes the installed bypass cable 20 to perform the special high-pressure three-phase uninterrupted work. It is done by.

Example 3

When there is a transformer column in the work zone as shown in FIG.

First of all, in order to perform uninterrupted operation of the extra-high voltage distribution facility in which the poles and wires are wired, the wire transfer mechanism 10 is installed on one side of the poles in the column, and then a separate bypass cable 20 is laid on the ground. If there is a transformer 30 in the work section after bypassing the first phase A of the phase, an uninterruptible transformer device is formed by branching a special high voltage by using a separate cable branch connecting member 40 in the middle of the bypass cable 20. The power supply of the transformer 30 is supplied to 50.

At this time, by installing the switchgear 70 for construction on each side of the bypass cable 20 as described above, the twisted pair work between the bypass cable 20, the uninterruptible transformer device 50 and the transformer line in a diagonal state is safely. After the twisted wire work is completed, the switchgear 70 for construction is operated to allow temporary transmission to the live state and the transformer line for the bypass cable 20.

Next, the jumper wire of the bypassed first phase (A) of the three phases of high pressure is separated to make the first phase (A) of the three phases oblique to secure a working space to complete the wire stranding and long wire work. After the jumper wire of the phase A is compressed, the transformer is newly returned to the first phase A transmitted and the terminal cable of the bypass cable is disconnected to complete the first phase A work.

In addition, during the work of the second phase (B) of the three phases, the bypass cable (20) already installed is bypassed to the second phase (B) of the three phases on both sides of the work section and then the second phase (B) in the work section. ), If there is a transformer 30, the secondary power supply of the uninterruptible transformer device 50 already installed is connected to the second phase (B) transformer for transmission, and the jumper wire of the second phase (B) is removed to be in a diagonal state. Wire and long wire work, compress the jumper wire of the second phase (B), return the transformer to the newly established second (B) phase, and disconnect the terminal cable of the bypass cable to perform the work of the second phase (B). In the third phase (C), the second phase (B) work process is repeatedly performed in the third phase (C), and the installed bypass cable 20 is removed to perform the extra-high voltage three-phase uninterrupted work. It's safe to complete.

Example 4

When there are ground obstacles and transformers in the work zone as shown in FIG.

First of all, in order to perform uninterrupted operation of the extra-high voltage distribution facility in which the poles and wires are wired, the wire transfer mechanism 10 is installed on one side of the pole in the column, and then a separate bypass cable 20 is processed and installed near the neutral line. If there is a transformer 30 in the work section after bypassing the first phase A of the high-pressure three phases, an uninterruptible voltage may be generated by branching the special high voltage by using a separate cable branch connecting member 40 in the middle of the bypass cable 20. The power supply of the transformer 30 is supplied to the transformer device 50.

At this time, by installing the switchgear 70 for construction on each side of the bypass cable 20 as described above, the twisted pair work between the bypass cable 20, the uninterruptible transformer device 50 and the transformer line in a diagonal state is safely. After the twisted wire work is completed, the switchgear 70 for construction is operated to allow temporary transmission to the live state and the transformer line for the bypass cable 20.

Next, the jumper wire of the bypassed first phase (A) of the three phases of high pressure is separated to make the first phase (A) of the three phases oblique to secure a working space to complete the wire stranding and long wire work. After the jumper wire of the phase (A) is compressed, the transformer is newly returned to the first phase (A) of the transmission and the terminal cable of the bypass cable is disconnected to complete the first phase (A) work.

In addition, during the work of the second phase (B) of the three phases, the bypass cable (20) already installed is bypassed to the second phase (B) of the three phases on both sides of the work section and then the second phase (B) in the work section. ), If there is a transformer 30, the secondary power supply of the uninterruptible transformer device 50 already installed is connected to the second phase (B) transformer for transmission, and the jumper wire of the second phase (B) is removed to be in a diagonal state. Wire and long wire work, compress the jumper wire of the second phase (B), return the transformer to the newly established second (B) phase, and disconnect the terminal cable of the bypass cable to perform the work of the second phase (B). In the third phase (C), the second phase (B) work process is repeatedly performed in the third phase (C), and the installed bypass cable 20 is removed to perform the extra-high voltage three-phase uninterrupted work. It's safe to complete.

Example 5

When there is a branch line by the branch line in the work section as shown in FIG.

First of all, in order to perform uninterrupted operation of the extra-high voltage distribution facility in which the poles and wires are wired, the wire transfer mechanism 10 is installed on one side of the poles in the column, and then a separate bypass cable 20 is laid on the ground. After bypassing the first phase (A) of the phase, if there is a branch column (60) in the work section, the special high-pressure first phase (A) is used by utilizing the cable branch connection member 40 in the middle of the bypass cable 20. After branching and connecting to the first phase of the branch line of the branch column 60 for temporary transmission, the jumper wire of the bypassed first phase A of the special high pressure three phases is separated and the first phase A of the three phases is separated. After making the wires in a diagonal state to secure the working space, complete the stranded wire and the long wire work, compress the jumper wire of the first phase (A), and establish the branch line to return to the transmitted first phase (A) and bypass the cable ( The terminal cable of 20) is disconnected to complete the first phase (A) work.

At this time, the bypass cable 20 as described above by installing the switchgear 70 for construction on each side end so that the twisted pair work between the bypass cable 20 and the branch line in the diagonal state can be made safely, the twisted pair work After this is completed by operating the construction switchgear 70 is to be made to temporarily transfer to the live state and branch line for the bypass cable (20).

In addition, during the work of the second phase (B) of the third phase, the already installed bypass cable 20 is bypassed to the second phase (B) of the third phase on both sides of the work section, and then the second phase in the work section. If there is a branch line in (B), the cable branched from the branch connection member 40 already installed is connected to the branch line second phase (B), and temporarily transferred to the branch line, and then the jumper wire of the second phase (B) Disconnect the wires, make twisted wire and long wire work, compress the jumper wire of the second phase (B), return the branch line to the newly established second phase (B), and terminate the terminal cable of the bypass cable (20). Separating to complete the work of the second phase (B), the third phase (C) is repeatedly performed the work process of the second phase (B) in the third phase (C), the installed bypass cable (20) ), You can safely complete the special high-voltage three-phase uninterrupted work.

Example 6

When there is a branch line by the ground obstacle and the branch line in the work zone as shown in FIG.

First of all, in order to perform uninterrupted operation of the extra-high voltage distribution facility where the poles and wires are wired, a wire bypass mechanism 10 is installed on one side of the poles, and then a separate bypass cable 20 is processed near the neutral state. After installing and bypassing the first phase (A) of the special high pressure three phases, and if there is a branch column (60) in the work section, the special branch of the high pressure After the phase A is branched and connected temporarily to the branch line of the branch column 60 for the first phase, the jumper wire of the bypassed first phase A of the special high pressure three phases is separated and the first of three phases is separated. Make phase (A) oblique and secure the working space to complete wire stranding and long wire work, compress the jumper wire of the first phase (A), and establish a branch line to return to the transmitted first phase (A). Then, the terminal cable of the bypass cable 20 is removed to complete the first phase (A) work.

At this time, the bypass cable 20 as described above by installing the switchgear 70 for construction on each side end so that the twisted pair work between the bypass cable 20 and the branch line in the diagonal state can be made safely, the twisted pair work After this is completed by operating the construction switchgear 70 is to be made to temporarily transfer to the live state and branch line for the bypass cable (20).

In addition, during the work of the second phase (B) of the third phase, the already installed bypass cable 20 is bypassed to the second phase (B) of the third phase on both sides of the work section, and then the second phase in the work section. If there is a branch line in (B), the cable branched from the branch connection member 40 already installed is connected to the branch line second phase (B), and temporarily transferred to the branch line, and then the jumper wire of the second phase (B) Disconnect the wires, make twisted wire and long wire work, compress the jumper wire of the second phase (B), return the branch line to the newly established second phase (B), and terminate the terminal cable of the bypass cable (20). Separating to complete the work of the second phase (B), the third phase (C) is repeatedly performed the work process of the second phase (B) in the third phase (C), the installed bypass cable (20) ), You can safely complete the special high-voltage three-phase uninterrupted work.

The uninterruptible power distribution method according to various embodiments of the present invention allows the bypass cable allowable capacity to be applied from 5,000 kV to 10,000 kV, and is not connected in 50 m units and does not have connection points in the work section. , 200m, 300m cable is provided, the existing bypass cable method is not possible to install a three-phase bypass cable on the main street in the present invention by installing only one-phase bypass cable in the downtown area for road crossing and pedestrian safety The technology has been further improved to enable the installation of special high voltage cables without the need for laying them on the ground.

It is to be understood that both the foregoing general description and the following detailed description of the present invention are exemplary and explanatory and are intended to provide further explanation of the present invention as defined by the appended claims. Examples should be understood.

10: wire wire mechanism
20: bypass cable
30: transformer note
40: branch connection member
50: uninterruptible transformer device
60: branch stock
70: construction switchgear
A: Phase 1 B: Phase 2
C: 3rd phase

Claims (6)

Installing a wire wire mechanism on one side of the pole in the column;
Laying a separate bypass cable to bypass the first phase of the extra-high pressure three phases;
Remove the jumper wire of the bypassed phase 1 wire in the extra-high voltage 3 phase, make the phase 1 of 3 phase oblique to secure the working space, complete the wire stranding and long wire work, and compress the phase 1 jumper wire Separating the terminal cable of the laid cable and completing the first phase work;
Bypass the already installed bypass cable from the both sides of the work section to the 2nd phase of the 3 phase during the 2nd phase work of the 3 phases, and then remove the jumper wire of the 2nd phase and make it diagonally Compressing the jumper wire of the second phase and disconnecting the terminal cable of the installed cable to complete the second phase work;
Repeating the work process of the second phase in the third phase;
Dismantling the installed bypass cable; Uninterruptible power distribution method using a wire transfer mechanism and a bypass cable, characterized in that by sequentially performing.
The method of claim 1,
Bypass cable is an uninterruptible power distribution method using wire transfer mechanism and bypass cable, which is installed in the ground according to the condition of the ground in the work area or processed in the state near the neutral line depending on the conditions of the construction site. .
Installing a wire wire mechanism on one side of the pole in the column;
Install a separate bypass cable to bypass the first phase of the special high voltage three phases, and then utilize the separate cable branch connection material located in the middle of the bypass cable to branch out the special high voltage and supply it to the uninterruptible transformer device to Supplying power to the phase;
Separate the jumper wire of the bypassed first phase among the three phases of high pressure and make the first phase of the three phases oblique to secure the working space to complete wire stranding and long wire work, compress the jumper wire of the first phase, and then Returning to the newly-transmitted first phase via and disconnecting the terminal cable of the bypass cable to complete work on the first phase;
After the already installed bypass cable is bypassed from both sides of the work section to the second of three phases, the second phase transformer in the work section transmits by connecting the secondary power of the uninterruptible transformer device already installed to the second phase transformer. Remove the second phase jumper wire and make it in a diagonal state to perform wire stranding and long wire work. Compress the jumper wire of the second phase, return the transformer to the new second phase, and disconnect the terminal cable of the bypass cable. Completing the process;
Repeating the work process of the second phase in the third phase;
Dismantling the installed bypass cable; Uninterruptible power distribution method using a wire transfer mechanism and a bypass cable, characterized in that by sequentially performing.
The method of claim 3, wherein
Bypass cable is an uninterruptible power distribution method using wire transfer mechanism and bypass cable, which is installed in the ground according to the condition of the ground in the work area or in the processing state near the neutral line depending on the construction site conditions.
Installing a wire wire mechanism on one side of the pole in the column;
Install a separate bypass cable to bypass the first phase of the special high voltage three phases, and then diverge from the special high voltage first phase and connect it to the first phase of the branch line by utilizing the cable branch connection material located in the middle of the bypass cable. After temporary transmission, separate the jumper wire of the 1st phase of the three phases of high pressure and make the 1st phase of the 3 phase diagonally to secure the working space to complete the wire stranding and the long wire work, and the jumper wire of the 1st phase After compression, returning the branch line to the newly-transmitted first phase and disconnecting the terminal cable of the bypass cable to complete the first phase work;
Bypass the already installed bypass cable from both sides of the work section to the second phase of the third phase and connect the cable branched from the branch connection material already installed on the branch line of the second phase in the work section to temporarily connect the second phase to the branch line. After transmission, separate the jumper wire of the 2nd phase to make it in a diagonal state, perform wire stranding and long wire work, compress the jumper wire of the 2nd phase, return the branch line to the newly established 2nd phase, and disconnect the terminal cable of the bypass cable. To complete the second phase of the work;
Repeating the work process of the second phase in the third phase;
Dismantling the installed bypass cable; Uninterruptible power distribution method using a wire transfer mechanism and a bypass cable, characterized in that by sequentially performing.
6. The method of claim 5,
Bypass cable is an uninterruptible power distribution method using wire transfer mechanisms and bypass cables, which are installed in the ground according to the condition of the ground in the work area or processed in the vicinity of the neutral line depending on the construction site conditions.
KR1020100071855A 2010-07-26 2010-07-26 Non-power-failure power distribution method using wire-changing device and bypasscable KR101122499B1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
KR1020100071855A KR101122499B1 (en) 2010-07-26 2010-07-26 Non-power-failure power distribution method using wire-changing device and bypasscable
PCT/KR2011/003996 WO2012015160A1 (en) 2010-07-26 2011-06-01 Method for distributing power without interruption using power line shifting device and bypass cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100071855A KR101122499B1 (en) 2010-07-26 2010-07-26 Non-power-failure power distribution method using wire-changing device and bypasscable

Publications (2)

Publication Number Publication Date
KR20120010370A true KR20120010370A (en) 2012-02-03
KR101122499B1 KR101122499B1 (en) 2012-03-16

Family

ID=45530318

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100071855A KR101122499B1 (en) 2010-07-26 2010-07-26 Non-power-failure power distribution method using wire-changing device and bypasscable

Country Status (2)

Country Link
KR (1) KR101122499B1 (en)
WO (1) WO2012015160A1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101394095B1 (en) * 2014-03-19 2014-05-14 운장전력 주식회사 Wiring system using overhead earth wire combined with neutral line
KR101704613B1 (en) * 2016-03-30 2017-02-08 미래전기기술단(주) Apparatus for exchanging the distribution line in the status of on line
WO2018093061A1 (en) * 2016-11-18 2018-05-24 대원전기 주식회사 Uninterruptible power distribution method without intermediate connectors of bypass cable, using single-phase multi-branch switchgear for distribution work
WO2018110845A1 (en) * 2016-12-13 2018-06-21 대원전기 주식회사 Construction method for uninterruptible power distribution without bypass cable intermediate connection points using individually openable single-phase multi-branch switchgear for construction
WO2018128269A1 (en) * 2017-01-05 2018-07-12 대원전기 주식회사 Method for performing uninterruptible power distribution work within section in de-energized line state by separating wires within pole-to-pole span by means of insulated live wire grip and bypass jumper cable

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102761076B (en) * 2012-07-05 2016-09-21 中国电力科学研究院 A kind of method for designing for 35kV circuit distribution
CA2981854C (en) 2015-04-09 2020-09-08 Quanta Associates, L.P. Conductor as a tool
KR101736175B1 (en) * 2016-10-17 2017-05-29 (주) 세양전기 Method of no power interruption in distribution line

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0670468A (en) * 1992-08-13 1994-03-11 Furukawa Electric Co Ltd:The Method and apparatus for non-interruption current changeover
JP3122553B2 (en) * 1993-03-11 2001-01-09 日本碍子株式会社 Power line switching equipment for three-phase distribution lines
KR200264163Y1 (en) * 2001-11-08 2002-02-19 한국전력공사 Device for fixing the bypass cable using no blackout process
KR100407376B1 (en) * 2002-01-10 2003-11-28 대원전기 주식회사 wire-changing device inside of electric pole and non-power-failure power distribution method
KR100479320B1 (en) * 2003-02-18 2005-03-25 우창전력(주) Uninterruptable distributing method of single-phase wire using temporary line
KR100864966B1 (en) * 2006-04-24 2008-10-22 에스엠 종합개발 주식회사 Replacement method of wire
KR20100054948A (en) * 2008-11-17 2010-05-26 (주) 진흥이엔지 By-pass construction method for replacement of pole-top transformer (1phase/3phase) using 1phase portable transformer

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101394095B1 (en) * 2014-03-19 2014-05-14 운장전력 주식회사 Wiring system using overhead earth wire combined with neutral line
WO2015141894A1 (en) * 2014-03-19 2015-09-24 대원전기 주식회사 Method for constructing power distribution line by using combined overhead ground wire and extra high voltage neutral line having separated installation structure for extra high voltage neutral line and low voltage neutral line
KR101704613B1 (en) * 2016-03-30 2017-02-08 미래전기기술단(주) Apparatus for exchanging the distribution line in the status of on line
WO2018093061A1 (en) * 2016-11-18 2018-05-24 대원전기 주식회사 Uninterruptible power distribution method without intermediate connectors of bypass cable, using single-phase multi-branch switchgear for distribution work
WO2018110845A1 (en) * 2016-12-13 2018-06-21 대원전기 주식회사 Construction method for uninterruptible power distribution without bypass cable intermediate connection points using individually openable single-phase multi-branch switchgear for construction
WO2018128269A1 (en) * 2017-01-05 2018-07-12 대원전기 주식회사 Method for performing uninterruptible power distribution work within section in de-energized line state by separating wires within pole-to-pole span by means of insulated live wire grip and bypass jumper cable

Also Published As

Publication number Publication date
KR101122499B1 (en) 2012-03-16
WO2012015160A1 (en) 2012-02-02

Similar Documents

Publication Publication Date Title
KR101122499B1 (en) Non-power-failure power distribution method using wire-changing device and bypasscable
KR100926445B1 (en) Uninterruptible bypassing method for underground power line using extension elbow
KR101777080B1 (en) Uninterrupted power distribution method in which wires are separated in de-energized power lines state by using insulated live wire grip and bypass jumper cables
EP2849296B1 (en) Live conductor stringing and splicing method and apparatus
KR20100054948A (en) By-pass construction method for replacement of pole-top transformer (1phase/3phase) using 1phase portable transformer
KR101598019B1 (en) Apparatus applied uninterruptible bypassing method for underground power line
KR101103553B1 (en) Uninterruptible power bypassing mehtod for power line using insulation guider for spacing
KR102128445B1 (en) Three Phases Pole Transformer for Uninterruptible Power Construction and Method Thereof
KR101766162B1 (en) Uninterruptible power distribution method without intermediate connection of bypass cable using single-phase multi-branch switchgear
KR20230124873A (en) Line construction method
US20090195083A1 (en) Live conductor stringing and splicing method and apparatus
CN104466949A (en) Method for 10 kV main and auxiliary line ring grid layout in small-medium urban districts in plain area
KR100407376B1 (en) wire-changing device inside of electric pole and non-power-failure power distribution method
KR101470868B1 (en) System applied uninterruptible bypassing method for underground power line
KR20010084955A (en) wire-changing device inside of electric pole and non-power-failure power distribution method
CA2995402C (en) Live conductor stringing, maintenance and repair method
KR20100036065A (en) Exchanging method of distribution line
KR101754043B1 (en) Uninterruptible power distribution method without intermediate connection of bypass cable using single-phase multi-branch switchgear with separately switching function
KR101736175B1 (en) Method of no power interruption in distribution line
CN203813320U (en) Tool for live exchange of 220 kV narrow base tower strain insulator string
JP2005191727A (en) Opgw system
CN202840317U (en) Fast-assembling transformer station
CN112491014B (en) Double-bus double-section and bus differential protection transformation method capable of reducing power failure time
KR100844039B1 (en) exchanging method of switch
D'Souza et al. Conversion of 230 KV switchyard to gas insulated substation in a gas plant

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20161220

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20171221

Year of fee payment: 7