KR20110066904A - A bridge structure water spout combined expansion joint apparatus - Google Patents

A bridge structure water spout combined expansion joint apparatus Download PDF

Info

Publication number
KR20110066904A
KR20110066904A KR1020110044378A KR20110044378A KR20110066904A KR 20110066904 A KR20110066904 A KR 20110066904A KR 1020110044378 A KR1020110044378 A KR 1020110044378A KR 20110044378 A KR20110044378 A KR 20110044378A KR 20110066904 A KR20110066904 A KR 20110066904A
Authority
KR
South Korea
Prior art keywords
bent
foreign matter
fixing
fixed frame
expansion joint
Prior art date
Application number
KR1020110044378A
Other languages
Korean (ko)
Inventor
정승영
전승환
Original Assignee
전승환
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 전승환 filed Critical 전승환
Priority to KR1020110044378A priority Critical patent/KR20110066904A/en
Publication of KR20110066904A publication Critical patent/KR20110066904A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/06Arrangement, construction or bridging of expansion joints
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/06Arrangement, construction or bridging of expansion joints
    • E01D19/062Joints having intermediate beams
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/08Damp-proof or other insulating layers; Drainage arrangements or devices ; Bridge deck surfacings
    • E01D19/086Drainage arrangements or devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE: A water receiver and expansion joint apparatus for a bridge is provided to prevent rainwater and impurities from flowing into a fixing frame using an impurity receiver member. CONSTITUTION: A water receiver and expansion joint apparatus for a bridge comprises first and second fixing frames(110,120), an impurity receiver member(130), and first and second impurity guide members(140,150). The first and second fixing frames symmetrically installed on a slab. The first and second fixing frame have top bent parts(111,121) and bottom bent parts(112,122). The impurity receiver member comprises first and second bent parts(131,132) and fastening protrusions(133). The first and second bent parts are inserted into the bottom bent parts. The fastening protrusions are inserted into fastening holes of the first and second impurity guide members. The first and second impurity guide members are fixed to the impurity receiver member.

Description

교량용 물받이 겸용 신축이음장치{A bridge structure water spout combined expansion joint apparatus}A bridge structure water spout combined expansion joint apparatus}

본 발명은 교량용 물받이 겸용 신축이음장치에 관한 것으로서, 상세하게는 신축기능을 가지면서 시공이 간편하고 내구성이 우수하며 유지보수가 간단한 교량용 물받이 겸용 신축이음장치에 관한 것이다. The present invention relates to a bridge and expansion expansion joint device for a bridge, and more particularly, to a bridge receiving and expansion expansion joint device having a simple construction and excellent durability and easy maintenance.

교량용 물받이 겸용 신축이음장치는 교량의 슬래브(slab) 사이에 설치되어 슬래브의 신축을 보상하는 장치이다. 통상 교량은 복수 개의 슬래브가 연결되어 설치되고, 온도 변화와 하중에 따라 팽창 및 수축을 하게 되므로 교량을 구성하는 슬래브는 일정 길이마다 적정한 간격을 뜻하는 유간을 갖고 설치되며, 이 유간에 신축이음장치가 설치되어 슬래브의 손상 방지는 물론 차량의 원활한 소통이 이루어지도록 하고 있다. The expansion joint for the bridge gutter for bridge is installed between the slab of the bridge to compensate for the expansion of the slab. In general, a bridge is installed with a plurality of slabs connected to each other, and expands and contracts according to temperature changes and loads, so that the slab constituting the bridge is installed with a spacing that represents an appropriate interval for each predetermined length. Is installed to prevent damage of the slab as well as to facilitate the communication of the vehicle.

한편, 교량 중 철도 교량은 다수의 교각과 교각의 상부에 양단부가 안착 고정되는 다수의 상판들로 구성되어 있으며, 이들 상판과 상판의 연결부위는 온도변화에 따라 상판이 변형되는 신축량을 흡수하고, 기차의 이동에 따른 상판 간의 간격의 변화량을 흡수할 수 있도록 상판이 서로 이격되어 설치되어 있으며, 이 이격된 틈새에는 상판의 변위를 수용하면서 상판과 상판을 연결해 주는 신축이음장치가 설치된다.On the other hand, the railway bridge of the bridge is composed of a plurality of bridges and a plurality of tops are fixed to both ends of the top of the bridge, the connection between these tops and tops absorbs the amount of expansion and deformation of the top plate according to temperature changes, The top plates are spaced apart from each other so as to absorb the amount of change in the gap between the top plates according to the movement of the train, and the spaced gaps are installed with expansion joints connecting the top plates with the top plates while receiving the displacement of the top plates.

이러한 신축이음장치는 양 상판에 대응되게 설치되는데 그 형상은 이음부의 틈새를 최소화하기 위하여 요철 형상의 핑거를 지그재그형으로 돌출시켜 상판과 상판의 연결에 의한 틈새를 최소화시켜 왔다. 이러한 틈새 이음장치의 조인트는 크게 개방형 조인트와 폐쇄형 조인트로 분류할 수 있다. 개방형 조인트가 구성된 틈새 이음장치는 시공이 편리하고 저렴한 장점이 있는 반면에 개방형 조인트 내로 빗물 등의 유입 우려가 있어 교량 구조물의 부식으로 내구성 저하 및 미관상 누수 흔적이 남는 단점이 있다. 폐쇄형 조인트가 구성된 틈새이음장치는 상판과 상판 사이에 삽입되는 탄성체가 일정시간이 지나면 탄성력이 저하되어 빗물 누수의 원인이 될뿐만 아니라, 설치방법이 복잡하고 비용이 많이 들며 구조가 복잡한 단점이 있다.These expansion joints are installed to correspond to the upper plate, the shape has been minimized by the connection of the upper plate and the upper plate by projecting the rugged finger zigzag in order to minimize the gap of the joint. Joints of such clearance joints can be classified into open joints and closed joints. The gap joint device composed of open joints has the advantages of convenient and inexpensive construction, while there is a risk of rainwater inflow into the open joints, which has the disadvantage of deterioration of durability and traces of aesthetic leakage due to corrosion of the bridge structure. The gap joint device composed of a closed joint has a disadvantage that the elastic body inserted between the upper plate and the upper plate deteriorates the elastic force after a certain time, causing rainwater leakage, and the installation method is complicated, expensive, and the structure is complicated. .

이러한 문제점을 해결하기 위해 특허등록 제0632961호(명칭: 철도교량의 신축이음장치)가 등록된 바 있다. 특허등록 제0632961호는 앵글, 덮개 및 물받이를 포함하는 신축이음장치를 제공하고 있으며, 앵글, 덮개 및 물받이는 성형하여 제작함으로써 제작비용을 절감하고, 제작이 용이한 이점이 있으며, 또한, 시공시 상판의 폭만큼 앵글, 덮개 및 물받이를 절단하여 시공함으로써 시공이 매우 간단하고, 시공비용이 절약되며, 상판의 신축에 관계없이 자갈 또는 빗물 등의 유입을 차단하여 교량 구조물의 내구성을 향상시켜 철도교량의 수명을 연장시키는 효과를 얻을 수 있다. In order to solve this problem, Patent Registration No. 0632961 (name: expansion joint device of railway bridge) has been registered. Patent registration No. 0632961 provides an expansion joint device including an angle, a cover and a drip tray. The angle, the lid and a drip tray are manufactured by molding to reduce manufacturing costs and facilitate manufacturing. By cutting the angle, cover and drip tray by the width of the top plate, the construction is very simple, and the construction cost is saved, and the bridge structure is improved by blocking the inflow of gravel or rainwater regardless of the expansion of the top plate to improve the durability of the bridge structure. It is possible to obtain an effect of extending the life of the.

전술한 특허등록 제0632961호외에 다른 예로 특허등록 제0938114호(명칭: 교량용 물받이 겸용 신축이음장치)가 등록된 바 있다. 도 1은 특허등록 제0938114호에서 제안된 종래기술에 따른 교량용 물받이 겸용 신축이음장치를 설명하기 위하여 도시한 사시도이다.In addition to the above-mentioned patent registration No. 0632961, as another example, patent registration No. 0938114 (name: expansion joint device for a combined use of a drip tray for bridge) has been registered. FIG. 1 is a perspective view illustrating a bridge joint expansion joint device according to the related art proposed in Patent Registration No. 0938114. FIG.

도 1을 참조하면, 특허등록 제0938114호에 제안된 종래기술에 따른 교량용 물받이 겸용 신축이음장치는 본선 궤도부 또는 보도부의 슬래브에 고정 설치되는 한 쌍의 고정대부재(50)와, 고정대부재(50)의 일측 상하단에 물받이부재(60)의 상단 양 날개인 절곡부(63)가 끼워져 조립되게 형성된 상단날개부(51) 및 하단날개부(52)와, 고정대부재(50)의 타측에 슬래브에 매몰 설치되어 고정대부재를 긴밀히 고정시키는 적어도 하나 이상의 고정용볼트(55)와, 한 쌍의 고정대부재(50) 사이에 조립 설치되며, 상판의 변위를 수용하면서도 자갈 또는 빗물의 유입을 차단하는 물받이부재(60)를 포함한다. 미설명된 '56', '57'은 고정대부재를 슬래브에 고정하기 위한 브라켓트를 나타낸다. Referring to Figure 1, the bridge joint expansion joint according to the prior art proposed in the patent registration No. 0938114 is a pair of stator member 50 is fixed to the slab of the main track or sidewalk, and the stator member ( The upper wing 51 and the lower wing 52 and formed on the other side of the holding member 50, the upper and lower ends of the bent portion 63 of the top of the drip member 60 is fitted into one side upper and lower ends of the 50) It is installed in the buried in at least one or more fixing bolts 55 for tightly fixing the holding member and the pair of holding members 50 are assembled and installed, while receiving the displacement of the upper plate while receiving the displacement of the gravel or rain water And a member 60. Unexplained '56' and '57' denote brackets for fixing the stator member to the slab.

이러한 구조를 갖는 종래기술에 따른 교량용 물받이 겸용 신축이음장치는 스테인레스 재질의 물받이를 적용하여 내구성이 우수함과 아울러 교체가 용이하며, 또한 블럭아웃(block out)없이 설치가 가능하므로 시공성이 우수한 이점이 있다. 또한, 대부분의 기성품과 달리 본선 궤도부와 보도부의 교량 슬래브에 연속 설치가 가능하고, 기성제품 대비 제조 단가가 저렴한 동시에 공사비 절감이 가능한 효과를 얻을 수 있다. Bridge joint expansion and contraction device according to the prior art having such a structure is excellent in durability because it is durable and easy to replace by applying a stainless steel drip and can be installed without block out (block out) have. In addition, unlike most ready-made products can be continuously installed in the bridge slab of the main track and sidewalk, and the manufacturing cost is lower than that of the ready-made products and the construction cost can be reduced.

그러나, 전술한 종래기술에 따른 교량용 물받이 겸용 신축이음장치들은 어느 정도 시공성과 작업능률을 개선한 것은 사실이나, 실질적으로 시공과정에서 요구되는 시공성과 작업능률 측면을 고려하면 여전히 시공성과 작업능률 측면에서 개선이 필요한 실정이다. However, it is true that the above-described conventional expansion joints for bridge gutters for bridges have improved construction and work efficiency to some extent. However, considering the workability and work efficiency required in the construction process, the construction and work efficiency aspects still remain. The situation is in need of improvement.

따라서, 본 발명은 종래기술에 따른 문제점을 해결하기 위해 제안된 것으로서, 시공성과 작업능률을 개선시킬 수 있는 교량용 물받이 겸용 신축이음장치를 제공하는데 그 목적이 있다. Therefore, the present invention has been proposed to solve the problems according to the prior art, and an object thereof is to provide a bridge gutter expansion and contraction device that can improve the workability and work efficiency.

상기한 목적을 달성하기 위한 일 측면에 따른 본 발명은 인접한 본선 궤도부 또는 인접한 슬래브에 각각 고정 설치되고, 일측 상하단에는 서로 대향하도록 절곡된 상단절곡부와 하단절곡부를 구비하며, 상기 상단절곡부는 상기 하단절곡부보다 내면에 더 근접하게 형성되어 있는 제1 및 제2 고정프레임과, 양측에 각각 형성된 제1 및 제2 절곡부를 구비하고, 상기 제1 절곡부는 상기 제1 고정프레임의 하단절곡부의 안쪽에 끼워지고, 상기 제2 절곡부는 상기 제2 고정프레임의 하단절곡부의 안쪽에 끼워져 상기 본선 궤도부 또는 상기 슬래브의 변위를 수용하도록 신축성을 가지며 빗물을 포함하는 이물질들을 받아 일측으로 배출하는 이물질받이부재와, 상기 제1 및 제2 고정프레임의 내면의 상부 모서리 부위로부터 각각 사선방향으로 상기 이물질받이부재의 일부를 덮도록 연장되어 설치되고, 일측부가 상기 이물질받이부재와 체결되어 상기 제1 및 제2 고정프레임 내부로 각각 유입되는 상기 빗물을 포함하는 이물질들을 상기 이물질받이부재로 유도하는 제1 및 제2 이물질안내부재를 포함하는 교량용 물받이 겸용 신축이음장치를 제공한다.The present invention according to one aspect for achieving the above object is fixedly installed on the adjacent main track or adjacent slab, respectively, the upper and lower ends have a bent upper and lower bent to face each other, the upper bent portion is First and second fixing frames formed closer to the inner surface than the lower bent portion, and the first and second bent portions formed on both sides, respectively, wherein the first bent portion is the inside of the lower bent portion of the first fixed frame The second bent part is fitted inside the lower bent part of the second fixed frame and is elastic to accommodate the displacement of the main track or the slab and receives foreign substances including rainwater to receive the foreign matter receiving member to one side And the foreign matter receiver in an oblique direction from upper edge portions of inner surfaces of the first and second fixing frames, respectively. First and second extending and installed to cover a portion of the first and the foreign matter including the rainwater flowing into the first and the second fixed frame respectively coupled to the foreign matter receiving member to guide the foreign matter receiving member. 2 Provides an expansion joint for both drip trays and bridges containing foreign material guide members.

바람직하게, 상기 제1 및 제2 고정프레임의 외면에 각각 체결되고, 중앙부가 상기 제1 및 제2 고정프레임의 외면에 용접 체결되며, 용접처리된 중앙부를 축으로 양측이 상기 제1 및 제2 고정프레임의 외면으로부터 멀어지는 방향으로 절곡되어 상기 중앙부로부터 펼쳐진 날개 구조를 가지며, 상기 제1 및 제2 고정프레임를 상기 본선 궤도부 또는 상기 슬래브에 고정하는 제1 및 제2 고정부재를 더 포함할 수 있다. Preferably, the first and second fixing frame is fastened to the outer surface, respectively, the central portion is welded to the outer surface of the first and second fixed frame, the welded center portion on both sides of the axis of the first and second It may have a wing structure that is bent in a direction away from the outer surface of the fixed frame extending from the center portion, and may further include first and second fixing members for fixing the first and second fixed frame to the main track or the slab. .

바람직하게, 상기 제1 및 제2 고정부재는 각각 양측부가 상기 제1 및 제2 고정프레임의 길이방향 또는 폭방향으로 설치되며, 상기 중앙부를 축으로 상기 제1 및 제2 고정프레임의 외면으로부터 일정 각도로 절곡되며, 상기 각도는 시공자에 의해 조정될 수 있다. Preferably, each of the first and second fixing members is provided at both sides in the longitudinal direction or the width direction of the first and second fixing frames, and is fixed from an outer surface of the first and second fixing frames with the central portion as an axis. It is bent at an angle, and the angle can be adjusted by the contractor.

바람직하게, 상기 제1 및 제2 이물질안내부재는 각각 일측부가 와셔(washer)를 통해 상기 이물질받이부재로부터 돌출된 체결돌기에 의해 체결되도록 체결공이 마련될 수 있다. Preferably, each of the first and second foreign matter guide member may be provided with a fastening hole such that one side thereof is fastened by a fastening protrusion protruding from the foreign matter receiving member through a washer.

바람직하게, 상기 와셔는 중앙부에 체결공이 마련되고, 상기 체결돌기가 삽입되어 체결되는 방식으로, 상기 체결공을 둘러싸도록 복수 개의 돌기가 형성될 수 있다. Preferably, the washer is provided with a fastening hole in the center portion, the fastening protrusion is inserted into a fastening manner, a plurality of protrusions may be formed to surround the fastening hole.

바람직하게, 상기 제1 및 제2 이물질안내부재는 각각 상기 제1 및 제2 고정프레임의 길이방향으로 연장된 판형 구조를 가지며, 상기 제1 및 제2 고정프레임의 하단절곡부에 대응되는 부위에 상기 이물질받이부재 방향으로 절곡된 절곡부를 가질 수 있다.Preferably, the first and second foreign matter guide member has a plate-like structure extending in the longitudinal direction of the first and second fixing frame, respectively, and at a portion corresponding to the lower bent portion of the first and second fixing frame. It may have a bent portion bent in the foreign matter receiving member direction.

바람직하게, 상기 슬래브를 형성하기 위한 콘크리트 타설 전에 상기 하단절곡부와 동일 선상에 위치되도록 상기 상단절곡부의 외면에 부착된 후 상기 콘크리트 타설 후 제거되는 보호부재를 더 포함할 수 있다.Preferably, the method may further include a protective member attached to the outer surface of the upper bent portion so as to be positioned in the same line as the lower bent portion before the concrete is poured to form the slab, and then removed after the concrete is poured.

이상에서 설명한 바와 같이, 본 발명에 의하면, 한 쌍의 고정프레임의 상단절곡부를 하단절곡부보다 내면에 더 근접하도록 형성함으로써 이물질받이부재의 상단 양 날개인 절곡부가 고정프레임 내부로 용이하게 끼워지도록 하여 시공성과 작업능률을 개선시킬 수 있다. As described above, according to the present invention, by forming the upper bent portion of the pair of fixed frame closer to the inner surface than the lower bent portion so that the bent portion of the upper wings of the foreign matter receiving member to be easily inserted into the fixed frame. Improve workability and work efficiency

또한, 본 발명에 의하면, 한 쌍의 고정프레임의 내면 모서리 부위로부터 사선방향으로 고정프레임 사이에 위치된 이물질받이부재의 일부를 덮도록 연장되어 설치되고, 일측부가 와셔(washer)를 통해 이물질받이부재의 체결돌기에 체결되도록 체결공이 마련된 이물질안내부재를 제공함으로써 고정프레임 내부로 유입되는 빗물(또는 자갈) 등을 이물질받이부재로 유도하여 빗물 등이 고정프레임 내부로 유입되는 것을 방지할 수 있다.In addition, according to the present invention, an extension is installed to cover a part of the foreign matter receiving member located between the fixing frames in an oblique direction from the inner edges of the pair of fixed frames, one side is the foreign matter receiving member through the washer (washer) By providing a foreign matter guide member provided with a fastening hole to be fastened to the fastening protrusion of the rainwater (or gravel) to be introduced into the fixed frame to the foreign matter receiving member can be prevented from entering the inside of the fixed frame.

또한, 본 발명에 의하면, 고정프레임의 외면에 설치되고, 중앙부가 용접처리되며, 용접처리된 중앙부를 축으로 양측이 고정프레임의 외면으로부터 멀어지는 방향으로 절곡되어 전체적인 형상이 중심부로부터 펼쳐진 양 날개 구조를 갖는 고정부재를 제공함으로써 시공자에 의해 고정부재의 양 날개의 각도를 용이하게 조절하도록 하여 고정프레임을 본선 궤도부 또는 슬래브에 안정적으로 고정 설치하는 것이 가능하다. In addition, according to the present invention, it is installed on the outer surface of the fixed frame, the center portion is welded, both sides of the welded center portion is bent in a direction away from the outer surface of the fixed frame to the axis and the overall shape is unfolded from the center portion It is possible to easily fix the fixed frame to the main track or slab by providing a fixing member having an easy to adjust the angle of both wings of the fixing member by the contractor.

또한, 본 발명에 의하면, 슬래브를 형성하기 위한 콘크리트 타설 전에 하단절곡부와 동일 선상에 위치되도록 상단절곡부의 외면에 부착된 후 상기 콘크리트 타설 후 제거되는 보호부재를 더 포함으로써 콘크리트 타설시 콘크리트가 고정프레임 내부로 유입되는 문제를 방지할 수 있다. In addition, according to the present invention, the concrete is fixed at the time of concrete installation by further comprising a protective member which is attached to the outer surface of the upper bent portion so as to be located in the same line as the lower bent portion before the concrete pouring to form the slab and then removed after the concrete is poured. The problem of entering into the frame can be prevented.

도 1은 종래기술에 따른 교량용 물받이 겸용 신축이음장치를 도시한 사시도.
도 2는 본 발명의 실시예에 따른 교량용 물받이 겸용 신축이음장치를 도시한 사시도.
도 3은 도 2에 도시된 교량용 물받이 겸용 신축이음장치를 도시한 정면도.
도 4는 도 2에 도시된 제1 및 제2 고정프레임(110, 120)을 도시한 사시도.
도 5는 도 2에 도시된 이물질받이부재(130)를 도시한 사시도.
도 6은 도 2에 도시된 제1 및 제2 이물질안내부재(140, 150)의 일례를 도시한 사시도.
도 7은 도 2에 도시된 제1 및 제2 이물질안내부재(140, 150)의 다른 예를 도시한 사시도.
Figure 1 is a perspective view showing the expansion and expansion joint device for the bridge according to the prior art.
Figure 2 is a perspective view showing the expansion and expansion joint device for a gutter for bridges according to an embodiment of the present invention.
Figure 3 is a front view showing the expansion and expansion joint device for the bridge shown in Figure 2;
4 is a perspective view of the first and second fixing frames 110 and 120 shown in FIG. 2.
5 is a perspective view showing the foreign matter receiving member 130 shown in FIG.
6 is a perspective view showing an example of the first and second foreign matter guide member (140, 150) shown in FIG.
FIG. 7 is a perspective view illustrating another example of the first and second foreign matter guide members 140 and 150 shown in FIG. 2.

본 발명의 이점 및 특징, 그리고 그것들을 달성하는 방법은 첨부되는 도면과 함께 상세하게 후술되는 실시예를 참조하면 명확해질 것이다. 그러나, 본 발명은 이하에서 개시되는 실시예로 한정되는 것이 아니라 서로 다른 다양한 형태로 구현될 것이다. Advantages and features of the present invention, and methods for achieving them will be apparent with reference to the embodiments described below in detail in conjunction with the accompanying drawings. However, the present invention is not limited to the embodiments disclosed below, but may be implemented in various different forms.

본 명세서에서 본 실시예는 본 발명의 개시가 완전하도록 하며, 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자에게 발명의 범주를 완전하게 알려주기 위해 제공되는 것이다. 그리고 본 발명은 청구항의 범주에 의해 정의될 뿐이다. 따라서, 몇몇 실시예에서, 잘 알려진 구성 요소, 잘 알려진 동작 및 잘 알려진 기술들은 본 발명이 모호하게 해석되는 것을 피하기 위하여 구체적으로 설명되지 않는다. In this specification, the embodiments are provided so that the disclosure of the present invention may be completed and the scope of the present invention may be completely provided to those skilled in the art. And the present invention is only defined by the scope of the claims. Thus, in some embodiments, well known components, well known operations and well known techniques are not described in detail in order to avoid obscuring the present invention.

또한, 명세서 전체에 걸쳐 동일 참조 부호는 동일 구성 요소를 지칭한다. 그리고, 본 명세서에서 사용된(언급된) 용어들은 실시예를 설명하기 위한 것이며 본 발명을 제한하고자 하는 것은 아니다. 본 명세서에서, 단수형은 문구에서 특별히 언급하지 않는 한 복수형도 포함한다. 또한, '포함(또는, 구비)한다'로 언급된 구성 요소 및 동작은 하나 이상의 다른 구성요소 및 동작의 존재 또는 추가를 배제하지 않는다. Also, like reference numerals refer to like elements throughout. In addition, the terms used (discussed) herein are for the purpose of describing the embodiments are not intended to limit the invention. In the present specification, the singular form includes plural forms unless otherwise specified in the specification. Also, components and acts referred to as " comprising (or comprising) " do not exclude the presence or addition of one or more other components and operations.

다른 정의가 없다면, 본 명세서에서 사용되는 모든 용어(기술 및 과학적 용어를 포함)는 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에게 공통적으로 이해될 수 있는 의미로 사용될 수 있을 것이다. 또 일반적으로 사용되는 사전에 정의되어 있는 용어들은 정의되어 있지 않은 한 이상적으로 또는 과도하게 해석되지 않는다.Unless otherwise defined, all terms (including technical and scientific terms) used in the present specification may be used in a sense that can be commonly understood by those skilled in the art. In addition, the terms defined in the commonly used dictionary are not ideally or excessively interpreted unless they are defined.

이하, 첨부된 도면들을 참조하여 본 발명의 기술적 특징을 구체적으로 설명하기로 한다.Hereinafter, technical features of the present invention will be described in detail with reference to the accompanying drawings.

실시예Example

도 2는 본 발명의 실시예에 따른 교량용 물받이 겸용 신축이음장치를 설명하기 위하여 도시한 사시도이고, 도 3은 도 2에 도시된 교량용 물받이 겸용 신축이음장치를 정면에서 바라본 도면이다. FIG. 2 is a perspective view illustrating a bridge gutter expansion and expansion device according to an embodiment of the present invention, and FIG. 3 is a view of the bridge gutter expansion and expansion device shown in FIG. 2 as viewed from the front.

도 2 및 도 3을 참조하면, 본 발명의 실시예에 따른 교량용 물받이 겸용 신축이음장치는 인접한 본선 궤도부 또는 보도부의 슬래브 사이 공간인 유간에 설치되며, 제1 및 제2 고정프레임(110, 120)과, 이물질받이부재(130)와, 제1 및 제2 이물질안내부재(140, 150)를 포함한다. Referring to Figures 2 and 3, the bridge gutter expansion and contraction apparatus according to an embodiment of the present invention is installed in the clearance between the slab of the adjacent main track or sidewalk, the first and second fixing frame 110, 120, the foreign matter receiving member 130, and the first and second foreign matter guide members 140 and 150.

제1 및 제2 고정프레임(110, 120)은 인접한 본선 궤도부 또는 보도부의 슬래브에 서로 대칭적으로 고정 설치된다. 제1 및 제2 고정프레임(110, 120)은 연속적으로 설치되는 형태일 수 있고, 제1 및 제2 고정프레임(110, 120)의 일측 상하단에는 각각 서로 대향하도록 절곡된 상단절곡부(111, 121)와 하단절곡부(112, 122)를 구비한다. The first and second fixing frames 110 and 120 are symmetrically fixed to each other on the slab of the adjacent main track or sidewalk. The first and second fixing frames 110 and 120 may be installed continuously, and the upper and lower bending portions 111, bent to face each other at the upper and lower ends of the first and second fixing frames 110 and 120, respectively. 121) and lower bends 112 and 122.

도 4는 도 2에 도시된 제1 및 제2 고정프레임(110, 120)을 도시한 사시도이다. 도 4에 도시된 바와 같이 상단절곡부(111)는 하단절곡부(112)보다 제1 고정프레임(110)의 내면(113)에 더 근접하게 형성되어 있다. 또한, 상단절곡부(121)는 하단절곡부(122)보다 제2 고정프레임(120)의 내면(123)에 더 근접하게 형성되어 있다. 즉, 상단절곡부(111, 121)는 하단절곡부(112, 122)보다 내면(113, 123) 방향으로 더 안쪽에 형성되어 있다. 4 is a perspective view illustrating the first and second fixing frames 110 and 120 shown in FIG. 2. As shown in FIG. 4, the upper bent part 111 is formed closer to the inner surface 113 of the first fixing frame 110 than the lower bent part 112. In addition, the upper bent part 121 is formed closer to the inner surface 123 of the second fixing frame 120 than the lower bent part 122. That is, the upper bent portions 111 and 121 are formed further inward in the inner surfaces 113 and 123 than the lower bent portions 112 and 122.

이와 같이 상단절곡부(111, 121)를 하단절곡부(112, 122)보다 내면(113, 123)에 더 근접하게 형성하는 이유는 이물질받이부재(130)의 제1 및 제2 절곡부(131, 132)를 각각 제1 및 제2 고정프레임(110, 120) 내부로 용이하게 인입시키기 위함이다. 이물질받이부재(130)는 양측에 도 1의 도면상에서 하방향으로 절곡된 제1 및 제2 절곡부(131, 132)가 형성되어 있다. 제1 및 제2 절곡부(131, 132)는 제1 및 제2 고정프레임(110, 120) 내부로 각각 삽입되고, 하단절곡부(112, 122)의 종단부가 제1 및 제2 절곡부(131, 132)에 의해 형성된 골('∧') 내부로 삽입되어 끼워지게 된다. The reason why the upper bent portions 111 and 121 are formed closer to the inner surfaces 113 and 123 than the lower bent portions 112 and 122 is because of the first and second bent portions 131 of the foreign matter receiving member 130. And 132 are easily introduced into the first and second fixing frames 110 and 120, respectively. The foreign matter receiving member 130 has first and second bent portions 131 and 132 bent downward on the drawings of FIG. 1 on both sides. The first and second bent portions 131 and 132 are inserted into the first and second fixing frames 110 and 120, respectively, and the end portions of the lower bent portions 112 and 122 are first and second bent portions ( 131 and 132 are inserted into the bone ('∧') formed by the fitting.

제1 및 제2 절곡부(131, 132)를 제1 및 제2 고정프레임(110, 120) 내부로 인입시키는 과정에서 상단절곡부(111, 121)와 하단절곡부(112, 122)가 일직선상으로 동일 선상에 형성되는 경우 제1 및 제2 절곡부(131, 132)를 제1 및 제2 고정프레임(110, 120) 내부로 인입시키는데 많은 어려움이 있다. 실질적으로 상단절곡부(111, 121)와 하단절곡부(112, 122) 간의 동일 선상에서의 이격거리는 충분히 크지 않기 때문에 제1 및 제2 절곡부(131, 132)를 제1 및 제2 고정프레임(110, 120)으로 인입시키는 것은 많은 노력이 요구되고, 이는 작업능률이 저하되는 요인이 되기도 한다. In the process of drawing the first and second bent portions 131 and 132 into the first and second fixing frames 110 and 120, the upper bent portions 111 and 121 and the lower bent portions 112 and 122 are aligned with each other. When formed on the same line, there are many difficulties in drawing the first and second bent portions 131 and 132 into the first and second fixing frames 110 and 120. Since the separation distance on the same line between the upper bent portions 111 and 121 and the lower bent portions 112 and 122 is not large enough, the first and second bent portions 131 and 132 may be replaced by the first and second fixed frames. Introducing to (110, 120) requires a lot of effort, which can be a factor of deteriorating work efficiency.

이러한 문제를 해결하기 위해 본 발명에서는 상단절곡부(111, 121)를 하단절곡부(112, 122)보다 내면(113, 123)에 더 근접하게 형성한다. 즉, 상단절곡부(111, 121)와 하단절곡부(112, 122)를 상하로 동일 선상에 형성하는 것이 아니라 서로 엇갈리도록 형성함으로써 실질적으로 상단절곡부(111, 121)와 하단절곡부(112, 122) 간의 이격거리는 동일 선상에 비해 사선거리만큼 증가시키는 효과를 얻을 수 있으며, 이를 통해, 제1 및 제2 절곡부(131, 132)의 삽입작업시 작업능률을 개선시킬 수 있다. In order to solve this problem, in the present invention, the upper bent portions 111 and 121 are formed closer to the inner surfaces 113 and 123 than the lower bent portions 112 and 122. That is, the upper bent portions 111 and 121 and the lower bent portions 112 and 122 are not formed in the same line up and down, but are formed to cross each other, thereby substantially the upper bent portions 111 and 121 and the lower bent portion 112. , 122) the separation distance can be obtained by increasing the diagonal line distance compared to the same line, through this, it is possible to improve the work efficiency during the insertion work of the first and second bent portions (131, 132).

한편, 도 1에는 상단절곡부(111, 121)가 제1 및 제2 고정프레임(110, 120)으로부터 각각 하방으로 수직으로 절곡되어 있으나, 본 발명은 이에 제한되는 것은 결코 아니다. 예를 들어, 상단절곡부(111, 121)는 각각 제1 및 제2 고정프레임(110, 120)의 내면(113, 123)으로부터 90°이하, 바람직하게는 30~80°의 각도로 절곡되어 형성될 수도 있다. 물론, 하단절곡부(112, 122) 또한 상단절곡부(111, 121)와 마찬가지로 형성될 수 있다. 이와 같이, 상단절곡부(111, 121)를 제1 및 제2 고정프레임(110, 120)의 내면(113, 123)으로부터 30~80°의 각도로 절곡시키는 이유는 각도가 줄어들수록 하단절곡부(112, 122)와의 이격거리를 증가시킬 수 있기 때문이다. Meanwhile, in FIG. 1, the upper bent portions 111 and 121 are bent vertically downward from the first and second fixed frames 110 and 120, respectively, but the present invention is not limited thereto. For example, the upper bent portions 111 and 121 are bent at an angle of 90 ° or less, preferably 30 to 80 °, from the inner surfaces 113 and 123 of the first and second fixed frames 110 and 120, respectively. It may be formed. Of course, the lower bent portions 112 and 122 may also be formed similarly to the upper bent portions 111 and 121. As such, the reason why the upper bent portions 111 and 121 are bent at an angle of 30 to 80 ° from the inner surfaces 113 and 123 of the first and second fixing frames 110 and 120 is lower as the angle is reduced. This is because the separation distance with (112, 122) can be increased.

도 5는 도 2에 도시된 이물질받이부재(130)를 도시한 사시도이다. 도 3에 도시된 바와 같이 이물질받이부재(130)는 양측에 날개 구조를 갖는 제1 및 제2 절곡부(131, 132)를 구비하며, 전체적으로는 'V'자, 바람직하게는 하단부가 장력(tension)을 갖도록 반원형으로 이루어진 'U'자 형상을 갖도록 형성된다. 제1 및 제2 절곡부(131, 132)는 각각 후크(hook) 형상으로 절곡되어 하단절곡부(112, 122)에 끼워진다. 5 is a perspective view illustrating the foreign matter receiving member 130 shown in FIG. 2. As illustrated in FIG. 3, the foreign matter receiving member 130 includes first and second bent portions 131 and 132 having a wing structure at both sides thereof, and are generally 'V' shaped, and preferably, the lower end thereof has a tension ( It is formed to have a 'U' shape made of a semicircle to have a tension). The first and second bent portions 131 and 132 are bent into hooks, respectively, and are fitted into the lower bent portions 112 and 122.

이물질받이부재(130)는 내구성이 우수한 재질로 형성할 수 있다. 예를 들어,강철, 알루미늄, 티타늄, 카본 파이버, 스테인리스(stainless)로 형성할 수 있다. 알루미늄과 티타늄은 일정한 강도를 가지면서 부식에 강하고 비교적 가벼운 이점이 있다. 특히 티타늄은 반영구적으로 사용할 수 있으며, 충격 흡수력도 우수한 것으로 알려져 있다. 카본 파이버는 여러 겹으로 제작되기 때문에 필요에 따라 강도를 높일 수 있고, 무게도 줄일 수 있으며, 티타늄과 같이 충격 흡수력도 우수한 것으로 알려져 있다. The foreign matter receiving member 130 may be formed of a material having excellent durability. For example, it may be formed of steel, aluminum, titanium, carbon fiber, stainless steel (stainless). Aluminum and titanium have the advantages of being of constant strength, resistant to corrosion and relatively light. In particular, titanium can be used semi-permanently, and is known to have excellent shock absorption. Since carbon fibers are manufactured in multiple layers, strength can be increased, weight can be reduced, and shock absorbing properties, such as titanium, are known to be excellent.

도 6은 도 2에 도시된 제1 및 제2 이물질안내부재(140, 150)의 일례를 도시한 사시도이고, 도 7은 도 2에 도시된 제1 및 제2 이물질안내부재(140, 150)의 다른 예를 도시한 사시도이다. 6 is a perspective view illustrating an example of the first and second foreign matter guide members 140 and 150 shown in FIG. 2, and FIG. 7 is a view of the first and second foreign matter guide members 140 and 150 shown in FIG. 2. Is a perspective view showing another example.

도 5 내지 도 7에 도시된 바와 같이, 이물질받이부재(130)는 제1 및 제2 고정프레임(110, 120)의 길이방향으로 신장되고, 그 양측에는 체결돌기(133)가 마련되어 있다. 각각의 체결돌기(133)는 이물질안내부재(140, 150)에 마련된 체결공(141, 151)에 각각 삽입되어 체결된다. 도 6 및 도 7과 같이 체결공(141, 151)은 복수 개가 형성되어 있으며, 바(bar) 형상으로 형성된다. 형성되는 위치에 따라, 예를 들면 도 3에서 바라보는 위치에서 첫번째 체결공은 이물질안내부재(140, 150)의 길이방향으로 신장되고, 최종번째 체결공은 이물질안내부재(140, 150)의 폭방향으로 신장된다. 5 to 7, the foreign matter receiving member 130 extends in the longitudinal direction of the first and second fixing frames 110 and 120, and fastening protrusions 133 are provided at both sides thereof. Each of the fastening protrusions 133 is inserted into and fastened to the fastening holes 141 and 151 provided in the foreign material guide members 140 and 150, respectively. 6 and 7, a plurality of fastening holes 141 and 151 are formed and are formed in a bar shape. Depending on the position formed, for example, the first fastening hole extends in the longitudinal direction of the foreign matter guide member (140, 150) in the position shown in Figure 3, the last fastening hole is the width of the foreign matter guide member (140, 150) Extend in the direction.

이물질안내부재(140, 150)는 일례로 도 6에 도시된 바와 같이 각각 제1 및 제2 고정프레임(110, 120)의 길이방향으로 연장된 판형 구조를 가지며, 제1 및 제2 고정프레임(110, 120)의 하단절곡부(112, 122)에 대응되는 부위에 이물질받이부재(130) 방향으로 절곡된 절곡부를 가질 수 있다. 다른 예로, 도 7에 도시된 바와 같이 이물질안내부재(140, 150)는 절곡부를 구비하지 않고 판형 구조로만 이루어질 수 있다. As illustrated in FIG. 6, the foreign matter guide member 140 or 150 has a plate-like structure extending in the longitudinal direction of the first and second fixing frames 110 and 120, respectively, and the first and second fixing frames ( It may have a bent portion that is bent in the direction of the foreign matter receiving member 130 in a portion corresponding to the lower bent portion (112, 122) of (110, 120). As another example, as illustrated in FIG. 7, the foreign material guide members 140 and 150 may be formed only in a plate structure without the bent portion.

이물질안내부재(140, 150)는 상단부가 각각 제1 및 제2 고정프레임(110, 120)의 내면 상부 모서리 부위에 끼워져 고정되고, 하단부가 이물질받이부재(130)에 체결 고정됨에 따라 제1 및 제2 고정프레임(110, 120) 내에서 이탈되지 않고, 고정될 수 있다. 도 1에 도시된 종래기술에서는 물받이부재(60)가 고정대부재(50)의 내면 모서리 부위와 이격되어 설치되기 때문에 작업에 따라 고정대부재(50) 내에서 고정되지 않고 움직이는 문제가 발생되고, 이 과정에서 물받이부재(60)가 이탈되는 문제가 발생될 수도 있다. 그러나, 본 발명에서는 이물질안내부재(140, 150)가 제1 및 제2 고정프레임(110, 120)의 내면 상부 모서리 부위에 끼워져 고정되기 때문에 종래기술와 같은 구조에서 발생될 수 있는 문제점이 원천적으로 발생되지 않는다. The foreign material guide members 140 and 150 are fitted into and fixed to the upper edge portions of the inner surfaces of the first and second fixing frames 110 and 120, respectively, and the lower ends are fastened and fixed to the foreign matter receiving member 130. The second fixing frames 110 and 120 may be fixed without being separated from each other. In the prior art shown in Figure 1 because the drip member 60 is installed to be spaced apart from the inner surface edge portion of the holder member 50, the problem occurs without moving in the holder member 50 in accordance with the operation, this process In the drip member 60 may be a problem that is separated. However, in the present invention, since the foreign matter guide member (140, 150) is fitted and fixed to the upper edge portion of the inner surface of the first and second fixing frame (110, 120), a problem that may occur in the same structure as the prior art occurs at the source. It doesn't work.

도 5에 도시된 바와 같이, 체결돌기(133)의 일측에 끼워져 이물질안내부재(140, 150)를 이물질받이부재(130)에 체결 고정하는 와셔(washer, 180)를 더 포함한다. 와셔(180)는 중앙부에 체결공(181)이 마련되고, 이물질안내부재(140, 150)의 체결공(141, 151)을 관통한 체결돌기(133)가 삽입되어 체결되도록 복수 개의 돌기(182)가 형성되어 있다. 돌기(182)는 서로 분리되어 체결공(181)을 둘러싸도록 체결공(181) 방향으로 신장된 구조를 가지며, 바깥쪽에서 안쪽으로 구부러진 곡면 형상으로 이루어져 일정한 크기의 탄성을 갖게 된다. 이에 따라, 체결돌기(133)는 체결공(181) 내부로 용이하게 삽입되지만 삽입된 후 돌기(182)에 의해 빠지지 않고 체결될 수 있다. As shown in FIG. 5, the cleaner further includes a washer 180 that is fitted to one side of the fastening protrusion 133 to fasten and fix the foreign material guide members 140 and 150 to the foreign substance receiving member 130. The washer 180 is provided with a fastening hole 181 at a central portion thereof, and a plurality of protrusions 182 to insert and fasten the fastening protrusion 133 penetrating the fastening holes 141 and 151 of the foreign material guide member 140 and 150. ) Is formed. The protrusions 182 are separated from each other and have a structure extended in the direction of the fastening hole 181 so as to surround the fastening hole 181, and have elasticity of a predetermined size made of a curved shape bent inward from the outside. Accordingly, the fastening protrusion 133 is easily inserted into the fastening hole 181, but may be fastened without being removed by the protrusion 182 after being inserted.

도 2 및 도 3에 도시된 바와 같이, 제1 및 제2 고정프레임(110, 120)의 외면(내면의 반대편에 위치되는 면)(114, 124)에는 각각 제1 및 제2 고정프레임(110, 120)을 보도부의 슬래브에 고정시키기 위한 제1 및 제2 고정부재(160, 170)가 체결되어 있다. 제1 및 제2 고정부재(160, 170)는 표면에 산화를 방지하기 위하여 아연으로 코팅처리될 수 있으며, 이를 통해 강도와 내구성을 향상시켜 부식 및 결함을 방지할 수 있다. 2 and 3, the outer and outer surfaces of the first and second fixing frames 110 and 120 (the surfaces positioned opposite to the inner surfaces) 114 and 124 are respectively the first and second fixing frames 110. , 120 and 170 are fastened to the first and second fixing members 160 and 170 for fixing the slab 120 to the slab of the sidewalk. The first and second fixing members 160 and 170 may be coated with zinc to prevent oxidation on the surface thereof, thereby improving strength and durability to prevent corrosion and defects.

제1 및 제2 고정부재(160, 170)는 제1 및 제2 고정프레임(110, 120)의 길이방향으로 설치된다. 하지만, 본 발명은 이에 한정되는 것은 결코 아니며, 제1 및 제2 고정부재(160, 170)는 제1 및 제2 고정프레임(110, 120)의 폭방향으로 설치될 수도 있다. 이러한 제1 및 제2 고정부재(160, 170)는 중앙부가 제1 및 제2 고정프레임(110, 120)에 용접 체결되고, 용접된 중앙부를 축으로 양측부가 제1 및 제2 고정프레임(110, 120)의 외면(114, 124)으로부터 각각 일정 각도로 절곡되어 있으며, 이때, 상기 각도는 시공자에 의해 조정이 가능하여 시공과 작업환경을 고려하여 변경될 수 있다. The first and second fixing members 160 and 170 are installed in the longitudinal direction of the first and second fixing frames 110 and 120. However, the present invention is not limited thereto, and the first and second fixing members 160 and 170 may be installed in the width direction of the first and second fixing frames 110 and 120. The first and second fixing members 160 and 170 have a central portion welded to the first and second fixing frames 110 and 120, and both sides of the first and second fixing members 160 and 170 are axially welded to the first and second fixing frames 110. , 120 are bent at a predetermined angle from the outer surfaces 114 and 124, respectively, in which the angle can be adjusted by the contractor to be changed in consideration of construction and working environment.

제1 및 제2 고정부재(160, 170)는 도시되지는 않았지만 콘크리트 타설 전에 슬래브 내부에 장착되어 있는 철근과 결합 철선을 통해 체결되는데, 제1 및 제2 고정부재(160, 170)의 양쪽 날개의 각도 조절이 시공자에 의해 간편하게 조정이 가능함에 따라 철근의 위치에 상관없이 제1 및 제2 고정부재(160, 170)를 조정함으로써 결합 철선을 이용하여 제1 및 제2 고정부재(160, 170)와 철근을 안정적으로 체결할 수 있다.Although not shown, the first and second fixing members 160 and 170 are fastened through reinforcing bars and coupling wires mounted inside the slab before concrete pouring. Both wings of the first and second fixing members 160 and 170 are fastened. Of the first and second fixing members 160 and 170 by using the combined wires by adjusting the first and second fixing members 160 and 170 irrespective of the position of the rebars, as the angle of the adjustment can be easily adjusted by the contractor. ) And reinforcing bars can be securely fastened.

한편, 제1 및 제2 고정부재(160, 170)는 도 2 및 도 3에 도시된 구조 이외에, 중앙부의 일부가 제1 및 제2 고정프레임(110, 120)의 외면에 용접 체결되고, 상하좌우 방향으로 절곡된 구조로 이루어질 수 있다. 도 2 및 도 3에서는 제1 및 제2 고정프레임(110, 120)의 폭방향, 즉 상하방향으로만 절곡된 구조로 이루어져 있으나, 이에 더하여, 제1 및 제2 고정프레임(110, 120)의 길이방향, 즉 좌우방향으로도 절곡될 수도 있다. 이를 통해 제1 및 제2 고정부재(160, 170)의 절곡부를 증가시켜 고정 특성을 향상시킬 수도 있다. 또한, 제1 및 제2 고정부재(160, 170)는 도 3과 같이 정면도에서 바라볼 때, '<'자 형상이 아닌 'ㄷ'자 형상으로도 절곡될 수도 있다. Meanwhile, in addition to the structure shown in FIGS. 2 and 3, the first and second fixing members 160 and 170 are welded to the outer surface of the first and second fixing frames 110 and 120 in a welded manner, and the upper and lower parts thereof. It may be made of a structure bent in the left and right directions. In FIGS. 2 and 3, the first and second fixing frames 110 and 120 are bent only in the width direction, that is, in the vertical direction. However, the first and second fixing frames 110 and 120 may be bent. It may also be bent in the longitudinal direction, ie in the left and right directions. Through this, the bent portions of the first and second fixing members 160 and 170 may be increased to improve fixing characteristics. In addition, the first and second fixing members 160 and 170 may be bent in a 'c' shape instead of a '<' shape when viewed from the front view as shown in FIG. 3.

이러한 제1 및 제2 고정부재(160, 170)는 제1 및 제2 고정프레임(110, 120)에 일부가 용접체결된 후 절곡시키지 않은 상태로 이송한 다음, 슬래브 내부에 설치하기 위하여 거푸집 내에 제1 및 제2 고정프레임(110, 120)을 설치한 후 절곡시켜 설치한다. 이에 따라, 제1 및 제2 고정프레임(110, 120)의 이송이 편리한 이점을 얻을 수 있다. The first and second fixing members 160 and 170 are transferred to the first and second fixing frames 110 and 120 without bending after being partially welded to the first and second fixing frames 110 and 120, and then installed in the formwork to be installed inside the slab. The first and second fixing frames 110 and 120 are installed and then bent. Accordingly, the transfer of the first and second fixed frames 110 and 120 may be advantageous.

도 2에 도시된 바와 같이, 슬래브의 콘크리트 타설 전에 제1 및 제2 고정프레임(110, 120)의 상단절곡부(111, 121)의 외면에는 보호부재(190)가 더 부착될 수 있다. 전술한 바와 같이 상단절곡부(111, 121)는 하단절곡부(112, 122)보다 제1 및 제2 고정프레임(110, 120)의 내면(113, 123)에 더 근접하게 형성됨에 따라 상단절곡부(111, 121)는 하단절곡부(112, 122)와 상하로 동일 선상에 위치될 수 없다. 이로 인해, 콘크리트 타설시 콘크리트가 제1 및 제2 고정프레임(110, 120) 내부로 유입되는 문제가 발생될 수 있는데, 이를 방지하기 위하여 상단절곡부(111, 121)의 외면에 보호부재(190)를 부착시켜 상하로 하단절곡부(112, 122)와 동일 선상에 위치시킨다. As shown in FIG. 2, the protection member 190 may be further attached to the outer surfaces of the upper bent portions 111 and 121 of the first and second fixing frames 110 and 120 before the slab is poured. As described above, the upper bent portions 111 and 121 are formed to be closer to the inner surfaces 113 and 123 of the first and second fixed frames 110 and 120 than the lower bent portions 112 and 122. The portions 111 and 121 may not be positioned on the same line up and down with the lower bend portions 112 and 122. As a result, when concrete is poured, a problem may occur in which concrete is introduced into the first and second fixing frames 110 and 120. In order to prevent this, the protection member 190 is disposed on the outer surfaces of the upper bent portions 111 and 121. ) Is placed on the same line as the lower bends 112 and 122.

이와 같이, 보호부재(190)를 상단절곡부(111, 121)의 외면에 부착시킴으로써 콘크리트 타설시 보호부재(190)는 콘크리트가 제1 및 제2 고정프레임(110, 120) 내부로 유입되는 것을 방지할 수 있다. 보호부재(190)는 신축이음장치의 시공이 완료된 후 제거될 수 있다. 보호부재(190)는 상단절곡부(111, 121)의 외면에 부착이 용이하도록 신축성을 가지면서 콘크리트에 포함된 물이 흡수되지 않는 재질로 사용하는 것이 바람직하다. 예를 들면, 볼륨감이 있는 테이프(양면 테이프) 또는 문풍지를 사용할 수 있다. 이외에도, 콘크리트 타설시 어느 정도의 하중을 견딜 수 있는 재료는 모두 사용할 수 있다. As such, by attaching the protection member 190 to the outer surfaces of the upper bent portions 111 and 121, the protection member 190 when the concrete is poured, the concrete is introduced into the first and second fixed frame (110, 120) It can prevent. The protective member 190 may be removed after the construction of the expansion joint device is completed. The protective member 190 is preferably used as a material that does not absorb water contained in the concrete while having elasticity to facilitate attachment to the outer surfaces of the upper bent portions 111 and 121. For example, a tape with a sense of volume (double-sided tape) or a wind paper can be used. In addition, any material that can withstand a certain load when placing concrete can be used.

한편, 도 2에서 미설명된 '200'은 이물질받이부재(130)의 하단에 설치되는 배수구이다. Meanwhile, '200', which is not described in FIG. 2, is a drain hole installed at the lower end of the foreign matter receiving member 130.

이러한 구조를 갖는 교량용 물받이 겸용 신축이음장치의 시공방법에 대해 간략하게 설명하기로 한다. The construction method of the expansion and expansion joint device for the bridge with such a structure will be briefly described.

먼저, 콘크리트 타설 전, 제1 및 제2 고정프레임(110, 120)을 거푸집(미도시) 내에 설치한다. 이때, 제1 및 제2 고정프레임(110, 120)의 외면(114, 124)에 각각 체결된 제1 및 제2 고정부재(160, 170)는 거푸집 내에 장착된 철근과 체결된다. First, before the concrete is poured, the first and second fixing frames 110 and 120 are installed in a formwork (not shown). At this time, the first and second fixing members 160 and 170 fastened to the outer surfaces 114 and 124 of the first and second fixing frames 110 and 120, respectively, are fastened to the rebar mounted in the formwork.

이러한 제1 및 제2 고정부재(160, 170)는 제1 및 제2 고정프레임(110, 120)에 일부가 용접체결된 후 절곡시키지 않은 상태로 이송한 다음, 슬래브 내부에 설치하기 위해 거푸집 내에 제1 및 제2 고정프레임(110, 120)을 설치한 후 절곡시켜 설치한다. 물론, 시공시 제1 및 제2 고정부재(160, 170)의 양측 날개의 각도를 조절하여 체결할 수 있다. The first and second fixing members 160 and 170 are transferred to the first and second fixing frames 110 and 120 without bending after being partially welded to the first and second fixing frames 110 and 120, and then installed in the formwork to be installed inside the slab. The first and second fixing frames 110 and 120 are installed and then bent. Of course, it can be fastened by adjusting the angle of the wings of both sides of the first and second fixing members (160, 170) during construction.

이후, 제1 및 제2 고정부재(160, 170)와 제1 및 제2 고정프레임(110, 120)의 일부는 콘크리트 타설에 의해 슬래브와 함께 고정된다. 이때, 콘크리트 타설은 제1 및 제2 고정프레임(110, 120)의 상단절곡부(111, 121)의 외면에 보호부재(190)가 부착된 상태에서 실시하며, 콘크리트 타설이 끝난 후 보호부재(190)는 제거될 수 있다. Thereafter, a portion of the first and second fixing members 160 and 170 and the first and second fixing frames 110 and 120 are fixed together with the slab by pouring the concrete. At this time, the concrete pouring is performed in a state in which the protection member 190 is attached to the outer surfaces of the upper bent portions 111 and 121 of the first and second fixing frames 110 and 120, and after the concrete is finished, the protection member ( 190 may be removed.

슬래브에 제1 및 제2 고정프레임(110, 120)이 고정 설치된 상태에서 도 2 및 도 3에 도시된 바와 같이 이물질받이부재(130)의 제1 및 제2 절곡부(131, 132)를 제1 및 제2 고정프레임(110, 120)의 내부에 끼워 조립 설치한다. 이때, 이물질받이부재(130)를 상호 압축시킨 상태로 제1 및 제2 고정프레임(110, 120) 사이로 삽입시킨다. 이후, 압축되었던 이물질받이부재(130)가 탄성에 의해 원상복귀되는 과정에서 제1 및 제2 고정프레임(110, 120) 내부로 제1 및 제2 절곡부(131, 132)가 조립 설치된다. As shown in FIGS. 2 and 3, the first and second bent parts 131 and 132 of the foreign matter receiving member 130 are removed while the first and second fixing frames 110 and 120 are fixed to the slab. Assemble and install inside the first and second fixing frames (110, 120). At this time, the foreign matter receiving member 130 is inserted between the first and second fixing frames (110, 120) in a state of mutual compression. Thereafter, the first and second bent parts 131 and 132 are assembled into the first and second fixing frames 110 and 120 in the process of returning the compressed foreign matter receiving member 130 to its original shape by elasticity.

그런 다음, 제1 및 제2 이물질안내부재(140, 150)를 사선방향으로 제1 및 제2 고정프레임(110, 120) 내부에 끼운 후 이물질받이부재(130)의 체결돌기(133)를 제1 및 제2 이물질안내부재(140, 150)의 체결공(141, 151)을 관통하도록 삽입시킨다. 이후, 체결공(141, 151)을 관통하여 돌출된 체결돌기(133)에 와셔(180)를 체결한다. Then, the first and second foreign matter guide members 140 and 150 are inserted into the first and second fixing frames 110 and 120 in an oblique direction, and then the fastening protrusion 133 of the foreign matter receiving member 130 is removed. The first and second foreign matter guide members 140 and 150 are inserted through the fastening holes 141 and 151. Thereafter, the washer 180 is fastened to the fastening protrusion 133 protruding from the fastening holes 141 and 151.

신축이음장치의 분해는, 상기에서 설명한 방법과 반대 순서로 진행하면 된다. 즉, 와셔(180)를 제거하여 제1 및 제2 이물질안내부재(140, 150)를 분해한 후 이물질받이부재(130)에 압력을 가하여 제1 및 제2 고정프레임(110, 120)으로부터 이탈시킨다. Disassembly of the expansion joint may be performed in the reverse order to the method described above. That is, the washer 180 is removed to disassemble the first and second foreign matter guide members 140 and 150, and then the pressure is applied to the foreign substance receiving member 130 to separate from the first and second fixed frames 110 and 120. Let's do it.

이상에서 설명한 바와 같이, 본 발명의 기술적 사상은 바람직한 실시예에서 구체적으로 기술되었으나, 이러한 실시예는 그 설명을 위한 것이며, 그 제한을 위한 것이 아님을 주의하여야 한다. 이처럼 이 기술 분야의 통상의 전문가라면 본 발명의 기술 사상의 범위 내에서 실시예의 결합을 통해 다양한 실시예들이 가능함을 이해할 수 있을 것이다. As described above, although the technical spirit of the present invention has been described in detail in the preferred embodiments, it should be noted that such embodiments are for the purpose of description and not of limitation. As such, those skilled in the art may understand that various embodiments are possible through the combination of embodiments within the scope of the technical idea of the present invention.

110 : 제1 고정프레임 120 : 제2 고정프레임
111, 121 : 상단절곡부 112, 122 : 하단절곡부
113, 123 : 내면 114, 124 : 외면
130 : 이물질받이부재 131 : 제1 절곡부
132 : 제2 절곡부 133 : 체결돌기
141, 151 : 체결공 140 : 제1 이물질안내부재
150 : 제2 이물질안내부재 160 : 제1 고정부재
170 : 제2 고정부재 180 : 와셔
181 : 체결공 182 : 돌기
190 : 보호부재
110: first fixed frame 120: second fixed frame
111, 121: upper bend 112, 122: lower bent
113, 123: Inside 114, 124: Outside
130: foreign matter receiving member 131: first bent portion
132: second bent portion 133: fastening protrusion
141, 151: fastening hole 140: first foreign matter guide member
150: second foreign matter guide member 160: first fixing member
170: second fixing member 180: washer
181: fastener 182: protrusion
190: protective member

Claims (7)

인접한 본선 궤도부 또는 인접한 슬래브에 각각 고정 설치되고, 일측 상하단에는 서로 대향하도록 절곡된 상단절곡부와 하단절곡부를 구비하며, 상기 상단절곡부는 상기 하단절곡부보다 내면에 더 근접하게 형성되어 있는 제1 및 제2 고정프레임;
양측에 각각 형성된 제1 및 제2 절곡부를 구비하고, 상기 제1 절곡부는 상기 제1 고정프레임의 하단절곡부의 안쪽에 끼워지고, 상기 제2 절곡부는 상기 제2 고정프레임의 하단절곡부의 안쪽에 끼워져 상기 본선 궤도부 또는 상기 슬래브의 변위를 수용하도록 신축성을 가지며 빗물을 포함하는 이물질들을 받아 일측으로 배출하는 이물질받이부재; 및
상기 제1 및 제2 고정프레임의 내면의 상부 모서리 부위로부터 각각 사선방향으로 상기 이물질받이부재의 일부를 덮도록 연장되어 설치되고, 일측부가 상기 이물질받이부재와 체결되어 상기 제1 및 제2 고정프레임 내부로 각각 유입되는 상기 빗물을 포함하는 이물질들을 상기 이물질받이부재로 유도하는 제1 및 제2 이물질안내부재를 포함하는 교량용 물받이 겸용 신축이음장치.
A first bent part and a bottom bent part which are respectively fixed to an adjacent main track part or an adjacent slab, and are bent so as to face each other, and the upper bent part is formed closer to the inner surface than the lower bent part. And a second fixed frame;
First and second bent portions respectively formed on both sides, the first bent portion is fitted inside the bottom bent portion of the first fixed frame, and the second bent portion is fitted inside the bottom bent portion of the second fixed frame. A foreign matter receiving member which is elastic to accommodate displacement of the main track or the slab and receives foreign substances including rainwater and discharges them to one side; And
The first and second fixing frame is installed to extend to cover a part of the foreign matter receiving member in an oblique direction from the upper edge portion of the inner surface, respectively, one side is fastened to the foreign matter receiving member and the first and second fixing frame Combined expansion and reception device for a bridge including a first and a second foreign matter guide member for inducing foreign matter including the rainwater respectively introduced into the foreign matter receiving member.
제 1 항에 있어서,
상기 제1 및 제2 고정프레임의 외면에 각각 체결되고, 중앙부가 상기 제1 및 제2 고정프레임의 외면에 용접 체결되며, 용접처리된 중앙부를 축으로 양측이 상기 제1 및 제2 고정프레임의 외면으로부터 멀어지는 방향으로 절곡되어 상기 중앙부로부터 펼쳐진 날개 구조를 가지며, 상기 제1 및 제2 고정프레임를 상기 본선 궤도부 또는 상기 슬래브에 고정하는 제1 및 제2 고정부재를 더 포함하는 교량용 물받이 겸용 신축이음장치.
The method of claim 1,
It is fastened to the outer surface of the first and second fixed frame, respectively, the central portion is welded to the outer surface of the first and second fixed frame, both sides of the welded center portion on the axis of the first and second fixed frame Flexural extension for bridges having a wing structure bent in a direction away from the outer surface and extending from the center portion, further comprising first and second fixing members for fixing the first and second fixing frames to the main track or the slab. Joints.
제 2 항에 있어서,
상기 제1 및 제2 고정부재는 각각 양측부가 상기 제1 및 제2 고정프레임의 길이방향 또는 폭방향으로 설치되며, 상기 중앙부를 축으로 상기 제1 및 제2 고정프레임의 외면으로부터 일정 각도로 절곡되며, 상기 각도는 시공자에 의해 조정되는 교량용 물받이 겸용 신축이음장치.
The method of claim 2,
Both sides of the first and second fixing members are installed in the longitudinal direction or the width direction of the first and second fixing frames, respectively, and are bent at an angle from the outer surfaces of the first and second fixing frames about the central portion. And, the angle is the expansion joint device for the drip tray for the bridge is adjusted by the contractor.
제 1 항에 있어서,
상기 제1 및 제2 이물질안내부재는 각각 일측부가 와셔(washer)를 통해 상기 이물질받이부재로부터 돌출된 체결돌기에 의해 체결되도록 체결공이 마련된 교량용 물받이 겸용 신축이음장치.
The method of claim 1,
The first and the second foreign matter guide member, each of the two sides of the expansion joint for the expansion joint is provided with a fastening hole to be fastened by a fastening protrusion protruding from the foreign matter receiving member through a washer (washer).
제 1 항에 있어서,
상기 와셔는 중앙부에 체결공이 마련되고, 상기 체결돌기가 삽입되어 체결되도록 상기 체결공을 둘러싸는 복수 개의 돌기가 형성된 교량용 물받이 겸용 신축이음장치.
The method of claim 1,
The washer is provided with a fastening hole in the center portion, the expansion joint device for a drip tray for the bridge formed with a plurality of projections surrounding the fastening hole so that the fastening projection is inserted and fastened.
제 1 항에 있어서,
상기 제1 및 제2 이물질안내부재는 각각 상기 제1 및 제2 고정프레임의 길이방향으로 연장된 판형 구조를 가지며, 상기 제1 및 제2 고정프레임의 하단절곡부에 대응되는 부위에 상기 이물질받이부재 방향으로 절곡된 절곡부를 갖는 교량용 물받이 겸용 신축이음장치.
The method of claim 1,
The first and second foreign matter guide member has a plate-like structure extending in the longitudinal direction of the first and second fixed frame, respectively, the foreign matter receiving portion in the portion corresponding to the lower bent portion of the first and second fixed frame Extension and expansion joints for bridges having a bent portion bent in the direction of the member.
제 1 항에 있어서,
상기 슬래브를 형성하기 위한 콘크리트 타설 전에 상기 하단절곡부와 동일 선상에 위치되도록 상기 상단절곡부의 외면에 부착된 후 상기 콘크리트 타설 후 제거되는 보호부재를 더 포함하는 교량용 물받이 겸용 신축이음장치.
The method of claim 1,
And an additional expansion joint for a bridge gutter, including a protective member attached to an outer surface of the upper bent portion to be positioned in the same line as the lower bent portion before the concrete is poured to form the slab, and then removed after the concrete is poured.
KR1020110044378A 2011-05-12 2011-05-12 A bridge structure water spout combined expansion joint apparatus KR20110066904A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110044378A KR20110066904A (en) 2011-05-12 2011-05-12 A bridge structure water spout combined expansion joint apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110044378A KR20110066904A (en) 2011-05-12 2011-05-12 A bridge structure water spout combined expansion joint apparatus

Publications (1)

Publication Number Publication Date
KR20110066904A true KR20110066904A (en) 2011-06-17

Family

ID=44399610

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110044378A KR20110066904A (en) 2011-05-12 2011-05-12 A bridge structure water spout combined expansion joint apparatus

Country Status (1)

Country Link
KR (1) KR20110066904A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20160008037A (en) 2014-07-11 2016-01-21 충남대학교산학협력단 Expansion Joint Combined Water Spout Apparatus
KR101654173B1 (en) 2016-01-12 2016-09-09 유한회사 평화스테인레스 Water Draining Device for Expansion Joint of Bridge

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20160008037A (en) 2014-07-11 2016-01-21 충남대학교산학협력단 Expansion Joint Combined Water Spout Apparatus
KR101654173B1 (en) 2016-01-12 2016-09-09 유한회사 평화스테인레스 Water Draining Device for Expansion Joint of Bridge

Similar Documents

Publication Publication Date Title
KR101203978B1 (en) upper structure of bridge
KR101084736B1 (en) A shear connector which install the position-fixing device, a girder with that connector, and the method of slab construction using it all
KR101635868B1 (en) Hanger type bridge drainpipe structure and construction method
KR101433064B1 (en) Composite beam using steel plate beam and tendon and the construction method therefor
KR101551451B1 (en) Steel plate girder improved coner fixing capacity and rahmen or box type structure construction method using the same
KR101028507B1 (en) Expansion joint without reinforced concrete for a bridge structure and construction method thereof
KR100838409B1 (en) Deck plate
RU2544186C2 (en) Device for strapping of deformation joints, shaped structure and method for obtaining joint profiles
KR101977651B1 (en) Expansion joint for bridge
KR102054709B1 (en) Extension sidewalk
KR20110066904A (en) A bridge structure water spout combined expansion joint apparatus
DK201670572A1 (en) A connector element for use in a flashing assembly for roof windows mounted side-by-side and a connector set including such a connector element
KR101160763B1 (en) Composite beam using deck plate having plulality of cap plate
KR101839135B1 (en) Method for constructing expansion joint for bridge
KR101105404B1 (en) Deck plate system using cap plate
CN103669592B (en) Bending resistance parts and beam-column connection
KR101829791B1 (en) Bridge structure and construction method thereof
KR101414801B1 (en) Composite girder
KR101571887B1 (en) Expansion joint for connecting slabs of a bridge structure
KR101721043B1 (en) Suspended-type bridge joint apparatus and a method for installing the same
KR100225536B1 (en) Expansion joint and its execution method
JP2019148156A (en) Drain ditch unit and construction method thereof
CN213013896U (en) Expansion joint device for bridge construction
KR102133079B1 (en) Structure of column and flat plate slab
KR100778139B1 (en) Frame for length adjustment in horizontal prop of mold

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application