KR20100029673A - Split construction pipe for main building and non-excavation pipe laying method using the same - Google Patents

Split construction pipe for main building and non-excavation pipe laying method using the same Download PDF

Info

Publication number
KR20100029673A
KR20100029673A KR1020080096400A KR20080096400A KR20100029673A KR 20100029673 A KR20100029673 A KR 20100029673A KR 1020080096400 A KR1020080096400 A KR 1020080096400A KR 20080096400 A KR20080096400 A KR 20080096400A KR 20100029673 A KR20100029673 A KR 20100029673A
Authority
KR
South Korea
Prior art keywords
pipe
split
split construction
main building
construction
Prior art date
Application number
KR1020080096400A
Other languages
Korean (ko)
Inventor
김태성
Original Assignee
김태성
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김태성 filed Critical 김태성
Publication of KR20100029673A publication Critical patent/KR20100029673A/en

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground
    • F16L1/036Laying or reclaiming pipes on land, e.g. above the ground in the ground the pipes being composed of sections of short length
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L9/00Rigid pipes
    • F16L9/22Pipes composed of a plurality of segments

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention relates to a split construction pipe for the main building and a non-excavation pipe laying method using the same, more specifically, to solve the problems that conventional steel pipe indentation or propulsion methods have an external cylindrical indentation or propulsion steel pipe or The construction process is to reduce construction costs and improve construction by replacing the concrete pipe with a split construction pipe for the purchase of the main building, which requires less material and construction costs within the structurally stable range, and constructing an unexcavated pipeline laying method using the same.

Description

Split construction pipe for main building and non-excavation pipe laying method using the same

The present invention relates to a split construction pipe for the main building to be applied to the water pipe, sewage pipe, waterway, electric power, communication, gas pipe and tunnel, and a non-excavated pipe laying method using the same.

In the conventional steel pipe indentation or propulsion applied to water pipes, sewer pipes, waterways and tunnels, the outer surface coating of steel pipes is damaged by friction with the ground, and primarily presses or injects tubular steel or concrete pipes of larger diameter than steel pipes. After propulsion, the main pipe including the steel pipe having a smaller diameter than the steel pipe or the concrete pipe is inserted into the inside of the steel pipe or the concrete pipe, and then press-fill the pipe by filling the gap space between the main pipe and the external indentation or propulsion steel pipe or concrete pipe with mortar. Alternatively, by pushing, the material cost of the external indentation or propulsion steel pipes or concrete pipes and the related construction costs are excessively consumed.

When the above-mentioned point is described in more detail, in the case of the conventional cylindrical steel pipe indentation or propulsion, in the case of the external indentation or propulsion steel pipe or concrete pipe, the gap space of the outer surface of the main pipe including the steel pipe is filled with mortar only in the construction process. As long as the stability is maintained, the use of expensive cylindrical steel pipes or concrete pipes of a conventional permanently stable structure is a kind of excessive planning or design, and consequently, excessive construction costs are required, resulting in cylindrical steel pipes or concrete pipes. As a result, the propulsion force gradually increased from the time of construction is accompanied, and even when propelling a long distance, the tip of the tubular steel or concrete pipe is damaged or the frictional force between the surrounding ground and the tubular steel or concrete pipe is Relatively increased by increasing Since the true distance is shortened, there was a problem that the workability is reduced.

In order to solve the problems of conventional steel pipe indentation or propulsion methods, the main pipe embedding temporary construction pipe and non-excavation pipe laying method using the same are structural in the process of constructing a cylindrical or concrete tube for external indentation or propulsion. The purpose is to reduce the construction cost and improve the constructability by substituting the split construction pipe for the purchase of the main building using the split construction pipe that requires less material and construction costs within the stable range and constructing a non-excavation pipe laying method using the construction.

As the first embodiment of the present invention, the split construction pipe for embedding main building is characterized in that the split construction pipe is divided into a predetermined quantity in the transverse direction with respect to the traveling direction of the pipeline, and the filling port provided in the split construction pipe.

Further, as a second embodiment, a linear reinforcement portion provided to protrude on either the outer surface, the inner surface of the split temporary pipe of the first embodiment, or on both sides including the outer surface and the inner surface, and the linear reinforcement portion has a predetermined interval at right angles. It is characterized in that it is configured to further include a linear force booster installed to protrude.

On the other hand, the third embodiment is characterized in that the reinforcement is further included in the split temporary pipe or the linear reinforcement in any one of the first embodiment or the second embodiment.

In addition, the non-excavation pipe laying method using the split construction pipe for the purchase of the main building is a step of drilling the pipe, the step of installing a split construction pipe in the pipe pipe excavated after the process, and the back of the split construction pipe after the process It is characterized in that it comprises a step of filling the filler, a step of inserting the main pipe into the split construction pipe after the step, and a step of filling the gap filler between the split construction pipe and the main pipe after the process.

In order to solve the problems of conventional steel pipe indentation or propulsion methods, the main pipe embedding temporary construction pipe and non-excavation pipe laying method using the same are structural in the process of constructing a cylindrical or concrete tube for external indentation or propulsion. The construction cost can be reduced and construction performance can be improved by substituting a split construction pipe for the main building purchase using a split construction pipe that requires less material and construction costs within a stable range and constructing an unexcavated pipeline laying method using the construction.

Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.

The split construction pipe 7 for main building purchase of the present invention is a split construction pipe 9 divided into a predetermined quantity in the transverse direction with respect to the traveling direction of the pipeline as shown in FIGS. 1 to 4 and 8 as the first embodiment. ) And the filling port 10 installed in the split temporary pipe 9.

Here, the shape of the divided temporary pipe (9) has a predetermined width and thickness and is divided into a predetermined quantity in the transverse direction with respect to the advancing direction of the pipeline, the material of the divided temporary pipe (9) is concrete, steel, plastic, It is preferable to use elastic structural materials including waste plastics and FRP.

On the other hand, each joint 15 of the divided temporary pipe (9) is fastened to the binding hole 17, the binding hole 17 is a hollow binding to the inner end of each of the divided temporary pipe (9) The space portion 19 is installed, and the binding space portion 19 is provided with a binding member 21 of a bolt or rod-shaped material to bind the divided temporary pipes 9 on both sides, and the binding member 21 is installed. Afterwards, the binding space 19 was configured to be filled with a space filler 22 containing a conventional mortar.

In addition, as the second embodiment, the split construction pipe 9 of the first embodiment further includes a linear reinforcement 23 at a predetermined interval on the outer surface of the split construction pipe 9 as shown in FIGS. 5 and 9. 6 or 10, or further including a linear reinforcement 23 ′ at predetermined intervals on the inner surface of the split temporary pipe 9, or as shown in FIGS. 7 and 11. The linear reinforcement parts 23 and 23 'and the linear reinforcement parts 23 and 23' which are installed to protrude at predetermined intervals on both sides including the outer surface and the inner surface of the pipe 9 are spaced at right angles, respectively. It is characterized in that it is configured to further include a linear force booster (27, 27 ') provided to protrude.

Here, the material of the linear reinforcing portion (23, 23 ') or the linear backing portion (27, 27') is made of concrete, steel, plastic, waste plastic, FRP (FRP) like the material of the split construction pipe (9) It is preferable to use an elastic structural material containing.

On the other hand, in the third embodiment, in any one of the first embodiment or the second embodiment, the split construction pipe 9 belonging to the tension side from the neutral axis on the basis of the site installation of the split construction pipe 7 for main tube embedding, or In the linear reinforcement 23 and 23 ′, a reinforcement 31, 31 ′ including the reinforcing wire including the wire mesh, the perforated plate or the metal lath, the reinforcing plate including the iron plate, the reinforcing wire or the reinforcing rod, is included. It is characterized by being configured to further include.

On the other hand, the non-excavation pipe laying method using the split construction pipe for the main building is a step of drilling the pipeline using a conventional pipe excavation device (5) through a vertical sphere (3) installed on a part of the ground (1), The step of installing a predetermined amount of split temporary pipe (9) in the pipe line excavated after the step, and the cement paste, mortar or grout material through the filling hole 10 on the back of the split temporary pipe (9) after the process A process of filling the back filler material 12, a step of inserting the main pipe 11 into the split temporary pipe 9 after the step, and a mortar between the split temporary pipe 9 and the main pipe 11 after the step. Or it is characterized by consisting of a process for filling the gap filler 13 comprising a grout material.

Here, the split temporary pipe (9) and the back filler (12) filled in the back of the split temporary pipe (9) acts as a composite pipe, characterized in that configured to increase the external pressure strength to withstand the earth pressure of the ground (1) There is this.

1 is a conceptual view of the construction of the non-excavation pipe laying method using the split construction pipe for the main building purchase of the present invention.

2 is a cross-sectional view according to A-A of FIG.

FIG. 3 is an enlarged view of B of FIG. 2 and a sectional view of the first embodiment; FIG.

4 is an enlarged view of FIG. 2C.

5 is an enlarged sectional view of the second embodiment of FIG.

6 is an enlarged cross sectional view of the third embodiment of FIG. 3;

7 is an enlarged cross-sectional view of the fourth embodiment of FIG.

8 is a cross-sectional view of D-D of FIG. 3.

9 is a cross-sectional view of F-F of FIG. 5.

10 is a cross-sectional view of G-G of FIG. 6.

FIG. 11 is a cross-sectional view of H-H of FIG. 7. FIG.

12 is a conceptual diagram further comprising a reinforcement for the case of the embodiment of FIG.

FIG. 13 is an enlarged view of E in FIG. 4. FIG.

14 is a process chart related to the non-excavation pipeline laying method using the split construction pipe for the main building embedded of the present invention.

Claims (4)

The present invention is a temporary pipe that is applied to the water pipe, sewage pipe, waterway, power port, communication port, gas pipe and tunnel, A divided temporary pipe divided into a predetermined quantity in the transverse direction with respect to the advancing direction of the pipeline; Split construction pipe for the main building buy, characterized in that consisting of the filling port installed in the split construction pipe. The method of claim 1, A linear reinforcement part installed to protrude on any one of an outer surface, an inner surface, or an outer surface and an inner surface of the divided temporary pipe; And the linear reinforcement unit further comprises a linear force unit installed to protrude at predetermined intervals in a direction perpendicular to the linear reinforcement unit. The method according to any one of claims 1 to 2, The split construction pipe for the main building embedded, characterized in that it further comprises a reinforcement in the split construction pipe or linear reinforcement. The present invention is a non-excavation pipe laying method applied to water pipes, sewer pipes, waterways, electric power, communication, gas pipes and tunnels, Process of drilling pipelines, A step of installing a split temporary pipe in the pipeline which is excavated after the step; After filling the back filler on the back of the split construction pipe after the step, Inserting the main building into the split construction pipe after the step; Non-excavation pipe laying method using a split construction pipe for the main building embedded, characterized in that the process is filled with a gap filler between the split construction pipe and the main pipe after the process.
KR1020080096400A 2008-09-08 2008-10-01 Split construction pipe for main building and non-excavation pipe laying method using the same KR20100029673A (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR1020080088008 2008-09-08
KR20080088008 2008-09-08

Publications (1)

Publication Number Publication Date
KR20100029673A true KR20100029673A (en) 2010-03-17

Family

ID=42179862

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080096400A KR20100029673A (en) 2008-09-08 2008-10-01 Split construction pipe for main building and non-excavation pipe laying method using the same

Country Status (1)

Country Link
KR (1) KR20100029673A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101325224B1 (en) * 2011-09-20 2013-11-04 코오롱글로벌 주식회사 Repair method for pipeline
KR101944262B1 (en) 2018-09-12 2019-01-30 주식회사 강물 Simultaneous propulsion construction method using double pipe

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101325224B1 (en) * 2011-09-20 2013-11-04 코오롱글로벌 주식회사 Repair method for pipeline
KR101944262B1 (en) 2018-09-12 2019-01-30 주식회사 강물 Simultaneous propulsion construction method using double pipe

Similar Documents

Publication Publication Date Title
KR100973770B1 (en) Non-excavation type constructed tunnels and conduits using arc-shaped divided segments and its construccting methods thereof
JP4757959B2 (en) Steel sheet pile wall and its construction method
CN101575859B (en) Anti-seepage joint of underground continuous walls and construction method thereof
CN206157786U (en) Compound muscle material anti -floating anchor rod structure of basalt
KR101029311B1 (en) Non-excavation laying method for pipeline and tunnel using temporary composite pipe
KR101066612B1 (en) Composite shell pile having waterstop and waterproof method for secant pile wall using the same
KR100971147B1 (en) Reinforce unit for grouting and soil nailing reinforce method using the same
KR20100029673A (en) Split construction pipe for main building and non-excavation pipe laying method using the same
CN210380191U (en) Lightweight power communication combination prefabricated cable channel
CN100494630C (en) Method for quickly constructing water gate wall under high pressure surging water in soft coal tunnel
KR101013627B1 (en) Roof of underground structure and method for constructing the same
KR200407437Y1 (en) Construction establishment method and the structure for underground tunnel formation
CN214741347U (en) Be used for hydraulic shield to construct building structure and strengthen fixing device
CN104652420A (en) Sinking pipe soil withdrawing and cast-in-place rectangular supporting pile diaphragm wall and construction method thereof
JP4705468B2 (en) Drainage pipe with deterrent function
KR200392163Y1 (en) Soil Nailing Device For Tension Reinforcement
US20180291582A1 (en) Anchor having fixing device at side of pressure plate to depress land slope and method of installing same
KR100776620B1 (en) Bar Type Anchor
CN204098067U (en) Side's culvert formula underground pipe gallery
KR100751969B1 (en) construction method of drain pipe
KR20100010044A (en) A reinforced divice for grouting pipe therefor method
KR100358577B1 (en) Polyethylene spiral double-wall tube
KR101068626B1 (en) Undrilled laying method for pipeline and tunnel using complex excavator
KR101040849B1 (en) A spacer for reinforcing pipeline and reinforced method of construction of pipeline using it
JP2001140592A (en) Tunnel lining segment and its construction method

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application