KR20100007062A - Form for steel-concrete composite slab of bridge - Google Patents

Form for steel-concrete composite slab of bridge Download PDF

Info

Publication number
KR20100007062A
KR20100007062A KR1020080067496A KR20080067496A KR20100007062A KR 20100007062 A KR20100007062 A KR 20100007062A KR 1020080067496 A KR1020080067496 A KR 1020080067496A KR 20080067496 A KR20080067496 A KR 20080067496A KR 20100007062 A KR20100007062 A KR 20100007062A
Authority
KR
South Korea
Prior art keywords
plate
corrugated strip
formwork
corrugated
concrete composite
Prior art date
Application number
KR1020080067496A
Other languages
Korean (ko)
Inventor
박종면
김선주
김성곤
Original Assignee
(주)지승컨설턴트
서울산업대학교 산학협력단
주식회사 노빌테크
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)지승컨설턴트, 서울산업대학교 산학협력단, 주식회사 노빌테크 filed Critical (주)지승컨설턴트
Priority to KR1020080067496A priority Critical patent/KR20100007062A/en
Publication of KR20100007062A publication Critical patent/KR20100007062A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/268Composite concrete-metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE: A form for a steel-concrete composite slab is provided to improve constructability and to improve the resistance about working load when temporarily installing the form. CONSTITUTION: A form for a steel-concrete composite slab comprises a form panel(10), a wavy tie plate assembly(20), and a connector(30). The wavy tie plate assembly is connected to the top of the form panel and is composed of plural wavy tie plate units(210). The wavy tie plate unit is composed of a pair of wavy tie plates(211). The wavy tie plate assembly and the from panel are connected each other by the connector.

Description

강콘크리트 합성 교량 바닥판용 거푸집{Form for steel-concrete composite slab of bridge}Form for steel-concrete composite slab of bridge

본 발명은 교량 바닥판용 거푸집에 관한 것으로, 보다 상세하게는 시공성과 가설시 작업하중에 대한 저항성이 향상된 강콘크리트 합성 교량 바닥판용 거푸집에 관한 것이다.The present invention relates to a formwork for bridge deck, and more particularly to a formwork for steel concrete composite bridge deck is improved construction and resistance to work load during construction.

교량이란 도로·철도 등의 운송로상의 장애 또는 방해가 되는 계곡, 호수, 해안, 해협 등을 건너거나 다른 철도, 도로, 수로, 가옥, 시가지 등을 통과할 목적으로 가설되는 구조물을 총칭하는 것으로 정의할 수 있다. 교량은 일반적으로 상부구조와 하부구조로 구성되어 있다. 상부구조는 자동차나 보행자 등을 직접 지지하는 부분을 말하고 하부구조는 상부구조를 지지하는 부분을 말한다. 상부구조를 구성하는 주요부분으로는 바닥판, 바닥틀(세로보와 가로보), 거더, 수평브레이싱, 수직브레이싱, 받침부 등이 있고 하부구조는 교대, 교각의 총칭으로 지상에 있는 부분을 구체, 지중에 묻혀있는 부분을 기초라 한다. A bridge is defined as a generic term for structures that are intended to cross valleys, lakes, shores, straits, or other railroads, roads, waterways, houses, towns, etc. that are obstructed or obstructed by roads and railways. can do. Bridges generally consist of a superstructure and a substructure. The upper structure refers to the portion directly supporting the car or pedestrian, and the lower structure refers to the portion supporting the upper structure. The main parts of the upper structure include bottom plate, floor frame (vertical beams and horizontal beams), girders, horizontal bracing, vertical bracing, and supporting parts, and the lower structure is a generic term for alternating and piers. It is based on the part buried in.

현재 교량 바닥판은 동바리를 받치고 그 위에 거푸집을 설치한 후 철근을 배근하고 콘크리트를 타설하는 현장타설 콘크리트 바닥판이 주로 적용되고 있다. 그 러나 이러한 현장타설 바닥판은 철근량이 많아 배근 작업에 시일이 많이 소요될 뿐만 아니라 많은 인력이 투입되는 노동집약적인 작업으로 공기 및 공사비 증가의 주요 원인이 되고 있다. 또한 바닥판 시공시 시공하중을 지지하기 위해 동바리의 사용이 필수적인데 교량의 설치장소에 따라서는 적용할 수 있는 동바리 시스템에 제한이 따를 수 있고 동바리 설치가 곤란한 경우가 발생할 수도 있다.Currently, bridge decks are supported by field casting concrete decks, which support copper bars, formwork on them, and reinforce rebars and cast concrete. However, such a cast-in-place floorboard has a large amount of rebar and it takes a lot of time for reinforcement work. In addition, the use of copper bars is essential to support the construction load during the construction of the bottom plate. Depending on the installation location of the bridge, there may be restrictions on the applicable copper bar system and the installation of copper bars may be difficult.

본 발명은 이러한 사정을 감안하여 안출된 것으로, 본 발명이 해결하고자 하는 과제는 시공성과 가설시 작업하중에 대한 저항성이 향상된 강콘크리트 합성 교량 바닥판용 거푸집을 제공하는 데 있다.The present invention has been made in view of the above circumstances, and an object of the present invention is to provide a formwork for steel concrete composite bridge deck plate with improved construction and resistance to work load during construction.

본 발명의 적절한 실시형태에 따르면, 거푸집 판과, 면에 수직한 방향으로 골과 마루가 연속적으로 반복 형성되도록 강재 띠판을 절곡 성형한 2개의 파형띠판의 골과 골이 서로 접합도록 결합한 파형띠판 단위체들을 결합하여 다수의 하니콤 셀 모양의 공간부가 형성되도록 조립된 파형띠판 조립체와, 적어도 2개의 파형띠판 단위체를 밀착 결합시키기 위한 채널과 채널에 의해 밀착 결합된 파형띠판 단위체를 거푸집 판에 고정시키기 위한 U자형 볼트와 U자형 볼트에 체결되는 너트로 이루어져 파형띠판 조립체를 거푸집 판에 고정시키기 위한 연결구를 포함하는 것을 특징으로 하는 강콘크리트 합성 교량 바닥판용 거푸집이 제공된다.According to a preferred embodiment of the present invention, the corrugated strip unit unit that combines the die and the corrugated board of the two corrugated strips formed by bending steel strips in a direction perpendicular to the plane to be continuously formed to be joined to each other. For fixing the corrugated strip plate assembly assembled to form a plurality of honeycomb cell-shaped spaces, and a channel for closely coupling the at least two corrugated strip unit units and the corrugated strip unit unit tightly coupled by the channel to the formwork plate. Formwork for the steel concrete composite bridge deck is provided comprising a connector for securing the corrugated strip plate assembly to the form plate consisting of a U-type bolt and a nut fastened to the U-shaped bolt.

본 발명의 다른 적절한 실시형태에 따르면, 전술한 실시형태에서 파형띠판에 는 다수 개의 관통공이 형성되어 있는 것을 특징으로 하는 강콘크리트 합성 교량 바닥판용 거푸집이 제공된다.According to another suitable embodiment of the present invention, there is provided a formwork for a steel concrete composite bridge deck, characterized in that a plurality of through holes are formed in the corrugated strip plate in the above-described embodiment.

본 발명의 거푸집에 따르면 교량 바닥판 콘크리트 타설을 위한 거푸집 기능과 함께 교량 바닥판 콘크리트와 일체로 합성되어 강콘크리트 합성 교량 바닥판을 구성할 수 있다.According to the formwork of the present invention can be combined with the bridge deck concrete with the formwork for the bridge deck concrete pouring can form a steel concrete composite bridge deck.

이하, 첨부된 도면을 참조하며 본 발명의 바람직한 실시 예를 상세히 설명하기로 한다. 도면들 중, 동일한 구성요소 또는 부품들은 가능한 한 동일한 참조부호를 표기하며, 관련된 공지기능 혹은 구성에 대한 구체적인 설명은 생략한다.Hereinafter, with reference to the accompanying drawings will be described in detail a preferred embodiment of the present invention. In the drawings, the same components or parts are denoted by the same reference numerals as much as possible, and detailed descriptions of related known functions or configurations are omitted.

도 1은 본 발명에 따른 강콘크리트 합성 교량 바닥판용 거푸집을 나타낸 분해사시도이고, 도 2는 파형띠판 단위체를 나타낸 사시도이다.1 is an exploded perspective view showing the formwork for the steel concrete composite bridge deck according to the present invention, Figure 2 is a perspective view showing a corrugated strip unit.

도 1을 참조하면, 본 발명에 따른 바닥판은 거푸집 판(10)과, 파형띠판 조립체(20)와, 파형띠판 조립체(20)를 거푸집 판(10)에 결합시키기 위한 연결구(30)로 이루어진다. Referring to FIG. 1, the bottom plate according to the present invention includes a formwork plate 10, a corrugated strip plate assembly 20, and a connector 30 for coupling the corrugated strip plate assembly 20 to the form plate 10. .

거푸집 판(10)은 현장타설되는 교량 바닥판 콘크리트가 경화되기까지 그 하중을 지지하는 부재로서 거더 위에 거치되며 콘크리트 경화 후에는 제거되는 가설부재이다. 거푸집 판(10)은 평평한 판재로서 인접하는 거더 사이의 거리에 대응되는 폭을 갖고 다수 개가 연결되어 거더 전체 길이에 대응될 수 있는 길이를 갖는다. 재질은 합판으로 구성하는 것이 경제적이나 이에 한정되지 않으며 자재의 입수 용이성, 전용성 등을 고려하여 강판 또는 합성수지판으로 구성될 수도 있다. 거푸집 판(10)에는 연결구(30)가 관통될 수 있도록 연결구(30)의 수에 대응되는 구멍(111)이 다수 개 천공되어 있다.Formwork plate 10 is a temporary member that is mounted on the girder as a member to support the load until the bridge deck concrete to be cast in the field is cured, and is removed after the concrete is hardened. Formwork plate 10 is a flat plate having a width corresponding to the distance between the adjacent girders and a plurality of connected to have a length that can correspond to the entire length of the girders. The material is economical to be composed of plywood, but is not limited thereto, and may be composed of a steel sheet or a synthetic resin in consideration of the availability of materials, exclusive use. The die plate 10 is provided with a plurality of holes 111 corresponding to the number of the connector 30 so that the connector 30 can be penetrated.

거푸집 판(10)의 상면에는 파형띠판 조립체(20)가 결합된다. 파형띠판 조립체(20)는 다수의 파형띠판 단위체(210)로 구성되며 각 파형띠판 단위체(210)는 한 쌍의 파형띠판(211)으로 구성된다. The corrugated strip plate assembly 20 is coupled to the upper surface of the form plate 10. The corrugated strip plate assembly 20 is composed of a plurality of corrugated strip plate units 210, and each corrugated strip plate unit 210 is composed of a pair of corrugated strip plates 211.

도 2를 참조하면, 파형띠판(211)은 면에 수직한 방향으로 골과 마루가 연속적으로 반복 형성되도록 강재 띠판(Steel strip)을 절곡 성형한 것이다. 파형띠판(211)은 냉간압연(Cold-rolling)으로 제조될 수 있으며 골의 형상은 도시된 “V"자형에 한정되지 않으며 둥근 형상으로 구성될 수도 있다. 파형띠판(211)에는 파형강판과 교량 바닥판 콘크리트 사이의 경계면에서 슬립이 일어나지 않고 이들이 일체로 합성될 수 있도록 다수 개의 관통공(212)을 형성하는 것이 바람직하다.Referring to FIG. 2, the corrugated strip 211 is formed by bending a steel strip to form a valley and a floor in a direction perpendicular to the plane. The corrugated strip plate 211 may be manufactured by cold rolling, and the shape of the valley is not limited to the “V” shape shown in the figure and may be formed in a round shape. The corrugated strip plate 211 has a corrugated steel sheet and a bridge. It is preferable to form a plurality of through holes 212 so that slip does not occur at the interface between the bottom plate concrete and they can be synthesized integrally.

파형띠판 단위체(210)는 이상과 같이 구성된 2개의 파형띠판(211)의 골과 골이 서로 접하도록 용접 또는 별도의 고정구를 이용하여 교호로 하니콤 셀 모양의 공간부(213)가 형성되도록 접합한 것이다. 이 공간부(213)에는 교량 바닥판 콘크리트가 채워지게 되는데 공간부(213)를 구획하는 파형띠판(211)에는 다수 개의 관통공(212)이 형성되어 있으므로 콘크리트가 관통공(212)에도 채워지게 되어 콘크리트가 경화된 후에는 마치 고리를 연결한 것과 같은 구조를 이루어 표면적이 큰 금속띠판을 보강재로 사용하는데 따른 단점을 해소할 수 있다.Corrugated strip plate unit 210 is joined to form a honeycomb cell-shaped space portion 213 alternately by using welding or separate fixtures so that the valleys and valleys of the two corrugated strip plates 211 configured as described above are in contact with each other. It is. Bridge space plate concrete is filled in the space portion 213. Since a plurality of through holes 212 are formed in the corrugated strip plate 211 partitioning the space portion 213, the concrete is also filled in the through holes 212. After the concrete is hardened, it is possible to solve the disadvantage of using a metal strip plate having a large surface area as a reinforcing material by forming a structure as if the rings are connected.

파형띠판 조립체(20)는 거푸집 판(10)의 전체 면을 덮도록 파형띠판 단위 체(210)들을 조립한 것이다. 파형띠판 단위체(210)들 간의 접합은 용접 또는 별도의 고정구를 이용할 수 있고 거푸집 판(10)에 결합시키기 위한 연결구(30)를 이용할 수도 있다. 파형띠판 조립체(20)는 교량 바닥판 철근을 대신하여 인장에 취약한 바닥판 콘크리트를 보강하는 역할을 하는데 위에서 살펴본 바와 같이 조립이 간편하여 철근을 배근하는 것에 비해 작업성이 뛰어나며 소수의 인원으로 작업이 가능하므로 공기단축 및 공사비 절감이 가능하다. 또한 파형강판 조립체(20)는 콘크리트 경화시까지 콘크리트의 자중을 지지할 뿐만 아니라 작업자 등 시공중 바닥판에 가해지는 하중을 지지하게 된다. 따라서 별도로 동바리로 지지할 필요가 없게 되거나 동바리의 수를 최소화할 수 있게 된다. 이러한 목적을 위해 파형띠판 조립체(20)가 거푸집 판(10)의 폭방향 단부보다 더 긴 길이를 갖도록 하여 파형띠판 조립체(20)의 양단부가 거푸집 판(10)으로부터 돌출되도록 함으로써 양단부가 거더 위에 거치될 수 있도록 하는 것이 바람직하다(도 3a 참조). 그리고 콘크리트 경화후 제거되는 거푸집 판(10)과 달리 콘크리트와 일체로 합성되어 일종의 강콘크리트 합성 바닥판을 구성한다. 이때 콘크리트와의 합성작용은 파형띠판(211)에 형성된 다수 개의 관통공(212)를 통해 달성된다. Corrugated strip plate assembly 20 is assembled by the corrugated strip plate unit body 210 to cover the entire surface of the form plate (10). Bonding between the corrugated strip plate unit 210 may use a welding or a separate fixture and may also use a connector 30 for coupling to the form plate 10. Corrugated strip plate assembly 20 serves to reinforce the bottom plate concrete vulnerable to tension in place of the bridge bottom plate reinforcement, as described above is easy to assemble and reinforce the reinforcement bar compared to the reinforcement and work with a small number of people As a result, it is possible to shorten the air and reduce construction costs. In addition, the corrugated steel sheet assembly 20 not only supports the weight of the concrete until the concrete hardening, but also supports the load applied to the bottom plate during construction such as an operator. Therefore, it is not necessary to separately support the grouping, or it is possible to minimize the number of groups. For this purpose, the corrugated strip plate assembly 20 has a length longer than the widthwise end of the form plate 10 so that both ends of the corrugated strip plate assembly 20 protrude from the form plate 10 so that both ends are mounted on the girder. It is desirable to be able to do so (see FIG. 3A). And unlike the formwork plate 10 that is removed after hardening concrete is synthesized integrally with the concrete to form a kind of steel concrete composite bottom plate. At this time, the synthesis with the concrete is achieved through a plurality of through holes 212 formed in the corrugated strip plate 211.

파형띠판 조립체(20)는 연결구(30)를 이용해 거푸집 판(10)에 고정된다. 연결구(30)는 적어도 2개의 파형띠판 단위체(210)를 밀착 결합시키기 위한 채널(310)과 채널(310)에 의해 밀착 결합된 파형띠판 단위체(210)를 거푸집 판(10)에 고정시키기 위한 U자형 볼트(320)와 U자형 볼트(320)에 체결되는 너트(330)로 구성된다. 채널(310)은 하니콤 셀 모양의 공간부(213)를 사이에 두고 면접된 파형띠판 단위 체(210)의 골 부분에 결합되며 따라서 2개의 파형띠판 단위체(210)에 의해 다시 하니콤 셀 모양의 공간부(213)가 형성되도록 파형띠판 단위체(210)를 서로 결합시킨다. 이와 같은 방식으로 다수의 파형띠판 단위체(210)를 조립함에 따라 파형띠판 조립체(20)를 구성하게 된다. U자형 볼트(320)는 채널(310)과 거푸집 판(10)을 순차적으로 관통한 후 단부에 너트(330)가 체결된다. 따라서 거푸집 판(10)은 너트(330)를 제거하면 교량 바닥판 콘크리트가 경화된 후 간단히 해체될 수 있다. Corrugated strip plate assembly 20 is fixed to formwork plate 10 using connector 30. The connector 30 has a channel 310 for tightly coupling the at least two corrugated strip unit units 210 and a U for fixing the corrugated strip unit unit 210 tightly coupled by the channel 310 to the form plate 10. The nut 330 is fastened to the female bolt 320 and the U-shaped bolt 320. The channel 310 is coupled to the valley portion of the corrugated strip plate unit 210 interviewed with the honeycomb cell-shaped space 213 interposed therebetween, and thus is formed again by the two corrugated strip unit units 210. The corrugated strip plate unit 210 is coupled to each other so that the space portion 213 is formed. By assembling the plurality of corrugated strip plate units 210 in this manner, the corrugated strip plate assembly 20 is configured. The U-shaped bolt 320 sequentially passes through the channel 310 and the formwork plate 10, and then the nut 330 is fastened to the end thereof. Therefore, the formwork plate 10 can be simply dismantled after the bridge deck concrete is hardened by removing the nut 330.

도 3a는 본 발명에 따른 강콘크리트 합성 교량 바닥판용 거푸집을 시공하는 모습을 보여주는 사시도이고, 도 3b는 본 발명에 따른 거푸집을 이용하여 강콘크리트 합성 교량 바닥판이 시공된 모습을 보여주는 단면도이다.Figure 3a is a perspective view showing the construction of the formwork for the steel concrete composite bridge deck according to the invention, Figure 3b is a cross-sectional view showing the construction of steel concrete composite bridge deck using the formwork according to the present invention.

본 발명에 따른 거푸집을 이용해 교량 바닥판을 시공하는 방법은, Method for constructing bridge deck using the formwork according to the invention,

먼저, 거푸집 판(10) 위에 다수 개의 파형띠판 단위체(210)를 배치하고 연결구(30)를 이용해 거푸집 판(10)에 고정하는 작업을 반복하여 거푸집 판(10)의 상면 전체에 파형띠판 조립체(20)를 배치하여 본 발명에 따른 거푸집을 완성한다. 거푸집은 공장에서 조립하여 현장에 반입할 수 있고 자재만 현장에 반입한 후 현장에서 거푸집 판(10)과 파형띠판 조립체(20)를 연결구(30)를 이용해 결합시켜 조립할 수도 있다. 이때, 파형띠판 조립체(20)가 거푸집 판(10)의 폭방향 단부보다 더 긴 길이를 갖도록 하여 파형띠판 조립체(20)의 양단부가 거푸집 판(10)으로부터 돌출되도록 하여 양단부가 거더(G) 위에 거치될 수 있도록 한다. First, a plurality of corrugated strip unit units 210 are disposed on the form plate 10, and the fixing plate 10 is repeatedly fixed to the form plate 10 by using the connector 30. 20) is arranged to complete the formwork according to the invention. The formwork may be assembled at the factory and brought into the site, and only the material may be brought into the site and then assembled by combining the formwork plate 10 and the corrugated strip plate assembly 20 using the connector 30 at the site. At this time, the corrugated strip plate assembly 20 has a length longer than the widthwise end of the form plate 10 so that both ends of the corrugated strip plate assembly 20 protrude from the form plate 10 so that both ends are placed on the girder G. Allow it to be mounted.

다음으로 준비된 거푸집을 거더(G) 위에 거치시킨다. 거더(G)는 현장타설에 의해 시공될 수도 있고 공장에서 미리 제작하여 현장에 반입할 수도 있다. 거푸집 설치가 완료되면 바닥판 상부철근(410)을 배근하고 콘크리트(420)를 타설한다. 그 후 콘크리트가 완전히 경화하여 소요 강도가 발현되면 거푸집 판(10)을 해체한다. 즉, 본 발명에 거푸집을 이루는 부재 중 거푸집 판(10)은 교량 바닥판 콘크리트 경화 후 제거되지만 파형띠판 조립체(20)는 콘크리트에 매설되어 교량 바닥판의 하부 철근을 대체하게 되고 콘크리트와 일체로 합성되어 강콘크리트 합성 바닥판을 구성하게 된다. Next, the prepared formwork is mounted on the girder (G). The girder (G) may be constructed by site casting or may be manufactured in the factory and brought to the site. When the formwork is completed, the bottom plate reinforcement 410 is placed and the concrete 420 is poured. After that, when the concrete is completely hardened and the required strength is expressed, the formwork plate 10 is dismantled. That is, in the present invention, the formwork plate 10 of the members forming the formwork is removed after curing the bridge deck concrete, but the corrugated strip plate assembly 20 is embedded in concrete to replace the lower reinforcement of the bridge deck and synthesized integrally with the concrete Thus, the steel concrete composite deck is constituted.

이상에서 본 발명을 예시한 도면을 참조로 하여 설명하였으나, 본 명세서에 개시된 실시 예와 도면에 의해 본 발명이 한정되는 것은 아니며, 본 발명의 기술사상의 범위 내에서 통상의 기술자에 의해 다양한 변형이 이루어질 수 있다.Although the present invention has been described above with reference to the drawings, the present invention is not limited to the embodiments and drawings disclosed herein, and various modifications may be made by those skilled in the art within the scope of the technical idea of the present invention. Can be done.

본 명세서에서 첨부되는 다음의 도면들은 본 발명의 바람직한 실시 예를 예시하는 것이며, 발명의 상세한 설명과 함께 본 발명의 기술사상을 더욱 이해시키는 역할을 하는 것이므로, 본 발명은 첨부한 도면에 기재된 사항에만 한정되어서 해석되어서는 아니된다.The following drawings, which are attached in this specification, illustrate the preferred embodiments of the present invention, and together with the detailed description thereof, serve to further understand the technical spirit of the present invention. It should not be construed as limited.

도 1은 본 발명에 따른 강콘크리트 합성 교량 바닥판용 거푸집을 나타낸 분해사시도이다. 1 is an exploded perspective view showing the formwork for steel concrete composite bridge deck according to the present invention.

도 2는 파형띠판 단위체를 나타낸 사시도이다.2 is a perspective view showing the corrugated strip plate unit.

도 3a는 본 발명에 따른 강콘크리트 합성 교량 바닥판용 거푸집을 시공하는 모습을 보여주는 사시도이다. Figure 3a is a perspective view showing the construction of formwork for steel concrete composite bridge deck according to the present invention.

도 3b는 본 발명에 따른 거푸집을 이용하여 강콘크리트 합성 교량 바닥판이 시공된 모습을 보여주는 단면도이다.Figure 3b is a cross-sectional view showing the construction of a steel concrete composite bridge deck using the formwork according to the present invention.

Claims (2)

거푸집 판과,Die plate, 면에 수직한 방향으로 골과 마루가 연속적으로 반복 형성되도록 강재 띠판을 절곡 성형한 2개의 파형띠판의 골과 골이 서로 접합도록 결합한 파형띠판 단위체들을 결합하여 다수의 하니콤 셀 모양의 공간부가 형성되도록 조립된 파형띠판 조립체와,Multiple honeycomb cell-shaped spaces are formed by combining the corrugated strip plate units combined with the corrugations of the corrugated board and the valleys of two corrugated strip plates formed by bending steel strips so that valleys and floors are continuously formed in a direction perpendicular to the plane. Corrugated strip plate assembly assembled to 적어도 2개의 파형띠판 단위체를 밀착 결합시키기 위한 채널과 채널에 의해 밀착 결합된 파형띠판 단위체를 거푸집 판에 고정시키기 위한 U자형 볼트와 U자형 볼트에 체결되는 너트로 이루어져 파형띠판 조립체를 거푸집 판에 고정시키기 위한 연결구를 포함하는 것을 특징으로 하는 강콘크리트 합성 교량 바닥판용 거푸집.Fixing the corrugated stripe assembly to the formwork plate consists of a channel for tightly joining the at least two corrugated strip unit and a nut fastened to the U-shaped bolt to secure the corrugated strip unit adhered by the channel to the form plate. Formwork for steel concrete composite bridge deck comprising a connector for making. 청구항 1에 있어서,The method according to claim 1, 파형띠판에는 다수 개의 관통공이 형성되어 있는 것을 특징으로 하는 강콘크리트 합성 교량 바닥판용 거푸집.Formwork for steel concrete composite bridge deck, characterized in that the corrugated strip plate is formed with a plurality of through holes.
KR1020080067496A 2008-07-11 2008-07-11 Form for steel-concrete composite slab of bridge KR20100007062A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080067496A KR20100007062A (en) 2008-07-11 2008-07-11 Form for steel-concrete composite slab of bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080067496A KR20100007062A (en) 2008-07-11 2008-07-11 Form for steel-concrete composite slab of bridge

Publications (1)

Publication Number Publication Date
KR20100007062A true KR20100007062A (en) 2010-01-22

Family

ID=41816107

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080067496A KR20100007062A (en) 2008-07-11 2008-07-11 Form for steel-concrete composite slab of bridge

Country Status (1)

Country Link
KR (1) KR20100007062A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108193597A (en) * 2018-03-13 2018-06-22 长沙慧桥科技有限公司 A kind of high-performance steel bridge floor structure
CN116732859A (en) * 2021-02-05 2023-09-12 成都蜂装钢构集团有限公司 Assembled elevated road and bridge mounting structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108193597A (en) * 2018-03-13 2018-06-22 长沙慧桥科技有限公司 A kind of high-performance steel bridge floor structure
CN116732859A (en) * 2021-02-05 2023-09-12 成都蜂装钢构集团有限公司 Assembled elevated road and bridge mounting structure

Similar Documents

Publication Publication Date Title
JP2002250009A (en) Steel-concrete composite beam using corrugated steel plate web
JP2006316580A (en) Corrugated steel plate web pc composite beam and construction method of bridge using corrugated steel plate web pc composite beam
KR20120033667A (en) Upper structure of bridge
RU2376408C2 (en) Tram way track arrangement and method of installation
KR100483083B1 (en) Composite Deck having Frame and Concrete
JP2004137686A (en) Composite panel structure, panel bridge structure and construction method for continuous composite girder bridge
KR101998822B1 (en) Composite rahmen bridge, steel girder for that and construction method of composite rahmen bridge
KR100963579B1 (en) Bar truss integrated deck-plate
JP2008088634A (en) Composite steel-concrete floor slab
KR20080093261A (en) Composite bridge construction method
JP4901178B2 (en) Steel / concrete composite rigid frame bridge construction method
JP4585614B1 (en) Method for constructing synthetic steel slab bridge, ribbed steel slab, and synthetic steel slab bridge
KR100621928B1 (en) Construction method of double composite plate girder railway bridge with precast concrete panels
KR20100007062A (en) Form for steel-concrete composite slab of bridge
KR20130090709A (en) Construction method for corrugated steel plate web-psc composite beam
KR20080107567A (en) Truss structure of a temporary bridge
JP3885583B2 (en) Composite truss bridge and its construction method
KR101010109B1 (en) Concrete filled composite lining board of assembly type
KR101272119B1 (en) PSC box girder of Propiled steel web for constructing bridge
KR100794444B1 (en) Construction Method of Composite Slab Bridge Using Composite Truss Girder
CN112281656A (en) Combined multi-span bridge plate connecting structure
KR20080004752U (en) Composite bridge
KR100962677B1 (en) Assembled bridge for constructing an assembled bridge
KR100503238B1 (en) railroad like steel girder
CN220099642U (en) Perforated steel grid-high-strength concrete cast-in-situ combined bridge deck

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application