KR20080005134U - Precast panel for construction of retaining wall - Google Patents

Precast panel for construction of retaining wall

Info

Publication number
KR20080005134U
KR20080005134U KR2020080001328U KR20080001328U KR20080005134U KR 20080005134 U KR20080005134 U KR 20080005134U KR 2020080001328 U KR2020080001328 U KR 2020080001328U KR 20080001328 U KR20080001328 U KR 20080001328U KR 20080005134 U KR20080005134 U KR 20080005134U
Authority
KR
South Korea
Prior art keywords
retaining wall
panel
drain groove
precast panel
panel body
Prior art date
Application number
KR2020080001328U
Other languages
Korean (ko)
Inventor
성낙영
Original Assignee
주식회사 팸택
성낙영
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 팸택, 성낙영 filed Critical 주식회사 팸택
Priority to KR2020080001328U priority Critical patent/KR20080005134U/en
Publication of KR20080005134U publication Critical patent/KR20080005134U/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/70Drying or keeping dry, e.g. by air vents
    • E04B1/7038Evacuating water from cavity walls, e.g. by using weep holes
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • E04B2/04Walls having neither cavities between, nor in, the solid elements
    • E04B2/06Walls having neither cavities between, nor in, the solid elements using elements having specially-designed means for stabilising the position
    • E04B2/08Walls having neither cavities between, nor in, the solid elements using elements having specially-designed means for stabilising the position by interlocking of projections or inserts with indentations, e.g. of tongues, grooves, dovetails

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Paleontology (AREA)
  • Physics & Mathematics (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Electromagnetism (AREA)
  • Environmental & Geological Engineering (AREA)
  • Retaining Walls (AREA)

Abstract

본 고안은, 절토 사면에 매설된 지중 보강재들 상에 상하좌우로 조립 및 설치되어 옹벽을 형성하되, 배수가 용이하게 수행되도록 하는 옹벽 시공용 조립식 프리캐스트 패널에 관한 것이다.The present invention relates to a prefabricated precast panel for retaining wall construction, which is assembled and installed up, down, left, and right on underground reinforcements embedded in cut slopes to form a retaining wall, so that drainage is easily performed.

본 고안의 옹벽 시공용 조립식 프리캐스트 패널은, 절토 사면에 매설된 지중 보강재에 삽입되는 패널몸체에 관통홀이 형성된 옹벽 시공용 조립식 프리캐스트 패널에 있어서, 상기 패널몸체의 상부 테두리면에 일정 깊이로 요입되는 제1 배수홈이 형성되고, 상기 제1 배수홈과 연통되어 배수로가 형성되도록 상기 패널몸체의 일측 테두리면에 일정 깊이로 요입되는 제2 배수홈이 형성되고, 인접되는 하부측 프리캐스트 패널의 상기 제1 배수홈측에 배수로가 형성되게 끼워지도록 상기 패널몸체의 하부 테두리면에 상기 제1 배수홈의 깊이보다 짧은 길이로 돌출된 제1 접속돌부가 형성되고, 인접되는 측부측 프리캐스트 패널의 상기 제2 배수홈측에 배수로가 형성되게 끼워지도록 상기 패널몸체의 타측 테두리면에 상기 제2 배수홈의 깊이보다 짧은 길이로 돌출된 제2 접속돌부가 형성된다.The prefabricated precast panel for retaining wall construction according to the present invention is a prefabricated precast panel for retaining wall construction in which a through hole is formed in a panel body inserted into an underground reinforcement embedded in a cut slope, and has a predetermined depth on an upper edge surface of the panel body. A first drain groove to be recessed is formed, and a second drain groove recessed to a certain depth is formed on one side edge of the panel body so as to communicate with the first drain groove to form a drainage path, and the adjacent lower side precast panel is formed. A first connection protrusion protruding to a length shorter than the depth of the first drain groove is formed on the lower edge of the panel body so that the drainage passage is formed on the first drain groove side of the first drain groove, Shorter than the depth of the second drain groove on the other side of the panel body so that the drainage passage is formed on the second drain groove side Additional exported second connection stones are formed.

이에 의해, 옹벽의 배면수가 프리캐스트 패널의 테두리부에 형성된 배수로를 통해 상측에서 하측으로 순차적으로 배수되므로, 종래와 같이 옹벽의 전면으로 배면수가 배출됨에 따라 보행자나 이동차량에 미치는 불편함과 안전사고의 위험성을 해소할 수 있고, 배면수나 녹물에 의한 오염을 방지할 수 있으므로 옹벽이나 옹벽 주변의 미관을 향상시킬 수 있는 효과가 있다.As a result, since the rear surface of the retaining wall is sequentially drained from the upper side to the lower side through the drainage channel formed at the edge of the precast panel, the inconvenience and safety accident affects the pedestrian or the moving vehicle as the rear surface water is discharged to the front of the retaining wall. It is possible to solve the risk of, and to prevent contamination by the backing water or rust, there is an effect that can improve the aesthetics around the retaining wall or retaining wall.

Description

옹벽 시공용 조립식 프리캐스트 패널{PRECAST PANEL FOR CONSTRUCTION OF RETAINING WALL}Prefabricated panel for retaining wall construction {PRECAST PANEL FOR CONSTRUCTION OF RETAINING WALL}

본 고안은 옹벽 시공용 조립식 프리캐스트 패널에 관한 것으로서, 더욱 상세하게는, 절토 사면에 매설된 지중 보강재들상에 상하좌우로 조립 및 설치되어 옹벽을 형성하되 배수가 용이하게 수행되도록 하는 옹벽 시공용 조립식 프리캐스트 패널에 관한 것이다.The present invention relates to a prefabricated precast panel for retaining wall construction, and more specifically, for retaining wall construction to be assembled and installed up, down, left, and right on underground reinforcements embedded in cut slopes to form retaining walls, and to easily perform drainage. It relates to a prefabricated precast panel.

도로, 건축물 등의 시공시에 경사면의 지반 붕괴를 방지하기 위해서 옹벽이 시공된다.Retaining walls are constructed to prevent ground collapse of slopes during construction of roads and buildings.

옹벽은 다수 개의 프리캐스트 패널을 상하좌우로 조립하여 형성하게 되고, 이와 같이 조립되는 프리캐스트 패널은 지반의 경사면에 매설되는 지중 보강재에 의해 지지된다. The retaining wall is formed by assembling a plurality of precast panels in up, down, left and right, and the assembled precast panels are supported by underground reinforcement embedded in the inclined surface of the ground.

프리캐스트 패널은 콘크리트 몰탈에 의해 패널몸체가 대략 장방형 형상을 갖도록 성형되고, 이와 같이 성형된 프리캐스트 패널들의 테두리부가 서로 면접촉되면서 조립된다. The precast panel is molded so that the panel body has an approximately rectangular shape by concrete mortar, and the edges of the thus formed precast panels are assembled while being in surface contact with each other.

지중 보강재의 설치작업은 절토된 경사면에 천공홀을 형성하고, 이 천공홀에 지중 보강재를 삽입하여 그라우팅을 시행한 후, 지중 보강재의 자유단으로 프리캐스트 패널을 삽입하고 지압 너트를 체결하게 된다. The installation work of underground reinforcement forms a drilled hole in the cut slope, inserts the underground reinforcement into the drilled hole and grouts, inserts the precast panel into the free end of the underground reinforcement and tightens the acupressure nut.

프리캐스트 패널이 설치되면, 그 배면과 지반의 경사면 사이에 토사를 채워넣고 다지는 되메우기 및 다짐작업을 시행하고, 지중 보강재를 잭에 의해 인장시킨 후 지압너트를 체결하여 프리캐스트 패널측에 밀착시키게 되면, 프리캐스트 패널이 뒤메우기된 토사를 압축시키면서 견고하게 고정된다.When the precast panel is installed, the soil is filled between the back side and the slope of the ground, the compaction is backfilled and compacted, the earth reinforcement is tensioned by the jack, and the pressure nut is tightened to bring it into close contact with the precast panel. The precast panel is firmly fixed while compressing the backfilled soil.

그러나, 상기와 같은 종래 프리캐스트 패널은 별도의 배수로가 구성되어 있지 않고 장방형의 패널몸체가 서로 면접촉되어 옹벽을 형성하게 되므로, 옹벽의 배면으로 지하수나 우수와 같은 배면수가 유입되면, 접촉 틈새를 통해 배면수가 프리캐스트 패널의 전면상으로 유출되게 된다. However, the conventional precast panel as described above does not have a separate drainage channel, and the rectangular panel bodies are in surface contact with each other to form the retaining wall. Therefore, when a backwater such as groundwater or rainwater flows into the rear surface of the retaining wall, a contact gap is formed. Through this, the back water flows out onto the front surface of the precast panel.

이와 같이 배면수가 프리캐스트 패널의 전면으로 유출되면 보행자나 이동차량의 통행에 불편함을 초래하게 되고, 심할 경우 안전사고를 유발시키는 문제점이 있었다. As such, when the rear surface water flows out to the front of the precast panel, it causes inconvenience to traffic of pedestrians or mobile vehicles, and in severe cases, causes a safety accident.

또한, 유출되는 배면수에 의해 프리캐스트 패널의 전면이나 배수구 주변이 오염될 뿐만 아니라, 옹벽의 시공시에 설치되는 금속성 부재들이 부식되면서 유출된 녹물에 의해 옹벽 표면에 자욱을 남기게 되므로 미관이 불량해지게 되는 문제점이 있었다.In addition, not only the front surface of the precast panel or the drainage area is contaminated by the drained back water, but also the aesthetics are poor because the metal members installed during the construction of the retaining wall are corroded, leaving a trace on the surface of the retaining wall. There was a problem.

본 고안은 상기 내용에 착안하여 제안된 것으로, 옹벽의 배면수가 프리캐스트 패널의 테두리부를 통해 상측에서 하측으로 순차적으로 배수되도록 함으로써, 안전사고가 방지되고 옹벽 주변의 미관이 향상되도록 한 옹벽 시공용 조립식 프리캐스트 패널을 제공하는데 그 목적이 있다.The present invention has been proposed in view of the above, by retaining the back surface of the retaining wall sequentially from the upper side to the lower side through the rim of the precast panel, to prevent safety accidents and to enhance the aesthetics around the retaining wall assembly type The purpose is to provide a precast panel.

상기 목적을 달성하기 위해, 본 고안의 옹벽 시공용 조립식 프리캐스트 패널은 절토 사면에 매설된 지중 보강재에 삽입되는 패널몸체에 관통홀이 형성된 옹벽 시공용 조립식 프리캐스트 패널에 있어서, 상기 패널몸체의 상부 테두리면에 일정 깊이로 요입되는 제1 배수홈이 형성되고, 상기 제1 배수홈과 연통되어 배수로가 형성되도록 상기 패널몸체의 일측 테두리면에 일정 깊이로 요입되는 제2 배수홈이 형성되고, 인접되는 하부측 프리캐스트 패널의 상기 제1 배수홈측에 배수로가 형성되게 끼워지도록 상기 패널몸체의 하부 테두리면에 상기 제1 배수홈의 깊이보다 짧은 길이로 돌출된 제1 접속돌부가 형성되고, 인접되는 측부측 프리캐스트 패널의 상기 제2 배수홈측에 배수로가 형성되게 끼워지도록 상기 패널몸체의 타측 테두리면에 상기 제2 배수홈의 깊이보다 짧은 길이로 돌출된 제2 접속돌부가 형성되는 것을 특징으로 한다.In order to achieve the above object, the prefabricated precast panel for retaining wall construction of the present invention is a prefabricated precast panel for retaining wall construction in which a through hole is formed in a panel body inserted into underground reinforcement embedded in a cut slope, the upper part of the panel body A first drain groove recessed to a predetermined depth is formed on the edge surface, and a second drain groove recessed to a predetermined depth is formed on one side edge surface of the panel body so as to communicate with the first drain groove to form a drainage passage. A first connection protrusion protruding to a length shorter than the depth of the first drain groove is formed on the lower edge of the panel body so that the drainage passage is formed on the first drain groove side of the lower precast panel. The second drainage on the other edge surface of the panel body so that the drainage passage is formed on the second drain groove side of the side precast panel. Than the depth of the protrusion a short length claim characterized in that the second connecting portion is formed stone.

상기 패널몸체의 상부 테두리면상에 돌출되는 적어도 하나 이상의 결합봉; 및 상기 패널몸체의 하부 테두리면상에 하부측 프리캐스트 패널의 상기 결합봉이 삽입되도록 동일 수직선상에 상방으로 요입되는 결합홀을 포함할 수 있다.At least one coupling rod protruding from the upper edge surface of the panel body; And a coupling hole recessed upward on the same vertical line to insert the coupling rod of the lower precast panel on the lower edge surface of the panel body.

이와 같은 본 고안의 옹벽 시공용 조립식 프리캐스트 패널에서, 상기 결합봉은 착탈 가능하게 구성될 수 있다.In such a prefabricated precast panel for retaining wall construction of the present invention, the coupling rod can be detachably configured.

본 고안의 옹벽 시공용 조립식 프리캐스트 패널은, 옹벽의 배면수가 프리캐스트 패널의 테두리부에 형성된 배수로를 통해 상측에서 하측으로 순차적으로 배수되므로, 종래와 같이 옹벽의 전면으로 배면수가 배출됨에 따라 보행자나 이동차량에 미치는 불편함과 안전사고의 위험성을 해소할 수 있고, 배면수나 녹물에 의한 오염을 방지할 수 있으므로 옹벽이나 옹벽 주변의 미관을 향상시킬 수 있는 효과가 있다.In the prefabricated precast panel for retaining wall construction of the present invention, since the back surface of the retaining wall is sequentially drained from the upper side to the lower side through the drainage channel formed at the edge of the precast panel, the back water is discharged to the front surface of the retaining wall as in the prior art. It can solve the inconvenience and the risk of safety accidents on the mobile vehicle, and can prevent the contamination by the back water or rust, it is effective to improve the aesthetics around the retaining wall or retaining wall.

도1은 본 고안의 일 실시예에 따른 옹벽 시공용 조립식 프리캐스트 패널을 나타내는 정면도, 1 is a front view showing a prefabricated precast panel for retaining wall construction according to an embodiment of the present invention;

도2a는 도1의 A-A선 단면도, Figure 2a is a cross-sectional view taken along the line A-A of Figure 1;

도2b는 도1의 B-B선 단면도, 2B is a cross-sectional view taken along the line B-B of FIG. 1;

도3은 본 고안의 일 실시예에 따른 옹벽 시공용 조립식 프리캐스트 패널을 이용한 옹벽의 시공방법을 설명하기 위한 설치단면도, Figure 3 is an installation cross-sectional view for explaining the construction method of the retaining wall using the prefabricated precast panel for retaining wall construction according to an embodiment of the present invention,

도4는 도3의 C부 확대도,4 is an enlarged view of part C of FIG. 3;

도5a는 본 고안의 일 실시예에 따른 옹벽 시공용 조립식 프리캐스트 패널을 이용한 옹벽의 시공방법에 따라 시공된 옹벽을 나타내는 측면도, Figure 5a is a side view showing a retaining wall constructed in accordance with the construction method of the retaining wall using the prefabricated precast panel for retaining wall construction according to an embodiment of the present invention,

도5b는 본 고안의 일 실시예에 따른 옹벽 시공용 조립식 프리캐스트 패널을 이용한 옹벽의 시공방법에 따라 시공된 옹벽을 나타내는 정면도,Figure 5b is a front view showing the retaining wall constructed in accordance with the construction method of the retaining wall using the prefabricated precast panel for retaining wall construction according to an embodiment of the present invention,

도5c는 본 고안의 다른 실시예에 따른 옹벽 시공용 조립식 프리캐스트 패널을 이용한 옹벽의 시공방법에 따라 시공된 옹벽을 나타내는 전개도이다.Figure 5c is a development view showing a retaining wall constructed in accordance with the construction method of the retaining wall using the prefabricated precast panel for retaining wall construction according to another embodiment of the present invention.

< 도면의 주요부분에 대한 부호의 설명 ><Description of Symbols for Major Parts of Drawings>

10:프리캐스트 패널 11:패널몸체10: Precast panel 11: Panel body

12:관통홀 13:제1 배수홈12: Through hole 13: First drain groove

14:제2 배수홈 15:제1 접속돌부14: second drain groove 15: first connection protrusion

16:제2 접속돌부 17:결합봉16: second connection protrusion 17: coupling rod

18:결합홀 20:배수패드(부직포)18: coupling hole 20: drainage pad (non-woven fabric)

30:지중 보강재 40:기초면30: underground reinforcement 40: base surface

50:기초블록 60:지압 너트 50: Foundation block 60: Acupressure nut

이하, 첨부된 도면을 참조하여 본 고안의 실시예를 구체적으로 설명한다.Hereinafter, with reference to the accompanying drawings will be described an embodiment of the present invention in detail.

도1은 본 고안의 일 실시예에 따른 옹벽 시공용 조립식 프리캐스트 패널을 나타내는 정면도, 도2a는 도1의 A-A선 단면도, 도2b는 도1의 B-B선 단면도이다.1 is a front view showing a prefabricated precast panel for retaining wall construction according to an embodiment of the present invention, FIG. 2A is a cross-sectional view taken along the line A-A of FIG. 1, and FIG. 2B is a cross-sectional view taken along the line B-B of FIG.

도1 내지 도2b를 참조하면, 본 고안의 일 실시예에 따른 옹벽 시공용 조립식 프리캐스트 패널(10)은 대략 장방형 형상을 갖는 패널몸체(11)에 절토 사면측으로 매설된 지중 보강재(30)의 자유단에 삽입되는 관통홀(12)이 형성되고, 패널몸체(11)의 테두리면상에 옹벽의 배면수가 배수되는 배수로가 형성된다.1 to 2B, the prefabricated precast panel 10 for retaining wall construction according to an embodiment of the present invention is made of underground reinforcement 30 embedded in a cut slope side in a panel body 11 having a substantially rectangular shape. A through hole 12 inserted into the free end is formed, and a drainage path through which the back surface of the retaining wall is drained is formed on the edge surface of the panel body 11.

배수로는 패널몸체(11)의 상부 테두리면에 일정 깊이로 요입되는 제1 배수홈(13)과, 제1 배수홈(13)과 연통되어 패널몸체(11)의 일측 테두리면에 일정 깊이로 요입되는 제2 배수홈(14)에 의해 형성된다.The drainage channel communicates with the first drain groove 13 that is recessed to a predetermined depth on the upper edge surface of the panel body 11 and the first drain groove 13 to recess the recess on one side of the panel body 11 at a predetermined depth. It is formed by the second drain groove (14).

패널몸체(11)의 하부 테두리면에 인접되는 하부측 프리캐스트 패널(10)의 제1 배수홈(13)측에 배수로가 형성되도록 끼워지게 돌출된 제1 접속돌부(15)가 형성되고, 패널몸체(11)의 타측 테두리면에 인접되는 측부측 프리캐스트 패널(10)의 제2 배수홈(14)측에 배수로가 형성되도록 끼워지게 돌출된 제2 접속돌부(16)가 형성된다.A first connecting protrusion 15 is formed to protrude so as to form a drainage path at the first drain groove 13 side of the lower precast panel 10 adjacent to the lower edge of the panel body 11, and the panel is formed. A second connecting protrusion 16 is formed to protrude so as to form a drainage path on the side of the second drain groove 14 of the side precast panel 10 adjacent to the other edge of the body 11.

제1 접속돌부(15) 및 제2 접속돌부(16)는 대응되는 제1 배수홈(13) 및 제2 배수홈(14)에 끼워지되, 배수로를 차단시키지 않도록 돌출 높이가 배수홈의 깊이보다 짧은 길이로 돌출된다.The first connecting protrusion 15 and the second connecting protrusion 16 are fitted in the corresponding first drain groove 13 and the second drain groove 14, but the protrusion height is greater than the depth of the drain groove so as not to block the drain passage. It protrudes into a short length.

한편, 본 실시예에 따른 프리캐스트 패널(10)에서는 패널몸체(11)의 하부 테두리면에 제1 접속돌부(15)가 돌출되고, 타측 테두리면에 제2 접속돌부(16)가 돌출되게 구성하였지만, 이에 한정되는 것은 아니며 프리캐스트 패널(10)이 상하좌우로 조립되는 과정에서 제1 배수홈(13) 및 제2 배수홈(14)을 차단시키지 않은 구조라면 다양한 구조로 형성할 수 있다. 예컨대 패널몸체(11)의 하부 테두리면과 타측 테두리면을 접속돌부가 삭제된 평면구조로 형성할 수 있을 것이다.Meanwhile, in the precast panel 10 according to the present exemplary embodiment, the first connecting protrusion 15 protrudes from the lower edge of the panel body 11, and the second connecting protrusion 16 protrudes from the other edge of the panel body 11. However, the present invention is not limited thereto, and the precast panel 10 may be formed in various structures as long as the first drain groove 13 and the second drain groove 14 are not blocked in the process of assembling the top, bottom, left and right. For example, the lower border surface and the other border surface of the panel body 11 may be formed in a planar structure in which the connection protrusion is deleted.

프리캐스트 패널(10)은 패널몸체(11)의 상부 테두리면상에 돌출되는 적어도 하나 이상의 결합봉(17)이 설치되고, 패널몸체(11)의 하부 테두리면상에는 상하로 조립되는 과정에서 하부측 프리캐스트 패널(10)의 결합봉(17)이 삽입되도록 동일 수직선상을 이루도록 상방으로 요입되는 결합홀(18)이 형성된다.The precast panel 10 has at least one coupling rod 17 protruding from the upper edge surface of the panel body 11, and the lower side free in the process of being assembled up and down on the lower edge surface of the panel body 11. A coupling hole 18 recessed upwardly to form the same vertical line to insert the coupling rod 17 of the cast panel 10 is formed.

결합봉(17)은 소정 길이를 갖는 환봉이나 철근과 같은 금속부재의 하부가 패널몸체(11)의 성형과정에서 일체로 매입되게 형성하는 것이 바람직하지만, 콘크리트 몰탈에 의해 패널몸체(11)를 형성하는 과정에서 결합봉(17)이 삽입될 수 있는 끼움홀을 형성함으로써, 프리캐스트 패널(10)의 조립과정에서 결합봉(17)을 끼움홀에 착탈시킬 수 있도록 구성할 수 있을 것이다.The coupling rod 17 is preferably formed such that the lower part of the metal member such as a round bar or reinforcing bar having a predetermined length is integrally embedded in the molding process of the panel body 11, but the panel body 11 is formed by concrete mortar. By forming a fitting hole into which the coupling rod 17 may be inserted in the process, the coupling rod 17 may be detachably attached to the fitting hole during the assembly of the precast panel 10.

도1의 미설명부호 11a와 11b는 패널몸체(11)의 전면에 돌출 및 요입되는 돌부와 홈부이고, 도2a의 미설명부호 19는 패널몸체(11)의 내부에 설치되는 보강용 철근이고, 19a는 프리캐스트 패널(10)의 조립시에 리프팅할 수 있도록 리프팅장비의 접속수단과 접속되는 리프팅 아이(Lifting eye)이다. Reference numerals 11a and 11b of FIG. 1 are protrusions and grooves protruding and recessed in the front of the panel body 11, and reference numeral 19 of FIG. 2a is a reinforcing steel reinforcing bar installed inside the panel body 11, 19a is a lifting eye which is connected with the connecting means of the lifting equipment so that it can be lifted when the precast panel 10 is assembled.

도3 및 도4를 본 고안의 일 실시예에 따른 옹벽 시공용 조립식 프리캐스트 패널을 이용한 옹벽의 시공방법을 설명하기 위한 설치단면도, 도4는 도3의 C부 확대도이다.3 and 4 are cross-sectional views illustrating a method of constructing a retaining wall using the prefabricated precast panel for retaining wall construction according to an embodiment of the present invention, and FIG. 4 is an enlarged view of part C of FIG. 3.

도3을 참조하면, 본 고안의 일 실시예에 따른 옹벽 시공용 조립식 프리캐스트 패널을 이용한 옹벽의 시공방법은, 프리캐스트 패널(10)을 다수 구비하는 단계, 프리캐스트 패널(10)을 설치할 위치에 따라 절토 사면을 천공하여 지중 보강재를 삽입하고 고정하는 단계, 프리캐스트 패널(10)이 옹벽을 형성하도록 지지하는 기초부를 마련하는 단계, 및 프리캐스트 패널(10)을 조립하는 단계를 포함한다.Referring to Figure 3, the method of constructing the retaining wall using the prefabricated precast panel for retaining wall construction according to an embodiment of the present invention, comprising a plurality of precast panel 10, the position to install the precast panel 10 And perforating the cut slope to insert and fix the underground reinforcement, providing a foundation for supporting the precast panel 10 to form the retaining wall, and assembling the precast panel 10.

프리캐스트 패널을 다수 구비하는 단계에서는, 상술한 바와 같이 장방형 형상을 갖는 패널몸체(11)의 상부 테두리면에 제1 배수홈(13)이 요입되고, 이 제1 배수홈(13)과 연통되도록 일측 테두리면에 제2 배수홈(14)이 형성되며, 패널몸체(11)의 하부 테두리면에 제1 접속돌부(15)가, 타측 테두리면에 제2 접속돌부(16)가 형성된 프리캐스트 패널(10)이 준비된다.In the step of providing a plurality of precast panels, as described above, the first drain groove 13 is recessed in the upper edge surface of the panel body 11 having a rectangular shape so as to communicate with the first drain groove 13. A precast panel having a second drainage groove 14 formed on one side of the edge, a first connecting protrusion 15 on the lower edge of the panel body 11, and a second connecting protrusion 16 on the other edge of the panel body 11. 10 is prepared.

이와 같이 준비된 프리캐스트 패널(10)을 조립하기 위해서, 절토 사면에 지중 보강재(30)를 매설하고, 절토 사면의 하측 기초면(40)에 기초블록(50)을 설치하여 기초부를 마련하는 단계가 시행된다.In order to assemble the precast panel 10 prepared as described above, the underground reinforcement material 30 is embedded in the cut slope, and the foundation block 50 is installed on the lower foundation surface 40 of the cut slope to prepare the foundation portion. Is implemented.

프리캐스트 패널(10)을 조립하는 단계는, 프리캐스트 패널(10)의 관통홀(12)을 지중 보강재(30)에 끼워 기초부 위에 적층하되, 제1 배수홈(13)과 제2 배수홈(14)이 서로 연통하여 배수로를 형성하도록 배수홈과 접속돌부가 이웃하는 프리캐스트 패널(10)의 접속돌부와 배수홈에 각각 맞물리도록 조립한다.In the step of assembling the precast panel 10, the through-hole 12 of the precast panel 10 is laminated on the foundation by sandwiching the underground reinforcement 30, but the first drain groove 13 and the second drain groove are The drain grooves and the connecting protrusions are assembled so as to engage the connecting protrusions and the drain grooves of the neighboring precast panel 10 so that the (14) communicate with each other to form a drainage passage.

즉, 프리캐스트 패널(10)을 좌우방향으로 조립하는 경우, 제2 배수홈(14)측이 인접되는 프리캐스트 패널(10)의 제2 접속돌부(16)에 끼워지게 설치되고, 상하방향으로 제1 배수홈(13)측이 인접되는 상측 프리캐스트 패널(10)의 제1 접속돌부(15)에 끼워지게 설치되어 제1 배수홈(13) 및 상기 제2 배수홈(14)이 서로 연통되면서 배수로가 형성되도록 조립한다.That is, when assembling the precast panel 10 in the left and right directions, the second drain groove 14 side is fitted to the second connection protrusion 16 of the precast panel 10 adjacent to each other, and is installed in the vertical direction. The first drain groove 13 and the second drain groove 13 and the second drain groove 14 communicate with each other by being installed to be fitted to the first connection protrusion 15 of the upper precast panel 10 adjacent to each other. While assembling to form a drainage.

프리캐스트 패널(10)을 상하방향으로 조립하는 경우, 하측 프리캐스트 패널(10)상에 형성된 결합봉(17)이 상측 프리캐스트 패널(10)의 하부에 형성된 결합홀(18)상에 삽입됨으로써, 조립되는 상하 프리캐스트 패널(10)의 조립위치가 일정하게 유지되고, 조립된 상태에서 옹벽의 배면에 채워지는 뒤메움 토사나 지반으로부터 인가되는 팽창력을 지지할 수 있게 된다.When assembling the precast panel 10 in the vertical direction, the coupling rod 17 formed on the lower precast panel 10 is inserted into the coupling hole 18 formed below the upper precast panel 10. The assembling position of the upper and lower precast panels 10 to be assembled is maintained at a constant level, and in the assembled state, it is possible to support the expansion force applied from the back-filled soil or ground filled in the rear surface of the retaining wall.

이와 같이 프리캐스트 패널을 조립하는 단계에 의해 형성된 옹벽의 배면으로 유입되는 배면수가 배수되는 과정에서 수분은 통과되고 뒤메움 토사의 유출이 차단되도록 프리캐스트 패널(10)의 배면에 배수패드(20)를 설치하는 단계가 시행된다.The drain pad 20 is disposed on the rear surface of the precast panel 10 so that moisture passes and the outflow of the backfill soil is blocked in the process of draining the rear surface water flowing into the rear surface of the retaining wall formed by assembling the precast panel. The steps to install it are carried out.

배수패드(20)를 설치하는 단계는 프리캐스트 패널(10)이 조립되기 전에 절토 사면에 매설된 지중 보강재(30)의 자유단으로 배수패드(20)를 끼워넣어 설치하는 것이 바람직하지만, 조립 대기상태의 프리캐스트 패널(10) 배면상에 직접 설치하거나, 프리캐스트 패널(10)에 의해 옹벽을 형성한 상태에서 그 배면측에 설치하는 방식으로도 시행할 수 있다.In the step of installing the drainage pad 20, it is preferable to insert the drainage pad 20 into the free end of the underground reinforcement 30 embedded in the cut slope before the precast panel 10 is assembled. It can also be performed by directly installing on the back surface of the precast panel 10 in a state, or installing on the back side in the state where the retaining wall is formed by the precast panel 10.

배수패드(20)는 토사의 유출은 차단되고 수분의 배수가 가능한 패드라면 제한없이 적용할 수 있지만, 오수 및 지중 화학성분에 대한 내구성이 크고, 소정의 신장률, 인장강도, 및 투수계수를 갖는 것이 바람직하다. 본 실시예에서는 배수패드(20)로서 상기한 특성을 만족하는 부직포로 선정하여 설치하였다.The drainage pad 20 can be applied without limitation as long as it prevents the outflow of soil and drains water, but has a high durability against sewage and underground chemical components, and has a predetermined elongation, tensile strength, and permeability coefficient. desirable. In this embodiment, the drain pad 20 is selected and installed as a nonwoven fabric that satisfies the above characteristics.

배수패드(20)를 설치하는 단계가 시행되면, 옹벽의 배면과 절토 사면 사이에 토사를 투입하고 다진 다음, 잭 등에 의해 지중 보강재(30)에 인장력을 작용시켜 긴장시키고, 지압 너트(60)를 체결하여 프리캐스트 패널(10)의 외면에 밀착 고정시킴으로서 프리캐스트 패널(10)에 의해 지반상으로 압축력이 작용되도록 한다.When the step of installing the drainage pad 20 is carried out, the earth and sand is put between the back surface of the retaining wall and the cut slope, and then crushed, by applying tension to the underground reinforcement 30 by a jack or the like, and tensioning the acupressure nut 60. By fastening and fastening the outer surface of the precast panel 10 in close contact, the compressive force is applied to the ground by the precast panel 10.

도5a는 본 고안의 일 실시예에 따른 옹벽 시공용 조립식 프리캐스트 패널을 이용한 옹벽의 시공방법에 따라 시공된 옹벽을 나타내는 측면도, 도5b는 본 고안의 일 실시예에 따른 옹벽 시공용 조립식 프리캐스트 패널을 이용한 옹벽의 시공방법에 따라 시공된 옹벽을 나타내는 정면도로서, 다수의 프리캐스트 패널(10)을 상술한 조립과정을 통해 상하좌우 방향으로 조립하게 되면 도5a 및 도5b에 도시된 형태를 갖는 옹벽의 시공이 완료된다. Figure 5a is a side view showing a retaining wall constructed according to the retaining wall construction method using the prefabricated precast panel for retaining wall construction according to an embodiment of the present invention, Figure 5b is a prefabricated precast for retaining wall construction according to an embodiment of the present invention As a front view showing a retaining wall constructed in accordance with a method of constructing a retaining wall using a panel, when a plurality of precast panels 10 are assembled in the up, down, left, and right directions through the above-described assembling process, the retaining walls have the shapes shown in FIGS. 5A and 5B. Construction of the retaining wall is completed.

이와 같이 시공된 옹벽과 지반 사이로 도5a에 도시된 바와 같이 강우나 지하수가 유입되면 토사가 혼합된 배면수가 옹벽으로 배면측으로 유출되는데, 이때 배수패드(20)에 의해 토사는 걸러지고 수분은 배수패드(20)를 통과하여 프리캐스트 패널(10) 테두리면상의 틈새로 유입되어 제1 배수홈(13) 및 제2 배수홈(14)상으로 채워지게 된다. As shown in FIG. 5A between the constructed retaining wall and the ground, when rainfall or groundwater flows in, the backwater mixed with soil is discharged to the back side by the retaining wall. At this time, the soil is filtered out by the drain pad 20 and the moisture is drained. Passing through the (20) is introduced into the gap on the rim surface of the precast panel 10 is filled on the first drain groove 13 and the second drain groove (14).

제1 배수홈(13) 및 제2 배수홈(14)상으로 유입된 배면수는 낙차에 의해 도5b에 도시된 바와 같이 상측에 조립된 프리캐스트 패널(10)로부터 제1 배수홈(13)을 따라 수평방향으로 흐른 다음, 제1 배수홈(13)과 연결된 제2 배수홈(14)을 타고 수직방향으로 흐르는 방식으로 배수되게 된다.  The back water flowing into the first drain groove 13 and the second drain groove 14 is first drain groove 13 from the precast panel 10 assembled on the upper side as shown in FIG. After the flow in the horizontal direction, the second drain groove 14 is connected to the first drain groove 13 is drained in a manner flowing in the vertical direction.

한편, 도면으로 상세히 도시하지는 않았지만 패널몸체(11)의 상부 테두리면에 제1 배수홈(13)을 형성하고, 일측 테두리면에 제2 배수홈(14)을 형성하되, 하부 테두리면과 타측 테두리면의 접속돌부를 삭제하여 평면구조로 형성한 프리캐스트 패널을 이용한 옹벽의 시공방법을 설명하면 다음과 같다.Meanwhile, although not shown in detail in the drawings, the first drain groove 13 is formed on the upper edge surface of the panel body 11, and the second drain groove 14 is formed on one edge surface, but the lower edge surface and the other edge are formed. Referring to the construction method of the retaining wall using a precast panel formed in a planar structure by removing the connection protrusion of the surface as follows.

상술한 바와 같이 옹벽의 시공방법은 프리캐스트 패널(10)을 다수 구비하는 단계, 프리캐스트 패널(10)을 설치할 위치에 따라 절토 사면을 천공하여 지중 보강재를 삽입하고 고정하는 단계, 프리캐스트 패널(10)이 옹벽을 형성하도록 지지하는 기초부를 마련하는 단계를 시행한 후, 프리캐스트 패널(10)을 조립하는 단계를 시행하게 된다.As described above, the method of constructing the retaining wall includes the steps of providing a plurality of precast panels 10, perforating a cut slope according to a location at which the precast panels 10 are to be installed, and inserting and fixing underground reinforcement materials, and a precast panel ( After performing the step of providing a base for supporting the retaining wall 10), the step of assembling the precast panel 10 is performed.

이때, 프리캐스트 패널(10)을 조립하는 단계는, 프리캐스트 패널(10)의 관통홀(12)을 지중 보강재(30)에 끼워 기초부 위에 적층하되, 프리캐스트 패널(10)의 제1 배수홈(13)측이 기초부의 상향 방향을 향하도록 하여 조립한다.At this time, the step of assembling the precast panel 10, the through-hole 12 of the precast panel 10 is laminated on the foundation by sandwiching the underground reinforcing material 30, the first drain of the precast panel 10 The groove 13 side is assembled with the base portion facing upward.

예컨대, 좌우방향으로 제2 배수홈(14)이 인접되는 프리캐스트 패널(10)의 제2 배수홈(12)과 서로 접하지 않고, 상하방향으로 제1 배수홈(13)측에 인접되는 프리캐스트 패널(10)의 제1 배수홈(13)과 서로 접하지 않도록 조립한다.For example, the free drain adjacent to the first drain groove 13 in the vertical direction without contacting the second drain groove 12 of the precast panel 10 adjacent to each other in the left and right directions. The first drain groove 13 of the cast panel 10 is assembled so as not to contact with each other.

이와 같이 조립하게 되면, 제1 배수홈(13)의 외면상에 평면구조의 하부 테두리면이 밀착되고, 제2 배수홈(14)의 외면상에 평면구조의 타측 테두리면이 밀착되면서 제1 및 제2 배수홈 내부가 차단되지 않게 된다.When assembled in this way, the lower edge of the planar structure is in close contact with the outer surface of the first drain groove 13, the other edge of the planar structure is in close contact with the outer surface of the second drain groove 14, the first and The inside of the second drain groove is not blocked.

이에 따라, 제1 배수홈(13) 및 제2 배수홈(14)에 의해 배수로가 형성되면서 배면수가 상술한 바와 같이 상측 프리캐스트 패널(10)로부터 제1 배수홈(13)을 따라 수평방향으로 흐른 다음, 제1 배수홈(13)과 연결된 제2 배수홈(14)을 타고 수직방향으로 흘러 배수되게 된다.Accordingly, the drainage path is formed by the first drain groove 13 and the second drain groove 14, and the rear surface thereof is horizontally along the first drain groove 13 from the upper precast panel 10 as described above. Next, the second drain groove 14 connected to the first drain groove 13 flows in a vertical direction to drain.

다음, 프리캐스트 패널(10)을 부분적으로 조립한 후, 프리캐스트 패널(10)의 배면과 절토면 사이의 공간을 절토시 이용했던 토사로 메우고 다진다.Next, after the precast panel 10 is partially assembled, the space between the back surface and the cut surface of the precast panel 10 is filled with earth and sand used during cutting.

토사를 메울 때, 토사의 하중에 의해 지중 보강재(30)가 휘어지지 않도록 주의한다. 다짐은 부등침하나 국부적인 함몰이 발생하지 않고 원지반과 프리캐스트 패널(10)이 밀착되어 압축력이 전달될 수 있도록 충분히 다져지도록 하되, 지중 보강재(30)에 손상이 가지 않도록 해야 한다. 프리캐스트 패널(10) 인접부의 과도한 다짐은 프리캐스트 패널(10)에 미치는 불필요한 수평력을 발생시키므로 주의를 기울여야 한다. When filling up the soil, be careful not to bend the ground reinforcement material 30 by the load of the soil. The compaction is to be sintered enough but not to cause local depression, the base and the precast panel 10 is in close contact so that the compressive force can be transmitted, but should not damage the underground reinforcement (30). Care should be taken because excessive compaction in the vicinity of the precast panel 10 generates unnecessary horizontal forces on the precast panel 10.

또한, 토사를 메우고 다지는 작업은 그 안에 매립되는 지중 보강재(30)를 파손시키지 않도록 수차례 나누어 진행하는 것이 바람직하다. In addition, it is preferable that the work of filling and compacting the soil is divided several times so as not to damage the underground reinforcing material 30 embedded therein.

토사로 덮히는 지중 보강재(30)가 수분에 의해 부식되는 것을 방지하기 위해, 적어도 그 부분에 대해서는 방청 처리를 수행하는 것이 바람직하다. 더불어, 토사를 메울 때에 방청층이 손상되는 것을 방지하기 위해 소정의 두께로 완충층을 형성해두는 것이 더욱 바람직하다. 예컨대, 부식 방지를 위한 아스팔트 방청 처리를 해주고, 3mm 두께의 방수포로 감싼 후 가열하여 녹입으로써 완충층을 형성하는 공정을 더 포함할 수 있다. In order to prevent the earth reinforcement material 30 covered with earth and sand from being corroded by moisture, it is preferable to perform antirust treatment on at least the part. In addition, it is more preferable to form a buffer layer with a predetermined thickness in order to prevent the rustproof layer from being damaged when the soil is filled. For example, the method may further include a step of forming an anti-corrosion treatment to prevent corrosion, and then forming a buffer layer by heating and melting a 3 mm thick tarpaulin.

이와 같이, 하나의 프리캐스트 패널(10)을 지중 보강재(30)에 끼워 기초부 위에 적층한 후 토사를 메우고 다지는 일련의 공정들이, 옹벽을 형성하는 프리캐스트 패널(10)들 각각에 대해 순차적으로 진행되는 것이 바람직하다. As described above, a series of processes for sandwiching one precast panel 10 into the ground reinforcement 30 to be stacked on the foundation and then filling and compacting the soil is sequentially performed for each of the precast panels 10 forming the retaining wall. It is preferable to proceed.

다음, 모든 프리캐스트 패널(10)들에 대해 고정 공정이 완료되면, 지중 보강재(30)의 말단에 인장력을 가하여 프리스트레스를 도입하면서 프리캐스트 패널 너트를 조여 프리캐스트 패널(10)에 밀착시킨 후, 프리캐스트 패널(10)에 지중 보강재의 관통홀 및 너트의 내부 공간을 그라우팅하여 너트의 인위적인 탈락과 내부 부식을 방지한다. 또한, 이러한 그라우팅 공정으로 인해 배면수가 관통홀을 통해 유출되는 것을 방지하고, 모든 배수가 배수홈을 통해 흐르도록 도모할 수 있다. Next, when the fixing process is completed for all the precast panels 10, by applying a tensile force to the end of the ground reinforcement (30) to tighten the precast panel nuts while introducing the prestress, and then in close contact with the precast panel 10, The precast panel 10 grouts the through hole of the ground reinforcement and the inner space of the nut to prevent artificial dropout and internal corrosion of the nut. In addition, the grouting process prevents the rear surface water from flowing out through the through-holes and allows all drainage to flow through the drain grooves.

도5c는 본 고안의 다른 실시예에 따른 옹벽 시공용 조립식 프리캐스트 패널을 이용한 옹벽의 시공방법에 따라 시공된 옹벽을 나타내는 전개도이다.Figure 5c is a development view showing a retaining wall constructed in accordance with the construction method of the retaining wall using the prefabricated precast panel for retaining wall construction according to another embodiment of the present invention.

도5b와 비교하면, 도5c의 옹벽 또한 대각선 방향으로 설치되어 서로 엇갈리는 형태를 갖는다는 점에서 공통된다. 이는 수직 방향으로 설치되는 옹벽에 비해 지반의 부등침하시 옹벽이 분리되고 절개되는 것을 효과적으로 방지할 수 있는 적층 구조를 제공한다.Compared with FIG. 5B, the retaining wall of FIG. 5C is also provided in a diagonal direction and is common in that they have a staggered form. This provides a laminated structure that can effectively prevent the retaining wall from being separated and cut during the inequality of the ground compared to the retaining wall installed in the vertical direction.

반면, 도5b에 대조적으로, 도5c의 옹벽은 수평방향으로 일정각도로 굽어지는 만곡 지점(P)을 가지며, 만곡 지점(P)에서 옹벽이 수직방향으로 정렬되도록 하기 위하여, 일정한 크기의 프리캐스트 패널(10) 보다 1.5배 큰 패널(10a)이 교대로 적층되어 있는 것을 볼 수 있다.On the other hand, in contrast to FIG. 5B, the retaining wall of FIG. 5C has a curved point P that is bent at an angle in the horizontal direction, and a predetermined size of precast is made so that the retaining wall is aligned vertically at the curved point P. It can be seen that panels 10a that are 1.5 times larger than the panel 10 are alternately stacked.

여기에서, 프리캐스트 패널(10a)의 크기는 반드시 1.5배 커야 할 필요는 없지만, 대량 생산으로 프리캐스트 패널(10)의 크기가 일정하게 규격화된다는 점과 부등침하를 방지하기 위해 상부 패널과 하부 패널의 절반씩 교차하도록 적층되는 것이 효과적인 점을 감안할 때 1.5배의 크기를 갖도록 하는 것이 효과적일 것이다.Here, the size of the precast panel 10a does not necessarily need to be 1.5 times larger, but the mass of the precast panel 10 is uniformly sized due to mass production, and the upper panel and the lower panel to prevent inequality. Considering that it is effective to stack by half of each other, it will be effective to have a size of 1.5 times.

이상에서 설명한 것은 본 고안에 따른 옹벽 시공용 조립식 프리캐스트 패널 을 실시하기 위한 하나의 실시예에 불과한 것으로서, 본 고안은 상기한 실시예에 한정되지 않고, 이하의 특허청구범위에서 청구하는 바와 같이 본 고안의 요지를 벗어남이 없이 당해 고안이 속하는 분야에서 통상의 지식을 가진 자라면 누구든지 다양한 변경실시가 가능한 범위까지 본 고안의 기술적 정신이 있다고 할 것이다.What has been described above is just one embodiment for carrying out the prefabricated precast panel for retaining wall construction according to the present invention, the present invention is not limited to the above embodiment, as claimed in the following claims Without departing from the gist of the invention, anyone with ordinary knowledge in the field to which the invention belongs will have a technical spirit of the present invention to the extent that various changes can be made.

Claims (3)

절토 사면에 매설된 지중 보강재에 삽입되는 패널몸체에 관통홀이 형성된 옹벽 시공용 조립식 프리캐스트 패널에 있어서,In the prefabricated precast panel for retaining wall construction in which a through hole is formed in a panel body inserted into an underground reinforcement embedded in a cut slope, 상기 패널몸체의 상부 테두리면에 일정 깊이로 요입되는 제1 배수홈이 형성되고,The first drain groove is formed in the upper rim surface of the panel body to a predetermined depth, 상기 제1 배수홈과 연통되어 배수로가 형성되도록 상기 패널몸체의 일측 테두리면에 일정 깊이로 요입되는 제2 배수홈이 형성되고,A second drainage groove is formed in one of the rim surface of the panel body so as to communicate with the first drainage groove to form a drainage path. 인접되는 하부측 프리캐스트 패널의 상기 제1 배수홈측에 배수로가 형성되게 끼워지도록 상기 패널몸체의 하부 테두리면에 상기 제1 배수홈의 깊이보다 짧은 길이로 돌출된 제1 접속돌부가 형성되고,A first connecting protrusion protruding to a length shorter than the depth of the first drain groove is formed on the lower edge surface of the panel body so that a drainage path is formed on the first drain groove side of the adjacent lower side precast panel. 인접되는 측부측 프리캐스트 패널의 상기 제2 배수홈측에 배수로가 형성되게 끼워지도록 상기 패널몸체의 타측 테두리면에 상기 제2 배수홈의 깊이보다 짧은 길이로 돌출된 제2 접속돌부가 형성되는 것을 특징으로 하는 옹벽 시공용 조립식 프리캐스트 패널.A second connecting protrusion protruding to a length shorter than the depth of the second drain groove is formed on the other edge of the panel body so that the drainage path is formed on the second drain groove side of the adjacent side precast panel. Precast panel for retaining wall construction to use. 제1항에 있어서,The method of claim 1, 상기 패널몸체의 상부 테두리면상에 돌출되는 적어도 하나 이상의 결합봉; 및At least one coupling rod protruding from the upper edge surface of the panel body; And 상기 패널몸체의 하부 테두리면상에 하부측 프리캐스트 패널의 상기 결합봉이 삽입되도록 동일 수직선상에 상방으로 요입되는 결합홀을 포함하는 것을 특징으로 하는 옹벽 시공용 조립식 프리캐스트 패널.And a coupling hole recessed upward on the same vertical line to insert the coupling rod of the lower side precast panel on the lower edge surface of the panel body. 제2항에 있어서,The method of claim 2, 상기 결합봉은 착탈 가능하게 구성되는 것을 특징으로 하는 옹벽 시공용 조립식 프리캐스트 패널.Prefabricated panel for retaining wall construction, characterized in that the coupling rod is detachably configured.
KR2020080001328U 2008-01-29 2008-01-29 Precast panel for construction of retaining wall KR20080005134U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020080001328U KR20080005134U (en) 2008-01-29 2008-01-29 Precast panel for construction of retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020080001328U KR20080005134U (en) 2008-01-29 2008-01-29 Precast panel for construction of retaining wall

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
KR1020070042007 Division 2007-04-30

Publications (1)

Publication Number Publication Date
KR20080005134U true KR20080005134U (en) 2008-11-04

Family

ID=41502801

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020080001328U KR20080005134U (en) 2008-01-29 2008-01-29 Precast panel for construction of retaining wall

Country Status (1)

Country Link
KR (1) KR20080005134U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100930829B1 (en) * 2009-05-04 2009-12-10 브사렐건설 주식회사 Pannel have rockbolt coupler
KR100950693B1 (en) * 2009-02-19 2010-03-31 브사렐건설 주식회사 Screw type anchor have wall structure
KR101384673B1 (en) * 2012-09-19 2014-04-14 한국철도기술연구원 Hybrid Wall for Supporting Reinforced Base of Rail Track and Constructing Method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100950693B1 (en) * 2009-02-19 2010-03-31 브사렐건설 주식회사 Screw type anchor have wall structure
KR100930829B1 (en) * 2009-05-04 2009-12-10 브사렐건설 주식회사 Pannel have rockbolt coupler
KR101384673B1 (en) * 2012-09-19 2014-04-14 한국철도기술연구원 Hybrid Wall for Supporting Reinforced Base of Rail Track and Constructing Method thereof

Similar Documents

Publication Publication Date Title
KR101105092B1 (en) A precast retaining panel and construction method of the same with half pc type backfill
KR101169732B1 (en) Earth anchor and retaining wall using it
KR100679480B1 (en) Drain board
KR20140139217A (en) Concrete protection wall with linear drainage functions and construction method thereof
KR20080005134U (en) Precast panel for construction of retaining wall
CN211972965U (en) Permeable pavement flat kerb drainage system
KR101495997B1 (en) Upright type rainwater storaging structure and Rainwater storaging facility having the structure and Method for building the facility
KR100734047B1 (en) Sump system and the setting method
KR200433220Y1 (en) Sump system
KR101673823B1 (en) Retaining wall system
KR101641050B1 (en) Drainage plate for bottom of underground
KR101770268B1 (en) Detention unit block and reservoir water tank structure for infiltration and detention of rainwater, and construction method for the same
KR100777800B1 (en) The drainage plate for dranining underground water of public works and construction method using thesame
KR200420394Y1 (en) Precast concrete block for cantilever retaining wall
KR20200131800A (en) Construction of free-flowing concrete in parking lot
KR200422102Y1 (en) The drainage plate for dranining underground water of public works
KR100821742B1 (en) Vertical reinforcement sump system
JP4092284B2 (en) Rainwater underground seepage structure and its construction method
KR101657279B1 (en) Permanent embedded anchor type slope ditch water way and slope ditch water way construction method using thereof
KR20200122081A (en) Construction method of free-flowing concrete in parking lot and construction method theerof
JP2006233429A (en) Drainage block
KR200299545Y1 (en) Mounting structure of concrete reinforcement block of reinforcement soil section for road
JP2005002710A (en) Concrete block for constructing sidewalk-roadway boundary body
CN218147591U (en) Prefabricated sidewalk plate
KR102629985B1 (en) Drainage construction method for cross fall conversion section

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application
J201 Request for trial against refusal decision

Free format text: TRIAL AGAINST DECISION OF REJECTION FOR APPEAL AGAINST DECISION TO DECLINE REFUSAL

J301 Trial decision

Free format text: TRIAL DECISION FOR APPEAL AGAINST DECISION TO DECLINE REFUSAL REQUESTED 20090213

Effective date: 20101028