KR200410995Y1 - gangform fasten means - Google Patents

gangform fasten means Download PDF

Info

Publication number
KR200410995Y1
KR200410995Y1 KR2020050036215U KR20050036215U KR200410995Y1 KR 200410995 Y1 KR200410995 Y1 KR 200410995Y1 KR 2020050036215 U KR2020050036215 U KR 2020050036215U KR 20050036215 U KR20050036215 U KR 20050036215U KR 200410995 Y1 KR200410995 Y1 KR 200410995Y1
Authority
KR
South Korea
Prior art keywords
fixing means
fastening
gangform
gang
fastening pin
Prior art date
Application number
KR2020050036215U
Other languages
Korean (ko)
Inventor
고창균
Original Assignee
고창균
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 고창균 filed Critical 고창균
Priority to KR2020050036215U priority Critical patent/KR200410995Y1/en
Application granted granted Critical
Publication of KR200410995Y1 publication Critical patent/KR200410995Y1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/06Tying means; Spacers ; Devices for extracting or inserting wall ties
    • E04G17/07Tying means, the tensional elements of which are fastened or tensioned by means of wedge-shaped members
    • E04G17/0707One-piece elements
    • E04G17/0714One-piece elements fully recoverable

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

갱폼 고정 수단을 개시한다. 본 고안에 따른 갱폼 고정 수단은, 외벽의 내측 거푸집으로부터 소정간격 이격되어 콘크리트 타설 공간을 형성하는 외벽의 외측 스틸폼을 고정하는 갱폼 고정 수단으로서, 스틸폼의 일측에 설치되고, 그 내부에는 스틸폼의 표면에 형성된 중공과 연통되는 관통홀이 형성되어 있는 관통 부재; 관통홀 및 중공에 삽입되며, 일단에는 돌기가 형성되어 있고 타단에는 갱폼 인상 작업시 크레인에 의해 끌여올려지는 케이블이 연결되는 연결고리가 형성되어 있는 체결핀; 및 콘크리트 타설 공간에서 체결핀의 일단에 연결되되, 그 내부에는 돌기를 가이드하는 가이드홈이 형성되어 있는 체결 부재;를 포함한다.The gangform fixing means is disclosed. Gang form fixing means according to the present invention is a gang form fixing means for fixing the outer steel foam of the outer wall to form a concrete placing space spaced a predetermined distance from the inner formwork of the outer wall, is installed on one side of the steel foam, the steel foam inside A through member formed with a through hole communicating with a hollow formed on a surface of the through member; A fastening pin inserted into the through-hole and the hollow, and having a protrusion formed at one end thereof and a connecting ring at which the cable is pulled up by the crane during the gang form lifting operation; And a fastening member connected to one end of the fastening pin in the concrete placing space, and having a guide groove formed therein for guiding the projection.

갱폼, 체결핀, 낙하 Gang Foam, Fastening Pins, Dropping

Description

갱폼 고정 수단 { gangform fasten means }Gangform fasten means {gangform fasten means}

본 고안은 아래 도면들에 의해 구체적으로 설명될 것이지만, 이러한 도면은 본 고안의 바람직한 실시예를 나타낸 것이므로 본 고안의 기술사상이 그 도면에만 한정되어 해석되어서는 아니된다.The present invention will be described in detail by the following drawings, but these drawings represent a preferred embodiment of the present invention, the technical concept of the present invention is not limited to the drawings and should not be interpreted.

도 1은 본 고안의 바람직한 실시예에 따른 갱폼 고정 수단의 분해사시도.1 is an exploded perspective view of a gangform fixing means according to a preferred embodiment of the present invention.

도 2는 도 1의 결합 단면 사시도.2 is a cross-sectional perspective view of the combination of FIG.

도 3은 본 고안의 바람직한 실시예에 따른 갱폼 고정 수단에서 관통 부재의 확대 사시도.Figure 3 is an enlarged perspective view of the penetrating member in the gangform fixing means according to a preferred embodiment of the present invention.

도 4는 본 고안의 바람직한 실시예에 따른 갱폼 고정 수단에서 체결 부재의 확대 사시도.Figure 4 is an enlarged perspective view of the fastening member in the gangform fixing means according to a preferred embodiment of the present invention.

도 5는 본 고안의 바람직한 실시예에 따른 갱폼 고정 수단에서 체결핀의 확대 사시도.Figure 5 is an enlarged perspective view of the fastening pin in the gangform fixing means according to an embodiment of the present invention.

도 6은 크레인에 의해 본 고안에 따른 갱폼 고정 수단의 해체 과정을 도시한 도면.6 is a view showing a dismantling process of the gangform fixing means according to the present invention by a crane.

도 7은 종래의 갱폼을 도시한 사시도.7 is a perspective view showing a conventional gangform.

본 고안은 갱폼 고정 수단에 관한 것으로서, 보다 상세하게는 외부의 충격에도 그 결속이 해제되지 않아 갱폼 낙하를 방지할 수 있는 갱폼 고정 수단에 관한 것이다.The present invention relates to a gangform fixing means, and more particularly, to a gangform fixing means that can prevent the gangform fall because the binding is not released even from an external impact.

최근에, 아파트, 빌딩 및 고층 건물을 시공하는 현장에서는 건물의 외벽을 시공하기 위하여 대형 철재로 이루어진 갱폼을 사용하고 있다. Recently, construction sites for apartments, buildings, and high-rise buildings use gangforms made of large steel to construct the exterior walls of buildings.

이러한 갱폼(1)은 도 7에 도시된 바와 같이, 외벽을 시공하기 위하여 설치되는 스틸폼(2)과, 작업발판 및 핸드레일 등이 설치된 케이지(3)와, 외벽의 내측 거푸집과 외측 스틸폼(2)을 고정하는 다수의 타이볼트(4) 및 갱폼 인상 작업시 크레인의 후크가 연결되는 인양고리(5) 등 다수부품으로 이루어진다. Such a gang form (1) is, as shown in Figure 7, the steel foam (2) is installed for the construction of the outer wall, the cage (3) provided with the working scaffold and handrail, the inner formwork and the outer steel foam of the outer wall (2) consists of a number of parts, such as a number of tie bolts (4) for fixing and lifting hooks (5) to which the hook of the crane is connected during the lifting of the gangform.

이와 같이 구성된 갱폼(1)은 해당 외벽층의 콘크리트 타설 및 양생작업을 마치게 되면, 다음층의 외벽 시공을 위해 크레인에 의해 끌어올려지게 되는데, 이 때 갱폼(1)을 고정하는 타이볼트(4)를 먼저 해제해야 한다. 이를 위해 작업자들은 작업의 편의를 위해 갱폼(1)의 아래 부분에 체결된 타이볼트(4b) 즉, 외벽면에 설치된 타이볼트(4b)를 먼저 해제하여 외벽 마감 작업을 마친 후에 갱폼(1)의 윗부분 즉, 바닥 슬라브 콘크리트에 매몰된 타이볼트(4a)를 해제하는 방법으로 작업을 수행하였다.The gangform (1) configured as described above is pulled up by a crane for the construction of the outer wall of the next layer, after finishing the concrete pouring and curing work of the outer layer, at this time tie bolts (4) for fixing the gangform (1) Must be released first. To this end, the workers first release the tie bolts 4b fastened to the lower part of the gangform 1, that is, the tie bolts 4b installed on the outer wall surface, and finish the outer wall finishing work. The work was performed by releasing the tie bolts 4a buried in the upper part, that is, the floor slab concrete.

하지만, 작업자가 마감 작업을 하는 중에 바닥 슬라브 콘크리트에 매몰된 타 이볼트(4a)가 그 결속이 종종 해제되어 갱폼(1)의 추락 및 작업자의 낙하 등과 같은 안전사고가 빈번하게 발생하여 인명 재산상에 피해가 막대하게 되는 문제점이 있었다.However, while the worker is finishing the work, the tie bolts 4a buried in the floor slab concrete are often released, and safety accidents such as falling of the gang form 1 and falling of the worker frequently occur. There was a problem that the damage is enormous.

본 고안은 상기와 같은 문제점을 해결하기 위하여 창안된 것으로서, 외부의 충격에도 그 결속이 해제되지 않아 안전사고를 방지할 수 있는 갱폼 고정 수단을 제공하는데 그 목적이 있다. The present invention was devised to solve the above problems, and the object of the present invention is to provide a gang form fixing means that can prevent the safety accident because the binding is not released even from the external impact.

상기와 같은 목적을 달성하기 위해 본 고안에 따른 갱폼 고정 수단은, 외벽의 내측 거푸집으로부터 소정간격 이격되어 콘크리트 타설 공간을 형성하는 외벽의 외측 스틸폼을 고정하는 갱폼 고정 수단으로서, 스틸폼의 일측에 설치되고, 그 내부에는 스틸폼의 표면에 형성된 중공과 연통되는 관통홀이 형성되어 있는 관통 부재; 관통홀 및 중공에 삽입되며, 일단에는 돌기가 형성되어 있고 타단에는 갱폼 인상 작업시 크레인에 의해 끌여올려지는 케이블이 연결되는 연결고리가 형성되어 있는 체결핀; 및 콘크리트 타설 공간에서 체결핀의 일단에 연결되되, 그 내부에는 돌기를 가이드하는 가이드홈이 형성되어 있는 체결 부재;를 포함한다.In order to achieve the above object, the gangform fixing means according to the present invention is a gangform fixing means for fixing the outer steel foam of the outer wall to form a concrete pouring space spaced a predetermined distance from the inner formwork of the outer wall, on one side of the steel foam A through member having a through hole formed therein and communicating with a hollow formed in a surface of the steel foam; A fastening pin inserted into the through-hole and the hollow, and having a protrusion formed at one end thereof and a connecting ring at which the cable is pulled up by the crane during the gang form lifting operation; And a fastening member connected to one end of the fastening pin in the concrete placing space, and having a guide groove formed therein for guiding the projection.

여기서, 상기 관통 부재는, 단면이 사각형의 형상으로, 그 내부에는 관통홀이 형성된 하나 이상의 격벽이 길이 방향을 따라 소정의 간격으로 설치되는 것이 바람직하다.Here, the through member has a rectangular cross section, and at least one partition wall having a through hole formed therein is preferably provided at predetermined intervals along the longitudinal direction.

또한, 상기 관통 부재의 일측과 상기 체결핀의 일단을 연결하는 탄성부재를 더 포함하는 것이 바람직하다.In addition, it is preferable to further include an elastic member for connecting one side of the through member and one end of the fastening pin.

아래 첨부된 도면들을 참조로 본 고안의 바람직한 실시예를 상세히 설명하기로 한다. 이에 앞서, 본 명세서 및 실용신안등록청구범위에 사용된 용어나 단어는 통상적이거나 사전적인 의미로 한정해서 해석되어서는 아니되며, 고안자는 그 자신의 고안을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 고안의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만한다. 따라서, 본 명세서에 기재된 실시예와 도면에 도시된 구성은 본 고안의 가장 바람직한 일 실시예에 불과할 뿐이고 본 고안의 기술적 사상을 모두 대변하는 것은 아니므로, 본 출원시점에 있어서 이들을 대체할 수 있는 다양한 균등물과 변형예들이 있을 수 있음을 이해하여야 한다.Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings. Prior to this, terms or words used in this specification and utility model registration claims should not be construed as being limited to the ordinary or dictionary meanings, and the inventors shall use the concept of terms to best describe their own designs. It should be interpreted as meanings and concepts corresponding to the technical idea of the present invention, based on the principle that can be properly defined. Therefore, the embodiments described in the specification and the drawings shown in the drawings are only the most preferred embodiment of the present invention and do not represent all of the technical ideas of the present invention, various modifications that can be replaced at the time of the present application It should be understood that there may be equivalents and variations.

도 1은 본 고안의 바람직한 실시예에 따른 갱폼 고정 수단의 분해사시도이고, 도 2는 도 1의 결합 단면 사시도이다.1 is an exploded perspective view of a gangform fixing means according to a preferred embodiment of the present invention, Figure 2 is a perspective view of the combined cross-section of FIG.

도 1 및 2를 참조하면, 본 고안에 따른 갱폼 고정 수단은, 외벽의 내측 거푸집으로부터 소정 간격 이격되어 콘크리트가 타설되는 공간을 형성하는 외벽의 외측 스틸폼(2)의 일측에 설치되는 관통 부재(10)와, 관통 부재(10)의 일단으로부터 연장된 직선상에 설치되는 체결 부재(20)와, 관통 부재(10)를 관통하여 체결 부재(20)에 착탈 가능하게 결합되는 체결핀(30)을 포함한다. 1 and 2, the gangform fixing means according to the present invention, the penetrating member is provided on one side of the outer steel foam (2) of the outer wall to form a space in which the concrete is spaced apart from the inner formwork of the outer wall at a predetermined interval ( 10), a fastening member 20 installed on a straight line extending from one end of the penetrating member 10, and a fastening pin 30 detachably coupled to the fastening member 20 through the penetrating member 10. It includes.

본 고안의 갱폼 고정 수단은 스틸폼(2)의 어디에도 설치될 수 있으나, 바람 직하게는 도 2에 도시된 바와 같이 갱폼 고정 수단의 체결 부재(20)가 바닥 슬라브 콘크리트에 매설되도록 스틸폼(2)의 상부에 설치되는 것이 바람직하다.Gang foam fixing means of the present invention can be installed anywhere on the steel foam (2), but preferably, as shown in Figure 2 steel foam (2) so that the fastening member 20 of the gang foam fixing means is embedded in the floor slab concrete It is preferable to be installed at the top of

도 3은 본 고안인 갱폼 고정 수단에 있어서 관통 부재(10)의 사시도이다. 도 3을 참조하면, 관통 부재(10)는 체결핀(30)이 관통되도록 그 내부에는 관통홀(10a)이 형성되어 있는데, 관통홀(10a)은 스틸폼(2)의 표면에 구비되어 있는 중공(2a)에 연통된다. 관통 부재(10)는 용접 등의 방법으로 스틸폼(2)의 수직지지폴(6: 도 6참조) 사이에 고정되는데, 이를 위해 관통 부재(10)는 금속재질의 사각형상의 파이프가 바람직하고, 그 내부에는 관통홀(10a)이 형성된 하나 이상의 격벽(11,12)이 길이 방향을 따라 소정의 간격으로 설치되는 것이 더 바람직하다. 3 is a perspective view of the penetrating member 10 in the gangform fixing means of the present invention. Referring to FIG. 3, the through member 10 has a through hole 10a formed therein so that the fastening pin 30 penetrates, and the through hole 10a is provided on the surface of the steel foam 2. It communicates with the hollow 2a. The penetrating member 10 is fixed between the vertical support poles 6 (see FIG. 6) of the steel foam 2 by welding or the like. For this purpose, the penetrating member 10 is preferably a rectangular metal pipe. It is more preferable that one or more partitions 11 and 12 having through holes 10a formed therein are provided at predetermined intervals along the longitudinal direction.

도 4는 본 고안인 갱폼 고정 수단에 있어서 체결 부재(20)의 사시도이다. 도 4를 참조하면, 체결 부재(20)의 내부에는 체결핀(30)을 가이드하는 가이드홈(21)이 형성되어 있다. 가이드홈(21)은 후술하는 체결핀(30)의 돌기(31:도 5참조)를 가이드하도록 형성된 것으로서, 길이방향으로 소정구간 형성된 홈(21a)과 원주방향으로 소정구간 형성된 홈(22b)으로 이루어져 있다. 원주방향으로 형성된 홈(21a)의 구간은 후술하는 바와 같이 갱폼 인상 작업시 크레인에 의해 인상되는 인양 와이어(8)의 높이를 고려하여 다양한 각도로 형성될 수 있으나, 체결 부재(20)의 중심을 기준으로 70°~ 110°로 형성되는 것이 바람직하다. 한편, 도 4에서 길이방향으로 형성된 가이드홈(21b)이 체결 부재(20)의 내부에 형성된 형태로 도시되어 있지만, 이에 한하지 않고 체결 부재(20)의 일측으로 개방된 형태 등, 돌기(31)를 가이드 할 수 있는 어떠한 형태로도 구성될 수 있음은 물론이다. 또한, 상술한 바와 같이 체 결 부재(20)는 바람직하게 바닥 슬라브 콘크리트에 매설되는 부분으로서 단단한 결속을 위해 그 일측이 구부려져 있는 것이 바람직하다.4 is a perspective view of the fastening member 20 in the gangform fixing means of the present invention. Referring to FIG. 4, a guide groove 21 for guiding the fastening pin 30 is formed inside the fastening member 20. The guide groove 21 is formed to guide the projection 31 (see FIG. 5) of the fastening pin 30 to be described later, and includes a groove 21a formed in a predetermined section in the longitudinal direction and a groove 22b formed in the circumferential direction. consist of. The section of the groove 21a formed in the circumferential direction may be formed at various angles in consideration of the height of the lifting wire 8 that is lifted by the crane during the gangform lifting operation as described below, but the center of the fastening member 20 It is preferable that it is formed at 70 ° ~ 110 ° as a reference. On the other hand, although the guide groove 21b formed in the longitudinal direction in Figure 4 is shown in the form formed in the interior of the fastening member 20, but not limited to this, such as a shape that is open to one side of the fastening member 20, projections 31 Of course, it can be configured in any form that can guide). In addition, as described above, the fastening member 20 is preferably a part embedded in the floor slab concrete, the one side is preferably bent for a solid binding.

도 5는 본 고안인 갱폼 고정 수단에 있어서 체결핀(30)의 사시도이다. 도 5를 참조하면, 체결핀(30)은 관통 부재(10), 중공(2a)을 거쳐 체결 부재(20)에 삽입되도록 환봉인 것이 바람직한데, 그 일단에는 체결 부재(20)의 가이드홈(21)을 따라 착탈 가능하게 삽입되도록 돌기(31)가 형성되어 있고, 타단에는 갱폼 인상 작업시 크레인에 의해 끌여올려지는 케이블이 연결되는 연결고리(32)가 형성되어 있다. 그리고, 용이하게 갱폼 고정 수단을 해체하기 위해서는 연결고리(32)가 형성되어 있는 체결핀(30)의 타단은 도 5에 도시된 바와 같이 굽은 형태가 바람직하다.5 is a perspective view of the fastening pin 30 in the gangform fixing means of the present invention. 5, the fastening pin 30 is preferably a round bar to be inserted into the fastening member 20 through the through member 10, the hollow (2a), one end of the guide groove of the fastening member (20) A projection 31 is formed to be detachably inserted along the 21), and the other end is formed with a connecting ring 32 to which a cable pulled up by a crane during the gang form lifting operation is connected. And, in order to easily dismantle the gangform fixing means, the other end of the fastening pin 30 in which the connecting ring 32 is formed is preferably bent as shown in FIG.

한편, 체결핀(30)의 일단과 관통 부재(10)의 일측을 연결되는 탄성부재(40)가 구비되는 것이 바람직한데, 이를 통해 후술하는 바와 같이 크레인에 의해 회동된 체결핀(30)이 원위치로 탄성 복원이 가능하므로 작업자가 체결 부재(20)에 체결핀(30)을 쉽게 체결할 수 있게 된다.On the other hand, it is preferable that the elastic member 40 is connected to one end of the fastening pin 30 and one side of the through member 10, through which the fastening pin 30 rotated by the crane as described below As it is possible to restore the elasticity, the operator can easily fasten the fastening pins 30 to the fastening member 20.

도 6은 크레인에 의해 본 고안에 따른 갱폼 고정 수단의 해체 과정을 도시한 도면이다. 도 6을 참조하면, 스틸폼(2)의 수직지지봉(6) 사이에 갱폼 고정 수단이 설치되어 있고, 스틸폼(2)의 상단에는 크레인의 후크가 연결되는 인양고리(5)가 구비되어 있다. 인양고리(5)의 일측에는 도르레(7)가 설치되어 있고, 인양고리(5)의 타측에는 체결핀(30)의 연결고리(32)에 걸어져 도르레(7)를 통과하는 인양 와이어(8)가 감겨져 고정되는 고정롤(9)이 설치되어 있다. 6 is a view showing a dismantling process of the gangform fixing means according to the present invention by a crane. Referring to FIG. 6, a gang form fixing means is installed between the vertical support rods 6 of the steel foam 2, and a lifting hook 5 to which a hook of a crane is connected is provided at the upper end of the steel foam 2. . A pulley 7 is provided at one side of the lifting ring 5, and a lifting wire 8 passing through the pulley 7 by being connected to the connecting ring 32 of the fastening pin 30 on the other side of the lifting ring 5. ) Is provided with a fixing roll 9 wound around.

갱폼 고정 수단을 해체하기 위해서는 우선, 고정롤(9)에 감겨진 인양 와이어 (8)를 도르레(7)를 거쳐 체결핀(30)의 연결고리(32)에 연결한 후, 인양 와이어(8)가 팽팽하도록 고정롤(9)을 감아 인양와이어(8)를 고정시킨다. 그런 다음, 크레인의 후크를 인양고리(32) 및 도르레(7)와 고정롤(9) 사이에 팽팽하게 유지되는 인양 와이어(8)를 함께 체결한 후, 크레인을 끌어올리게 되면 크레인의 상부로 끌어올리는 힘에 의해 체결핀(30)이 회전함으로써, 가이드홈(21)에 결합된 체결핀(30)의 돌기(31)가 해제된다. 이후, 풀려진 체결핀(30)을 작업자가 간단하게 제거할 수가 있어 안전한 갱폼 인상 작업이 이루어지게 된다. In order to dismantle the gangform fixing means, first, the lifting wire 8 wound on the fixing roll 9 is connected to the connecting ring 32 of the fastening pin 30 via the pulley 7 and then the lifting wire 8 The fixing roll 9 is wound so that the lifting wire 8 is fixed so as to tighten. Then, the hook of the crane is fastened together with the lifting hook 32 and the lifting wire 8 held tightly between the pulley 7 and the fixing roll 9, and when the crane is lifted, the crane is pulled to the top of the crane. As the fastening pin 30 rotates by the lifting force, the protrusion 31 of the fastening pin 30 coupled to the guide groove 21 is released. Afterwards, the worker can easily remove the loosened fastening pin 30, and a safe gang form lifting operation is made.

한편, 가이드홈(21)에 결합된 돌기(31)를 해제하기 위해 회전시켜야 할 체결핀(30)의 각도를 계산하여, 도르레(7)와 고정롤(9) 사이에 설치된 인양 와이어(8)와 인양고리(32)와의 간격을 설정해야 함은 물론이다. Meanwhile, the lifting wire 8 installed between the pulley 7 and the fixing roll 9 is calculated by calculating the angle of the fastening pin 30 to be rotated to release the protrusion 31 coupled to the guide groove 21. Of course, you must set the interval with the lifting ring (32).

본 고안의 갱폼 고정 수단에 따르면, 갱폼 인상 작업시 크레인에 의해 그 결속이 해제될 수 있을 뿐 외부의 다른 충격에 의해서는 그 결속이 해제되지 않아서 갱폼의 낙하 또는 작업자의 추락 등으로 인한 안전사고를 방지할 수 있다.According to the gangform fixing means of the present invention, the binding can be released by the crane during the lifting work of the gangform, but the bond is not released by other external impacts, so that safety accidents due to the fall of the gangform or the fall of the worker are caused. You can prevent it.

Claims (3)

외벽의 내측 거푸집으로부터 소정간격 이격되어 콘크리트 타설 공간을 형성하는 외벽의 외측 스틸폼을 고정하는 갱폼 고정 수단으로서,As a gang form fixing means for fixing the outer steel foam of the outer wall to form a concrete pouring space spaced apart from the inner formwork of the outer wall, 상기 스틸폼의 일측에 설치되고, 그 내부에는 상기 스틸폼의 표면에 형성된 중공과 연통되는 관통홀이 형성되어 있는 관통 부재;A through member installed on one side of the steel foam and having a through hole communicating therewith with a hollow formed on a surface of the steel foam; 상기 관통홀 및 중공에 삽입되며, 일단에는 돌기가 형성되어 있고 타단에는 갱폼 인상 작업시 크레인에 의해 끌여올려지는 케이블이 연결되는 연결고리가 형성되어 있는 체결핀; 및A fastening pin inserted into the through hole and the hollow, and having a protrusion formed at one end thereof and a connecting ring connected to a cable drawn by the crane at the other end of the gang form lifting operation; And 상기 콘크리트 타설 공간에서 돌기가 형성되어 있는 상기 체결핀의 일단에 연결되되, 그 내부에는 상기 돌기를 가이드하는 가이드홈이 형성되어 있는 체결 부재;를 포함하는 것을 특징으로 하는 갱폼 고정 수단.Gang fastening means characterized in that it comprises a; fastening member is connected to one end of the fastening pin is formed in the concrete casting space, the guide groove is formed therein to guide the projection. 제 1 항에 있어서,The method of claim 1, 상기 관통 부재는,The through member is, 단면이 사각형의 형상으로, 그 내부에는 관통홀이 형성된 하나 이상의 격벽이 길이 방향을 따라 소정의 간격으로 설치되는 것을 특징으로 하는 갱폼 고정 수단.Gang-shaped fixing means, characterized in that the cross section is in the shape of a square, one or more partition walls with a through hole formed therein at predetermined intervals along the longitudinal direction. 제 1 항에 있어서,The method of claim 1, 상기 관통 부재의 일측과 상기 체결핀의 일단을 연결하는 탄성부재를 더 포함하는 것을 특징으로 하는 갱폼 고정 수단.Ganggang fixing means further comprises an elastic member for connecting one side of the through member and one end of the fastening pin.
KR2020050036215U 2005-12-23 2005-12-23 gangform fasten means KR200410995Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR2020050036215U KR200410995Y1 (en) 2005-12-23 2005-12-23 gangform fasten means

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR2020050036215U KR200410995Y1 (en) 2005-12-23 2005-12-23 gangform fasten means

Publications (1)

Publication Number Publication Date
KR200410995Y1 true KR200410995Y1 (en) 2006-03-09

Family

ID=41761332

Family Applications (1)

Application Number Title Priority Date Filing Date
KR2020050036215U KR200410995Y1 (en) 2005-12-23 2005-12-23 gangform fasten means

Country Status (1)

Country Link
KR (1) KR200410995Y1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101978599B1 (en) 2018-01-24 2019-05-15 김종근 Apparatus for fixing gangform to the wall

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101978599B1 (en) 2018-01-24 2019-05-15 김종근 Apparatus for fixing gangform to the wall

Similar Documents

Publication Publication Date Title
KR100760286B1 (en) Safty apparatus for prevention of gang form's drop
KR200420484Y1 (en) A bracket for guide rails of gang porm
US9359779B2 (en) Space saving anchor point for a concrete structure
KR100976562B1 (en) Safety apparatus for lift gang form
KR100777937B1 (en) Construcion safety working cage with scaffold
US9353535B2 (en) Space saving anchor point for a concrete structure
KR101310595B1 (en) Gang form
KR102024302B1 (en) Structure of exterior insulation
KR20180137350A (en) The steel frame structure
CN105347142B (en) A kind of building hoist is mounted on the threading installation method on basement roof
KR200391342Y1 (en) A guide rail fix device of a contructing a building gaengpom
KR200410995Y1 (en) gangform fasten means
KR200406601Y1 (en) An apparatus for fixing a rope for hanging the duster of building
KR200412991Y1 (en) Pipe support for construction
KR200413527Y1 (en) Gang form falling prevention apparatus
KR100835613B1 (en) Apparatus for preventing a crashing of gang-form buit-in type
KR101978599B1 (en) Apparatus for fixing gangform to the wall
CN102116084B (en) Hanging formwork device replacing supporting formwork for pouring concrete floor slab in multilayer building
KR100812262B1 (en) Device for preventing falling of gangform and method for constructing reinforced concrete structure using the same
KR101021945B1 (en) Steel form for forming lining wall of vertical tunnel
KR101492774B1 (en) Disengagement prevent system
KR101113274B1 (en) gang form assembly
KR100945240B1 (en) Worker Falling Prevention Door of Gang Form
KR200426297Y1 (en) Construcion safety working cage with scaffold
KR100901016B1 (en) Safety bracket to external wall scaffolding for a structure

Legal Events

Date Code Title Description
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20070214

Year of fee payment: 3

LAPS Lapse due to unpaid annual fee