KR200370053Y1 - A fabricated manhole - Google Patents

A fabricated manhole Download PDF

Info

Publication number
KR200370053Y1
KR200370053Y1 KR20-2004-0027626U KR20040027626U KR200370053Y1 KR 200370053 Y1 KR200370053 Y1 KR 200370053Y1 KR 20040027626 U KR20040027626 U KR 20040027626U KR 200370053 Y1 KR200370053 Y1 KR 200370053Y1
Authority
KR
South Korea
Prior art keywords
manhole
bodies
present
prefabricated
inlet
Prior art date
Application number
KR20-2004-0027626U
Other languages
Korean (ko)
Inventor
안계헌
Original Assignee
주식회사 대한콘설탄트
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 대한콘설탄트 filed Critical 주식회사 대한콘설탄트
Priority to KR20-2004-0027626U priority Critical patent/KR200370053Y1/en
Application granted granted Critical
Publication of KR200370053Y1 publication Critical patent/KR200370053Y1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/121Manhole shafts; Other inspection or access chambers; Accessories therefor characterised by the connection between shaft elements, e.g. of rings forming said shaft
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/02Manhole shafts or other inspection chambers; Snow-filling openings; accessories
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B65CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
    • B65DCONTAINERS FOR STORAGE OR TRANSPORT OF ARTICLES OR MATERIALS, e.g. BAGS, BARRELS, BOTTLES, BOXES, CANS, CARTONS, CRATES, DRUMS, JARS, TANKS, HOPPERS, FORWARDING CONTAINERS; ACCESSORIES, CLOSURES, OR FITTINGS THEREFOR; PACKAGING ELEMENTS; PACKAGES
    • B65D90/00Component parts, details or accessories for large containers
    • B65D90/10Manholes; Inspection openings; Covers therefor
    • B65D90/105Manholes; Inspection openings; Covers therefor for underground containers
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/02Manhole shafts or other inspection chambers; Snow-filling openings; accessories
    • E03F2005/028Sealing joints between manhole segments

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Health & Medical Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

본 고안은 조립식 맨홀에 관한 것으로, 운반/취급이 용이하게 하여 좁은 장소에서도 용이하게 설치할 수 있도록 함을 목적으로 한다.The present invention relates to a prefabricated manhole, the purpose of which is easy to transport / handle so that it can be easily installed in a narrow place.

개시된 본 고안에 따른 조립식 맨홀은, 서로 마주보는 일측이 개구된 좌우 대칭형상이면서 개구부의 둘레부에 플랜지(11,21)가 형성되어 가스켓(40)을 사이에 두고 서로 체결구(30)를 통해 결합되는 제1 및 제2맨홀몸체(10,20)로 이루어지며, 상기 제1 및 제2맨홀몸체의 상부와 측부에는 상호 결합에 의해 입구(110)와 관연결부(120)가 각각 형성된다. 상기 제1 및 제2맨홀몸체는 중량을 최소화하기 위하여 주조 가공된다.The prefabricated manhole according to the present invention has a left-right symmetrical shape with one side facing each other, and flanges 11 and 21 are formed at the periphery of the opening, so that the gasket 40 is interposed therebetween through the fasteners 30. The first and second manhole bodies 10 and 20 are coupled to each other, and the inlet 110 and the pipe connection unit 120 are formed on the upper and side portions of the first and second manhole bodies by mutual coupling, respectively. The first and second manhole bodies are cast to minimize weight.

Description

조립식 맨홀{A fabricated manhole}A fabricated manhole

본 고안은 조립식 맨홀에 관한 것으로, 더욱 상세하게는 맨홀을 분리 형성하여 좁은 장소에서도 취급/운반 등이 용이하도록 한 조립식 맨홀에 관한 것이다.The present invention relates to a prefabricated manhole, and more particularly, to a prefabricated manhole formed by separating the manhole to facilitate handling / transport, etc. even in a narrow place.

맨홀은 노면(路面)에 지하로 작업자가 출입할 수 있도록 하기 위한 것으로서, 설치 장소는 상하수도관의 굵기와 방향이 바뀌는 곳, 기점이나 교차점, 길이가 긴 직선부의 중간에 설치된다.The manhole is for allowing workers to enter and exit the road surface. The installation place is installed in the middle of a place where the thickness and direction of the water and sewage pipe are changed, a starting point, an intersection point, and a long straight part.

종래의 맨홀은 콘크리트를 현장 타설하거나 또는 일정형태로 제작된 콘크리트 기성 제품을 사용하여 시공하고 있었다.Conventional manholes are being constructed using concrete ready-made products that are cast in place or made in a certain form.

그러나, 먼저, 콘크리트를 현장 타설하여 시공하는 기존의 방식으로 맨홀을 제작할 경우에는 일정 형태의 거푸집을 시공하고, 이 시공된 거푸집 내에 배근을 취한 후 일정량의 콘크리트를 타설해 주어야 함에 따라 사실상 시공을 신속 용이하게 완료할 수 없는 문제점이 있고, 또한 공사지연에 따른 통행 불편을 호소하는 민원이 자주 제기되는 문제점이 있으며, 장기간 사용시 배근된 철근이 부식되어 심한 균열 등이 발생되어 보수를 취해야 하는 문제점 등이 있다.However, first, when manufacturing manholes in the existing way of placing concrete on-site, construct a form of formwork, take a reinforcement in the form, and then install a certain amount of concrete. There is a problem that cannot be completed easily, and there is a problem that often complains of a traffic inconvenience due to construction delays, and the problem that the reinforcing steel is corroded due to corrosion and severe cracks, etc. have.

그리고, 일정형태로 제작된 콘크리트 기성 제품을 사용하여 시공하는 기존의 방식은 공장에서 규격에 맞게 제작한 후 현장으로 운반하여 조립거치하기 때문에 상술한 바와 같이 현장에서 타설하여 시공하는 방식에 비해 시공을 신속 용이하게 이룰 수 있고, 시공비가 30~40% 가량 절감되는 등의 여러 가지의 긍정적인 측면이 있는 반면, 각도방향과 높이조정을 전혀 취할 수 없는 형태적 구조로 제작되어 있어 시공과정에서 주변에 위치한 하수관을 연결하는데 상당한 불편과 어려움을 제공하는 문제점도 있다.In addition, the existing method of construction using concrete ready-made products manufactured in a certain form is manufactured in accordance with the standard at the factory, and then transported to the site for assembly. While there are many positive aspects such as quick and easy to achieve, and construction cost is reduced by 30 ~ 40%, it is manufactured in the form of structure that cannot adjust angle and height at all. There are also problems that provide significant inconvenience and difficulty in connecting the sewer pipes located.

본 고안은 상기한 종래 문제점을 해결하기 위한 것으로서, 내구성과 조립성이 우수하여 운반 및 시공을 신속 용이하게 할 수 있도록 한 조립식 맨홀을 제공하려는데 그 목적이 있다.An object of the present invention is to provide a prefabricated manhole that can solve the conventional problems described above, and can be easily transported and installed with excellent durability and assembly.

도 1은 본 고안에 따른 조립식 맨홀의 조립 상태를 나타낸 사시도.1 is a perspective view showing the assembled state of the prefabricated manhole according to the present invention.

도 2는 본 고안에 따른 조립식 맨홀의 분해 사시도.Figure 2 is an exploded perspective view of the prefabricated manhole according to the present invention.

도 3은 본 고안에 따른 조립식 맨홀의 조립 상태를 보인 단면도.Figure 3 is a cross-sectional view showing an assembled state of the prefabricated manhole according to the present invention.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

10,20 : 맨홀몸체, 11,21 : 플랜지10,20: manhole body, 11,21: flange

12,13,22,23 : 개구부, 30 : 체결구12, 13, 22, 23: opening, 30: fastener

40 : 가스켓, 41 : 체결공40: gasket, 41: fastening hole

50 : 맨홀 뚜껑, 100 : 맨홀50: manhole cover, 100: manhole

110 : 입구, 120 : 관연결부110: inlet, 120: pipe connection

상기와 같은 목적을 달성하기 위한 본 고안에 따른 조립식 맨홀은, 운반/시공 등의 취급이 용이하도록 주조 가공된 두 개의 몸체로 분리 형성되어 각각 분리된 상태로 보관/운반되고, 설치시 서로 결합되는 구조인 것을 특징으로 한다.The prefabricated manhole according to the present invention for achieving the above object is formed into two bodies that are cast and processed to facilitate handling, such as transport / construction, each is stored / transported in a separate state, and are coupled to each other during installation It is characterized by the structure.

본 고안의 특징 및 이점들은 첨부도면에 의거한 다음의 상세한 설명으로 더욱 명백해질 것이다. 이에 앞서, 본 명세서 및 청구범위에 사용된 용어나 단어는 고안자가 그 자신의 고안을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 고안의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다.The features and advantages of the present invention will become more apparent from the following detailed description based on the accompanying drawings. Prior to this, terms or words used in the present specification and claims are defined in the technical spirit of the present invention based on the principle that the inventor can appropriately define the concept of the term in order to best describe his or her own design. It must be interpreted to mean meanings and concepts.

도 1 내지 도 3에 도시된 바와 같이, 본 고안에 따른 조립식 맨홀(100)은, 좌우 이등분으로 분할 형성된 제1 및 제2맨홀몸체(10,20)가 서로 결합되어 이루어진다. 즉, 제1 및 제2맨홀몸체(10,20)를 각각 단품으로 보관/운반 후 설치장소에서 서로 결합하여 설치함으로써 운반/취급이 용이하며, 운반/취급이 더욱 용이하도록 제1 및 제2맨홀몸체(10,20)는 주조 가공된다.As shown in Figures 1 to 3, the prefabricated manhole 100 according to the present invention, the first and second manhole body (10, 20) formed by dividing the left and right in half is formed by coupling to each other. That is, the first and second manhole bodies 10 and 20 are separately stored and transported separately, and then installed in combination with each other at the installation place, so that the first and second manholes are easily transported and handled. The bodies 10 and 20 are cast.

제 1 및 제2맨홀몸체(10,20)는 각각 서로 마주보는 일측이 개구된 대략 디귿자 단면으로 이루어지며, 개구부의 둘레부(최소 2개면 이상)에는 서로 접합되어 볼트 등의 체결구(30)를 통해 체결되는 플랜지(11,21)가 형성된다.The first and second manhole bodies 10 and 20 each have a substantially depressed cross section with one side facing each other, and are joined to each other (at least two sides or more) of the opening to fastener 30 such as a bolt. Flange (11, 21) is fastened through is formed.

맨홀(100)은 그 목적에 따라 작업자가 출입할 수 있도록 상부에는 입구(110)가 형성되며, 측부에는 하나 이상의 상하수도관(1)이 연결되는 관연결부(120)가 형성된다. 입구(110)와 관연결부(120)는 각각 제1 및 제2맨홀몸체(10,20)의 결합에 의해 완전한 형상을 갖추게 되는 것으로, 예컨대, 입구(110)는 제1 및 제2맨홀몸체의 상부에 형성된 제1개구부(예컨대 반원형)(12,22)의 결합에 의해 완전한 형상으로 형성되며, 관연결부(120)는 제1 및 제2맨홀몸체(10,20)의 측벽에 형성된 제2개구부(예컨대 반원형)(13,23)의 결합에 의해 완전한 형상으로 형성된다.The manhole 100 has an inlet 110 is formed in the upper portion so that the worker can enter and exit according to the purpose, the side portion is formed with a pipe connection portion 120 is connected to one or more water pipes. The inlet 110 and the pipe joint 120 have a complete shape by coupling the first and second manhole bodies 10 and 20, respectively. For example, the inlet 110 is formed of the first and second manhole bodies. It is formed in a perfect shape by the combination of the first opening (for example semi-circular) (12, 22) formed in the upper portion, the pipe connection portion 120 is the second opening formed on the side walls of the first and second manhole body (10, 20) (E.g., semicircular) 13, 23 to form a perfect shape.

관연결부(120)는 제1 및 제2맨홀몸체(10,20)의 결합에 의해 형성되는 것에 한정되지 않고, 완전한 형상의 것이 제1 및 제2맨홀몸체(10,20)에 형성될 수도 있다.The connection part 120 is not limited to being formed by the combination of the first and second manhole bodies 10 and 20, and a perfect shape may be formed on the first and second manhole bodies 10 and 20. .

맨홀(100)이 제1 및 제2맨홀몸체(10,20)의 결합에 의해 이루어지기 때문에 그들의 연결부를 통해 상하수/이물질이 유입될 수 있으므로 이를 방지하기 위하여 제1 및 제2맨홀몸체(10,20)의 사이에는 가스켓(40)이 개재된다. 가스켓(40)은 탄성력을 가지며 띠형태로 이루어지면서 체결공(41)이 형성되어 제1 및 제2맨홀몸체(10,20)의 플랜지(11,21) 사이에 개재되면서 제1 및 제2맨홀몸체(10,20)를 체결하는 체결구(30)로 체결된다. 가스켓(40)은 제1 및 제2맨홀몸체(10,20)의 체결력에 의해 탄성변형되면서 그 사이를 수밀하게 된다.Since the manhole 100 is made by the combination of the first and second manhole bodies 10 and 20, water and sewage / foreign material may flow through their connecting parts, so that the first and second manhole bodies 10 and 10 may be prevented. The gasket 40 is interposed between 20). The gasket 40 has an elastic force and is formed in a belt shape, and a fastening hole 41 is formed to be interposed between the flanges 11 and 21 of the first and second manhole bodies 10 and 20, and thus the first and second manholes. Fasteners 30 are fastened to the bodies 10 and 20. The gasket 40 is elastically deformed by the fastening force of the first and second manhole bodies 10 and 20 and is watertight therebetween.

맨홀(100)의 입구(110)에는 입구(110)를 개폐하는 맨홀뚜껑(50)이 설치된다.The inlet 110 of the manhole 100 is provided with a manhole cover 50 for opening and closing the inlet 110.

맨홀몸체(10,20)의 내구성 향상, 부식 방지 등을 목적으로 그 내외면에 코팅막이 형성된다.Coating films are formed on the inner and outer surfaces of the manhole bodies 10 and 20 for the purpose of improving durability and preventing corrosion.

이와 같이 구성된 본 고안에 따른 조립식 맨홀의 작용을 설명한다.The operation of the prefabricated manhole according to the present invention configured as described above will be described.

맨홀(100)을 구성하는 맨홀몸체(10,20)는 각각 단품으로 독립된 상태로 적층되어 보관된다.The manhole bodies 10 and 20 constituting the manhole 100 are stored separately stacked in a single state.

맨홀(100)의 설치를 위해서는 보관 중인 맨홀몸체(10,20)를 2개 한 셋트로 하여 운반한다(맨홀몸체(10,20)는 좌우 대칭형이기 때문에 보관/운반시에는 서로 구분되지 않는다.). 맨홀몸체(10,20)는 크레인 등의 운반장치를 이용하여 운반될 수 있고, 한편 운반장치를 이용할 수 없는 좁은 장소에 맨홀(100)을 설치할 경우 맨홀몸체(10,20)가 서로 분리 상태이고 인력으로 충분히 운반할 수 있는 중량이기 때문에 무리없이 맨홀몸체(10,20)를 운반할 수 있다.In order to install the manhole 100, the manhole bodies 10 and 20 being stored are carried in one set (manhole bodies 10 and 20 are symmetrical and thus are not distinguished from each other during storage / transport). . The manhole bodies 10 and 20 may be transported using a transport device such as a crane. Meanwhile, when the manhole 100 is installed in a narrow place where the transport device cannot be used, the manhole bodies 10 and 20 are separated from each other. Since the weight can be sufficiently carried by the manpower can be carried without hesitation the manhole body (10, 20).

이처럼 맨홀몸체(10,20)를 설치 장소로 운반한 후, 각 맨홀몸체(10,20)의 플랜지(11,21) 사이에 가스켓(40)을 개재하고(가스켓(40)을 접착제, 접착시트 등을 통해 플랜지(11,21)에 가접착하여 설치할 수 있음), 관연결부(120)에 상하수도관(1)을 삽입 연결한 후, 체결구(30)를 플랜지(11,21)에 체결하여 제1 및 제2맨홀몸체(10,20)를 서로 결합하고, 입구(110)에 맨홀 뚜껑(50)을 결합한 후, 맨홀(100) 주변을 흙으로 채움으로써 맨홀(100)의 설치를 완료한다.After transporting the manhole bodies 10 and 20 to the installation place as described above, the gasket 40 is interposed between the flanges 11 and 21 of the manhole bodies 10 and 20 (the gasket 40 is glued and adhesive sheets). Can be installed by temporarily attaching to the flanges (11, 21), etc.), and after connecting the water supply and sewage pipe (1) to the pipe connection portion 120, and tighten the fastener 30 to the flanges (11, 21) After the first and second manhole bodies 10 and 20 are coupled to each other, the manhole cover 50 is coupled to the inlet 110, and the manhole 100 is filled with soil to complete the installation of the manhole 100. .

이상에서 설명한 바와 같이, 본 고안에 따른 조립식 맨홀에 의하면, 2개로 분할된 맨홀몸체가 설치장소에서 서로 결합됨으로써 크레인과 같은 기계장치를 사용할 수 없는 좁은 공간에서도 인력에 의하여 맨홀몸체를 이동 및 설치할 수 있으므로 설치 및 유지비용이 절감되고, 신속하게 설치할 수 있는 등의 효과가 있다.As described above, according to the prefabricated manhole according to the present invention, the manhole body divided into two can be coupled to each other at the installation place, the manhole body can be moved and installed by manpower even in a narrow space where a machine such as a crane cannot be used. Therefore, the installation and maintenance costs are reduced, and the effect can be quickly installed.

이상, 본 고안을 본 고안의 원리를 예시하기 위한 바람직한 실시예와 관련하여 설명하고 도시하였지만, 본 고안은 그와 같이 도시되고 설명된 그대로의 구성 및 작용으로 한정되는 것이 아니다. 오히려, 첨부된 청구범위의 사상 및 범주를 일탈함이 없이 본 고안에 대한 다수의 변경 및 수정이 가능함을 당업자들은 잘 이해할 수 있을 것이다. 따라서, 그러한 모든 적절한 변경 및 수정과 균등물들도 본 고안의 범위에 속하는 것으로 간주되어야 할 것이다.The invention has been described and illustrated in connection with a preferred embodiment for illustrating the principles of the invention, but the invention is not limited to the configuration and operation as shown and described. Rather, those skilled in the art will appreciate that many modifications and variations of the present invention are possible without departing from the spirit and scope of the appended claims. Accordingly, all such suitable changes, modifications, and equivalents should be considered to be within the scope of the present invention.

Claims (2)

서로 마주보는 일측이 개구된 좌우 대칭형상이면서 개구부의 둘레부에 플랜지(11,21)가 형성되어 가스켓(40)을 사이에 두고 서로 체결구(30)를 통해 결합되는 제1 및 제2맨홀몸체(10,20)로 이루어지며, 상기 제1 및 제2맨홀몸체의 상부와 측부에는 상호 결합에 의해 입구(110)와 관연결부(120)가 각각 형성되는 것을 특징으로 하는 조립식 맨홀.The first and second manhole bodies, which are symmetrical in shape with one side facing each other and have flanges 11 and 21 formed at the periphery of the opening, are coupled to each other through the fastener 30 with the gasket 40 therebetween. It consists of (10,20), the prefabricated manhole, characterized in that the inlet 110 and the pipe connection portion 120 are formed by the mutual coupling on the upper and side portions of the first and second manhole body, respectively. 제 1 항에 있어서, 상기 제1 및 제2맨홀몸체는 주조 가공된 것을 특징으로 하는 조립식 맨홀.2. The prefabricated manhole according to claim 1, wherein the first and second manhole bodies are cast.
KR20-2004-0027626U 2004-09-24 2004-09-24 A fabricated manhole KR200370053Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20-2004-0027626U KR200370053Y1 (en) 2004-09-24 2004-09-24 A fabricated manhole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20-2004-0027626U KR200370053Y1 (en) 2004-09-24 2004-09-24 A fabricated manhole

Publications (1)

Publication Number Publication Date
KR200370053Y1 true KR200370053Y1 (en) 2004-12-10

Family

ID=49442558

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20-2004-0027626U KR200370053Y1 (en) 2004-09-24 2004-09-24 A fabricated manhole

Country Status (1)

Country Link
KR (1) KR200370053Y1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101448610B1 (en) 2013-12-31 2014-10-13 주식회사 성은특수콘크리트 Concret pour mold for pipe connection part of pc manhole

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101448610B1 (en) 2013-12-31 2014-10-13 주식회사 성은특수콘크리트 Concret pour mold for pipe connection part of pc manhole

Similar Documents

Publication Publication Date Title
US11306478B2 (en) Integrally assembled hidden beam hollow two-way floor system and method for assembling the same
US9151034B2 (en) Turnbuckle for joining structural elements
US5309691A (en) Shear connected structural units
JPS58501957A (en) Method for manufacturing hollow structures such as conduits, silos or shelters
KR100892593B1 (en) Assembly manhole
KR100810424B1 (en) Glass-fiber reinforced plastics manhole having upper portion contact type sealing rubber ring
KR200370053Y1 (en) A fabricated manhole
KR100920198B1 (en) The steel box for the concrete filling type manhole
KR200403877Y1 (en) A connection pipe device of manhole
JP5169924B2 (en) Floor slab bridge, floor slab unit, and method for constructing floor slab bridge
WO2011152660A2 (en) Precast concrete culvert
KR101991071B1 (en) Corrugated steel plate concrete composite structure reinforced with anchor and stud
KR200418633Y1 (en) Jointing structure of concrete manhole
KR200418632Y1 (en) Jointing structure of concrete manhole
KR100777036B1 (en) Manufacturing equipment for a pc box culvert with liner, assembling method for a pc box culvert, manufacturing method for a pc box culvert, and pc box culvert using the same method
KR200268599Y1 (en) Rainwater and polluted water pipe height control structure of manhole
KR101059542B1 (en) manhole
KR100711282B1 (en) Manhole having connection structure a strong
KR200350364Y1 (en) Manhole for water valve
JPH04351390A (en) Hollow structure
AU2012372530A1 (en) Turnbuckle for connecting structural elements
KR970009366B1 (en) A prefabricated sewer pipes
JP3270694B2 (en) Tunnel constructed by approximately trapezoidal resin-coated segments
KR200362348Y1 (en) Assembly type joint pipe
JPS6117641A (en) Coupler for assembled manhole unit and its formation

Legal Events

Date Code Title Description
REGI Registration of establishment
T201 Request for technology evaluation of utility model
T701 Written decision to grant on technology evaluation
G701 Publication of correction
FPAY Annual fee payment

Payment date: 20130102

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20140102

Year of fee payment: 10

EXPY Expiration of term