KR200354891Y1 - Structure of hollow slab beam - Google Patents

Structure of hollow slab beam Download PDF

Info

Publication number
KR200354891Y1
KR200354891Y1 KR20-2004-0010397U KR20040010397U KR200354891Y1 KR 200354891 Y1 KR200354891 Y1 KR 200354891Y1 KR 20040010397 U KR20040010397 U KR 20040010397U KR 200354891 Y1 KR200354891 Y1 KR 200354891Y1
Authority
KR
South Korea
Prior art keywords
hollow slab
slab beam
stress
manufactured
structural
Prior art date
Application number
KR20-2004-0010397U
Other languages
Korean (ko)
Inventor
전찬진
Original Assignee
인덱스엔지니어링 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 인덱스엔지니어링 주식회사 filed Critical 인덱스엔지니어링 주식회사
Priority to KR20-2004-0010397U priority Critical patent/KR200354891Y1/en
Application granted granted Critical
Publication of KR200354891Y1 publication Critical patent/KR200354891Y1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/02Load-carrying floor structures formed substantially of prefabricated units
    • E04B5/04Load-carrying floor structures formed substantially of prefabricated units with beams or slabs of concrete or other stone-like material, e.g. asbestos cement
    • E04B5/043Load-carrying floor structures formed substantially of prefabricated units with beams or slabs of concrete or other stone-like material, e.g. asbestos cement having elongated hollow cores
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/02Load-carrying floor structures formed substantially of prefabricated units
    • E04B5/08Load-carrying floor structures formed substantially of prefabricated units assembled of block-shaped elements, e.g. hollow stones
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/268Composite concrete-metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Rod-Shaped Construction Members (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

내부에 구조보강재가 제공되어 휨모멘트에 대한 응력을 더욱 강화시키고 처짐에 대한 응력이 보강된 중공 슬래브 빔을 제공하기 위하여,Structural reinforcement is provided inside to further strengthen the stress on the bending moment and to provide the hollow slab beam with the stress against deflection.

내부공간의 단면이 대략 박스 형상의 공간부로 이루어지고 그 외부에는 소정의 두께로 이루어진 중공 슬래브 빔에 있어서,In the hollow slab beam having a cross section of an inner space having a substantially box-shaped space and having a predetermined thickness on the outside thereof,

상기 내부공간에는 중공 슬래브 빔의 제작시에는 내부거푸집의 역할을 수행하고, 빔이 제작된 후에는 휨모멘트에 대한 응력 강화 및 처짐에 대한 응력을 보강하는 구조보강재가 설치된 중공 슬래브 빔의 구조를 제공한다.The inner space serves as an internal formwork when the hollow slab beam is manufactured, and after the beam is manufactured, provides a hollow slab beam structure in which a structural reinforcement is installed to reinforce the stress against the bending moment and the deflection stress. do.

상기 구조보강재는 소정의 간격을 유지하며 서로 대응되는 파형으로 연속적으로 절곡된 구조로 이루어진다.The structural reinforcing material is a structure that is continuously bent in a waveform corresponding to each other while maintaining a predetermined interval.

Description

중공 슬래브 빔의 구조{STRUCTURE OF HOLLOW SLAB BEAM}Structure of Hollow Slab Beam {STRUCTURE OF HOLLOW SLAB BEAM}

본 고안은 중공 슬래브 빔에 관한 것으로, 더욱 상세하게는 내부에 구조보강재가 제공되어 휨모멘트에 대한 응력을 더욱 강화시키고 처짐에 대한 응력이 보강된 중공 슬래브 빔에 관한 것이다.The present invention relates to a hollow slab beam, and more particularly, to a hollow slab beam provided with structural reinforcement therein to further strengthen the stress on the bending moment and the stress against deflection.

일반적으로 중공 슬래브는 얇은 두께의 철근 콘크리트로 상자 형태의 단면을 만들고, 이를 스판이 큰 교량이나 건축물의 바닥 구조재로 사용하는 것으로서, 이러한 상자형의 구조물을 서로 맞대어 배치하여 별도의 바닥 슬래브 공사 없이 보와 슬래브를 겸용하는 구조인 관계로 속이 빈 중공슬래브라고 불리워지고 있다.In general, hollow slab is made of thin reinforced steel concrete to make a box-shaped cross section and use it as a floor span of a bridge or a building with a large span. It is called hollow hollow slab because it is a structure that combines and slab.

이러한 중공 슬래브는 프리스트레스의 구조로 만들어 보의 춤이 낮고 공장에서 소정의 규격으로 대량으로 생산할 수 있으므로, 이를 이용한 구조물의 설치에 따른 공사기간이 비교적 짧게 소요되므로 단기간 공사를 완결하여야 하는 교량구조에 적합하다.Since the hollow slab is made of prestressed structure, the dance of the beam is low and can be produced in a large quantity at a predetermined standard in the factory. Do.

이웃나라 일본의 경우 프리스트레스 구조물이 발달하여 있으며, 이와 같은 중공슬래브도 표준화하여 오래 전부터 구조물의 설치에 널리 사용되고 있다.In neighboring countries, prestressed structures have been developed, and hollow slabs have been standardized and widely used for the installation of structures for a long time.

이러한 중공 슬래브는 설치시 현장 가설재가 필요없는 공장제품이지만, 공장에서 제작을 할 때 내부와 외부에는 거푸집이 필요하며, 내부용 거푸집은 슬래브에 매설될 수밖에 없으므로 통상적으로 스티로폼과 같은 재료를 내부거푸집으로 사용하여 중공 슬래브를 제작하게 된다.These hollow slabs are factory products that do not require on-site temporary materials when installed, but formwork is required inside and outside when manufacturing at the factory, and since the internal formwork can only be embedded in the slab, materials such as styrofoam are usually used as internal formwork. To produce a hollow slab.

그러나, 이와 같은 종래의 중공 슬래브 빔은 그 내부에 설치된 내부거푸집은 슬래브를 제작할 때 거푸집의 용도로만 이용되고, 슬래브가 제작된 후에는 아무런 역할을 할 수 없으므로 휨 모멘트와 처짐에 대한 응력이 저하되는 문제점이 있다.However, such a conventional hollow slab beam is used only for the formwork when manufacturing the slab, and the internal formwork installed therein can not play any role after the slab is manufactured, so that the stress on the bending moment and deflection decreases. There is a problem.

또한 종래의 중공 슬래브 빔은, 내부의 빈 공간을 이루도록 내부에 매설되는 내부 거푸집은 중공 슬래브 빔이 제작완료 된 후에도 해체 및 탈형 할 수 없으므로 그에 따른 제작비용이 더 소요되는 단점이 있다.In addition, the conventional hollow slab beam, the inner formwork embedded inside to form an empty space therein can not be dismantled and demolded even after the hollow slab beam is completed, there is a disadvantage that the manufacturing cost accordingly takes more.

본 고안은 상기한 바와 같은 종래의 문제점을 해결하기 위하여 안출된 것으로서, 본 고안의 목적은 중공 슬래브 빔을 제작할 때는 내부거푸집의 역할을 수행하고, 빔이 제작된 후에는 휨 모멘트에 대한 응력을 더욱 강화시키고 처짐에 대한 응력을 보강하는 역할을 수행하는 구조보강재를 갖는 중공 슬래브 빔을 제공하는데 있다.The present invention is devised to solve the conventional problems as described above, the object of the present invention is to perform the role of the internal formwork when manufacturing the hollow slab beam, and after the beam is manufactured to further stress the bending moment To provide a hollow slab beam having a structural stiffener that serves to reinforce and reinforce stress against deflection.

도 1은 본 고안에 의한 중공 슬래브 빔의 구조를 도시한 단면도.1 is a cross-sectional view showing the structure of a hollow slab beam according to the present invention.

도 2는 본 고안에 의한 중공 슬래브 빔에 제공된 구조보강재의 사시도.Figure 2 is a perspective view of the structural reinforcement provided in the hollow slab beam according to the present invention.

도 3은 본 고안에 의한 중공 슬래브 빔의 설치상태를 예시한 도면.3 is a view illustrating an installation state of a hollow slab beam according to the present invention.

본 고안이 제안하는 중공 슬래브 빔은, 내부공간의 단면이 대략 박스 형상의 공간부로 이루어지고 그 외부에는 소정의 두께로 이루어진 중공 슬래브 빔에 있어서,Hollow slab beam proposed by the present invention, in the hollow slab beam made of a cross section of the inner space of the box-shaped space portion and a predetermined thickness outside thereof,

상기 내부공간에는 중공 슬래브 빔의 제작시에는 내부거푸집의 역할을 수행하고, 빔이 제작된 후에는 휨 모멘트에 대한 응력 강화 및 처짐에 대한 응력을 보강하는 구조보강재가 설치된 중공 슬래브 빔을 제공한다.The inner space provides a hollow slab beam provided with a structural reinforcing member which serves as an internal formwork when fabricating the hollow slab beam, and reinforcing stress for bending moment and stress for deflection after the beam is manufactured.

상기 구조보강재는 소정의 간격을 유지하며 서로 대응되는 파형으로 연속적으로 절곡된 구조로 이루어진다.The structural reinforcing material is a structure that is continuously bent in a waveform corresponding to each other while maintaining a predetermined interval.

이하, 본 고안의 바람직한 실시예를 첨부한 도면을 참조하여 더욱 상세히 설명한다.Hereinafter, with reference to the accompanying drawings, preferred embodiments of the present invention will be described in more detail.

도 1은 본 고안에 의한 중공 슬래브 빔의 구조를 나타내는 단면도로서, 본 고안의 중공 슬래브 빔은 빔 본체(2)와, 이 본체(2)의 내부에 대략적인 사각형상으로 형성된 공간부(4)로 이루어진다.1 is a cross-sectional view showing the structure of a hollow slab beam according to the present invention, the hollow slab beam of the present invention is a beam body 2, and the space portion (4) formed in an approximately rectangular shape inside the body (2) Is made of.

상기 빔 본체(2)는 콘크리트(6)와 그 내부에 철근으로 이루어진 보강재(8)로 형성되며, 이러한 빔 본체(2)는 구조계산에 의하여 설계하중을 충분히 견딜 수 있도록 소정의 길이와 크기 및 두께를 갖도록 제작된다.The beam body 2 is formed of a concrete 6 and a reinforcement 8 made of reinforcing bars therein. The beam body 2 has a predetermined length and size so as to withstand the design load by structural calculation. It is manufactured to have a thickness.

이러한 중공 슬래브 빔을 제작하기 위해서는 먼저, 빔의 공간부(4)를 이루도록 내부 거푸집이 설치되어야 하는데, 본 고안에서는 이러한 내부 거푸집은 중공 슬래브 빔의 제작시에는 내부거푸집의 역할을 수행하고, 빔이 제작된 후에는 휨모멘트에 대한 응력 강화 및 처짐에 대한 응력을 보강하도록 이루어진구조보강재(10)로 구성된다.In order to manufacture such a hollow slab beam, first, the inner formwork should be installed to form the space portion 4 of the beam. In the present design, the inner formwork performs the role of the inner formwork when the hollow slab beam is manufactured. After fabrication is made of a structural reinforcement (10) made to reinforce the stress for bending moment and the stress for deflection.

상기 구조보강재(10)는 도 2에 도시된 바와 같이, 소정의 간격을 유지하며 서로 대응되는 방향으로 위치하는 복수의 파형부(12a)(12b)와, 이들 파형부(12a)(12b)들을 소정의 각도로 연결하는 연결부(14)들로 이루어진다.As shown in FIG. 2, the structural reinforcing material 10 includes a plurality of corrugated portions 12a and 12b and a plurality of corrugated portions 12a and 12b which are positioned in directions corresponding to each other while maintaining a predetermined interval. It consists of connecting parts 14 connecting at a predetermined angle.

이러한 구조보강재(10)는 소정의 두께를 갖는 평면의 철판을 프레스 등으로 가압하거나 절곡된 상태로 성형할 수 있다.The structural reinforcing material 10 may be molded in a bent state by pressing or pressing a flat iron plate having a predetermined thickness.

이러한 형상의 구조보강재(10)는 파형부(12a)(12b)들로 인하여 x,y,z축 중에서 y축과 z축 방향으로 더욱 큰 강성이 제공된다.The structural reinforcing material 10 of this shape is provided with greater rigidity in the y-axis and z-axis directions among the x, y, z axis due to the corrugated portion (12a) (12b).

이와 같은 구조보강재(10)는 박스형태로 제공될 수 있으며, 이러한 구조보강재(12)가 설치되면 그와 소정의 거리를 유지하며 보강재(8)를 배근하고 그 외측에 도시되지 않은 외부거푸집을 설치한 후, 구조보강재(10)와 외부거푸집 사이에 콘크리트(6)를 타설하여 일정시간 양생한다.Such a structural reinforcement 10 may be provided in a box form, and when the structural reinforcement 12 is installed, it maintains a predetermined distance therefrom and reinforces the reinforcement 8 and installs an external formwork not shown outside thereof. After that, the concrete 6 is poured between the structural reinforcing material 10 and the external formwork and cured for a predetermined time.

타설된 콘크리트(6)가 양생된 후, 외부거푸집을 해체하면 중공슬래브 빔의 제작이 완료되는데, 콘크리트로 이루어진 빔 본체(2)의 내부에는 철판으로 이루어진 구조보강재(10)가 위치하여 콘크리트와 철판으로 이루어진 합성구조의 형상을 갖게되므로 보의 높이 즉, 본체(2)의 높이를 낮출 수 있고 구조보강재(10)의 강성으로 보의 처짐과 진동을 줄여줄 수 있는 장점을 갖게된다.After the cast concrete is cured, the external formwork is dismantled to complete the production of the hollow slab beam, and the structural reinforcement material 10 made of steel is placed inside the beam body 2 made of concrete, and the concrete and the iron plate are located. Since it has the shape of the composite structure consisting of the height of the beam, that is, the height of the body (2) can be lowered and the rigidity of the structural reinforcement (10) has the advantage of reducing the deflection and vibration of the beam.

이러한 구조의 중공슬래브 빔은 공장에서 제작하여 가설 현장으로 운반한 후, 도 3에서와 같이 길이 방향으로 나란히 설치하고, 그 상부에 슬래브를 타설하면 일정구간의 교량이나 건축물을 축조하게 된다.Hollow slab beam of such a structure is manufactured in the factory and transported to the construction site, and installed side by side in the longitudinal direction as shown in Figure 3, when the slab is placed on the upper part to build a bridge or building of a certain section.

이상 설명한 바와 같이 본 고안에 의한 중공 슬래브 빔은, 내부공간에 파형강판으로 이루어진 구조보강재가 제공된 합성구조이므로 빔의 높이를 종래의 철근콘크리트나 박스형 보다 현저히 낮출 수 있는 장점이 있다.As described above, since the hollow slab beam according to the present invention is a composite structure provided with structural reinforcement made of corrugated steel sheet in the inner space, there is an advantage that the height of the beam can be significantly lower than that of the conventional reinforced concrete or box type.

또한 구조보강재를 제작할 때 약간의 솟음치를 주어 콘크리트에 매설하여 합성구조를 이룰 경우, 프리스트레스와 동일한 효과를 이룰 수 있으므로 빔을 제작하기 위한 재료의 이용을 효과적으로 할 수 있다.In addition, when fabricating the structural reinforcement material to give a little rise to the concrete to form a composite structure, the same effect as the prestress can be achieved, so it is possible to effectively use the material for producing the beam.

Claims (2)

내부공간의 단면이 대략 박스 형상의 공간부로 이루어지고 그 외부에는 소정의 두께로 이루어진 중공 슬래브 빔에 있어서,In the hollow slab beam having a cross section of an inner space having a substantially box-shaped space and having a predetermined thickness on the outside thereof, 상기 내부공간에는 중공 슬래브 빔의 제작시에는 내부거푸집의 역할을 수행하고, 빔이 제작된 후에는 휨 모멘트에 대한 응력 강화 및 처짐에 대한 응력을 보강하는 구조보강재가 제공된 중공 슬래브 빔의 구조.The internal space of the hollow slab beam provided with a structural reinforcing material to serve as an internal formwork during the manufacture of the hollow slab beam, and to reinforce the stress for the bending moment and the deflection stress after the beam is manufactured. 청구항 1에 있어서, 상기 구조보강재는 소정의 간격을 유지하며 서로 대응되는 파형으로 연속적으로 절곡된 구조로 이루어진 중공 슬래브 빔의 구조.The structure of claim 1, wherein the structural reinforcing material has a predetermined interval and is continuously curved in a waveform corresponding to each other.
KR20-2004-0010397U 2004-04-14 2004-04-14 Structure of hollow slab beam KR200354891Y1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20-2004-0010397U KR200354891Y1 (en) 2004-04-14 2004-04-14 Structure of hollow slab beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20-2004-0010397U KR200354891Y1 (en) 2004-04-14 2004-04-14 Structure of hollow slab beam

Publications (1)

Publication Number Publication Date
KR200354891Y1 true KR200354891Y1 (en) 2004-07-05

Family

ID=49347639

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20-2004-0010397U KR200354891Y1 (en) 2004-04-14 2004-04-14 Structure of hollow slab beam

Country Status (1)

Country Link
KR (1) KR200354891Y1 (en)

Similar Documents

Publication Publication Date Title
KR102178461B1 (en) Hollow precast concrete slab with inside partition wall, and manufacturing method for the same
JP2002021240A (en) Precast concrete plate, slab and structure
KR102000534B1 (en) Construction method using textile reinforcing panel of high durability for combined usage of permanent form
KR20200061161A (en) Mold for manufacturing precast concrete double wall standing and manufacturing method of precast concrete double wall using of the same
KR200393006Y1 (en) Connection structure of precast concrete using fiber reinforced plastics construction
KR102047275B1 (en) Composite Precast Wall Systems for Easy Lifting and Installation
KR100757960B1 (en) Two-way hollow core slab and construction method thereof
JPH0419137Y2 (en)
KR200354891Y1 (en) Structure of hollow slab beam
KR101190385B1 (en) Half Precast Concrete Slab Capable of Topping concrete Reduction and Improvement of Attachment Efficiency
KR101688440B1 (en) Reinforcement Member for Beam, Beam Equipped with the Reinforcement Member, Construction Structure Using the Beam
KR101440556B1 (en) Floor structure of modular building
KR100615042B1 (en) Method for producing reinforced concrete structures including spacers
JP2008223242A (en) Manufacturing method for precast concrete panel
JPH116296A (en) Concrete placing work execution method
KR102337880B1 (en) A precast concrete hollow column using square pipe
JP7449699B2 (en) Manufacturing method for precast concrete wall components
CN215367738U (en) Prefabricated caisson and connected node thereof
CN216948993U (en) Assembled superstructure
KR100445254B1 (en) Folded concrete permanent form
JP3751735B2 (en) Concrete slabs and structures
CN113027022A (en) Fully-precast concrete plate cap component and construction method thereof
JPH09155846A (en) Production of precast concrete form
KR20230114790A (en) Bracket reinforcement structure of hollow-core column and its construction method
KR20230134910A (en) Precast concrete inner mould, precast concrete beam using the same and manufacturing, construction method thereof

Legal Events

Date Code Title Description
REGI Registration of establishment
FPAY Annual fee payment

Payment date: 20050314

Year of fee payment: 3

LAPS Lapse due to unpaid annual fee