KR102648051B1 - Self-supporting structure with back-row type bracing device and its construction method - Google Patents

Self-supporting structure with back-row type bracing device and its construction method Download PDF

Info

Publication number
KR102648051B1
KR102648051B1 KR1020230160287A KR20230160287A KR102648051B1 KR 102648051 B1 KR102648051 B1 KR 102648051B1 KR 1020230160287 A KR1020230160287 A KR 1020230160287A KR 20230160287 A KR20230160287 A KR 20230160287A KR 102648051 B1 KR102648051 B1 KR 102648051B1
Authority
KR
South Korea
Prior art keywords
support
inclined brace
wall pile
coupled
ground
Prior art date
Application number
KR1020230160287A
Other languages
Korean (ko)
Inventor
노승오
Original Assignee
주식회사 조은이엔지
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 조은이엔지 filed Critical 주식회사 조은이엔지
Priority to KR1020230160287A priority Critical patent/KR102648051B1/en
Application granted granted Critical
Publication of KR102648051B1 publication Critical patent/KR102648051B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

본 발명은 토목공사나 건축공사 현장에서 터파기에 의해 형성되는 굴착영역에 설치하는 흙막이 구조물의 버팀장치를 구비한 자립구조물 및 이의 시공방법에 관한 것으로, 보다 상세하게 설명하면, 굴착영역의 경계에 상부가 지상으로 돌출되도록 벽체파일을 설치하고, 상기 벽체파일의 후방에 수직하게 어스앵커를 설치하여 협소한 공간에서도 설치가 용이함은 물론 안정성을 확보할 수 있으며, 상기 벽체파일의 상부에 후방이 결합되어 상기 어스앵커를 전방에 고정하는 경사버팀지지대와 상기 경사버팀지지대와 상기 벽체파일의 상부에 경사지는 경사버팀대를 공장에서 제작하여 현장에서 조립설치 및 해체가 용이하여 공사기간 단축 및 자재를 절감할 수 있는 한편, 굴착영역의 내부공간 확보가 용이하여 굴착영역 내부 작업이 원활하게 이루어질 수 있도록 하는 후열식 버팀장치를 구비한 자립구조물 및 그 시공방법에 관한 기술분야가 개시된다.The present invention relates to a self-supporting structure equipped with a support device for an earth retaining structure installed in an excavation area formed by excavation at a civil engineering or building construction site and a construction method thereof. To be described in more detail, the upper part is located at the boundary of the excavation area. Wall piles are installed so that they protrude from the ground, and an earth anchor is installed perpendicularly to the rear of the wall piles, making it easy to install and ensuring stability even in a narrow space. The rear is attached to the top of the wall piles, so that the The inclined brace support that secures the earth anchor to the front and the inclined brace that slopes to the upper part of the inclined brace support and the wall pile are manufactured at the factory and are easy to assemble and dismantle on site, shortening the construction period and saving materials. Meanwhile, the technical field regarding a self-supporting structure equipped with a post-heating support device and its construction method is disclosed, which facilitates securing the internal space of the excavation area and allows work inside the excavation area to be carried out smoothly.

Description

후열식 버팀장치를 구비한 자립구조물 및 그 시공방법{Self-supporting structure with back-row type bracing device and its construction method}Self-supporting structure with back-row type bracing device and its construction method {Self-supporting structure with back-row type bracing device and its construction method}

본 발명은 토목공사나 건축공사 현장에서 터파기에 의해 형성되는 굴착영역에 설치하는 흙막이 구조물의 후열식 버팀장치를 구비한 자립구조물 및 이의 시공방법에 관한 것으로, 보다 상세하게 설명하면, 굴착영역의 경계에 상부가 지상으로 돌출되도록 벽체파일을 설치하고, 상기 벽체파일의 후방에 수직하게 어스앵커를 설치하여 협소한 공간에서도 설치가 용이함은 물론 안정성을 확보할 수 있으며, 상기 벽체파일의 상부에 후방이 결합되어 상기 어스앵커를 전방에 고정하는 경사버팀지지대와 상기 경사버팀지지대와 상기 벽체파일의 상부에 경사지는 경사버팀대를 공장에서 제작하여 현장에서 조립설치 및 해체가 용이하여 공사기간 단축 및 자재를 절감할 수 있는 한편, 굴착영역의 내부공간 확보가 용이하여 굴착영역 내부 작업이 원활하게 이루어질 수 있도록 하는 후열식 버팀장치를 구비한 자립구조물 및 그 시공방법에 관한 것이다.The present invention relates to a self-supporting structure equipped with a post-heating support device for an earth retaining structure installed in an excavation area formed by excavation at a civil engineering or building construction site and a construction method thereof. To be described in more detail, the present invention relates to a self-supporting structure and a construction method thereof, located at the boundary of the excavation area. Wall piles are installed so that the upper part protrudes from the ground, and an earth anchor is installed perpendicularly to the rear of the wall pile, making it easy to install even in a narrow space and ensuring stability, and the rear is connected to the upper part of the wall pile. The inclined brace support that secures the earth anchor to the front, the inclined brace support, and the inclined brace that is inclined to the upper part of the wall pile are manufactured at the factory, making it easy to assemble and dismantle on site, shortening the construction period and saving materials. On the other hand, it relates to a self-supporting structure equipped with a post-heating support device and a construction method thereof that facilitates securing of the internal space of the excavation area so that work inside the excavation area can be carried out smoothly.

일반적으로 흙막이 공법이란 지하공사를 원활하게 할 수 있도록 굴토벽면의 붕괴나 토사의 유입을 방지하기 위한 목적으로 설치되는 가설구조물로써 안전성과 시공성은 물론 경제성도 동시에 요구되는 시설이다.In general, the earth retaining method is a temporary structure installed for the purpose of preventing the collapse of the excavation wall or the inflow of soil to facilitate underground construction, and is a facility that requires not only safety and constructability but also economic efficiency.

또한, 흙막이 벽체공법은 HPILE+토류판, CIP, SCW 공법이나 SHEET PILE 벽체공법 및 조립식 간이 흙막이 설치공법등이 주로 사용되고 있으며 설치현장의 토질 및 지하수위등 제반조건 등에 따라 적합한 공법이 선택되어 설치되며 지하매설물의 노선선정, 매설형태(매설폭 및 심도)결정, 토압계산, 안전율적용, 흙막이의 필요, 강도계산, 공사비 비교 등을 종합적으로 검토하여 흙막이 벽체공법의 선정 및 설계 시공순으로 결정된다.In addition, the earth retaining wall method is mainly used as HPILE + earth plate, CIP, SCW method, SHEET PILE wall method, and prefabricated simple earth retaining installation method. The appropriate method is selected and installed depending on the soil quality and groundwater level of the installation site and other general conditions. A comprehensive review of route selection, burial type (burial width and depth) determination, earth pressure calculation, safety factor application, need for earth retaining, strength calculation, construction cost comparison, etc. is conducted in order of selection and design of earth retaining wall construction method.

흙막이 벽체공법의 일반적인 예로 지지말뚝+토류판 공법은 수직하게 설치된 복수개의 지지말뚝(H 빔)과, 이들 지지말뚝 사이에 결합되어 후방의 지반이 전방으로 무너지는 것을 방지하는 토류판을 포함하는 구성으로 이루어진다.A common example of an earth retaining wall method is the support pile + earth plate method, which consists of a plurality of vertically installed support piles (H beams) and an earth plate that is coupled between these support piles to prevent the rear ground from collapsing forward. .

이때 토류판으로는 소정 규격의 목재판 또는 강재판이 사용되며, 이를 적층하여 벽체를 형성하고, 그 적층된 토류판을 고정하기 위하여 끼움목(쐐기)을 설치한 구조를 갖는다.At this time, wooden or steel plates of a certain standard are used as the earth plates, which are stacked to form a wall, and a structure in which wedges (wedges) are installed to fix the stacked earth plates.

이와 같은 지지말뚝의 흙막이 벽체공법은 고심도의 터파기 공사를 수행하는 경우, H 빔만으로는 배후토사의 토압에 저항할 수 없으므로, 이를 보강하기 위하여 터파기 공사구간 쪽에 많은 수의 지보재(Strut, Earth Anchor, Raker 등)를 사용해야 하는데, 이러한 방식은 공사기간이 많이 소요되고 비경제적일 뿐만 아니라, 작업공간의 확보를 어렵게 하고, 구조적으로 비효율적이므로 주변지반 침하의 우려가 높고, 상부두부 변위가 상대적으로 크게 발생하므로 배면부 지반의 이완이 크게 발생하는 문제점이 발생하였다.In the case of performing high-depth excavation work, such a supporting pile retaining wall method cannot resist the earth pressure of the background soil with only H beams, so to reinforce this, a large number of supporting materials (Strut, Earth) are installed on the excavation construction section. anchor, raker, etc.), but this method not only requires a long construction period and is uneconomical, but also makes it difficult to secure work space, and is structurally inefficient, so there is a high risk of surrounding ground subsidence, and the displacement of the upper head is relatively high. As this occurred significantly, the problem of significant loosening of the ground at the rear occurred.

상기와 같은 문제점을 해결하기 위한 선행기술로 대한민국 등록특허공보 제10-0964993호(2010.06.21.)에는 고심도의 터파기 작업을 수행하는 경우에도 지보재(Strut, Earth Anchor, Raker 등) 없이 배후토사의 토압에 충분히 저항하도록 하고, 흙막이 구조물의 전체적인 변위의 발생을 억제할 수 있도록 하는 고심도 2열식 억지말뚝 흙막이 벽체공법을 제시하고 있으며 이러한 고심도 2열식 억지말뚝 흙막이 벽체공법을 통하여 배후토사의 토압에 충분히 저항하도록 하고 흙막이 구조물의 전체적인 변위발생을 억제할 수 있는 기술이 제공되었다.As a prior art to solve the above problems, Korea Patent Publication No. 10-0964993 (June 21, 2010) discloses that even when performing high-depth excavation work, there is no support material (Strut, Earth Anchor, Raker, etc.). We propose a high-depth two-row pile retaining wall construction method that sufficiently resists the earth pressure of the soil and suppresses the occurrence of overall displacement of the retaining structure. Through this high-depth, two-row suppressed pile retaining wall construction method, the background soil is maintained. A technology has been provided that can sufficiently resist earth pressure and suppress the overall displacement of the retaining structure.

상기와 같은 2열식 억지말뚝 흙막이 벽체공법의 구성적 특징을 살펴보면 도 4에 도시한 바와 같이 1열 엄지말뚝과 2열 억지말뚝을 일정간격 이격된 상태로 지면과 수직되게 근입한 상태에서 상부를 연결부재를 통하여 연결함으로써 대략 "П"의 형태로 말뚝을 설치함으로써 기존 1열의 말뚝을 이용한 흙막이 벽체공법에 비하여 더욱 우수하게 배후토사의 압력에 충분히 저항함으로써 흙막이 말뚝의 변형을 방지할 수 있는 공법이 개시되어 있다.Looking at the structural characteristics of the two-row interference pile retaining wall method as described above, as shown in Figure 4, the upper part of the first-row thumb pile and the second-row interference pile are connected perpendicular to the ground at a certain distance apart. A method is disclosed that can prevent deformation of retaining piles by sufficiently resisting the pressure of the background soil, which is superior to the existing retaining wall method using a single row of piles by installing piles in an approximate "П" shape by connecting them through members. It is done.

그러나 상기와 같이 2열식 억지말뚝 흙막이 벽체공법 또한 1열식 흙막이 벽체공법에 비하여 높은 토압에 대한 저항치수가 높은 것은 확인할 수 있으나 구조적인 휨으로 인해 변위가 크게 발생하는 문제점이 계속하여 발생하였다.However, as described above, it can be confirmed that the two-row retaining pile wall method has a higher resistance to high earth pressure compared to the one-row retaining pile method, but the problem of large displacement due to structural bending continues to occur.

또한, 이러한 2열 억지말뚝의 저항력을 높이기 위하여 말뚝의 내측으로 앵커 또는 레일을 부가적으로 설치함으로써 흙막이 공사의 공기가 길어지고 설치비가 증가하는 문제점이 발생하였다.In addition, in order to increase the resistance of these two-row restraining piles, anchors or rails were additionally installed on the inside of the piles, which resulted in the problem of lengthening the period of earth retaining construction and increasing installation costs.

또 다른 선행기술로는 대한민국 등록특허공보 제10-1262357호(2013.05.08.)의 지주식 흙막이 공법이 제공되고 있으며, 그 구성은 보링장치로 일정간격을 두고 다수개의 흙막이용 지주구멍을 천공하는 구멍천공단계와, 천공된 지주구멍에 제1지주말뚝과 제2지주말뚝을 각각 근입하는 지주설치단계와, 상기 제1지주말뚝과 제2지주말뚝의 상단 연결부분을 결속수단을 이용하여 연결하는 결속단계와, 상기 제1지주말뚝과 제2지주말뚝이 연결된 상태에서 제1지주말뚝의 일측면이 노출되도록 지면을 굴착하는 굴착단계와, 상기 노출된 제1지주말뚝과 노출된 제1지주말뚝 사이에 흙막이판을 설치하는 흙막이판 설치단계;를 포함하고, 상기 제2지주말뚝은 하단부에 고정부가 가접(假接)되어 인발부와 고정부로 분할 형성하고 상기 제2지주말뚝의 외주면에 하나 이상의 와이어가 밀착되며 끝부분을 피복하여 노출된 강선이 고정부에 연결되는 지주식 흙막이 공법에 있어서, 상기 고정부는 일측이 상기 제2지주말뚝의 끝부분에 가접되며 표면에 여러 개의 구멍을 갖는 강관과, 상기 강관의 내부에 형성되는 여러 개의 스페이스와, 상기 강관 내부에서 여러 개의 스페이서를 연결고정하는 결속선 및 상기 강관의 내부에 삽입되며 와이어로부터 피복되어 노출된 하나 이상의 강선을 포함하며, 여기서, 상기 강관의 외측에 콘크리트를 타설함으로서 콘크리트가 강관의 구멍을 통하여 강관의 내부와 외부로 고르게 타설되어 고정부와 내부에 삽입된 강선을 견고하게 양생한 것으로 이루어진 지주식 흙막이 공법을 제공하고 있다.Another prior art is the prop-type earth retaining method of Republic of Korea Patent Publication No. 10-1262357 (May 8, 2013), which consists of drilling a plurality of retaining support holes at regular intervals with a boring device. A hole drilling step, a prop installation step of inserting the first and second prop piles into the drilled prop holes, and the upper connecting portions of the first and second prop piles are connected using a binding means. A binding step, an excavation step of excavating the ground so that one side of the first support pile is exposed while the first support pile and the second support pile are connected, and the exposed first support pile and the exposed first support pile. It includes a retaining plate installation step of installing a retaining plate between them, wherein the second support pile is divided into a drawing part and a fixing part by tack welding a fixing part at the lower end, and one is formed on the outer peripheral surface of the second support pile. In the prop-type earth retaining method in which the above wires are closely adhered and the exposed steel wire that covers the ends is connected to the fixing part, the fixing part is a steel pipe that is tack-welded on one side to the end of the second support pile and has several holes on the surface. And, a plurality of spaces formed inside the steel pipe, a tie line for connecting and fixing a plurality of spacers inside the steel pipe, and one or more steel wires inserted into the inside of the steel pipe and exposed by being covered with a wire, wherein, By pouring concrete on the outside of the steel pipe, the concrete is evenly poured into the inside and outside of the steel pipe through the holes of the steel pipe to firmly cure the fixing part and the steel wire inserted inside.

이러한 구성의 경우 제1지주말뚝과 제2지주말뚝을 각각 경사지게 설치하여 상단이 서로 만나도록 한 것으로 시공성이 떨어지고, 장소가 협소한 도심지역에서 경사진 제1지주말뚝과 제2지주말뚝을 시공하는 지주구멍을 천공하기 위한 공간확보에 어려움이 있어 현장 적용에 어려움이 있었다.In this configuration, the first and second support piles are installed at an angle so that the upper ends meet each other, which reduces constructability, and it is difficult to construct the inclined first and second support piles in urban areas where the space is limited. There were difficulties in field application due to difficulties in securing space to drill support holes.

대한민국 공개특허 제10-2020-0124949호(2020.11.04.)Republic of Korea Patent Publication No. 10-2020-0124949 (2020.11.04.) 대한민국 등록특허 제10-1498711호(2015.02.26.)Republic of Korea Patent No. 10-1498711 (2015.02.26.)

본 발명은 상술한 종래기술에 따른 문제점을 해결하고자 안출된 기술로서, 종래의 흙막이 공법에 사용되는 구조물은 구조적인 휨으로 인해 변위가 크게 발생하고, 시공성이 떨어지며, 장소가 협소한 도심지역에서 공사시 공간을 확보하기 어려울 뿐만 아니라 굴착영역 내부의 공간에 추가적인 구조물이 설치되는 경우 굴착영역 내부 공간확보가 어려워 작업에 제한이 발생되는 문제점이 발생하는 바,The present invention is a technology developed to solve the problems caused by the prior art described above. The structures used in the conventional earth retaining method have large displacements due to structural bending, have poor constructability, and are difficult to construct in urban areas where the space is limited. Not only is it difficult to secure space, but if additional structures are installed in the space inside the excavation area, it is difficult to secure space inside the excavation area, which causes limitations in work.

굴착영역의 경계에 설치되는 벽체파일의 후방에 수직하게 어스앵커를 설치하여 협소한 공간에서도 설치가 용이하고, 굴착영역 내부 공간의 확보가 용이하여 작업이 원활하게 이루어질 수 있도록 하며, 상기 벽체파일과 어스앵커를 경사버팀지지대와 경사버팀대를 통해 견고하게 고정 및 연결하여 상기 벽체파일이 안정적으로 설치된 상태를 유지할 수 있도록 하되, 상기 경사버팀지지대와 경사버팀대를 조립식으로 설치하여 시공이 용이하므로 공사기간을 확보할 수 있는 후열식 버팀장치를 구비한 자립구조물 및 시공방법을 제공하는 것이다.An earth anchor is installed vertically at the rear of the wall pile installed at the boundary of the excavation area, making it easy to install even in a narrow space. It is easy to secure the space inside the excavation area to ensure smooth work, and the wall pile and The earth anchor is firmly fixed and connected through the inclined brace supports and the inclined braces to ensure that the wall piles remain stably installed. However, the inclined brace supports and the inclined braces are installed in a prefabricated manner to facilitate construction, shortening the construction period. The purpose is to provide a self-supporting structure and construction method equipped with a rear-heating support device that can be secured.

본 발명은 상기와 같은 소기의 목적을 실현하고자, 터파기에 형성된 굴착영역(10)의 경계에 설치되되, 상부가 지상으로 돌출되도록 설치되는 벽체파일(100);과 상기 벽체파일(100)의 후방에 이격되어 지중에 수직하게 설치되는 어스앵커(200);와 지면에 안착되어 설치되되, 전방이 상기 벽체파일(100)의 후면에 결합되고, 후방에 상기 어스앵커(200)의 상부가 관통된 후 고정되는 경사버팀지지대(300); 및 상기 경사버팀지지대(300)의 상부면에 하부가 결합되고, 상기 벽체파일(100)의 상부에 상부가 결합되어 경사지게 설치되는 경사버팀대(400);를 포함하여 구성되는 것을 특징으로 하는 후열식 버팀장치를 구비한 자립구조물을 제시한다.In order to achieve the above-mentioned object, the present invention provides a wall pile (100) installed at the border of the excavation area (10) formed in the trench, with the upper part protruding from the ground; and the rear of the wall pile (100). an earth anchor (200) installed vertically in the ground and spaced apart; and an earth anchor (200) installed while seated on the ground, the front of which is coupled to the rear of the wall pile (100), and the upper part of the earth anchor (200) penetrating the rear. An inclined brace support (300) that is fixed afterward; And an inclined brace 400, the lower part of which is coupled to the upper surface of the inclined brace support 300, and the upper part of which is coupled to the upper part of the wall pile 100, and which are installed inclinedly. A self-supporting structure equipped with a supporting device is presented.

또한, 본 발명의 상기 경사버팀지지대(300)는 상부플랜지와 하부플랜지의 후방에 각각 관통형성되되, 웨브를 중심으로 일측과 타측에 대향되도록 형성되는 한 쌍의 관통홀(310);과 상기 상부플랜지의 한 쌍의 관통홀(310)을 덮도록 안착되어 설치되고, 상기 관통홀(310)과 연통되도록 복수 개의 고정홀(322)이 형성되는 제1플레이트(320); 및 하부방향으로 갈수록 외경과 내경이 좁아지도록 형성되고, 상기 고정홀(322)의 상부에 하부가 끼워져 결합되는 웨지(330);를 포함하여 구성되고, 상기 어스앵커(200)는 지중에 삽입되어 고정되는 내하체(210);와 상기 내하체(210)에 하부가 결합되고, 상기 관통홀(310)과 고정홀(322)을 관통하며, 상기 웨지(330)가 상부 외주연에 결합되는 강연선(220);을 포함하여 구성되는 것을 특징으로 한다.In addition, the inclined support support 300 of the present invention has a pair of through holes 310 formed through the rear of the upper flange and the lower flange, respectively, and formed to face each other on one side and the other around the web; and the upper part. A first plate 320 that is seated and installed to cover a pair of through holes 310 of the flange and has a plurality of fixing holes 322 formed to communicate with the through holes 310; and a wedge 330 whose outer diameter and inner diameter are formed to become narrower toward the bottom, and whose lower part is fitted and coupled to the upper part of the fixing hole 322. The earth anchor 200 is inserted into the ground. An inner body 210 that is fixed; and a strand whose lower part is coupled to the inner body 210, penetrates the through hole 310 and the fixing hole 322, and the wedge 330 is coupled to the upper outer periphery. It is characterized in that it includes (220);

또한, 본 발명의 상기 경사버팀지지대(300)는 상기 어스앵커(200)의 전방에 위치되도록 관통형성되되, 웨브를 중심으로 일측과 타측에 관통형성되는 복수 개의 결합홀(340);을 포함하여 구성되고, 상기 경사버팀대(400)는 하부 말단에 형성되고, 상기 결합홀(340)과 대응되는 복수 개의 체결홀(412)이 형성되는 결합판(410);을 포함하여 구성되는 것을 특징으로 한다.In addition, the inclined brace support 300 of the present invention is formed through a penetrating position to be located in front of the earth anchor 200, and includes a plurality of coupling holes 340 formed through one side and the other side centered on the web. It is configured, and the inclined brace 400 is formed at the lower end, and is characterized in that it includes a coupling plate 410 on which a plurality of fastening holes 412 corresponding to the coupling holes 340 are formed. .

또한, 본 발명의 상기 경사버팀대(400)는 상부 말단에 형성되고, 상기 벽체파일(100)이 관통되어 고정되는 연결부재(420);를 포함하여 구성되는 것을 특징으로 한다.In addition, the inclined brace 400 of the present invention is formed at the upper end, and is characterized by including a connecting member 420 through which the wall pile 100 is fixed.

또한, 본 발명의 상기 연결부재(420)는 상기 경사버팀대(400)의 상부 말단에 후방이 결합되고, 전방에 상기 벽체파일(100)의 후방이 내입되는 'ㄷ'형태의 제1커플러(422);와 상기 제1커플러(422)와 대향되도록 위치된 후 복수 개의 볼트를 통해 상기 벽체파일(100)과 결합되는 'ㄷ'형태의 제2커플러(423);를 포함하여 구성되는 것을 특징으로 한다.In addition, the connecting member 420 of the present invention is coupled at the rear to the upper end of the inclined brace 400, and the first coupler 422 of the 'ㄷ' shape is inserted into the rear of the wall pile 100 at the front. ); and a 'ㄷ' shaped second coupler 423 that is positioned opposite the first coupler 422 and then coupled to the wall pile 100 through a plurality of bolts. do.

또한, 본 발명의 상기 제1커플러(422)와 제2커플러(423)는 후방 또는 전방 일측과 타측에 돌출형성되는 결합플랜지(424);와 상부 외측면과 하부 외측면에 각각 돌출형성되는 한 쌍의 외곽 스티프너(425); 및 상기 결합플랜지(424)와 측면을 연결하도록 형성되는 복수 개의 보강 스티프너(426);를 포함하여 구성되는 것을 특징으로 한다.In addition, the first coupler 422 and the second coupler 423 of the present invention have a coupling flange 424 protruding on one rear or front side and the other side; and a coupling flange 424 protruding on the upper outer surface and the lower outer surface, respectively. Pair of outer stiffeners (425); And a plurality of reinforcing stiffeners 426 formed to connect the coupling flange 424 and the side surface.

또한, 본 발명의 상기 제2커플러(423)는 후면에 형성되는 보강부(423a);와 상기 제2커플러(423)의 측면까지 연장형성되는 연장보강부(423a-1);를 포함하여 구성되는 것을 특징으로 한다.In addition, the second coupler 423 of the present invention includes a reinforcing portion 423a formed on the rear side; and an extension reinforcing portion 423a-1 extending to the side of the second coupler 423. It is characterized by being

또한, 본 발명은 상기와 같은 후열식 버팀장치를 구비한 자립구조물의 시공방법에 있어서, 벽체파일(100)을 지중에 수직하게 삽입하여 설치하되, 상부가 지상으로 돌출되도록 설치하는 제1단계(S10);와 상기 벽체파일(100)의 후방에 이격되어 지중에 수직하게 어스앵커(200)를 설치하는 제2단계(S20);와 지면에 경사버팀지지대(300)를 설치하되, 상기 어스앵커(200)의 상부가 상기 경사버팀지지대(300)의 후방을 관통하고, 상기 경사버팀지지대(300)의 전방이 벽체파일(100)의 후면에 결합되도록 하는 제3단계(S30);와 상기 벽체파일(100)의 상부에 상기 경사버팀대(400)의 상부를 결합하고, 상기 경사버팀지지대(300)의 상부면에 경사버팀대(400)의 하부를 결합하되, 상기 경사버팀대(400)를 경사지게 설치하는 제4단계(S40); 및 상기 어스앵커(200)를 인장하여 상기 벽체파일(100)이 견고하게 고정되도록 하는 제5단계(S50);를 포함하여 구성되는 것을 특징으로 하는 후열식 버팀장치를 구비한 자립구조물 시공방법을 제시한다.In addition, the present invention relates to a construction method of a self-supporting structure equipped with a rear-heating bracing device as described above, the first step of installing the wall pile 100 by inserting it vertically into the ground, but installing the wall pile 100 so that the upper part protrudes from the ground ( S10); and a second step (S20) of installing the earth anchor 200 vertically in the ground and spaced apart from the rear of the wall pile 100; and installing an inclined support support 300 on the ground, wherein the earth anchor A third step (S30) in which the upper part of (200) penetrates the rear of the inclined brace support 300 and the front of the inclined brace support 300 is coupled to the rear of the wall pile 100; and the wall The upper part of the inclined brace 400 is coupled to the upper part of the pile 100, and the lower part of the inclined brace 400 is coupled to the upper surface of the inclined brace support 300, and the inclined brace 400 is installed at an angle. The fourth step (S40); And a fifth step (S50) of tensioning the earth anchor 200 to ensure that the wall pile 100 is firmly fixed. present.

상기와 같이 제시된 본 발명에 의한 후열식 버팀장치를 구비한 자립구조물 및 시공방법은 벽체파일, 어스앵커, 경사버팀지지대 및 경사버팀대를 규격화시켜 공장 등에서 제작함에 따라 현장에서 조립시공 및 해체가 용이하므로 공사기간을 단축시킬 수 있는 효과를 얻을 수 있다.The self-supporting structure and construction method equipped with a rear-heating brace according to the present invention presented as described above is manufactured in a factory by standardizing wall piles, earth anchors, inclined brace supports, and inclined braces, making it easy to assemble and dismantle on site. This can have the effect of shortening the construction period.

또한, 본 발명은 'ㄷ' 형태의 한 쌍의 연결부재를 통해 상기 경사버팀대와 벽체파일을 결합함으로써, 별도의 브라켓 및 띠장 설치가 필요없어 시공이 간편하게 이루어질 수 있는 효과 및 벽체파일의 손상을 최소화하여 상기 벽체파일의 강성이 저하되는 것을 방지할 수 있는 효과를 얻을 수 있다.In addition, the present invention combines the inclined brace and the wall pile through a pair of 'ㄷ' shaped connecting members, which eliminates the need for installation of separate brackets and strips, making construction easy and minimizing damage to the wall pile. Thus, it is possible to obtain the effect of preventing the rigidity of the wall pile from being reduced.

또한, 본 발명은 상기 경사버팀지지대에 복수 개의 관통홀이 형성되고, 상기 경사버팀대에 상기 관통홀과 대응되는 체결홀이 형성된 결합판을 통해 경사버팀지지대와 경사버팀대의 체결시 시공의 정밀도를 높일 수 있는 효과 및 시공시간을 단축할 수 있는 효과를 얻을 수 있다.In addition, the present invention increases the precision of construction when fastening the inclined brace support and the inclined brace through a coupling plate in which a plurality of through holes are formed in the inclined brace support and fastening holes corresponding to the through holes are formed in the inclined brace. You can achieve the effect of shortening the construction time and the effect that can be achieved.

또한, 본 발명은 상기 벽체파일이 후방 즉, 굴착영역의 후방에 상기 벽체파일과 이격되어 수직하게 어스앵커를 설치함으로써, 경사버팀의 변위를 억제할 수 있는 효과와, 좁은 공사공간에서도 시공이 가능한 효과를 얻을 수 있으며, 별도의 콘크리트블럭이 필요 없어 시공비용 및 시공시간을 단축할 수 있는 효과를 얻을 수 있다.In addition, the present invention has the effect of suppressing the displacement of the slope support by installing an earth anchor vertically and spaced apart from the wall pile at the rear of the wall pile, that is, at the rear of the excavation area, and allows construction even in a narrow construction space. The effect can be achieved and the construction cost and construction time can be reduced as there is no need for a separate concrete block.

또한, 본 발명은 벽체파일과 경사버팀지지대에 경사지게 경사버팀대를 설치하고 상기 경사버팀대를 어스앵커로 고정함으로써, 상기 벽체파일이 전도나 휨에 용이하게 저항할 수 있어 견고하게 지지되는 효과를 얻을 수 있다.In addition, the present invention installs an inclined brace at an angle on the wall pile and the inclined brace support and fixes the inclined brace with an earth anchor, so that the wall pile can easily resist falling or bending, thereby achieving the effect of being firmly supported. there is.

또한, 본 발명은 상기 어스앵커와 경사버팀지지대 및 경사버팀대가 벽체파일의 후방에 설치되는 구조로 인해 굴착영역의 내부 작업공간이 확보되고, 이에 따라 굴착영역 내부 작업이 원활하게 이루어질 수 있는 효과를 얻을 수 있다.In addition, the present invention has the effect that the internal work space of the excavation area is secured due to the structure in which the earth anchor, inclined support support, and inclined support are installed at the rear of the wall pile, and thus work inside the excavation area can be performed smoothly. You can get it.

도 1은 본 발명의 바람직한 실시예에 의한 자립구조물을 나타낸 측면도.
도 2는 본 발명의 바람직한 실시예에 의한 자립구조물을 나타낸 사시도.
도 3은 본 발명의 바람직한 실시예에 의한 자립구조물의 경사버팀대와 벽체파일을 나타낸 분해 사시도.
도 4는 본 발명의 바람직한 실시예에 의한 자립구조물의 경사버팀지지대와 벽체파일을 나타낸 부분 분해 사시도.
도 5는 본 발명의 바람직한 실시예에 의한 경사버팀지지대와 경사버팀대를 나타낸 부분 분해 사시도.
도 6은 본 발명의 바람직한 실시예에 의한 경사버팀지지대와 어스앵커를 나타낸 부분 분해 사시도.
도 7은 본 발명의 바람직한 실시예에 의한 시공방법의 제1단계를 개략적으로 나타낸 측면도.
도 8은 본 발명의 바람직한 실시예에 의한 시공방법의 제2단계를 개략적으로 나타낸 측면도.
도 9는 본 발명의 바람직한 실시예에 의한 시공방법의 제3단계와 제4단계를 개략적으로 나타낸 측면도.
도 10은 본 발명의 바람직한 실시예에 의한 시공방법의 제5단계를 개략적으로 나타낸 측면도.
1 is a side view showing a self-supporting structure according to a preferred embodiment of the present invention.
Figure 2 is a perspective view showing a self-supporting structure according to a preferred embodiment of the present invention.
Figure 3 is an exploded perspective view showing an inclined brace and wall pile of a self-supporting structure according to a preferred embodiment of the present invention.
Figure 4 is a partially exploded perspective view showing the inclined brace support and wall pile of a self-supporting structure according to a preferred embodiment of the present invention.
Figure 5 is a partially exploded perspective view showing an inclined brace support and an inclined brace according to a preferred embodiment of the present invention.
Figure 6 is a partially exploded perspective view showing an inclined brace support and an earth anchor according to a preferred embodiment of the present invention.
Figure 7 is a side view schematically showing the first step of the construction method according to a preferred embodiment of the present invention.
Figure 8 is a side view schematically showing the second step of the construction method according to a preferred embodiment of the present invention.
Figure 9 is a side view schematically showing the third and fourth steps of the construction method according to a preferred embodiment of the present invention.
Figure 10 is a side view schematically showing the fifth step of the construction method according to a preferred embodiment of the present invention.

본 발명은 토목공사나 건축공사 현장에서 터파기에 의해 형성되는 굴착영역(10)에 설치하는 흙막이 구조물의 버팀장치를 구비한 자립구조물 및 그 시공방법에 관한 것으로, 보다 상세하게 설명하면, 굴착영역(10)의 경계에 상부가 지상으로 돌출되도록 벽체파일(100)을 지중에 근입하여 설치하고, 상기 벽체파일(100)의 후방에 이격되도록 수직하게 어스앵커(200)를 설치하며, 상기 경사버팀지지대(300)와 경사버팀대(400)를 상기 벽체파일(100)과 상호 연결되도록 설치한 후 상기 경사버팀지지대(300)에 상기 어스앵커(200)가 고정되도록 하되, 상기 벽체파일(100), 경사버팀지지대(300) 및 경사버팀대(400)를 조립시공 및 해체하여 시공이 간편하고, 상기 벽체파일(100)의 전도 및 휨을 보다 원활하게 저항할 수 있는 한편, 'ㄷ'형태의 한 쌍의 연결부재(420)를 통해 상기 경사버팀대(400)와 벽체파일(100)을 결합함으로써, 시공이 간편하게 이루어질 수 있음은 물론 상기 벽체파일(100)의 손상을 최소화하여 상기 벽체파일(100)의 강성이 저하되는 것을 방지할 수 있는 후열식 버팀장치를 구비한 자립구조물 및 시공방법에 관한 것이다.The present invention relates to a self-supporting structure equipped with a support device for an earth retaining structure installed in an excavation area (10) formed by excavation at a civil engineering or building construction site and a construction method thereof. To be described in more detail, the present invention relates to a self-supporting structure and a construction method thereof. ), the wall pile 100 is installed by entering the ground so that the upper part protrudes from the ground at the boundary of the wall pile 100, the earth anchor 200 is installed vertically to be spaced apart from the rear of the wall pile 100, and the inclined support support ( 300) and the inclined brace 400 are installed to be interconnected with the wall pile 100, and then the earth anchor 200 is fixed to the inclined brace support 300, and the wall pile 100 and the inclined brace Construction is easy by assembling and disassembling the support 300 and the inclined brace 400, and can more smoothly resist falling and bending of the wall pile 100, while a pair of 'ㄷ' shaped connecting members By combining the inclined brace 400 and the wall pile 100 through (420), construction can be easily performed and damage to the wall pile 100 is minimized, thereby reducing the rigidity of the wall pile 100. It relates to a self-supporting structure and construction method equipped with a rear-heating bracing device that can prevent damage.

상기와 같은 본 발명의 후열식 버팀장치를 구비한 자립구조물은 터파기에 형성된 굴착영역(10)의 경계에 설치되되, 상부가 지상으로 돌출되도록 설치되는 벽체파일(100);과 상기 벽체파일(100)의 후방에 이격되어 지중에 수직하게 설치되는 어스앵커(200);와 지면에 안착되어 설치되되, 전방이 상기 벽체파일(100)의 후면에 결합되고, 후방에 상기 어스앵커(200)의 상부가 관통된 후 고정되는 경사버팀지지대(300); 및 상기 경사버팀지지대(300)의 상부면에 하부가 결합되고, 상기 벽체파일(100)의 상부에 상부가 결합되어 경사지게 설치되는 경사버팀대(400);를 포함하여 구성되는 것을 특징으로 한다.The self-supporting structure equipped with the rear-heating bracing device of the present invention as described above is installed at the border of the excavation area 10 formed in the trench, and the wall pile 100 is installed so that the upper part protrudes from the ground; and the wall pile 100 ) and an earth anchor (200) that is installed vertically in the ground and spaced apart from the rear; and is installed and seated on the ground, the front of which is coupled to the rear of the wall pile (100), and the upper part of the earth anchor (200) at the rear. An inclined support support 300 that is fixed after being penetrated; And an inclined brace 400, the lower part of which is coupled to the upper surface of the inclined brace support 300, and the upper part of which is coupled to the upper part of the wall pile 100, and which are installed inclinedly.

또한, 본 발명의 상기 경사버팀지지대(300)는 상부플랜지와 하부플랜지의 후방에 각각 관통형성되되, 웨브를 중심으로 일측과 타측에 대향되도록 형성되는 한 쌍의 관통홀(310);과 상기 상부플랜지의 한 쌍의 관통홀(310)을 덮도록 안착되어 설치되고, 상기 관통홀(310)과 연통되도록 복수 개의 고정홀(322)이 형성되는 제1플레이트(320); 및 하부방향으로 갈수록 외경과 내경이 좁아지도록 형성되고, 상기 고정홀(322)의 상부에 하부가 끼워져 결합되는 웨지(330);를 포함하여 구성되고, 상기 어스앵커(200)는 지중에 삽입되어 고정되는 내하체(210);와 상기 내하체(210)에 하부가 결합되고, 상기 관통홀(310)과 고정홀(322)을 관통하며, 상기 웨지(330)가 상부 외주연에 결합되는 강연선(220);을 포함하여 구성되는 것을 특징으로 한다.In addition, the inclined support support 300 of the present invention has a pair of through holes 310 formed through the rear of the upper flange and the lower flange, respectively, and formed to face each other on one side and the other around the web; and the upper part. A first plate 320 that is seated and installed to cover a pair of through holes 310 of the flange and has a plurality of fixing holes 322 formed to communicate with the through holes 310; and a wedge 330 whose outer diameter and inner diameter are formed to become narrower toward the bottom, and whose lower part is fitted and coupled to the upper part of the fixing hole 322. The earth anchor 200 is inserted into the ground. An inner body 210 that is fixed; and a strand whose lower part is coupled to the inner body 210, penetrates the through hole 310 and the fixing hole 322, and the wedge 330 is coupled to the upper outer periphery. It is characterized in that it includes (220);

또한, 본 발명의 상기 경사버팀지지대(300)는 상기 어스앵커(200)의 전방에 위치되도록 관통형성되되, 웨브를 중심으로 일측과 타측에 관통형성되는 복수 개의 결합홀(340);을 포함하여 구성되고, 상기 경사버팀대(400)는 하부 말단에 형성되고, 상기 결합홀(340)과 대응되는 복수 개의 체결홀(412)이 형성되는 결합판(410);을 포함하여 구성되는 것을 특징으로 한다.In addition, the inclined brace support 300 of the present invention is formed through a penetrating position to be located in front of the earth anchor 200, and includes a plurality of coupling holes 340 formed through one side and the other side centered on the web. It is configured, and the inclined brace 400 is formed at the lower end, and is characterized in that it includes a coupling plate 410 on which a plurality of fastening holes 412 corresponding to the coupling holes 340 are formed. .

또한, 본 발명의 상기 경사버팀대(400)는 상부 말단에 형성되고, 상기 벽체파일(100)이 관통되어 고정되는 연결부재(420);를 포함하여 구성되는 것을 특징으로 한다.In addition, the inclined brace 400 of the present invention is formed at the upper end, and is characterized by including a connecting member 420 through which the wall pile 100 is fixed.

또한, 본 발명의 상기 연결부재(420)는 상기 경사버팀대(400)의 상부 말단에 후방이 결합되고, 전방에 상기 벽체파일(100)의 후방이 내입되는 'ㄷ'형태의 제1커플러(422);와 후방에 상기 벽체파일(100)의 전방이 내입되고, 상기 제1커플러(422)와 대향되도록 위치된 후 복수 개의 볼트를 통해 상기 벽체파일(100)과 결합되는 'ㄷ'형태의 제2커플러(423);를 포함하여 구성되는 것을 특징으로 한다.In addition, the connecting member 420 of the present invention is coupled at the rear to the upper end of the inclined brace 400, and the first coupler 422 of the 'ㄷ' shape is inserted into the rear of the wall pile 100 at the front. ); and the front of the wall pile 100 is inserted into the rear, positioned to face the first coupler 422, and then coupled to the wall pile 100 through a plurality of bolts. It is characterized in that it includes 2 couplers (423).

또한, 본 발명의 상기 제1커플러(422)와 제2커플러(423)는 후방 또는 전방 일측과 타측에 돌출형성되는 결합플랜지(424);와 상부 외측면과 하부 외측면에 각각 돌출형성되는 한 쌍의 외곽 스티프너(425); 및 상기 결합플랜지(424)와 측면을 연결하도록 형성되는 복수 개의 보강 스티프너(426);를 포함하여 구성되는 것을 특징으로 한다.In addition, the first coupler 422 and the second coupler 423 of the present invention have a coupling flange 424 protruding on one rear or front side and the other side; and a coupling flange 424 protruding on the upper outer surface and the lower outer surface, respectively. Pair of outer stiffeners (425); And a plurality of reinforcing stiffeners 426 formed to connect the coupling flange 424 and the side surface.

또한, 본 발명의 상기 제2커플러(423)는 후면에 형성되는 보강부(423a);를 포함하여 구성되고, 상기 보강부(423a)는 양측에 돌출형성되어 상기 제2커플러(423)의 측면까지 연장형성되는 연장보강부(423a-1);를 포함하여 구성되는 것을 특징으로 한다.In addition, the second coupler 423 of the present invention is configured to include a reinforcing part 423a formed on the rear side, and the reinforcing part 423a is formed to protrude on both sides to form a side surface of the second coupler 423. It is characterized in that it includes an extension reinforcement portion (423a-1) extending up to.

상기와 같은 본 발명의 후열식 버팀장치를 구비한 자립구조물 시공방법은 상기와 같은 후열식 버팀장치를 구비한 자립구조물의 시공방법에 있어서, 벽체파일(100)을 지중에 수직하게 삽입하여 설치하되, 상부가 지상으로 돌출되도록 설치하는 제1단계(S10);와 상기 벽체파일(100)의 후방에 이격되어 지중에 수직하게 어스앵커(200)를 설치하는 제2단계(S20);와 지면에 경사버팀지지대(300)를 설치하되, 상기 어스앵커(200)의 상부가 상기 경사버팀지지대(300)의 후방을 관통하고, 상기 경사버팀지지대(300)의 전방이 벽체파일(100)의 후면에 결합되도록 하는 제3단계(S30);와 상기 벽체파일(100)의 상부에 상기 경사버팀대(400)의 상부를 결합하고, 상기 경사버팀지지대(300)의 상부면에 경사버팀대(400)의 하부를 결합하되, 상기 경사버팀대(400)를 경사지게 설치하는 제4단계(S40); 및 상기 어스앵커(200)를 인장하여 상기 벽체파일(100)이 견고하게 고정되도록 하는 제5단계(S50);를 포함하여 구성되는 것을 특징으로 한다.In the construction method of a self-supporting structure equipped with a post-heating bracing device of the present invention as described above, the wall pile 100 is installed by inserting it vertically into the ground. , a first step (S10) of installing the upper part so that it protrudes from the ground; and a second step (S20) of installing the earth anchor 200 vertically in the ground and spaced apart from the rear of the wall pile 100; and on the ground. An inclined brace support 300 is installed, where the upper part of the earth anchor 200 penetrates the rear of the inclined brace support 300, and the front of the inclined brace support 300 is at the rear of the wall pile 100. A third step (S30) to couple the upper part of the inclined brace 400 to the upper part of the wall pile 100, and the lower part of the inclined brace 400 to the upper surface of the inclined brace support 300. A fourth step (S40) of combining and installing the inclined brace 400 at an angle; And a fifth step (S50) of tensioning the earth anchor 200 so that the wall pile 100 is firmly fixed.

이하, 본 발명의 실시예를 도시한 도면 1 내지 10를 참고하여 본 발명을 구체적으로 설명하면 다음과 같다.Hereinafter, the present invention will be described in detail with reference to Figures 1 to 10 showing embodiments of the present invention.

먼저, 토목공사나 건축공사 현장에서 터파기를 할 때 터파기 할 경계에 라인을 긋고, 이 라인을 따라 일정간격으로 지주구멍을 천공하여 H빔 구성의 지주말뚝(본 발명에서는 '벽체파일(100)'에 해당)을 복수 개 설치하며, 지주말뚝들 사이에는 토류판을 끼워 토사가 터파기 지역(본 발명에서는 '굴착영역(10)'에 해당)으로 유입되는 것을 차단하게 되는데, 이때 종래에는 지주말뚝이 터파기 공간으로 붕괴되는 등의 위험성을 해소할 수 있도록 터파기 공사구간 쪽에 많은 수의 지보재(Strut, Earth Anchor, Raker 등)를 사용하게 된다.First, when excavating at a civil engineering or building construction site, a line is drawn on the boundary to be excavated, and holding holes are drilled at regular intervals along this line to create H-beam holding piles (in the present invention, 'wall piles 100'). (corresponding to 'excavation area 10' in the present invention) is installed in plural, and an earthen plate is inserted between the holding piles to block soil from flowing into the excavation area (corresponding to the 'excavation area 10' in the present invention). To eliminate the risk of collapse into the excavation space, a large number of supporting materials (Strut, Earth Anchor, Raker, etc.) are used in the excavation construction section.

이때, 이하에서 설명된 전방과 후방은 터파기를 시행하는 공간 즉, 터파기를 시행하여 형성되는 굴착영역(10)을 전방으로 설명하고, 상기 굴착영역(10)의 전방과 반대되는 방향을 후방으로 설명하며, 이는 터파기를 시행하여 형성되는 공간의 내측이 전방, 외측이 후방에 해당되는 것을 의미한다.At this time, the front and rear described below describe the space where excavation is performed, that is, the excavation area 10 formed by excavation, as the front, and the direction opposite to the front of the excavation area 10 is described as the rear. This means that the inside of the space created by digging is the front, and the outside is the back.

본 발명의 주요 구성요소인 벽체파일(100)은The wall pile 100, which is a main component of the present invention, is

터파기에 형성된 굴착영역(10)의 경계에 설치되되, 상부가 지상으로 돌출되도록 설치되는 것으로, 터파기를 시행하기 전에 터파기 할 경계 라인을 따라 일정간격으로 천공된 지주구멍에 복수 개가 설치된다.It is installed at the border of the excavation area 10 formed in the trench, and is installed so that the upper part protrudes from the ground. A plurality of trenches are installed in support holes drilled at regular intervals along the boundary line to be dug before excavation.

이때, 본 발명의 벽체파일(100)은 상부가 지상으로 돌출되도록 설치됨에 따라, 경사버팀지지대(300)의 전방이 후방에 결합될 수 있도록 하고, 경사버팀대(400)의 상부가 후방에서 상부에 결합될 수 있도록 한다.At this time, the wall pile 100 of the present invention is installed so that the upper part protrudes from the ground, so that the front of the inclined brace support 300 can be coupled to the rear, and the upper part of the inclined brace 400 is positioned at the top from the rear. so that they can be combined.

즉, 본 발명의 벽체파일(100)은 상부가 지상으로 돌출되도록 굴착영역(10)의 경계에 설치되어 경사버팀지지대(300) 및 경사버팀대(400)를 통해 어스앵커(200)와 연결되어 지지됨에 따라 시공이 간편하면서도 견고하고 안정적으로 설치되는 효과를 얻을 수 있다.That is, the wall pile 100 of the present invention is installed at the boundary of the excavation area 10 so that the upper part protrudes to the ground, and is connected to and supported by the earth anchor 200 through the inclined brace support 300 and the inclined brace 400. As a result, construction is simple, yet sturdy and stable installation is achieved.

본 발명의 주요 구성요소인 어스앵커(200)는The earth anchor 200, a main component of the present invention,

상기 벽체파일(100)의 후방에 이격되어 지중에 수직하게 설치되는 것으로, 이후에 자세히 설명될 경사버팀지지대(300)의 후방에 고정되어 상기 벽체파일(100)과 연결됨에 따라, 상기 벽체파일(100)의 후방 모멘트를 발생시켜 상기 벽체파일(100)이 안정적이고 견고하게 설치된 상태를 유지할 수 있도록 한다.It is installed vertically in the ground and spaced apart from the rear of the wall pile 100, and is fixed to the rear of the inclined support support 300, which will be described in detail later, and is connected to the wall pile 100, so that the wall pile ( 100) generates a rearward moment so that the wall pile 100 can be maintained in a stable and solidly installed state.

이러한, 본 발명의 어스앵커(200)는 지중에 수직하게 설치됨에 따라 협소한 공간 즉, 터파기를 시행할 굴착영역(10)의 주변 공간이 협소하여도 효과적으로 터파기가 시행될 수 있도록 하는 효과를 실현케 한다.As the earth anchor 200 of the present invention is installed vertically in the ground, it realizes the effect of enabling trench digging to be carried out effectively even in a narrow space, that is, the space around the excavation area 10 where trench digging is to be performed. Do it.

구체적으로, 본 발명의 어스앵커(200)는 지중에 삽입되어 고정되는 내하체(210)와, 상기 내하체(210)에 하부가 결합되고, 지상으로 돌출되어 이후에 자세히 설명될 경사버팀지지대(300)의 관통홀(310)과 제1플레이트(320)의 고정홀(322)을 관통하며, 이후에 자세히 설명될 웨지(330)에 상부가 결합되는 강연선(220)을 포함하여 구성된다.Specifically, the earth anchor 200 of the present invention includes an inner body 210 that is inserted and fixed into the ground, a lower part coupled to the inner body 210, and an inclined support support that protrudes to the ground and will be described in detail later ( It passes through the through hole 310 of the 300 and the fixing hole 322 of the first plate 320, and includes a strand 220 whose upper part is coupled to the wedge 330, which will be described in detail later.

상기 내하체(210)는 지중에 삽입되어 고정됨에 따라 고정력을 발생시키고, 상기 강연선(220)은 이후에 인장되어 상기 웨지(330)에 의해 상기 경사버팀지지대(300)에 고정됨에 따라 항상 인장된 상태를 유지하여 상기 벽체파일(100)의 후방 모멘트가 발생될 수 있도록 한다.The inner body 210 generates a fixing force as it is inserted into the ground and fixed, and the strand 220 is subsequently tensioned and fixed to the inclined support 300 by the wedge 330, so that it is always tensioned. The state is maintained so that the rear moment of the wall pile 100 can be generated.

이때, 본 발명의 어스앵커(200)는 상기 벽체파일(100)의 후방에 이격되어 지중에 수직하게 설치될 수 있도록 지중에 앵커홀이 천공된 후 삽입되고, 그라우팅관을 통해 충진재를 상기 앵커홀에 충진하면 상기 내하체(210)가 고정된다.At this time, the earth anchor 200 of the present invention is inserted after an anchor hole is drilled in the ground so that it can be installed vertically in the ground and spaced apart from the rear of the wall pile 100, and filler is inserted into the anchor hole through a grouting pipe. When filled, the inner body 210 is fixed.

상기 강연선(220)은 상기 내하체(210)의 상부에 하부가 결합되고, 복수 개가 상기 내하체(210)에 결합될 수 있으며, 이후에 자세히 설명될 경사버팀지지대(300)의 웨브를 중심으로 형성된 한 쌍의 관통홀(310)을 관통하여 제1플레이트(320)와 웨지(330)에 의해 안정적으로 고정될 수 있도록 적어도 한 쌍이 구비되는 것이 바람직하다.The lower part of the strand 220 is coupled to the upper part of the inner body 210, and a plurality of the strands may be coupled to the inner body 210, centered around the web of the inclined brace 300, which will be described in detail later. It is preferable that at least one pair is provided so that it can pass through the formed pair of through holes 310 and be stably fixed by the first plate 320 and the wedge 330.

본 발명의 주요 구성요소인 경사버팀지지대(300)는The inclined brace support 300, which is a main component of the present invention,

지면에 안착되어 설치되되, 전방이 상기 벽체파일(100)의 후면에 결합되고, 후방에 상기 어스앵커(200)의 상부가 관통된 후 고정되는 것으로, 앞서 설명된 바와 같이, 어스앵커(200)의 강연선(220)이 관통된 후 웨지(330)에 의해 후방에 고정되면 상기 어스앵커(200)에 의해 벽체파일(100)의 후방 모멘트가 안정적으로 발생될 수 있도록 한다.It is seated and installed on the ground, and the front is coupled to the rear of the wall pile 100, and the upper part of the earth anchor 200 is penetrated and then fixed at the rear. As described above, the earth anchor 200 When the strand 220 penetrates and is fixed to the rear by the wedge 330, the rear moment of the wall pile 100 can be stably generated by the earth anchor 200.

이러한, 본 발명의 경사버팀지지대(300)는 H빔으로 이루어지고, 상부플랜지와 하부플랜지가 각각 상부와 하부에 위치되도록 지면에 안착되어 설치되고, 상기 상부플랜지와 하부플랜지를 연결하는 웨브가 형성된다.The inclined brace support 300 of the present invention is made of an H beam, is installed and seated on the ground so that the upper flange and the lower flange are located at the upper and lower portions, respectively, and a web is formed to connect the upper flange and the lower flange. do.

구체적으로, 본 발명의 경사버팀지지대(300)는 상부플랜지와 하부플랜지의 후방에 각각 관통형성되되, 웨브를 중심으로 일측과 타측에 대향되도록 형성되는 한 쌍의 관통홀(310)과, 상기 상부플랜지에 형성된 한 쌍의 관통홀(310)을 덮도록 안착되어 설치되고, 상기 관통홀(310)과 연통되도록 복수 개의 고정홀(322)이 형성되는 제1플레이트(320) 및 하부방향으로 갈수록 외경과 내경이 좁아지도록 형성되고, 상기 고정홀(322)의 상부에 하부가 끼워져 결합되는 웨지(330)를 포함하여 구성된다.Specifically, the inclined support support 300 of the present invention includes a pair of through holes 310 formed through the rear of the upper flange and the lower flange, respectively, and formed to face each other on one side and the other with the web as the center, and the upper part. A first plate 320 that is seated and installed to cover a pair of through holes 310 formed in the flange and has a plurality of fixing holes 322 formed to communicate with the through holes 310, and the outer diameter increases in the downward direction. It is formed to have a narrow inner diameter and includes a wedge 330 whose lower part is fitted and coupled to the upper part of the fixing hole 322.

상기 관통홀(310)은 상기 웨브를 중심으로 상부플랜지와 하부플랜지의 일측과 타측에 각각 대향되도록 형성되어 상기 어스앵커(200)의 강연선(220)이 원활하게 관통될 수 있도록 하되, 경사버팀지지대(300)가 상기 제1플레이트(320)와 웨지(330)에 의해 상기 강연선(220)이 안정적으로 고정될 수 있도록 함과 동시에 안정적이고 견고하게 지면에 안착되어 설치된 상태를 유지할 수 있도록 하는 효과를 실현케 한다.The through hole 310 is formed to face one side and the other side of the upper flange and the lower flange, respectively, centered on the web, so that the strand 220 of the earth anchor 200 can pass through smoothly, and the inclined brace support (300) has the effect of enabling the strand 220 to be stably fixed by the first plate 320 and the wedge 330, and at the same time being stably and firmly seated on the ground and maintaining the installed state. Make it come true

상기 제1플레이트(320)는 상기 상부플랜지의 상부면에 안착되어 설치되되, 상기 웨지(330)가 관통되며 끼워져 결합되도록 함으로써, 상기 웨지(330)를 관통하여 설치된 강연선(220)이 상기 웨지(330)에 의해 인장되어 안정적으로 인장력이 형성된 상태를 유지할 수 있도록 하는 효과를 실현케 한다.The first plate 320 is installed and seated on the upper surface of the upper flange, and is coupled to the wedge 330 by passing through it, so that the strand 220 installed penetrating the wedge 330 is connected to the wedge ( 330), which achieves the effect of maintaining a stable tensile force.

즉, 상기 제1플레이트(320)는 상기 웨지(330)가 경사버팀지지대(300)에 직접끼워져 결합되지 않도록 함으로써, 상기 경사버팀지지대(300)가 쉽게 파손되는 것을 방지할 뿐만 아니라 상기 웨지(330)의 설치가 안정적이고 견고하며 용이하게 이루어질 수 있도록 하는 효과를 실현케 한다.That is, the first plate 320 not only prevents the inclined brace support 300 from being easily damaged by preventing the wedge 330 from being directly inserted into and coupled to the inclined brace support 300, but also prevents the wedge 330 from being easily damaged. ) achieves the effect of ensuring that the installation is stable, sturdy, and easy.

상기 웨지(330)는 내경이 하부방향으로 갈수록 좁아져 내측에 상기 강연선(220)이 관통되어 고정되고, 외경 또한 내경과 같이 하부방향으로 갈수록 좁아져 상기 제1플레이트(320)의 고정홀(322)에 끼워져 결합되는데, 상기 어스앵커(200)를 인장한 후 상기 어스앵커(200) 즉, 강연선(220)이 인장된 상태를 유지한 상태에서 상기 고정홀(322)에 고정된다.The wedge 330 has an inner diameter that narrows downward so that the strand 220 passes through and is fixed on the inside, and the outer diameter also narrows downward like the inner diameter to secure the fixing hole 322 of the first plate 320. ), and after the earth anchor 200 is tensioned, the earth anchor 200, that is, the strand 220, is fixed to the fixing hole 322 while maintaining the tensioned state.

아울러, 본 발명의 경사버팀지지대(300)는 상기 어스앵커(200)의 전방에 위치되도록 관통형성되되, 웨브를 중심으로 일측과 타측에 대향되도록 관통형성되는 복수 개의 결합홀(340)을 포함하여 구성된다.In addition, the inclined brace support 300 of the present invention is formed through a penetrating position to be located in front of the earth anchor 200, and includes a plurality of coupling holes 340 formed through the web so as to face each other on one side and the other side. It is composed.

상기 결합홀(340)은 경사버팀대(400)가 상기 벽체파일(100)과의 사이에서 경사지게 설치될 때, 상기 경사버팀대(400)의 하부가 결합되도록 하는 것으로, 상기 경사버팀지지대(300)의 길이방향으로 복수 개가 형성되어 상기 경사버팀대(400)의 하부가 결합되는 위치를 용이하게 조절할 수 있도록 하는 효과를 실현케 한다.The coupling hole 340 allows the lower part of the inclined brace 400 to be coupled when the inclined brace 400 is installed at an angle between the wall pile 100 and the inclined brace support 300. A plurality of pieces are formed in the longitudinal direction to achieve the effect of easily adjusting the position where the lower part of the inclined brace 400 is coupled.

이때, 상기 결합홀(340)은 앞서 설명된 한 쌍의 관통홀(310)과 마찬가지로 웨브를 중심으로 일측과 타측에 한 쌍이 대향되도록 형성되고, 복수 개의 한 쌍이 경사버팀지지대(300)의 상부플랜지에 길이방향으로 형성되어 상기 경사버팀대(400)의 하부가 결합되는 위치를 용이하게 조절할 수 있도록 함은 물론 상기 상부플랜지에 안정적이고 견고하게 상기 경사버팀대(400)가 설치될 수 있도록 한다.At this time, the coupling holes 340, like the pair of through holes 310 described above, are formed with a pair facing each other on one side and the other around the web, and a plurality of pairs are connected to the upper flange of the inclined brace support 300. It is formed in the longitudinal direction to easily adjust the position where the lower part of the inclined brace 400 is coupled, as well as to enable the inclined brace 400 to be installed stably and firmly on the upper flange.

상기와 연관하여, 본 발명의 경사버팀지지대(300)는 전방 말단에 결합되고, 복수 개의 결합홀이 형성되는 제2플레이트를 포함하여 구성되고, 상기 벽체파일(100)은 지중에 삽입되어 설치된 후 상기 제2플레이트의 결합홀과 대응되는 위치의 후방 플랜지에 복수 개의 체결홀이 천공되어 형성되어 복수 개의 볼트 및 너트를 통해 상기 경사버팀지지대(300)의 전방과 후방의 플랜지가 결합된다.In connection with the above, the inclined brace support 300 of the present invention is coupled to the front end and includes a second plate in which a plurality of coupling holes are formed, and the wall pile 100 is inserted into the ground and installed. A plurality of fastening holes are drilled in the rear flange at a position corresponding to the coupling hole of the second plate, and the front and rear flanges of the inclined brace support 300 are coupled through a plurality of bolts and nuts.

이때, 상기 제2플레이트는 용접 등을 통해 상기 경사버팀지지대(300)의 전방 말단 즉, 전면에 결합된다.At this time, the second plate is coupled to the front end, that is, the front, of the inclined brace support 300 through welding or the like.

본 발명의 주요 구성요소인 경사버팀대(400)는The inclined brace 400, which is a main component of the present invention,

상기 경사버팀지지대(300)의 상부면에 하부가 결합되고, 상기 벽체파일(100)의 상부에 상부가 결합되어 경사지게 설치되는 것으로, 상기 경사버팀지지대(300)와 상기 벽체파일(100)의 사이에 설치되어 상기 벽체파일(100)의 후방으로 안정적인 모멘트가 형성될 수 있도록 하고, 상기 경사버팀지지대(300) 및 벽체파일(100)의 손상을 최소화한다.The lower part is coupled to the upper surface of the inclined support 300, and the upper part is coupled to the upper part of the wall pile 100 and is installed inclinedly, between the inclined support 300 and the wall pile 100. It is installed to ensure that a stable moment is formed at the rear of the wall pile 100 and to minimize damage to the inclined support support 300 and the wall pile 100.

이러한, 본 발명의 경사버팀대(400)는 상기 벽체파일(100)과 경사버팀지지대(300)와 마찬가지로 H빔으로 이루어지고, 상기 경사버팀지지대(300)에 형성된 복수 개의 결합홀(340)에 하부가 안정적이고 견고하게 결합될 수 있도록 하부 말단에 형성되고, 상기 결합홀(340)과 대응되는 복수 개의 체결홀(412)이 형성되는 결합판(410)을 포함하여 구성된다.Like the wall pile 100 and the inclined brace support 300, the inclined brace 400 of the present invention is made of an H beam, and has a lower part in the plurality of coupling holes 340 formed in the inclined brace support 300. It is formed at the lower end so that it can be stably and firmly coupled, and includes a coupling plate 410 on which a plurality of fastening holes 412 corresponding to the coupling holes 340 are formed.

즉, 본 발명의 경사버팀대(400)는 상기 경사버팀지지대(300)의 상부플랜지에 하부가 안정적이고 견고하게 결합될 수 있도록 하부 말단에 상기 결합판(410)이 용접되어 결합되고, 상기 결합판(410)이 경사지게 설치될 수 있도록 하부 말단 즉, 하부면이 경사지게 형성되어 있다.That is, the inclined brace 400 of the present invention is joined by welding the coupling plate 410 to the lower end so that the lower part can be stably and firmly coupled to the upper flange of the inclined brace support 300, and the coupling plate The lower end, that is, the lower surface, is formed to be inclined so that (410) can be installed at an angle.

부가하여 설명하면, 상기 결합판(410)과 상기 경사버팀지지대(300)의 상부플랜지는 상기 결합홀(340)과 체결홀(412)이 일치되도록 상기 경사버팀대(400)의 하부가 위치된 후 복수 개의 볼트와 너트를 통해 결합된다.In addition, the coupling plate 410 and the upper flange of the inclined brace support 300 are formed after the lower part of the inclined brace 400 is positioned so that the coupling hole 340 and the fastening hole 412 are aligned. They are joined through a plurality of bolts and nuts.

아울러, 본 발명의 경사버팀대(400)는 상기 벽체파일(100)의 상부에 쉽고 견고하게 결합될 수 있도록 상부 말단에 형성되고, 상기 벽체파일(100)이 관통되어 고정되는 연결부재(420)를 포함하여 구성되는데, 상기 연결부재(420)는 상기 벽체파일(100)이 관통될 수 있도록 상하부가 개방된 중공이 형성된다.In addition, the inclined brace 400 of the present invention is formed at the upper end so that it can be easily and firmly coupled to the upper part of the wall pile 100, and has a connecting member 420 through which the wall pile 100 is penetrated and fixed. It is configured to include, wherein the connecting member 420 is formed with a hollow top and bottom that is open so that the wall pile 100 can penetrate.

보다 상세하게 설명하면, 상기 연결부재(420)는 상기 경사버팀대(400)의 상부 말단에 후방이 용접 등에 의해 결합되고, 전방에 상기 벽체파일(100)의 후방이 내입되는 'ㄷ'형태의 제1커플러(422)와, 후방에 상기 벽체파일(100)의 전방이 내입되고, 상기 제1커플러(422)와 대향되도록 위치된 후 복수 개의 볼트와 너트를 통해 상기 벽체파일(100)과 결합되는 'ㄷ'형태의 제2커플러(423)를 포함하여 구성된다.In more detail, the connecting member 420 is a 'ㄷ' shaped member whose rear is coupled to the upper end of the inclined brace 400 by welding, etc., and where the rear of the wall pile 100 is inserted into the front. 1 coupler 422 and the front of the wall pile 100 are inserted into the rear, positioned to face the first coupler 422, and then coupled to the wall pile 100 through a plurality of bolts and nuts. It is composed of a 'ㄷ' shaped second coupler (423).

상기 제1커플러(422)는 상기 경사버팀대(400)의 상부 말단에 결합되어 내측에 상기 벽체파일(100)의 후방이 내입되고, 상기 제2커플러(423)가 대향되어 결합됨에 따라 상기 벽체파일(100)에 상기 경사버팀대(400)의 상부가 견고하게 결합될 수 있도록 한다.The first coupler 422 is coupled to the upper end of the inclined brace 400 so that the rear of the wall pile 100 is inserted inside, and the second coupler 423 is coupled to face the wall pile 100. The upper part of the inclined brace 400 can be firmly coupled to (100).

상기 제2커플러(423)는 상기 벽체파일(100)의 전방이 내입되고, 상기 제1커플러(422)와 대향되는 위치에서 복수 개의 볼트와 너트를 통해 상기 제1커플러(422)와 결합됨으로써, 보다 쉽게 상기 경사버팀대(400)가 벽체파일(100)에 결합될 수 있도록 한다.The second coupler 423 is inserted into the front of the wall pile 100 and is coupled to the first coupler 422 through a plurality of bolts and nuts at a position opposite to the first coupler 422, This allows the inclined brace 400 to be more easily coupled to the wall pile 100.

즉, 상기 연결부재(420)는 제1커플러(422)와 제2커플러(423)로 구성됨에 따라 상기 경사버팀대(400)의 상부를 벽체파일(100)에 보다 쉽게 결합할 수 있도록 함은 물론 상기 경사버팀대(400)의 상부가 상기 벽체파일(100)에 결합되는 위치를 용이하게 조절할 수 있어 시공시간을 단축시킬 수 있는 효과를 얻을 수 있다.That is, the connecting member 420 is composed of the first coupler 422 and the second coupler 423, so that the upper part of the inclined brace 400 can be more easily coupled to the wall pile 100. The position at which the upper part of the inclined brace 400 is coupled to the wall pile 100 can be easily adjusted, which has the effect of shortening construction time.

부가하여, 본 발명의 경사버팀대(400)는 상기 결합판(410)과 상기 연결부재(420)의 제1커플러(422)가 시공전에 제조되어 시공될 수 있도록 하고, 상기 제2커플러(423) 또한 시공전에 제조되어 조립에 의해 상기 벽체파일(100)에 상부가 결합됨으로써, 보다 편리하게 시공을 시행할 수 있는 효과를 실현케 한다.In addition, the inclined brace 400 of the present invention allows the first coupler 422 of the coupling plate 410 and the connecting member 420 to be manufactured and installed before construction, and the second coupler 423 In addition, it is manufactured before construction and the upper part is coupled to the wall pile 100 through assembly, thereby realizing the effect of enabling more convenient construction.

아울러, 상기 제1커플러(422)와 제2커플러(423)는 후방 일측과 타측 또는 전방 일측과 타측에 각각 돌출형성되는 결합플랜지(424)와, 상부 외측면과 하부 외측면에 각각 돌출형성되는 한 쌍의 외곽 스티프너(425) 및 상기 결합플랜지(424)와 측면을 연결하도록 형성되는 복수 개의 보강 스티프너(426)를 포함하여 구성된다.In addition, the first coupler 422 and the second coupler 423 have a coupling flange 424 protruding on one side and the other rear or one side and the other front, respectively, and a coupling flange 424 protruding on the upper outer surface and the lower outer surface, respectively. It is configured to include a pair of outer stiffeners 425 and a plurality of reinforcing stiffeners 426 formed to connect the side surfaces of the coupling flange 424.

상기 결합플랜지(424)는 상기 제1커플러(422)와 제2커플러(423)가 대향되어 결합될 수 있도록 하고, 상기 외곽 스티프너(425)는 상기 제1커플러(422)와 제2커플러(423)의 상부와 하부의 휨을 방지할 수 있도록 내구성을 보강하며, 상기 보강 스티프너(426)는 상기 결합플랜지(424)의 휨을 방지할 수 있도록 내구성을 보강하여 경사버팀대(400)의 상부와 벽체파일(100)이 보다 안정적이고 견고하게 결합된 상태를 유지할 수 있도록 하는 효과를 실현케 한다.The coupling flange 424 allows the first coupler 422 and the second coupler 423 to be coupled to each other, and the outer stiffener 425 connects the first coupler 422 and the second coupler 423. ), and the reinforcing stiffener 426 reinforces durability to prevent bending of the coupling flange 424, so that the upper part of the inclined brace 400 and the wall pile ( 100) achieves the effect of maintaining a more stable and solidly coupled state.

또한, 상기 제2커플러(423)는 후면에 형성되는 보강부(423a)를 더 포함하여 구성되는데, 상기 보강부(423a)는 양측에 돌출형성되어 상기 제2커플러(423)의 측면까지 연장형성되는 연장보강부(423a-1)를 포함하여 구성되는 것을 특징으로 한다.In addition, the second coupler 423 further includes a reinforcing portion 423a formed on the rear side, and the reinforcing portion 423a protrudes on both sides and extends to the side of the second coupler 423. It is characterized in that it includes an extension reinforcement portion (423a-1).

상기 보강부(423a)는 상기 제2커플러(423)의 전면에 상기 제1커플러(422)의 후면처럼 결합되는 구성이 없어 상기 제2커플러(423)의 전면의 휨을 방지하여 내구성을 보강하는 효과를 실현케 한다.The reinforcement portion 423a does not have a configuration that is coupled to the front of the second coupler 423 like the rear of the first coupler 422, thereby preventing bending of the front of the second coupler 423, thereby reinforcing durability. make it come true.

이때, 상기 연장보강부(423a-1)는 상기 제2커플러(423)의 측면까지 형성되어 측면의 휨을 방지함으로써, 상기 벽체파일(100)에 전방 모멘트가 발생되어도 보다 안정적으로 결합을 유지할 수 있도록 하는 효과를 실현케 한다.At this time, the extension reinforcement portion 423a-1 is formed to the side of the second coupler 423 to prevent bending of the side, so that the connection can be maintained more stably even if a forward moment occurs in the wall pile 100. realize the effect of

또한, 경사버팀지지대 및 경사버팀대를 규격화시켜 공장 등에서 제작함에 따라 현장에서 조립시공 및 해체가 용이하므로 공사기간을 단축시킬 수 있는 효과를 얻을 수 있다.In addition, as the inclined brace supports and inclined braces are standardized and manufactured in factories, it is easy to assemble and dismantle on site, which has the effect of shortening the construction period.

이하, 도면 7 내지 도면 10을 참고하여 본 발명의 후열식 버팀장치를 구비한 자립구조물 시공방법을 설명하도록 한다.Hereinafter, the method of constructing a self-supporting structure equipped with a rear-heating support device of the present invention will be described with reference to Figures 7 to 10.

본 발명의 후열식 버팀장치를 구비한 자립구조물 시공방법은 벽체파일(100)을 지중에 수직하게 삽입하여 설치하되, 상부가 지상으로 돌출되도록 설치하는 제1단계(S10)와, 상기 벽체파일(100)의 후방에 이격되어 지중에 수직하게 어스앵커(200)를 설치하는 제2단계(S20)와, 지면에 경사버팀지지대(300)를 설치하되, 상기 어스앵커(200)의 상부가 상기 경사버팀지지대(300)의 후방을 관통하고, 상기 경사버팀지지대(300)의 전방이 벽체파일(100)의 후면에 결합되도록 하는 제3단계(S30)와, 상기 벽체파일(100)의 상부에 상기 경사버팀대(400)의 상부를 결합하고, 상기 경사버팀지지대(300)의 상부면에 경사버팀대(400)의 하부를 결합하되, 상기 경사버팀대(400)를 경사지게 설치하는 제4단계(S40) 및 상기 어스앵커(200)를 인장하여 상기 벽체파일(100)이 견고하게 고정되도록 하는 제5단계(S50)를 포함하여 구성된다.The construction method of a self-supporting structure equipped with a post-heating bracing device of the present invention includes a first step (S10) of installing the wall pile 100 by inserting it vertically into the ground, but installing the upper part so that the upper part protrudes from the ground, and the wall pile (100) A second step (S20) of installing the earth anchor 200 vertically in the ground and spaced apart from the rear of 100), and installing an inclined support support 300 on the ground, where the upper part of the earth anchor 200 is inclined A third step (S30) of penetrating the rear of the brace support 300 and allowing the front of the inclined brace 300 to be coupled to the rear of the wall pile 100, and the upper part of the wall pile 100. A fourth step (S40) of coupling the upper part of the inclined brace 400, coupling the lower part of the inclined brace 400 to the upper surface of the inclined brace support 300, and installing the inclined brace 400 at an angle, and It includes a fifth step (S50) of tensioning the earth anchor 200 so that the wall pile 100 is firmly fixed.

상기 제1단계(S10)는 벽체파일(100)을 지중에 수직하게 삽입하여 설치하기 위해 터파기에 의해 형성되는 굴착영역(10)의 경계에 설치될 수 있도록 상기 경계를 따라 복수 개의 지주홀을 형성하는 제1-1단계(S12)와, 상기 제1-1단계(S12) 이후 지주홀에 벽체파일(100)을 수직하게 삽입하여 설치하되, 상기 벽체파일(100)의 상부가 지상으로 돌출되도록 설치하는 제1-2단계(S14)를 포함하여 구성된다.In the first step (S10), a plurality of support holes are formed along the boundary so that the wall pile 100 can be installed at the boundary of the excavation area 10 formed by digging in order to install the wall pile 100 by inserting it vertically into the ground. In the 1-1 step (S12), and after the 1-1 step (S12), the wall pile (100) is vertically inserted into the support hole and installed, so that the upper part of the wall pile (100) protrudes to the ground. It consists of steps 1 and 2 of installation (S14).

상기 제2단계(S20)는 상기 제1단계(S10) 이후 상기 벽체파일(100)의 후방에 이격되도록 앵커홀을 천공하는 제2-1단계(S22)와, 상기 제2-1단계(S22) 이후 상기 앵커홀에 강연선(220)과 그라우팅 주입관이 상부에 연결된 내하체(210)를 삽입하는 제2-2단계(S24)와, 상기 제2-2단계(S24) 이후 상기 그라우팅 주입관을 통해 몰탈을 주입하여 상기 내하체를 상기 앵커홀에 고정하는 제2-3단계(S26)를 포함하여 구성된다.The second step (S20) includes a 2-1 step (S22) of drilling an anchor hole to be spaced apart from the rear of the wall pile 100 after the first step (S10), and the 2-1 step (S22). ) After the 2-2 step (S24) of inserting the inner body 210 with the strand 220 and the grouting injection pipe connected to the upper part into the anchor hole, and the grouting injection pipe after the 2-2 step (S24) It includes the second and third steps (S26) of fixing the inner body to the anchor hole by injecting mortar through.

이때, 상기 제2-2단계(S24)는 상기 내하체(210)가 제2-3단계(S26)에서 보다 안정적이고 견고하게 고정될 수 있도록 상기 앵커홀의 내측 하부면으로부터 상기 내하체(210)가 일정거리, 일예로 약 0.5m 이격되도록 삽입하고, 상기 강연선(220)은 상기 앵커홀의 상부로 돌출되도록 설치된다.At this time, in the 2-2 step (S24), the inner lower body 210 is removed from the inner lower surface of the anchor hole so that the inner lower body 210 can be fixed more stably and firmly in the 2-3 step (S26). are inserted at a certain distance, for example, about 0.5 m apart, and the strands 220 are installed to protrude from the top of the anchor hole.

상기 제3단계(S30)는 경사버팀지지대(300)의 제2플레이트의 결합홀과 대응되도록 벽체파일(100)의 후방 플랜지에 체결홀을 천공하는 제3-1단계(S32)와, 상기 제3-1단계(S32) 이후 상기 경사버팀지지대(300)를 지면에 안착시켜 설치하되, 상기 어스앵커(200)의 상부가 후방 즉, 관통홀(310)을 관통하도록 설치하고, 상기 경사버팀지지대(300)의 전방 즉, 제2플레이트가 상기 벽체파일(100)의 후면에 결합되도록 하는 제3-2단계(S34)를 포함하여 구성된다.The third step (S30) includes a 3-1 step (S32) of drilling a fastening hole in the rear flange of the wall pile 100 to correspond to the coupling hole of the second plate of the inclined brace support 300, and the first After step 3-1 (S32), the inclined brace support 300 is installed by seating it on the ground, and the upper part of the earth anchor 200 is installed to penetrate the rear, that is, through hole 310, and the inclined brace support 300 is installed by seating it on the ground. It is configured to include a 3-2 step (S34) in which the front of 300, that is, the second plate, is coupled to the rear of the wall pile 100.

상기 제4단계(S40)는 상기 벽체파일(100)의 상부 후방을 상기 경사버팀대(400)의 제1커플러(422)의 내측에 내입되도록 하는 제4-1단계(S42)와, 상기 제4-1단계(S42) 이후 상기 제1커플러(422)의 전방에 제2커플러(423)의 후방을 결합하되, 상기 제2커플러(423)의 후방에 상기 벽체파일(100)의 상부 전방이 내입되도록 하여 상기 제1커플러(422)와 제2커플러(423) 즉, 연결부재(420)가 상기 벽체파일(100)을 따라 이동될 수 있도록 결합하는 제4-2단계(S44)와, 상기 제4-2단계(S44) 이후 상기 경사버팀대(400)의 하부를 상기 경사버팀지지대(300)의 후방 상부에 결합하는 제4-3단계(S46) 및 상기 제4-3단계(S46) 이후 상기 제1커플러(422)와 제2커플러(423) 즉, 연결부재(420)를 견고하게 고정시켜 상기 경사버팀대(400)의 상부가 상기 벽체파일(100)에 고정되도록 하는 제4-4단계(S48)를 포함하여 구성된다.The fourth step (S40) includes a 4-1 step (S42) of inserting the upper rear of the wall pile 100 into the inside of the first coupler 422 of the inclined brace 400, and the fourth step S42. - After step 1 (S42), the rear of the second coupler 423 is coupled to the front of the first coupler 422, and the upper front of the wall pile 100 is inserted into the rear of the second coupler 423. A 4-2 step (S44) of coupling the first coupler 422 and the second coupler 423, that is, the connecting member 420, so that they can be moved along the wall pile 100, and After the 4-2 step (S44), the 4-3 step (S46) of coupling the lower part of the inclined brace 400 to the rear upper part of the inclined brace support 300, and after the 4-3 step (S46) Step 4-4 of firmly fixing the first coupler 422 and the second coupler 423, that is, the connecting member 420, so that the upper part of the inclined brace 400 is fixed to the wall pile 100 ( It consists of S48).

즉, 상기 제4단계(S40)는 제4-2단계(S44) 이후 상기 경사버팀대(400)의 하부가 안정적으로 경사버팀지지대(300)에 결합될 수 있도록 위치가 조정된 후 제4-3단계(S46)에서 상기 경사버팀대(400)의 하부가 경사버팀지지대(300)에 결합되도록 하고, 상기 제4-4단계(S48)에서 상기 경사버팀대(400)의 상부가 상기 벽체파일(100)에 견고하게 결합되도록 함으로써, 보다 용이하게 경사버팀대(400)를 설치할 수 있도록 하는 효과를 얻을 수 있다.That is, in the fourth step (S40), after the 4-2 step (S44), the position of the lower part of the inclined brace 400 is adjusted so that it can be stably coupled to the inclined brace support 300, and then the 4-3 step is performed. In step S46, the lower part of the inclined brace 400 is coupled to the inclined brace support 300, and in step 4-4 (S48), the upper part of the inclined brace 400 is connected to the wall pile 100. By being firmly coupled to, it is possible to obtain the effect of allowing the inclined brace 400 to be installed more easily.

상기 제5단계(S50)는 상기 어스앵커(200)의 강연선(220)이 제1플레이트(320)의 고정홀(322)을 관통하도록 상기 제1플레이트(320)를 상기 경사버팀지지대(300)의 상부면에 안착시켜 설치하는 제5-1단계(S52)와, 상기 제5-1단계(S52) 이후 상기 강연선(220)에 웨지(330)를 이동가능하도록 설치하는 제5-2단계(S54) 및 상기 제5-2단계(S54) 이후 상기 강연선(220)을 인장하고, 상기 강연선(220)이 인장된 상태에서 상기 웨지(330)를 상기 고정홀(322)과 근접한 위치의 강연선(220)의 외주연에 고정하며, 상기 강연선(220)의 인장을 해제하는 제5-3단계(S56)를 포함하여 구성된다.In the fifth step (S50), the first plate 320 is connected to the inclined brace support 300 so that the strand 220 of the earth anchor 200 penetrates the fixing hole 322 of the first plate 320. A 5-1 step (S52) of installing and seating on the upper surface of the 5-1 step (S52), and a 5-2 step of movably installing the wedge 330 on the strand 220 ( After S54) and step 5-2 (S54), the strand 220 is tensioned, and the wedge 330 is placed in a position close to the fixing hole 322 while the strand 220 is tensioned ( It is fixed to the outer periphery of the strand 220) and includes a 5-3 step (S56) of releasing the tension of the strand 220.

즉, 상기 제5단계(S50)는 상기 제5-3단계(S56) 이후 상기 웨지(330)에 의해 상기 강연선(220)이 인장된 상태로 상기 제1플레이트(320) 즉, 상기 경사버팀지지대(300)의 후방에 고정되도록 함으로써, 상기 벽체파일(100)에 후방 모멘트가 발생되도록 한다.That is, in the fifth step (S50), the first plate 320, that is, the inclined brace support, is performed in a state in which the strand 220 is tensioned by the wedge 330 after the fifth-3 step (S56). By being fixed to the rear of 300, a rearward moment is generated in the wall pile 100.

상기 제5단계(S50) 이후 상기 벽체파일(100)의 전방에 터파기를 시행하여 굴착영역(10)을 형성한다.After the fifth step (S50), excavation is performed in front of the wall pile 100 to form an excavation area 10.

상기는 본 발명의 바람직한 실시예를 참고로 설명하였으며, 본 발명은 상기의 실시예에 한정되지 아니하고, 상기의 실시예를 통해 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 본 발명의 요지를 벗어나지 않는 범위에서 다양한 변경으로 실시할 수 있는 것이다.The above has been described with reference to preferred embodiments of the present invention, and the present invention is not limited to the above embodiments, and through the above embodiments, those skilled in the art will understand the gist of the present invention. It can be implemented with various changes without departing from the scope.

10 : 굴착영역 100 : 벽체파일
200 : 어스앵커 210 : 내하체
220 : 강연선 300 : 경사버팀지지대
310 : 관통홀 320 : 제1플레이트
322 : 고정홀 330 : 웨지
340 : 결합홀 400 : 경사버팀대
410 : 결합판 412 : 체결홀
420 : 연결부재 422 : 제1커플러
423 : 제2커플러 423a : 보강부
423a-1 : 연장보강부 424 : 결합플랜지
425 : 외곽 스티프너 426 : 보강 스티프너
10: Excavation area 100: Wall pile
200: Earth anchor 210: Underbody
220: steel wire 300: inclined brace support
310: Through hole 320: First plate
322: fixing hole 330: wedge
340: coupling hole 400: inclined brace
410: Coupling plate 412: Fastening hole
420: Connecting member 422: First coupler
423: Second coupler 423a: Reinforcement part
423a-1: Extension reinforcement 424: Coupling flange
425: Outer stiffener 426: Reinforcement stiffener

Claims (8)

터파기에 형성된 굴착영역(10)의 경계에 설치되되, 상부가 지상으로 돌출되도록 설치되는 벽체파일(100);과
상기 벽체파일(100)의 후방에 이격되어 지중에 수직하게 설치되는 어스앵커(200);와
지면에 안착되어 설치되되, 전방이 상기 벽체파일(100)의 후면에 결합되고, 후방에 상기 어스앵커(200)의 상부가 관통된 후 고정되는 경사버팀지지대(300); 및
상기 경사버팀지지대(300)의 상부면에 하부가 결합되고, 상기 벽체파일(100)의 상부에 상부가 결합되어 경사지게 설치되는 경사버팀대(400);를 포함하고,
상기 경사버팀지지대(300)는
상부플랜지와 하부플랜지의 후방에 각각 관통형성되되, 웨브를 중심으로 일측과 타측에 대향되도록 형성되는 한 쌍의 관통홀(310);과 상기 상부플랜지의 한 쌍의 관통홀(310)을 덮도록 안착되어 설치되고, 상기 관통홀(310)과 연통되도록 복수 개의 고정홀(322)이 형성되는 제1플레이트(320); 및 하부방향으로 갈수록 외경과 내경이 좁아지도록 형성되고, 상기 고정홀(322)의 상부에 하부가 끼워져 결합되는 웨지(330);를 포함하여 구성되고,
상기 어스앵커(200)는
지중에 삽입되어 고정되는 내하체(210);와 상기 내하체(210)에 하부가 결합되고, 상기 관통홀(310)과 고정홀(322)을 관통하며, 상기 웨지(330)가 상부 외주연에 결합되는 강연선(220);을 포함하고,
상기 경사버팀대(400)는
상부 말단에 형성되고, 상기 벽체파일(100)이 관통되어 고정되는 연결부재(420);를 포함하고,
상기 연결부재(420)는
상기 경사버팀대(400)의 상부 말단에 후방이 결합되고, 전방에 상기 벽체파일(100)의 후방이 내입되는 'ㄷ'형태의 제1커플러(422);와 상기 제1커플러(422)와 대향되도록 위치된 후 복수 개의 볼트를 통해 상기 벽체파일(100)과 결합되는 'ㄷ'형태의 제2커플러(423);를 포함하여 구성되는 것을 특징으로 하는 후열식 버팀장치를 구비한 자립구조물.
A wall pile (100) installed on the border of the excavation area (10) formed in the trench, with the upper part protruding from the ground; and
An earth anchor (200) spaced apart from the rear of the wall pile (100) and installed vertically in the ground; and
An inclined support support 300 that is installed and seated on the ground, the front of which is coupled to the rear of the wall pile 100, and the upper part of the earth anchor 200 penetrating and then being fixed to the rear; and
It includes an inclined brace 400, the lower part of which is coupled to the upper surface of the inclined brace support 300, and the upper part of which is coupled to the upper part of the wall pile 100 and installed at an angle,
The inclined support support 300 is
A pair of through holes 310 formed through the rear of the upper flange and the lower flange, respectively, and formed to face each other on one side and the other around the web; and to cover the pair of through holes 310 of the upper flange. A first plate 320 that is seated and installed and has a plurality of fixing holes 322 formed to communicate with the through hole 310; And a wedge 330 whose outer diameter and inner diameter are formed to become narrower toward the bottom, and whose lower part is fitted and coupled to the upper part of the fixing hole 322,
The earth anchor 200 is
An inner body 210 that is inserted and fixed into the ground; and a lower part is coupled to the inner body 210, penetrates the through hole 310 and the fixing hole 322, and the wedge 330 has an upper outer periphery. Includes a strand (220) coupled to,
The inclined brace 400 is
It includes a connecting member 420 formed at the upper end and through which the wall pile 100 is fixed,
The connecting member 420 is
A first coupler 422 in the shape of 'ㄷ', the rear of which is coupled to the upper end of the inclined brace 400, and the rear of the wall pile 100 is inserted into the front; and opposite to the first coupler 422 A self-supporting structure equipped with a rear-heating support device, characterized in that it includes a second coupler (423) in the shape of 'ㄷ' that is positioned so that it is then coupled to the wall pile (100) through a plurality of bolts.
삭제delete 제1항에 있어서,
상기 경사버팀지지대(300)는
상기 어스앵커(200)의 전방에 위치되도록 관통형성되되, 웨브를 중심으로 일측과 타측에 관통형성되는 복수 개의 결합홀(340);을 포함하여 구성되고,
상기 경사버팀대(400)는
하부 말단에 형성되고, 상기 결합홀(340)과 대응되는 복수 개의 체결홀(412)이 형성되는 결합판(410);을 포함하여 구성되는 것을 특징으로 하는 후열식 버팀장치를 구비한 자립구조물.
According to paragraph 1,
The inclined support support 300 is
A plurality of coupling holes 340 are formed penetratingly so as to be positioned in front of the earth anchor 200, and are formed penetratingly on one side and the other side centered on the web,
The inclined brace 400 is
A self-supporting structure with a post-heating support device, characterized in that it includes a coupling plate (410) formed at the lower end and having a plurality of fastening holes (412) corresponding to the coupling holes (340).
삭제delete 삭제delete 제1항에 있어서,
상기 제1커플러(422)와 제2커플러(423)는
후방 또는 전방 일측과 타측에 돌출형성되는 결합플랜지(424);와
상부 외측면과 하부 외측면에 각각 돌출형성되는 한 쌍의 외곽 스티프너(425); 및
상기 결합플랜지(424)와 측면을 연결하도록 형성되는 복수 개의 보강 스티프너(426);를 포함하여 구성되는 것을 특징으로 하는 후열식 버팀장치를 구비한 자립구조물.
According to paragraph 1,
The first coupler 422 and the second coupler 423 are
A coupling flange 424 protruding on one rear or front side and the other side; and
A pair of outer stiffeners 425 protruding from the upper outer surface and the lower outer surface, respectively; and
A self-supporting structure with a rear-row support device, characterized in that it includes a plurality of reinforcing stiffeners (426) formed to connect the coupling flange (424) and the side surface.
제6항에 있어서,
상기 제2커플러(423)는
후면에 형성되는 보강부(423a);와 양측에 돌출형성되어 상기 제2커플러(423)의 측면까지 연장형성되는 연장보강부(423a-1);를 포함하여 구성되는 것을 특징으로 하는 후열식 버팀장치를 구비한 자립구조물.
According to clause 6,
The second coupler 423 is
A rear-row brace comprising a reinforcing portion 423a formed at the rear; and an extension reinforcing portion 423a-1 protruding from both sides and extending to the side of the second coupler 423. A self-supporting structure equipped with equipment.
제1항, 제3항, 제6항 및 제7항 중 어느 한 항의 후열식 버팀장치를 구비한 자립구조물의 시공방법에 있어서,
벽체파일(100)을 지중에 수직하게 삽입하여 설치하되, 상부가 지상으로 돌출되도록 설치하는 제1단계(S10);와
상기 벽체파일(100)의 후방에 이격되어 지중에 수직하게 어스앵커(200)를 설치하는 제2단계(S20);와
지면에 경사버팀지지대(300)를 설치하되, 상기 어스앵커(200)의 상부가 상기 경사버팀지지대(300)의 후방을 관통하고, 상기 경사버팀지지대(300)의 전방이 벽체파일(100)의 후면에 결합되도록 하는 제3단계(S30);와
상기 벽체파일(100)의 상부에 상기 경사버팀대(400)의 상부를 결합하고, 상기 경사버팀지지대(300)의 상부면에 경사버팀대(400)의 하부를 결합하되, 상기 경사버팀대(400)를 경사지게 설치하는 제4단계(S40); 및
상기 어스앵커(200)를 인장하여 상기 벽체파일(100)이 견고하게 고정되도록 하는 제5단계(S50);를 포함하여 구성되는 것을 특징으로 하는 후열식 버팀장치를 구비한 자립구조물 시공방법.
In the construction method of a self-supporting structure equipped with a rear-heating bracing device according to any one of paragraphs 1, 3, 6, and 7,
A first step (S10) of installing the wall pile 100 by inserting it vertically into the ground, but installing it so that the upper part protrudes above the ground;
A second step (S20) of installing the earth anchor 200 vertically in the ground and spaced apart from the rear of the wall pile 100;
An inclined brace support 300 is installed on the ground, where the upper part of the earth anchor 200 penetrates the rear of the inclined brace support 300, and the front of the inclined brace support 300 is of the wall pile 100. The third step (S30) of coupling to the rear; and
The upper part of the inclined brace 400 is coupled to the upper part of the wall pile 100, and the lower part of the inclined brace 400 is coupled to the upper surface of the inclined brace support 300. The fourth step of installing at an angle (S40); and
A method of constructing a self-supporting structure with a post-heating bracing device, comprising: a fifth step (S50) of tensioning the earth anchor (200) so that the wall pile (100) is firmly fixed.
KR1020230160287A 2023-11-20 2023-11-20 Self-supporting structure with back-row type bracing device and its construction method KR102648051B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020230160287A KR102648051B1 (en) 2023-11-20 2023-11-20 Self-supporting structure with back-row type bracing device and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020230160287A KR102648051B1 (en) 2023-11-20 2023-11-20 Self-supporting structure with back-row type bracing device and its construction method

Publications (1)

Publication Number Publication Date
KR102648051B1 true KR102648051B1 (en) 2024-03-15

Family

ID=90272649

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020230160287A KR102648051B1 (en) 2023-11-20 2023-11-20 Self-supporting structure with back-row type bracing device and its construction method

Country Status (1)

Country Link
KR (1) KR102648051B1 (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120011175A (en) * 2010-07-28 2012-02-07 (주)영신디엔씨 Slope guard construction method using bended connector
KR20120104798A (en) * 2011-03-14 2012-09-24 (주)피에스테크 Apparatus for connecting struts to each other
KR101498711B1 (en) 2013-09-09 2015-03-05 이대동 Soil retaining wall and construction method thereof
KR20200124949A (en) 2019-04-25 2020-11-04 주식회사 일정건설 Anchor Tension way sheathing structure and sheathing method of construction
KR20230130783A (en) * 2022-03-04 2023-09-12 이룸토건 주식회사 Self-supporting retaining structure and its construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120011175A (en) * 2010-07-28 2012-02-07 (주)영신디엔씨 Slope guard construction method using bended connector
KR20120104798A (en) * 2011-03-14 2012-09-24 (주)피에스테크 Apparatus for connecting struts to each other
KR101498711B1 (en) 2013-09-09 2015-03-05 이대동 Soil retaining wall and construction method thereof
KR20200124949A (en) 2019-04-25 2020-11-04 주식회사 일정건설 Anchor Tension way sheathing structure and sheathing method of construction
KR20230130783A (en) * 2022-03-04 2023-09-12 이룸토건 주식회사 Self-supporting retaining structure and its construction method

Similar Documents

Publication Publication Date Title
KR100866162B1 (en) Chair-type self-supported earth retaining wall constructing method
KR102234513B1 (en) Block type reinforcement retaining wall structure and constructing method for the same
KR20200124949A (en) Anchor Tension way sheathing structure and sheathing method of construction
KR100831332B1 (en) Underground retaining wall for public works and method for constructing the same
KR101061516B1 (en) Temporary wall structure using arched steel pile
KR102362257B1 (en) Top-down construction method
KR102648051B1 (en) Self-supporting structure with back-row type bracing device and its construction method
KR102184900B1 (en) Temporary retaining wall structure using circular steel pipe and construction method thereof
JP6477565B2 (en) Reinforcing structure and reinforcing method of existing steel sheet pile wall
KR102490872B1 (en) Reinforced earth retaining wall and construction method using tensile force of steel rod piles
KR200370107Y1 (en) Forms for edge girder construction
US20060177279A1 (en) Reinforcing wall in a deep excavation site
KR102429084B1 (en) Double pile self-reliance retaining wall construction method
KR102476068B1 (en) Retaining wall structure with multidirectional anchor fixtures and construction method thereof
KR102617795B1 (en) Retaining wall system combine H-piles with steel reinforcement structure
KR20190002845U (en) Braced wall
KR102141679B1 (en) Freestanding sheathing construction method using I-type buttress
KR20230030532A (en) Thumb pile using guide bracket and ground anchor and construction method of retaining temporary facility using the same
KR102150531B1 (en) Retaining wall structure using vertical underground insert and its construction method
KR101218825B1 (en) Method of land-side protection wall using bracing
KR101465111B1 (en) Reinforcing structure for protecting landslide and construction method structure for protecting landslide using the same
KR102523155B1 (en) Connecting structure of middle girder and construction method thereof
KR102392517B1 (en) Top-down method using by double beam system
KR102647387B1 (en) Steel assembly for pile for construction of earth retaining wall
KR102265218B1 (en) Wall members and underground wall using the same

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant