KR102522943B1 - Procurement management method for facility construction where cost accounting and bidding are processed using CBS-based design details data including WBS information - Google Patents

Procurement management method for facility construction where cost accounting and bidding are processed using CBS-based design details data including WBS information Download PDF

Info

Publication number
KR102522943B1
KR102522943B1 KR1020220184535A KR20220184535A KR102522943B1 KR 102522943 B1 KR102522943 B1 KR 102522943B1 KR 1020220184535 A KR1020220184535 A KR 1020220184535A KR 20220184535 A KR20220184535 A KR 20220184535A KR 102522943 B1 KR102522943 B1 KR 102522943B1
Authority
KR
South Korea
Prior art keywords
construction
procurement
data
cbs
bidding
Prior art date
Application number
KR1020220184535A
Other languages
Korean (ko)
Inventor
이창호
조명완
유준형
강구형
김지영
김인숙
유흥배
윤현식
최경일
황선호
Original Assignee
대한민국(조달청장)
주식회사 아이디어정보기술
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 대한민국(조달청장), 주식회사 아이디어정보기술 filed Critical 대한민국(조달청장)
Priority to KR1020220184535A priority Critical patent/KR102522943B1/en
Application granted granted Critical
Publication of KR102522943B1 publication Critical patent/KR102522943B1/en

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/04Billing or invoicing
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/06Buying, selling or leasing transactions
    • G06Q30/0601Electronic shopping [e-shopping]
    • G06Q30/0613Third-party assisted
    • G06Q30/0619Neutral agent
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/06Buying, selling or leasing transactions
    • G06Q30/08Auctions

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Human Resources & Organizations (AREA)
  • Accounting & Taxation (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Finance (AREA)
  • Development Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Geometry (AREA)
  • Computer Hardware Design (AREA)
  • Tourism & Hospitality (AREA)
  • Mathematical Analysis (AREA)
  • Structural Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Primary Health Care (AREA)
  • Evolutionary Computation (AREA)
  • Pure & Applied Mathematics (AREA)
  • Mathematical Optimization (AREA)
  • Computational Mathematics (AREA)
  • General Health & Medical Sciences (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to a procurement management method for facility construction in which cost accounting and bidding are processed by using cost breakdown structure (CBS)-based design details data including work breakdown structure (WBS) information. More specifically, for a procurement method for government procurement construction, a procurement agency receives data of CBS-based design details including WBS information that a demanding agency has received from a designer, and then unifies the CBS of the construction with quantity database (QDB) details that are separately written for each lowermost WBS into a construction cost-accounting compatible regulations (C3R) system to be used for cost calculation and confirmation, a construction order bidding notice, and a screening process for a bidding contractor, and a contract.

Description

WBS 데이터가 포함된 CBS 기반의 설계 내역 데이터를 이용하여 원가계산 및 입찰이 처리되는 시설공사 조달 관리 방법{Procurement management method for facility construction where cost accounting and bidding are processed using CBS-based design details data including WBS information}Procurement management method for facility construction where cost accounting and bidding are processed using CBS-based design details data including WBS information }

본 발명은 WBS 데이터가 포함된 CBS 기반의 설계 내역 데이터를 이용하여 원가계산 및 입찰이 처리되는 시설공사 조달 관리 방법에 관한 것으로, 자세하게는 수요기관에서 제출한 WBS 데이터가 포함된 CBS 기반 설계내역서 데이터를 바탕으로 건설공사의 공종별 산출수량과 작업단위별 산출수량 내역이 결합된 원가 계산을 수행하여 시공사들의 입찰 및 심사 과정에 사용토록 하는 조달 관리 방법에 관한 것이다.The present invention relates to a facility construction procurement management method in which cost calculation and bidding are processed using CBS-based design details data including WBS data. Based on this, it is about a procurement management method that performs cost calculation combining the output quantity by work type and the output quantity by work unit, and uses it in the bidding and screening process of construction companies.

일반적으로 국가에서 건설공사 발주하고 조달하는 업무의 흐름을 살펴보면 다음과 같다.In general, the flow of work ordering and procurement of construction works by the state is as follows.

발주처인 수요기관(예, 국토교통부 또는 정부기관)에서 발주 의뢰한 건설사업에 대해 설계사에서 설계도면, 보고서 및 CBS 기반 내역별 원가계산서 정보가 포함된 설계도서를 납품받아 조달기관(조달청 기술과)에 제출하여 발주의뢰 수요제기를 한다. Procurement agency (Public Procurement Service Technology Division) by receiving design drawings, reports, and design documents including CBS-based cost invoice information for each construction project from the design company for the construction project requested by the consuming organization (e.g., Ministry of Land, Infrastructure and Transport or government agency) Submit to and raise demand for ordering request.

이후 조달기관의 담당부서(기술과)에서는 CBS 기반 설계내역서를 바탕으로 원가계산 업무를 진행 후 그 결과를 담당부서(조달청 계약과)에 보내 공사발주 입찰공고를 한다.Afterwards, the department in charge of the procurement agency (Technical Division) proceeds with cost calculation based on the CBS-based design statement, and sends the result to the department in charge (Public Procurement Service Contract Division) to publicize the construction order and bid.

이후 다수의 시공사가 조달기관에서 공고한 입찰공고를 보고 입찰서를 작성 후 응찰한다.(전자 입찰의 경우 만들어진 응찰가와 기본적인 데이터만 응찰시 전송하고 구체적인 데이터는 서류로 첨부함)Afterwards, multiple construction companies read the bidding notice announced by the procurement agency, prepare a tender form, and submit a bid.

이후 조달기관은 내부 심사절차를 거쳐 입찰 종류에 따른 최종 낙찰자(시공사)를 정하여 낙찰 공고하고 계약하는 흐름을 가진다.Afterwards, the procurement agency goes through an internal screening process to determine the final successful bidder (constructor) according to the type of bidding, announces the successful bid, and has a flow of contracting.

이후 시공사는 조달기관에서 정한 CBS 기반 설계내역서를 바탕으로 공사비 및 설계도면에 따라 수요기관이 제기한 공사를 시공하게 된다. 이때 시공사는 공사진행 과정에 따른 비용을 기성처리하기 위해 CBS 기반 설계내역서를 별도로 물량 분개(공종정보, 부위정보, 공간정보, 수량정보)하여 수요기관에 청구하고, 수요기관은 내역분류체계(CBS)에 따라 청구된 공사비에 대한 기성대가를 지불하게 된다.Afterwards, the contractor constructs the construction proposed by the procuring agency according to the construction cost and design drawings based on the CBS-based design statement determined by the procurement agency. At this time, the constructor separates the CBS-based design statement (work type information, part information, space information, quantity information) and claims it to the consuming agency in order to process the cost according to the construction process, and the consuming agency ), payment of the completed price for the requested construction cost.

이후 공사가 준공되면 수요기관은 건물의 생애 주기 동안 관리하는 흐름을 가진다.After that, when the construction is completed, the consuming organization has a flow of management throughout the life cycle of the building.

하지만 상기와 같은 CBS(cost breakdown structure: 내역분류체계)에 따른 내역서를 사용한 국가 건설공사 조달업무는 입찰과정에서 WBS(work breakdown structure: 작업분류체계) 정보가 없어서 내역서에는 임의분류된 공종별 산출기준만 존재하는 수량산출 데이터를 사용하기 때문에 부위별 공간별 분류기준이 없어서 표준화된 공정별 사용되는 물량의 수량산출하여 필요 공사비에 대한 원가계산을 도출하기 어려워 수요기관과 조달기관 및 시공사 간 공사 건물에 대한 공간별, 부위별에 대한 공정별 공사원가 관련 데이터 호환에 많은 불편함을 초래한다는 문제가 있다.(도 6 참조)However, the procurement work for national construction works using a statement based on the CBS (cost breakdown structure) as described above does not have WBS (work breakdown structure) information in the bidding process, so only the calculation criteria for each arbitrarily classified work type are included in the statement Because existing quantity calculation data is used, there is no classification standard for each part and space, so it is difficult to calculate the cost of the required construction cost by calculating the quantity used for each standardized process. There is a problem that it causes a lot of inconvenience in data compatibility related to construction cost by process for each space and part (see Fig. 6).

즉, 조달기관은 수요기관을 통해 제출 받은 CBS 기반 설계내역서에 포함된 데이터를 가지고 입찰 단계에서 공사 원가계산시 필요로 하는 WBS체계 정보를 활용할 수 없어서 정확한 원가산정에 많은 어려움이 있다는 단점이 있다.In other words, the procurement agency cannot utilize the WBS system information required for construction cost calculation at the bidding stage with the data included in the CBS-based design statement submitted by the procuring agency, so it is difficult to accurately estimate the cost.

또한 조달기관에서 CBS 기반 설계내역서를 바탕으로 원가계산시 임의코드로 작성된 자재 정보가 제출될 경우 자재의 단가를 산정하기 위해 수 많은 자재 단가정보를 수작업으로 검색 취합하여 해당 자재와 유사 또는 동일한 것으로 가격 결정을 해야하기 때문에 해당 자재의 정보가 정확하지 않을 수 있고, 또한 최신 자재 단가 정보를 적용하기 어려워 원가계산의 단가 정보의 정확성과 이를 도출하고 결정하는 업무에 많은 시간이 소요된다는 단점이 있다.In addition, when the procurement agency submits material information written in arbitrary code during cost calculation based on the CBS-based design statement, numerous material unit price information is manually searched and collected to calculate the unit price of the material, and the price is similar or identical to the material. Since a decision has to be made, the information on the relevant material may not be accurate, and it is difficult to apply the latest material unit price information, so it takes a lot of time to determine the accuracy of the unit price information of cost calculation and to derive and determine it.

또한 입찰과정을 거쳐 낙찰된 시공사는 계약이후 공사수행 단계에서 기성처리를 위해 WBS체계를 적용하여 공정별로 기성처리를 해야 하기 때문에 CBS 기반 설계내역서 데이터를 수작업으로 물량 분개(공종정보, 부위정보, 공간정보, 수량정보)하는 재작업 과정이 필요하여 공정관리와 계약 및 기성관리에 많은 단점이 있다.In addition, since the contractor who wins the bid through the bidding process must apply the WBS system for ready-made processing for each process at the construction stage after the contract, the CBS-based design statement data is manually classified (work type information, part information, space There are many disadvantages in process management, contracts, and ready-made management because a rework process is required.

또한 수요기관 역시 시공과정에서 시공사로부터 청구된 기성대가를 처리시 공사 진척과 공사비가 별개로 관리되는 기존 관리체계(운영중인 체계 공종항목을 기초로 내역이 작성됨으로 공종 분류체계)에 의해 역번호, 항목, 규격, 단위 등으로 구성 건설사와 관련된 모든 수량과 공사비가 내역분류체계(CBS)로 표현된 데이터로 인해 건설사업관리시스템 운영시 공사비가 실제 공정과의 연계 관리 및 기성근거 확보 등의 한계가 발생하여 이를 검증하고 관리하는데 많은 어려움이 있고, 단순히 문서관리 및 게시판 위주의 기능만을 제공하여 정부 및 민간 영역의 디지털 기반의 활용도가 매우 저조한 상태여서 건설사업관리에 많은 어려움이 있다는 단점이 있다.In addition, when the demand organization also handles the completed price claimed from the constructor during the construction process, the construction progress and construction cost are managed separately. Composed of items, specifications, units, etc. Due to the data expressed in the CBS (CBS) for all quantities and construction costs related to construction companies, there are limitations in managing construction costs in connection with actual processes and securing established basis when operating the construction management system. There are many difficulties in verifying and managing it, and it provides only document management and bulletin board-oriented functions, so the utilization of digital infrastructure in the government and private sectors is very low, so there are many difficulties in managing construction projects.

또한 수요기관은 준공된 건물에 대한 생애주기 관리시 WBS체계(일정) 정보를 활용한 데이터를 확보하지 못해 유지관리비 산정에 많은 어려움이 있다는 단점이 있다.In addition, when managing the life cycle of a completed building, the consuming organization has a disadvantage in that it has many difficulties in calculating the maintenance cost because it cannot secure data using the WBS system (schedule) information.

한국 등록특허공보 등록번호 10-0886418(2009.02.24.)Korea Registered Patent Publication No. 10-0886418 (2009.02.24.) 한국 등록특허공보 등록번호 10-1019231(2011.02.24.)Korea Registered Patent Publication No. 10-1019231 (2011.02.24.) 한국 등록특허공보 등록번호 10-0634586(2006.10.09.)Korea Registered Patent Publication No. 10-0634586 (2006.10.09.) 한국 등록특허공보 등록번호 10-0439565(2004.06.29.)Korea Registered Patent Publication Registration No. 10-0439565 (2004.06.29.)

상기와 같은 문제점을 해결하기 위한 본 발명의 목적은 정부조달 건설공사 조달방법에 있어서 조달기관은 수요기관이 설계사로부터 받은 WBS 데이터가 포함된 CBS 기반 설계 내역서의 데이터를 제출받아 건설공사의 공종별 산출수량(CBS)과 최하위 작업단위별(WBS)로 분리 기재된 작업단위별 산출수량(QDB) 내역을 원가 호환 체계인 C3R 체계로 일원화하여 원가 계산 및 확정, 공사발주 입찰공고, 응찰한 시공사들에 심사 과정 및 계약에 사용하도록 구성된 조달 관리 방법을 제공하는데 있다.The purpose of the present invention to solve the above problems is that in the procurement method for government procurement construction work, the procurement agency receives the data of the CBS-based design statement including the WBS data received from the design company by the procuring agency, and calculates the output quantity for each type of construction work (CBS) and the lowest work unit (WBS), the details of the output quantity (QDB) by work unit, which are separately recorded, are unified into the C3R system, a cost compatible system, to calculate and determine the cost, announce the construction order, bid announcement, and review the bidders and a procurement management method adapted for use in contracts.

또한 본 발명의 다른 목적은 WBS 데이터가 포함된 CBS 기반 설계 내역서 데이터를 바탕으로 원가계산시 표준공사코드에 기반한 자재 데이터를 이용한 디지털데이터와 유사도 검색을 활용하여 자재 단가를 효율적으로 확정하는 조달 관리 방법을 제공하는데 있다.In addition, another object of the present invention is a procurement management method that efficiently determines the unit cost of materials by utilizing digital data and similarity search using material data based on standard construction codes during cost calculation based on CBS-based design statement data including WBS data is providing

또한 본 발명의 다른 목적은 정부 조달에서 낙찰된 시공사는 WBS 데이터가 포함된 CBS 기반 설계내역서 데이터를 활용함으로써 종래처럼 별도의 물량 분개 재작업 없이 즉시 공종정보, 부위정보, 공간정보, 수량정보를 공정관리와 계약 및 기성관리에 활용할 수 있도록 한 조달 관리 방법을 제공하는데 있다.In addition, another object of the present invention is to process the construction type information, part information, space information, and quantity information immediately without separate volume journal rework as in the prior art by utilizing the CBS-based design statement data that includes the WBS data for the contractor that has won a successful bid in government procurement. It is to provide a procurement management method that can be used for management, contract and established management.

또한 본 발명의 다른 목적은 수요기관이 WBS 데이터가 포함된 CBS 기반 설계내역서 데이터를 바탕으로 시공사가 청구한 기성대가 지급에 사용하고, 준공된 건물의 생애주기 관리에 활용할 수 있도록 한 조달 관리 방법을 제공하는데 있다.In addition, another object of the present invention is to provide a procurement management method that allows the requesting agency to use the CBS-based design statement data included in the WBS data to pay for the existing price requested by the constructor and to use it for life cycle management of the completed building. is in providing

상기한 바와 같은 목적을 달성하고 종래의 결점을 제거하기 위한 과제를 수행하는 본 발명은 정부조달 건설공사 조달방법에 있어서, (a) 수요기관 단말에서 조달기관의 공사원가통합관리시스템 서버로 WBS 데이터가 포함된 CBS 기반 설계내역서 데이터를 전송하여 조달 의뢰하는 단계와;The present invention, which achieves the above object and eliminates the conventional drawbacks, is a method for procurement of government procured construction work, (a) WBS data from the terminal of the procuring agency to the integrated construction cost management system server of the procurement agency Requesting procurement by transmitting CBS-based design statement data including;

(b) 조달기관의 공사원가통합관리시스템 서버는 조달 의뢰된 수요기관의 설계내역서 데이터를 검토하여 CBS 기반 공종별 산출 수량 내역과 WBS 기반 작업단위별 산출수량 내역이 결합된 공사원가로 계산하여 확정후, C3R 디지털 표준 형식의 입찰용 공내역서를 작성하여 배포하면서 수요기관의 공사발주를 입찰공고하는 단계와;(b) The server of the integrated construction cost management system of the procurement agency reviews the data of the design statement of the requesting organization requested for procurement, calculates and confirms the construction cost as a combination of the CBS-based output quantity details by work type and the WBS-based output quantity details by work unit , preparing and distributing a public statement for bidding in the C3R digital standard format, and announcing the bid for the construction order of the procuring entity;

(c) 입찰공고에 따라 다수 시공사 단말이 공사원가통합관리시스템 서버에 접속하여 C3R 디지털 표준 형식 공내역서 및 입찰내역작성소프트웨어를 다운로드 후 WBS 및 CBS 기반 산출수량(QDB) 정보가 결합된 C3R 디지털 표준 형식 입찰 내역서를 작성후 업로드하여 전자입찰에 응찰하는 단계와;(c) According to the bidding announcement, multiple construction company terminals access the construction cost integrated management system server, download the C3R digital standard format construction statement and bidding details creation software, and then combine the WBS and CBS-based output quantity (QDB) information into the C3R digital standard. preparing and uploading a formal bid statement and submitting a bid to electronic bidding;

(d) 조달기관의 공사원가통합관리시스템 서버는 업로드된 다수 시공사의 입찰 내역서를 심사후 낙찰자를 선정하는 단계를 거쳐 수요기관에 C3R 디지털 표준 형식으로 작성된 계약내역서(BID)와 WBS 및 CBS 기반 산출수량(QDB)을 포함하는 입찰용 설계내역서를 전송하는 단계와;(d) The procurement agency's integrated construction cost management system server reviews the uploaded bid statements of multiple contractors and selects a successful bidder, and calculates the contract details (BID) written in the C3R digital standard format and WBS and CBS-based calculations to the consuming agency Transmitting a design statement for bidding including a quantity (QDB);

(e) 조달기관의 공사원가통합관리시스템 서버로부터 낙찰자를 통보받은 수요기관의 건설사업관리시스템 서버가 낙찰된 시공사 단말을 통해 계약 확인 및 체결하는 단계;를 포함하는 것을 특징으로 하는 WBS 데이터가 포함된 CBS 기반의 설계 내역 데이터를 이용하여 원가계산 및 입찰이 처리되는 시설공사 조달 관리 방법을 제공함으로써 달성된다.(e) confirming and concluding a contract through the construction company terminal where the construction project management system server of the procuring institution notified of the successful bidder by the construction cost management system server of the procurement institution; This is achieved by providing a facility construction procurement management method in which cost calculation and bidding are processed using the design detail data based on the CBS.

바람직한 실시예로, 상기 시설공사 조달 관리 방법은, In a preferred embodiment, the facility construction procurement management method,

(f) 시공사 단말이 건설 공사 시작 후, 별도의 분개작업 없이 수요기관의 건설사업관리시스템 서버에서 제공받은 WBS 데이터를 기반으로 현장별 WBS를 조정(구간반영)하고 도급내역 정보를 작성 후, 공사 진척도에 따라 기성에 관한 산출 내역서를 작성하여 공사비를 수요기관의 건설사업관리시스템 서버에 청구하는 단계와;(f) After the construction company terminal starts the construction work, without separate journaling, adjust the WBS for each site based on the WBS data provided from the construction project management system server of the procuring entity (reflecting the section), write the contract details information, and preparing a calculation statement for completion according to the progress and claiming the construction cost to the construction project management system server of the procuring agency;

(g) 수요기관의 건설사업관리시스템 서버가 시공사 단말에서 전송된 산출내역서의 WBS 데이터를 기반으로 기성내역을 검토하여 기성 공사비를 지불하면서 공사진척관리를 진행하는 단계;를 더 포함하는 것을 특징으로 한다.(g) a step in which the construction project management system server of the requesting organization reviews the finished details based on the WBS data of the calculation statement transmitted from the constructor terminal and proceeds with the construction progress management while paying the ready-made construction cost; do.

바람직한 실시예로, 상기 시설공사 조달 관리 방법은, In a preferred embodiment, the facility construction procurement management method,

(h) 수요기관의 건설사업관리시스템 서버가 준공된 건물에 대한 유지관리를 WBS 데이터가 포함된 CBS 기반 데이터를 기반한 준공도서를 납품받아 시설물유지관리시스템 서버로 이관하여 유지관리하는 단계;를 더 포함하는 것을 특징으로 한다.(h) the step of transferring the maintenance of the completed building to the facility maintenance management system server by receiving the completed building based on the CBS-based data including the WBS data; It is characterized by including.

바람직한 실시예로, 상기 (a) 단계는, In a preferred embodiment, the step (a) is,

(a') 수요기관의 건설사업관리시스템 서버에 접속한 설계사 단말을 통해 설계사가 작성한 설계도면 데이터와; 조달기관의 표준공사코드로 기재된 CBS 기반 공종별 산출 수량과 원가 내역과 WBS 기반 작업단위별 산출수량과 원가 내역이 결합된 설계내역서 데이터;가 포함된 설계도서 파일을 납품받는 단계를 포함하는 것을 특징으로 한다.(a') design drawing data prepared by the designer through the designer's terminal connected to the construction project management system server of the procuring entity; It is characterized by including the step of receiving the design document file containing; do.

바람직한 실시예로, 상기 표준공사코드는 설계사 단말이 조달기관의 공사원가통합관리시스템 서버에 접속해 내려받는 코드로, 공정분류에 따라 품명과 규격 단위, 규격화 여부로 분류된 세부공종코드로 이루어진 공종별코드와; 물품분류에 따라 품명, 규격, 단위, 인도조건, 지수구분, 물품설명으로 분류된 순수자원코드로 이루어진 물품별 코드;인 것을 특징으로 한다.In a preferred embodiment, the standard construction code is a code that is downloaded by the designer terminal by accessing the integrated construction cost management system server of the procurement agency. code; Characterized in that it is a code for each item consisting of pure resource codes classified into product name, standard, unit, delivery condition, index classification, and product description according to product classification.

바람직한 실시예로, 상기 (b) 단계와 (C)단계의 C3R 디지털 표준 형식의 입찰용 공내역서 또는 (C)단계와 (d)단계의 C3R 디지털 표준 형식 입찰 내역서는 조달기관에서 규정한 입찰정보, 단위공사, 단위공사내역서, 원가계산서, 하도급 조사금액, 하도급 공사비산출서, 하도급 내역서, 작업분류 수량, 작업분류 정보, 하도급가능 심사업종 정보 구조로 작성된 XML 형식 파일인 것을 특징으로 한다.In a preferred embodiment, the public statements for bidding in the C3R digital standard format in the steps (b) and (C) or the bidding statements in the C3R digital standard format in the steps (C) and (d) are the bidding information specified by the procurement agency. , unit work, unit construction statement, cost invoice, subcontract investigation amount, subcontract construction cost calculation statement, subcontract statement, work classification quantity, work classification information, characterized in that it is an XML format file created in the information structure of subcontractable categories.

바람직한 실시예로, 상기 (b) 단계에서 조달기관의 공사원가통합관리시스템 서버는 자재단가 원가계산시 수요기관에서 전송된 WBS 데이터가 포함된 CBS 기반 설계내역서의 원가정보를 해당 데이터에 포함된 표준공사코드를 기반으로 검토 대상 자재명, 규격, 단위를 직전 3개월 검토자료 데이터와, 정기가격조사 자료 데이터를 가지고 유사도 알고리즘을 적용하여 비교 검토한 단가데이터와, 물가협회 디지털 자재단가 단가 데이터를 비교하여 원가계산하는 단계를 수행하는 것을 특징으로 한다.In a preferred embodiment, in step (b), the server of the integrated construction cost management system of the procurement agency converts the cost information of the CBS-based design statement including the WBS data transmitted from the procuring agency when the cost is calculated to the standard included in the data. Based on the construction code, the unit price data that was compared and reviewed by applying the similarity algorithm with the review data of the previous three months for the material name, standard, and unit to be reviewed and the data of the regular price survey data, and the unit price data of the Digital Materials Foundation of the Korea Price Association It is characterized by performing a cost calculation step.

바람직한 실시예로, 상기 설계내역서는 조달기관(조달청)의 C3R 기반 설계내역서 디지털 표준을 만족하고, 입찰내역서는 조달기관(조달청)의 입찰내역서(BID) 디지털 표준을 만족하는 파일이고,In a preferred embodiment, the design details are files that satisfy the C3R-based design specifications digital standard of the procurement agency (Public Procurement Service), and the bidding details satisfy the digital standards of the bidding details (BID) of the procurement agency (Public Procurement Service),

상기 설계내역서 중 CBS는 조달기관(조달청)의 CBS 데이터 표준을 만족하고, 상기 WBS는 국토교통부 및 수요기관의 데이터 표준을 만족하는 파일로 구성된 것을 특징으로 한다.Among the design specifications, the CBS satisfies the CBS data standard of the procurement agency (Public Procurement Service), and the WBS is characterized in that it consists of files that satisfy the data standard of the Ministry of Land, Infrastructure and Transport and the demand agency.

바람직한 실시예로, 상기 설계내역서에 포함된 작업단위별(WBS) 내역은 시설명, 공종명, 시설물명, 방향공간명, 확장공간명, 작업관리명, 세부작업관리명으로 이루어진 7단계 레벨의 수량 및 단가 정보가 포함된 것을 특징으로 한다.In a preferred embodiment, the details of each work unit (WBS) included in the design statement are 7 levels of facility name, work species name, facility name, direction space name, expansion space name, work management name, and detailed work management name. It is characterized by including quantity and unit price information.

바람직한 실시예로, 상기 공사원가통합관리시스템 서버는,In a preferred embodiment, the construction cost integrated management system server,

수요기관에서 의뢰된 공사원가를 산정하는 공사원가계산 모듈; 설계사, 수요기관, 시공사에서 공통적으로 사용될 표준공사코드를 관리하는 공사코드운영모듈; 제출된 설계내역서와 입찰내역서가 공사호환규정을 준수하는 디지털파일 형식인지를 검증하는 C3R호환검증 모듈; 제출된 내역을 심사하는 내역입찰심사모듈; 제출된 내역을 심사하는 종합심사제평가모듈; 공내역서 데이터와 입찰내역작성프로그램을 관리하는 입찰내역작성프로그램 모듈;을 포함하는 것을 특징으로 한다.Construction cost calculation module for calculating the construction cost commissioned by the consuming organization; A construction code operation module that manages standard construction codes commonly used by design companies, demand organizations, and construction companies; A C3R compatibility verification module that verifies whether the submitted design details and bidding statements are in digital file format that complies with construction compatibility regulations; Details tender review module for reviewing the submitted details; Comprehensive review system evaluation module that reviews submitted details; It is characterized in that it includes; a bid details writing program module that manages the public statement data and the bid details writing program.

상기와 같은 특징을 갖는 본 발명은 정부조달 건설공사 조달방법에 있어서 조달기관은 수요기관이 설계사로부터 받은 WBS 데이터가 포함된 CBS 기반 설계 내역서의 데이터를 제출받아 건설공사의 공종별 산출수량(CBS)과 최하위 작업단위별(WBS)로 분리 기재된 작업단위별 산출수량(QDB) 내역을 원가 호환 체계인 C3R 체계로 일원화하여 원가 계산 및 확정, 공사발주 입찰공고, 응찰한 시공사들에 심사 과정 및 계약에 사용하도록 조달 업무를 구성하였다는 효과를 가진다.In the present invention having the above characteristics, in the government procurement construction procurement method, the procurement agency receives the data of the CBS-based design statement including the WBS data received from the design company by the consuming agency, and calculates the quantity (CBS) and The details of output quantity (QDB) by work unit, which are separately listed by the lowest work unit (WBS), are unified into the C3R system, which is a cost compatible system, and used for cost calculation and confirmation, construction order bidding announcement, and evaluation process and contract with bidders. It has the effect of organizing the procurement work to

즉, 데이터 표준은 조달기관의 WBS 데이터와 수요기관의 WBS 데이터가 결합된 데이터로 표준화하고, 디지털 표준은 조달기관의 C3R 기반 설계내역서와 BID 데이터를 디지털 표준으로 일원화된 세부공정 합산 내역서를 사용하여 발주기관, 조달기관 및 시공사 간의 데이터가 활용되도록 하였다는 효과를 가진다.In other words, the data standard standardizes the combined data of the procurement agency's WBS data and the consuming agency's WBS data, and the digital standard uses the procurement agency's C3R-based design statement and BID data as a digital standard and unifies detailed process summation statements. It has the effect of allowing data between the ordering agency, the procurement agency, and the construction company to be utilized.

또한 본 발명은 WBS 데이터가 포함된 CBS 기반 설계내역서 데이터를 바탕으로 원가계산시 표준공사코드에 기반한 자재 데이터를 이용한 디지털데이터와 유사도 검색을 활용하여 자재 단가를 효율적으로 확정할 수 있다는 효과를 가진다.In addition, the present invention has the effect of efficiently determining the unit cost of materials by utilizing digital data and similarity search using material data based on standard construction codes during cost calculation based on CBS-based design specification data including WBS data.

또한 본 발명은 정부 조달에서 낙찰된 시공사는 WBS 데이터가 포함된 CBS 기반 설계내역서 데이터를 활용함으로써 종래처럼 별도의 물량 분개 재작업 없이 즉시 공종정보, 부위정보, 공간정보, 수량정보를 공정관리와 계약 및 기성관리에 활용가능하다는 효과를 가진다.In addition, the present invention contracts with process management for construction type information, part information, space information, and quantity information immediately without separate volume journaling rework as in the prior art by utilizing CBS-based design statement data that includes WBS data for the contractor who has won a successful bid in government procurement. And it has the effect that it can be used for ready-made management.

또한 본 발명은 수요기관은 WBS 데이터가 포함된 CBS 기반 설계내역서 데이터를 바탕으로 시공사가 청구한 기성대가 지급에 사용하고, 준공된 건물의 생애주기 관리에 활용 가능하다는 효과를 가진다.In addition, the present invention has an effect that the demand organization can use the CBS-based design statement data included in the WBS data to pay for the finished price requested by the constructor, and can be used for life cycle management of the completed building.

또한 본 발명은 조달기관(조달청)의 데이터 표준화 및 공사원가통합관리시스템 구축사업을 통하여 정부, 국토교통부, 산하기관 및 민간 건설관련업계(건설,설계,SW, 물가지기관 등)와의 QDB가 탑재된 C3R기준 기반으로 작성, 유통, 활용을 할 수 있는 상호간의 협약과 이를 지원하는 공공기관의 디지털 데이터 기준과 정보시스템이 구축되어 이를 민간 영역의 다양한 업무용 소프트웨어, 플랫폼에서 유통될 수 있다는 효과를 가진다.In addition, the present invention is equipped with QDB with the government, the Ministry of Land, Infrastructure and Transport, affiliated organizations and private construction-related industries (construction, design, SW, water branch agencies, etc.) through data standardization of procurement agencies (Public Procurement Service) and construction cost integrated management system construction Mutual agreements that can be created, distributed, and utilized based on the established C3R standards, and digital data standards and information systems of public institutions that support them are established, which have the effect of distributing them in various business software and platforms in the private sector. .

또한 본 발명은 국토교통부, 조달청 주도 건설분야의 양대축인 공정(WBS, QDB)과 공사비(C3R, BID)가 일체화될 수 있다는 효과를 가진다.In addition, the present invention has an effect that the process (WBS, QDB) and the construction cost (C3R, BID), which are the two major axes of the construction sector led by the Ministry of Land, Infrastructure and Transport and the Public Procurement Service, can be integrated.

또한 본 발명은 조달업무에 있어서 설계단계의 발주자, 설계사, 기자재업체, 물가지기관, 관련지자체 등과의 C3R 기반의 정보와 데이터를 제공하고, 조달기관에서의 입찰/심사/평가단계에서 조달기관(조달청), 발주자(수요기관), 입찰자 등과의 정보를 처리하며, 건설단계에서는 발주자(수요기관), 계약자(건설사,CM/감리,기자재업체 등)와 관련 행정기관과의 정보(데이터)전달 및 커뮤니케이션을 지원할 수 있다는 효과를 가진다.In addition, the present invention provides C3R-based information and data with the owner, design company, equipment company, water agency, related local government, etc. in the design stage in procurement work, and procurement agency ( Public Procurement Service), owner (demanding organization), and bidder, etc. are processed, and in the construction stage, information (data) transmission and It has the effect of being able to support communication.

본 발명은 상기와 같은 다양한 효과를 가진 유용한 발명으로 산업상 그 이용이 크게 기대되는 발명이다.The present invention is a useful invention having various effects as described above, and its use in industry is greatly expected.

도 1은 본 발명의 한 실시예에 따른 개략적인 조달 시스템의 구성도이고,
도 2는 본 발명의 한 실시예에 따른 조달 방법을 보인 순서도이고,
도 3은 본 발명의 한 실시예에 따른 WBS 기반 내역과 CBS 기반 내역이 결합된 설계 내역구조를 보인 예시도이고,
도 4는 본 발명의 한 실시예에 따른 WBS 구조를 보인 예시도이고,
도 5는 종래 한 실시예에 따른 CBS 기반 내역의 설계 내역구조를 보인 예시도이다.
1 is a block diagram of a schematic procurement system according to an embodiment of the present invention;
Figure 2 is a flow chart showing a procurement method according to an embodiment of the present invention,
3 is an exemplary view showing a design details structure in which WBS-based details and CBS-based details are combined according to an embodiment of the present invention;
4 is an exemplary diagram showing a WBS structure according to an embodiment of the present invention;
5 is an exemplary diagram showing a design details structure of CBS-based details according to a conventional embodiment.

이하 본 발명의 실시 예인 구성과 그 작용을 첨부도면에 연계시켜 상세히 설명하면 다음과 같다. 또한 본 발명을 설명함에 있어서, 관련된 공지기능 혹은 구성에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우 그 상세한 설명은 생략한다. Hereinafter, the configuration and operation of an embodiment of the present invention will be described in detail in association with the accompanying drawings. In addition, in describing the present invention, if it is determined that a detailed description of a related known function or configuration may unnecessarily obscure the gist of the present invention, the detailed description will be omitted.

이하 본 발명에서 WBS(work breakdown structure)는 공사내용을 파악하기 위해서 작업의 공종별로 세분화시킨 작업분류체계를 말한다.Hereinafter, in the present invention, a work breakdown structure (WBS) refers to a work breakdown structure subdivided by work type in order to understand construction details.

또한 이하 본 발명에서 CBS(cost breakdown structure)는 비용분류체계를 말한다.In addition, in the present invention, a cost breakdown structure (CBS) refers to a cost classification system.

또한 본 발명에서 QDB(Quantity Data Base)는 수량산출DB(부위별물량내역서)를 말한다.In addition, in the present invention, QDB (Quantity Data Base) refers to a quantity calculation DB (quantity statement for each part).

또한 이하 본 발명에서 C3R(Construction Cost-accounting Compatible Regulations)은 조달기관의 공사 원가 호환 규정을 말한다.Further, in the present invention, C3R (Construction Cost-accounting Compatible Regulations) refers to construction cost-accounting compatible regulations of a procurement agency.

또한 이하 본 발명에서 QDB(Quanity Data Base)는 국토교통부의 CALS 체계의 일환으로 공정, 공사비의 실시간 관리를 위한 작업분류체계 기반의 수량산출정보 표준파일 규격으로 건설정보표준 6종에 포함되어 국토교통부 및 산하기관의 표준을 말한다.In addition, in the present invention, QDB (Quanity Data Base) is a work classification system-based quantity calculation information standard file standard for real-time management of processes and construction costs as part of the CALS system of the Ministry of Land, Infrastructure and Transport, and is included in six types of construction information standards. and standards of affiliated organizations.

도 1은 본 발명의 한 실시예에 따른 개략적인 조달 시스템의 구성도이고, 도 2는 본 발명의 한 실시예에 따른 공사원가통합관리시스템 서버의 구성을 보인 예시도이고, 도 3은 본 발명의 한 실시예에 따른 조달 방법을 보인 순서도이고, 도 4는 본 발명의 한 실시예에 따른 WBS 기반 내역과 CBS 기반 내역이 결합된 설계 내역구조를 보인 예시도이고, 도 5는 본 발명의 한 실시예에 따른 WBS 구조를 보인 예시도이다.1 is a schematic configuration diagram of a procurement system according to an embodiment of the present invention, FIG. 2 is an exemplary view showing the configuration of a construction cost integrated management system server according to an embodiment of the present invention, and FIG. 3 is an exemplary view of the present invention. It is a flow chart showing a procurement method according to an embodiment of the present invention, Figure 4 is an exemplary view showing a design details structure in which WBS-based details and CBS-based details are combined according to an embodiment of the present invention, Figure 5 is one of the present invention It is an exemplary diagram showing a WBS structure according to an embodiment.

도시된 바와 같이 본 발명의 시스템은 크게 정부조달 건설공사 조달업무를 위해 조달기관의 공사원가통합관리시스템 서버(1), 수요기관의 단말(2), 시공사의 단말(3), 설계사의 단말(4)이 유무선 방식으로 연결되어 WBS 데이터가 포함된 CBS 기반 설계내역서 데이터를 포함한 각종 데이터가 교환되도록 구성된다.As shown, the system of the present invention is largely divided into a construction cost integrated management system server (1) of a procurement agency, a terminal (2) of a demand agency, a terminal (3) of a constructor, and a terminal ( 4) is connected in a wired/wireless manner so that various data including CBS-based design specification data including WBS data are exchanged.

상기 공사원가통합관리시스템 서버(1)는 수요기관에서 의뢰된 공사원가를 산정하는 공사원가계산 모듈(11); 설계사, 수요기관, 시공사에서 공통적으로 사용될 표준공사코드를 관리하는 공사코드운영모듈(12); 제출된 설계내역서와 입찰내역서가 공사호환규정을 준수하는 디지털파일 형식인지를 검증하는 C3R호환검증 모듈(13); 제출된 내역을 심사하는 내역입찰심사모듈(14); 제출된 내역을 심사하는 종합심사제평가모듈(15); 공내역서 데이터와 입찰내역작성프로그램을 관리하는 입찰내역작성프로그램 모듈(16);을 포함한다. The construction cost integrated management system server 1 includes a construction cost calculation module 11 for calculating the construction cost requested by the consuming organization; A construction code operation module 12 that manages standard construction codes commonly used by design companies, demand organizations, and construction companies; A C3R compatible verification module 13 that verifies whether the submitted design details and bid details are in digital file format that complies with construction compatibility regulations; Details of the bid review module 14 for reviewing the submitted details; Comprehensive screening system evaluation module 15 for reviewing the submitted details; A bid details writing program module 16 that manages the public statement data and the bid details writing program;

또한 공사원가통합관리시스템 서버(1)는 상기 각 모듈에서 생성된 데이터가 수요기관의 단말(2) 및 시공사의 단말(3)에서 전송된 데이터를 저장하는 통합 DB 저장소 또는 각 모듈만을 위한 DB 저장소가 구비된다.In addition, the integrated construction cost management system server 1 stores the data generated in each module transmitted from the terminal 2 of the procuring agency and the terminal 3 of the contractor, or a DB storage for each module only. is provided

상기 수요기관의 단말(2)은 조달업무 수행시에는 조달기관의 공사원가통합관리시스템 서버(1)와 데이터를 교환하는 클라이언트 단말로 활용되고, 시공사의 단말(3), 설계사의 단말(4)과 관련해서는 건설사업관리시스템 서버 역할을 한다. 또한 건설공사 준공후에는 시설물유지관리시스템 서버로 활용된다.The terminal 2 of the demand organization is used as a client terminal exchanging data with the server 1 of the integrated construction cost management system of the procurement agency when performing procurement work, and the terminal 3 of the constructor and the terminal 4 of the designer In relation to , it serves as a construction project management system server. In addition, after construction is completed, it is used as a facility maintenance management system server.

상기 수요기관의 단말(2)을 구성하는 조달과정에서의 클라이언트 단말, 건설사업관리시스템 서버 및 시설물유지관리시스템 서버는 하나의 컴퓨터시스템으로 구성하여 각 클라이언트프로그램과 서버프로그램이 탑재되도록 구성하거나 각각의 컴퓨터시스템으로 구성하여 각각 조달관련 클라이언트프로그램 또는 시공관리 관련 서버프로그램 또는 시설물유지관리 관련 서버 프로그램이 탑재되도록 구성할 수 있음은 물론이다. The client terminal, construction project management system server, and facility maintenance management system server in the procurement process constituting the terminal 2 of the demand organization are configured as one computer system so that each client program and server program are installed, or each Of course, it can be configured as a computer system so that procurement-related client programs, construction management-related server programs, or facility maintenance-related server programs are installed.

다만, 편의상 본 발명에서는 하나의 컴퓨터시스템으로 설명한다.However, for convenience, the present invention describes a single computer system.

상기 시공사의 단말(3), 설계사의 단말(4)은 조달기관의 공사원가통합관리시스템 서버(1)와의 관계에서는 조달관련 클라이언트 단말로 활용되고, 수요기관의 단말이 건설사업관리시스템 서버 역할을 할때는 설계 및 시공관련 클라이언트 단말로 활용된다. 이 경우도 하나의 컴퓨터시스템으로 구성하거나 별도의 컴퓨터시스템으로 구성할 수 있음은 물론이다.The construction company's terminal (3) and designer's terminal (4) are used as procurement-related client terminals in relation to the construction cost integrated management system server (1) of the procurement agency, and the terminal of the procuring agency serves as a construction project management system server. It is used as a client terminal related to design and construction. Of course, in this case, it can be configured as one computer system or as a separate computer system.

다만, 편의상 본 발명에서는 하나의 컴퓨터시스템으로 설명한다.However, for convenience, the present invention describes a single computer system.

상기와 같은 본 발명 구성을 통해 수행되는 정부조달 건설공사 조달방법은 다음과 같은 흐름을 가진다.The government procurement construction work procurement method performed through the configuration of the present invention as described above has the following flow.

(a) 수요기관 단말에서 조달기관의 공사원가통합관리시스템 서버로 WBS 데이터가 포함된 CBS 기반 설계내역서 데이터를 전송하여 조달 의뢰하는 단계를 가진다.(a) Step of requesting procurement by transmitting CBS-based design specification data including WBS data from the terminal of the procuring entity to the integrated construction cost management system server of the procurement agency.

이때 상기 (a) 단계는, (a') 수요기관의 건설사업관리시스템 서버에 접속한 설계사 단말을 통해 설계사가 작성한 설계도면 데이터와; 조달기관의 표준공사코드로 기재된 CBS 기반 공종별 산출 수량과 원가 내역과 WBS 기반 작업단위별 산출수량과 원가 내역이 결합된 설계내역서 데이터;가 포함된 설계도서 파일을 납품받는 단계를 포함한다.At this time, the step (a) includes: (a') design drawing data prepared by the designer through the designer terminal connected to the construction project management system server of the procuring agency; Includes a step of receiving a design document file including; the design statement data that combines the calculated quantity and cost details by work type based on CBS and the calculated quantity and cost details by work unit based on WBS described in the standard construction code of the procurement agency;

상기 표준공사코드는 설계사 단말이 조달기관의 공사원가통합관리시스템 서버에 접속해 표준공사코드를 관리하는 공사코드운영모듈(12)에서 내려받는 코드로, 공정분류에 따라 품명과 규격 단위, 규격화 여부로 분류된 세부공종코드로 이루어진 공종별코드와; 물품분류에 따라 품명, 규격, 단위, 인도조건, 지수구분, 물품설명으로 분류된 순수자원코드로 이루어진 물품별 코드;로 이루어진다.The standard construction code is a code downloaded from the construction code operation module 12 that manages the standard construction code by accessing the construction cost integrated management system server of the procurement agency by the designer terminal. A code for each work type consisting of detailed work code classified as; Code for each item consisting of pure resource codes classified into product name, standard, unit, delivery condition, index classification, and product description according to product classification.

상기 설계내역서에 포함된 작업단위별(WBS) 내역은 시설명, 공종명, 시설물명, 방향공간명, 확장공간명, 작업관리명, 세부작업관리명으로 이루어진 7단계 레벨의 수량 및 단가 정보가 포함된 것The details of each work unit (WBS) included in the design specifications include the quantity and unit price information of 7 levels consisting of facility name, work type name, facility name, direction space name, expansion space name, work management name, and detailed work management name. included

(b) 이후 조달기관의 공사원가통합관리시스템 서버는 조달 의뢰된 수요기관의 설계내역서 데이터를 검토하여 CBS 기반 공종별 산출 수량 내역과 WBS 기반 작업단위별 산출수량 내역이 결합된 공사원가로 계산하여 확정후, C3R 디지털 표준 형식의 입찰 공내역서를 작성하여 배포하면서 수요기관의 공사발주를 입찰공고하는 단계를 가진다.(b) Afterwards, the procurement agency's integrated construction cost management system server reviews the data of the design statement of the demand organization requested for procurement, and calculates and confirms the construction cost as a combination of the CBS-based output quantity details by work type and the WBS-based output quantity details by work unit. Afterwards, there is a step of publicizing the bid for the construction order of the procuring organization while preparing and distributing the bidding statement in the C3R digital standard format.

상기 C3R 디지털 표준 형식의 입찰용 공내역서는 조달기관에서 규정한 입찰정보, 단위공사, 단위공사내역서, 원가계산서, 하도급 조사금액, 하도급 공사비산출서, 하도급 내역서, 작업분류 수량, 작업분류 정보, 하도급가능 심사업종 정보 구조로 작성된 XML 형식 파일이다.The construction statement for bidding in the C3R digital standard format includes bidding information, unit construction, unit construction statement, cost invoice, subcontract investigation amount, subcontract construction cost calculation statement, subcontract statement, work classification quantity, work classification information, and subcontracting specified by the procurement agency. It is an XML formatted file written in the information structure of the applicable category of examination.

상기 조달기관의 공사원가통합관리시스템 서버는 자재단가 원가계산시 공사원가계산 모듈(11)에서 수요기관에서 전송된 WBS 데이터가 포함된 CBS 기반 설계내역서의 원가정보를 해당 데이터에 포함된 표준공사코드를 기반으로 검토 대상 자재명, 규격, 단위를 직전 3개월 검토자료 데이터와, 정기가격조사 자료 데이터를 가지고 유사도 알고리즘을 적용하여 비교 검토한 단가데이터와, 물가협회 디지털 자재단가 단가 데이터를 비교하여 원가계산하는 단계를 수행한다.The construction cost integrated management system server of the procurement agency converts the cost information of the CBS-based design statement including the WBS data transmitted from the procuring agency in the construction cost calculation module 11 to the standard construction code included in the data when the material cost is calculated. Cost calculation by comparing the unit price data, which was compared and reviewed by applying the similarity algorithm with the data of the material name, standard, and unit to be reviewed for the immediately preceding 3 months, and the data of the regular price survey data, and the unit price data of the Digital Materials Foundation of the Korea Price Association. perform the steps

상기 유사도 알고리즘으로는 편집거리개념, 같은 낱말이 문자열 내 특정한 거리내에 있을 때 높은 관련도 점수를 할당하는 Jaro-Winkier Distance를 사용하여 수행할 수 있다. 이 방식은 정밀도/재현율이 0.476/0.710의 값을 가진다.The similarity algorithm can be performed using the Jaro-Winkier Distance concept, which assigns a high relevance score when the same word is within a specific distance in the text string. This method has precision/recall values of 0.476/0.710.

(c) 이후 입찰공고에 따라 다수 시공사 단말이 공사원가통합관리시스템 서버에 접속하여 C3R 디지털 표준 형식 공내역서 및 입찰내역작성소프트웨어를 다운로드 후 WBS 및 CBS 기반 산출수량(QDB) 정보가 결합된 C3R 디지털 표준 형식 입찰 내역서를 작성후 업로드하여 전자입찰에 응찰하는 단계를 가진다.(c) Following the bidding notice, multiple construction company terminals access the construction cost integrated management system server, download the C3R digital standard format construction statement and bidding details creation software, and then combine the WBS and CBS-based output quantity (QDB) information into the C3R digital After preparing the standard format bidding statement, upload it and submit a bid to the electronic bidding.

상기 C3R 디지털 표준 형식의 입찰용 공내역서는 조달기관에서 규정한 입찰정보, 단위공사, 단위공사내역서, 원가계산서, 하도급 조사금액, 하도급 공사비산출서, 하도급 내역서, 작업분류 수량, 작업분류 정보, 하도급가능 심사업종 정보 구조로 작성된 XML 형식 파일이고, 입찰 내역서는 해당 공내역에 시공사의 정보가 입력된 파일이다.The construction statement for bidding in the C3R digital standard format includes bidding information, unit construction, unit construction statement, cost invoice, subcontract investigation amount, subcontract construction cost calculation statement, subcontract statement, work classification quantity, work classification information, and subcontracting specified by the procurement agency. It is an XML formatted file written in the information structure of possible types of examination, and the bidding statement is a file in which the information of the construction company is entered in the relevant public sector.

상기 공사원가통합관리시스템 서버는 공내역서 데이터와 입찰내역작성프로그램을 관리하는 입찰내역작성프로그램 모듈(16)을 통해 해당 단말기로 해당 데이터를 전송하는 과정을 가진다.The construction cost integrated management system server has a process of transmitting the corresponding data to the corresponding terminal through the bid details writing program module 16 that manages the construction bill data and the bid details writing program.

(d) 이후 조달기관의 공사원가통합관리시스템 서버는 업로드된 다수 시공사의 입찰 내역서를 심사후 낙찰자를 선정하는 단계를 거쳐 수요기관에 C3R 디지털 표준 형식으로 작성된 계약내역서(BID)와 WBS 및 CBS 기반 산출수량(QDB)을 포함하는 입찰용 설계내역서를 전송하는 단계를 가진다.(d) Afterwards, the procurement agency's integrated construction cost management system server reviews the uploaded bid statements of multiple constructors and selects a successful bidder, and provides the contract details (BID) written in the C3R digital standard format to the consuming agency based on WBS and CBS. and transmitting a design statement for bidding including an output quantity (QDB).

상기 C3R 디지털 표준 형식의 입찰 내역서는 조달기관에서 규정한 입찰정보, 단위공사, 단위공사내역서, 원가계산서, 하도급 조사금액, 하도급 공사비산출서, 하도급 내역서, 작업분류 수량, 작업분류 정보, 하도급가능 심사업종 정보 구조로 공내역에 입찰한 시공사의 정보가 입력되어 작성된 XML 형식 파일이다.The bidding statement in the C3R digital standard format includes bidding information, unit work, unit construction statement, cost invoice, subcontract investigation amount, subcontract construction cost calculation statement, subcontract statement, work classification quantity, work classification information, and subcontractability review specified by the procurement agency. It is an XML format file created by inputting the information of the construction company that bid for the public sector in the industry information structure.

상기 조달기관의 공사원가통합관리시스템 서버는 C3R호환검증 모듈(13)을 이용래 제출된 C3R 디지털 표준 형식으로 작성된 계약내역서(BID)와 WBS 및 CBS 기반 산출수량(QDB)을 포함하는 입찰 내역서가 공사호환규정을 준수하는지 여부를 확인하여 불수리 또는 재작성 기회를 가질 수 있게 할 수 있다.The construction cost integrated management system server of the procurement agency uses the C3R compatibility verification module 13 to submit contract details (BID) in the C3R digital standard format and bid details including WBS and CBS-based output quantity (QDB). You can check whether it complies with the compatibility regulations so that you have the opportunity to make a non-repair or rewrite.

또한 상기 공사원가통합관리시스템 서버는 제출된 내역을 심사하는 내역입찰심사모듈(14); 제출된 내역을 심사하는 종합심사재평가모듈(15);을 통해 해당 입찰내역서의 내용을 검증하여 담합을 검증하고 해당 입찰방식에 따른 적절한 시공사 낙찰과정을 수행한다.In addition, the construction cost integrated management system server includes a detailed bid review module 14 for reviewing the submitted details; Comprehensive review and re-evaluation module 15 that reviews the submitted details; verifies the contents of the bidding details to verify collusion, and performs an appropriate bidding process for the construction company according to the bidding method.

또한 상기 설계내역서는 조달기관(조달청)의 C3R 기반 설계내역서 디지털 표준을 만족하고, 입찰내역서는 조달기관(조달청)의 입찰내역서(BID) 디지털 표준을 만족하는 파일이고, 상기 설계내역서 중 CBS는 조달기관(조달청)의 CBS 데이터 표준을 만족하고, 상기 WBS는 국토교통부 및 수요기관의 데이터 표준을 만족하는 파일로 구성된다.In addition, the design details satisfy the C3R-based design specifications digital standard of the procurement agency (Public Procurement Service), and the bidding details are files that satisfy the digital standard of the bidding details (BID) of the procurement agency (Public Procurement Service). It satisfies the CBS data standard of the agency (Public Procurement Service), and the WBS is composed of files that satisfy the data standard of the Ministry of Land, Infrastructure and Transport and the demand agency.

상기 설계내역서에 포함된 작업단위별(WBS) 내역은 시설명, 공종명, 시설물명, 방향공간명, 확장공간명, 작업관리명, 세부작업관리명으로 이루어진 7단계 레벨의 수량 및 단가 정보가 포함된다.The details of each work unit (WBS) included in the design specifications include the quantity and unit price information of 7 levels consisting of facility name, work type name, facility name, direction space name, expansion space name, work management name, and detailed work management name. included

(e) 이후 조달기관의 공사원가통합관리시스템 서버로부터 낙찰자를 통보받은 수요기관의 건설사업관리시스템 서버가 낙찰된 시공사 단말을 통해 계약 확인 및 체결하는 단계;를 가진다.(e) Thereafter, the construction project management system server of the procuring agency, which has been notified of the successful bidder by the integrated construction cost management system server of the procurement agency, confirms and concludes the contract through the terminal of the successful bidder.

(f) 이후 시공사 단말이 건설 공사 시작 후, 별도의 분개작업 없이 수요기관의 건설사업관리시스템 서버에서 제공받은 WBS 데이터를 기반으로 현장별 WBS를 조정(구간반영)하고 도급내역 정보를 작성 후, 공사 진척도에 따라 기성에 관한 산출 내역서를 작성하여 공사비를 수요기관의 건설사업관리시스템 서버에 청구하는 단계를 가진다.(f) After that, after the construction company terminal starts the construction work, without separate journaling work, adjust the WBS for each site based on the WBS data provided from the construction project management system server of the procuring entity (reflecting the section) and write the contract details information, According to the progress of the construction, a calculation statement on completion is prepared and the construction cost is charged to the construction project management system server of the procuring agency.

이로 인해 정부 조달에서 낙찰된 시공사는 WBS 데이터가 포함된 CBS 기반 설계내역서 데이터를 활용함으로써 종래처럼 별도의 물량 분개 재작업 없이 즉시 공종정보, 부위정보, 공간정보, 수량정보를 공정관리와 계약 및 기성관리에 활용가능하게 된다.As a result, the contractor that won the government procurement can use the CBS-based design statement data that includes the WBS data to immediately transfer work type information, part information, space information, and quantity information to process management, contract, and completion without separate volume journaling and rework as in the past. available for management.

(g) 이후 수요기관의 건설사업관리시스템 서버가 시공사 단말에서 전송된 산출내역서의 WBS 데이터를 기반으로 기성내역을 검토하여 기성 공사비를 지불하면서 공사진척관리를 진행하는 단계;를 가진다.(g) After that, the construction project management system server of the procuring entity reviews the finished details based on the WBS data of the calculation statement transmitted from the constructor's terminal and proceeds with the construction progress management while paying the finished construction cost.

(h) 이후 수요기관의 건설사업관리시스템 서버가 준공된 건물에 대한 유지관리를 WBS 데이터가 포함된 CBS 기반 데이터를 기반한 준공도서를 납품받아 시설물유지관리시스템 서버로 이관하여 유지관리하는 단계를 가진다.(h) Thereafter, the construction project management system server of the procuring entity receives the completion book based on the CBS-based data including the WBS data and transfers the maintenance management to the facility maintenance management system server for maintenance. .

상기와 같은 단계를 가짐으로써 본 발명은 조달기관의 공사원가통합관리시스템 서버(1)는 수요기관 단말에서 WBS 데이터가 포함된 CBS 기반의 설계내역 데이터를 데이터 표준화 및 디지털 표준화된 데이터 형식으로 전송받아 발주 공사 의뢰가 오면, 이를 바탕으로 공사원가를 계산하여 확정 후 공내역 BID를 생성하여 입찰공고를 하고, 입찰공고된 사항에 따라 다수의 시공사가 입찰서를 작성 후 응찰하면, 심사 후 시공사를 낙찰하게 된다.By having the above steps, in the present invention, the construction cost integrated management system server 1 of the procurement agency receives CBS-based design detail data including WBS data from the terminal of the procuring agency in a data standardized and digitally standardized data format When a contracted construction request comes in, the construction cost is calculated based on this, and after confirmation, a construction BID is generated and a bid is announced. do.

이후 낙찰된 시공사는 별도의 물량 분개(공종정보, 부위정보, 공간정보, 수량정보) 재작업 없이 입찰내역서를 구성하는 WBS 데이터가 포함된 CBS 기반 설계내역서 데이터를 바탕으로 공정관리와 계약 및 기성관리에 활용하게 된다.Afterwards, the successful contractor does not have to rework the separate quantity journal (work type information, part information, space information, quantity information), and manages process management, contracts, and completion based on CBS-based design statement data including WBS data constituting the bidding statement. will be used for

마찬가지로 수요기관도 WBS 데이터가 포함된 CBS 기반 설계내역서 데이터를 바탕으로 시공사에서 청구한 기성대가 지급에 사용하고, 준공된 건물의 생애주기 관리에 활용하게 된다.Similarly, the demand organization will also use the CBS-based design statement data, which includes WBS data, to pay for the finished price claimed by the construction company, and use it to manage the life cycle of the completed building.

본 발명은 상술한 특정의 바람직한 실시 예에 한정되지 아니하며, 청구범위에서 청구하는 본 발명의 요지를 벗어남이 없이 당해 발명이 속하는 기술분야에서 통상의 지식을 가진 자라면 누구든지 다양한 변형실시가 가능한 것은 물론이고, 그와 같은 변경은 청구범위 기재의 범위 내에 있게 된다. The present invention is not limited to the specific preferred embodiments described above, and various modifications can be made by anyone having ordinary knowledge in the art to which the present invention belongs without departing from the gist of the present invention claimed in the claims. Of course, such changes are within the scope of the claims.

(1) : 공사원가통합관리시스템 서버
(2) : 수요기관의 단말
(3) : 시공사의 단말
(4) : 설계사의 단말
(11) : 공사원가계산 모듈
(12) : 공사코드운영모듈
(13) : C3R호환검증 모듈
(14) : 내역입찰심사모듈
(15) : 종합심사재평가모듈
(16) : 입찰내역작성프로그램 모듈
(1): Construction cost integrated management system server
(2): Terminal of the consuming organization
(3): Construction company's terminal
(4): Designer's terminal
(11): Construction costing module
(12): Construction code operation module
(13): C3R compatible verification module
(14): Detailed bidding review module
(15): Comprehensive review and re-evaluation module
(16): Bid details writing program module

Claims (10)

정부조달 건설공사 조달방법에 있어서,
(a) 수요기관 단말에서 조달기관의 공사원가통합관리시스템 서버로 WBS 데이터가 포함된 CBS 기반 설계내역서 데이터를 전송하여 조달 의뢰하는 단계와;
(b) 조달기관의 공사원가통합관리시스템 서버는 조달 의뢰된 수요기관의 설계내역서 데이터를 검토하여 CBS 기반 공종별 산출 수량 내역과 WBS 기반 작업단위별 산출수량 내역이 결합된 공사원가로 계산하여 확정후, C3R 디지털 표준 형식의 입찰용 공내역서를 작성하여 배포하면서 수요기관의 공사발주를 입찰공고하는 단계와;
(c) 입찰공고에 따라 다수 시공사 단말이 공사원가통합관리시스템 서버에 접속하여 C3R 디지털 표준 형식 공내역서 및 입찰내역작성소프트웨어를 다운로드 후 WBS 및 CBS 기반 산출수량(QDB) 정보가 결합된 C3R 디지털 표준 형식 입찰용 설계내역서를 작성후 업로드하여 전자입찰에 응찰하는 단계와;
(d) 조달기관의 공사원가통합관리시스템 서버는 업로드된 다수 시공사의 입찰 내역서를 심사후 낙찰자를 선정하는 단계를 거쳐 수요기관에 C3R 디지털 표준 형식으로 작성된 계약내역서(BID)와 WBS 및 CBS 기반 산출수량(QDB)을 포함하는 입찰용 설계내역서를 전송하는 단계와;
(e) 조달기관의 공사원가통합관리시스템 서버로부터 낙찰자를 통보받은 수요기관의 건설사업관리시스템 서버가 낙찰된 시공사 단말을 통해 계약 확인 및 체결하는 단계;를 포함하되,
상기 (a) 단계는, (a') 수요기관의 건설사업관리시스템 서버에 접속한 설계사 단말을 통해 설계사가 작성한 설계도면 데이터와; 설계사 단말이 조달기관의 공사원가통합관리시스템 서버에 접속해 표준공사코드를 관리하는 공사코드운영모듈에서 내려받은 조달기관의 표준공사코드로 기재된 CBS 기반 공종별 산출 수량과 원가 내역과 WBS 기반 작업단위별 산출수량과 원가 내역이 결합된 설계내역서 데이터;가 포함된 설계도서 파일을 납품받는 단계를 포함하고,
상기 (b) 단계에서 조달기관의 공사원가통합관리시스템 서버는 자재단가 원가계산시 수요기관에서 전송된 WBS 데이터가 포함된 CBS 기반 설계내역서의 원가정보를 해당 데이터에 포함된 표준공사코드를 기반으로 검토 대상 자재명, 규격, 단위를 직전 3개월 검토자료 데이터와, 정기가격조사 자료 데이터를 가지고 유사도 알고리즘을 적용하여 비교 검토한 단가데이터와, 물가협회 디지털 자재단가 단가 데이터를 비교하여 원가계산하는 단계를 수행하되, 상기 유사도 알고리즘은 편집거리개념, 같은 낱말이 문자열 내 특정한 거리내에 있을 때 높은 관련도 점수를 할당하는 Jaro-Winkier Distance를 사용하여 수행하는 것을 특징으로 하는 WBS 데이터가 포함된 CBS 기반의 설계 내역 데이터를 이용하여 원가계산 및 입찰이 처리되는 시설공사 조달 관리 방법.
In the government procurement construction procurement method,
(a) requesting procurement by transmitting CBS-based design specification data including WBS data from a terminal of a demand institution to a server of an integrated construction cost management system of a procurement institution;
(b) The server of the integrated construction cost management system of the procurement agency reviews the data of the design statement of the requesting organization requested for procurement, calculates and confirms the construction cost as a combination of the CBS-based output quantity details by work type and the WBS-based output quantity details by work unit , preparing and distributing a public statement for bidding in the C3R digital standard format, and announcing the bid for the construction order of the procuring entity;
(c) According to the bidding announcement, multiple construction company terminals access the construction cost integrated management system server, download the C3R digital standard format construction statement and bidding details creation software, and then combine the WBS and CBS-based output quantity (QDB) information into the C3R digital standard. preparing and uploading design specifications for formal bidding and submitting bids to electronic bidding;
(d) The procurement agency's integrated construction cost management system server reviews the uploaded bid statements of multiple contractors and selects a successful bidder, and calculates the contract details (BID) written in the C3R digital standard format and WBS and CBS-based calculations to the consuming agency Transmitting a design statement for bidding including a quantity (QDB);
(e) the construction project management system server of the procuring agency, which has been notified of the successful bidder by the integrated construction cost management system server of the procurement agency, confirms and concludes the contract through the terminal of the successful bidder, including,
The step (a) includes: (a') design drawing data prepared by the designer through the designer terminal connected to the construction project management system server of the procuring agency; The designer’s terminal connects to the procurement agency’s integrated construction cost management system server and manages the standard construction code. The standard construction code of the procurement agency downloaded from the construction code operation module calculates quantity and cost details for each CBS-based work type and WBS-based work unit. Including the step of receiving a design document file containing;
In the step (b) above, the integrated construction cost management system server of the procurement agency converts the cost information of the CBS-based design statement including the WBS data transmitted from the consuming agency to the standard construction code included in the data The step of calculating the cost by comparing the unit price data that was compared and reviewed by applying the similarity algorithm with the review data of the previous three months for the material name, specification, and unit to be reviewed, and the data of the regular price survey data, and the unit price data of the Digital Materials Foundation of the Korea Price Association. However, the similarity algorithm is performed using the Jaro-Winkier Distance, which assigns a high relevance score when the same word is within a specific distance in the text string, CBS-based design including WBS data. A facility construction procurement management method in which cost calculation and bidding are processed using detailed data.
청구항 1에 있어서,
상기 시설공사 조달 관리 방법은,
(f) 시공사 단말이 건설 공사 시작 후, 별도의 분개작업 없이 수요기관의 건설사업관리시스템 서버에서 제공받은 WBS 데이터를 기반으로 현장별 WBS를 조정(구간반영)하고 도급내역 정보를 작성 후, 공사 진척도에 따라 기성에 관한 산출 내역서를 작성하여 공사비를 수요기관의 건설사업관리시스템 서버에 청구하는 단계와;
(g) 수요기관의 건설사업관리시스템 서버가 시공사 단말에서 전송된 산출내역서의 WBS 데이터를 기반으로 기성내역을 검토하여 기성 공사비를 지불하면서 공사진척관리를 진행하는 단계;를 더 포함하는 것을 특징으로 하는 WBS 데이터가 포함된 CBS 기반의 설계 내역 데이터를 이용하여 원가계산 및 입찰이 처리되는 시설공사 조달 관리 방법.
The method of claim 1,
The facility construction procurement management method,
(f) After the construction company terminal starts the construction work, without separate journaling, adjust the WBS for each site based on the WBS data provided from the construction project management system server of the procuring entity (reflecting the section), write the contract details information, and preparing a calculation statement for completion according to the progress and claiming the construction cost to the construction project management system server of the procuring agency;
(g) a step in which the construction project management system server of the requesting organization reviews the finished details based on the WBS data of the calculation statement transmitted from the constructor terminal and proceeds with the construction progress management while paying the ready-made construction cost; A facility construction procurement management method in which cost calculation and bidding are processed using CBS-based design details data including WBS data for
청구항 1에 있어서,
상기 시설공사 조달 관리 방법은,
(h) 수요기관의 건설사업관리시스템 서버가 준공된 건물에 대한 유지관리를 WBS 데이터가 포함된 CBS 기반 데이터를 기반한 준공도서를 납품받아 시설물유지관리시스템 서버로 이관하여 유지관리하는 단계;를 더 포함하는 것을 특징으로 하는 WBS 데이터가 포함된 CBS 기반의 설계 내역 데이터를 이용하여 원가계산 및 입찰이 처리되는 시설공사 조달 관리 방법.
The method of claim 1,
The facility construction procurement management method,
(h) the step of transferring the maintenance of the completed building to the facility maintenance management system server by receiving the completed building based on the CBS-based data including the WBS data; A facility construction procurement management method in which cost calculation and bidding are processed using CBS-based design detail data containing WBS data, characterized in that it comprises.
삭제delete 청구항 1에 있어서,
상기 표준공사코드는 설계사 단말이 조달기관의 공사원가통합관리시스템 서버에 접속해 내려받는 코드로, 공정분류에 따라 품명과 규격 단위, 규격화 여부로 분류된 세부공종코드로 이루어진 공종별코드와; 물품분류에 따라 품명, 규격, 단위, 인도조건, 지수구분, 물품설명으로 분류된 순수자원코드로 이루어진 물품별 코드;인 것을 특징으로 하는 WBS 데이터가 포함된 CBS 기반의 설계 내역 데이터를 이용하여 원가계산 및 입찰이 처리되는 시설공사 조달 관리 방법.
The method of claim 1,
The standard construction code is a code downloaded by the design company terminal by accessing the construction cost integrated management system server of the procurement agency, and a work type code composed of detailed work type codes classified according to product name, standard unit, and standardization according to process classification; Cost by using CBS-based design details data including WBS data, characterized in that; A facility construction procurement management method in which calculations and tenders are processed.
청구항 1에 있어서,
상기 (b) 단계와 (C)단계의 C3R 디지털 표준 형식의 입찰용 공내역서 또는 (C)단계와 (d)단계의 C3R 디지털 표준 형식 입찰 내역서는 조달기관에서 규정한 입찰정보, 단위공사, 단위공사내역서, 원가계산서, 하도급 조사금액, 하도급 공사비산출서, 하도급 내역서, 작업분류 수량, 작업분류 정보, 하도급가능 심사업종 정보 구조로 작성된 XML 형식 파일인 것을 특징으로 하는 WBS 데이터가 포함된 CBS 기반의 설계 내역 데이터를 이용하여 원가계산 및 입찰이 처리되는 시설공사 조달 관리 방법.
The method of claim 1,
Public statements for bidding in C3R digital standard format in steps (b) and (C) above or bidding statements in C3R digital standard format in steps (C) and (d) are bidding information, unit construction, and unit specified by the procurement agency. Construction statement, cost invoice, subcontract investigation amount, subcontract construction cost calculation statement, subcontract statement, work classification quantity, work classification information, CBS-based CBS-based file containing WBS data, characterized in that it is an XML format file created in the information structure of the subcontractable audit category. A facility construction procurement management method in which cost calculation and bidding are processed using design details data.
삭제delete 청구항 1에 있어서,
상기 설계내역서는 조달기관(조달청)의 C3R 기반 설계내역서 디지털 표준을 만족하고, 입찰내역서는 조달기관(조달청)의 입찰내역서(BID) 디지털 표준을 만족하는 파일이고,
상기 설계내역서 중 CBS는 조달기관(조달청)의 CBS 데이터 표준을 만족하고, 상기 WBS는 국토교통부 및 수요기관의 데이터 표준을 만족하는 파일로 구성된 것을 특징으로 하는 WBS 데이터가 포함된 CBS 기반의 설계 내역 데이터를 이용하여 원가계산 및 입찰이 처리되는 시설공사 조달 관리 방법.
The method of claim 1,
The design details are files that satisfy the C3R-based design specifications digital standard of the procurement agency (Public Procurement Service), and the bidding details are files that satisfy the digital standards of the bidding details (BID) of the procurement agency (Public Procurement Service),
Among the design details, the CBS satisfies the CBS data standards of the procurement agency (Public Procurement Service), and the WBS is composed of files that satisfy the data standards of the Ministry of Land, Infrastructure and Transport and the demand agency CBS-based design details containing WBS data, characterized in that A facility construction procurement management method in which cost calculation and bidding are processed using data.
청구항 1에 있어서,
상기 설계내역서에 포함된 작업단위별(WBS) 내역은 시설명, 공종명, 시설물명, 방향공간명, 확장공간명, 작업관리명, 세부작업관리명으로 이루어진 7단계 레벨의 수량 및 단가 정보가 포함된 것을 특징으로 하는 WBS 데이터가 포함된 CBS 기반의 설계 내역 데이터를 이용하여 원가계산 및 입찰이 처리되는 시설공사 조달 관리 방법.
The method of claim 1,
The details of each work unit (WBS) included in the design specifications include the quantity and unit price information of 7 levels consisting of facility name, work type name, facility name, direction space name, expansion space name, work management name, and detailed work management name. A facility construction procurement management method in which cost calculation and bidding are processed using CBS-based design details data including WBS data, characterized in that included.
청구항 1에 있어서,
상기 공사원가통합관리시스템 서버는,
수요기관에서 의뢰된 공사원가를 산정하는 공사원가계산 모듈; 설계사, 수요기관, 시공사에서 공통적으로 사용될 표준공사코드를 관리하는 공사코드운영모듈; 제출된 설계내역서와 입찰내역서가 공사호환규정을 준수하는 디지털파일 형식인지를 검증하는 C3R호환검증 모듈; 제출된 내역을 심사하는 내역입찰심사모듈; 제출된 내역을 심사하는 종합심사재평가모듈; 공내역서 데이터와 입찰내역작성프로그램을 관리하는 입찰내역작성프로그램 모듈;을 포함하는 것을 특징으로 하는 WBS 데이터가 포함된 CBS 기반의 설계 내역 데이터를 이용하여 원가계산 및 입찰이 처리되는 시설공사 조달 관리 방법.
The method of claim 1,
The construction cost integrated management system server,
Construction cost calculation module for calculating the construction cost commissioned by the consuming organization; A construction code operation module that manages standard construction codes commonly used by design companies, demand organizations, and construction companies; A C3R compatibility verification module that verifies whether the submitted design details and bidding statements are in digital file format that complies with construction compatibility regulations; Details tender review module for reviewing the submitted details; Comprehensive review and re-evaluation module that reviews submitted details; A facility construction procurement management method in which cost calculation and bidding are processed using CBS-based design details data containing WBS data, characterized in that it includes; .
KR1020220184535A 2022-12-26 2022-12-26 Procurement management method for facility construction where cost accounting and bidding are processed using CBS-based design details data including WBS information KR102522943B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020220184535A KR102522943B1 (en) 2022-12-26 2022-12-26 Procurement management method for facility construction where cost accounting and bidding are processed using CBS-based design details data including WBS information

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020220184535A KR102522943B1 (en) 2022-12-26 2022-12-26 Procurement management method for facility construction where cost accounting and bidding are processed using CBS-based design details data including WBS information

Publications (1)

Publication Number Publication Date
KR102522943B1 true KR102522943B1 (en) 2023-04-19

Family

ID=86142489

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020220184535A KR102522943B1 (en) 2022-12-26 2022-12-26 Procurement management method for facility construction where cost accounting and bidding are processed using CBS-based design details data including WBS information

Country Status (1)

Country Link
KR (1) KR102522943B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102626067B1 (en) * 2023-07-17 2024-01-17 (주)고려소프트웨어 Automated quantity take-off method for linking work breakdown structure and cost breakdown structure in bim(building information modeling)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100439565B1 (en) 2004-03-17 2004-07-07 대한민국 Procurement management method for integrated processing cost accounting procedure and bidding procedure through the Internet
KR100634586B1 (en) 2006-07-18 2006-10-16 대한민국 Construction procurement management method for automatically processing selection and decision of actual unit cost using breakdown of bid accumulated through the internet and the like
KR100800547B1 (en) * 2006-12-28 2008-02-04 주식회사 포스코건설 Method of construction process management connecting cost information by element
KR100886418B1 (en) 2008-11-13 2009-03-04 대한민국 Procuring management system and its managing method of cost accounting distributing board using cad system with material counting and its cost accounting
KR101019231B1 (en) 2010-10-28 2011-03-04 주식회사 아이디어정보기술 Method for cost accounting using estimate intermediate and recording medium containg thereof
KR101365481B1 (en) * 2013-04-25 2014-02-25 한양대학교 산학협력단 System for generating and managing a portal for program management
KR101760260B1 (en) * 2016-12-20 2017-07-21 조재한 BIM omitted
KR102308200B1 (en) * 2021-02-19 2021-10-05 주식회사 한울씨앤비 Method for management build construction based Building Information Modeling

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100439565B1 (en) 2004-03-17 2004-07-07 대한민국 Procurement management method for integrated processing cost accounting procedure and bidding procedure through the Internet
KR100634586B1 (en) 2006-07-18 2006-10-16 대한민국 Construction procurement management method for automatically processing selection and decision of actual unit cost using breakdown of bid accumulated through the internet and the like
KR100800547B1 (en) * 2006-12-28 2008-02-04 주식회사 포스코건설 Method of construction process management connecting cost information by element
KR100886418B1 (en) 2008-11-13 2009-03-04 대한민국 Procuring management system and its managing method of cost accounting distributing board using cad system with material counting and its cost accounting
KR101019231B1 (en) 2010-10-28 2011-03-04 주식회사 아이디어정보기술 Method for cost accounting using estimate intermediate and recording medium containg thereof
KR101365481B1 (en) * 2013-04-25 2014-02-25 한양대학교 산학협력단 System for generating and managing a portal for program management
KR101760260B1 (en) * 2016-12-20 2017-07-21 조재한 BIM omitted
KR102308200B1 (en) * 2021-02-19 2021-10-05 주식회사 한울씨앤비 Method for management build construction based Building Information Modeling

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102626067B1 (en) * 2023-07-17 2024-01-17 (주)고려소프트웨어 Automated quantity take-off method for linking work breakdown structure and cost breakdown structure in bim(building information modeling)

Similar Documents

Publication Publication Date Title
US11636413B2 (en) Autonomic discrete business activity management method
JP5172354B2 (en) Project information planning / scope change management information and business information synergy system and method
TW535088B (en) Method and system for facilitating parts procurement and production planning across an extended supply chain
US7302405B2 (en) Methods for managing and developing sourcing and procurement operations
US20080300959A1 (en) Enterprise application procurement system
US20020087440A1 (en) Method for reconstructing and validating a bill of materials and creating a comprehensive bill of materials
CN112215558B (en) Purchasing Internet of things cloud platform system
CN103765463A (en) Method and system for efficiently processing large volumes of complex small value financial transactions
CN103246950A (en) Method for promising order of semiconductor assembly and test enterprise
EP1730657A2 (en) Method of and system for consultant re-seller business informatiojn transfer
KR102522943B1 (en) Procurement management method for facility construction where cost accounting and bidding are processed using CBS-based design details data including WBS information
CN114443923A (en) Electronic archiving method and system for power grid operation and inspection project archives
US20080288364A1 (en) Construction project submittal management
CN114529197A (en) Data management method, system, terminal and storage medium for engineering cost
US20210358062A1 (en) System and method for on-demand ownership management
KR100634586B1 (en) Construction procurement management method for automatically processing selection and decision of actual unit cost using breakdown of bid accumulated through the internet and the like
US20230394426A1 (en) Supply chain management system and methods
CN113283766B (en) Contract management method, contract management device, electronic equipment and storage medium
CN114663201A (en) Electronic bidding management system and method
KR20060124926A (en) Method for mediating of export and import business using online trading server
KR20040025084A (en) System and method for administering operation cost of particulars of construction work
US20240185316A1 (en) Utilizing blockchain technology to automate service invoice processing
US20170124661A1 (en) Book exchange process
KR100872594B1 (en) Method evaluating building cost managed by writing up daily site-reports via internet
CN115204824A (en) EPC management platform based on decoration design industry

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant