KR102229586B1 KR1020180104428A KR20180104428A KR102229586B1 KR 102229586 B1 KR102229586 B1 KR 102229586B1 KR 1020180104428 A KR1020180104428 A KR 1020180104428A KR 20180104428 A KR20180104428 A KR 20180104428A KR 102229586 B1 KR102229586 B1 KR 102229586B1
Authority
KR
South Korea
Prior art keywords
wall
underground
steel
guide
index plate
Prior art date
Application number
KR1020180104428A
Other languages
Korean (ko)
Other versions
KR20200026467A (en
Inventor
유병훈
Original Assignee
유병훈
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 유병훈 filed Critical 유병훈
Priority to KR1020180104428A priority Critical patent/KR102229586B1/en
Publication of KR20200026467A publication Critical patent/KR20200026467A/en
Application granted granted Critical
Publication of KR102229586B1 publication Critical patent/KR102229586B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

트렌치 굴착후, 지중벽체용 PC벽체를 서로 연결시켜 지중벽체를 시공함에 있어 프리캐스트 방식으로 제작된 지중벽체용 PC벽체의 연결부위 방수 및 가이드 시공이 가능한 지중벽체용 PC벽체에 관한 것으로서, 방수시트에 의한 구체방수, 수팽창지수재의 팽창, 강재지수판의 재질 및 고압 분사되어 충진된 충진재를 이용하여 방수되도록 하는 강재지수판을 이용한 지중벽체용 PC벽체.It relates to a PC wall for underground walls that allows waterproofing and guide construction of the connection part of the PC wall for underground walls manufactured in a precast method in constructing the underground walls by connecting the PC walls for underground walls after trench excavation. PC wall for underground walls using a steel index plate to make waterproofing by using concrete waterproofing, expansion of the water expansion index, the material of the steel index plate, and the filler filled by high pressure spraying.

Description

강재지수판을 이용한 지중벽체용 PC벽체{PRECAST CONCRETE WALL STRUCTURE FOR UNDERGROUND USING STEEL WATER-STOP}PC wall for underground wall using steel index plate{PRECAST CONCRETE WALL STRUCTURE FOR UNDERGROUND USING STEEL WATER-STOP}

본 발명은 강재지수판을 이용한 지중벽체용 PC벽체에 관한 것이다. 더욱 구체적으로 트렌치 굴착후, 지중벽체용 PC벽체를 서로 연결시켜 지중벽체를 시공함에 있어 프리캐스트 방식으로 제작된 지중벽체용 PC벽체의 연결부위 방수 및 가이드 시공이 가능한 지중벽체용 PC벽체에 관한 것이다.The present invention relates to a PC wall for an underground wall using a steel index plate. More specifically, it relates to a PC wall for underground walls capable of waterproofing and guide construction at the connection part of the PC wall for underground walls manufactured by a precast method in constructing the underground walls by connecting the PC walls for underground walls after trench excavation. .

도 1a는 종래 지하차도 등을 프리캐스트 벽체를 이용하여 시공하는 종래 SLIT 공법(슬릿공법)의 시공도를 도시한 것이다.1A is a diagram showing a construction diagram of a conventional SLIT method (slit method) in which a conventional underground roadway is constructed using a precast wall.

이러한 슬릿공법은 프리캐스트 부재인 측벽 부재(40)를 이용하여 시공하고, 프리캐스트 상판구조물(50)을 설치하여 개착식 지하 구조물 시공과 대비하여 복공판을 설치하지 않고 지상부를 조기에 완성하고 내부를 굴착 및 구축하는 개착 지하 구조물 구축 방법이라 할 수 있다.This slit construction method is constructed using the side wall member 40, which is a precast member, and a precast top plate structure 50 is installed to complete the above-ground part early without installing a reinforcement plate in preparation for the construction of an open-ended underground structure. It can be said to be a method of constructing an excavated underground structure through excavation and construction.

이러한 슬릿공법에 사용되는 측벽 부재(40)는 프리캐스트 부재(41)의 바닥 면에 시공 시의 지지 말뚝 및 측방 토압에 저항하는 H빔(42)이 하방 돌출되도록 한 것을 지중에 서로 연결하여 지하 구조물의 양 측벽을 시공하게 되는데, 이는 지하 구조물 양 측벽 전부를 프리캐스트 부재로 시공하는 경우와 비교하여 운반과 시공이 상대적으로 용이하고 이로서 비용 절감이 가능하다는 장점이 있게 된다.The side wall member 40 used in this slit method is formed by connecting the supporting piles during construction and the H beam 42 that resists side earth pressure to the bottom surface of the precast member 41 to protrude downward to the ground. Both sidewalls of the structure are constructed, which has the advantage of being relatively easy to transport and constructing compared to the case of constructing both sidewalls of an underground structure with a precast member, thereby reducing cost.

도 1b는 종래 주열식벽체의 시공도이다.Figure 1b is a construction diagram of a conventional main heating wall.

즉, 지반을 트렌치 굴착하여 형성된 굴착공간에 프리캐스트 벽체파일을 지중구조물 저판 이하의 심도(D)를 가지도록 삽입 시공하되 종방향으로 연속하여 연결 시공하고 횡방향으로 서로 이격되도록 시공하여 지중구조물의 벽체부로서 주열식벽체를 시공하고 있음을 알 수 있다.In other words, the precast wall pile is inserted into the excavation space formed by trench excavation of the ground so as to have a depth (D) less than the bottom plate of the underground structure. It can be seen that the main heat type wall is being constructed as the wall part.

이때 상기 트렌치 굴착을 구체적으로 살펴보면At this time, looking at the trench excavation in detail

트렌치 형태로 굴착된 굴착공간(S1)의 공벽을 유지하고, 프리캐스트 벽체파일을 인양하여 굴착공간(S1)에 하강 삽입시켜 시공하게 되고, The hollow wall of the excavation space (S1) excavated in the form of a trench is maintained, and the precast wall pile is lifted and lowered into the excavation space (S1) to be constructed.

상기 프리캐스트 벽체파일(11)은 H형 단면으로 형성되어 굴착공간(S1)의 종방향으로 양 플랜지가 측방으로 서로 가이드부재(17,18)를 이용하여 접하면서 플랜지에 의하여 연결공간(S2)이 확보되고,The precast wall pile 11 is formed in an H-shaped cross section so that both flanges are in contact with each other in the longitudinal direction of the excavation space S1 laterally using the guide members 17 and 18, and the connection space S2 by the flange Is secured,

상기 연결공간(S2)에 연결보강재(14)를 삽입한 후 충전콘크리트(C)를 타설하여 프리캐스트 벽체파일(11)을 서로 일체화 되면서 주열식벽체(10)가 형성되도록 하고 있음을 알 수 있다.It can be seen that the precast wall pile 11 is integrated with each other by inserting the connection stiffener 14 into the connection space S2 and then pouring the filled concrete C to form the main heat-type wall 10. .

이로서 종래 H형 단면의 프리캐스트 벽체파일(11)을 이용하는 방법은 미리 지중에 트렌치 굴착에 의한 굴착공간을 확보하고 이러한 굴착공간에 H빔(42)이 하부에 형성된 측벽 부재(40), H형 단면의 프리캐스트 벽체파일(11)을 삽입하는 방식을 따르고 있음을 알 수 있다.As a result, the conventional method of using the precast wall pile 11 of the H-shaped cross section secures an excavation space by trench excavation in the ground in advance, and the side wall member 40, H-beam 42 formed at the lower part of the excavation space. It can be seen that the method of inserting the precast wall pile 11 of the cross section is followed.

또한 도 1a와 같이 종래 SLIT 공법(슬릿공법)의 시공에 있어서도, 트렌치 굴착에 의한 굴착공간을 확보하고 H빔(42)이 하부에 일체로 형성되는 측벽 부재(40)를 삽입하는 방식을 역시 따르고 있음을 알 수 있다.In addition, in the construction of the conventional SLIT method (slit method) as shown in FIG. 1A, the method of securing the excavation space by trench excavation and inserting the side wall member 40 in which the H beam 42 is integrally formed at the lower part is also followed. You can see that there is.

도 1c는 종래 트렌치 굴착기의 시공도이다. 1C is a construction view of a conventional trench excavator.

즉, 상기 트렌치 굴착에 의한 굴착공간을 확보하기 위해 도 1c와 같은 트렌치 굴착기를 사용하고 있다.That is, in order to secure an excavation space by the trench excavation, a trench excavator as shown in FIG. 1C is used.

상기 트렌치 굴착기는 도 1c와 같이 체인(9)에 비트(1)를 장착하고, 체인(9)을 상,하로 회전시키켜서 체인에 장착된 비트가 지반을 굴착하여 굴착공간(S1)이 형성되도록 한 것으로서, 굴착된 토사는 배토시키거나 벤토나이트 충전액과 일부 교반되어 굴착된 트렌치의 공벽을 유지하도록 하게 된다.The trench excavator mounts the bit 1 on the chain 9 as shown in FIG. 1C and rotates the chain 9 up and down so that the bit mounted on the chain excavates the ground to form an excavation space S1. For one thing, the excavated soil is embrittled or partially agitated with a bentonite filling solution to maintain the hollow wall of the excavated trench.

즉, 공벽 유지된 굴착공간(S1)에 도 1a 및 도 1b에서 살펴본 H빔(42)이 하부에 형성된 측벽 부재(40), H형 단면의 프리캐스트 벽체파일(11)을 하강 삽입하는 방식으로 시공하게 된다.That is, in the way of descending and inserting the side wall member 40 and the precast wall pile 11 of the H-shaped cross section formed under the H-beam 42 as seen in FIGS. 1A and 1B into the excavation space S1 maintained by the empty wall. It will be constructed.

도 1d는 종래 콘크리트 부재의 시공이음 부위에 설치되는 지수판의 시공도를 도시한 것이다. 1D is a diagram showing a construction diagram of a water stop plate installed at a construction joint of a conventional concrete member.

이러한 지수판은 강재 또는 폴리염화비닐과 같은 플라스틱재질로 제작된 것을 이용하되, 이미 타설되어 양생된 일측 콘크리트 부재에 지수판 일측이 매립되고 콘크리트 타설될 거푸집 내부로 타측이 연장되어 있음을 알 수 있어, 결국 지수판은 콘크리트 내부에 매립 설치되도록 하게 된다.Such a waterstop plate is made of a plastic material such as steel or polyvinyl chloride, but it can be seen that one side of the waterstop plate is buried in one concrete member on one side that has already been poured and cured, and the other side extends into the formwork to be poured concrete. The waterstop plate is to be installed embedded in the concrete.

이때 상기 지수판에는 수팽창지수재가 부착되어 있어 수팽창지수재의 수팽창에 의한 차수효과를 가질 수 있도록 하고 있음을 알 수 있다.At this time, it can be seen that the water-expansion index material is attached to the water-stop plate so that the water-expansion index material can have a water-order effect by the water expansion.

하지만 이러한 지수판 설치는 현장타설콘크리트 방식으로 콘크리트 부재를 시공함에 있어서 이용할 수 있는 것이고,However, installation of such a waterstop plate can be used in constructing concrete members using the cast-in-place concrete method,

앞서 살펴본 H빔(42)이 하부에 형성된 측벽 부재(40), H형 단면의 프리캐스트 벽체파일(11)과 같이 프리캐스트 부재에 적용하기 위해서는 별도의 설치장치 또는 고정 장치가 필요하게 된다.In order to be applied to a precast member, such as the side wall member 40 in which the H beam 42 is formed below and the precast wall pile 11 having an H-shaped cross section, a separate installation device or a fixing device is required.

이에 종래 지중에 프리캐스트 부재를 연속하여 시공함에 있어 연결부위의 지수를 위하여 도 1d와 같이 현장타설 콘크리트(C)와 거푸집(23)을 이용하여 설치되는 지수판(21), 수팽창지수재(22)를 도시하고 있다. 하지만 이러한 콘크리트(C)와 거푸집(23)을 이용하여 설치되는 지수판(21), 수팽창지수재(22)는 H빔(42)이 하부에 형성된 측벽 부재(40), H형 단면의 프리캐스트 벽체파일(11)과 같이 프리캐스트 부재에 그대로 이용하는 것은 거의 불가능하고, 설사 이용한다 할지라도 시공성이 떨어져 품질관리도 어려워 사실상 지수에 한계가 있게 된다.Therefore, in the conventional underground precast member construction, the water-stop plate 21 and the water-expansion index 22 are installed using the cast-in-place concrete (C) and the formwork (23) as shown in Fig. 1d for the index of the connection part. ). However, the water-stop plate 21 and the water-expansion index material 22 installed using the concrete (C) and the formwork (23) are the side wall members (40) in which the H-beam (42) is formed under the precast H-shaped section. It is almost impossible to use it as it is for a precast member like the wall pile 11, and even if it is used, it is difficult to manage quality due to poor workability, and thus, there is a limit to the index.

또한, 도 1b에서와 같이, H형 단면의 프리캐스트 벽체파일(11)을 서로 연결하는 방식을 살펴보면, 양 플랜지가 측방으로 서로 가이드부재(17,18)를 이용하여 접하면서 연속으로 시공되도록 하고 있음을 알 수 있으며, 이러한 가이드부재를 수용하기 위한 연결홈들은 최종 충진재로 마감되도록 하여 차수 가능하도록 하고 있다.In addition, as shown in FIG. 1B, looking at the method of connecting the precast wall piles 11 of the H-shaped cross section to each other, both flanges are in contact with each other in the lateral direction using the guide members 17 and 18 to be continuously constructed. It can be seen that, and the connecting grooves for accommodating the guide member are finished with a final filler to enable ordering.

결국, 종래 H빔(42)이 하부에 형성된 측벽 부재(40), H형 단면의 프리캐스트 벽체파일(11)과 같이 프리캐스트 부재의 시공에 있어 연결부위의 방수문제 및 연결수단은 다수 소개되어 있지만 실제 방수문제를 근본적으로 해결할 수 있을 정도는 아님을 알 수 있다.As a result, in the construction of the precast member, such as the side wall member 40 in which the H-beam 42 is formed under the conventional H-beam 42, and the precast wall pile 11 of the H-shaped cross section, a number of waterproofing problems and connecting means at the connection portion are introduced However, it can be seen that it is not enough to fundamentally solve the real waterproof problem.

대한민국 공개특허 제 10-2018-0014793호(발명의 명칭: 연결형강을 이용한 이중벽체 구조물 제작방법 및 그 시공방법, 공개일자: 2018년02월09일)Republic of Korea Patent Publication No. 10-2018-0014793 (Name of the invention: method of manufacturing a double-walled structure using connected steel and its construction method, publication date: February 9, 2018) 대한민국 등록실용신안 제 20-0402361호(발명의 명칭: 콘크리트 신축 이음용 복합지수판, 공개일자: 2005년11월29일)Republic of Korea Utility Model No. 20-0402361 (Name of invention: composite index plate for new concrete joints, publication date: November 29, 2005) 대한민국 특허 제 10-0463006호(발명의 명칭: 콘크리트 친화형 점착성 미가황고무 지수재의 제조 방법과이를 이용한 시공방법, 공개일자: 2004년12월23일)Republic of Korea Patent No. 10-0463006 (Name of invention: manufacturing method of concrete-friendly adhesive unvulcanized rubber index material and construction method using it, publication date: December 23, 2004)

이에 본 발명은 종래 프리캐스트 방식의 지중벽체용 PC벽체를 연결 시공함에 있어 연결부위 방수에 종래 지수판을 설치하는 것과 대비하여 완벽한 방수가 가능하도록 하되, 프리캐스트 지중벽체용 PC벽체를 연속하여 연결하면서 시공할 수 있도록 함으로서 지중벽체용 PC벽체의 효율적인 시공이 가능한 강재지수판을 이용한 지중벽체용 PC벽체 제공을 해결하고자 하는 기술적 과제로 한다.Accordingly, the present invention enables complete waterproofing compared to the conventional waterstop plate for waterproofing of the connection part in the connection construction of the PC wall for the underground wall of the conventional precast method, but while continuously connecting the PC wall for the precast underground wall. This is a technical task to solve the provision of PC walls for underground walls using steel index plates that enable efficient construction of PC walls for underground walls.

상기 과제를 달성하기 위한 본 발명의 본 발명의 강재지수판을 이용한 지중벽체용 PC벽체는 PC wall for an underground wall using the steel index plate of the present invention of the present invention to achieve the above object

트렌치 굴착기에 의하여 형성된 굴착공간(S1)에 먼저 설치된 일측 지중벽체용 PC벽체에 가이드되어 설치되는 타측 지중벽체용 PC벽체의 연결부위에 방수가이드장치가 설치되도록 하되, 상기 방수가이드장치로서,A waterproof guide device is installed at the connection part of the PC wall for an underground wall on the other side, which is guided to the PC wall for an underground wall installed first in the excavation space (S1) formed by the trench excavator, as the waterproof guide device,

원통형가이드부와 양 수평가이드부가 일측 지중벽체용 PC벽체의 플랜지부의 내부로 일체로 매입 설치되도록 하여, 플랜지부의 연결단부면(A)으로 양 수평가이드부에 의한 개구부(S2)가 형성되도록 하고 개구부(S2) 반대쪽으로 개구부와 연통되는 원통형가이드부에 의한 수직홀(S3)이 형성되도록 하는 가이드관; 및 타측 지중벽체용 PC벽체의 플랜지부의 연결단부면에 수직판삽입부의 일측이 매립 설치되도록 하고, 타측은 연결단부면으로부터 돌출되어 단부에 충진홀이 형성된 수직원통삽입관이 일체로 형성되도록 하여, 충진홀이 형성된 수직원통삽입관이 가이드관의 수직홀(S3)에 가이드되어 삽입되도록 하고, 노출된 수직판삽입부는 개구부(S2)에 가이드되어 삽입되도록 하는 강재지수판;를 포함하되, 수직원통삽입관 내부로 고압으로 충진시켜 충진재는 수직원통삽입관 내부를 채우면서 충진홀을 통해 가이드관과 수직원통삽입관 사이공간(S4)까지 충진되도록 하며, 상기 강재지수판의 수직원통삽입관 전체와 노출되는 수직판삽입부를 감싸도록 부착됨과 더불어 매립된 수직판삽입부의 단부에 형성된 수팽창지수재를 포함하며, 상기 일측 및 타측 지중벽체용 PC벽체의 표면에는 방수시트가 부착되도록 하여 구체방수가 가능하도록 하여, 수팽창지수재의 팽창, 강재지수판의 재질 및 고압 분사되어 충진된 충진재를 이용하여 방수되도록 하게 된다.The cylindrical guide part and both horizontal guide parts are integrally embedded and installed into the flange part of the PC wall for an underground wall, so that an opening (S2) by both horizontal guide parts is formed as the connecting end surface (A) of the flange part. And a guide tube to form a vertical hole (S3) by a cylindrical guide portion in communication with the opening opposite to the opening (S2); And one side of the vertical plate insertion part is buried in the connection end surface of the flange part of the other side of the PC wall for the underground wall, and the other side protrudes from the connection end surface so that a male tube insertion pipe with a filling hole formed at the end is integrally formed. , Including, a male staff barrel insertion pipe having a filling hole formed therein to be guided and inserted into the vertical hole (S3) of the guide pipe, and the exposed vertical plate insertion portion guided and inserted into the opening (S2); Filling the inside of the insertion tube at high pressure so that the filler fills the inside of the male staff tube insertion tube and fills up to the space (S4) between the guide tube and the male staff tube insertion tube through the filling hole, and exposes the entire male staff tube insertion tube of the steel material index plate. Includes a water expansion index material formed at the end of the embedded vertical plate insertion part while being attached to surround the vertical plate insertion part, and a waterproof sheet is attached to the surface of the PC wall for one side and the other side of the underground wall so that concrete waterproofing is possible. Thus, it is made to be waterproof using the expansion of the water expansion index material, the material of the steel material index plate, and the filler filled by high-pressure spraying.

본 발명의 강재지수판을 이용한 지중벽체용 PC벽체는 강재지수판과 수팽창지수재를 이용하고, 이때 강재지수판은 지중벽체용 PC벽체의 가이드수단으로도 기능할 수 있는 강성을 확보할 수 있도록 하되, 수팽창지수재를 부착시킨 것을 이용하여 팽창에 의한 방수효과도 가지도록 하게 된다.The PC wall for an underground wall using a steel index plate of the present invention uses a steel index plate and a water expansion index material, and at this time, the steel index plate can secure rigidity that can function as a guide means for the PC wall for underground walls, Water-expansion index material is attached so that it has a waterproof effect by expansion.

또한 강재지수판은 강재로 제작된 것이기 때문에 지하수등(W)이 통과하지 못하는 재질로서 가장 방수효과가 크다는 장점이 있고, 종래 플라스틱계열의 지수판을 이용함에 따른 시공과정에서의 파손문제, 휘어짐 문제 등을 극복할 수 있게 된다.In addition, since the steel index plate is made of steel, it has the advantage of having the greatest waterproof effect as a material that does not allow the groundwater lamp (W) to pass. You will be able to overcome it.

또한 강재지수판은 수직원통삽입관을 이용하되 수직원통삽입관은 충전홀이 형성되어 있어 수직원통삽입관의 상부에서 고압으로 충진재를 압입 충전시키고, 압입 충전된 충진재가 충전홀을 통해 가이드관을 함께 채워줌에 따라 수팽창지수재의 수팽창 및 충진재 마감에 의한 방수효과를 극대화시켜 보다 효율적인 방수효과를 가질 수 있게 된다.In addition, the steel index plate uses the male staff tube insertion pipe, but the male staff tube insertion pipe has a filling hole, so the filler is press-fitted at high pressure from the top of the male staff tube insertion pipe, and the pressure-filled filler material joins the guide tube through the charging hole. As it is filled, it is possible to have a more efficient waterproof effect by maximizing the waterproof effect by the water expansion of the water expansion index material and the finishing of the filler material.

도 1a는 종래 SLIT 공법(슬릿공법)의 시공도,
도 1b는 종래 주열식벽체의 시공도,
도 1c는 종래 트렌치 굴착기의 시공도,
도 1d는 종래 콘크리트 부재의 시공이음 부위에 설치되는 지수판의 시공도,
도 2a 및 도 2b는 본 발명의 강재지수판을 이용한 지중벽체용 PC벽체의 구성도 및 확대상세도,
도 2c는 본 발명의 강재지수판을 이용한 지중벽체용 PC벽체의 방수작용도,
도 2d 및 도 2e는 본 발명의 강재지수판을 이용한 지중벽체용 PC벽체의 시공도이다.
Figure 1a is a construction diagram of a conventional SLIT method (slit method),
1B is a construction view of a conventional main heat type wall,
1C is a construction view of a conventional trench excavator,
1D is a construction diagram of a water stop plate installed at a construction joint of a conventional concrete member,
Figures 2a and 2b is a configuration and enlarged detail view of a PC wall for an underground wall using the steel index plate of the present invention,
Figure 2c is a waterproofing action diagram of the PC wall for an underground wall using the steel index plate of the present invention,
2D and 2E are construction views of a PC wall for an underground wall using the steel index plate of the present invention.

아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명한다. 그러나 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those of ordinary skill in the art can easily implement the present invention. However, the present invention may be implemented in various different forms and is not limited to the embodiments described herein. In the drawings, parts irrelevant to the description are omitted in order to clearly describe the present invention, and similar reference numerals are attached to similar parts throughout the specification.

명세서 전체에서, 어떤 부분이 어떤 구성요소를 "포함"한다고 할 때, 이는 특별히 반대되는 기재가 없는 한 다른 구성요소를 제외하는 것이 아니라 다른 구성요소를 더 포함할 수 있는 것을 의미한다.Throughout the specification, when a certain part "includes" a certain component, it means that other components may be further included rather than excluding other components unless specifically stated to the contrary.

[ 강재지수판(220)을 이용한 지중벽체용 PC벽체(100)][PC wall 100 for underground wall using steel index plate 220]

도 2a는 본 발명의 강재지수판(220)을 이용한 지중벽체용 PC벽체(100)의 구성도를 도시한 것이다.Figure 2a shows the configuration of the PC wall 100 for an underground wall using the steel index plate 220 of the present invention.

먼저, 지중벽체용 PC벽체(100)가 삽입될 수 있도록 일정한 폭을 가진 직육면체 형태의 굴착공간(S1)을 트렌치(Trench)라고 지칭하고, 이러한 트렌치를 지중에 형성시키기 위한 굴착을 트렌치 굴착이라고 지칭하기로 한다.First, the excavation space S1 in the form of a rectangular parallelepiped having a certain width so that the PC wall 100 for an underground wall can be inserted is referred to as a trench, and the excavation to form such a trench in the ground is referred to as trench excavation. I will do it.

이때 상기 지중벽체용 PC벽체(100)는 트렌치 굴착에 의하여 지중에 형성된 굴착공간(S1) 내부로 하강 삽입되는 프리캐스트 콘크리트 벽체이다.At this time, the PC wall 100 for the underground wall is a precast concrete wall that is lowered and inserted into the excavation space S1 formed in the underground by trench excavation.

이러한 지중벽체용 PC벽체(100)는 제작, 운반 및 시공이 가능한 범위에서 공장에서 미리 직육면체 형태로 제작된 것을 이용하게 되며 도 2a에 의하면 H형 단면의 프리캐스트 콘크리트 벽체로 형성됨을 알 수 있다.The PC wall 100 for an underground wall is made of a rectangular parallelepiped shape in advance in a factory within the range that can be manufactured, transported, and constructed, and according to FIG. 2A, it can be seen that it is formed of a precast concrete wall having an H-shaped cross section.

즉, 복부(110)와 양 플랜지부(120)로 제작되어 굴착공간(S1)에 한개 씩 인양되어 하강 삽입되도록 하되, 먼저 시공된 지중벽체용 PC벽체(100)를 기준으로 추가로 지중벽체용 PC벽체(100)가 연결 시공되도록 하게 되며, 이러한 연결 시공은 본 발명의 강재지수판(220)을 포함하는 방수가이드장치(200)를 이용하게 된다.That is, it is manufactured with the abdomen 110 and both flanges 120 so that it is lifted and inserted one by one into the excavation space (S1), but additionally for the underground wall based on the PC wall 100 for the underground wall installed first. The PC wall 100 is connected and constructed, and this connection construction uses the waterproof guide device 200 including the steel index plate 220 of the present invention.

이러한 방수가이드장치(200)는 지중벽체용 PC벽체(100)의 연결부위의 방수 및 추가 시공되는 지중벽체용 PC벽체(100)의 가이드 역할을 하게 되며, 상기 연결부위는 지중벽체용 PC벽체(100)의 플랜지 단부이다.This waterproof guide device 200 serves as a guide for waterproofing of the connection part of the PC wall 100 for an underground wall and the PC wall 100 for an underground wall to be additionally constructed, and the connection part is a PC wall for an underground wall ( 100) is the end of the flange.

이에 상기 방수가이드장치(200)를 살펴보면 도 2a, 도 2b 및 도 2c와 같이, 지중벽체용 PC벽체(100)의 플랜지 단부에 형성되는 것으로서 가이드관(210), 강재지수판(220), 수팽창지수재(230)를 포함한다.Accordingly, looking at the waterproof guide device 200, as shown in FIGS. 2A, 2B, and 2C, as formed on the flange end of the PC wall 100 for an underground wall, the guide pipe 210, the steel index plate 220, and the water expansion It includes a water-stop material 230.

먼저 상기 가이드관(210)은 도 2a, 도 2b 및 도 2c와 같이, 지중벽체용 PC벽체(100)의 플랜지부(120) 연결단부면(A)에 노출되도록 형성된 수직홀로서 강재지수판(220)이 내부에 삽입되도록 하는 가이드 역할을 하게 된다.First, the guide pipe 210 is a vertical hole formed to be exposed to the connection end surface (A) of the flange portion 120 of the PC wall 100 for an underground wall, as shown in FIGS. 2A, 2B, and 2C. ) Acts as a guide to be inserted inside.

지중벽체용 PC벽체(100)의 플랜지부(120)는 콘크리트로 형성되기 때문에 가이드관(210)은 상기 플랜지부(120)에 미리 매립되도록 하되 플랜지부(120) 연결단부면(A)으로 개구부가 형성되도록 형성시키게 된다.Since the flange portion 120 of the PC wall 100 for an underground wall is formed of concrete, the guide pipe 210 is pre-embedded in the flange portion 120, but the opening through the flange portion 120 connecting end face (A) Is formed to form.

도 2b에 의하면, 원통형가이드부(211)와 양 수평가이드부(212)가 플랜지부(120)의 내부로 일체로 매입되도록 하되 양 수평가이드부(212)에 의하여 형성되는 개구부(S2)가 플랜지부(120) 연결단부면(A) 쪽에서 노출되어 있음을 알 수 있다.According to FIG. 2B, the cylindrical guide part 211 and both horizontal guide parts 212 are integrally embedded in the flange part 120, but the opening S2 formed by both horizontal guide parts 212 is planed. It can be seen that the branch 120 is exposed from the connection end surface (A) side.

이에 플랜지부(120)의 연결단부면(A)으로 양 수평가이드부(212)에 의한 개구부(S2)가 형성되도록 하고 개구부(S2) 반대쪽으로 개구부와 연통되는 원통형가이드부(211)에 의한 수직홀(S3)이 형성되고 있음을 알 수 있다.Accordingly, an opening (S2) by both horizontal guide portions 212 is formed on the connection end surface (A) of the flange portion 120, and the vertical by the cylindrical guide portion 211 communicating with the opening opposite the opening (S2). It can be seen that the hole S3 is being formed.

이에 상기 원통형가이드부(211)에는 후술되는 강재지수판(220)의 수직원통삽입관(221)이 하방으로 가이드 되면서 삽입되고, 양 수평가이드부(212)에는 후술되는 강재지수판(220)의 수직판삽입부(222)가 가이드 되면서 삽입되도록 하게 된다.Accordingly, the cylindrical guide part 211 is inserted while the male staff tube insertion pipe 221 of the steel material index plate 220 to be described later is guided downward, and the vertical plate of the steel material index plate 220 to be described later in both horizontal guide parts 212 The insertion portion 222 is inserted while being guided.

상기 수직원통삽입관(221)과 수직판삽입부(222)는 일체화되어 있으므로 결국 가이드관(210)에 강재지수판(220)을 삽입하는 방식으로 서로 인접한 일측 및 타측 지중벽체용 PC벽체(100)의 가이드 설치가 가능하게 됨을 알 수 있으며 강재로 제작된 것을 이용하면 되고, 이러한 수직원통삽입관(221)과 수직판삽입부(222)는 플랜지부(120) 연장길이에 대응하는 연장길이를 가지도록 형성됨을 알 수 있다.Since the male staff tube insertion pipe 221 and the vertical plate insertion part 222 are integrated, in the end, one side and the other side of the underground wall PC wall 100 adjacent to each other by inserting the steel material index plate 220 into the guide tube 210 It can be seen that the guide installation is possible, and it is possible to use one made of steel, and the male staff tube insertion pipe 221 and the vertical plate insertion part 222 have an extension length corresponding to the extension length of the flange part 120. It can be seen that it is formed to be

상기 강재지수판(220)은 도 2a, 도 2b 및 도 2c와 같이, 충진홀(223)이 형성된 수직원통삽입관(221)과 수직판삽입부(222)가 일체로 형성된 것으로서 강재를 이용하여 제작한 것을 이용하며, 예컨대 추가로 시공되는 지중벽체용 PC벽체(100)의 플랜지부(120)에 일측은 매립되고 타측은 역시 플랜지부(120)의 연결단부면(A)으로부터 돌출되어 노출되도록 형성된다.The steel index plate 220 is manufactured by using a steel material as a male and female tube insertion pipe 221 having a filling hole 223 formed therein and a vertical plate insertion portion 222 as shown in FIGS. 2A, 2B, and 2C. Using one, for example, one side is buried in the flange portion 120 of the PC wall 100 for an underground wall to be additionally constructed, and the other side is also formed to protrude from the connection end surface (A) of the flange portion 120 to be exposed. do.

이때 상기 수직원통삽입관(221)는 먼저 시공된 지중벽체용 PC벽체(100)의 플랜지부(120)에 형성된 가이드관(210)에 하강 삽입되는 강재원통부를 이용하게 된다. At this time, the male staff tube insertion pipe 221 uses a steel cylindrical portion that is downwardly inserted into the guide pipe 210 formed on the flange portion 120 of the PC wall 100 for an underground wall installed first.

이로서 플랜지부(120) 연장길이에 대응하는 연장길이를 가지도록 형성시키되, 충진홀(223)이 다수 형성되어 있음을 알 수 있다.As a result, it can be seen that the flange portion 120 is formed to have an extension length corresponding to the extension length, but a plurality of filling holes 223 are formed.

이에 도 2b와 같이, 충진재(224)를 수직원통삽입관(221) 내부로 고압으로 충진시킴에 따라 충진재(224)는 수직원통삽입관(221) 내부를 채우면서 충진홀(223)을 통해 가이드관(210)과 수직원통삽입관(221) 사이공간(S4)까지 모두 충진이 가능하도록 하여 가이드관(210)과 수직원통삽입관(221) 사이 및 수직원통삽입관(221) 내부에 고압에 의하여 분사되는 충진재(224)에 의한 방수가 가능하도록 하게 됨을 알 수 있다.As shown in Figure 2b, as the filler 224 is filled into the male staff tube insertion pipe 221 at high pressure, the filler material 224 fills the inside of the male staff tube insertion tube 221 while guiding through the filling hole 223 It is possible to fill all of the spaces (S4) between the pipe 210 and the male staff tube insertion pipe 221, so that high pressure is applied between the guide pipe 210 and the male staff tube insertion pipe 221 and the inside of the male staff tube insertion pipe 221. It can be seen that waterproofing by the filler 224 sprayed by it is possible.

종래에는 단지 플랜지부의 연결단부에 형성된 수직홀에 충진재를 부어넣는 정도에 그쳤지만 본 발명은 강재로 제작된 수직원통삽입관(221)과 충진홀(223)을 통해 고압 분사에 의한 충진에 의한 변형등이 발생하지 않아 보다 밀실한 충진재 마감이 가능하도록 한것이다.Conventionally, the filling material was merely poured into the vertical hole formed at the connection end of the flange, but the present invention is made by filling by high-pressure injection through the male threaded tube insertion pipe 221 and the filling hole 223 made of steel. It is designed to allow a tighter filling material finish as no deformation occurs.

이때 상기 수직판삽입부(222)는 인접한 추가로 시공되는 지중벽체용 PC벽체(100)의 플랜지부(120)에 매입되도록 형성되어 있음을 알 수 있다. At this time, it can be seen that the vertical plate insertion portion 222 is formed to be embedded in the flange portion 120 of the PC wall 100 for an underground wall to be additionally constructed adjacent.

이에 수직판삽입부(222)을 기준으로 보면 일측(우측)은 추가로 시공되는 지중벽체용 PC벽체(100)에 매입되어 있고, 타측(좌측)은 수직원통삽입관(221)가 형성되어 있어 강재지수판(220)이 형성된 지중벽체용 PC벽체(100)를 가이드관(210)이 형성된 지중벽체용 PC벽체(100)에 연결시공 되도록 하되,Therefore, looking at the vertical plate insertion part 222 as a reference, one side (right side) is embedded in the PC wall 100 for an underground wall to be additionally constructed, and the other side (left side) has a male staff tube insertion pipe 221 formed therein. The PC wall 100 for an underground wall in which the steel index plate 220 is formed is connected to the PC wall 100 for an underground wall in which the guide pipe 210 is formed,

원통형가이드부(211)에는 수직원통삽입관(221)이 하방으로 가이드 되면서 삽입되고, 양 수평가이드부(212)에는 수직판삽입부(222)이 가이드 되면서 삽입되도록 하게 됨을 알 수 있다.It can be seen that the cylindrical guide part 211 is inserted while the male staff tube insertion pipe 221 is guided downward, and the vertical plate insertion part 222 is guided and inserted into both horizontal guide parts 212.

상기 수팽창지수재(230)는 도 2a, 도 2b 및 도 2c와 같이, 물과 접촉하면 팽창함으로서 공간을 메꾸어 주는 역할을 하는 것이다. As shown in FIGS. 2A, 2B, and 2C, the water expansion index material 230 fills a space by expanding when it comes into contact with water.

이러한 수팽창지수재(230)를 사용하게 되면 물의 접촉함에 따른 방수역할을 하는 것으로서 앞서 살펴본 강재지수판(220)을 감싸도록 설치된다.When such a water expansion index material 230 is used, it acts as a waterproof function according to the contact of water, and is installed so as to surround the steel material index plate 220 described above.

즉, 도 2a와 같이, 강재지수판(220)의 수직원통삽입관(221) 전체와 노출되는 수직판삽입부(222) 일부를 감싸도록 부착시키게 되며, 매립된 수직판삽입부(222)의 단부에도 수팽창지수재(230)를 더 형성시켜 방수성능을 확보할 수 있도록 하게 된다.That is, as shown in Fig. 2a, it is attached so as to surround the entire male staff tube insertion pipe 221 of the steel index plate 220 and a part of the vertical plate insertion portion 222 exposed, and the end of the embedded vertical plate insertion portion 222 In addition, the water expansion index material 230 is further formed to ensure waterproof performance.

이에 상기 매립된 수직판삽입부(222)의 단부에 형성되는 수팽창지수재(230)는 지중벽체용 PC벽체(100) 제작 시 미리 거푸집 내부에 배치하여 콘크리트를 타설함으로서 형성시키면 되고, 수직원통삽입관(221) 전체와 노출되는 수직판삽입부(222)을 감싸도록 형성되는 수팽창지수재(230)는 공장에서 미리 형성되도록 하되, 현장에서 필요시 형성시킬 수 있게 된다.Accordingly, the water expansion index material 230 formed at the end of the buried vertical plate insertion part 222 may be formed by placing concrete inside the formwork in advance when manufacturing the PC wall 100 for an underground wall and pouring concrete. The water expansion index material 230 formed to surround the entire insertion tube 221 and the vertical plate insertion portion 222 exposed is to be formed in advance in a factory, but can be formed if necessary in the field.

이에 수직원통삽입관(221) 전체와 노출되는 수직판삽입부(222)을 감싸도록 형성되는 수팽창지수재(230)는 강재로 제작되는 수직원통삽입관(221)과 수직판삽입부(222)이 외기에 노출되지 않도록 하는 역할도 하여 부식방지에 매우 효과적이게 된다.Accordingly, the water expansion index material 230 formed to surround the entire male staff tube insertion pipe 221 and the vertical plate insertion part 222 exposed is the male staff tube insertion pipe 221 and the vertical plate insertion part 222 made of steel. ) Is also very effective in preventing corrosion as it prevents exposure to outside air.

이에 도 2c를 참조하면 배면 토사쪽으로 지하수등(W)이 지중벽체용 PC벽체(100)의 연결부위인 플랜지부(120)의 연결부위를 통해 침투하려고 함에 있어, Accordingly, referring to FIG. 2C, in the groundwater lamp (W) toward the rear soil, in an attempt to penetrate through the connection part of the flange part 120, which is the connection part of the PC wall 100 for an underground wall,

첫째, 지중벽체용 PC벽체(100)의 표면에 부착된 방수시트(130)에 의하여 지하수등(W)에 대한 구체방수가 가능하게 되며,First, concrete waterproofing of the groundwater lamp (W) is possible by the waterproof sheet 130 attached to the surface of the PC wall 100 for underground walls,

둘째, 인접한 양 플랜지부(120) 연결부위의 틈새로 침투하는 지하수등(W)은 수팽창지수재(230)와 접촉하게 되면서 수팽창지수재(230)의 팽창에 의하여 방수되고,Second, the groundwater lamp (W) penetrating into the gap between the adjacent flange portions 120 is in contact with the water expansion index material 230 and is waterproofed by the expansion of the water expansion index member 230,

셋째, 강재지수판(220)이 양 플랜지부의 연결단부를 가로막도록 배치되어 있어 지하수등(W)은 강재지수판을 달리 침투하지 못하게 되어 방수되고,Third, since the steel material index plate 220 is arranged to block the connecting ends of both flanges, the groundwater lamp (W) cannot otherwise penetrate the steel material index plate so that it is waterproof,

넷째, 일측 지중벽체용 PC벽체(100)의 플랜지에 형성되어 있는 가이드관(210)과 강재지수판(220) 사이에 충진된 충진재(224)에 의하여 지하수등(W)은 추가적으로 방수되며, Fourth, the groundwater lamp (W) is additionally waterproofed by the filler 224 filled between the guide pipe 210 and the steel index plate 220 formed on the flange of the PC wall 100 for an underground wall,

다섯째, 타측 중벽체용 PC벽체(100)의 플랜지에 형성되어 있는 강재지수판(220)은 매립되어 있기는 하지만 역시 단부의 수팽창지수재(230)에 의하여 방수되도록 함을 알 수 있다.Fifth, it can be seen that the steel material index plate 220 formed on the flange of the other heavy wall PC wall 100 is buried, but is also waterproofed by the water expansion index material 230 at the end.

[ 본 발명의 강재지수판(220)을 이용한 지중벽체용 PC벽체(100)][PC wall 100 for an underground wall using the steel index plate 220 of the present invention]

도 2d 및 도 2e는 본 발명의 강재지수판(220)을 이용한 지중벽체용 PC벽체(100)의 시공도를 도시한 것이다.Figures 2d and 2e shows a construction diagram of a PC wall 100 for an underground wall using the steel index plate 220 of the present invention.

먼저 지중벽체용 PC벽체(100)는 직육면체 형태로 제작된 것으로서 H형 단면의 프리캐스트 콘크리트 벽체로 형성되어 복부(110)와 양 플랜지부(120)로 구성되어 있음을 알 수 있다.First, it can be seen that the PC wall 100 for an underground wall is manufactured in the form of a rectangular parallelepiped and is formed of a precast concrete wall having an H-shaped cross section and is composed of the abdomen 110 and both flanges 120.

이에 상기 양 플랜지부(120) 연결부위에는 앞서 살펴본 강재지수판(220)을 포함하는 방수가이드장치(200)가 각각 형성되어 있고, 이러한 방수가이드장치(200)를 이용하여 지중벽체용 PC벽체(100)를 연속 시공하게 된다.Accordingly, a waterproof guide device 200 including a steel index plate 220 as previously described is formed at the connection portion of the flanges 120, and the PC wall 100 for an underground wall using the waterproof guide device 200 ) Will be constructed continuously.

이에 도 2d 및 도 2e와 같이, 트렌치 굴착에 의한 굴착공간(S1)에 먼저 지중벽체용 PC벽체(100)를 삽입시공하게 되며, 경우에 따라서는 굴착공간(S1)은 공벽유지를 위한 벤토나이트등을 포함하는 공벽유지재가 충진될 수 있다.Accordingly, as shown in FIGS. 2D and 2E, the PC wall 100 for underground walls is first inserted into the excavation space S1 by trench excavation, and in some cases, the excavation space S1 is bentonite, etc. An empty wall retaining material comprising a may be filled.

이러한 지중벽체용 PC벽체(100)는 H형 단면이므로 큰 저항없이 삽입이 가능하게 된다.Since the PC wall 100 for an underground wall has an H-shaped cross section, it can be inserted without great resistance.

이에 먼저 시공된 지중벽체용 PC벽체(100)는 추가 시공되는 지중벽체용 PC벽체(100)의 가이드 역할을 하면서 연결부위의 방수처리는 방수가이드장치(200)를 이용하게 되며 이는 결국 충진재(224) 고압 충진 작업 정도로 마무리 될 수 있어 신속한 방수작업이 가능하게 된다.Accordingly, the PC wall 100 for an underground wall installed first serves as a guide for the PC wall 100 for an underground wall to be additionally constructed, and the waterproofing of the connection part uses the waterproof guide device 200, which in turn uses the filler material 224 ) As it can be finished with high pressure filling, quick waterproof work is possible.

이에 지중벽체용 PC벽체(100)는 굴착공간(S1)에 하강 삽입하여 자립되도록 먼저 설되어 있으며, 각 플랜지부(120)에 있어 일측 플랜지부(120)들에서는 방수가이드장치(200)로서 가이드관(210)이 매립 형성되어 있고, 타측 플랜지부(120)들에서는 방수가이드장치(200)로서 강재지수판(220)이 돌출되어 노출되어 있음을 알 수 있다. 또한 지중벽체용 PC벽체(100)의 표면에는 배면쪽으로 방수시트(130)를 부착시켜 놓게 된다.Accordingly, the PC wall 100 for an underground wall is first installed so as to be self-standing by descending into the excavation space (S1), and in each flange portion 120, the one side flange portion 120 is guided as a waterproof guide device 200 It can be seen that the pipe 210 is buried, and the steel index plate 220 protrudes and is exposed as the waterproof guide device 200 in the other flange portions 120. In addition, a waterproof sheet 130 is attached to the rear surface of the PC wall 100 for an underground wall.

상기 가이드관(210)에 의하여 플랜지부 연결단부면으로 노출되는 개구부(S2)와 연통되는 원통형가이드부(211)에 의한 수직홀(S3)이 형성됨을 알 수 있고,It can be seen that the vertical hole S3 is formed by the cylindrical guide part 211 in communication with the opening S2 exposed to the flange part connection end surface by the guide tube 210,

상기 강재지수판(220)은 수직원통삽입관(221) 전체와 수직원통삽입관(221)과 연결된 수직판삽입부(222) 일부가 노출되어 있고, 상기 수직원통삽입관(221)과 연결된 수직판삽입부(222) 일부는 수팽창지수재(230)가 감싸도록 하여 외기로 노출되지 않도록 하게 됨을 알 수 있다.The steel index plate 220 is a vertical plate connected to the entire male staff tube insertion pipe 221 and a part of the vertical plate insertion portion 222 connected to the male staff tube insertion pipe 221 is exposed, and the male staff tube insertion pipe 221 It can be seen that a part of the insertion part 222 is enclosed by the water expansion index material 230 so that it is not exposed to the outside air.

이에 먼저 시공된 지중벽체용 PC벽체(100)의 가이드관(210)에 강재지수판(220)이 하강 삽입되면서 가이드 되도록 하는 방식으로 추가 시공될 지중벽체용 PC벽체(100)가 설치된다.Accordingly, the PC wall 100 for an underground wall to be additionally constructed is installed in such a manner that the steel material index plate 220 is guided while being downwardly inserted into the guide pipe 210 of the PC wall 100 for an underground wall installed first.

이는 결국 가이드관(210)의 원통형가이드부(211)에 강재지수판(220)의 수직원통삽입관(221)이 하방으로 가이드 되면서 삽입되도록 하고,This in turn is inserted into the cylindrical guide portion 211 of the guide pipe 210 while the male staff tube insertion pipe 221 of the steel index plate 220 is guided downward,

가이드관(210)의 양 수평가이드부(212)에는 강재지수판(220)의 수직판삽입부(222)이 가이드 되면서 삽입되도록 하여 이루어지게 됨은 살펴본 바와 같다.As described above, the vertical plate insertion portions 222 of the steel material index plate 220 are guided and inserted into both horizontal guide portions 212 of the guide pipe 210.

이로서 먼저 시공된 지중벽체용 PC벽체(100)에 가이드 되어 추가 시공될 지중벽체용 PC벽체(100)가 설치되면 복부(110) 사이의 공간에 콘크리트(C)를 추가 타설하여 서로 연속화되도록 하고,As a result, when the PC wall 100 for an underground wall to be additionally constructed is installed by being guided to the PC wall 100 for an underground wall constructed first, concrete (C) is additionally poured into the space between the abdomen 110 so that they are continuous with each other,

추가로 강재지수판(220)의 수직원통삽입관(221) 내부로 고압에 의한 충진재(224)가 충진되도록 하여 충진재(224)는 수직원통삽입관(221) 내부를 채우면서 충진홀(223)을 통해 가이드관(210)과 수직원통삽입관(221) 사이공간(S4)까지 충진되도록 하게 되어 방수가 가능하도록 하면서 양 플랜지부의 연속화 마감이 가능하게 된다.In addition, the filling material 224 by high pressure is filled into the inside of the male staff tube insertion pipe 221 of the steel material index plate 220, so that the filler material 224 fills the inside of the male staff tube insertion tube 221 while filling the filling hole 223. Through the guide pipe 210 and the male staff tube insertion pipe 221 to be filled up to the space (S4) to enable waterproofing while the continuous finish of both flange portions is possible.

즉, 충진재(224)는 서로 인접하는 양 플랜지부 연결단부면 사이 공간도 함께 충진되도록 하고, 상기 콘크리트(C) 타설이 밀실하게 되지 않은 부위까지 충진될 수 있도록 함으로서 방수효과를 극대화시키고, 수팽창지수재(230)와 방수시트(130)에 의한 기본적인 구체방수가 가능하도록 하게 된다.That is, the filler 224 maximizes the waterproofing effect by allowing the space between the connecting end surfaces of both flanges adjacent to each other to be filled together, and to be filled to the part where the concrete (C) pouring is not closed, thereby maximizing the waterproofing effect and water expansion. Basic concrete waterproofing is possible by the water-stop material 230 and the waterproof sheet 130.

또한, 강재지수판(220)을 이용하여 연결부위 강성도 충분히 확보할 수 있게 되고 시공 시 파손되는 현상도 거의 발생하지 않게 되어 지하수등이 침투를 원천적으로 제어할 수 있게 된다.In addition, by using the steel index plate 220, it is possible to sufficiently secure the rigidity of the connection portion, and the phenomenon of damage during construction hardly occurs, so that the penetration of groundwater, etc. can be fundamentally controlled.

이러한 지중벽체용 PC벽체(100)는 도 2d 및 도 2e와 같이, 트렌치에 의한 굴착공간에 연속으로 시공되어 구조물의 지중벽체의 외측벽체로 이용되어 사이에 바닥판 등을 연결 시공하여 지중구조체를 시공하게 된다.The PC wall 100 for an underground wall is continuously constructed in the excavation space by a trench, as shown in Figs. 2d and 2e, and is used as an outer wall of the underground wall of the structure, and a floor plate is connected therebetween to construct an underground structure. It is done.

전술한 본 발명의 설명은 예시를 위한 것이며, 본 발명이 속하는 기술분야의 통상의 지식을 가진 자는 본 발명의 기술적 사상이나 필수적인 특징을 변경하지 않고서 다른 구체적인 형태로 쉽게 변형이 가능하다는 것을 이해할 수 있을 것이다. 그러므로 이상에서 기술한 실시예들은 모든 면에서 예시적인 것이며 한정적이 아닌 것으로 이해해야만 한다. 예를 들어, 단일형으로 설명되어 있는 각 구성 요소는 분산되어 실시될 수도 있으며, 마찬가지로 분산된 것으로 설명되어 있는 구성 요소들도 결합된 형태로 실시될 수 있다.The above description of the present invention is for illustrative purposes only, and those of ordinary skill in the art to which the present invention pertains will be able to understand that other specific forms can be easily modified without changing the technical spirit or essential features of the present invention. will be. Therefore, it should be understood that the embodiments described above are illustrative and non-limiting in all respects. For example, each component described as a single type may be implemented in a distributed manner, and similarly, components described as being distributed may also be implemented in a combined form.

본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present invention is indicated by the claims to be described later rather than the detailed description, and all changes or modified forms derived from the meaning and scope of the claims and their equivalent concepts should be construed as being included in the scope of the present invention. do.

100: 지중벽체용 PC벽체
110: 복부 120: 플랜지부
130: 방수시트 200: 방수가이드장치
210: 가이드관 211: 원통형가이드부
212: 수평가이드부 220: 강재지수판
221: 수직원통삽입관 222: 양 수평가이드부
223: 충진홀 224: 충진재
230: 수팽창지수재
100: PC wall for underground wall
110: abdomen 120: flange portion
130: waterproof sheet 200: waterproof guide device
210: guide tube 211: cylindrical guide portion
212: horizontal guide part 220: steel index plate
221: male staff tube insertion pipe 222: both horizontal guides
223: filling hole 224: filling material
230: water expansion index material

Claims (5)

트렌치 굴착기에 의하여 형성된 굴착공간(S1)에 먼저 설치된 일측 지중벽체용 PC벽체에 가이드되어 설치되는 타측 지중벽체용 PC벽체의 연결부위에 방수가이드장치가 설치되도록 하되, 상기 방수가이드장치(200)는,
원통형가이드부(211)와 양 수평가이드부(212)가 일측 지중벽체용 PC벽체의 플랜지부(120)의 내부로 일체로 매입 설치되도록 하여, 플랜지부(120)의 연결단부면(A)으로 양 수평가이드부(212)에 의한 개구부(S2)가 형성되도록 하고 개구부(S2) 반대쪽으로 개구부와 연통되는 원통형가이드부(211)에 의한 수직홀(S3)이 형성되도록 하는 가이드관(210); 및
타측 지중벽체용 PC벽체(100)의 플랜지부(120)의 연결단부면에 수직판삽입부(222)의 일측이 매립 설치되도록 하고, 타측은 연결단부면으로부터 돌출되어 단부에 충진홀(223)이 형성된 수직원통삽입관(221)이 일체로 형성되도록 하여, 충진홀(223)이 형성된 수직원통삽입관(221)이 가이드관(210)의 수직홀(S3)에 가이드되어 삽입되도록 하고, 노출된 수직판삽입부(222)는 개구부(S2)에 가이드되어 삽입되도록 하는 강재지수판(220);를 포함하되,
수직원통삽입관(221) 내부로 고압으로 충진시켜 충진재(224)는 수직원통삽입관(221) 내부를 채우면서 충진홀(223)을 통해 가이드관(210)과 수직원통삽입관(221) 사이공간(S4)까지 충진되도록 하며,
상기 강재지수판(220)의 수직원통삽입관(221) 전체와 노출되는 수직판삽입부(222)를 감싸도록 부착됨과 더불어 매립된 수직판삽입부(222)의 단부에 형성된 수팽창지수재(230)를 포함하며, 상기 일측 및 타측 지중벽체용 PC벽체(100)의 표면에는 방수시트(130)가 부착되도록 하여 구체방수가 가능하도록 하여, 수팽창지수재(230)의 팽창, 강재지수판(220)의 재질 및 고압 분사되어 충진된 충진재(224)를 이용하여 방수되도록 하는 강재지수판을 이용한 지중벽체용 PC벽체.
A waterproof guide device is installed at the connection part of the PC wall for an underground wall on the other side that is guided to the PC wall for an underground wall installed first in the excavation space (S1) formed by the trench excavator, the waterproof guide device 200 ,
The cylindrical guide part 211 and both horizontal guide parts 212 are integrally embedded and installed into the inside of the flange part 120 of the PC wall for an underground wall, so that the connection end surface (A) of the flange part 120 A guide pipe 210 for forming an opening S2 by both horizontal guide portions 212 and forming a vertical hole S3 by a cylindrical guide portion 211 communicating with the opening opposite to the opening S2; And
One side of the vertical plate insertion part 222 is buried in the connection end surface of the flange part 120 of the other side of the PC wall 100 for an underground wall, and the other side protrudes from the connection end surface and a filling hole 223 at the end The formed male staff tube insertion pipe 221 is integrally formed, so that the male staff tube insertion tube 221 having the filling hole 223 is guided and inserted into the vertical hole (S3) of the guide tube 210, and exposed The vertical plate insertion part 222 is a steel material index plate 220 to be guided and inserted into the opening S2; including,
By filling the inside of the male staff tube insertion pipe 221 at high pressure, the filler 224 fills the inside of the male staff tube insertion tube 221 and between the guide pipe 210 and the male staff tube insertion pipe 221 through the filling hole 223 To fill up to the space (S4),
A water expansion index material 230 formed at the end of the vertical plate insertion part 222 embedded in the steel material index plate 220 attached to surround the entire male staff tube insertion pipe 221 and the exposed vertical plate insertion part 222 ), and a waterproof sheet 130 is attached to the surface of the PC wall 100 for the one side and the other side of the underground wall to enable concrete waterproofing, so that the expansion of the water expansion index material 230, the steel material index plate 220 PC wall for an underground wall using a steel index plate to be waterproof using the material and high pressure sprayed filler (224).
삭제delete 제 1항에 있어서,
상기 일측 및 타측 지중벽체용 PC벽체(100)는 H형 단면의 프리캐스트 콘크리트 벽체로서 복부(110)와 양 플랜지부(120)로 제작되어 인접한 양 플랜지부(120)는 연결부위로서 방수가이드장치(200)의 가이드관(210)에 강재지수판(220)이 가이드되어 삽입되도록 함으로서 일측 및 타측 지중벽체용 PC벽체(100)가 서로 연결되도록 하는 강재지수판을 이용한 지중벽체용 PC벽체.
The method of claim 1,
The one side and the other side of the PC wall for the underground wall 100 is a precast concrete wall of H-shaped cross section, and is made of the abdomen 110 and both flanges 120, so that both flanges 120 adjacent to each other is a waterproof guide device as a connection part. A PC wall for an underground wall using a steel index plate so that the one side and the other side of the PC wall 100 for the underground wall 100 are connected to each other by guiding and inserting the steel index plate 220 into the guide pipe 210 of (200).
제 1항에 있어서,
일측 지중벽체용 PC벽체(100)에 가이드 되어 타측 지중벽체용 PC벽체(100)가 설치되면 복부(110) 사이의 공간에 콘크리트(C)를 추가 타설하여 서로 연속화되도록 하되, 상기 충진재(224)는 서로 인접하는 양 플랜지부 연결단부면 사이 공간도 함께 충진되도록 하고, 상기 콘크리트(C) 타설이 밀실하게 되지 않은 부위까지 충진될 수 있도록 하는 강재지수판을 이용한 지중벽체용 PC벽체.
The method of claim 1,
When the PC wall 100 for one side of the underground wall is guided and the PC wall 100 for the other side of the underground wall is installed, concrete (C) is additionally poured into the space between the abdomen 110 so that they are continuous with each other, but the filler 224 A PC wall for underground walls using a steel index plate so that the space between the connecting end surfaces of both flanges adjacent to each other is also filled, and the concrete (C) pouring can be filled to a part where the pouring is not tight.
삭제delete
KR1020180104428A 2018-09-03 2018-09-03 Precast concrete wall structure for underground using steel water-stop KR102229586B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020180104428A KR102229586B1 (en) 2018-09-03 2018-09-03 Precast concrete wall structure for underground using steel water-stop

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020180104428A KR102229586B1 (en) 2018-09-03 2018-09-03 Precast concrete wall structure for underground using steel water-stop

Publications (2)

Publication Number Publication Date
KR20200026467A KR20200026467A (en) 2020-03-11
KR102229586B1 true KR102229586B1 (en) 2021-03-18

Family

ID=69809969

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020180104428A KR102229586B1 (en) 2018-09-03 2018-09-03 Precast concrete wall structure for underground using steel water-stop

Country Status (1)

Country Link
KR (1) KR102229586B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102540345B1 (en) 2023-01-17 2023-06-08 이형훈 Stopper for precast concrete structure and connection method therewith

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115162543B (en) * 2022-07-11 2023-10-20 中冶南方城市建设工程技术有限公司 A waterproof protective cylinder of combined type for reserving hole

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101764390B1 (en) * 2016-09-13 2017-08-02 유한회사 강남이앤씨 3-Layered cutoff wall structure with pile of wall steel pipe and variabld linking body, and construction method of cutoff wall using the same
KR101863627B1 (en) * 2017-10-20 2018-06-01 (주)더케이프리캐스트 Top-down Construction method using Drainage H-type prestressed concrete wall and drainage JRS slab system

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07317095A (en) * 1994-05-26 1995-12-05 Kyowa Kaihatsu Kk Waterproofing underground structure, building method therefor, and material used therein
KR100463006B1 (en) 2001-06-05 2004-12-23 이대우 Manufacturing method of concrete affinity type adhesion unvulcanize rubber waterproof sheet and construction method for using the waterproof sheet
KR200402361Y1 (en) 2005-09-20 2005-11-29 대룡공업주식회사 Complex water protecting penel for construction of concreat
KR102171825B1 (en) 2018-01-22 2020-10-29 유병훈 Double wall structure construction method using connection steel beam and wall structure construction method therewith

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101764390B1 (en) * 2016-09-13 2017-08-02 유한회사 강남이앤씨 3-Layered cutoff wall structure with pile of wall steel pipe and variabld linking body, and construction method of cutoff wall using the same
KR101863627B1 (en) * 2017-10-20 2018-06-01 (주)더케이프리캐스트 Top-down Construction method using Drainage H-type prestressed concrete wall and drainage JRS slab system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102540345B1 (en) 2023-01-17 2023-06-08 이형훈 Stopper for precast concrete structure and connection method therewith

Also Published As

Publication number Publication date
KR20200026467A (en) 2020-03-11

Similar Documents

Publication Publication Date Title
CN106049530B (en) City integrated piping lane and construction method
KR101331261B1 (en) Underground prefabricated precast concrete rainwater recycling facility using precast concrete continuous wall in strut structure or earth anchor and construction method of the same
KR100862977B1 (en) Precast concrete file and method for constructing thereof
KR102229586B1 (en) Precast concrete wall structure for underground using steel water-stop
JP6186267B2 (en) How to build an underground tunnel
KR101524303B1 (en) The wall members and underground wall, underground wall construction method using the same
KR101021915B1 (en) A method for constructing cut-off temporary structure for sheathing work
KR101324231B1 (en) Soil cement wall structure and method for constructing thereof
KR101902786B1 (en) Under ground structure construction method using composite sheet pile and under ground structure therewith
KR102239089B1 (en) Underaround continued wall structure using casing and pile continuous connection and method therefor
JP3829319B2 (en) Construction method of underground hollow structure and its underground hollow structure
KR101267688B1 (en) The shore protection construction method using a precast finish panel
JP6584979B2 (en) Construction method of underground tank structure, underground tank structure
KR102237058B1 (en) Construction method of synthetic piles for water barriers in rock layers
KR101835828B1 (en) Complex Steel Pipe Structure for Underground Wall and the Construction Method Using the Same
JP4888293B2 (en) Earth retaining wall made of parent pile sheet pile, water stop structure of earth retaining wall made of parent pile side sheet pile, construction method of earth retaining wall made of parent pile side sheet pile, and retaining wall of earth retaining wall made of parent pile side sheet pile Water method
KR20120134677A (en) The precast concrete closed conduit that is reinforced by the shear connector and constructing method of it
KR100401330B1 (en) A method of construction for earth-protection walls of building
KR102310265B1 (en) Construction method of vertical cutoff wall foundation
KR200224760Y1 (en) Culvert assembly
KR102610909B1 (en) Method and structure of steel pipe propulsion using anchor installation inside steel pipe to prevent sinking
KR102439239B1 (en) Connecting box for underground continuous wall and construction method using them same
KR102466403B1 (en) Synthetic piles for water barriers and construction method thereof
KR20010016504A (en) Culvert assembly
KR101352429B1 (en) Water-proofing type temporary soil sheathing construction method using crrugated steel plate segments

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right