KR102226699B1 - Construction method of new steel tower using the site of existing steel tower - Google Patents

Construction method of new steel tower using the site of existing steel tower Download PDF

Info

Publication number
KR102226699B1
KR102226699B1 KR1020190126886A KR20190126886A KR102226699B1 KR 102226699 B1 KR102226699 B1 KR 102226699B1 KR 1020190126886 A KR1020190126886 A KR 1020190126886A KR 20190126886 A KR20190126886 A KR 20190126886A KR 102226699 B1 KR102226699 B1 KR 102226699B1
Authority
KR
South Korea
Prior art keywords
pylon
steel tower
new
existing
site
Prior art date
Application number
KR1020190126886A
Other languages
Korean (ko)
Inventor
전용철
정재은
진복수
Original Assignee
한국전력공사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한국전력공사 filed Critical 한국전력공사
Priority to KR1020190126886A priority Critical patent/KR102226699B1/en
Application granted granted Critical
Publication of KR102226699B1 publication Critical patent/KR102226699B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/34Arrangements for erecting or lowering towers, masts, poles, chimney stacks, or the like
    • E04H12/348Arrangements for demolition towers or the like
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals
    • E02D5/285Prefabricated piles made of steel or other metals tubular, e.g. prefabricated from sheet pile elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/02Structures made of specified materials
    • E04H12/08Structures made of specified materials of metal
    • E04H12/10Truss-like structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Materials Engineering (AREA)
  • Wood Science & Technology (AREA)
  • Chemical & Material Sciences (AREA)
  • Electric Cable Installation (AREA)

Abstract

The present invention relates to a new steel tower construction method using a site of an existing steel tower. The method includes the following steps of: locating a new steel tower in a site where an existing steel tower is constructed, and designing the new steel tower such that height center axes of the existing steel tower and the new steel tower are not overlapped with each other; installing a reinforcement material on a main leg forming the bottom of the existing steel tower adjacent to the ground, and removing a sub leg located between the ground and the reinforcement material; constructing the new steel tower such that its height center axis is not overlapped with the existing steel tower; and removing the existing steel tower, and restoring the ground. Since the new steel tower is designed to be constructed in a secured site, even when a new steel tower which is larger than the existing steel tower needs to be constructed, there is no need to secure an additional site.

Description

기설철탑의 부지를 활용한 신설철탑 건설 방법{Construction method of new steel tower using the site of existing steel tower}Construction method of new steel tower using the site of existing steel tower}

본 발명은 기설철탑의 부지를 활용한 신설철탑 건설 방법에 관한 것으로, 더욱 상세하게는, 기설철탑이 건설된 부지 외에 추가적으로 부지를 매입하지 않더라도 신설철탑을 건설할 수 있는 기설철탑의 부지를 활용한 신설철탑 건설 방법에 관한 것이다. The present invention relates to a method of constructing a new pylon using the site of an existing pylon, and more particularly, by utilizing the site of an existing pylon that can construct a new pylon even without additionally purchasing a site other than the site at which the existing pylon is constructed. It relates to a method of constructing a new pylon.

국토가 개발됨에 따라서, 철탑부지 또는 선하지 인근의 토지에 흙이 쌓이거나, 건축물이 신축될 수 있다. 흙이 쌓일 경우에는, 설계기준과 대비해서 철탑의 적정 지상고가 낮아질 수 있고, 전력선과 토지 사이의 거리가 짧아질 수 있으며. 건축물이 신축될 경우에는, 설계기준과 대비해서 전력선과 건축물과의 거리가 짧아질 수 있다. As the land is developed, soil may accumulate on the site of the steel tower or the land near the shipbuilding site, or new buildings may be built. In the case of soil accumulation, the proper ground clearance of the pylon may be lowered compared to the design standard, and the distance between the power line and the land may be shortened. When a building is newly built, the distance between the power line and the building may be shortened compared to the design standard.

그런데, 전력선과 토지 또는 전력선과 건축물 간의 거리가 설계기준과 대비해서 짧아질 경우, 접촉을 통해서 일반인 안전사고가 발생될 수 있고, 전력선에 고장이 발생될 수도 있다. 국토 개발에 따라 이러한 사고가 발생되는 것을 예방하고자 철탑의 지상고를 확대해 적정 지상고를 충족시킴으로써, 전력선과 토지 또는 전력선과 건축물 사이의 안전이격거리를 확보해야만 한다.However, if the distance between the power line and the land or between the power line and the building is shortened compared to the design standard, a general public safety accident may occur through contact, or a breakdown in the power line may occur. In order to prevent such accidents from occurring due to national land development, it is necessary to secure a safe separation distance between power lines and land or between power lines and buildings by expanding the ground clearance of the steel tower to meet the appropriate ground clearance.

안전이격거리 확보를 위해서, 종래에는 기설철탑 주변에 가철탑을 신설하고, 기설철탑을 철거한 뒤에, 기설철탑 자리에 지상고가 확대된 신설철탑을 건설하고, 가철탑을 철거하였었다. In order to secure a safe separation distance, conventionally, a temporary steel tower was built around an existing steel tower, and after the existing steel tower was demolished, a new steel tower with an enlarged ground clearance was built in the place of the existing steel tower, and the temporary steel tower was demolished.

이러한 방법은 철탑의 위치가 변동되지 않게 됨에 따라, 전력선의 길이 및 설치 위치도 변경되지 않는 장점이 있지만, 가철탑의 건설과 철거에 추가적인 비용 및 시간이 소모되므로, 공사비 및 공사기간이 크게 소모된다.This method has the advantage of not changing the length and installation location of the power line as the location of the pylon does not change, but since additional cost and time are consumed in the construction and demolition of the temporary pylon, the construction cost and construction period are greatly consumed.

이에 따라, 기설철탑 위에 기설철탑 보다 거대하게 신설철탑을 건설하는 방법이 제안되었다. 가철탑의 건설 및 철거가 필요 없도록 기설철탑을 덮도록 신설철탑이 건설되고, 전력선이 기설철탑에서 신설철탑으로 이전되는 방법이다.Accordingly, a method of constructing a new steel tower larger than the existing steel tower on the existing steel tower has been proposed. This is a method in which a new pylon is constructed to cover the existing pylon so that there is no need for the construction and demolition of a temporary pylon, and power lines are transferred from the existing pylon to the new pylon.

그러나, 신설철탑의 기저면이 기설철탑에 비해 크게 설계되므로, 도 1에 도시된 바와 같이, 확보된 부지 외에 추가적으로 인근 부지를 매입해야할 상황이 발생된다. 추가적으로 매입해야할 부지의 소유자가 부지 판매를 반대할 경우, 이러한 철탑 건설 방법은 적용될 수 없었다.However, since the base surface of the new steel tower is designed to be larger than that of the existing steel tower, as shown in FIG. 1, a situation arises in which a nearby site must be additionally purchased in addition to the secured site. If the owner of the additional site to be purchased opposes the sale of the site, this method of building a pylon could not be applied.

대한민국 공개특허공보 제10-2001-0025613호(2001.04.06.)Republic of Korea Patent Publication No. 10-2001-0025613 (2001.04.06.)

이에 상기와 같은 점을 감안해 발명된 본 발명의 목적은, 기설철탑이 건설된 부지 외에 추가적으로 부지를 매입하지 않더라도 신설철탑을 건설할 수 있는 기설철탑의 부지를 활용한 신설철탑 건설 방법을 제공하는 것이다.Accordingly, it is an object of the present invention in consideration of the above points to provide a method for constructing a new pylon using the site of an existing pylon that can construct a new pylon even without additionally purchasing a site other than the site on which the existing pylon is constructed. .

위와 같은 목적을 달성하기 위해서 본 발명의 일실시예의 기설철탑의 부지를 활용한 신설철탑 건설 방법은, 기설철탑이 건설된 부지 내에 신설철탑이 위치되고, 기설철탑과 신설철탑의 높이방향 중심축이 서로 중첩되지 않도록 신설철탑이 설계되는 단계와, 지면과 인접한 기설철탑의 하단부를 형성하는 주주재에 보강재가 설치되고, 보강재와 지면 사이에 위치하는 부주재가 철거되는 단계와, 설계된 내용에 따라, 기설철탑과 높이방향 중심축이 중첩되지 않도록 신설철탑이 건설되는 단계와, 기설철탑이 철거되고, 지면이 복구되는 단계를 포함한다.In order to achieve the above object, in the method of constructing a new pylon using the site of an existing pylon according to an embodiment of the present invention, a new pylon is located within the site where the existing pylon is constructed, and the central axis in the height direction of the existing pylon and the newly constructed pylon is The steps of designing a new pylon so that they do not overlap each other, installing a reinforcing material on the main main material forming the lower end of the existing steel tower adjacent to the ground, and removing the sub-main material located between the reinforcing material and the ground, and depending on the design contents, the existing construction It includes the steps of constructing a new pylon so that the pylon and the central axis in the height direction do not overlap, and the steps of removing the existing pylon and restoring the ground.

또한, 신설철탑이 설계되는 단계에서는, 신설철탑이 기설철탑과 간섭되지 않도록 신설철탑의 결구 형태가 결정되고, 신설철탑과 기설철탑의 이격거리에 따라 신설철탑의 기초 형태가 결정되고, 신설철탑의 결구 형태 및 기초 형태에 따라 신설철탑의 3D 설계도가 구현될 수 있다.In addition, in the design stage of the new pylon, the structure of the new pylon is determined so that the new pylon does not interfere with the existing pylon, and the basic shape of the new pylon is determined according to the separation distance between the new pylon and the existing pylon. A 3D blueprint of a new pylon may be implemented according to the structure of the structure and the form of the foundation.

또한, 지면과 인접한 기설철탑의 하단부를 형성하는 주주재에 보강재가 설치되고, 보강재와 지면 사이에 위치하는 부주재가 철거되는 단계에서는, 주주재에 홀이 가공되고, 홀을 통해 보강재가 주주재에 결합되며, 보강재는 측면에서 봤을 때, '∏'형태를 형성하도록 주주재에 설치될 수 있다.In addition, in the step in which the reinforcing material is installed in the main main material forming the lower end of the existing steel tower adjacent to the ground, and the sub-main material located between the reinforcement material and the ground is removed, a hole is processed in the main main material, and the reinforcement material is applied to the main main material through the hole. Bonded, and the reinforcement can be installed on the main body to form a'∏' shape when viewed from the side.

또한, 신설철탑이 건설되는 단계는, 신설철탑의 기초가 시공되는 단계와, 신설철탑이 조립 시공되는 단계와, 신설철탑에 전력선이 가선되는 단계를 포함하며, 신설철탑이 조립 시공되는 단계에서는, 신설철탑이 설계되는 단계에서 결정된 결구 형태에 따라 신설철탑이 조립될 수 있다.In addition, the step of constructing the new pylon includes the step of constructing the foundation of the new pylon, the step of assembling and constructing the new pylon, and the step of wiring a power line to the new pylon, and in the step of assembling and constructing the new pylon, The new steel tower may be assembled according to the shape of the structure determined at the stage in which the new steel tower is designed.

또한, 신설철탑의 기초가 시공되는 단계에서는, 강관파일공법을 통해 신설철탑의 기초가 형성될 수 있다.In addition, in the step in which the foundation of the new pylon is constructed, the foundation of the new pylon may be formed through the steel pipe pile method.

또한, 신설철탑에 전력선이 가선되는 단계에서는, 기설철탑에 연결된 1개 이상의 전력선들 중 가장 높이 위치된 전력선에서 가장 아래에 위치된 전력선 순서로 전력선들이 기설철탑에서 신설철탑으로 이동되고, 서로 대칭되도록 전방측에서 기설철탑에 도달한 전력선과 후방측에서 기설철탑에 도달한 전력선 중 어느 한 전력선이 신설철탑으로 이동된 뒤, 나머지 전력선이 신설철탑으로 이동될 수 있다.In addition, in the step of wiring the power lines to the new pylon, the power lines are moved from the existing pylon to the new pylon in the order of the lowest power line from the highest power line among the one or more power lines connected to the existing pylon, so that they are symmetrical to each other. After any one of the power lines reaching the existing pylon from the front side and the power line reaching the existing pylon from the rear side is moved to the new pylon, the remaining power lines may be moved to the new pylon.

또한, 기설철탑과 연결된 전력선은 신설철탑으로 이동되기 직전 휴전되며, 서로 대칭되도록 전방측에서 기설철탑에 도달한 전력선과 후방측에서 기설철탑에 도달한 전력선이 모두 기설철탑에서 신설철탑으로 이동된 후, 기설철탑에서 암이 제거되면, 기설철탑에서 신설철탑으로 이동된 두 전력선이 가압될 수 있다.In addition, the power line connected to the existing pylon is ceased immediately before it is moved to the new pylon, and the power line that reached the existing pylon from the front side and the power line that reached the pylon from the rear side have been moved from the existing pylon to the new pylon so that they are symmetrical to each other. , When the cancer is removed from the existing pylon, the two power lines moved from the existing pylon to the new pylon can be pressurized.

위와 같이 구성되는 본 발명의 일실시예의 기설철탑의 부지를 활용한 신설철탑 건설 방법에 따르면, 확보된 부재 내에 건설되도록 신설철탑이 설계되므로, 기설철탑 보다 큰 크기의 신설철탑을 건설하더라도 추가 적인 부지 확보가 불필요해지는 효과가 있다.According to the new pylon construction method using the site of the existing pylon according to the embodiment of the present invention configured as above, since the new pylon is designed to be built within the secured member, even if a new pylon having a size larger than that of the existing pylon is constructed, an additional site There is an effect that securing is unnecessary.

또한, 신설철탑과 기설철탑의 높이방향 중심축이 서로 중첩되지 않게 됨에 따라, 신설철탑의 암을 기설철탑의 암과 평행하게 설치할 수 있게 된다. 따라서, 전력선 이전이 한층 더 간편해 진다. In addition, as the height direction central axes of the new pylon and the existing pylon do not overlap each other, the arm of the new pylon can be installed in parallel with the arm of the existing pylon. Therefore, the power line transfer becomes even more convenient.

또한, 확보된 부지를 더 효과적으로 사용할 수 있게 된다. 기설철탑 하단부를 해체해 공사공간을 확보하므로, 공사가 편리하게 수행될 수 있고, 기간을 단축시킬 수 있게 된다. 공사기간이 단축되므로, 공사비는 절감시킬 수 있고, 건설 설비의 안정성을 쉽게 유지할 수 있다.In addition, it is possible to use the secured site more effectively. Since the construction space is secured by dismantling the lower part of the existing steel tower, the construction can be conveniently performed and the period can be shortened. Since the construction period is shortened, construction costs can be reduced, and the stability of construction equipment can be easily maintained.

도 1은 기설철탑을 덮도록 신설철탑이 건설되는 경우를 보여주는 예시도이다.
도 2는 본 발명의 일실시예의 기설철탑의 부지를 활용한 신설철탑 건설 방법의 절차도이다.
도 3은 도 2의 기설철탑의 부지를 활용한 신설철탑 건설 방법에 따라 신설철탑이 건설될 경우를 보여주는 예시도이다.
도 4 내지 도 5는 도 2의 기설철탑의 부지를 활용한 신설철탑 건설 방법에 따라 신설철탑이 설계되는 것을 보여주는 예시도이다.
도 6은 도 2의 기설철탑의 부지를 활용한 신설철탑 건설 방법에 따라 기설철탑에 보강재가 설치되고, 보강재와 지면 사이에 위치하는 부주재가 철거된 것을 보여주는 예시도이다.
도 7 내지 도 8은 도 2의 기설철탑의 부지를 활용한 신설철탑 건설 방법에 따라 신설철탑의 기초가 시공되는 것을 보여주는 예시도이다.
도 9는 도 2의 기설철탑의 부지를 활용한 신설철탑 건설 방법에 따라 신설철탑이 조립되는 것을 보여주는 예시도이다.
도 10은 도 2의 기설철탑의 부지를 활용한 신설철탑 건설 방법에 따라 전력선이 이전되는 것을 보여주는 예시도이다.
도 11은 도 2의 기설철탑의 부지를 활용한 신설철탑 건설 방법에 따라 기설철탑이 철거되는 것을 보여주는 예시도이다.
1 is an exemplary view showing a case in which a new steel tower is constructed to cover an existing steel tower.
Figure 2 is a procedure diagram of a method for constructing a new pylon using the site of an existing pylon according to an embodiment of the present invention.
3 is an exemplary view showing a case where a new pylon is constructed according to the method of constructing a new pylon using the site of the existing pylon of FIG. 2.
4 to 5 are exemplary views showing that a new steel tower is designed according to a method of constructing a new steel tower using the site of the existing steel tower of FIG. 2.
6 is an exemplary view showing that a reinforcing material is installed in an existing steel tower and a sub-main material positioned between the reinforcement material and the ground is removed according to the method of constructing a new steel tower using the site of the existing steel tower of FIG. 2.
7 to 8 are exemplary views showing that the foundation of the new pylon is constructed according to the method of constructing a new pylon using the site of the existing pylon of FIG.
9 is an exemplary view showing that a new steel tower is assembled according to a method of constructing a new steel tower using the site of the existing steel tower of FIG. 2.
FIG. 10 is an exemplary view showing that a power line is transferred according to a method of constructing a new steel tower using the site of the existing steel tower of FIG. 2.
11 is an exemplary view showing that the existing steel tower is demolished according to the method of constructing a new steel tower using the site of the existing steel tower of FIG. 2.

이하 첨부된 도면을 참조로 본 발명의 일실시예의 기설철탑(100)의 부지를 활용한 신설철탑 건설 방법을 설명한다.Hereinafter, a method of constructing a new pylon using the site of the existing pylon 100 according to an embodiment of the present invention will be described with reference to the accompanying drawings.

도 2에 도시된 바와 같이, 본 발명의 일실시예의 기설철탑(100)의 부지를 활용한 신설철탑 건설 방법은, 기설철탑(100)이 건설된 부지 내에 신설철탑(200)이 위치되고, 기설철탑(100)과 신설철탑(200)의 높이방향 중심축이 서로 중첩되지 않도록 신설철탑(200)이 설계되는 단계(S100)와, 지면과 인접한 기설철탑(100)의 하단부(140)를 형성하는 주주재(110)에 보강재가 설치되고, 보강재와 지면 사이에 위치하는 부주재(120)가 철거되는 단계(S200)와, 설계된 내용에 따라, 기설철탑(100)과 높이방향 중심축이 중첩되지 않도록 신설철탑(200)이 건설되는 단계(S300)와, 기설철탑(100)이 철거되고, 지면이 복구되는 단계(S400)를 포함한다. 기설철탑(100)의 하단부(140)는, 지면으로부터 기설철탑(100)을 형성하는 주주재(110)들 중 지면과 가장 가깝고 지면과 수평한 주주재(110)들까지이다.As shown in Figure 2, the new pylon construction method using the site of the existing pylon 100 according to an embodiment of the present invention, a new pylon 200 is located in the site where the existing pylon 100 is built, and The step (S100) of designing the new pylon 200 so that the central axis in the height direction of the pylon 100 and the new pylon 200 does not overlap each other, and forming the lower end 140 of the existing pylon 100 adjacent to the ground The reinforcing material is installed in the main material 110, and the sub-main material 120 located between the reinforcement material and the ground is demolished (S200), and according to the design, the existing pylon 100 and the height direction central axis do not overlap. To prevent the construction of the new pylon 200 (S300), and the existing pylon 100 is demolished, and includes a step (S400) of restoring the ground. The lower end portion 140 of the existing pylon 100 is from the ground to the main members 110 that are closest to the ground and horizontal to the ground among the main main members 110 forming the existing steel tower 100.

도 3에 도시된 바와 같이, 신설철탑(200)과 기설철탑(100)의 높이방향 중심축이 서로 중첩되지 않도록 신설철탑(200)이 설계됨에 따라, 확보된 원래 부지내에서 신설철탑(200)을 건설할 수 있게 된다. 이에 따라, 부지확보를 위한 시간 및 자금이 절약된다.As shown in FIG. 3, as the new pylon 200 is designed so that the central axes in the height direction of the new pylon 200 and the existing pylon 100 do not overlap each other, the new pylon 200 in the original site secured Can be built. Accordingly, time and money for securing the site are saved.

도 4 내지 도 5에 도시된 바와 같이, 신설철탑(200)이 설계되는 단계(S100)에서는, 신설철탑(200)이 기설철탑(100)과 간섭되지 않도록 신설철탑(200)의 결구 형태가 결정된다. 기설철탑(100)과 대면하는 신설철탑(200)의 제1면, 제1면과 대칭되는 제2면 제1면과 제2면을 연결하는 제3면의 결구 형태가 결정된다. 기설철탑(100)과 신설철탑(200)이 접촉하지 않도록, 주주재와 부주재의 크기 및 배열 등이 결정된다.As shown in Figures 4 to 5, in the step (S100) of designing the new pylon 200, the structure of the new pylon 200 is determined so that the new pylon 200 does not interfere with the existing pylon 100 do. The first surface of the new pylon 200 facing the existing pylon 100, the second surface symmetrical to the first surface, and the third surface connecting the first surface and the second surface are determined. The size and arrangement of the main main material and the sub main material are determined so that the existing steel tower 100 and the new steel tower 200 do not come into contact with each other.

그리고, 신설철탑(200)이 설계되는 단계(S100)에서, 신설철탑(200)과 기설철탑(100)의 이격거리에 따라 신설철탑(200)의 기초(210) 형태가 결정된다. 신설철탑(200)의 기초(210) 형태가 기설철탑(100)과의 이격거리에 따라 결정되므로, 공간이 제약되더라도 시공성을 확보할 수 있게 된다.And, in the step (S100) of designing the new pylon 200, the form of the foundation 210 of the new pylon 200 is determined according to the separation distance between the new pylon 200 and the existing pylon 100. Since the shape of the foundation 210 of the new pylon 200 is determined according to the separation distance from the existing pylon 100, workability can be secured even if space is limited.

또한, 신설철탑(200)의 결구 형태 및 기초(210) 형태에 따라 신설철탑(200)의 3D 설계도가 구현된다. 신설철탑(200)의 3D 설계도가 구현됨에 따라, 발생가능한 시공상의 문제점을 검토할 수 있게 된다. 특히, 기설철탑(100)과의 간섭 문제를 미연에 해결할 수 있다.In addition, a 3D design diagram of the new pylon 200 is implemented according to the structure of the new pylon 200 and the shape of the foundation 210. As the 3D blueprint of the new pylon 200 is implemented, possible construction problems can be reviewed. In particular, it is possible to solve the problem of interference with the existing steel tower 100 in advance.

도 6에 도시된 바와 같이, 부주재(120)가 철거되는 단계(S200)에서는, 보강재가 주주재(110)에 결합되고, 기설철탑(100)으로부터 부주재(120)가 철거된다. 보강재는 H형강 일 수 있으며, 필요에 따라서, 주주재(110)에 비해 더 큰 강도를 나타내는 물체가 사용될 수도 있다.As shown in Figure 6, in the step (S200) in which the sub-main material 120 is demolished, the reinforcing material is coupled to the main main material 110, and the sub-main material 120 is demolished from the existing steel tower 100. The reinforcing material may be H-beam, and if necessary, an object having a greater strength than the main material 110 may be used.

기설철탑(100)의 주주재(110)에 홀(111)이 가공되고, 홀(111)을 통해 보강재가 주주재(110)에 결합된다. 보강재는 측면에서 봤을 때, '∏'형태를 형성하도록 주주재(110)에 설치된다.The hole 111 is processed in the main material 110 of the existing steel tower 100, and the reinforcing material is coupled to the main material 110 through the hole 111. When viewed from the side, the reinforcing material is installed on the main material 110 to form a'∏' shape.

도 1, 도 7 내지 도 10에 도시된 바와 같이, 신설철탑(200)이 건설되는 단계(S300)는, 신설철탑(200)의 기초(210)가 시공되는 단계(S310)와, 신설철탑(200)이 조립 시공되는 단계(S320)와, 신설철탑(200)에 전력선이 가선되는 단계(S330)를 포함한다.1, 7 to 10, the step of constructing a new pylon 200 (S300), the step of constructing the foundation 210 of the new pylon 200 (S310), and a new pylon ( 200) includes a step of assembly and construction (S320), and a step (S330) of wiring a power line to the new pylon 200.

도 7 내지 도 8에 도시된 바와 같이, 신설철탑(200)의 기초(210)가 시공되는 단계(S310)에서는, 보강재가 설치된 기설철탑(100) 일측에 신설철탑(200)의 기초(210)가 시공된다. 신설철탑(200)의 기초(210)는 강관파일공법을 통해 형성될 수 있다. 강관파일공법은, 천공, 케이싱 및 강관파일 항타를 통해 시공된다. 강관파일공법은, 천공 범위가 제한적이므로, 기설철탑(100)과 가깝게 신설철탑(200)의 기초(210)가 시공될 수 있다. 또한, 절토구역이 최소화되므로, 기설철탑(100) 기초(130)의 인발 저항이 적게 발생되고, 이에 따라, 안전도가 확보된다. 7 to 8, in the step (S310) in which the foundation 210 of the new pylon 200 is constructed (S310), the foundation 210 of the new pylon 200 on one side of the existing pylon 100 on which a reinforcement is installed Is constructed. The foundation 210 of the new pylon 200 may be formed through a steel pipe pile method. The steel pipe pile construction method is constructed through drilling, casing and driving of steel pipe piles. In the steel pipe pile construction method, since the perforation range is limited, the foundation 210 of the new pylon 200 may be constructed close to the existing pylon 100. In addition, since the cutting area is minimized, the pull-out resistance of the existing pylon 100 and the foundation 130 is reduced, and thus, safety is ensured.

도 9에 도시된 바와 같이, 신설철탑(200)이 조립 시공되는 단계(S320)에서는, 신설철탑(200)이 설계되는 단계(S100)에서 결정된 결구 형태에 따라 신설철탑(200)이 조립된다. 설계시 발생가능한 기설철탑(100)과의 간섭문제를 검토하였으므로, 조립 시간이 단축될 수 있다.As shown in Figure 9, in the step (S320) in which the new pylon 200 is assembled and constructed, the new pylon 200 is assembled according to the structure determined in the step (S100) in which the new pylon 200 is designed. Since the interference problem with the existing pylon 100 that may occur during design has been examined, the assembly time can be shortened.

도 10에 도시된 바와 같이, 신설철탑(200)에 전력선이 가선되는 단계(S330)에서는, 기설철탑(100)에 연결된 1개 이상의 전력선들 중 가장 높이 위치된 전력선에서 가장 아래에 위치된 전력선 순서로 전력선들이 기설철탑(100)에서 신설철탑(200)으로 이동된다.As shown in Figure 10, in the step (S330) in which the power line is wired to the new pylon 200, the order of the power line located at the bottom from the power line located highest among one or more power lines connected to the existing pylon 100 The furnace power lines are moved from the existing pylon 100 to the new pylon 200.

서로 대칭되도록 전방측에서 기설철탑(100)에 도달한 전력선과 후방측에서 기설철탑(100)에 도달한 전력선 중 어느 한 전력선이 신설철탑(200)으로 이동된 뒤, 나머지 전력선이 신설철탑(200)으로 이동된다.After any one of the power lines reaching the existing pylon 100 from the front side and the power lines reaching the existing pylon 100 from the rear side to be symmetrical to each other is moved to the new pylon 200, the remaining power lines are transferred to the new pylon 200 ).

기설철탑(100)과 연결된 전력선은 신설철탑(200)으로 이동되기 직전 휴전된다. 서로 대칭되도록 전방측에서 기설철탑(100)에 도달한 전력선과 후방측에서 기설철탑(100)에 도달한 전력선이 모두 기설철탑(100)에서 신설철탑(200)으로 이동된 후, 기설철탑(100)에서 암이 제거되면, 기설철탑(100)에서 신설철탑(200)으로 이동된 두 전력선이 가압된다.The power line connected to the existing pylon 100 is ceased immediately before moving to the new pylon 200. After all the power lines reaching the existing pylon 100 from the front side and the power lines reaching the existing pylon 100 from the rear side are moved from the existing pylon 100 to the new pylon 200 so that they are symmetric with each other, the existing pylon 100 ), when the arm is removed, the two power lines moved from the existing pylon 100 to the new pylon 200 are pressurized.

정해진 순서에 따라, 전력선이 기설철탑(100)에서 신설철탑(200)으로 이동하게 되며, 이동 직선 휴전되므로, 전력 공급에 차질이 발생되지 않으며, 전력선이 서로 접촉될 여지가 없다.According to a predetermined order, the power lines are moved from the existing pylon 100 to the new pylon 200, and since the moving line is ceased, there is no disruption in power supply, and there is no room for the power lines to contact each other.

도 11에 도시된 바와 같이, 기설철탑(100)이 철거되고, 지면이 복구되는 단계(S400)에서는, 암이 제거된 상태의 기설철탑(100)이 위에서 아래방향으로 분해된다. 기설철탑(100) 기초(130)의 형태에 따라, 기설철탑(100)의 기초(130)가 제거될 수 있다. 기설철탑(100)의 기초(130)가 제거됨에 따라 발생된 구덩이에 흙을 덮어 복구한다.As shown in FIG. 11, in the step (S400) in which the existing pylon 100 is demolished and the ground is restored, the existing pylon 100 in a state in which the arm is removed is disassembled from top to bottom. Depending on the shape of the existing pylon 100 and the foundation 130, the base 130 of the existing pylon 100 may be removed. As the foundation 130 of the existing steel tower 100 is removed, the resulting pit is covered with soil to recover.

기설철탑(100)의 기초(130)가 제거되지 않더라도, 기설철탑(100)의 기초(130)가 지표면에 노출됨에 따라, 미관이 저하된다고 생각될 경우에는 기설철탑(100)의 기초(130)가 보여지지 않도록 흙을 덮어 복구하게 된다.Even if the foundation 130 of the existing pylon 100 is not removed, as the foundation 130 of the existing pylon 100 is exposed to the ground surface, if it is thought that the aesthetics are deteriorated, the foundation 130 of the existing pylon 100 It is restored by covering the soil so that it is not visible.

위와 같이 구성되는 본 발명의 일실시예의 기설철탑(100)의 부지를 활용한 신설철탑(200) 건설 방법에 따르면, 확보된 부재 내에 건설되도록 신설철탑(200)이 설계되므로, 기설철탑(100) 보다 큰 크기의 신설철탑(200)을 건설하더라도 추가 적인 부지 확보가 불필요해지는 효과가 있다.According to the construction method of the new pylon 200 using the site of the existing pylon 100 of an embodiment of the present invention configured as above, since the new pylon 200 is designed to be built within the secured member, the existing pylon 100 Even if a new steel tower 200 of a larger size is constructed, there is an effect that it is not necessary to secure an additional site.

또한, 신설철탑(200)과 기설철탑(100)의 높이방향 중심축이 서로 중첩되지 않게 됨에 따라, 신설철탑(200)의 암을 기설철탑(100)의 암과 평행하게 설치할 수 있게 된다. 따라서, 전력선 이전이 한층 더 간편해 진다. In addition, as the central axes in the height direction of the new pylon 200 and the existing pylon 100 do not overlap each other, the arm of the new pylon 200 can be installed in parallel with the arm of the existing pylon 100. Therefore, the power line transfer becomes even more convenient.

또한, 확보된 부지를 더 효과적으로 사용할 수 있게 된다. 기설철탑(100) 하단부(140)를 해체해 공사공간을 확보하므로, 공사가 편리하게 수행될 수 있고, 기간을 단축시킬 수 있게 된다. 공사기간이 단축되므로, 공사비는 절감시킬 수 있고, 건설 설비의 안정성을 쉽게 유지할 수 있다.In addition, it is possible to use the secured site more effectively. Since the construction space is secured by dismantling the lower part 140 of the existing pylon 100, the construction can be conveniently performed and the period can be shortened. Since the construction period is shortened, construction costs can be reduced, and the stability of construction equipment can be easily maintained.

100: 기설철탑 110: 주주재
111: 홀 120: 부주재
130: 기설철탑의 기초 140: 하단부
200: 신설철탑 210: 신설철탑의 기초
100: existing steel tower 110: main house
111: hall 120: sub-presidential
130: the foundation of the existing pylon 140: the lower part
200: new pylon 210: foundation of new pylon

Claims (7)

기설철탑이 건설된 부지 내에 신설철탑이 위치되고, 상기 기설철탑과 상기 신설철탑의 높이방향 중심축이 서로 중첩되지 않도록 상기 신설철탑이 설계되는 단계;
지면과 인접한 상기 기설철탑의 하단부를 형성하는 주주재에 보강재가 설치되고, 상기 보강재와 지면 사이에 위치하는 부주재가 철거되는 단계;
설계된 내용에 따라, 상기 기설철탑과 높이방향 중심축이 중첩되지 않도록 상기 신설철탑이 건설되는 단계;
상기 기설철탑이 철거되고, 지면이 복구되는 단계; 를 포함하고,
지면과 인접한 상기 기설철탑의 하단부를 형성하는 주주재에 보강재가 설치되고,
상기 보강재와 지면 사이에 위치하는 부주재가 철거되는 단계에서는, 상기 주주재에 홀이 가공되고, 상기 홀을 통해 상기 보강재가 상기 주주재에 결합되며,
상기 보강재는 측면에서 봤을 때, '∏'형태를 형성하도록 상기 주주재에 설치되는 것을 특징으로 하는 기설철탑의 부지를 활용한 신설철탑 건설 방법.
Designing the new steel tower so that the new steel tower is located in the site where the existing steel tower is constructed, and the central axis in the height direction of the existing steel tower and the new steel tower does not overlap each other;
A step of installing a reinforcement material on the main main material forming the lower end of the existing steel tower adjacent to the ground, and removing the sub main material located between the reinforcement material and the ground;
Constructing the new steel tower so that the existing steel tower and the central axis in the height direction do not overlap according to the designed contents;
The existing steel tower is demolished and the ground is restored; Including,
A reinforcing material is installed on the main material forming the lower end of the existing steel tower adjacent to the ground,
In the step of removing the sub-main material located between the reinforcing material and the ground, a hole is processed in the main main material, and the reinforcing material is coupled to the main main material through the hole,
The reinforcing material is installed on the main body to form a'∏' shape when viewed from the side.
제1항에 있어서,
상기 신설철탑이 설계되는 단계에서는,
상기 신설철탑이 상기 기설철탑과 간섭되지 않도록 상기 신설철탑의 결구 형태가 결정되고,
상기 신설철탑과 상기 기설철탑의 이격거리에 따라 상기 신설철탑의 기초 형태가 결정되고,
상기 신설철탑의 결구 형태 및 기초 형태에 따라 상기 신설철탑의 3D 설계도가 구현되는 기설철탑의 부지를 활용한 신설철탑 건설 방법.
The method of claim 1,
In the step of designing the new pylon,
The structure of the new steel tower is determined so that the new steel tower does not interfere with the existing steel tower,
The basic shape of the new steel tower is determined according to the separation distance between the new steel tower and the existing steel tower,
A method of constructing a new steel tower using the site of an existing steel tower in which a 3D blueprint of the new steel tower is implemented according to the structure of the new steel tower and the form of the foundation.
삭제delete 제1항에 있어서,
상기 신설철탑이 건설되는 단계는,
상기 신설철탑의 기초가 시공되는 단계;
상기 신설철탑이 조립 시공되는 단계;
상기 신설철탑에 전력선이 가선되는 단계를 포함하며,
상기 신설철탑이 조립 시공되는 단계에서는,
상기 신설철탑이 설계되는 단계에서 결정된 결구 형태에 따라 상기 신설철탑이 조립되는 기설철탑의 부지를 활용한 신설철탑 건설 방법.
The method of claim 1,
The step of constructing the new pylon,
The step of constructing the foundation of the new pylon;
The step of assembling and constructing the new steel tower;
Including the step of wiring a power line to the new pylon,
In the step of assembling and constructing the new pylon,
A method of constructing a new steel tower using the site of an existing steel tower to which the new steel tower is assembled according to the structure determined in the step of designing the new steel tower.
제4항에 있어서,
상기 신설철탑의 기초가 시공되는 단계에서는,
강관파일공법을 통해 상기 신설철탑의 기초가 형성되는 기설철탑의 부지를 활용한 신설철탑 건설 방법.
The method of claim 4,
In the step of constructing the foundation of the new pylon,
A new steel tower construction method using the site of an existing steel tower on which the foundation of the new steel tower is formed through a steel pipe pile method.
제4항에 있어서,
상기 신설철탑에 전력선이 가선되는 단계에서는,
상기 기설철탑에 연결된 1개 이상의 전력선들 중 가장 높이 위치된 전력선에서 가장 아래에 위치된 전력선 순서로 전력선들이 상기 기설철탑에서 상기 신설철탑으로 이동되고,
서로 대칭되도록 전방측에서 상기 기설철탑에 도달한 전력선과 후방측에서 상기 기설철탑에 도달한 전력선 중 어느 한 전력선이 상기 신설철탑으로 이동된 뒤, 나머지 전력선이 상기 신설철탑으로 이동되는 기설철탑의 부지를 활용한 신설철탑 건설 방법.
The method of claim 4,
In the step of wiring a power line to the new pylon,
Among the one or more power lines connected to the existing pylon, power lines are moved from the existing pylon to the new pylon in the order of the lowest located power line from the highest power line,
The site of the existing pylon in which one of the power lines reaching the existing pylon from the front side and the power line reaching the existing pylon from the rear side is moved to the new pylon, and the remaining power lines are moved to the new pylon so that they are symmetric with each other. How to build a new steel tower using the.
제6항에 있어서,
상기 기설철탑과 연결된 전력선은 상기 신설철탑으로 이동되기 직전 휴전되며,
서로 대칭되도록 전방측에서 상기 기설철탑에 도달한 전력선과 후방측에서 상기 기설철탑에 도달한 전력선이 모두 상기 기설철탑에서 상기 신설철탑으로 이동된 후, 상기 기설철탑에서 암이 제거되면, 상기 기설철탑에서 상기 신설철탑으로 이동된 두 전력선이 가압되는 기설철탑의 부지를 활용한 신설철탑 건설 방법.
The method of claim 6,
The power line connected to the existing pylon is halted immediately before being moved to the new pylon,
When both the power line reaching the existing pylon from the front side and the power line reaching the existing pylon from the rear side are moved from the existing pylon to the new pylon so that they are symmetrical to each other, when the arm is removed from the existing pylon, the existing pylon In the new pylon construction method using the site of the existing pylon in which the two power lines moved to the new pylon are pressurized.
KR1020190126886A 2019-10-14 2019-10-14 Construction method of new steel tower using the site of existing steel tower KR102226699B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190126886A KR102226699B1 (en) 2019-10-14 2019-10-14 Construction method of new steel tower using the site of existing steel tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190126886A KR102226699B1 (en) 2019-10-14 2019-10-14 Construction method of new steel tower using the site of existing steel tower

Publications (1)

Publication Number Publication Date
KR102226699B1 true KR102226699B1 (en) 2021-03-11

Family

ID=75142853

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190126886A KR102226699B1 (en) 2019-10-14 2019-10-14 Construction method of new steel tower using the site of existing steel tower

Country Status (1)

Country Link
KR (1) KR102226699B1 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010025613A (en) 2001-01-11 2001-04-06 정재기 Grounding Resistance Measurement System for Electric Support Tower on Power Service
JP2018150683A (en) * 2017-03-10 2018-09-27 中国電力株式会社 Reconstructing method for steel tower
KR20190018299A (en) * 2017-08-14 2019-02-22 한국전력공사 Electric pole for changing transmission power and installing method thereof

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010025613A (en) 2001-01-11 2001-04-06 정재기 Grounding Resistance Measurement System for Electric Support Tower on Power Service
JP2018150683A (en) * 2017-03-10 2018-09-27 中国電力株式会社 Reconstructing method for steel tower
KR20190018299A (en) * 2017-08-14 2019-02-22 한국전력공사 Electric pole for changing transmission power and installing method thereof

Similar Documents

Publication Publication Date Title
KR101595702B1 (en) Soil retaining structure using plate pile with reinforcing bridge and construction method thereof
JP6480815B2 (en) Tunnel junction structure and tunnel construction method
JP4746602B2 (en) Segment connection structure
CN205822220U (en) A kind of assembled open caisson
KR102226699B1 (en) Construction method of new steel tower using the site of existing steel tower
JP2020153066A (en) Open shield machine
EP2957676A1 (en) Telescopic type riser system equipment for digging round pits and its utilization method
KR100376589B1 (en) Underground construction method using permanent reinforced concrete girders as temporary struts
KR20000058237A (en) Underground construction method using permanent structural members as temporary struts
JP2013040488A (en) Press bar for open shield machine
US20210032830A1 (en) Cover band of steel pipe strut connector, steel pipe strut connector having same, and steel pipe strut assembly
JP2001303553A (en) Underground continuous wall and its construction method
KR102186630B1 (en) Water and sewage construction method
KR20150059640A (en) Perpendicular hall module and construction method for perpendicular hall using the same
JP5169638B2 (en) Construction method of underground structure
US6691727B2 (en) Device and method for protecting a subterranean pipe from damage during excavation
JP4746603B2 (en) Segment connection structure
JP6592331B2 (en) Survey method of circumferential shield machine
CN209179034U (en) A kind of relief well reinforcing operating platform being used in turn
JP6130139B2 (en) Caisson structure having pressure-resistant plate and construction method thereof
JP2019199698A (en) Structure, construction method, and formwork used for construction of workspace for wall balustrade buried pipeline
JP7038014B2 (en) Construction method of seismic isolation structure
KR20230112211A (en) Retaining wall with hollow reinforcement
CN109403336B (en) Dangerous house protection structure near foundation pit and construction method thereof
JP4630215B2 (en) Relocation method for buried objects

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant