KR102202853B1 - Concrete Embedded Rail Anchor Construction Method for Adjusting a Horizontal Level Easily - Google Patents

Concrete Embedded Rail Anchor Construction Method for Adjusting a Horizontal Level Easily Download PDF

Info

Publication number
KR102202853B1
KR102202853B1 KR1020200096089A KR20200096089A KR102202853B1 KR 102202853 B1 KR102202853 B1 KR 102202853B1 KR 1020200096089 A KR1020200096089 A KR 1020200096089A KR 20200096089 A KR20200096089 A KR 20200096089A KR 102202853 B1 KR102202853 B1 KR 102202853B1
Authority
KR
South Korea
Prior art keywords
rail
bracket
horizontal level
rail bracket
fixing
Prior art date
Application number
KR1020200096089A
Other languages
Korean (ko)
Inventor
김기종
Original Assignee
주식회사 금라이엔지
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 금라이엔지 filed Critical 주식회사 금라이엔지
Priority to KR1020200096089A priority Critical patent/KR102202853B1/en
Application granted granted Critical
Publication of KR102202853B1 publication Critical patent/KR102202853B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/10Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/005Piers, trestles, bearings, expansion joints or parapets specially adapted for portable or sectional bridges
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16BDEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
    • F16B7/00Connections of rods or tubes, e.g. of non-circular section, mutually, including resilient connections
    • F16B7/18Connections of rods or tubes, e.g. of non-circular section, mutually, including resilient connections using screw-thread elements
    • F16B7/187Connections of rods or tubes, e.g. of non-circular section, mutually, including resilient connections using screw-thread elements with sliding nuts or other additional connecting members for joining profiles provided with grooves or channels

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention provides a construction method of a concrete-embedded preinstalled rail anchor for easily adjusting the horizontal level to efficiently construct facilities such as a bridge inspection passage by aligning and adjusting the horizontal level by a guide rail in the rail anchor construction of a concrete structure such as a bridge column. The construction method of a concrete-embedded preinstalled rail anchor for easily adjusting a horizontal level comprises: (a) a step of measuring a level from a construction reference point in the form of a concrete structure, aligning the position of an upper rail bracket among rail brackets having a first rail groove and a second rail groove formed on the front and rear to measure the level; (b) a step of inserting and coupling a laterally extended guide rail into the second rail groove of the upper rail bracket to connect the upper rail brackets positioned and separated from each other to align and correct the horizontal level; (c) a step of fixing the upper rail bracket with the adjusted horizontal level on the form of the concrete structure; (d) a step of aligning the position of lower rail brackets among rail brackets provided with a first rail groove and a second rail groove formed on the front and rear and separated from each other underneath the upper rail bracket on the form of the concrete structure to measure the horizontal level alignment, and connecting a gap adjustment bracket between the upper rail bracket and the lower rail bracket to adjust the gap; (e) a step of inserting and coupling a laterally extended guide rail to the second rail groove of the lower rail bracket to connect the lower rail brackets positioned and separated from each other to align the horizontal level; and (f) a step of fixing the lower rail bracket with the adjusted gap and the adjusted horizontal level on the form of the concrete structure.

Description

수평 레벨 조정이 용이한 콘크리트 매립형 선설치 레일 앵커 시공공법 {Concrete Embedded Rail Anchor Construction Method for Adjusting a Horizontal Level Easily}Concrete Embedded Rail Anchor Construction Method for Adjusting a Horizontal Level Easily}

본 발명은 수평 레벨 조정이 용이한 콘크리트 매립형 선설치 레일 앵커 시공공법에 관한 것으로서, 더욱 상세하게는 교량기둥과 같은 콘크리트 구조물의 레일 앵커 시공에 수평 레벨을 가이드레일로 맞춤 조정하여 교량 점검로와 같은 시설물을 효율적으로 시공하는 것이 가능한 수평 레벨 조정이 용이한 콘크리트 매립형 선설치 레일 앵커 시공공법에 관한 것이다.The present invention relates to a concrete buried type pre-installed rail anchor construction method for easy horizontal level adjustment, and more particularly, by adjusting the horizontal level with a guide rail for rail anchor construction of concrete structures such as bridge columns, It relates to a concrete embedded pre-installed rail anchor construction method that can easily adjust the horizontal level that enables efficient construction of facilities.

일반적으로 교량기둥과 같은 콘크리트 구조물에 교량 점검로 등의 시설물을 고정함에는 콘크리트 구조물의 시공을 마친 후 콘크리트 구조물의 벽면에 드릴로 천공하며, 천공 홀에 세트 앵커나 케미컬 앵커를 매입하여 고정한 다음 시설물과 함께 볼트로 조립하여 시공하는 공법을 사용하고 있다.In general, to fix facilities such as bridge inspection paths to concrete structures such as bridge pillars, drill holes into the walls of the concrete structure after the construction of the concrete structure is completed, and set anchors or chemical anchors are embedded and fixed in the drill hole. It uses a method of assembling and installing with bolts together.

이러한 시공공법은 콘크리트 구조물을 완성한 후에 앵커 매입을 위한 구멍을 콘크리트에 천공시키기 때문에 구조물에 손상을 주게 되고, 천공시 콘크리트 표면 가까이에 배치된 철근과 간섭 현상이 발생하여 철근이 손상되거나 원하는 위치에 맞게 천공할 수 없게 되며, 앵커의 진입 깊이가 철근과의 간섭에 따라 일정하지 않아 앵커의 허용력이 작아지고 신뢰할 수 없게 된다는 문제가 있었다.This construction method damages the structure because the hole for anchoring is drilled into the concrete after the concrete structure is completed, and the reinforcement is damaged due to interference with the reinforcing bar placed close to the concrete surface during drilling. There is a problem that it becomes impossible to drill, and the depth of entry of the anchor is not constant according to interference with the reinforcing bar, so that the allowable power of the anchor becomes small and it becomes unreliable.

상기와 같은 문제를 해결하기 위하여 개시되어 있었던 종래기술로써, 대한민국 공개특허공보 제37696호(2010.04.12.)에는 앵커볼트의 일측 단부 내측에 나사산을 가진 부착물결합부가 형성된 앵커형너트를 콘크리트 타설전에 미리 매입하여 시공하는 매입용 앵커를 설치하는 방법에 있어서, 앵커형너트를 콘크리트 타설전에 거푸집 내측 소정의 위치에 밀착 배치하며, 거푸집에는 부착물결합부와 호형으로 구멍을 형성하여 거푸집 외측에서 임시고정볼트로 거푸집과 부착물결합부를 고정한 후 콘크리트를 타설하고, 콘크리트가 경화된 후 임시고정볼트를 풀어 거푸집을 탈형한 후 상기 부착물결합부에 고정볼트로 부착물을 고정하도록 구성됨에 따라 콘크리트 타설 전에 미리 콘크리트 속에 매입되어 콘크리트 구조물과 일체로 형성되므로 견고하고 신뢰성 높은 앵커부를 간단한 방법으로 정밀하게 형성할 수 있는 매입형 앵커 설치방법이 공지되어 있다.As a prior art disclosed in order to solve the above problems, Korean Patent Laid-Open Publication No. 37696 (2010.04.12.) discloses an anchor type nut with a threaded attachment joint formed inside one end of the anchor bolt before concrete pouring. In the method of installing an embedding anchor that is embedded and installed in advance, the anchor-type nut is placed in close contact with a predetermined position inside the formwork before concrete pouring, and a temporary fixing bolt is formed outside the formwork by forming a hole in an arc shape with the attachment joint in the formwork. It is configured to fix the formwork and the attachment joint with the concrete, pour the concrete, and after the concrete is hardened, loosen the temporary fixing bolts to remove the formwork, and then fix the attachment with fixing bolts on the attachment joint. As a result, since it is formed integrally with a concrete structure, a method of installing a buried anchor capable of precisely forming a strong and reliable anchor portion in a simple manner is known.

또한, 등록특허공보 제707685호(2007.04.07.)에는 철근 콘크리트 구조물에 시설물을 매달기 위해 시공하는 매입용 앵커에 있어서, 일측의 단부에는 앵커헤드가 형성되고 다른 단부는 소켓너트에 고정되는 앵커부재와, 상기 앵커부재와 일측 단부가 결합되고 다른 단부는 너트형 나사산이 형성되어 볼트고정부를 형성하는 소켓너트와, 상기 소켓너트 다수개가 소켓너트의 너트형 나사산이 형성된 볼트고정부 단부에 소정의 형상과 넓이를 가지며 상기 소켓너트의 볼트고정부 단부에 대응하여 볼트구멍이 형성되며 임시고정용 리벳구멍을 추가로 다수 개 형성하는 판부재와 고정되며, 상기 판부재를 거푸집에 일시적으로 고정하는 임시고정리벳, 상기 소켓너트의 볼트고정부 위치에 맞게 부착물을 고정하면서 조립되는 부착용볼트를 포함하여 구성됨에 따라 콘크리트 타설 전에 미리 콘크리트 속에 매입되어 콘크리트 구조물과 일체로 형성되므로 견고하고 신뢰성 높은 앵커부를 간단한 방법으로 정밀하게 형성할 수 있는 너트가 부착된 매입용 앵커가 공지되어 있다.In addition, Patent Publication No. 707685 (2007.04.07.) discloses a buried anchor constructed to hang facilities on a reinforced concrete structure, wherein an anchor head is formed at one end and an anchor fixed to a socket nut at the other end. A member, the anchor member and one end of which are coupled, the other end of which is formed with a nut-like thread to form a bolt fixing part, and a plurality of the socket nuts are predetermined at the end of the bolt fixing part where the nut-like thread of the socket nut is formed. It has the shape and width of the socket nut and has a bolt hole formed corresponding to the end of the bolt fixing portion of the socket nut, and is fixed with a plate member forming a plurality of additional rivet holes for temporary fixing, and temporarily fixing the plate member to the formwork. As it is composed of a temporary fixing rivet and an attachment bolt that is assembled while fixing the attachment according to the position of the bolt fixing part of the socket nut, it is embedded in the concrete before concrete pouring and is formed integrally with the concrete structure. An embedding anchor with a nut that can be precisely formed by a method is known.

또, 등록실용신안공보 제206699호(2000.10.04.)에는 교각의 슬래브 일정위치에 상하 일정간격으로 매입 설치되는 길이방향의 전,후면에 각각 안내홈을 갖는 레일과, 상기 각각의 레일의 안내홈에 머리가 삽입안내되는 볼트와, 상기 볼트를 상하 일정 간격으로 유지하기 위해 상,하부에 볼트의 로드가 관통되는 구멍을 일정간격으로 갖는 간격편과, 상기 볼트의 로드에는 너트를 체결하여 상기 간격편을 고정하고, 상기 안내홈에 가이드되어 교각에 배근된 수직철근에 접촉되어 용접 또는 결속끈으로 고정되고, 전면의 안내홈에는 교각 거푸집에 콘크리트 붓기시 메움방지용으로 삽입되는 실링과, 상기 안내홈에는 대상물 고정수단으로써, 머리가 삽입되어 가이드되는 볼트에 대상물을 관통하여 고정하는 너트로 구성됨에 따라 설치가 용이하고 안정적인 부착 고정력을 도모할 수 있는 교각에 점검대를 설치하기 위한 고정장치가 공지되어 있다.In addition, Registered Utility Model Publication No. 206699 (October 4, 2000) includes rails having guide grooves on the front and rear sides of the pier, which are buried and installed at regular intervals up and down at a fixed position of the slab, and guides of each of the rails. A bolt through which the head is inserted into the groove, and a gap piece having a hole through which the rod of the bolt passes through the upper and lower portions of the bolt at regular intervals, and a nut is fastened to the rod of the bolt. The spacing piece is fixed, the guide groove is guided to the vertical reinforcing bar placed on the pier and fixed with welding or binding strings, and the front guide groove has a sealing inserted to prevent filling when concrete is poured into the pier formwork, and the guide The groove is an object fixing means, and as it is composed of a nut that penetrates and fixes the object to the bolt guided by inserting a head, there is a known fixing device for installing an inspection stand on the pier that is easy to install and can achieve a stable attachment and fixation force. Has been.

그러나 상기한 종래기술 중 공개특허공보 제37696호의 경우에는 콘크리트 구조물 내 매입되는 복수 개의 앵커가 서로 연결되지 않은 채 낱개로 고정되는 구조이기 때문에 시공시 앵커 간의 간격을 정확하게 유지하기 어려우며 시공성이 현저히 떨어진다는 문제가 있었다.However, in the case of Korean Patent Publication No. 37696, among the above-described prior art, it is difficult to accurately maintain the spacing between anchors during construction because a plurality of anchors embedded in a concrete structure are fixed individually without being connected to each other. There was a problem.

또한, 상기한 종래기술 중 공개특허공보 제37696호 및 등록특허공보 제707685호, 등록실용신안공보 제206699호의 경우에는 모두 콘크리트 구조물에 대응된 앵커의 시공 위치에 철근이 존재하는 경우 앵커의 위치 자체를 이동시켜 주어야 하기 때문에 앵커 간 간격을 균일하게 유지하기가 어려우며, 앵커에 고정볼트 등으로 결합하는 시설물의 프레임 간 시공 간격에 차이가 발생하는 등 결합 위치가 변경되고, 이에 따라 앵커 간의 간격을 정확하게 유지하지 못하게 시공하여 앵커의 시공 간격이 서로 다르게 적용됨에 따라 원하는 지지력을 달성하기 어려움은 물론 시설물의 안정적인 시공이 어렵다는 문제가 있었다.In addition, in the case of Public Patent Publication No. 37696, Registered Patent Publication No. 707685, and Registered Utility Model Publication No. 206699, among the above-described conventional technologies, when reinforcing bars exist at the construction positions of anchors corresponding to concrete structures, the position of the anchor itself It is difficult to maintain a uniform spacing between anchors because of the need to move the anchors, and the joint position is changed, such as a difference in the construction spacing between frames of facilities that are joined to the anchors with fixing bolts, etc. As the construction was not maintained so that the construction intervals of the anchors were applied differently, there was a problem in that it was difficult to achieve the desired supporting force as well as the stable construction of the facility.

KR 공개특허공보 제10-2010-0037696호 (2010.04.12.)KR Patent Publication No. 10-2010-0037696 (2010.04.12.) KR 등록특허공보 제10-0707685호 (2007.04.07.)KR Registered Patent Publication No. 10-0707685 (2007.04.07.) KR 등록실용신안공보 제20-0206699호 (2000.10.04.)KR Registered Utility Model Publication No. 20-0206699 (2000.10.04.)

본 발명은 상기와 같은 문제점을 해결하기 위한 것으로서, 히든레일 앵커 간의 수평 레벨을 슬라이드 연결방식의 가이드레일을 이용해 맞춤 조정하면서 시공하므로 시공의 편의성 및 정확성을 높이면서 시공품질을 증진시킬 수 있는 수평 레벨 조정이 용이한 콘크리트 매립형 선설치 레일 앵커 시공공법을 제공하는데, 그 목적이 있다.The present invention is to solve the above problems, and the horizontal level between the hidden rail anchors is customized and adjusted using a guide rail of a slide connection method, so that the horizontal level that can improve the construction quality while increasing the convenience and accuracy of construction To provide an easy-to-adjust concrete buried type pre-installed rail anchor construction method, the purpose is.

뿐만 아니라 본 발명은 히든레일마다 상하 간격을 두고 위치한 앵커 간의 간격을 모두 동일한 위치로 맞춤 조정할 수 있게 시공하므로 앵커 간 일률적인 간격을 정확하게 유지하면서 시설물의 시공 안정성을 높일 수 있는 수평 레벨 조정이 용이한 콘크리트 매립형 선설치 레일 앵커 시공공법을 제공하기 위한 것이다.In addition, the present invention makes it possible to customize the distance between anchors located at the top and bottom of each hidden rail to the same position, so it is easy to adjust the horizontal level that can increase the construction stability of the facility while accurately maintaining the uniform gap between anchors. It is to provide a concrete embedded pre-installed rail anchor construction method.

본 발명이 제안하는 수평 레벨 조정이 용이한 콘크리트 매립형 선설치 레일 앵커 시공공법은 (a)콘크리트 구조물의 거푸집 중 시공 기준지점에서부터 레벨을 측량하되 전후로 제1레일홈 및 제2레일홈이 형성된 레일브라켓 중 상부레일브라켓의 위치를 맞춰 레벨을 측량하는 단계와; (b)횡 방향으로 연장 형성된 가이드레일을 상기 상부레일브라켓의 제2레일홈에 끼움 결합하여 서로 간격을 두고 위치한 상기 상부레일브라켓 간에 연결하여 수평 레벨을 맞춰 수정하는 단계와; (c)콘크리트 구조물의 거푸집 상에 수평 레벨이 조정된 상기 상부레일브라켓을 고정하는 단계와; (d)상기 상부레일브라켓의 하측에 간격을 두고 전후 제1레일홈 및 제2레일홈이 형성된 레일브라켓 중 하부레일브라켓을 콘크리트 구조물의 거푸집 상에 위치를 맞춰 레벨을 측량하되, 상기 상부레일브라켓과 상기 하부레일브라켓 간에 간격조절브라켓을 연결하여 간격을 조절하는 단계와; (e)횡 방향으로 연장 형성된 가이드레일을 상기 하부레일브라켓의 제2레일홈에 끼움 결합하여 서로 간격을 두고 위치한 상기 하부레일브라켓 간에 연결하여 수평 레벨을 맞춰 수정하는 단계와; (f)콘크리트 구조물의 거푸집 상에 간격 조절 및 수평 레벨이 조정된 상기 하부레일브라켓을 고정하는 단계;를 포함하여 이루어진다.The concrete embedding type pre-installed rail anchor construction method that is easy to adjust the horizontal level proposed by the present invention is (a) a rail bracket in which the first rail groove and the second rail groove are formed before and after measuring the level from the construction reference point of the formwork of the concrete structure. Measuring a level according to the position of the upper rail bracket; (b) fitting a guide rail extending in a transverse direction into a second rail groove of the upper rail bracket and connecting the upper rail brackets located at a distance from each other to match the horizontal level; (c) fixing the upper rail bracket whose horizontal level is adjusted on the formwork of the concrete structure; (d) Measure the level by aligning the lower rail bracket on the formwork of the concrete structure among the rail brackets in which the front and rear first rail grooves and the second rail grooves are formed at an interval under the upper rail bracket, and the upper rail bracket Adjusting the distance by connecting the distance adjustment bracket between the lower rail bracket and the lower rail bracket; (e) fitting a guide rail extending in a transverse direction into a second rail groove of the lower rail bracket and connecting the lower rail brackets spaced apart from each other to match the horizontal level; and (f) fixing the lower rail bracket whose spacing and horizontal level are adjusted on the formwork of the concrete structure.

상기 (a)단계 및 상기 (d)단계에서는, 콘크리트 구조물의 거푸집에 대응하여 대면하는 상기 레일브라켓의 고정면에 자석의 자력을 이용하여 레벨 측량시 임시 부착한다.In the above (a) and (d) steps, the rail bracket is temporarily attached to the fixed surface of the rail bracket facing the formwork of the concrete structure using the magnetic force of a magnet during level measurement.

상기 (c)단계 및 상기 (f)단계에서는, 상기 레일브라켓의 고정부에 형성된 고정홀에 피스 또는 리벳으로 고정한다.In the step (c) and step (f), the fixing hole formed in the fixing portion of the rail bracket is fixed with a piece or rivet.

상기 (d)단계에서는, 상기 간격조절브라켓에 형성된 복수 개의 간격조절공에 상기 레일브라켓을 끼움 결합하여 상기 상부레일브라켓 및 상기 하부레일브라켓 간에 상하 간격을 조절 설정한다.In the step (d), the rail bracket is fitted into a plurality of space adjusting holes formed in the space adjusting bracket to adjust the vertical distance between the upper rail bracket and the lower rail bracket.

상기 (d)단계에서는, 상기 상부레일브라켓 및 상기 하부레일브라켓 간에 간격을 조절할 때 거푸집에 대응하여 연장된 상기 간격조절브라켓의 고정자석에 의한 자력을 이용하여 상기 간격조절브라켓을 임시로 부착 고정하게 이루어진다.In the step (d), when adjusting the gap between the upper rail bracket and the lower rail bracket, the gap adjustment bracket is temporarily attached and fixed using magnetic force by a fixed magnet of the gap adjusting bracket extended in response to a formwork. Done.

상기 (d)단계에서 상기 간격조절브라켓을 연결함에는, 상기 레일브라켓에 레일고정수단을 설치하되, 상기 레일브라켓의 제2레일홈 내 고정너트를 설치하여 좌우 위치 조정한 후, 상기 고정너트에 대응하여 고정볼트를 결합 설치하여 고정하게 이루어진다.In the step (d), when connecting the gap adjustment bracket, a rail fixing means is installed on the rail bracket, and a fixing nut in the second rail groove of the rail bracket is installed to adjust the left and right positions, and then to the fixing nut. Correspondingly, fixing bolts are installed and fixed.

본 발명에 따른 수평 레벨 조정이 용이한 콘크리트 매립형 선설치 레일 앵커 시공공법에 의하면 가이드레일을 이용하여 레일 앵커 간의 수평 레벨을 맞춤 조정하며 시공하므로, 작업이 매우 간편함은 물론 신속한 작업진행으로 공기를 최소화하고, 우수한 작업 정확성을 도모하여 시공품질을 향상시킬 수 있는 효과를 얻는다.According to the concrete embedded pre-installed rail anchor construction method for easy horizontal level adjustment according to the present invention, the horizontal level between rail anchors is adjusted and constructed using a guide rail, so the work is very simple and the air is minimized by rapid work progress. And, by promoting excellent work accuracy, the effect of improving construction quality is obtained.

뿐만 아니라 본 발명에 따른 수평 레벨 조정이 용이한 콘크리트 매립형 선설치 레일 앵커 시공공법은 상하 레일 간의 간격을 간격조절브라켓으로 연결 조절하면서 상호 간격을 맞춤 조정하게 시공하므로, 보다 신속한 시공으로 공기를 보다 단축하며 시설물의 구조적 시공 안정성을 보다 향상시킬 수 있는 효과가 있다.In addition, the concrete embedding type pre-installed rail anchor construction method for easy horizontal level adjustment according to the present invention is constructed so that the intervals between the upper and lower rails are connected and adjusted with a spacing adjustment bracket, so that the intervals are customized to be adjusted, so the construction time is shorter with faster construction And there is an effect that can further improve the structural construction stability of the facility.

도 1은 본 발명에 따른 일실시예를 나타내는 공정도.
도 2는 본 발명에 따른 일실시예를 나타내는 블록도.
도 3은 본 발명에 따른 일실시예를 나타내는 단면도.
도 4는 본 발명에 따른 일실시예를 나타내는 정면도.
1 is a process diagram showing an embodiment according to the present invention.
Figure 2 is a block diagram showing an embodiment according to the present invention.
3 is a cross-sectional view showing an embodiment according to the present invention.
Figure 4 is a front view showing an embodiment according to the present invention.

본 발명은 (a)콘크리트 구조물의 거푸집 중 시공 기준지점에서부터 레벨을 측량하되 전후로 제1레일홈 및 제2레일홈이 형성된 레일브라켓 중 상부레일브라켓의 위치를 맞춰 레벨을 측량하는 단계와; (b)횡 방향으로 연장 형성된 가이드레일을 상기 상부레일브라켓의 제2레일홈에 끼움 결합하여 서로 간격을 두고 위치한 상기 상부레일브라켓 간에 연결하여 수평 레벨을 맞춰 수정하는 단계와; (c)콘크리트 구조물의 거푸집 상에 수평 레벨이 조정된 상기 상부레일브라켓을 고정하는 단계와; (d)상기 상부레일브라켓의 하측에 간격을 두고 전후 제1레일홈 및 제2레일홈이 형성된 레일브라켓 중 하부레일브라켓을 콘크리트 구조물의 거푸집 상에 위치를 맞춰 레벨을 측량하되, 상기 상부레일브라켓과 상기 하부레일브라켓 간에 간격조절브라켓을 연결하여 간격을 조절하는 단계와; (e)횡 방향으로 연장 형성된 가이드레일을 상기 하부레일브라켓의 제2레일홈에 끼움 결합하여 서로 간격을 두고 위치한 상기 하부레일브라켓 간에 연결하여 수평 레벨을 맞춰 수정하는 단계와; (f)콘크리트 구조물의 거푸집 상에 간격 조절 및 수평 레벨이 조정된 상기 하부레일브라켓을 고정하는 단계;를 포함하는 수평 레벨 조정이 용이한 콘크리트 매립형 선설치 레일 앵커 시공공법을 기술구성의 특징으로 한다.The present invention includes the steps of: (a) measuring a level from a construction reference point in a formwork of a concrete structure, but measuring a level by aligning the position of the upper rail bracket among the rail brackets in which the first and second rail grooves are formed; (b) fitting a guide rail extending in a transverse direction into a second rail groove of the upper rail bracket and connecting the upper rail brackets located at a distance from each other to match the horizontal level; (c) fixing the upper rail bracket whose horizontal level is adjusted on the formwork of the concrete structure; (d) Measure the level by aligning the lower rail bracket on the formwork of the concrete structure among the rail brackets in which the front and rear first rail grooves and the second rail grooves are formed at an interval under the upper rail bracket, and the upper rail bracket Adjusting the distance by connecting the distance adjustment bracket between the lower rail bracket and the lower rail bracket; (e) fitting a guide rail extending in a transverse direction into a second rail groove of the lower rail bracket and connecting the lower rail brackets spaced apart from each other to match the horizontal level; (f) fixing the lower rail bracket with the adjustment of the spacing and the horizontal level on the formwork of the concrete structure; a concrete embedded pre-installation rail anchor construction method that is easy to adjust the horizontal level, including .

다음으로 본 발명에 따른 수평 레벨 조정이 용이한 콘크리트 매립형 선설치 레일 앵커 시공공법의 바람직한 실시예를 도면을 참조하여 상세하게 설명한다.Next, a preferred embodiment of the concrete embedding type pre-installation rail anchor construction method for easy horizontal level adjustment according to the present invention will be described in detail with reference to the drawings.

먼저 본 발명에 따른 수평 레벨 조정이 용이한 콘크리트 매립형 선설치 레일 앵커 시공공법의 일실시예는 도 1 및 도 2에 나타낸 바와 같이, (a)상부레일브라켓(10a)의 레벨을 측량하는 단계(S10)와, (b)상부레일브라켓(10a)의 레벨을 수정하는 단계(S20)와, (c)상부레일브라켓(10a)을 고정하는 단계(S30)와, (d)하부레일브라켓(10b)의 레벨 측량 및 간격을 조절하는 단계(S40)와, (e)하부레일브라켓(10b)의 레벨을 수정하는 단계(S50)와, (f)하부레일브라켓(10b)을 고정하는 단계(S60)를 포함하여 이루어진다.First, an embodiment of the concrete embedded pre-installation rail anchor construction method for easy horizontal level adjustment according to the present invention is as shown in Figs. 1 and 2, (a) measuring the level of the upper rail bracket (10a) ( S10), (b) correcting the level of the upper rail bracket (10a) (S20), (c) fixing the upper rail bracket (10a) (S30), and (d) the lower rail bracket (10b) ) Level measurement and adjusting the interval (S40), (e) correcting the level of the lower rail bracket (10b) (S50), and (f) fixing the lower rail bracket (10b) (S60) ), including.

상기 (a)단계(S10)에서는 교량 등 콘크리트 구조물을 시공하기 위하여 설치되는 거푸집(D)에 교량점검시설물(B)을 시공하기 위한 기초적인 지지 위치 즉 레일의 위치를 설정하도록 레일브라켓(10) 중 상부레일브라켓(10a)의 시공 레벨을 측량한다.In the step (a) (S10), the rail bracket (10) to set the basic support position for installing the bridge inspection facility (B) in the form (D) installed to construct a concrete structure such as a bridge, that is, the position of the rail. The construction level of the upper rail bracket 10a is measured.

상기에서 레일브라켓(10)에는 도 3 및 도 4에 나타낸 바와 같이, 상부레일브라켓(10a)과 하부레일브라켓(10b)을 구비하며, 상기 상부레일브라켓(10a)과 상기 하부레일브라켓(10b)은 서로 동일한 구조로 형성된 것으로서, 일정 길이를 갖으며 전후로 제1레일홈(12) 및 제2레일홈(14)이 형성된다.In the above, the rail bracket 10 includes an upper rail bracket 10a and a lower rail bracket 10b, as shown in FIGS. 3 and 4, and the upper rail bracket 10a and the lower rail bracket 10b Are formed in the same structure, and have a predetermined length, and a first rail groove 12 and a second rail groove 14 are formed in front and rear.

상기 레일브라켓(10)은 전후로 구분하여 고정부(11) 및 앵커부(13)를 구비토록 형성한다. 즉, 상기 레일브라켓(10)은 전방이 콘크리트 구조물(C)의 거푸집(D)에 대응하여 고정 설치되는 고정부(11)를 형성하며, 후방이 콘크리트 구조물(C)에 매립 가능한 레일고정수단(40)를 구비하는 앵커부(13)를 형성한다.The rail bracket 10 is divided into front and rear, and is formed to have a fixing portion 11 and an anchor portion 13. In other words, the rail bracket 10 forms a fixing part 11 that is fixedly installed at the front corresponding to the form D of the concrete structure C, and the rail fixing means capable of being embedded in the concrete structure C at the rear ( An anchor portion 13 having 40) is formed.

상기에서 레일브라켓(10)의 고정부(11)에는 교량점검시설물(B)의 고정을 위한 고정수단(F) 및 마스킹고무(도면에 미도시)가 끼움 결합할 수 있는 상기 제1레일홈(12)을 구비하며, 상기 앵커부(13)에는 레일고정수단(40)이 좌우 위치조정 가능하게 결합할 수 있는 제2레일홈(14)을 구비한다.In the above, the fixing means (F) for fixing the bridge inspection facility (B) and the masking rubber (not shown in the drawings) are fitted to the fixing part 11 of the rail bracket 10, the first rail groove ( 12), and the anchor part 13 includes a second rail groove 14 to which the rail fixing means 40 can be coupled so that the left and right positions can be adjusted.

상기 (a)단계(S10)에서는 복수의 상기 상부레일브라켓(10a)의 동일한 수평선상의 위치로 레벨을 측량하되 콘크리트 구조물(C)의 거푸집(D) 중 시공 기준지점에서부터 레벨을 측량하되, 교량점검시설물(B)을 시공할 위치로 상기 상부레일브라켓(10a)의 위치를 맞춰 레벨을 측량한다.In the step (a) (S10), the level is measured at the same horizontal position of the plurality of upper rail brackets 10a, but the level is measured from the construction reference point among the formwork (D) of the concrete structure (C), and the bridge is checked. The level is measured by aligning the position of the upper rail bracket 10a to the location where the facility (B) will be installed.

상기 (a)단계(S10)에서는 콘크리트 구조물(C)의 거푸집(D)에 대응하여 대면하는 상기 레일브라켓(10) 중 고정부(11)의 고정면에 자석(도면에 미도시)을 매설토록 구비하며, 자석의 자력을 이용하여 레벨 측량시 임시 부착 가능하게 시공하는 것도 가능하다.In the step (a) (S10), a magnet (not shown in the drawing) is buried on the fixing surface of the fixing part 11 of the rail brackets 10 that face in correspondence with the formwork D of the concrete structure (C). It is provided, and it is also possible to construct a temporary attachment during level measurement using the magnetic force of a magnet.

상기 (b)단계(S20)에서는 콘크리트 구조물(C)의 거푸집(D) 상에 횡 방향으로 서로 간격을 두고 위치한 상기 상부레일브라켓(10a)의 수평 레벨을 동일하게 맞춰 수정한다.In the step (b) (S20), the horizontal level of the upper rail bracket 10a located at a distance from each other in the transverse direction on the formwork D of the concrete structure C is adjusted to be the same.

상기 (b)단계(S20)에서 수평 레벨을 수정함에는 횡 방향으로 연장 형성된 가이드레일(20)을 사용한다. 즉, 상기 상부레일브라켓(10a) 간에 상기 가이드레일(20)을 연결하여 수평 레벨을 맞추되, 상기 가이드레일(20)을 상기 상부레일브라켓(10a)의 제2레일홈(14)에 끼움 결합하면서 동일한 수평선상에 복수의 상기 상부레일브라켓(10a)이 위치할 수 있게 조정하여 수정한다.To correct the horizontal level in step (b) (S20), a guide rail 20 extending in the transverse direction is used. That is, the guide rail 20 is connected between the upper rail brackets 10a to adjust the horizontal level, and the guide rail 20 is fitted into the second rail groove 14 of the upper rail bracket 10a. While correcting it by adjusting the plurality of upper rail brackets 10a to be positioned on the same horizontal line.

상기에서 가이드레일(20)은 상기 상부레일브라켓(10a)의 제2레일홈(14) 상에 슬라이딩 형태로 끼움 결합하여 연결한다.In the above, the guide rail 20 is fitted and connected in a sliding manner on the second rail groove 14 of the upper rail bracket 10a.

상기 (c)단계(S30)에서는 콘크리트 구조물(C)의 거푸집(D) 상에 수평 레벨이 조정된 상기 상부레일브라켓(10a)을 고정한다.In the step (c) (S30), the upper rail bracket 10a whose horizontal level is adjusted is fixed on the formwork (D) of the concrete structure (C).

상기에서 레일브라켓(10) 즉 상기 상부레일브라켓(10a)을 고정함에는 상기 고정부(11)에 형성된 고정홀에 피스 또는 리벳을 사용하여 고정한다.In the above, to fix the rail bracket 10, that is, the upper rail bracket 10a, a piece or rivet is used to fix the fixing hole formed in the fixing part 11.

상기 (d)단계에서는 선설치된 상기 상부레일브라켓(10a)마다 대응하여 상기 레일브라켓(10) 중 상기 하부레일브라켓(10b)의 레벨을 측량함과 동시에 상기 상부레일브라켓(10a)과의 설치 간격을 조절한다.In the step (d), the level of the lower rail bracket 10b among the rail brackets 10 is measured in correspondence with each of the previously installed upper rail brackets 10a, and the installation distance between the upper rail bracket 10a and the upper rail bracket 10a Adjust.

상기 (d)단계(S40)에서는 상기 상부레일브라켓(10a)의 하측에 대응하여 간격을 두고 상기 하부레일브라켓(10b)을 위치하되, 전후 제1레일홈(12) 및 제2레일홈(14)이 형성된 상기 하부레일브라켓(10b)을 콘크리트 구조물(C)의 거푸집(D) 상에 위치를 맞춰 레벨을 측량한다.In the step (d) (S40), the lower rail bracket 10b is positioned at an interval corresponding to the lower side of the upper rail bracket 10a, but the front and rear first rail grooves 12 and the second rail groove 14 The level is measured by aligning the lower rail bracket (10b) with) on the formwork (D) of the concrete structure (C).

상기 (d)단계(S40)에서는 콘크리트 구조물(C)의 거푸집(D)에 대응하여 대면하는 상기 레일브라켓(10) 중 고정부(11)의 고정면에 자석을 구비하며, 자석의 자력을 이용하여 레벨 측량시 임시 부착 가능하게 시공하는 것도 가능하다.In the step (d) (S40), a magnet is provided on the fixing surface of the fixing part 11 among the rail brackets 10 facing in response to the formwork (D) of the concrete structure (C), and the magnetic force of the magnet is used. Therefore, it is also possible to temporarily attach it during leveling.

상기 (d)단계(S40)에서는 상기 상부레일브라켓(10a)과 상기 하부레일브라켓(10b) 간에 간격조절브라켓(30)을 연결하여 간격을 조절한다.In the step (d) (S40), the distance adjustment bracket 30 is connected between the upper rail bracket 10a and the lower rail bracket 10b to adjust the distance.

상기 간격조절브라켓(30)은 상기 레일브라켓(10) 중 앵커부(13)에 대응하여 레일고정수단(40)과 함께 연결 설치한다.The spacing adjustment bracket 30 is connected and installed together with the rail fixing means 40 corresponding to the anchor part 13 of the rail bracket 10.

상기에서 간격조절브라켓(30)에는 도 4에 나타낸 바와 같이, 일정간격을 두고 복수 개의 간격조절공(31)을 구비하고, 복수 개의 상기 간격조절공(31)에 상기 레일브라켓(10) 즉 상기 상부레일브라켓(10a)과 상기 하부레일브라켓(10b)을 끼움 결합하여 상기 상부레일브라켓(10a) 및 상기 하부레일브라켓(10b) 간에 상하 간격을 조절 설정한다.In the above, as shown in Fig. 4, the spacing adjustment bracket 30 includes a plurality of spacing adjusting holes 31 at regular intervals, and the rail bracket 10, that is, the plurality of spacing adjusting holes 31, The upper rail bracket (10a) and the lower rail bracket (10b) are fitted and coupled to adjust the vertical gap between the upper rail bracket (10a) and the lower rail bracket (10b).

상기 간격조절브라켓(30)에는 콘크리트 구조물(C)의 거푸집(D)에 대응하여 일측으로 연장된 고정자석(33)을 구비한다.The spacing adjustment bracket 30 is provided with a fixed magnet 33 extending to one side corresponding to the formwork (D) of the concrete structure (C).

상기 (d)단계(S40)에서는 상기 상부레일브라켓(10a) 및 상기 하부레일브라켓(10b) 간에 간격을 조절할 때 상기 고정자석(33)의 자력을 이용하여 거푸집(D)에 상기 간격조절브라켓(30)을 임시로 부착 고정한다.In step (d) (S40), when adjusting the gap between the upper rail bracket 10a and the lower rail bracket 10b, the gap adjusting bracket (D) is attached to the formwork using the magnetic force of the fixed magnet 33. 30) is temporarily attached and fixed.

상기에서 레일브라켓(10) 간에 상기 간격조절브라켓(30)을 연결함에는 상하 간격을 두고 배치된 상기 레일브라켓(10)에 레일고정수단(40)을 설치한다.In the above, when connecting the distance adjustment brackets 30 between the rail brackets 10, the rail fixing means 40 are installed on the rail brackets 10 arranged at a vertical distance.

상기 레일고정수단(40)은 상기 레일브라켓(10)의 제2레일홈(14) 내 고정너트(41)를 설치한다.The rail fixing means 40 installs a fixing nut 41 in the second rail groove 14 of the rail bracket 10.

상기 고정너트(41)는 상기 제2레일홈(14) 내 삽입한 후 좌우 위치 조정한다.상기에서 레일브라켓(10)에는 좌우 간격을 두고 설치하되 상기 제2레일홈(14)을 향해 돌출 형성하여 상기 고정너트(41)의 좌우 위치 조정 가능한 영역을 조성토록 지지하는 스토퍼나사(45)를 구성하므로, 콘크리트 구조물의 철근에 따른 간섭을 피해 레일고정수단(40)을 설치 가능하면서 고정너트(41)의 이탈을 방지하는 것이 가능하다.The fixing nut 41 is inserted into the second rail groove 14 and then adjusted to its left and right position. In the above, the rail bracket 10 is installed at left and right intervals, but protrudes toward the second rail groove 14 Thus, since the stopper screw 45 is configured to support the region in which the left and right positions of the fixing nut 41 can be adjusted, it is possible to install the rail fixing means 40 to avoid interference due to the reinforcement of the concrete structure, while the fixing nut 41 ) It is possible to prevent the deviation.

상기 레일고정수단(40)을 설치함에는 상기 고정너트(41)에 대응하여 고정볼트(43)를 결합 설치하여 고정한다. When the rail fixing means 40 is installed, the fixing bolt 43 is coupled and fixed in correspondence with the fixing nut 41.

이때, 종래 레일고정수단(40)은 볼트의 머리부(예 : 사각형의 머리부)를 별도로 제작하여 상기 머리부를 제2레일홈(14)에 슬라이드 삽입하여 사용하였으나, 상기 볼트의 머리부를 별도로 제작하여야 하는 번거로움과 비용의 증가문제가 있었다.At this time, in the conventional rail fixing means 40, the head of the bolt (for example, a square head) was separately manufactured and used by sliding the head into the second rail groove 14, but the head of the bolt was separately manufactured. There was a problem of an increase in the hassle and cost that had to be done.

본 발명에서는 이를 해결하기 위해, 상기 고정너트(41)는 일반적으로 널리 사용되는 너트이고, 상기 고정볼트(43)는 일반적으로 널리 사용되는 볼트머리 달린 볼트를 사용하는 것을 특징으로 하며, 이로 인해 상기 레일고정수단(40)을 별도로 제작하지 않는 장점이 있게 된다.In the present invention, in order to solve this, the fixing nut 41 is a nut that is generally widely used, and the fixing bolt 43 is characterized by using a generally widely used bolt-headed bolt. There is an advantage in that the rail fixing means 40 is not separately manufactured.

상기 (e)단계(S50)에서는 콘크리트 구조물(C)의 거푸집(D) 상에 상기 상부레일브라켓(10a)의 하측에 간격을 두고 위치하되, 횡 방향으로 서로 간격을 두고 위치한 상기 하부레일브라켓(10b)의 수평 레벨을 동일하게 맞춰 수정한다.In the (e) step (S50), the lower rail brackets are positioned at intervals below the upper rail brackets 10a on the formwork D of the concrete structure C, but are spaced apart from each other in the transverse direction. Adjust the horizontal level in 10b) to be the same.

상기 (e)단계(S50)에서도 상기 (b)단계(S20)와 마찬가지로 수평 레벨을 수정할 때 횡 방향으로 연장 형성된 가이드레일(20)을 사용한다. 즉, 상기 하부레일브라켓(10b) 간에 상기 가이드레일(20)을 연결하여 수평 레벨을 맞추되, 상기 가이드레일(20)을 상기 하부레일브라켓(10b)의 제2레일홈(14)에 끼움 결합하면서 동일한 수평선상에 복수의 상기 상부레일브라켓(10a)이 위치할 수 있게 조정하여 수정하다.In step (e) (S50) as well as in step (b) (S20), a guide rail 20 extending in the transverse direction is used when correcting the horizontal level. That is, the guide rail 20 is connected between the lower rail brackets 10b to achieve a horizontal level, and the guide rail 20 is fitted into the second rail groove 14 of the lower rail bracket 10b. While adjusting so that the plurality of upper rail brackets 10a can be positioned on the same horizontal line, the correction is made.

상기 (f)단계(S60)에서는 콘크리트 구조물(C)의 거푸집(D) 상에 상하 간격 조절 및 수평 레벨이 조정된 상기 하부레일브라켓(10b)을 고정한다.In the step (f) (S60), the lower rail bracket 10b whose vertical spacing and horizontal level are adjusted is fixed on the formwork (D) of the concrete structure (C).

상기에서 레일브라켓(10) 즉 상기 하부레일브라켓(10b)을 고정함에는 상기 고정부(11)에 형성된 고정홀에 피스 또는 리벳을 사용하여 고정한다.In the above, to fix the rail bracket 10, that is, the lower rail bracket 10b, a piece or rivet is used to fix the fixing hole formed in the fixing part 11.

아울러, 상기 고정된 상기 하부레일브라켓(10b)도 레일고정수단(40)을 설치하며, 상기 (d)단계와 동일하게 상기 고정너트(41)는 상기 제2레일홈(14) 내 삽입한 후 좌우 위치 조정한다. 상기에서 레일브라켓(10)에는 좌우 간격을 두고 설치하되 상기 제2레일홈(14)을 향해 돌출 형성하여 상기 고정너트(41)의 좌우 위치 조정 가능한 영역을 조성토록 지지하는 스토퍼나사(45)를 구성하므로, 콘크리트 구조물의 철근에 따른 간섭을 피해 레일고정수단(40)을 설치 가능하면서 고정너트(41)의 이탈을 방지하는 것이 가능하다.In addition, the fixed lower rail bracket (10b) is also provided with a rail fixing means (40), and the fixing nut (41) is inserted into the second rail groove (14) in the same manner as in step (d) Adjust the left and right position. In the above, the rail bracket 10 is installed at left and right intervals, but protruding toward the second rail groove 14, and a stopper screw 45 supporting the fixing nut 41 to form an adjustable left and right position of the fixing nut 41 is provided. Therefore, it is possible to prevent the separation of the fixing nut 41 while it is possible to install the rail fixing means 40 to avoid interference due to the reinforcement of the concrete structure.

상기 레일고정수단(40)을 설치함에는 상기 고정너트(41)에 대응하여 고정볼트(43)를 결합 설치하여 고정한다. When the rail fixing means 40 is installed, the fixing bolt 43 is coupled and fixed in correspondence with the fixing nut 41.

이후, 상기 상부레일브라켓(10a) 및 하부레일브라켓(10b)이 고정되고, 상기 레일고정수단(40)을 설치가 완료되며, 거푸집에 콘크리트를 타설하고 양생한 후, 거푸집을 제거하여 전면에 제1레일홈(12)이 노출되도록하고 상기 제1레일홈(12)에 교량점검로 등의 부착구조물이 부착되도록 구성되며, 이러한 부착구조물은 다양한 형태로 상세한 설명은 생략한다.Thereafter, the upper rail bracket (10a) and the lower rail bracket (10b) are fixed, and the rail fixing means (40) is installed. After concrete is poured into the formwork and cured, the formwork is removed to prepare the front surface. 1 The rail groove 12 is exposed and an attachment structure such as a bridge inspection path is attached to the first rail groove 12, and detailed descriptions of such attachment structures are omitted in various forms.

상기와 같이 구성되는 본 발명에 따른 수평 레벨 조정이 용이한 콘크리트 매립형 선설치 레일 앵커 시공공법에 의하면, 가이드레일을 이용하여 레일 앵커 간의 수평 레벨을 맞춤 조정하며 시공하므로, 작업이 매우 간편함은 물론 신속한 작업진행으로 공기를 최소화하고, 우수한 작업 정확성을 도모하여 시공품질을 향상시키는 것이 가능하다.According to the concrete embedded pre-installed rail anchor construction method for easy horizontal level adjustment according to the present invention configured as described above, the horizontal level between rail anchors is adjusted and constructed using a guide rail, so the operation is very simple and quick. It is possible to improve construction quality by minimizing work progress and promoting excellent work accuracy.

뿐만 아니라 본 발명은 상하 레일 간의 간격을 간격조절브라켓으로 연결 조절하면서 상호 간격을 맞춤 조정하게 시공하므로, 보다 신속한 시공으로 공기를 보다 단축하며 시설물의 구조적 시공 안정성을 보다 향상시키는 것이 가능하다.In addition, according to the present invention, since the space between the upper and lower rails is connected and adjusted with a gap adjustment bracket, the space is customized to each other, so it is possible to shorten the construction period and improve the structural construction stability of the facility through a faster construction.

상기에서는 본 발명에 따른 수평 레벨 조정이 용이한 콘크리트 매립형 선설치 레일 앵커 시공공법의 바람직한 실시예에 대하여 설명하였지만, 본 발명은 이에 한정되는 것이 아니고 특허청구범위와 발명의 명세서 및 첨부한 도면의 범위 안에서 여러 가지로 변형하여 실시하는 것이 가능하고, 이 또한 본 발명의 범위에 속한다.In the above, a preferred embodiment of the concrete-embedded pre-installed rail anchor construction method for easy horizontal level adjustment according to the present invention has been described, but the present invention is not limited thereto, and the scope of the claims, the specification of the invention, and the accompanying drawings It is possible to carry out various modifications within, and this also falls within the scope of the present invention.

10 : 레일브라켓 10a : 상부레일브라켓
10b : 하부레일브라켓 11 : 고정부
12 : 제1레일홈 13 : 앵커부
14 : 제2레일홈 20 : 가이드레일
30 : 간격조절브라켓 31 : 간격조절공
33 : 고정자석 40 : 레일고정수단
41 : 고정너트 43 : 고정볼트
45 : 스토퍼나사
10: Rail bracket 10a: Upper rail bracket
10b: lower rail bracket 11: fixed part
12: first rail groove 13: anchor part
14: second rail groove 20: guide rail
30: gap adjustment bracket 31: gap adjustment hole
33: fixed magnet 40: rail fixing means
41: fixing nut 43: fixing bolt
45: stopper screw

Claims (7)

(a) 콘크리트 구조물의 거푸집 중 시공 기준지점에서부터 레벨을 측량하되 전후로 제1레일홈 및 제2레일홈이 형성된 레일브라켓 중 상부레일브라켓의 위치를 맞춰 레벨을 측량하는 단계와;
(b) 횡 방향으로 연장 형성된 가이드레일을 상기 상부레일브라켓의 제2레일홈에 끼움 결합하여 서로 간격을 두고 위치한 상기 상부레일브라켓 간에 연결하여 수평 레벨을 맞춰 수정하는 단계와;
(c) 콘크리트 구조물의 거푸집 상에 수평 레벨이 조정된 상기 상부레일브라켓을 고정하는 단계와;
(d) 상기 상부레일브라켓의 하측에 간격을 두고 전후 제1레일홈 및 제2레일홈이 형성된 레일브라켓 중 하부레일브라켓을 콘크리트 구조물의 거푸집 상에 위치를 맞춰 레벨을 측량하되, 상기 상부레일브라켓과 상기 하부레일브라켓 간에 간격조절브라켓을 연결하여 간격을 조절하는 단계와;
(e) 횡 방향으로 연장 형성된 가이드레일을 상기 하부레일브라켓의 제2레일홈에 끼움 결합하여 서로 간격을 두고 위치한 상기 하부레일브라켓 간에 연결하여 수평 레벨을 맞춰 수정하는 단계와;
(f) 콘크리트 구조물의 거푸집 상에 간격 조절 및 수평 레벨이 조정된 상기 하부레일브라켓을 고정하는 단계;를 포함하여 이루어지고,
상기 (d)단계에서 상기 간격조절브라켓을 연결함에는, 상기 레일브라켓에 레일고정수단을 설치하되, 상기 레일브라켓의 제2레일홈 내 고정너트를 설치하여 좌우 위치 조정한 후, 상기 고정너트에 대응하여 고정볼트를 결합 설치하여 고정하는 수평 레벨 조정이 용이한 콘크리트 매립형 선설치 레일 앵커 시공공법.
(a) measuring the level from the construction reference point in the formwork of the concrete structure, but measuring the level by aligning the position of the upper rail bracket among the rail brackets in which the first and second rail grooves are formed;
(b) fitting a guide rail extending in the transverse direction into a second rail groove of the upper rail bracket and connecting the upper rail brackets located at a distance from each other to match the horizontal level;
(c) fixing the upper rail bracket whose horizontal level is adjusted on the formwork of the concrete structure;
(d) Measure the level by aligning the lower rail bracket on the formwork of the concrete structure among the rail brackets in which the front and rear first rail grooves and the second rail grooves are formed at an interval under the upper rail bracket, and the upper rail bracket Adjusting the distance by connecting the distance adjustment bracket between the lower rail bracket and the lower rail bracket;
(e) fitting a guide rail extending in the transverse direction into a second rail groove of the lower rail bracket and connecting the lower rail brackets spaced apart from each other to match the horizontal level;
(f) fixing the lower rail bracket with the adjusted spacing and horizontal level on the formwork of the concrete structure; and
In the step (d), when connecting the gap adjustment bracket, a rail fixing means is installed on the rail bracket, and a fixing nut in the second rail groove of the rail bracket is installed to adjust the left and right positions, and then to the fixing nut. A concrete embedded pre-installed rail anchor construction method that facilitates horizontal level adjustment by combining and installing fixing bolts in response.
청구항 1에 있어서,
상기 (a)단계 및 상기 (d)단계에서는, 콘크리트 구조물의 거푸집에 대응하여 대면하는 상기 레일브라켓의 고정면에 자석의 자력을 이용하여 레벨 측량시 임시 부착하는 수평 레벨 조정이 용이한 콘크리트 매립형 선설치 레일 앵커 시공공법.
The method according to claim 1,
In the above (a) and (d) steps, a concrete embedded line that is easily attached to the horizontal level temporarily attached during level measurement using the magnetic force of a magnet on the fixed surface of the rail bracket that faces in response to the formwork of the concrete structure. Installation rail anchor construction method.
청구항 1에 있어서,
상기 (c)단계 및 상기 (f)단계에서는, 상기 레일브라켓의 고정부에 형성된 고정홀에 피스 또는 리벳으로 고정하는 수평 레벨 조정이 용이한 콘크리트 매립형 선설치 레일 앵커 시공공법.
The method according to claim 1,
In the (c) and (f) steps, a concrete embedded pre-installed rail anchor construction method for easy horizontal level adjustment of fixing with pieces or rivets in the fixing hole formed in the fixing part of the rail bracket.
청구항 1에 있어서,
상기 (d)단계에서는, 상기 간격조절브라켓에 형성된 복수 개의 간격조절공에 상기 레일브라켓을 끼움 결합하여 상기 상부레일브라켓 및 상기 하부레일브라켓 간에 상하 간격을 조절 설정하는 수평 레벨 조정이 용이한 콘크리트 매립형 선설치 레일 앵커 시공공법.
The method according to claim 1,
In the step (d), the rail bracket is inserted into a plurality of space adjustment holes formed in the space adjustment bracket to adjust the vertical distance between the upper rail bracket and the lower rail bracket. Pre-installed rail anchor construction method.
청구항 4에 있어서,
상기 (d)단계에서는, 상기 상부레일브라켓 및 상기 하부레일브라켓 간에 간격을 조절할 때 거푸집에 대응하여 연장된 상기 간격조절브라켓의 고정자석에 의한 자력을 이용하여 상기 간격조절브라켓을 임시로 부착 고정하는 수평 레벨 조정이 용이한 콘크리트 매립형 선설치 레일 앵커 시공공법.
The method of claim 4,
In the step (d), when adjusting the gap between the upper rail bracket and the lower rail bracket, the gap adjusting bracket is temporarily attached and fixed using magnetic force by a fixed magnet of the gap adjusting bracket extended in response to a formwork. Concrete embedded pre-installed rail anchor construction method for easy horizontal level adjustment.
삭제delete 제1항에 있어서,
상기 레일브라켓에는 좌우 간격을 두고 설치하되 상기 제2레일홈을 향해 돌출 형성하여 콘크리트 구조물의 철근에 따른 간섭을 피해 상기 레일고정수단을 설치 가능하도록 상기 고정너트의 좌우 위치 조정 가능한 영역을 조성하고, 상기 고정너트의 이탈을 방지하는 스토퍼나사를 구성하는 수평 레벨 조정이 용이한 콘크리트 매립형 선설치 레일 앵커 시공공법.
The method of claim 1,
The rail bracket is installed at left and right intervals, but protrudes toward the second rail groove to form a region capable of adjusting the left and right positions of the fixing nut so that the rail fixing means can be installed avoiding interference due to the reinforcement of the concrete structure, Concrete embedded pre-installed rail anchor construction method for easy horizontal level adjustment constituting a stopper screw that prevents separation of the fixing nut.
KR1020200096089A 2020-07-31 2020-07-31 Concrete Embedded Rail Anchor Construction Method for Adjusting a Horizontal Level Easily KR102202853B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020200096089A KR102202853B1 (en) 2020-07-31 2020-07-31 Concrete Embedded Rail Anchor Construction Method for Adjusting a Horizontal Level Easily

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020200096089A KR102202853B1 (en) 2020-07-31 2020-07-31 Concrete Embedded Rail Anchor Construction Method for Adjusting a Horizontal Level Easily

Publications (1)

Publication Number Publication Date
KR102202853B1 true KR102202853B1 (en) 2021-01-14

Family

ID=74141420

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020200096089A KR102202853B1 (en) 2020-07-31 2020-07-31 Concrete Embedded Rail Anchor Construction Method for Adjusting a Horizontal Level Easily

Country Status (1)

Country Link
KR (1) KR102202853B1 (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200206699Y1 (en) 2000-05-15 2000-12-15 주식회사로드맥스 엔지니어링 Fixation Device for Mounting Checking Plate in a Bent
JP2003247241A (en) * 2002-02-26 2003-09-05 Sumitomo Forestry Co Ltd Installation method for foundation packing material
KR100707685B1 (en) 2004-10-23 2007-04-17 이근식 A embeded anchor with socket nut
KR20100037696A (en) 2008-10-02 2010-04-12 이근식 A embeded anchor
KR102107939B1 (en) * 2019-08-19 2020-05-28 김기종 Magnetic type embeded anchor

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200206699Y1 (en) 2000-05-15 2000-12-15 주식회사로드맥스 엔지니어링 Fixation Device for Mounting Checking Plate in a Bent
JP2003247241A (en) * 2002-02-26 2003-09-05 Sumitomo Forestry Co Ltd Installation method for foundation packing material
KR100707685B1 (en) 2004-10-23 2007-04-17 이근식 A embeded anchor with socket nut
KR20100037696A (en) 2008-10-02 2010-04-12 이근식 A embeded anchor
KR102107939B1 (en) * 2019-08-19 2020-05-28 김기종 Magnetic type embeded anchor

Similar Documents

Publication Publication Date Title
KR102108417B1 (en) magnetic type jig for anchor bolt installation for facility construction of concrete structure and method of construction concrete structure using the jig
JP4732915B2 (en) Foundation construction method and device, and anchor bolt support device for construction
JP4738886B2 (en) Equipment foundation
KR101848727B1 (en) Joint structure for PC column and joining method using the same
US20050246981A1 (en) Device for, and method of, supporting a glass panel for forming a frameless glass panel fence
KR20110128396A (en) Pre-embedded anchor frame equipped with coupler and anchoring method of steel column thereof
JP4915653B2 (en) Anchor bolt positioning jig
KR102202853B1 (en) Concrete Embedded Rail Anchor Construction Method for Adjusting a Horizontal Level Easily
KR101990065B1 (en) Joint of PC column using steel block
CN110067257B (en) Column base anchor bolt device and using method thereof
KR102320545B1 (en) Reinforcing rod fixing system for pricast concrete column
CN106930406A (en) A kind of preparation method of Anchor Bolts in Steel Column Bases positioning structure
KR101627159B1 (en) Concrete placing leveler and installing jig thereof
KR20120078217A (en) Block out construction method for apparatus base
JPH0138947B2 (en)
AU2021103095A4 (en) Channel installation frame and method
JPH01278620A (en) Installation method for anchor bolt and anchor bolt supporting device used therefor
JP6427814B2 (en) Tunnel construction method, invert construction method, and formwork apparatus
CN216194782U (en) Steel pipe column positioning system
CN217356170U (en) Direct-buried foundation bolt mounting part
KR101426650B1 (en) Forming Structure of Building Frame
EP1651826B1 (en) Formwork fixing and method
KR102186078B1 (en) A method of construction for bridge abutment using concrete retaining wall
JP5291643B2 (en) How to build a wall
JPH0532536B2 (en)

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant