KR102116934B1 - Pressurized type Pre-embedded Anchor by Pressurized for Bridge Inspection Facility and Method for constructing this same - Google Patents

Pressurized type Pre-embedded Anchor by Pressurized for Bridge Inspection Facility and Method for constructing this same Download PDF

Info

Publication number
KR102116934B1
KR102116934B1 KR1020190024183A KR20190024183A KR102116934B1 KR 102116934 B1 KR102116934 B1 KR 102116934B1 KR 1020190024183 A KR1020190024183 A KR 1020190024183A KR 20190024183 A KR20190024183 A KR 20190024183A KR 102116934 B1 KR102116934 B1 KR 102116934B1
Authority
KR
South Korea
Prior art keywords
base plate
fixing
formwork
bolt
coupler
Prior art date
Application number
KR1020190024183A
Other languages
Korean (ko)
Inventor
윤종희
조현모
Original Assignee
현빈개발 주식회사
누리이앤씨(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 현빈개발 주식회사, 누리이앤씨(주) filed Critical 현빈개발 주식회사
Priority to KR1020190024183A priority Critical patent/KR102116934B1/en
Application granted granted Critical
Publication of KR102116934B1 publication Critical patent/KR102116934B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/10Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
    • E01D19/106Movable inspection or maintenance platforms, e.g. travelling scaffolding or vehicles specially designed to provide access to the undersides of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16BDEVICES FOR FASTENING OR SECURING CONSTRUCTIONAL ELEMENTS OR MACHINE PARTS TOGETHER, e.g. NAILS, BOLTS, CIRCLIPS, CLAMPS, CLIPS OR WEDGES; JOINTS OR JOINTING
    • F16B37/00Nuts or like thread-engaging members
    • F16B37/04Devices for fastening nuts to surfaces, e.g. sheets, plates

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to a pressurized pre-embedded anchor for fixing a bridge inspection facility, and a construction method thereof which ensures stability due to pre-embedding thereof by fixing the pre-embedded anchor using a form and rebars during bridge construction, and which fixes the pre-embedded anchor by a simple operation without damage to the form and the rebars. The pressurized pre-embedded anchor for fixing a bridge inspection facility comprises: a coupler assembly which includes a base plate (10) having at least one anchor bolt through-hole and is supported by the pouring surface of the form, and a nut-type coupler (20) having an anchor bolt fastening portion passing through the anchor bolt through-hole of the base plate, and fixed to the base plate; and a pressure assembly for fixing the coupler assembly by bringing the same into contact with the form using, as a support base, the rebars arranged inside the form. The pressure assembly includes: a pressure bolt (30) having a front end supported by the base plate of the coupler assembly; and a pressure plate (40) which is screw-fastened to the pressure bolt and pressurizes and supports the coupler assembly against the form through the pressure bolt by being supported by the rebars while being moved to the rebars by the fastening of the pressure bolt.

Description

교량 점검시설 고정용 가압식 선매립 앵커 및 이의 시공 방법{Pressurized type Pre-embedded Anchor by Pressurized for Bridge Inspection Facility and Method for constructing this same}Pressurized type Pre-embedded Anchor by Pressurized for Bridge Inspection Facility and Method for constructing this same}

본 발명은 교량 점검시설 고정용 앵커에 관한 것으로, 더욱 상세하게는 교량의 시공 시 거푸집과 철근을 이용하여 선매립 앵커를 고정함으로써 선매립으로 인한 안정성을 확보하고 거푸집과 철근의 손상없이 간단한 조작으로 고정하는 교량 점검시설 고정용 가압식 선매립 앵커 및 이의 시공 방법에 관한 것이다.The present invention relates to an anchor for fixing a bridge inspection facility, and more specifically, to secure stability due to line reclamation by fixing the line reclamation anchor using formwork and rebar during construction of the bridge, and by simple operation without damaging the formwork and rebar. It relates to a pressurized pre-embedded anchor for fixing a bridge inspection facility to be fixed and a construction method therefor.

이 부분은 본 출원 내용과 관련된 배경 정보를 제공할 뿐 반드시 선행기술이 되는 것은 아니다.This part provides background information related to the contents of the present application, but is not necessarily prior art.

일반적으로 교량의 유지 관리(예를 들어 교각 상부에 설치되어 교량을 지지하는 슈의 점검)를 위하여 교량 점검 시설이 적용된다.Generally, a bridge inspection facility is applied for maintenance of the bridge (for example, inspection of a shoe installed on the bridge top to support the bridge).

상기 교량 점검 시설은 교량 슬래브를 출입하기 위한 출입부, 교각으로 내려가기 위한 계단부 및 교각의 둘레를 따라 통로를 제공하는 점검로 등으로 구성되며, 앵커를 통해 교량에 고정 설치된다.The bridge inspection facility is composed of an entrance for entering and exiting the bridge slab, a step for descending to the pier, and an inspection path providing a passage along the perimeter of the pier, and is fixedly installed on the bridge through the anchor.

교량 점검 시설의 고정을 위한 앵커 방식은 예를 들어, 교량에 앵커홈을 형성한 후 기계(쐐기식)식 앵커볼트를 체결하는 기계식 앵커, 앵커홀에 화학제품을 충진하여 앵커볼트를 고정하는 케미컬 앵커, 교량의 콘크리트 시공 시 커플러를 매립하고 상기 커플러에 앵커볼트를 체결하는 선매립 앵커 등이 있다.An anchor method for fixing a bridge inspection facility is, for example, a mechanical anchor that forms an anchor groove on a bridge and then tightens a mechanical (wedge) anchor bolt, and a chemical that fills an anchor hole with chemicals to fix the anchor bolt. An anchor, a pre-embedded anchor, etc., which fills a coupler during concrete construction of a bridge and fastens an anchor bolt to the coupler.

특허문헌(등록특허 제10-0707685호)은 선매립 앵커로서, 일 측의 단부에는 앵커헤드가 형성되고 다른 단부는 소켓너트에 고정되는 앵커부재와, 상기 앵커부재와 일 측 단부가 결합되고 다른 단부는 너트형 나사산이 형성되어 볼트고정부를 형성하는 소켓너트와, 상기 소켓너트 다수개가 소켓너트의 너트형 나사산이 형성된 볼트고정부 단부에 소정의 형상과 넓이를 가지며 상기 소켓너트의 볼트고정부 단부에 대응하여 볼트구멍이 형성되며 임시고정용 리벳구멍을 추가로 다수 개 형성하는 판부재와 고정되며, 상기 판부재를 거푸집에 일시적으로 고정하는 임시고정리벳, 상기 소켓너트의 볼트고정부 위치에 맞게 부착물을 고정하면서 조립되는 부착용볼트로 구성되며, 임시고정리벳을 이용하여 거푸집에 고정하기 때문에 거푸집의 손상으로 거푸집의 재사용이 어렵고 임시고정리벳에 의한 거푸집의 고정 작업과 임시고정리벳의 제거 작업이 반드시 필요하므로 시공성이 떨어지는 문제점이 있다. Patent document (registration patent No. 10-0707685) is a pre-embedded anchor, an anchor head is formed at one end, and an anchor member is fixed to the socket nut at the other end, and the anchor member and one end are coupled to each other. The end is a socket nut having a nut-shaped thread formed to form a bolt fixing portion, and the plurality of socket nuts has a predetermined shape and width at an end of the bolt fixing portion having a nut-shaped thread of the socket nut, and the bolt fixing portion of the socket nut. A bolt hole is formed corresponding to the end, and is fixed with a plate member forming a plurality of additional rivet holes for temporary fixing. It is composed of attachment bolts that are assembled while fixing the attachments properly. Since it is fixed to the formwork using a temporary fixing rivet, it is difficult to reuse the formwork due to damage to the formwork, and the fixing work of the formwork by the temporary fixing rivet and the removal of the temporary fixation rivet Since it is necessary, there is a problem in that the workability is poor.

등록특허 제10-0792434호Registered Patent No. 10-0792434 등록특허 제10-0707685호Registered Patent No. 10-0707685

본 발명은 전술한 바와 같은 문제점을 해결하기 위한 것으로, 교량의 시공 시 거푸집과 철근을 이용하여 선매립 앵커를 고정함으로써 선매립으로 인한 안정성을 확보하고 거푸집과 철근의 손상없이 간단한 조작으로 고정하는 교량 점검시설 고정용 가압식 선매립 앵커 및 이의 시공 방법을 제공하려는데 그 목적이 있다. The present invention is to solve the problems as described above, by securing the stability due to the pre-embedment by fixing the pre-embedding anchor using the formwork and rebar during the construction of the bridge and fixed by a simple operation without damaging the formwork and rebar The purpose is to provide a pressurized pre-embedded anchor for fixing the inspection facility and a construction method therefor.

본 발명에 의한 교량 점검시설 고정용 가압식 선매립 앵커는, 하나 이상의 앵커볼트 관통홀이 구비되며 거푸집의 타설면에 지지되는 기초판 및 상기 기초판의 앵커볼트 관통홀과 통하는 앵커볼트 체결부가 구비되며 상기 기초판에 고정되는 너트형의 커플러로 이루어지는 커플러 조립체와; 상기 거푸집의 안쪽에 배근되는 철근을 지지기반으로 하여 상기 커플러 조립체를 상기 거푸집에 밀착시켜 고정하는 가압 조립체를 포함하며, 교량의 콘크리트 타설로 교량 안에 매립 설치된다.The pressurized pre-embedded anchor for fixing the bridge inspection facility according to the present invention is provided with at least one anchor bolt through hole, and is provided with a base plate supported on the pouring surface of the formwork and an anchor bolt fastening part communicating with the anchor bolt through hole of the base plate. A coupler assembly comprising a nut-shaped coupler fixed to the base plate; It includes a pressing assembly for fixing the coupler assembly in close contact with the formwork on the basis of a reinforcing bar reinforced on the inside of the formwork, and is embedded in the bridge by pouring concrete into the bridge.

본 발명은 상기 기초판의 가장자리를 통해 거푸집과 기초판 사이에 물이 침투하는 것을 막기 위한 차수판이 더 포함되는 것을 특징으로 한다.The present invention is characterized in that it further comprises a water shield plate for preventing water from penetrating between the formwork and the base plate through the edge of the base plate.

상기 차수판은 자석의 자력으로 거푸집(철제 거푸집)에 부착된다.The water plate is attached to the formwork (iron formwork) by the magnetic force of the magnet.

본 발명에 의한 교량 점검시설 고정용 가압식 선매립 앵커 및 이의 시공 방법에 의하면, 너트형의 커플러를 교량의 시공 시 함께 시공하여 콘크리트 안에 매립함으로써 이탈의 위험을 없애 교량 점검 시설의 시공 강도를 높이는 효과가 있고, 또한, 거푸집에 구멍을 천공하는 등의 손상없이 가압 조립체를 이용한 가압 방식으로 커플러를 설치하여 거푸집의 내구성 유지와 재사용의 이점 및 시공성 향상의 효과가 있다.According to the pressurized pre-embedding anchor for fixing the bridge inspection facility according to the present invention and its construction method, the nut-type coupler is installed together during the construction of the bridge and embedded in concrete to eliminate the risk of departure, thereby increasing the construction strength of the bridge inspection facility There is also, there is an advantage of maintaining the durability and reuse of the formwork and improving the workability by installing the coupler in a pressurized manner using a pressing assembly without damage such as drilling a hole in the formwork.

그리고, 차수판을 통해 거푸집과 기초판 사이를 수밀하게 조성하여 기초판과 커플러의 이탈, 커플러의 막힘 등 손상을 방지하여 앵커의 내구성을 향상하는 효과가 있다.In addition, there is an effect of improving the durability of the anchor by preventing damage such as separation of the base plate and the coupler and clogging of the coupler by tightly forming the formwork and the base plate through the water shield plate.

또한, 본 발명은 별도의 간격유지장치를 사용하지 않고 거푸집과 철근 사이의 간격을 유지하는 것도 가능하여 간격유지장치의 설치를 위한 자재와 작업이 없어지므로 추가적인 시공성 향상과 비용 절감 효과가 있다.In addition, the present invention is possible to maintain the gap between the formwork and the reinforcing bar without using a separate gap maintaining apparatus, so there is no material and work for the installation of the gap maintaining apparatus, thereby improving additional workability and reducing costs.

도 1은 본 발명의 실시예 1에 의한 교량 점검시설 고정용 가압식 선매립 앵커의 분해 사시도.
도 2는 본 발명의 실시예 1에 의한 교량 점검시설 고정용 가압식 선매립 앵커의 설치 상태 측면도.
도 3은 본 발명의 실시예 1에 의한 교량 점검시설 고정용 가압식 선매립 앵커의 설치 상태 정면도.
도 4는 본 발명의 실시예 1에 의한 교량 점검시설 고정용 가압식 선매립 앵커의 시공 공정도.
도 5는 본 발명의 실시예 2에 의한 교량 점검시설 고정용 가압식 선매립 앵커의 설치 상태 측면도.
도 6은 본 발명에 의한 교량 점검시설 고정용 가압식 선매립 앵커가 적용된 교량점검시설의 시공 상태 도면.
1 is an exploded perspective view of a pressurized pre-embedded anchor for fixing a bridge inspection facility according to a first embodiment of the present invention.
Figure 2 is a side view of the installation state of the pressure-type pre-embedded anchor for fixing the bridge inspection facility according to the first embodiment of the present invention.
Figure 3 is a front view of the installation state of the pressure-type pre-embedded anchor for fixing the bridge inspection facility according to the first embodiment of the present invention.
Figure 4 is a construction process of the pressurized pre-embedded anchor for fixing the bridge inspection facility according to the first embodiment of the present invention.
Figure 5 is a side view of the installation state of the pressure-type pre-embedded anchor for fixing the bridge inspection facility according to the second embodiment of the present invention.
6 is a construction state diagram of a bridge inspection facility to which a pressure-type pre-embedded anchor for fixing a bridge inspection facility according to the present invention is applied.

하기에서 본 발명을 설명함에 있어, 관련된 공지 기능 또는 구성에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우에는 그 상세한 설명은 생략할 것이다. 그리고 후술되는 용어들은 본 발명에서의 기능을 고려하여 정의된 용어들로서 이는 사용자, 운용자의 의도 또는 관례 등에 따라 달라질 수 있다. 그러므로 그 정의는 본 명세서 전반에 걸친 내용을 토대로 내려져야 할 것이다.In the following description of the present invention, when it is determined that a detailed description of related known functions or configurations may unnecessarily obscure the subject matter of the present invention, the detailed description will be omitted. In addition, terms to be described later are terms defined in consideration of functions in the present invention, which may vary according to a user's or operator's intention or practice. Therefore, the definition should be made based on the contents throughout this specification.

본 발명은 기능적으로 볼 때 커플러 조립체와 가압 조립체로 구분되고, 물론, 이들 조립체는 서로 분리된 것과 연결된 것 모두가 가능하며, 하기에서는 분리된 것을 예로 들어 설명하고, 실시예 1은 기본형이고, 실시예 2는 기본형에서 거푸집과의 사이에 물이 침투하는 것을 차단하는 차수형이다.The present invention is functionally divided into a coupler assembly and a pressure assembly, and, of course, these assemblies are capable of being separated from each other and connected to each other. In the following, an example of separation is described, and Example 1 is a basic type. Example 2 is the order type that blocks the penetration of water between the formwork and the basic form.

본 발명의 선매립 앵커(100)는 도 6에서 보이는 것처럼, 교량 점검 시설을 교량에 고정하기 위한 모든 곳(계단, 점검로 등)에 적용 가능하다.Pre-embedding anchor 100 of the present invention, as shown in Figure 6, it is applicable to all places (stairs, inspection paths, etc.) for fixing the bridge inspection facility to the bridge.

<실시예 1><Example 1>

도 1 내지 도 3에서 보이는 바와 같이, 본 실시예에 의한 교량 점검시설 고정용 가압식 선매립 앵커(100)는, 커플러 조립체로서 기초판(10)과 커플러(20), 상기 커플러 조립체를 철근(2)을 지지기반으로 하여 거푸집(1)에 밀착시켜 콘크리트의 타설 시 상기 커플러 조립체가 설치 위치를 유지하도록 하는 가압 조립체로서 가압 볼트(30)와 가압판(40)으로 구성된다.1 to 3, the pressurized pre-embedding anchor 100 for fixing the bridge inspection facility according to the present embodiment is a base plate 10, a coupler 20, a coupler assembly, and a rebar 2 ) Is a pressing assembly that is in close contact with the formwork (1) based on a support to maintain the installation position of the coupler assembly when pouring concrete, and is composed of a pressing bolt (30) and a pressing plate (40).

기초판(10)은 커플러(20)를 넓은 면적으로 거푸집(1)에 지지하기 위한 것이며, 교량 점검 시설의 고정을 위하여 다수개의 앵커볼트가 사용되는 것을 고려할 때 하나의 기초판(10)에는 다수개의 커플러(20)가 수용되도록 구성된다.The base plate 10 is for supporting the coupler 20 to the formwork 1 with a large area, and considering that a plurality of anchor bolts are used for fixing the bridge inspection facility, the base plate 10 has a plurality Dog coupler 20 is configured to be accommodated.

기초판(10)은 평평한 판재(예를 들어 사각형으로 도시되었으며, 원형 등 다양한 형상이 가능함)이고, 앵커 볼트(3)가 설치되도록 다수의 앵커볼트 관통홀(11)이 구비된다. The base plate 10 is a flat plate material (for example, shown in a square shape, and various shapes such as a circular shape are possible), and a plurality of anchor bolt through holes 11 are provided so that the anchor bolt 3 is installed.

거푸집(1)과 기초판(11) 사이에 콘크리트가 침투할 수 없다면 앵커볼트 관통홀(11)은 콘크리트의 침투로 인한 막힘이 발생하지 않으며, 콘크리트의 침투로 인한 막힘을 방지하기 위하여 앵커볼트 관통홀(11)에 채움재(스폰지 등)가 적용될 수 있다. 상기 채움재는 콘크리트의 양생 후 거푸집(1)을 탈형한 다음 앵커볼트(3)를 체결하기 전에 제거된다.If concrete cannot penetrate between the formwork (1) and the base plate (11), the anchor bolt through-hole 11 does not cause clogging due to the penetration of concrete, and the anchor bolt penetrates to prevent clogging due to the penetration of concrete A filling material (sponge, etc.) may be applied to the hole 11. The filling material is removed prior to fastening the anchor bolt 3 after demolding the formwork 1 after curing the concrete.

기초판(10)과 커플러(20)는 조립식이 바람직하며, 왜냐하면, 거푸집(1)과 철근(2) 사이에 커플러 조립체를 설치하기 위한 작업은 커플러 조립체를 거푸집(1)의 상부쪽 가장자리에서부터 설치 위치로 밀어 삽입하는 작업을 필요로 하고 이 때, 커플러 조립체의 기초판(10)과 커플러(20)가 조립된 부피가 거푸집(1)과 철근(2) 사이의 간격보다 커 철근(2)과 간섭을 일으키게 됨으로써 작업이 불가능하거나 매우 불편하기 때문이다.The base plate 10 and the coupler 20 are preferably assembled, because the operation for installing the coupler assembly between the formwork 1 and the reinforcing bar 2 installs the coupler assembly from the upper edge of the formwork 1 It is necessary to push the insert into position, and at this time, the volume of the base plate 10 and the coupler 20 of the coupler assembly assembled is greater than the distance between the formwork 1 and the reinforcing bar 2, and the reinforcing bar 2 and This is because the work is impossible or very inconvenient due to the interference.

기초판(10)과 커플러(20)의 조립 방식으로 바람직하게 기초판(10)의 안쪽면에 고정 너트(13)가 용접 고정된다. 고정 너트(13)는 커플러(20)를 고정하기 위한 것이며, 커플러(20)를 나사 체결로 조립하기 위한 것이다. 따라서, 고정 너트(13)는 커플러(20)가 용접으로 고정되는 경우 나사선이 없으면서 커플러(20)가 삽입되는 파이프로 대체 가능하다.In the assembly method of the base plate 10 and the coupler 20, the fixing nut 13 is preferably welded and fixed to the inner surface of the base plate 10. The fixing nut 13 is for fixing the coupler 20, and is for assembling the coupler 20 by screwing. Therefore, the fixing nut 13 can be replaced with a pipe into which the coupler 20 is inserted without a thread when the coupler 20 is fixed by welding.

커플러(20)는 파이프 형태로서, 외주면에는 고정 너트(13)에 나사 체결을 위하여 나사선이 형성된다.The coupler 20 is in the form of a pipe, and a thread is formed on the outer circumferential surface for screwing to the fixing nut 13.

또한, 커플러(20)의 안쪽에는 고장력 볼트(21)가 조립될 수 있다. In addition, a high-strength bolt 21 may be assembled inside the coupler 20.

따라서, 커플러(20)는 앵커볼트(3)와 고장력 볼트(21)의 체결을 위하여 내주면에 나사선이 형성되며, 이 때 나사선은 앵커볼트(3)와 고장력 볼트(21)의 외경에 맞는 직경으로 형성된다.Therefore, the coupler 20 is formed with a screw thread on the inner circumferential surface for fastening the anchor bolt 3 and the high-strength bolt 21, wherein the screw thread has a diameter suitable for the outer diameter of the anchor bolt 3 and the high-strength bolt 21. Is formed.

고장력 볼트(21)는 필요에 따라 선택되는 것으로, 커플러(20)의 단부 중에서 기초판(10)에 연결되지 않는 단부에 확장에 의한 고장력부가 일체로 구성 가능하고 또한 콘크리트가 내부에 침투하지 못하는 구조이다.The high-strength bolt 21 is selected as needed, and the high-strength portion by expansion to the end of the coupler 20 that is not connected to the base plate 10 is integrally configurable and concrete does not penetrate inside. to be.

가압 조립체로 가압 볼트(30)와 가압판(40)은 다음과 같이 구성된다.The pressing bolt 30 and the pressing plate 40 as the pressing assembly are configured as follows.

하나 이상(바람직하게 2개)의 가압 볼트(30)는 가압판(40)에 나사 체결되어 조립체를 구성한다.One or more (preferably two) pressure bolts 30 are screwed to the pressure plate 40 to form an assembly.

가압판(40)은 예를 들어 사각형의 판재이며 나사탭을 가공하는 방법 또는 구멍을 천공하고 이 구멍에 맞춰 너트를 용접 고정하는 방법을 통해 가압 볼트(30)를 수용한다.The pressure plate 40 is, for example, a rectangular plate material, and accommodates the pressure bolt 30 through a method of processing a screw tab or a method of drilling a hole and welding and fixing a nut according to the hole.

가압 볼트(30)는 가압판(40)에 나사 체결된 상태에서 선단부가 기초판(10)의 면에 지지되며, 거푸집(1)에서부터 철근(2)까지의 거리보다 긴 길이로 구성된다.The pressing bolt 30 is supported on the surface of the base plate 10 in a state where it is screwed to the pressing plate 40 and is configured to have a length longer than the distance from the formwork 1 to the reinforcing bar 2.

이와 같은 구성에 의한 가압 조립체는 가압 볼트(30)의 선단부를 기초판(10)에 지지한 상태에서 가압 볼트(30)를 돌리면 가압판(40)이 철근(2)쪽으로 이동하여 철근(2)에 접촉된 상태에서부터는 철근(2)과 가압 볼트(2)를 서로 반대 방향으로 미는 힘을 발휘하여 결과적으로 기초판 조립체를 거푸집(1)과 철근(2)에 견고하게 고정한다.In the pressing assembly according to the above configuration, when the pressing bolt 30 is rotated while the front end portion of the pressing bolt 30 is supported on the base plate 10, the pressing plate 40 moves toward the reinforcing bar 2 to the reinforcing bar 2 From the contacted state, the force of pushing the reinforcing bar 2 and the pressing bolt 2 in opposite directions is exerted, and as a result, the base plate assembly is firmly fixed to the formwork 1 and reinforcing bar 2.

도면에서 가압 조립체는 기초판(10)의 상부와 하부에 적용되는 것으로 도시되었으며, 이에 한정되지 아니하고 상하부와 좌우측에도 적용 가능하고 또한 기초판(10)의 중심부에도 가능하다.In the drawing, the pressing assembly is illustrated as being applied to the upper and lower portions of the base plate 10, but is not limited thereto, and is applicable to the upper and lower portions and the left and right sides, and is also applicable to the center portion of the base plate 10.

본 실시예에 의한 교량 점검시설 고정용 가압식 선매립 앵커의 시공 방법은 다음과 같다(도 4 참고).The construction method of the pressurized pre-embedded anchor for fixing the bridge inspection facility according to this embodiment is as follows (see FIG. 4).

제1단계 : 커플러 조립체 조립 및 배치.
기초판(10)과 커플러(20)의 커플러 조립체를 조립한 후 거푸집(1)에 배치하며 그 구체적인 공정은 다음과 같다.
Step 1: Assemble and place the coupler assembly.
After assembling the coupler assembly of the base plate 10 and the coupler 20, placed in the formwork 1, the specific process is as follows.

가. 기초판 배치.end. Baseplate placement.

교량의 콘크리트 시공을 위하여 거푸집(1)이 설치되어 있고 거푸집(1) 안의 타설공간에 철근(2)이 배근되어 있다.For the concrete construction of the bridge, the formwork (1) is installed and the reinforcing bar (2) is reinforced in the pour space inside the formwork (1).

기초판(10)을 거푸집(1)에 배치하고 이 위치는 점검시설의 고정을 위한 앵커볼트의 위치이다.The base plate (10) is placed in the formwork (1) and this position is the position of the anchor bolt for fixing the inspection facility.

나. 커플러 조립.I. Coupler assembly.

기초판(10)의 고정 너트(12)에 커플러(20)를 나사 체결하여 조립한다.The coupler 20 is screwed to the fixing nut 12 of the base plate 10 and assembled.

기초판(10)의 안쪽에는 다수의 철근(2)이 배근되어 있지만 커플러(20)는 부피가 작은 파이프의 형태이기 때문에 철근(2)들 사이의 빈 공간을 통해 커플러(20)를 삽입하여 조립하는 것이 가능하다.A plurality of reinforcing bars (2) are reinforced inside the base plate (10), but since the coupler (20) is in the form of a small-volume pipe, it is assembled by inserting the coupler (20) through an empty space between the reinforcing bars (2). It is possible to do.

다. 고장력 볼트 조립.All. High tension bolt assembly.

커플러(20)의 안쪽(뒤쪽)에 고장력 볼트(21)를 나사 체결로 조립한다.
이상의 공정을 통해 상기 커플러 조립체를 거푸집(1)에 배치한다.
The high tension bolt 21 is assembled to the inside (back) of the coupler 20 by screwing.
Through the above process, the coupler assembly is disposed in the formwork (1).

제2단계 : 가압 조립체 설치.
가압 볼트(30)와 가압판(40)로 이루어진 가압 조립체를 설치 및 상기 커플러 조립체를 밀착 고정하는 공정이며 구체적인 공정은 다음과 같다.
Step 2: Install the pressure assembly.
The process of installing the pressure assembly consisting of the pressure bolt 30 and the pressure plate 40 and closely fixing the coupler assembly is as follows.

가압 조립체의 가압볼트(30)의 단부를 기초판(10)의 안쪽면에 지지하고 가압볼트(30)를 돌리면서 가압판(40)을 잡고 철근(2) 방향으로 밀면 기초판(10)이 거푸집(1)에 의해 밀리지 않는 고정 상태이기 때문에 가압판(40)이 철근(2)쪽으로 밀리게 되고, 가압판(40)이 철근(2)에 닿은 상태에서 가압볼트(30)를 좀 더 돌려 가압판(40)에 의해 철근(2)을 미는 힘이 발생토록 하며, 이 때, 가압볼트(30)는 선단부를 통해 기초판(10)을 미는 힘을 발생하게 되고, 따라서, 기초판(10)은 가압 조립체를 통해 거푸집(1)과 철근(2)에 가압력으로 고정된 상태이다.Support the end of the pressure bolt 30 of the pressure assembly to the inner surface of the base plate 10, while holding the pressure plate 40 while turning the pressure bolt 30, push the base plate 10 in the direction of the rebar 2, and the base plate 10 is formwork Because it is in a fixed state that is not pushed by (1), the pressure plate 40 is pushed toward the reinforcing bar 2, and in the state where the pressure plate 40 is in contact with the reinforcing bar 2, the pressure bolt 30 is further rotated to further press the pressure plate 40 ) To force the reinforcing bar 2 to be generated, and at this time, the pressing bolt 30 generates a force to push the base plate 10 through the tip portion, and thus, the base plate 10 is a pressing assembly. Through the formwork (1) and the reinforcing bar (2) is fixed to the pressing force.

이상의 공정을 완료한 후 콘크리트를 타설하여 교량을 시공한다.After completing the above process, concrete is poured to construct the bridge.

본 발명은 기초판(10), 가압판(40), 커플러(20)가 세트로서 거푸집(1)과 철근(2)에 고정되기 때문에 거푸집(1)과 철근(2)의 간격을 유지하는 것이 가능하고 따라서, 피복 두께 확보나 거푸집과 철근 간의 간격 유지를 위한 별도의 간격유지장치를 사용하지 않는다.In the present invention, since the base plate 10, the pressure plate 40, and the coupler 20 are fixed to the formwork 1 and the reinforcing bar 2 as a set, it is possible to maintain the distance between the formwork 1 and the reinforcing bar 2 Therefore, a separate gap maintaining device is not used for securing the thickness of the coating or maintaining the gap between the formwork and the reinforcing bar.

본 발명에 따른 점검시설 설치 방법은 거푸집(1)의 탈형 후 앵커볼트(3)를 교량 안에 매립된 커플러(20)에 나사 체결하는 것으로 가능하다.The installation method of the inspection facility according to the present invention is possible by screwing the anchor bolt 3 to the coupler 20 embedded in the bridge after demolding the formwork 1.

거푸집(1)의 탈형 시 본 발명의 선매립 앵커(100)는 기초판 조립체와 가압 조립체 모두 교량 안에 매립 상태를 유지하고 기초판(10)의 면, 앵커볼트 관통홀(11)이 외부로 보이게 되어 작업자가 앵커볼트 관통홀(11)을 확인하면서 앵커볼트(3)를 체결하여 교량 점검 시설을 설치한다.When the formwork 1 is demolded, the pre-embedded anchor 100 of the present invention maintains a buried state in the bridge both the base plate assembly and the pressure assembly, and the surface of the base plate 10, the anchor bolt through hole 11 is visible to the outside. As the operator checks the anchor bolt through hole 11, the anchor bolt 3 is fastened to install a bridge inspection facility.

<실시예 2><Example 2>

도 5에서 보이는 것처럼, 본 실시예에 의한 교량 점검시설 고정용 가압식 선매립 앵커(100)는, 기초판(10)과 거푸집(1) 사이에 물이 침투하지 않도록 차수판(50)을 포함하는 점에서 실시예 1과 차이가 있으며, 나머지 구성(커플러 조립체, 가압 조립체)은 실시예 1과 동일하다.As shown in FIG. 5, the pressurized pre-embedding anchor 100 for fixing the bridge inspection facility according to the present embodiment includes a water shield plate 50 so that water does not penetrate between the base plate 10 and the formwork 1. It differs from Example 1 in that the rest of the configuration (coupler assembly, pressure assembly) is the same as in Example 1.

차수판(50)은 기초판(10)의 가장자리를 통해 기초판(10)과 거푸집(1) 사이에 물이 침투하는 것을 막는 것이며, 예를 들어 기초판(10)의 상부와 하부에 각각 적용되고 거푸집(1)에 고정되면서 거푸집(1)과 기초판(10) 사이를 폐쇄한다. 물론, 차수판(50)은 기초판(10)의 상하좌우 4곳 모두 즉 기초판(10)의 모든 둘레부에도 적용 가능하다.The water plate 50 prevents water from penetrating between the base plate 10 and the formwork 1 through the edge of the base plate 10, for example, applied to the upper and lower portions of the base plate 10, respectively. It is fixed to the formwork (1) and closes between the formwork (1) and the base plate (10). Of course, the water plate 50 can be applied to all four upper, lower, left, and right sides of the base plate 10, that is, all circumferences of the base plate 10.

차수판(50)은 거푸집(1)과 기초판(10) 사이의 틈을 막는 구조이며, 예를 들어 전체적으로 띠의 형태로서 거푸집 고정부(51) 및 차수날개(52)로 구성된다.The water plate 50 is a structure that closes the gap between the formwork 1 and the base plate 10, and is composed of, for example, a formwork fixing part 51 and a waterfoil blade 52 in the form of a strip as a whole.

거푸집 고정부(51)는 거푸집(1)에 고정되는 부분이고, 차수날개(52)는 거푸집 고정부(51)의 일측에서 연장 형성되어 기초판(10)의 가장자리를 덮음으로써 거푸집(1)과 기초판(10) 사이의 틈을 폐쇄하는 것이다.The formwork fixing part 51 is a part that is fixed to the formwork 1, and the order wings 52 are formed to extend from one side of the formwork fixing part 51 to cover the edge of the base plate 10 and formwork 1 The gap between the base plates 10 is closed.

거푸집 고정부(51)의 고정방법으로 자석(53)에 의한 자력식 방법이 있다.As a method of fixing the formwork fixing part 51, there is a magnetic method using a magnet 53.

거푸집 고정부(51)는 일측을 향해 개방되는 홈을 갖는 구조이고, 상기 홈에 자석(53)이 삽입 설치된다. The formwork fixing part 51 is a structure having a groove that is open toward one side, and a magnet 53 is inserted into the groove.

본 실시예는 차수판(50)을 통해 거푸집(1)과 기초판(10) 사이에 물이 침투하지 못하게 하여 기초판(10)의 위치 변동(이탈)이나 거푸집(1)으로부터 들뜸 현상을 막는 특징이 있고, 이 때 차수판(50)을 자석(53)으로 고정함으로써 거푸집(1)을 훼손하지 아니하며 실시예 1에 비해 차수판(50)을 통해 기초판(10)을 고정하기 때문에 가압 조립체의 가압 시 기초판(10)을 잡고 있는 불편함을 해결하는 특징도 있다.This embodiment prevents water from penetrating between the formwork (1) and the base plate (10) through the water plate (50) to prevent displacement (deviation) or lifting from the formwork (1) of the base plate (10). It is characterized in that, at this time, by fixing the water plate 50 with a magnet 53, the formwork 1 is not damaged, and the pressure plate assembly is fixed because the base plate 10 is fixed through the water plate 50 compared to Example 1 There is also a feature that solves the inconvenience of holding the base plate 10 when pressed.

자석(53)은 커플러(20)의 설치시에만 사용되고 커플러(20)의 설치를 완료한 후에는 철거될 수 있다. 이 때, 자석(53)이 차수판(50)에서 분리되어 차수판(50)은 남은 상태에서 자석(53)만 철거될 수 있고 또는 차수판(50)과 자석(53) 모두가 콘크리트 타설 전 철거될 수 있다.The magnet 53 is used only when the coupler 20 is installed, and can be removed after completing the installation of the coupler 20. At this time, the magnet 53 is separated from the water plate 50, the water plate 50 can be removed only the magnet 53 in the remaining state, or both the water plate 50 and the magnet 53 before pouring concrete Can be demolished.

본 실시예에 의한 교량 점검시설 고정용 가압식 선매립 앵커의 시공 방법은, 실시예 1과 비교하면 기초판(10) 배치와 차수판(50) 부착의 공정에 차이가 있고 나머지 공정은 실시예 1과 동일하다.The construction method of the pressurized pre-embedded anchor for fixing the bridge inspection facility according to the present embodiment differs from the first embodiment in the process of placing the base plate 10 and attaching the water plate 50, and the rest of the process is Example 1 Is the same as

상기 공정은 기초판(10)의 위치를 잡고 차수판(50)을 자석(53)의 자력으로 거푸집(1)에 부착하면서 기초판(10)을 고정하는 공정이다.The above process is a process of fixing the base plate 10 while holding the position of the base plate 10 and attaching the water plate 50 to the formwork 1 with the magnetic force of the magnet 53.

1 : 거푸집, 2 : 철근
3 : 앵커볼트,
10 : 기초판, 11 : 앵커볼트 관통홀
12 : 고정 너트, 20 : 커플러
21 : 고장력 볼트, 30 : 가압 볼트
40 : 가압판, 50 : 차수판
51 : 거푸집 고정부, 52 : 차수날개
53 : 자석
1: Formwork, 2: Rebar
3: Anchor bolt,
10: base plate, 11: anchor bolt through hole
12: fixing nut, 20: coupler
21: high tension bolt, 30: pressurized bolt
40: pressure plate, 50: water plate
51: formwork fixing part, 52: order wing
53: magnet

Claims (6)

하나 이상의 앵커볼트 관통홀이 구비되며 거푸집의 타설면에 지지되는 기초판 및 상기 기초판의 앵커볼트 관통홀과 통하는 앵커볼트 체결부가 구비되며 상기 기초판에 고정되는 너트형의 커플러로 이루어지는 커플러 조립체와;
상기 거푸집의 안쪽에 배근되는 철근을 지지기반으로 하여 상기 커플러 조립체를 상기 거푸집에 밀착시켜 고정하는 가압 조립체와;
상기 거푸집에 고정되며 상기 커플러 조립체의 기초판의 둘레부 중 일측 이상을 외부와 차단하는 차수판을 포함하고,
상기 가압 조립체는 선단부가 상기 커플러 조립체의 기초판에 형성되는 고정 너트에 나사 체결되는 가압 볼트 및 상기 가압 볼트에 나사 체결되며 상기 가압 볼트의 체결에 의해 상기 철근으로 이동하면서 상기 철근에 지지되어 상기 가압 볼트를 통해 상기 커플러 조립체를 상기 거푸집에 가압 지지하는 가압판을 포함하고,
상기 차수판은 상기 거푸집에 고정되는 거푸집 고정부 및 상기 거푸집 고정부의 일측에서 연장 형성되어 상기 기초판의 가장자리를 덮어 상기 거푸집과 기초판 사이의 틈을 폐쇄하는 차수날개를 포함하되,
상기 거푸집 고정부는 일측을 향해 개방되는 홈을 구비하여 상기 홈에 자석이 삽입됨으로써 상기 자석의 자력을 통해 상기 거푸집에 부착되며, 이에 의하여 상기 기초판의 둘레부를 외부와 차단하는 한편 상기 기초판을 상기 거푸집에 고정하는 겸용인 것을 특징으로 하는 교량 점검시설 고정용 가압식 선매립 앵커.
A coupler assembly comprising at least one anchor bolt through hole, a base plate supported on the pouring surface of the formwork, an anchor bolt fastening part communicating with the anchor bolt through hole of the base plate, and a nut-type coupler fixed to the base plate and ;
A pressing assembly for fixing the coupler assembly in close contact with the formwork based on a support base reinforced on the inside of the formwork;
It is fixed to the formwork and includes a water shield plate blocking at least one side of the peripheral portion of the base plate of the coupler assembly from the outside,
The pressing assembly is screwed to the pressing bolt and the pressing bolt, the distal end of which is screwed to the fixing nut formed on the base plate of the coupler assembly and is supported by the reinforcing bar while being moved to the reinforcing bar by fastening of the pressing bolt. It includes a pressure plate for supporting the coupler assembly to the formwork through a bolt,
The water plate includes a form fixing part fixed to the formwork and an extension wing formed on one side of the form fixing part to cover an edge of the base plate to close a gap between the formwork and the base plate,
The form fixing part has a groove that is open toward one side, and a magnet is inserted into the groove to be attached to the form through the magnetic force of the magnet, thereby blocking the circumference of the base plate from the outside while blocking the base plate. Pressurized pre-embedded anchor for fixing the bridge inspection facility, characterized in that it is also used for fixing to the formwork.
삭제delete 삭제delete 삭제delete 청구항 1에 있어서, 상기 커플러 조립체는 상기 앵커볼트 관통홀과 통하는 너트 형태이며 상기 기초판에 고정되면서 상기 커플러가 나사 체결로 고정되는 고정 너트, 상기 커플러에 나사 체결되는 고장력 볼트를 포함하는 조립식인 것을 특징으로 하는 교량 점검시설 고정용 가압식 선매립 앵커.The method according to claim 1, The coupler assembly is in the form of a nut that communicates with the anchor bolt through-hole and is fixed to the base plate, the coupler being a fixing nut fixed by screw fastening, and a high-strength bolt screwed into the coupler. A pressurized pre-embedded anchor for fixing the bridge inspection facility. 청구항 1에 의한 교량 점검시설 고정용 가압식 선매립 앵커의 시공 방법으로서,
하나 이상의 앵커볼트 관통홀이 구비된 기초판 및 상기 기초판에 조립되는 커플러로 이루어진 커플러 조립체를 거푸집에 배치하는 제1단계와;
상기 거푸집의 안쪽에 배근된 철근을 지지기반으로 하여 상기 커플러 조립체의 기초판을 상기 거푸집에 밀착 고정한 후 상기 기초판의 둘레부 중 일측 이상에 차수판을 설치하는 제2단계를 포함하는 것을 특징으로 하는 교량 점검시설 고정용 가압식 선매립 앵커의 시공 방법.



As a construction method of the pressurized pre-embedded anchor for fixing the bridge inspection facility according to claim 1,
A first step of arranging a coupler assembly comprising a base plate provided with at least one anchor bolt through-hole and a coupler assembled to the base plate in a formwork;
And a second step of installing a water shield plate on at least one side of the circumference of the base plate after closely fixing the base plate of the coupler assembly to the die based on a support base reinforced on the inside of the die. Construction method of pressurized pre-embedded anchor for fixing bridge inspection facility.



KR1020190024183A 2019-02-28 2019-02-28 Pressurized type Pre-embedded Anchor by Pressurized for Bridge Inspection Facility and Method for constructing this same KR102116934B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190024183A KR102116934B1 (en) 2019-02-28 2019-02-28 Pressurized type Pre-embedded Anchor by Pressurized for Bridge Inspection Facility and Method for constructing this same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190024183A KR102116934B1 (en) 2019-02-28 2019-02-28 Pressurized type Pre-embedded Anchor by Pressurized for Bridge Inspection Facility and Method for constructing this same

Publications (1)

Publication Number Publication Date
KR102116934B1 true KR102116934B1 (en) 2020-05-29

Family

ID=70912178

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190024183A KR102116934B1 (en) 2019-02-28 2019-02-28 Pressurized type Pre-embedded Anchor by Pressurized for Bridge Inspection Facility and Method for constructing this same

Country Status (1)

Country Link
KR (1) KR102116934B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102277193B1 (en) 2021-01-12 2021-07-14 (주)이알코리아 Formwork perforation type pre-embedded anchor device for installation of bridge inspection facilities
KR102413916B1 (en) 2021-01-12 2022-06-28 (주)이알코리아 Construction method of pre-buried anchor in formwork perforation type for installation of bridge inspection facility
KR20220112615A (en) 2021-02-04 2022-08-11 (주)이알코리아 Construction method and structure of pre-embedded anchor set for installation of bridge inspection facilities using form tie

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11107526A (en) * 1997-10-06 1999-04-20 Sekisui House Ltd Concrete embedded body
KR20070017873A (en) * 2005-08-08 2007-02-13 (주)엠씨에스공법 Mold assembly, composite crossbeam and construction method using the same
KR100707685B1 (en) 2004-10-23 2007-04-17 이근식 A embeded anchor with socket nut
KR100792434B1 (en) 2006-09-06 2008-01-10 현빈개발 주식회사 Bridge check way installation method
KR20150029782A (en) * 2013-09-09 2015-03-19 주식회사 정우비엔씨 Coupler protecting cap for connecting steeel reinforcement and coupler constructing method using the same
KR101904447B1 (en) * 2017-11-15 2019-01-24 윤필용 Retrofitted Aseismic Bridge bearing and Bridge bearing construction method using the same

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11107526A (en) * 1997-10-06 1999-04-20 Sekisui House Ltd Concrete embedded body
KR100707685B1 (en) 2004-10-23 2007-04-17 이근식 A embeded anchor with socket nut
KR20070017873A (en) * 2005-08-08 2007-02-13 (주)엠씨에스공법 Mold assembly, composite crossbeam and construction method using the same
KR100792434B1 (en) 2006-09-06 2008-01-10 현빈개발 주식회사 Bridge check way installation method
KR20150029782A (en) * 2013-09-09 2015-03-19 주식회사 정우비엔씨 Coupler protecting cap for connecting steeel reinforcement and coupler constructing method using the same
KR101904447B1 (en) * 2017-11-15 2019-01-24 윤필용 Retrofitted Aseismic Bridge bearing and Bridge bearing construction method using the same

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102277193B1 (en) 2021-01-12 2021-07-14 (주)이알코리아 Formwork perforation type pre-embedded anchor device for installation of bridge inspection facilities
KR102413916B1 (en) 2021-01-12 2022-06-28 (주)이알코리아 Construction method of pre-buried anchor in formwork perforation type for installation of bridge inspection facility
KR20220112615A (en) 2021-02-04 2022-08-11 (주)이알코리아 Construction method and structure of pre-embedded anchor set for installation of bridge inspection facilities using form tie

Similar Documents

Publication Publication Date Title
KR102078267B1 (en) Rebar fixed type Pre-embedded Prefabricated Anchor for Bridge Inspection Facility and Method for constructing this same
KR102116934B1 (en) Pressurized type Pre-embedded Anchor by Pressurized for Bridge Inspection Facility and Method for constructing this same
KR101503809B1 (en) Spacer for truss girder fixing and deck plate combine structure for ceiling mold using there of
JP4738886B2 (en) Equipment foundation
US6837473B2 (en) Method and apparatus for erecting forms for concrete pours
KR20030064362A (en) Structure and Method for Precast Deck-to-Girder Connections
KR101565467B1 (en) complex cast-in insert apparatus for concrete
KR102168358B1 (en) Landfill facility for bridge inspection structure and construction method
KR102059519B1 (en) Inspection facility structure using recessed anchor bolt and construction method
US20070068105A1 (en) Concrete form
KR100737841B1 (en) Clamp for fixing a concrete form
JP6632290B2 (en) Steel column leg structure and steel column leg construction method
KR100715788B1 (en) Fixing apparatus for mold
KR100932299B1 (en) Device under the concrete for partial removal and reinforcing bar extension at the reinforced concrete work
KR20200144240A (en) Embedded anchor structure and Installation method
KR101518034B1 (en) manufacturing method for concrete column having self-restraint features
KR101425511B1 (en) complex cast-in insert apparatus for concrete
KR100737995B1 (en) Insert for ceiling finish panel installation
KR200392009Y1 (en) Composite frame for Slab-form
JP2009257006A (en) Ground anchor construction method
KR102304230B1 (en) Demountable shear connector apparatus and bridge structure with the same, and bridge concrete slab construction method using the same
JPH10266428A (en) Permanent form
KR20210033652A (en) Expansion joints for bridge decks that can be easily replaced without using concrete in the field
KR200354124Y1 (en) Structure fixing plate
JP3002742B2 (en) Reinforcement support structure to formwork

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant