KR102043582B1 - Construction method of retaining wall using panel having base for reinforce - Google Patents

Construction method of retaining wall using panel having base for reinforce Download PDF

Info

Publication number
KR102043582B1
KR102043582B1 KR1020190001953A KR20190001953A KR102043582B1 KR 102043582 B1 KR102043582 B1 KR 102043582B1 KR 1020190001953 A KR1020190001953 A KR 1020190001953A KR 20190001953 A KR20190001953 A KR 20190001953A KR 102043582 B1 KR102043582 B1 KR 102043582B1
Authority
KR
South Korea
Prior art keywords
panel
upper cap
retaining wall
hole
module
Prior art date
Application number
KR1020190001953A
Other languages
Korean (ko)
Inventor
정명수
Original Assignee
정명수
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 정명수 filed Critical 정명수
Priority to KR1020190001953A priority Critical patent/KR102043582B1/en
Application granted granted Critical
Publication of KR102043582B1 publication Critical patent/KR102043582B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0241Retaining or protecting walls comprising retention means in the backfill the retention means being reinforced earth elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0266Retaining or protecting walls characterised by constructional features made up of preformed elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/205Securing of slopes or inclines with modular blocks, e.g. pre-fabricated
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

According to the present invention, a construction method of a retaining wall using a panel having a base reinforcement method constructed by using a reinforcement support pipe having a predetermined length and an upper cap coupled to an upper end portion of the reinforcement support pipe comprises the following steps of: cutting a slope; installing the reinforcement support pipe in a vertical direction on a terrain in front of the cut slope; coupling the upper cap to an upper end portion of the installed reinforcement support pipe; forming a base portion with a structure of surrounding the upper cap; installing a panel with a predetermined height at an upper side of the formed base portion; performing construction work of backfilling a rear side of the installed panel; and cutting a slope at a front lower side of the installed panel.

Description

기초부 보강방안이 구비된 절토부 패널식 옹벽 시공방법{Construction method of retaining wall using panel having base for reinforce}Construction method of retaining wall using panel having base for reinforce}

본 발명은 절토부 옹벽 시공방법에 관한 것으로서, 보다 상세하게는 지반에 삽입되는 지지관을 이용하여 옹벽 구축 작업 시 현장 안전성을 도모함과 동시에 구축 후에도 패널 옹벽의 구조적 안정성을 확보할 수 있도록 구성된 기초부 보강방안이 구비된 절토부 패널식 옹벽 시공방법에 관한 것이다.The present invention relates to a method for constructing a cut retaining wall, and more specifically, a foundation part configured to secure structural stability of a panel retaining wall even after construction while promoting site safety during retaining wall construction by using a support pipe inserted into the ground. It relates to a cut panel panel retaining wall construction method provided with a reinforcement.

일반적으로 흙이나 암석이 무너지지 않게 토압력에 저항하는 벽체를 '옹벽'이라 하며, 이러한 옹벽은 앵커를 이용하거나 또는 락볼트 및 쏘일 네일을 이용하여 옹벽을 고정한다.In general, a wall that resists earth pressure to prevent soil or rock from falling down is called a 'retaining wall', and the retaining wall is fixed by using anchors or rock bolts and saw nails.

최근 들어서는 패널을 이용하여 경사진 지형에 옹벽을 구축하는 방법이 많이 적용되고 있는데, 이와 같은 패널을 이용하는 옹벽은 도 1에서와 같이, 경사진 지형을 절취한 후에 절취면 전방측 하부에 기초부(10)를 구축하고 상기 기초부(10) 상측으로 패널(20)을 계획고까지 적층하여 쌓는 방식으로 이루어진다.Recently, a method of constructing a retaining wall on a sloped terrain using a panel has been widely applied. As shown in FIG. 1, a retaining wall using such a panel has a base portion at a lower portion of the front side of the cut surface after cutting the sloped terrain. 10) is constructed by stacking and stacking the panel 20 to the planned height above the foundation 10.

이때, 공지된 기술에서와 같이, 상기 각 패널(20)은 후방 지형에 쏘일 네일링 공법 등에 의하여 설치된 보강부재에 연결된 형태를 이룰 수 있으며, 패널(20)과 절취 지형 사이에는 뒷채움 흙이 충진된다.In this case, as in the known art, each panel 20 may be connected to a reinforcing member installed by a nailing method, etc., which is disposed on the rear terrain, and the backfill soil is filled between the panel 20 and the cutout terrain. .

그리고, 이와 같은 패널 옹벽은 탑다운 방식으로 다시 하측 지형을 절토한 후에 그 전방측에 전술한 과정을 거쳐 패널 옹벽이 구축되도록 할 수 있다.In addition, the panel retaining wall may cut the topography again in a top-down manner, and then the panel retaining wall may be constructed through the above-described process on the front side thereof.

그런데, 이와 같은 패널 옹벽의 경우는 기초부(10)가 지형에 완전히 밀착되지 못하는 경우 또는 기초부(10) 바닥 지형에 파괴가 일어나는 경우 패널 옹벽의 안전성을 확보할 수 없었다. 특히, 탑다운 방식으로 지형을 절취하면 상부에 구축된 패널 옹벽의 하중으로 인하여 하측 지형 절취 시 현장 안전에 큰 불안점을 가져오게 된다.However, in the case of such a panel retaining wall, when the foundation 10 is not completely in contact with the terrain or when the destruction occurs on the ground of the foundation 10, the panel retaining wall cannot be secured. In particular, when cutting the terrain in a top-down manner, due to the load of the panel retaining wall built on the top, it brings great anxiety to site safety when cutting the lower terrain.

이와 같은 문제점을 해소하기 위하여, 도 2에서와 같이, 절취부 전방 지형에 마이크로 파일(40)을 삽입한 후, 상기 마이크로 파일(40) 상부에 프리캐스트 기초부(32)를 구축하고, 상기 프리캐스트 기초부(32) 상측으로 패널(20)을 쌓아 올려 옹벽을 구축하는 방법도 제시되었다.In order to solve such a problem, as shown in Figure 2, after inserting the micro pile 40 in the cut-out front terrain, the precast base 32 is built on the micro pile 40, and the pre A method of constructing a retaining wall has also been proposed by stacking panels 20 on top of cast base 32.

그런데, 이와 같은 패널 옹벽의 경우는 패널 및 뒷채움흙의 하중이 기초부(32) 및 마이크로 파일(40)에 수직으로 직접 걸리게 되는데, 특히 프리캐스트 기초부(32)가 각각 독립적으로 적용되어 있어 기초부(32) 바닥 지형의 파괴가 일어나는 경우 그곳으로 하중이 집중되어 패널(20)의 침하발생 우려가 있다. 이에 따라서 탑다운방식으로 상부에 구축된 패널 옹벽 하측으로 지형을 절취하는 작업 및 절취된 하부 지형에 새로운 패널 옹벽을 구축 시 후방측 마이크로 파일이 설치된 지형이 파손되거나 또는 일부 전방으로 이동함으로써 작업상 불안정함을 초래함은 물론 최종 구축된 옹벽의 내구성에 대한 신뢰도 확보에도 문제가 있게 되었다.However, in the case of such a panel retaining wall, the load of the panel and the backfilling soil is directly applied to the foundation 32 and the micro pile 40 directly, and in particular, the precast foundation 32 is applied independently. When the destruction of the bottom surface of the part 32 occurs, the load is concentrated there, which may cause settlement of the panel 20. Therefore, the operation of cutting the terrain under the panel retaining wall built on the top by the top-down method, and when constructing a new panel retaining wall on the cut lower terrain, the terrain with the rear micro pile installed is damaged or moved forward. In addition, there is also a problem in securing the reliability of the durability of the final retaining wall.

한국등록특허 제10-1785677호Korea Patent Registration No. 10-1785677

본 발명은 상술한 종래 기술의 문제점을 해결하기 위하여 안출된 발명으로서, 탑다운 방식으로 다단으로 경사진 절취부를 적용하며 패널 옹벽을 시공 시 보다 안전한 작업 환경을 제공하는데 그 목적이 있다.The present invention has been made in order to solve the problems of the prior art described above, the object of the present invention is to apply a cut inclined in multiple stages in a top-down manner and to provide a safer working environment when constructing a panel retaining wall.

또한, 본 발명은 시공이 완료된 패널 옹벽의 구조적 안정성이 확보되도록 하는데 그 목적이 있다.In addition, an object of the present invention is to ensure the structural stability of the panel retaining wall completed construction.

본 발명의 과제들은 이상에서 언급한 과제들로 제한되지 않으며, 언급되지 않은 또 다른 과제들은 아래의 기재로부터 당업자에게 명확하게 이해될 수 있을 것이다.The objects of the present invention are not limited to the above-mentioned objects, and other objects that are not mentioned will be clearly understood by those skilled in the art from the following description.

상기한 목적을 달성하기 위하여, 본 발명은 소정 길이를 가지는 보강지지관과 상기 보강지지관의 상단부에 결합되는 상부캡을 이용하여 구축되는 기초부 보강방안이 구비된 절토부 패널식 옹벽 시공방법에 있어서, 비탈면 절취단계; 상기 절취된 비탈면 전방측 지형에 상기 보강지지관을 상하방향으로 설치하는 단계; 상기 설치된 보강지지관의 상단부에 상기 상부캡을 결합하는 단계; 상기 상부캡을 덮어 감싸는 구조로 기초부를 형성하는 단계; 상기 형성된 기초부 상측으로 패널을 기 설정 높이로 설치하는 단계; 상기 설치된 패널 후방측으로 뒷채움 시공작업을 하는 단계; 및 상기 설치된 패널 전방 하부측 비탈면을 절취하는 단계;를 포함하는 기초부 보강방안이 구비된 절토부 패널식 옹벽 시공방법을 제공한다.In order to achieve the above object, the present invention is a cut-out panel retaining wall construction method provided with a reinforcement support tube having a predetermined length and the base portion reinforcement plan is constructed by using an upper cap coupled to the upper end of the reinforcement support tube. In, slope cutting; Installing the reinforcing support pipe in the vertical direction on the cut slope front side terrain; Coupling the upper cap to an upper end of the installed reinforcing support tube; Forming a base part to cover the upper cap; Installing a panel at a predetermined height above the formed foundation; Performing a backfill construction work toward the rear side of the panel; It provides a cut-out panel retaining wall construction method provided with a foundation reinforcement plan including a;

여기서, 상기 상부캡은 측면상 "T"자형으로 이루어질 수 있다.Here, the upper cap may be made of a "T" shape on the side.

또한, 상기 보강지지관은 길이방향을 따라서 하부가 소정 각도 후방측으로 경사져 설치될 수 있다.In addition, the reinforcing support pipe may be installed to be inclined toward the rear of the predetermined angle along the longitudinal direction.

또한, 상기 비탈면 절취단계이후 천공홀을 형성하고 상기 천공홀에 상기 보강지지관을 상하방향으로 설치한 후, 상기 보강지지관이 설치된 천공홀에 그라우팅재를 충진하는 단계를 더 포함할 수 있다.The method may further include forming a drilling hole after the inclined surface cutting step and installing the reinforcing support pipe in the vertical direction in the drilling hole, and filling the grouting material in the drilling hole in which the reinforcing support pipe is installed.

상기와 같이 구성된 본 발명 기초부 보강방안이 구비된 절토부 패널식 옹벽 시공방법은 다음과 같은 효과가 있다.The cut panel panel retaining wall construction method provided with the present invention reinforcement plan configured as described above has the following effects.

첫째, 본 발명은 다단으로 경사진 절취부를 적용하며 패널 옹벽을 시공 시 상부에 위치된 패널 옹역의 하부 지형 내구성이 확보되어 하측 지형 절취 작업 시 보다 안전한 작업 환경을 제공할 수 있는 효과를 가져온다.First, the present invention is applied to the multi-stage inclined cut and ensures the durability of the lower terrain of the panel retaining area located at the top when the panel retaining wall is constructed to bring an effect that can provide a safer working environment when cutting the lower terrain.

둘째, 본 발명은 시공이 완료된 패널 옹벽의 구조적 내구성이 확보되는 효과를 가져온다.Second, the present invention has the effect of ensuring the structural durability of the completed panel retaining wall construction.

셋째, 본 발명은 기초지지관과 상부캡의 결합 작업이 용이하게 이루어지며, 상부캡 또한 철근 콘크리트 기초 내부에 삽입된 형태를 이루게 되어 구조적 일체성을 확보할 수 있게 된다.Third, the present invention is easily made the coupling operation of the base support pipe and the upper cap, the upper cap also forms a shape inserted into the reinforced concrete foundation to ensure structural integrity.

본 발명의 효과들은 이상에서 언급한 효과들로 제한되지 않으며, 언급되지 않은 또 다른 효과들은 청구범위의 기재로부터 당업자에게 명확하게 이해될 수 있을 것이다.The effects of the present invention are not limited to the above-mentioned effects, and other effects not mentioned will be clearly understood by those skilled in the art from the description of the claims.

도 1은 종래 패널 옹벽의 일 형태를 개략적으로 나타낸 도면;
도 2는 종래 패널 옹벽의 다른 형태를 개략적으로 나타낸 도면;
도 3 및 4는 본 발명의 일 실시예에 따른 기초부 보강방안이 구비된 절토부 패널식 옹벽 시공방법을 순차적으로 나타낸 도면;
도 5는 상부캡과 보강지지관이 연결되는 형태를 나타낸 측면도;
도 6 및 7은 본 발명의 일 실시예에 따른 기초부 보강방안이 구비된 절토부 패널식 옹벽 시공방법을 순차적으로 나타낸 도면;
도 8은 상부캡과 보강지지관이 연결되는 형태를 나타낸 측면도;
도 9은 및 도 10은 상기 각 실시예들에 적용된 상부캡에 하중로드가 설치된 상태를 개략적으로 나타낸 측면도;
도 11은 보강지지관에 결합되는 상부캡모듈 및 상부캡고정모듈 나타낸 사시도;
도 12는 상기 도 11의 상부캡모듈이 보강지지관에 설치되는 모습을 나타낸 단면도;
도 13은 상기 도 12에서 기초부가 적용된 모습을 나타낸 단면도; 및
도 14는 상부캡모듈 상부에 경사각조절모듈이 설치된 상태를 나타낸 도면이다.
1 is a view schematically showing one form of a conventional panel retaining wall;
2 schematically illustrates another form of a conventional panel retaining wall;
3 and 4 are views sequentially showing a cut panel panel retaining wall construction method provided with a foundation reinforcement method according to an embodiment of the present invention;
Figure 5 is a side view showing the form in which the upper cap and the reinforcing support pipe is connected;
6 and 7 are views sequentially showing a cut panel panel retaining wall construction method provided with a foundation reinforcement method according to an embodiment of the present invention;
8 is a side view showing a form in which the upper cap and the reinforcing support pipe is connected;
9 and 10 are side views schematically showing a state in which a load rod is installed on the upper cap applied to the above embodiments;
11 is a perspective view showing an upper cap module and an upper cap fixing module coupled to the reinforcing support pipe;
12 is a cross-sectional view showing a state in which the upper cap module of Figure 11 is installed in the reinforcement support tube;
FIG. 13 is a cross-sectional view illustrating a state in which a foundation is applied in FIG. 12; FIG. And
14 is a view showing a state in which the inclination angle control module is installed on the upper cap module.

이하 본 발명의 목적이 구체적으로 실현될 수 있는 본 발명의 바람직한 실시예를 첨부된 도면을 참조하여 설명한다. 본 실시예를 설명함에 있어서, 동일 구성에 대해서는 동일 명칭 및 동일 부호가 사용되며 이에 따른 부가적인 설명은 생략하기로 한다.DETAILED DESCRIPTION Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings. In the description of this embodiment, the same name and the same reference numerals are used for the same configuration and additional description thereof will be omitted.

도 3 및 도 4는 본 발명의 일 실시예에 따른 기초부 보강방안이 구비된 절토부 패널식 옹벽 시공방법을 순차적으로 나타낸 도면이다.3 and 4 are views sequentially showing a cut panel panel retaining wall construction method provided with a foundation reinforcement method according to an embodiment of the present invention.

본 실시예에 따른 기초부 보강방안이 구비된 절토부 패널식 옹벽 시공방법은 도 3(a)에 도시된 것처럼, 먼저 소정 경사진 지형의 비탈면을 절취하는 단계를 수행하게 된다.In the cut panel retaining wall construction method provided with the foundation reinforcement method according to the present embodiment, as shown in FIG. 3 (a), first, a step of cutting a slope of a predetermined sloped terrain is performed.

상기 비탈면의 절취 단계는 현장에 투입된 작업자는 물론 백호우 등을 이용하여 비탈면을 소정 높이에 걸쳐 기 설정된 소정 경사 각도로 절취하고 필요 시 표면을 다지는 작업을 포함하게 된다.The step of cutting the inclined surface includes cutting the inclined surface at a predetermined inclination angle over a predetermined height by using a backhoe or the like, as well as the worker put into the site, and then, if necessary, to compact the surface.

그리고 난 후, 도 3(b)에서와 같이, 상기 절취된 비탈면 전방측 지형에 보강지지관(110)을 상하방향으로 설치하는 단계를 수행하게 된다. 여기서, 상기 보강지지관(110)은 내부가 중공되고 소정 지름을 가지는 관 형태로 이루어진다.Then, as shown in Figure 3 (b), the step of installing the reinforcing support pipe 110 in the vertical direction to the cut slope front side terrain. Here, the reinforcing support pipe 110 is made of a pipe shape having a hollow inside and a predetermined diameter.

한편, 이때 상기 절취면 전방 측에 상하방향으로 천공홀(H)을 형성하고 상기 천공홀(H)에 상기 보강지지관(110)을 상하방향으로 설치한 후, 상기 보강지지관(110)이 설치된 천공홀(H)에 그라우팅재(G)를 충진하는 작업이 추가 적용됨이 바람직하다. On the other hand, at this time, after forming the punching hole (H) in the vertical direction on the front side of the cut-out surface and install the reinforcing support pipe 110 in the vertical hole in the drilling hole (H), the reinforcing support pipe 110 is It is preferable to further apply the operation of filling the grouting material (G) in the installed hole (H).

다음으로는, 상기 설치된 보강지지관(110)의 상단부에 상부캡(130)을 결합하는 단계를 수행한다.Next, the step of coupling the upper cap 130 to the upper end of the installed reinforcement support pipe (110).

도 5는 상부캡과 보강지지관이 연결되는 형태를 나타낸 측면도이다.Figure 5 is a side view showing the form in which the upper cap and the reinforcing support pipe is connected.

도 3(b) 및 도 5에서와 같이, 상기 상부캡(130)은 지면 상부에 노출되며 소정 면적 및 두께를 가지는 사각 또는 원형 판상의 보드부(132)와, 상기 보드부(132)의 중앙부 하측으로 돌출된 형태로 구비되는 결합부(134)를 포함한다. 즉, 상기 상부캡(130)은 측면상 "T"자형으로 이루어진다.As shown in Figure 3 (b) and 5, the upper cap 130 is exposed on the upper surface of the board portion 132 of the rectangular or circular plate shape having a predetermined area and thickness, and the central portion of the board portion 132 It includes a coupling portion 134 provided in a form protruding downward. That is, the upper cap 130 is made of a "T" shape on the side.

그리고, 상기 상부캡(130)은 상기 보강지지관(110)의 상단부에 결합되는 구조를 이루게 되는데, 도시된 바와 같이, 상기 보강지지관(110)의 상부 외주면에는 나사산부(115)가 구비되고, 상기 결합부(134)는 관형태로 이루어지되 상기 보강지지관(110)의 상부에 나사결합되도록 내주면에 나사산부(미도시)가 형성되어 상기 결합부(134)가 상기 보강지지관(110)의 상부에 나사결합되도록 형성됨이 바람직하다.In addition, the upper cap 130 has a structure that is coupled to the upper end of the reinforcing support tube 110, as shown, the threaded portion 115 is provided on the upper outer peripheral surface of the reinforcement support tube 110 The coupling portion 134 is formed in a tubular shape, but a threaded portion (not shown) is formed on an inner circumferential surface of the coupling portion 134 so that the coupling portion 134 is screwed to an upper portion of the reinforcement support tube 110. It is preferable that it is formed to be screwed on the top of).

이때 상기 상부캡(130)의 보드부(132)는 상부캡(130)을 보강지지관(110)에 연결한 후 지형에 수평하게 배치되도록 함이 더욱 바람직하다.At this time, the board portion 132 of the upper cap 130 is more preferably to be arranged horizontally on the terrain after connecting the upper cap 130 to the reinforcing support pipe 110.

상기 상부캡(130)을 보강지지관(110)에 결합한 후에는 상기 상부캡(130) 외부를 덮어 감싸는 형태로 기초부(150)를 형성한다.After the upper cap 130 is coupled to the reinforcing support tube 110, the base 150 is formed to cover the outside of the upper cap 130.

콘크리트를 타설하여 다지는 형태로 상기 기초부(150)는 형성될 것이며, 자세히 도시되어 있지는 않으나, 복수 개의 보강지지관(110)이 횡방향으로 지형에 설치된 경우 상기 각 보강지지관(110)의 상부에 상부캡(130)이 설치된 상태에서 여러 개의 상부캡(130)을 횡방향으로 동시에 덮어 연결하는 형태로 상기 기초부(150)가 형성됨이 바람직하다.The foundation portion 150 will be formed in the form of pouring concrete, it is not shown in detail, but when the plurality of reinforcement support pipe 110 is installed on the terrain in the transverse direction, the upper portion of each of the reinforcement support pipe 110 In the state in which the upper cap 130 is installed in the base portion 150 is preferably formed in the form of connecting the plurality of upper cap 130 at the same time in the transverse direction.

그리고 난 후, 도 3(c) 및 도 3(d)에서와 같이, 상기 기초부(150) 상측으로 계획고까지 패널(170)을 설치 적용하게 되며, 이때 각각의 패널(170)은 종래 공지된 기술과 같이 후방측 지형에 쏘일 네일링(180) 등 구조물에 연결된 상태를 이룸이 바람직하다.Then, as shown in Figs. 3 (c) and 3 (d), the panel 170 is installed and applied to the planned height above the base portion 150, wherein each panel 170 is known in the prior art. It is preferable that the state connected to the structure, such as nailing (180) to be shot on the rear side terrain as described above.

다음으로는 상기 설치된 패널(170)과 절취된 지형 사이로 토사나 모래 등을 이용한 뒷채움 작업을 수행하여 패널 옹벽이 완성되도록 한 후, 도 4(a) 및 도 4(b)와 같이 완성된 패널 옹벽 전방측 지형을 다시 절취하고 기초부(150)를 구축한 후, 패널(170)을 계획고까지 구축하는 과정을 수행하게 된다.Next, after the panel retaining wall is completed between the installed panel 170 and the cut terrain by using soil sand or sand, the panel retaining wall is completed, as shown in FIGS. 4 (a) and 4 (b). After cutting the front side again and building the foundation 150, the process of building the panel 170 to the planned height is performed.

그리고 난 후, 하측에 위치되는 패널 옹벽은 별도로 보강지지관을 설치하지 않고 도 4(c) 내지 도 4(d)에서와 같이, 지형에 쏘일 네일링을 설치 후 기초부(150) 상측으로 패널 설치 공정과 뒷채움 작업을 수행함으로써 완료시킬 수 있다.Then, the panel retaining wall located on the lower side of the panel does not need to install a reinforcing support tube separately, as shown in FIGS. This can be done by performing the installation process and backfilling.

상술한 바와 같이 구성된 본 발명의 일 실시예에 따른 기초부 보강방안이 구비된 절토부 패널식 옹벽 시공방법에 의하면, 다단으로 경사진 절취부를 적용하며 패널 옹벽을 시공 시 상부에 위치된 패널 옹역에 적용된 보강지지관(110)에 의하여, 하측 지형 절취 작업 시 보강지지관(110) 전방측 지형의 내구성이 확보되어 안전한 작업이 가능하게 된다.According to the cut panel panel retaining wall construction method provided with a foundation reinforcement method according to an embodiment of the present invention configured as described above, applying the inclined cut portion in multiple stages to the panel retaining wall located at the top By the applied reinforcement support pipe 110, the durability of the terrain in front of the reinforcement support pipe 110 is secured at the time of the lower terrain cutting operation is possible to safely work.

특히, 복수 개의 상부캡(130)을 횡방향 철근으로 연결하고 동시에 콘크리트로 덮어 감싸는 형태로 기초부(150)를 적용하여 패널(170)에 걸리는 하중을 횡방향으로 분산시킬 수 있을 뿐 아니라 상부캡(130)의 보드부(32) 전체에 걸쳐 수평하게 패널 하중이 지지되어 구조적 내구성 확보가 가능하여 진다.In particular, by connecting the plurality of upper caps 130 with transverse reinforcement and simultaneously covering with concrete to cover the base portion 150 to distribute the load applied to the panel 170 in the horizontal direction as well as the upper cap The panel load is horizontally supported over the entire board portion 32 of the 130 to ensure structural durability.

도 6 및 도 7은 본 발명의 다른 실시예에 따른 기초부 보강방안이 구비된 절토부 패널식 옹벽 시공방법을 순차적으로 나타낸 도면이다.6 and 7 are views sequentially showing a cut panel panel retaining wall construction method provided with a foundation reinforcement method according to another embodiment of the present invention.

본 실시예에 따른 기초부 보강방안이 구비된 절토부 패널식 옹벽 시공방법도 도 6(a)에 도시된 것처럼, 먼저 소정 경사진 지형의 비탈면을 절취하는 단계를 수행하게 된다.The cut panel retaining wall construction method provided with the foundation reinforcement method according to the present embodiment is also shown in Fig. 6 (a), first to cut the slope of the predetermined inclined terrain.

그리고 난 후, 도 6(b)에서와 같이, 상기 절취된 비탈면 전방측 지형에 보강지지관(110)을 상하방향으로 설치하는 단계를 수행하게 된다. 이때에도, 상기 보강지지관(110)은 내부가 중공되고 소정 지름을 가지는 관 형태로 이루어진다.Then, as shown in Figure 6 (b), to perform the step of installing the reinforcing support pipe 110 in the vertical direction to the cut slope front side terrain. In this case, the reinforcement support tube 110 is hollow and has a tube shape having a predetermined diameter.

한편, 본 실시예에 따른 패널 옹벽 시공방법은 상기 절취면 전방 측에 상하방향으로 천공홀(H)을 형성하되, 상기 천공홀(H)은 하단부가 후방측으로 소정 각도 경사지게 형성되도록 한다.On the other hand, the panel retaining wall construction method according to the present embodiment is to form a punching hole (H) in the vertical direction on the front side of the cutting surface, the punching hole (H) is formed so that the lower end is inclined at a predetermined angle to the rear side.

그리고, 형성된 상기 천공홀(H)에 상기 보강지지관(110)을 상기 천공홀(H)의 경사진 각도에 대응되도록 경사져 설치한 후, 상기 보강지지관(110)이 설치된 천공홀에 그라우팅재(G)를 충진하게 된다. In addition, after the reinforcing support pipe 110 is installed to be inclined to correspond to the inclined angle of the drilling hole H in the formed drilling hole H, the grouting material is installed in the drilling hole in which the reinforcing support pipe 110 is installed. (G) is filled.

또한, 상기 설치된 보강지지관(110)의 상단부에 상부캡(230)을 결합하는 단계를 수행한다.In addition, the step of coupling the upper cap 230 to the upper end of the installed reinforcement support pipe (110).

도 8은 상부캡과 보강지지관이 연결되는 형태를 나타낸 측면도이다.8 is a side view showing a form in which the upper cap and the reinforcing support pipe is connected.

본 실시예에 적용되는 상부캡(230)도 원판 형태의 보드부(232)와 결합부(234)가 적용된 형태를 이루되, 본 실시에에 따른 상부캡(230)은 상기 결합부(234)가 상기 보드부(232)가 소정 각도 경사진 형태를 이룬다.The upper cap 230 applied to the present embodiment also forms a disk-shaped board portion 232 and the coupling portion 234 is applied, the upper cap 230 according to the present embodiment is the coupling portion 234 The board portion 232 is inclined at a predetermined angle.

특히, 상기 결합부(234)가 상기 보강지지관(110)의 상단부에 결합된 후 상기 보드부(232)가 지형에 수평한 상태를 이루도록 구성됨이 바람직하다.In particular, after the coupling portion 234 is coupled to the upper end of the reinforcing support pipe 110, the board portion 232 is preferably configured to form a horizontal state on the terrain.

이 경우에도 상기 결합부(234)와 상기 보강지지관(110)의 상단부는 나사결합이 가능한 구조로 이루어진다.Even in this case, the upper end of the coupling portion 234 and the reinforcement support tube 110 is made of a structure capable of screwing.

다시 도 6(b)를 참조하면, 상기 상부캡(230)을 보강지지관(110)에 결합한 후에는 상기 상부캡(230) 외부를 콘크리트로 덮어 감싸는 형태로 기초부(150)를 형성한다.Referring back to FIG. 6 (b), after the upper cap 230 is coupled to the reinforcing support tube 110, the foundation 150 is formed to cover the exterior of the upper cap 230 with concrete.

그리고 난 후, 도 6(c) 및 도 6(d)에서와 같이, 상기 기초부(150) 상측으로 계획고까지 패널(170)을 설치 적용하게 되며, 이때 각각의 패널(170)은 종래 공지된 기술과 같이 후방측 지형에 설치된 쏘일 네일링(180) 등에 연결된 구조를 이룰 수 있다.Then, as shown in Figure 6 (c) and 6 (d), the panel 170 is installed and applied to the plan height above the base portion 150, wherein each panel 170 is known in the prior art As described above, it is possible to achieve a structure connected to the saw nailing 180 and the like installed on the rear side terrain.

다음으로는 상기 설치된 패널(170)과 지형 사이로 뒷채움 작업을 수행하여 패널 옹벽이 완성되도록 한 후, 도 7(a) 내지 도 7(d)와 같이 완성된 패널 옹벽 전방측 지형을 다시 절취하고 기초부(150)를 구축 후, 쏘일 네일링(180) 및 패널(170), 뒷채움 작업 등을 적용하여 하방 패널 옹벽을 구축하여 작업이 완료된다.Next, after the panel retaining wall is completed by performing backfilling between the installed panel 170 and the terrain, the top surface of the panel retaining wall front side as shown in FIGS. 7 (a) to 7 (d) is again cut and After the construction of the unit 150, the work is completed by constructing the lower panel retaining wall by applying the nail nailing 180, the panel 170, and the back filling operation.

상술한 바와 같이 구성된 본 발명의 다른 실시예에 따른 기초부 보강방안이 구비된 절토부 패널식 옹벽 시공방법에 의하면, 보강지지관(110)이 경사져 설치되어 있으므로, 도 7에서와 같이 보강지지관(110) 전방측으로 보다 많은 부분(A)적에 걸쳐 안전성이 확보된 지형을 구축할 수 있게 된다.According to the cut panel panel retaining wall construction method provided with a foundation reinforcement plan according to another embodiment of the present invention configured as described above, since the reinforcement support pipe 110 is inclined, the reinforcement support pipe as shown in FIG. (110) It is possible to build a terrain in which safety is secured over a larger portion (A) to the front side.

이에 따라서 상부 패널 옹벽 하측 지형 절취 작업 시 보다 수직에 가까운 급격한 절취 지형 확보도 가능하게 됨은 물론 상술한 실시예와 마찬가지로 안정적 작업 확경 구축을 할 수 있게 된다.Accordingly, it is possible to secure a sharp cut terrain closer to the vertical at the time of cutting the top surface of the lower wall retaining wall, as well as to build a stable work diameter as in the above-described embodiment.

한편, 도 9 및 도 10에서와 같이, 상기 각 실시예들에 있어서 상부캡(130, 230)의 보드부(132, 232) 상측으로 설치홈(138, 238)이 적용되도록 한 후, 상기 설치홈(138, 238)에 보조로드부(162)가 설치되도록 할 수 있다. Meanwhile, as shown in FIGS. 9 and 10, in each of the above embodiments, the installation grooves 138 and 238 are applied to the upper side of the board portions 132 and 232 of the upper caps 130 and 230. The auxiliary rod part 162 may be installed in the grooves 138 and 238.

이와 같은 보조로드부(162)가 적용된 상부캡(130, 230)의 경우 패널로부터 걸리는 하중을 보다 안정적으로 받을 수 있도록 하게 되며, 특히, 인접하는 상부캡들에 상기 보조로드부(162)가 상부캡들을 연결하는 형태로 설치 적용 시에는 패널로부터 걸리는 하중을 분산시키는 효과도 가져올 수 있게 된다,In the case of the upper caps 130 and 230 to which the auxiliary rods 162 are applied, the loads from the panel can be more stably received, and in particular, the auxiliary rods 162 are adjacent to the upper caps. When the installation is applied in the form of connecting the caps can also distribute the load from the panel,

도 11은 보강지지관에 결합되는 상부캡모듈 및 상부캡고정모듈 나타낸 사시도이며, 도 12는 상기 도 11의 상부캡모듈이 보강지지관에 설치되는 모습을 나타낸 단면도이고, 도 13은 상기 도 12에서 기초부가 적용된 모습을 나타낸 단면도이다.11 is a perspective view showing the upper cap module and the upper cap fixing module coupled to the reinforcing support tube, Figure 12 is a cross-sectional view showing a state in which the upper cap module of Figure 11 is installed in the reinforcing support tube, Figure 13 is the Figure 12 Is a cross-sectional view showing the appearance of the foundation is applied.

본 실시예에 따른 상부캡모듈(330)은 커버부(332)와, 상기 커버부(332) 하부 둘레에 연결되며 신축성을 가지는 주름관부(334)를 포함한다.The upper cap module 330 according to the present exemplary embodiment includes a cover part 332 and a corrugated pipe part 334 connected to the bottom of the cover part 332 and having elasticity.

상기 커버부(332)는 하부가 개구된 원형 드럼 형태로 이루어지며, 주입공(332a)과 확인공(332b)이 구비된다.The cover part 332 is formed in the form of a circular drum with a lower opening, and is provided with an injection hole 332a and a confirmation hole 332b.

그리고, 상기 커버부(332)의 중앙부에는 하측으로 하부가 개구된 연결관부(336)가 구비되되, 상기 연결관부(336)는 상술한 실시예들에 따른 결합부와 같이 상기 보강지지관(110)의 상부에 나사결합되는 구성을 이룬다.In addition, the center portion of the cover portion 332 is provided with a connecting pipe portion 336, the lower opening of the lower side, the connecting pipe portion 336 is the reinforcement support pipe 110 as the coupling portion according to the above-described embodiments It is configured to be screwed on the top of the).

여기서, 상기 주름관부(334)는 전체적으로 상하부가 개구된 드럼 형태로 이루어지되 상기 커버부(332)의 하측 둘레에 연장된 형태로 결합된다.Here, the corrugated pipe part 334 is formed in a drum shape of the upper and lower parts as a whole, but is coupled in an extended form around the lower side of the cover part 332.

그리고, 상기 주름관부(334)는 하측 둘레부 외측으로 돌출되어 평면상 링형 형태로 이루어진 외측둘레부(338)가 구비되며, 상기 외측둘레부(338)는 소정 이격 간격마다 원주를 따라서 결합공(339)이 구비된다.The corrugated pipe part 334 protrudes outward from the lower circumference and has an outer circumferential part 338 formed in a planar ring shape, and the outer circumferential part 338 has a coupling hole along the circumference at predetermined intervals ( 339).

한편, 상기 각각의 결합공(339)을 관통하여 상기 상부캡(330)을 지반에 고정시키는 상부캡고정모듈(350)이 구비된다.On the other hand, the upper cap fixing module 350 for fixing the upper cap 330 to the ground through the respective coupling holes 339 is provided.

상기 상부캡고정모듈(350)은 지형에 하부가 삽입되는 삽입로드(352)와 상기 삽입로드(352)의 중앙부에 구비되는 중간걸림부(354) 및 상기 삽입로드(352)의 상부에 구비되는 상단타격부(356)를 구비한다.The upper cap fixing module 350 is provided on the insertion rod 352 is inserted into the terrain and the intermediate catching portion 354 is provided in the center of the insertion rod 352 and the upper portion of the insertion rod 352 The upper striker 356 is provided.

그리고, 상기 상단타격부(356)는 인접하는 상부캡고정부(350)와 철 재질의 스트링(388)에 의하여 연결되도록 하는 스트링연결홀(358)이 구비된다.In addition, the upper percussion part 356 is provided with a string connection hole 358 to be connected by the adjacent upper cap fixing portion 350 and the iron string (388).

도 12에서와 같이, 지형에 천공홀(H)을 형성한 후, 상기 천공홀(H)에 보강지지관(110)을 상부가 일부 지형 외측으로 돌출되게 설치한다.As shown in FIG. 12, after the drilling hole H is formed in the terrain, the upper portion of the reinforcing support pipe 110 is installed in the drilling hole H so as to protrude outward from the terrain.

그리고 난 후, 상기 보강지지관(110)에 본 실시예에 따른 상부캡모듈(330)의 연결관부(338) 내측으로 보강지지관(110)의 상단부를 나사결합시킨다.Then, the upper end of the reinforcing support pipe 110 is screwed into the connection pipe part 338 of the upper cap module 330 according to the present embodiment to the reinforcing support pipe 110.

이때, 도 12에서와 같이, 상기 커버부(332)의 하측 주름관부(334)는 커버부(332)의 기울인 정도에 상관없이 각 부분별로 소정 길이 접쳐져 지형 외부 표면에 주름관부(334) 하부 전체가 밀착된 형태를 이룰 수 있게 된다.At this time, as shown in Figure 12, the lower corrugated pipe portion 334 of the cover portion 332 is folded for a predetermined length for each portion irrespective of the degree of inclination of the cover portion 332, the lower portion of the corrugated tube portion 334 on the terrain outer surface The whole can be in close contact.

다음으로는 상기 외측둘레부(338)의 결합공(339)에 상기 상부캡고정모듈(350)의 삽입로드(352)를 상기 상단타격부(356)를 타격하여 지형에 삽입시키어 상기 중간걸림부(354)를 이용 상부캡모듈(330)의 외측둘레부(338)가 지형에 완전히 밀착된 상태를 이루도록 고정시킨다.Next, the insertion rod 352 of the upper cap fixing module 350 hits the upper striking portion 356 to the coupling hole 339 of the outer peripheral portion 338 to insert into the terrain by the intermediate catching portion The outer circumferential portion 338 of the upper cap module 330 is fixed to form a state in which the top cap module 330 is completely in contact with the terrain.

다음으로는 서로 인접하는 상기 상단타격부(358)의 스트링연결홀(358)을 연결하는 형태로 스트링(388)을 연결한 후, 상기 커버부(332)의 주입공(332a)과 확인공(332b)을 이용하여 그라우팅재(G)를 주입하여 상부캡모듈(330) 내측과 천공홀(H)에 그라우팅재가 완전히 충진되도록 한다.Next, after connecting the strings 388 in the form of connecting the string connection hole 358 of the upper strike portion 358 adjacent to each other, the injection hole 332a and the confirmation hole (332) of the cover portion 332 ( The grouting material (G) is injected using 332b) to completely fill the grouting material in the upper cap module 330 and the hole H.

상기 상부캡모듈(330) 내측과 천공홀(H) 내부까지 완전히 그라우팅재가 충진되어 굳어진 후에는 상기 상부캡모듈(330)을 덮어 감싸는 형태로 콘크리트 등을 이용하여 기초부(150)를 구축하게 된다.After the grouting material is completely filled and hardened to the inside of the upper cap module 330 and the inside of the hole H, the foundation 150 is constructed by using concrete to cover the upper cap module 330. .

본 실시예에 따른 상부캡모듈(330)을 적용하는 경우에는 내부 그라우팅재를 상부캡모듈(330) 내측까지 충진된 후 굳어지도록 함으로써 보강지지관(110)과 상부캡모듈(330)이 일체화된 상태를 이루어 구조적 안정성이 배가된다.In the case of applying the upper cap module 330 according to the present embodiment, the inner grouting material is filled to the upper cap module 330 and then hardened so that the reinforcing support pipe 110 and the upper cap module 330 are integrated. State, which doubles the structural stability.

또한, 상기 스트링연결홀(358)을 연결하는 형태로 스트링(388)이 적용되어 기초부(150)의 뼈대 역할을 이루도록 함으로써 기초부(150)의 내구성 확보가 가능하게 된다.In addition, the string 388 in the form of connecting the string connecting hole 358 is applied to form a skeleton of the foundation 150, it is possible to ensure the durability of the foundation 150.

도 14는 상부캡모듈 상부에 경사각조절모듈이 설치된 상태를 나타낸 도면이다.14 is a view showing a state in which the inclination angle control module is installed on the upper cap module.

본 실시예에 따른 경사각조절모듈(370)은 철질 재질로 이루어지며 소정 경사 각도를 가지는 쐐기 형태로 이루어지되 상기 주입공(332a)과 확인공(332b)에 연통되는 형태를 이룸이 가능한 위치로 상기 주입공(332a)과 확인공(332b)보다 큰 직경을 가지는 보조주입공(372)과 보조확인공(374)이 구비된다.The inclination angle adjusting module 370 according to the present embodiment is made of a steel material and is formed in a wedge shape having a predetermined inclination angle, but the position in which the form of communicating with the injection hole 332a and the confirmation hole 332b is possible. An auxiliary injection hole 372 and an auxiliary confirmation hole 374 having a larger diameter than the injection hole 332a and the confirmation hole 332b are provided.

그리고, 상기 커버부(332)와 인접하는 경사각조절모듈(370)이 서로 자력에 의하여 결합되도록 하는 자석부(376)가 구비된다,In addition, the cover part 332 and the inclination angle control module 370 adjacent to each other is provided with a magnet portion 376 to be coupled to each other by magnetic force,

이와 같은 경사각조절모듈(370)은 도 14에서와 같이, 필요에 따라 복수 개를 상기 상부캡모듈(330) 상부에 연결하여 경사각조절모듈(370) 상단이 지형에 수평한 상태를 이루도록 연결할 수 있으며, 필요 시 상기 경사각조절모듈(370)들과 커버부(332)를 용접함으로써 일체화된 상태를 이루도록 할 수 있게 된다.Such inclination angle control module 370, as shown in Figure 14, can be connected to form a horizontal state on the top of the inclination angle control module 370 by connecting a plurality of the upper cap module 330, if necessary. If necessary, the inclination angle adjusting module 370 and the cover part 332 may be welded to achieve an integrated state.

이상과 같이 본 발명에 따른 바람직한 실시예를 살펴보았으며, 앞서 설명된 실시예 이외에도 본 발명이 그 취지나 범주에서 벗어남이 없이 다른 특정 형태로 구체화될 수 있다는 사실은 해당 기술에 통상의 지식을 가진 이들에게는 자명한 것이다. 그러므로, 상술된 실시예는 제한적인 것이 아니라 예시적인 것으로 여겨져야 하고, 이에 따라 본 발명은 상술한 설명에 한정되지 않고 첨부된 청구항의 범주 및 그 동등 범위 내에서 변경될 수도 있다.As described above, a preferred embodiment according to the present invention has been described, and the fact that the present invention can be embodied in other specific forms in addition to the above-described embodiments without departing from the spirit or scope thereof has ordinary skill in the art. It is obvious to them. Therefore, the above-described embodiments should be regarded as illustrative rather than restrictive, and thus, the present invention is not limited to the above description and may be modified within the scope of the appended claims and their equivalents.

110: 보강지지관 130, 230: 상부캡
132, 232: 보드부 134, 234: 결합부
330: 상부캡모듈 332: 커버부
334: 주름관부 336: 연결관부
338: 외측둘레부 339: 결합공
110: reinforcing support pipe 130, 230: upper cap
132, 232: board portion 134, 234: coupling portion
330: upper cap module 332: cover
334: corrugated pipe portion 336: connector
338: outer peripheral portion 339: coupling hole

Claims (4)

하부가 개구된 원형 드럼 형태로 이루어지며 주입공과 확인공이 형성된 커버부와, 상기 커버부의 내부 중앙부 하측으로 하부가 개구된 형태로 구비되는 연결관부와, 상기 커버부 둘레 하측으로 연장된 형태로 구비됨과 동시에 신축성을 가지는 주름관부와, 상기 주름관부의 하측 둘레부 외측으로 돌출되며 평면상 링형 형태로 이루어짐과 동시에 원주방향을 따라서 소정 이격된 간격마다 결합공이 구비된 외측둘레부를 포함하는 상부캡모듈; 상기 연결관부에 상부가 삽입 고정되는 보강지지관; 및 상기 결합공에 관통하여 상기 상부캡모듈을 지반에 고정하도록 하는 삽입로드와, 상기 삽입로드의 중앙부에 구비되는 중간걸림부와, 상기 삽입로드의 상부에 구비되며 스트링연결홀이 형성된 상단타격부를 포함하는 상부캡고정모듈;을 이용하여 구축되는 기초부 보강방안이 구비된 절토부 패널식 옹벽 시공방법에 있어서,
비탈면 절취단계;
상기 비탈면 전방측에 상하방향으로 천공홀을 형성하고 상기 천공홀에 상기 보강지지관을 설치하는 단계;
상기 설치된 보강지지관의 상단부가 상기 연결관부 내측에 삽입 고정되도록 하면서 상기 상부캡모듈을 설치하는 단계;
상기 상부캡고정모듈의 삽입로드를 상기 중간걸림부가 상기 외측둘레부의 상부를 가압하도록 상기 결합공을 관통하여 설치하는 단계;
인접하는 상기 상부캡고정모듈의 상기 스트링연결홀을 연결하는 형태로 스트링을 설치하는 단계;
상기 주입공을 통하여 상기 커버부와 상기 천공홀 내측으로 그라우팅재를 충진하는 단계;
상기 상부캡모듈 및 상기 상부캡고정모듈을 덮어 감싸는 구조로 기초부를 형성하는 단계;
상기 형성된 기초부 상측으로 패널을 기 설정 높이로 설치하는 단계;
상기 설치된 패널 후방측으로 뒷채움 시공작업을 하는 단계; 및
상기 설치된 패널 전방 하부측 비탈면을 절취하는 단계;
를 포함하는 기초부 보강방안이 구비된 절토부 패널식 옹벽 시공방법.
It is formed in the form of a circular drum having a lower opening and a cover portion formed with an injection hole and a confirmation hole, a connecting tube portion provided in a form in which the lower portion is opened below the inner central portion of the cover portion, and is provided in a form extending downward around the cover portion; At the same time, the upper cap module comprising a corrugated pipe portion having an elasticity, and an outer peripheral portion protruding outward from the lower circumferential portion of the corrugated pipe portion and having a coupling hole at predetermined intervals along the circumferential direction at the same time as the ring-shaped shape in the circumferential direction; A reinforcement support tube having an upper portion inserted and fixed to the connection tube; And an insertion rod for penetrating the coupling hole to fix the upper cap module to the ground, an intermediate catching portion provided at the center of the insertion rod, and an upper hitting portion formed at an upper portion of the insertion rod and having a string connection hole formed therein. In the cut panel panel retaining wall construction method provided with a foundation reinforcement plan to be constructed using an upper cap fixing module comprising:
Slope cutting step;
Forming a drilling hole in the vertical direction on the slope side front side and installing the reinforcing support pipe in the drilling hole;
Installing the upper cap module while allowing the upper end of the installed reinforcing support tube to be inserted and fixed inside the connection tube part;
Installing the insertion rod of the upper cap fixing module through the coupling hole such that the intermediate catching portion presses the upper portion of the outer circumferential portion;
Installing a string in such a manner as to connect the string connection holes of the upper cap fixing module adjacent thereto;
Filling a grouting material into the cover part and the drilling hole through the injection hole;
Forming a base part to cover the upper cap module and the upper cap fixing module;
Installing a panel at a predetermined height above the formed foundation;
Performing a backfill construction work toward the rear side of the panel; And
Cutting the installed front lower side slope of the panel;
Cut panel panel retaining wall construction method provided with a foundation reinforcement plan comprising a.
삭제delete 제1항에 있어서,
상기 상부캡은 측면상 "T"자형으로 이루어지는,
기초부 보강방안이 구비된 절토부 패널식 옹벽 시공방법.
The method of claim 1,
The upper cap is made of a "T" shape on the side,
Cut panel retaining wall construction method provided with reinforcement plan of foundation part.
삭제delete
KR1020190001953A 2019-01-07 2019-01-07 Construction method of retaining wall using panel having base for reinforce KR102043582B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190001953A KR102043582B1 (en) 2019-01-07 2019-01-07 Construction method of retaining wall using panel having base for reinforce

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190001953A KR102043582B1 (en) 2019-01-07 2019-01-07 Construction method of retaining wall using panel having base for reinforce

Publications (1)

Publication Number Publication Date
KR102043582B1 true KR102043582B1 (en) 2019-11-11

Family

ID=68535796

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190001953A KR102043582B1 (en) 2019-01-07 2019-01-07 Construction method of retaining wall using panel having base for reinforce

Country Status (1)

Country Link
KR (1) KR102043582B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113174994A (en) * 2021-03-24 2021-07-27 湖北省路桥集团有限公司 Construction method of high retaining wall structure with complex steep terrain

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100967897B1 (en) * 2009-11-04 2010-07-06 주식회사 에스지오텍 Construction methods using apparatus for reinforcing inclined plane used in retaining wall
KR101785677B1 (en) 2017-04-15 2017-10-17 류근호 Construction method of retaining wall using precast slope panel
KR101864544B1 (en) * 2017-08-09 2018-06-05 썬엔지니어링 (주) Distribution plate unit for connecting rebar and distribution structure of micropile and smallcaliber pile using of the same

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100967897B1 (en) * 2009-11-04 2010-07-06 주식회사 에스지오텍 Construction methods using apparatus for reinforcing inclined plane used in retaining wall
KR101785677B1 (en) 2017-04-15 2017-10-17 류근호 Construction method of retaining wall using precast slope panel
KR101864544B1 (en) * 2017-08-09 2018-06-05 썬엔지니어링 (주) Distribution plate unit for connecting rebar and distribution structure of micropile and smallcaliber pile using of the same

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113174994A (en) * 2021-03-24 2021-07-27 湖北省路桥集团有限公司 Construction method of high retaining wall structure with complex steep terrain

Similar Documents

Publication Publication Date Title
JP4010383B2 (en) Pile method
KR101696916B1 (en) Construction method of permanent wall with retaining wall combined PHC pile and steel pipe
KR100886922B1 (en) Footing reinforcing or structure recovering method
KR102195504B1 (en) Construction method for Eearth self-retaining wall using reinforcing member and CIP construction method
KR20090120092A (en) Precast concrete wall and construction method using the same
KR101195235B1 (en) Underground structure construction method using composite pile
KR102195510B1 (en) Construction method for earth self-retaining wall using reinforcing member and PHC pile
KR20210012525A (en) Steel structures and top-down method using it
KR102043582B1 (en) Construction method of retaining wall using panel having base for reinforce
KR100698912B1 (en) Applying method of the PHC pile as the footing with the column of building
JP2000352296A (en) Method o constructing passage just under underground structure
JP5456627B2 (en) Connection structure and method of connection between pile and steel column
KR100984040B1 (en) Method of reinforced earth retaining wall for cutting face through double reinforcing execution
JP6461690B2 (en) Foundation structure and foundation construction method
KR101032408B1 (en) Method of reinforced earth retaining wall for cutting face through reinforcing execution and concrete block
KR101253841B1 (en) Vertically Inserting Column into the Eccentrically Bored Hole & the Method Thereof
KR102150531B1 (en) Retaining wall structure using vertical underground insert and its construction method
JP4612422B2 (en) Construction method of structure and foundation structure used for it
JP2017197910A (en) Construction method of earth retaining wall structure, and earth retaining wall structure
KR20100076404A (en) Metal tubing picket with reinforced tip for auger-drilled piling method
JP3805342B2 (en) Yamadome wall structure
KR20090042395A (en) Retainning wall and its construction method
KR101876414B1 (en) Pile with reinforced tip and its construction method thereof
JP2858997B2 (en) Temporary support column used for reverse driving method
KR101567358B1 (en) Reinforced method using steel piles with ribs for foundation of building

Legal Events

Date Code Title Description
GRNT Written decision to grant