KR101753744B1 - Structure and Constructing Method of Integrated Pier-Base - Google Patents

Structure and Constructing Method of Integrated Pier-Base Download PDF

Info

Publication number
KR101753744B1
KR101753744B1 KR1020160045071A KR20160045071A KR101753744B1 KR 101753744 B1 KR101753744 B1 KR 101753744B1 KR 1020160045071 A KR1020160045071 A KR 1020160045071A KR 20160045071 A KR20160045071 A KR 20160045071A KR 101753744 B1 KR101753744 B1 KR 101753744B1
Authority
KR
South Korea
Prior art keywords
column
foundation
concrete
landfill
mold
Prior art date
Application number
KR1020160045071A
Other languages
Korean (ko)
Inventor
한효석
정원용
Original Assignee
(주)나눔시스템
정원용
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)나눔시스템, 정원용 filed Critical (주)나눔시스템
Priority to KR1020160045071A priority Critical patent/KR101753744B1/en
Application granted granted Critical
Publication of KR101753744B1 publication Critical patent/KR101753744B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • E02D27/08Reinforcements for flat foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/40Miscellaneous comprising stabilising elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Foundations (AREA)

Abstract

본 발명은 콘크리트 타설에 의해 기초부를 시공하고 이와 연속하여 기둥을 시공함에 있어서, 매립 거푸집을 하부지지프레임에 지지된 상태로 그 하부가 기초부에 매립되도록 배치하되, 매립 거푸집이 기둥 하단부의 외면에서 기둥 본체와 일체로 되도록 함과 동시에 기둥과 기초부 사이의 콘크리트 불연속면(cold joint)이 매립 거푸집 내에 존재하도록 함으로써, 기둥 하단부와 기초부 간의 연결부위에 대하여 우수한 구조적 안정성을 확보하고, 연직 상향으로 기둥의 중간 및 상부를 시공하기 위한 기둥 거푸집을 용이하게 설치할 수 있도록 함으로써 시공효율을 향상시킬 수 있는 "하부지지프레임 및 매립 거푸집을 이용한 기둥-기초부 일체 결합 시공방법 및 이에 의해 시공된 기둥-기초부 일체 결합 구조물"에 관한 것이다. The present invention is characterized in that a foundation is constructed by pouring concrete and a pillar is continuously constructed by arranging the bottom of the pillar in a state where the bottom of the pillar is supported by the lower support frame, And a cold joint between the column and the foundation is present in the embedding form so that excellent structural stability with respect to the connection between the lower end of the column and the foundation is ensured, Which can improve the efficiency of construction by allowing the column formwork for constructing the middle and upper part of the column and the upper part of the column to be easily installed, Integrally bonded structure ".

Figure R1020160045071
Figure R1020160045071

Description

기초부 보강 하부지지프레임 및 매립 거푸집을 이용한 기둥-기초부 일체 결합 시공방법 및 이에 의해 시공된 기둥-기초부 일체 결합 구조물{Structure and Constructing Method of Integrated Pier-Base}BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a pillar-to-foundation integral assembly method using a foundation-reinforced lower support frame and a buried form,

본 발명은 교량의 교각 등과 같은 기둥과 그 하부의 기초부를 일체로 결합하여 시공하는 방법 및 이에 의하여 시공되어 기둥과 그 하부의 기초부가 일체로 결합된 구조물에 관한 것으로서, 구체적으로는 콘크리트 타설에 의해 기초부를 시공하고 이와 연속하여 기둥을 시공함에 있어서, 매립 거푸집을 그 하부가 기초부에 매립되도록 배치하되, 매립 거푸집이 기둥 하단부의 외면에서 기둥 본체와 일체로 되도록 함과 동시에 기둥과 기초부 사이의 콘크리트 불연속면(cold joint)이 매립 거푸집 내에 존재하도록 함으로써 기둥 하단부와 기초부 간의 연결부위에 대하여 우수한 구조적 안정성을 확보하고, 연직 상향으로 기둥의 중간 및 상부를 시공하기 위한 기둥 거푸집을 용이하게 설치할 수 있도록 함으로써 시공효율을 향상시킬 수 있으며, 매립 거푸집을 지지하기 위한 하부지지프레임을 이용하여 기초부를 보강함으로써 기초부의 규모를 축소하거나 또는 기초부의 보강을 위한 보강철근의 사용량을 절감할 수 있는 "기초부 보강 하부지지프레임 및 매립 거푸집을 이용한 기둥-기초부 일체 결합 시공방법 및 이에 의해 시공된 기둥-기초부 일체 결합 구조물"에 관한 것이다. The present invention relates to a method of integrally joining a column such as a pier of a bridge and a foundation of a lower part thereof, and a structure in which the column and the foundation of the lower part are integrally joined. More specifically, The bottom of the embedding form is placed so as to be embedded in the base, wherein the embedding form is integrated with the column main body at the outer surface of the lower end of the column, and at the same time, In order to ensure the excellent structural stability of the joint between the lower part of the column and the foundation by making the concrete joint exist in the embankment form and to install the column formwork for the middle and upper part of the column vertically upward Thereby improving the efficiency of the construction, Which can reduce the scale of the foundation or reduce the amount of reinforcing steel used for reinforcement of the foundation, by reinforcing the foundation by using a lower support frame for supporting the foundation, An integral bonding method and a column-foundation integral bonding structure constructed thereby ".

교량의 교각과 같은 기둥과 기초부를 시공함에 있어서, 종래에는 콘크리트로 기초부를 시공 완료한 후, 기초부 위에 거푸집을 설치하고 콘크리트를 타설하여 기초부에 연속하여 기둥을 시공하는 것이 일반적이다. 도 1 내지 도 3에는 종래 기술에 따라 기초부와 기둥이 연속되도록 시공하는 과정을 순차적으로 보여주는 개략적인 사시도가 도시되어 있다. 우선 도 1에 도시된 것처럼 콘크리트에 의해 블록 형태의 기초부(2)를 제작하게 되는데, 이 때 기초부(2)의 콘크리트에 매립된 기초부 보강용 철근조립체의 연직결합철근(21)을 상면에 돌출시킨다. 기초부(2)의 콘크리트 양생이 이루어진 후, 도 2에 도시된 것처럼 기둥을 위한 기둥 거푸집(4)을 조립하여 기초부(2) 위에 설치하게 된다. 이 때 연직결합철근(21)은 기둥 거푸집(4) 내에 위치한다. 기둥 거푸집(4)의 조립이 완료되면 기둥 거푸집(4) 내에 기둥보강철근망을 배치하고 기둥보강철근망을 연직결합철근(21)과 연결한 후, 도 3에 도시된 것처럼 기둥 거푸집(4) 내에 콘크리트를 타설하여 기둥(1)의 하부를 기초부(2)위에 시공한다. 후속하여 추가적인 기둥 거푸집(4)을 연직하게 적층하여 조립 설치하고 콘크리트를 타설하는 과정을 반복하여 설계된 높이의 기둥(1)을 시공하게 된다. Conventionally, in the construction of columns and bases such as piers of bridges, it is common to install piles on concrete bases and concrete piles on concrete bases. FIGS. 1 to 3 are schematic perspective views sequentially illustrating a process of constructing a foundation and a column so that they are continuous according to the related art. 1, a block-shaped base 2 is manufactured by using a concrete. At this time, the vertical joining reinforcing bars 21 of the reinforcing bars for reinforcing the base portion embedded in the concrete of the base portion 2, . After the concrete curing of the foundation part 2 is completed, the column formwork 4 for the column is assembled as shown in FIG. 2 and installed on the foundation part 2. At this time, the vertical joining reinforcing bars 21 are located in the pillar mold 4. Once the column formwork 4 has been assembled, a column reinforcing steel net is disposed in the column form 4 and the column reinforcing steel net is connected to the vertical joining reinforcing bar 21. Then, as shown in FIG. 3, And the lower part of the column 1 is placed on the foundation part 2. [ Subsequently, an additional column 4 is stacked vertically, assembled, and concrete is laid repeatedly, thereby constructing a column 1 of designed height.

그런데 이와 같은 종래 기술의 경우, 기초부(2)가 완성된 상태에서 기초부(2) 상면에 기둥 거푸집(4)을 조립하여 위치시키게 되므로, 만일 기초부(2)의 상면이 평탄하지 않을 경우에는 기둥 거푸집(4)이 기울어지게 되어 기둥 거푸집(4)에 의해 만들어진 기둥(1)이 설계된 연직도를 가지지 못하게 된다. 이를 방지하기 위해서는 기초부(2)의 상면을 평판하게 만드는 작업을 반드시 수행하여야 하는데, 예를 들어 기초부(2)의 상면을 그라인더 등으로 갈아서 평탄하게 만들거나 또는 판재 등을 기초부(2)의 상면에 포설하여 기초부(2) 상면의 평탄성을 확보한 후에야 기둥 거푸집(4)을 설치할 수 있게 된다. 이와 같이 종래 기술에서는 "그라인딩 작업, 판재 설치작업 등을 이용한 기초부(2) 상면 평탄성 확보"라는 추가적인 작업이 수반되어야 하는데, 그라인딩 작업 등에는 많은 소음과 분진이 발생하게 되어 주변 환경에 악영향을 줄 뿐만 아니라, 작업 자체도 번거롭고 비용과 시간이 많이 소요되므로 작업 효율성이 저하되어 시공비 및 시공기간의 증가를 피할 수 없게 되는 단점이 있다. However, in such a conventional technique, since the column mold 4 is assembled and positioned on the upper surface of the base portion 2 in a state where the base portion 2 is completed, if the upper surface of the base portion 2 is not flat The column mold 4 is tilted so that the column 1 made by the column mold 4 does not have the designed verticalness. In order to prevent this, it is necessary to perform an operation of flattening the upper surface of the base portion 2. For example, the upper surface of the base portion 2 may be ground by a grinder or the like, It is possible to install the column formwork 4 only after securing the flatness of the upper surface of the base portion 2. [ As described above, in the prior art, an additional work such as "ensuring the flatness of the top surface 2 of the base part 2 by using a grinding operation and a plate material installation work" must be accompanied by an additional work. In grinding work, etc., much noise and dust are generated, In addition, since the work itself is cumbersome and takes a lot of cost and time, the work efficiency is lowered and the construction cost and the construction period can not be increased.

또한 기둥 거푸집(4)이 단순히 기초부(2)의 상면에 놓이는 것이므로, 기둥 거푸집(4)의 전도나 기울어짐, 또는 수평이동을 방지하기 위하여 종래 기술에서는 기둥 거푸집(4)의 측면과 기초부(2) 상면 사이에 보조지지부재(9)를 설치할 필요가 있다. 따라서 종래 기술에서는 보조지지부재(9)의 설치에 따른 작업효율 저하, 비용 증가, 시공기간의 증가가 수반될 수밖에 없다. Since the column formwork 4 is simply placed on the upper surface of the foundation section 2 in order to prevent the column formwork 4 from being tilted or tilted or horizontally moved, It is necessary to provide an auxiliary supporting member 9 between the upper surfaces of the supporting members 2. Therefore, in the prior art, it is inevitably accompanied by a decrease in working efficiency, an increase in costs, and an increase in a construction period due to the installation of the auxiliary supporting member 9.

무엇보다도 종래 기술에서는 기초부(2)와 기둥 하단 사이에 콘크리트 불연속면(cold joint)이 존재할 수밖에 없다는 구조적인 약점을 가지고 있다. 기둥 거푸집(4)은 콘크리트의 높은 타설압력을 견딜 수 있도록 강재로 제작되므로 그 자체의 무게가 상당하다. 따라서 종래 기술에서는 기둥 거푸집(4)을 설치하기에 앞서, 기초부(2)의 상면이 기둥 거푸집(4)의 무게를 지지할 수 있을 만큼 기초부(2)의 콘크리트가 충분히 양생되어 사실상 기초부(2)가 완성되어 있어야 한다. 이와 같이 종래 기술에서는 기초부(2)의 상면이 양생되어 기초부(2)가 완성된 후에야 비로소 기초부(2) 위에 기둥(1)을 위한 콘크리트가 타설되므로, 기둥(1)의 콘크리트와 기초부(2)의 콘크리트 사이에는 상당한 시간 간격의 콘크리트 타설 시기 차이가 존재할 수밖에 없고, 이로 인하여 기초부(2)와 기둥 하단 사이에는 콘크리트가 서로 일체화되지 않은 콘크리트 불연속면(cold joint)이 존재할 수밖에 없게 되는 것이다. 도 4에는 위와 같은 종래 기술에 의해 시공된 기둥-기초부 결합 구조물 하부에서 기초부와 기둥 하단 사이에 콘크리트 불연속면(J)이 형성된 것을 보여주는 개략적인 단면도가 도시되어 있다. 도 4에서는 편의상 콘크리트에 매립되어 있는 철근의 도시는 생략하고, 오로지 콘크리트만을 도시하였다. Above all, the prior art has a structural weak point that a concrete joint must exist between the foundation 2 and the bottom of the column. The column formwork (4) is made of steel so as to withstand the high pouring pressure of the concrete, and therefore the weight itself is significant. Therefore, prior to installing the column formwork 4 in the prior art, the concrete of the foundation section 2 is sufficiently cured so that the upper surface of the foundation section 2 can support the weight of the column formwork 4, (2) must be completed. The concrete for the column 1 is placed on the foundation 2 only after the upper surface of the foundation 2 is cured and the foundation 2 is completed. There is a significant difference in time of concrete pouring time between the concrete of the part 2 and a concrete joint between the foundation part 2 and the lower part of the column is inevitably a cold joint which is not integrated with each other will be. FIG. 4 is a schematic cross-sectional view showing that a concrete discontinuity J is formed between the base portion and the bottom of the column at the lower portion of the column-foundation coupling structure constructed by the above conventional technique. In FIG. 4, for the sake of convenience, the illustration of the reinforcing bars embedded in the concrete is omitted, and only the concrete is shown.

기둥-기초부의 결합 구조물의 경우, 기둥과 기초부가 연속되는 부분에 큰 휨모멘트가 작용하게 되므로 기둥-기초부 간의 견고한 일체화가 매우 중요하다. 그런데 종래 기술에 의하면 위와 같이 기둥과 기초부가 연속되는 부분에 콘크리트 불연속면(J)이 존재할 수밖에 없어서, 기둥과 기초부가 연속되는 부분에서의 완전하고 견고한 일체화를 이루기 어렵게 되며 결과적으로 구조적으로 매우 취약한 상태가 된다. In the case of the joining structure of the column-base portion, since a large bending moment acts on the continuous portion of the column and the base portion, solid integration between the column and the base portion is very important. However, according to the prior art, there is a possibility that the concrete discontinuity surface J exists at the portion where the column and the base portion are continuous as described above, so that it is difficult to achieve complete and solid integration at the continuous portion of the column and the base portion, do.

이러한 구조적인 문제점 때문에, 대한민국 등록특허 제10-0830119호와 같은 선행특허에서는 기둥과 기초부 사이에 걸쳐서 추가적인 이형철근을 배치하고, 이형철근이 매립되도록 기둥 주변에 돌출된 형태의 콘크리트부를 추가로 더 타설하는 방식을 제시하고 있으나, 이러한 선행특허의 경우에도 기둥과 기초부 사이에는 콘크리트 불연속면(cold joint)이 여전히 존재하고 있어서 종래 기술의 위와 같은 문제점을 해결하지 못한 채, 오히려 단순히 부재의 단면 크기만을 증가시켜서 외관만 악화시키는 부작용만 초래하게 된다. In view of such a structural problem, in the prior arts such as Korean Patent No. 10-0830119, an additional deformed reinforcing bar is disposed between the column and the base portion, and a concrete portion protruding around the column is further provided However, in the case of this prior patent, there is still a concrete joint between the column and the base portion, so that the above-mentioned problems of the prior art can not be solved, And only the side effect which exacerbates the appearance is brought about.

대한민국 등록특허 제10-0830119호(2008. 05. 20. 공고).Korean Patent No. 10-0830119 (2008. 05. 20. Announcement).

본 발명은 위와 같은 종래 기술의 한계를 극복하기 위하여 개발된 것으로서, 기초부를 시공한 후 기둥을 기초부와 연속하여 시공함에 있어서, 기둥 시공을 위한 거푸집을 설계된 연직도를 갖도록 용이하게 설치할 수 있도록 함과 동시에 인장와이어 등과 같은 보조적인 지지부재의 설치 없이도 거푸집을 안정적으로 거푸집을 적층 설치할 수 있도록 하며, 더 나아가 기둥의 하단과 기초부 사이의 콘크리트 불연속면으로 인한 구조적인 취약점을 해소하여 기둥과 기초부가 구조적으로 견고하게 일체화될 수 있게 만드는 기둥-기초부 일체 결합 시공방법을 제공하는 것을 목적으로 한다. The present invention has been developed in order to overcome the limitations of the prior art as described above, and it is possible to easily install the mold for the column construction with the designed vertical degree when the column is continuously installed with the base after the foundation is constructed It is possible to stably form the formwork without the need of an auxiliary supporting member such as a tensile wire and to solve the structural weakness caused by the concrete discontinuity between the bottom of the column and the foundation, So that it is possible to firmly integrate the pillar-base integral assembly.

위와 같은 과제를 달성하기 위하여 본 발명에서는, 기초부에 기둥의 하단부가 결합된 기둥-기초부 결합 구조물의 시공방법으로서, 기초부의 제작을 위한 기초부 거푸집을 설치하고, 기초부 보강용 철근조립체를 제작하여 기초부 거푸집 내에 배치함과 동시에 또는 이에 후속하여 하부지지프레임을 기초부 거푸집 내에 배치하는 단계; 기둥의 연직방향 단면 형상에 대응되는 연직방향 단면을 가지는 통형상의 부재로 이루어진 매립 거푸집을, 그 하단이 기초부의 콘크리트에 매립될 수 있도록, 하부지지프레임에 의해 지지되는 상태로 하부지지프레임 위에 배치하는 단계; 기초부 거푸집 내에 1차 콘크리트를 타설하여 기초부 보강용 철근조립체와 하부지지프레임이 1차 콘크리트에 매립되도록 채움으로써 기초부를 제작하되, 매립 거푸집 내부에도 기초부의 상면보다 더 높지만 매립 거푸집의 최상단보다는 아래의 위치까지 콘크리트가 채워지도록 함으로써, 매립 거푸집의 하단이 상부에 매립되어 있는 상태로 기초부를 제작하는 단계; 매립 거푸집 위에 기둥의 시공을 위한 기둥 거푸집을 설치하는 단계; 기둥 거푸집 내에 기둥보강철근망을 삽입배치하고, 매립 거푸집 내에서 비어 있던 공간과 기둥 거푸집 내에 2차 콘크리트를 타설하여 기둥을 제작하는 단계; 및 매립 거푸집은 남겨둔 채로, 기둥 거푸집을 탈형하는 단계를 포함함으로써, 매립 거푸집의 하부가 기초부에 매립되고 매립 거푸집이 기둥의 하단부를 피복하여 기둥의 일부분을 이루고 있으며, 기초부와 기둥의 하단부를 이루도록 1차 타설된 콘크리트와 기둥의 본체를 이루도록 2차 타설된 콘크리트 사이의 콘크리트 불연속면이 매립 거푸집 내에 위치하게 되도록 하는 것을 특징으로 하는 기둥-기초부 일체 결합 구조물의 시공방법이 제공된다. In order to accomplish the above object, according to the present invention, there is provided a method of constructing a column-foundation coupling structure in which a lower end of a column is coupled to a foundation, comprising the steps of providing a base part for making a base part, Disposing a lower support frame in the base mold at the same time as or after being fabricated and placed in the base mold; The buried form consisting of a tubular member having a vertical cross section corresponding to the vertical sectional shape of the column is placed on the lower support frame in a state of being supported by the lower support frame so that the lower end thereof can be embedded in the concrete in the foundation ; The primary concrete is laid in the base part form so that the reinforcing assembly for the foundation part and the lower supporting frame are filled in the primary concrete to form the base part. The inside of the buried formwork is higher than the upper part of the foundation part, So that the concrete is filled up to the position of the bottom of the embedment form; Installing a column mold for the installation of the column on the landfill form; A step of inserting a column reinforcing steel net in a column formwork, preparing a column by placing a secondary concrete in a vacant space and a column formwork in an embedment formwork; And a step of demolding the column form with the buried form left, whereby the lower part of the buried form is buried in the foundation, the buried form covers the lower end of the column to form a part of the column, and the base part and the lower part of the column Wherein a concrete discontinuity between the first laid concrete and the second laid concrete so as to form the main body of the column is positioned in the embedding formwork.

상기한 본 발명의 시공방법에서. 매립 거푸집의 하단부에서 매립 거푸집의 하단 가장자리에는 위쪽으로 오목하게 파인 오목부가 형성되어 있으며; 매립 거푸집을 하부지지프레임 위에 배치하는 단계에서는, 기초부 보강용 철근조립체의 수평철근이 오목부 내에 위치하도록 매립 거푸집을 설치하게 될 수 있다. In the construction method of the present invention described above. At the lower end of the embedment form, a concave depression is formed at the lower edge of the embedment form upwardly; In the step of disposing the embedding form on the lower support frame, the embedding form may be installed such that the horizontal reinforcing bars of the foundation reinforcing steel assembly are located in the recesses.

더 나아가 상기한 본 발명의 시공방법에서는 매립 거푸집의 외면에는, 거푸집 지지대가 외측으로 돌출된 상태로 구비되어 있으며; 매립 거푸집 위에 기둥의 시공을 위한 기둥 거푸집을 설치하는 단계에서는, 기둥 거푸집의 하단을 거푸집 지지대 위에 놓은 후, 기둥 거푸집과 거푸집 지지대를 연결판에 의해 일체로 조립하는 구성을 가질 수도 있다. Furthermore, in the above-described construction method of the present invention, the mold support is provided on the outer surface of the embedment form so as to protrude outwardly; In the step of installing the column formwork for constructing the column on the embedment formwork, the lower end of the column formwork may be placed on the formwork support, and then the column formwork and the formwork support may be integrally assembled by the connecting plate.

아울러 본 발명에서는 상기한 목적을 달성하기 위하여, 위에서 설명한 본 발명에 따른 시공방법에 의해 시공되어, 매립 거푸집의 하부가 기초부에 매립되고 매립 거푸집이 기둥의 하단부를 피복하여 기둥의 일부분을 이루고 있으며, 기초부와 기둥의 하단부를 이루도록 1차 타설된 콘크리트와 기둥의 본체를 이루도록 2차 타설된 콘크리트 사이의 콘크리트 불연속면이 매립 거푸집 내에 위치하는 구성을 가지게 되는 것을 특징으로 하는 기초부에 기둥의 하단부가 결합된 기둥-기초부 결합 구조물이 제공된다. In order to attain the above object, the present invention provides a method for constructing a pillar of a building, comprising the steps of: constructing a pillar of the pillar by inserting a lower part of the pillar into a base part; And a concrete discontinuity surface between the first concrete laid so as to form the base portion and the lower portion of the column and the concrete laid secondarily to form the main body of the column is located in the landfill form. A combined column-base bonded structure is provided.

본 발명에 의하면, 기둥과 기초부간의 콘크리트 불연속면이, 기초부의 상면에 존재하는 것이 아니라, 기초부에 하단부가 매립된 매립 거푸집의 내부에 존재하게 되며, 그에 따라 기둥과 기초부가 완전하고 견고한 일체화를 이룰 수 있게 되고 기둥-기초부의 접합 위치에서는 매우 큰 휨모멘트 저항력이 발휘되어 구조적으로 매우 안정적이고 견고한 기둥-기초부의 접합 상태가 만들어지게 되는 장점이 있다. According to the present invention, the concrete discontinuity between the column and the base part does not exist on the upper surface of the base part, but exists inside the buried formwork in which the lower part is embedded in the base part, And a very large bending moment resistance is exerted at the joining position of the column-base portion, so that there is an advantage that the joining state of the column-base portion is structurally very stable and rigid.

또한 본 발명에서는 기초부에 연속하여 기둥이 시공됨에 있어서, 큰 휨모멘트가 작용하게 되는 기둥의 하단부가 매립 거푸집에 의해 피복된 상태가 되며, 그에 따라 기둥 하단부에서의 휨강성이 더욱 증가하게 되며, 그에 따라 구조적으로 더욱 안전한 기둥을 구축할 수 있게 되는 장점이 있다. Further, in the present invention, when the column is continuously installed on the base portion, the lower end portion of the column to which a large bending moment is applied is covered by the buried formwork, thereby further increasing the bending stiffness at the column bottom portion, Therefore, there is an advantage that a more secure structure can be constructed.

또한 본 발명에서는 콘크리트를 타설하기 전에 매립 거푸집의 연직도를 설계에 맞춰 조정해둔 상태이므로, 1차 콘크리트를 타설하여 기초부와 매립 거푸집 내부에서의 기둥 하단 일부를 일체 시공한 후, 매립 거푸집 위에 기둥 거푸집을 적층 설치할 때에는 추가적으로 기둥 거푸집의 연직도를 조정하지 않고서도 설계된 연직도를 가지는 기둥을 용이하게 시공할 수 있게 된다. 따라서 본 발명에서는 종래 기술에서 요구되었던 기초부 상면의 평탄성 확보를 위한 추가적인 작업이 전혀 필요하지 않으며, 그에 따라 종래 기술보다 월등히 향상된 작업 효율성을 발휘할 수 있게 되어, 시공비의 절감 및 시공기간의 단축의 잇점이 발휘된다. In the present invention, since the vertical degree of the embedding form is adjusted according to the design before the concrete is laid, a part of the lower part of the column in the base part and the inside of the embedding formwork is integrally constructed by pouring the primary concrete, When the formwork is laminated, it is possible to easily construct the column having the designed vertical degree without adjusting the verticality of the column formwork. Therefore, the present invention does not require any additional work for securing the flatness of the upper surface of the foundation, which is required in the prior art, and thus can exert a significantly improved working efficiency over the prior art, thereby reducing the construction cost and shortening the construction period .

더 나아가, 본 발명에서는 기둥 거푸집을 지지하는 매립 거푸집은, 그 하단부가 기초부의 콘크리트에 매립된 상태로 견고하게 설치 위치를 유지하게 되므로, 매립 거푸집과 기둥 거푸집을 서로 견고하게 결합하는 것만으로도 기둥 거푸집을 안정적으로 연직 설치할 수 있게 되며, 그에 따라 종래 기술에서 필요로 하였던 기둥 거푸집의 전도, 기울어짐, 또는 수평이동을 방지를 위한 보조지지부재의 설치 작업이 필요하지 않게 되며, 그에 따라 추가적인 작업효율 향상, 시공비 절감 및 시공기간 단축의 잇점을 발휘하게 된다. Further, in the present invention, since the lower end portion of the embedment die supporting the column formwork is firmly installed at a state where the lower end portion thereof is embedded in the concrete of the foundation portion, by merely firmly engaging the embedment formwork and the column formwork, It is possible to stably install the formwork vertically and accordingly it is not necessary to install the auxiliary support member for preventing the conduction, tilting, or horizontal movement of the column formwork, which is required in the prior art, Improvement of construction cost, and shortening of construction time.

도 1 내지 도 3는 각각 종래 기술에 따라 기초부와 기둥이 연속되도록 시공하는 과정을 순차적으로 보여주는 개략적인 사시도이다.
도 4는 종래 기술에 의해 시공된 기둥-기초부 결합 구조물 하부에서 기초부와 기둥 하단 사이에 콘크리트 불연속면이 형성된 것을 보여주는 개략적인 단면도이다.
도 5 및 도 6은 각각 본 발명의 시공방법에서 이용되는 매립 거푸집의 일예를 바라보는 방향을 달리하여 보여주는 개략적인 사시도이다.
도 7은 도 5의 선 A-A에 따른 개략적인 반단면 사시도이다.
도 8은 본 발명에서 수평방향의 양측 부재를 서로 마주하여 통형상의 매립 거푸집을 조립하는 상태를 보여주는 개략적인 분해 사시도이다.
도 9는 하단부 가장자리에 오목부가 형성된 본 발명의 매립 거푸집을 기초부 보강용 철근조립체의 수평철근 위에 배치한 상태를 보여주는 개략적인 사시도이다.
도 10은 본 발명에서 매립 거푸집이 기초부 보강용 철근조립체의 수평철근 위에 배치되는 상태를 보여주는 개략적인 부분 측면도이다.
도 11은 본 발명에 따라 기초부 보강용 철근조립체의 상부에 매립 거푸집을 배치한 상태를 보여주는 개략적인 측면도이다.
도 12는 본 발명에 따라 기초부의 거푸집과 매립 거푸집 내의 일부 높이까지 1차적인 콘크리트가 타설된 상태를 보여주는 개략적인 단면도이다.
도 13은 본 발명에 따라 매립 거푸집 위에 기둥 거푸집을 적층 설치한 상태를 보여주는 개략적인 측면도이다.
도 14는 도 13에 도시된 상태에 후속하여, 본 발명에 따라 매립 거푸집의 내부 및 기둥 거푸집의 내부에 2차적인 콘크리트를 타설한 상태를 보여주는 개략적인 단면도이다.
도 15는 본 발명의 시공방법에 의해 기둥-기초부 결합 구조물이 시공됨으로써 매립 거푸집 내의 위치에서 콘크리트 불연속면이 형성된 것을 보여주는 개략적인 단면도이다.
FIGS. 1 to 3 are schematic perspective views sequentially illustrating a process of constructing a foundation and a column so that they are continuous according to the related art.
FIG. 4 is a schematic cross-sectional view showing that a concrete discontinuity is formed between a base portion and a bottom of a column at the bottom of a column-base attachment structure constructed by a conventional technique.
FIG. 5 and FIG. 6 are schematic perspective views showing different directions of an example of a landfill mold used in the construction method of the present invention.
7 is a schematic half cross-sectional perspective view along line AA of FIG.
8 is a schematic exploded perspective view showing a state in which a tubular embedding mold is assembled with both side members in the horizontal direction facing each other in the present invention.
9 is a schematic perspective view showing a state in which the embedding form of the present invention, in which a concave portion is formed at a lower end edge, is disposed on a horizontal reinforcing bar of a foundation reinforcing steel assembly;
10 is a schematic partial side view showing a state in which the embedding form is disposed on a horizontal reinforcing bar of a reinforcing bar assembly of a foundation part in the present invention.
11 is a schematic side view showing a state in which a buried formwork is disposed on an upper portion of a foundation reinforcing steel assembly according to the present invention.
12 is a schematic sectional view showing a state in which a primary concrete is laid up to a height of a part of a base part and a buried formwork according to the present invention.
FIG. 13 is a schematic side view showing a state in which a column form is stacked on an embedding form according to the present invention.
14 is a schematic cross-sectional view showing a state in which a secondary concrete is laid in the inside of the landfill mold and the inside of the pillar mold according to the present invention, following the state shown in Fig.
15 is a schematic cross-sectional view showing that a concrete discontinuity is formed at a position in a buried formwork after the column-foundation bonded structure is constructed by the construction method of the present invention.

이하, 본 발명의 바람직한 실시예를 첨부한 도면을 참조하여 설명한다. 본 발명은 도면에 도시된 실시예를 참고로 설명되었으나 이는 하나의 실시예로서 설명되는 것이며, 이것에 의해 본 발명의 기술적 사상과 그 핵심 구성 및 작용이 제한되지 않는다. Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings. Although the present invention has been described with reference to the embodiments shown in the drawings, it is to be understood that the technical idea of the present invention and its essential structure and operation are not limited thereby.

본 발명에 따른 기둥-기초부 일체 결합 시공방법에서는, 우선 기초부를 시공할 때, 매립 거푸집의 하단부가 기초부의 콘크리트에 매립되도록 기초부를 위한 콘크리트를 타설함으로써, 기초부의 상면에 매립 거푸집이 고정 배치되어 있는 상태로 기초부를 제작하게 된다. In the pillar-to-foundation integrally bonded construction method according to the present invention, the concrete for the foundation is placed so that the lower end of the buried formwork is embedded in the concrete at the time of constructing the foundation, so that the buried formwork is fixedly disposed on the upper surface of the foundation The base portion is produced.

도 5 및 도 6에는 각각 본 발명의 시공방법에서 이용되는 매립 거푸집(3)의 일예를 바라보는 방향을 달리하여 보여주는 개략적인 사시도가 도시되어 있다. 도 7에는 도 5의 선 A-A에 따른 개략적인 반단면 사시도가 도시되어 있으며, 도 8에는 수평방향의 양측 부재를 서로 마주하여 통형상의 매립 거푸집(3)을 조립하는 상태를 보여주는 개략적인 분해 사시도가 도시되어 있다. FIGS. 5 and 6 are schematic perspective views showing different views of an example of the landfill mold 3 used in the construction method of the present invention. Fig. 7 is a schematic half cross-sectional perspective view taken along the line AA in Fig. 5, and Fig. 8 is a schematic exploded perspective view showing a state in which a tubular embedding mold 3 is assembled with both side members in the horizontal direction facing each other Are shown.

도 5 내지 도 8에 예시된 것처럼, 매립 거푸집(3)은, 시공하고자 하는 기둥(1)의 연직방향 단면 형상에 대응되는 연직방향 단면을 가지는 통형상의 부재를 포함하는데, 통형상 부재로 이루어진 매립 거푸집(3)의 외면에는, 매립 거푸집(3) 위에 기둥 제작을 위한 기둥 거푸집(4)이 놓여서 적층될 수 있게 하는 거푸집 지지대(31)가 외측으로 돌출된 상태로 구비되어 있다. 도면에 예시된 실시예의 경우, 거푸집 지지대(31)는 연직한 판부재로 이루어져서 매립 거푸집(3)의 상단에서 원주를 따라 간격을 두고 복수개로 구비되어 있다. 이러한 거푸집 지지대(31)는 후술하는 것처럼 기둥 거푸집(4)을 지지하는 기능을 가지고 있지만, 이에 더하여 기둥 거푸집(4)과 매립 거푸집(3)을 일체로 결합하는데 이용될 수도 있다. 이에 대해서는 후술한다. 5 to 8, the embedding mold 3 includes a tubular member having a vertical cross section corresponding to the vertical cross-sectional shape of the column 1 to be installed, On the outer surface of the landfill mold 3, there is provided a formwork support 31 which protrudes outward so that the column mold 4 for laying the column can be laid on the landfill 3. In the embodiment illustrated in the figures, the form supports 31 are comprised of a vertical plate member and are provided at a plurality of intervals along the circumference at the top of the embedding form 3. The mold support 31 has a function of supporting the column mold 4 as described later. In addition, the mold support 4 and the buried form 3 can be integrally combined. This will be described later.

한편, 매립 거푸집(3)의 내면에는 구조적인 보강 및 콘크리트와의 일체화를 위한 보강매립재(30)가 돌출된 형태로 구비될 수도 있다. 도면에 예시된 실시예에서 보강매립재(30)는 판부재로 이루어져서 연직하게 배치되어 매립 거푸집(3)의 내면에 돌출된 상태로 용접 등의 방법에 의해 일체로 부착 구비되어 있다. 필요에 따라서는 판부재로 이루어진 보강매립재(30)를 콘크리트가 통과하도록 하여 콘크리트와의 일체화를 더욱 강화시키기 위하여 보강매립재(30)에는 통과공(32)이 형성될 수도 있다. On the other hand, a reinforced embedding material 30 for structural reinforcement and integration with concrete may be provided on the inner surface of the embedding form 3. In the embodiment illustrated in the drawings, the reinforced embedding member 30 is integrally attached by a method such as welding in a state of being formed of a plate member and vertically arranged and protruding from the inner surface of the embedding formwork 3. [ A through hole 32 may be formed in the reinforced buried material 30 in order to allow the concrete to pass through the reinforced buried material 30 formed of the plate member to further strengthen the integration with the concrete.

매립 거푸집(3)은 강관처럼 하나의 통형상 부재로 이루어질 수 있지만 수평방향으로 조립되는 구성을 가질 수 있다. 이와 같이 매립 거푸집(3)이 수평방향으로 조립되는 구성을 가지는 경우, 보강매립재(30)를 판부재로 제작하게 되면, 매립 거푸집(3)을 이루는 수평방향의 양측 부재를 서로 마주하여 통형상으로 만들었을 때, 판부재의 보강매립재(30)가 서로 접하도록 한 상태에서 볼트 등의 체결부재를 보강매립재(30)에 관통시켜 결합함으로써, 용이하게 수평방향의 양측 부재를 서로 마주하여 원통형의 매립 거푸집(3)을 조립 제작할 수 있게 된다. 물론 보강매립재(30)와 별도로 판형의 결합플랜지를 매립 거푸집(3) 내에 설치하여 수평방향의 양측 부재를 서로 마주하여 통형상으로 만들었을 때 결합플랜지가 서로 접하도록 하고 위와 같이 체결부재를 이용하여 결합하도록 구성할 수도 있다. 도면에는 도시되지 않았지만, 매립 거푸집(3)은 연직방향으로도 복수개로 분할된 것이 적층 결합되는 구성을 가질 수도 있다. The landfill mold 3 may be made of a single tubular member, such as a steel pipe, but may have a construction that is assembled in the horizontal direction. In the case where the embedding form 3 is assembled in the horizontal direction as described above, when the reinforced embedding material 30 is made of a plate member, the horizontal two side members constituting the embedding form 3 face each other, The reinforcing embedding member 30 of the plate member is brought into contact with each other so that the fastening member such as a bolt is inserted through the reinforcing filler 30 so as to easily face the both side members in the horizontal direction The cylindrical buried formwork 3 can be assembled and manufactured. Of course, when the plate-shaped coupling flange is provided in the landfill mold 3 separately from the reinforced filler 30 so that the coupling flanges are brought into contact with each other when the both side members in the horizontal direction are made to face each other, So as to be combined. Although not shown in the drawing, the embedding form 3 may have a structure in which a plurality of divided parts in the vertical direction are laminated.

한편, 보강매립재(30)는 판부재로 이루어지되, 도면에 예시된 것처럼 절곡된 판부재로 이루어질 수도 있다. 보강매립재(30)는 매립 거푸집(3)의 연직 높이 전체에 걸쳐 구비될 수도 있지만 연직 높이의 일부분에만 구비될 수도 있다. 더 나아가 이러한 보강매립재(30)는 생략할 수도 있다. On the other hand, the reinforced embedding material 30 may be a plate member, and may be a bent plate member as illustrated in the drawing. The reinforced embedding material 30 may be provided over the entire vertical height of the embedding form 3, but may be provided only at a part of the vertical height. Further, such reinforced embedding material 30 may be omitted.

한편, 본 발명에 따른 매립 거푸집(3)의 하단부에서 매립 거푸집(3)의 하단 가장자리에는 위쪽으로 오목하게 파인 오목부(36)가 형성될 수 있다. 본 발명에서 매립 거푸집(3)은 그 하부가 기초부(2)의 콘크리트에 매립된다. 기초부(2)에는 보강을 위한 철근조립체(기초부 보강용 철근조립체)가 콘크리트에 매립되며, 이러한 기초부 보강용 철근조립체에는 수평철근이 구비되어 있다. 그러므로 매립 거푸집(3)을 설치할 때, 매립 거푸집(3)은 기초부 보강용 철근조립체의 수평철근 위에 위치할 수밖에 없다. 이와 같이 매립 거푸집(3)이 기초부 보강용 철근조립체의 수평철근 위에 놓을 때, 매립 거푸집(3)의 하단부 가장자리가 기초부 보강용 철근조립체의 수평철근 위에 직접 놓이게 되면, 매립 거푸집(3)의 하부가 기초부(2)의 콘크리트에 매립되는 깊이는 결국 기초부 보강용 철근조립체를 이루는 수평철근의 피복두께로 제한된다. 즉, 수평철근의 피복두께 만큼만 매립 거푸집(3)의 하부가 기초부(2)의 콘크리트에 매립되므로, 만일 수평철근의 피복두께가 작은 경우에는 매립 거푸집(3)의 콘크리트 매립깊이(매립 거푸집(3)의 하부가 기초부(2)의 콘크리트에 매립되는 깊이)도 작아지게 되는 것이다. 본 발명에서 오목부(36)를 형성함으로써, 이러한 매립 거푸집(3)의 콘크리트 매립깊이를 더 증가시키게 되는 유리한 효과가 발휘된다. In the lower end of the landfill 3 according to the present invention, a concave portion 36 may be formed at the lower edge of the landfill 3 in an upwardly concave manner. In the present invention, the bottom of the landfill 3 is embedded in the concrete of the foundation 2. A reinforcing assembly for reinforcement (base reinforcing steel reinforcing assembly) is embedded in the concrete in the base portion 2. The reinforcing steel assembly for reinforcing the base portion is provided with horizontal reinforcing bars. Therefore, when installing the landfill 3, the landfill 3 must be positioned above the horizontal reinforcing bars of the reinforcing steel assembly for the foundation. When the bottom end edge of the embedding form 3 is directly placed on the horizontal reinforcement of the foundation reinforcement assembly when the embedding form 3 is placed on the horizontal reinforcement of the foundation reinforcement reinforcement assembly 3, The depth at which the bottom is embedded in the concrete of the foundation 2 is ultimately limited to the thickness of the covering of the horizontal reinforcing bars constituting the foundation reinforcing steel assembly. That is, the lower portion of the embedding form 3 is embedded in the concrete of the foundation 2 only by the coating thickness of the horizontal reinforcement. If the covering thickness of the horizontal reinforcement is small, the concrete embedment depth of the embedding form 3 3) is embedded in the concrete of the foundation 2) is also reduced. By forming the recess 36 in the present invention, an advantageous effect of further increasing the depth of concrete embedding of the embedding form 3 is exhibited.

도 9에는 하부지지프레임(33)을 이용하여 매립 거푸집(3)을 설치한 상태를 보여주는 개략적인 사시도가 도시되어 있다. 기초부를 형성하기 위한 기초부 거푸집(도시를 생략함) 내에 기초부 보강용 철근조립체를 배근하기에 앞서 또는 기초부 보강용 철근조립체의 배근과 동시에, 매립 거푸집(3)을 그 하부에서 지지하기 위한 하부지지프레임(33)을 우선적으로 기초부 거푸집 내에 배치하게 된다. 도면에 도시된 실시예의 경우, 하부지지프레임(33)은 강재 빔을 사다리꼴 형태로 조립한 형태를 가지고 있는데, 특히 하부지지프레임(33)은 수평방향으로 길게 연장된 바닥수평빔(330)을 구비하고 있다. 하부지지프레임(33)을 강재 빔으로 형성하는 경우, 각각의 강재 빔에는 굳지 않은 콘크리트가 통과할 수 있는 통과공(35)이 형성되는 것이 바람직하다. 물론 바닥수평빔(330)에도 통과공(35)이 형성되는 것이 바람직하다. 이는 하부지지프레임(33)이, 기초부 형성을 위한 콘크리트 내에 매립되었을 때, 굳지 않은 콘크리트가 통과공(35)을 통과한 상태로 경화됨으로써, 하부지지프레임(33)과 기초부의 더욱 견고한 일체화가 이루어질 수 있기 때문이다. FIG. 9 is a schematic perspective view showing a state in which the landfill 3 is installed using the lower support frame 33. FIG. (Not shown) for laying the foundation reinforcing steel assembly in the base part for forming the base part or for supporting the filler mold 3 in the lower part thereof at the same time as the foundation of the base part reinforcing steel assembly The lower support frame 33 is preferentially placed in the base mold. In the embodiment shown in the drawing, the lower support frame 33 has a shape in which a steel beam is assembled into a trapezoidal shape. Particularly, the lower support frame 33 has a horizontal horizontal beam 330 . When the lower support frame 33 is formed of a steel beam, it is preferable that a through hole 35 through which the unhardened concrete can pass is formed in each steel beam. It is also preferable that a through hole 35 is formed in the horizontal horizontal beam 330 as well. This is because when the lower support frame 33 is embedded in the concrete for forming the base portion, the unhardened concrete is hardened while passing through the through hole 35, so that the lower support frame 33 and the base portion are more firmly integrated .

이러한 하부지지프레임(33)은 매립 거푸집(3)을 지지하는 기능 이외에도, 기초부에 매립된 보강재의 역할을 하게 되어 기초부를 보강하는 기능도 발휘하게 된다. 즉, 바닥수평빔(330)을 포함하는 하부지지프레임(33)의 설치에 의해 기초부 자체의 휨강성, 인장강성 등이 더욱 강화되어 보강되는 것이며, 그에 따라 기초부의 규모를 축소하거나 기초부 내에 매립되는 기초부 보강용 철근조립체의 물량을 줄일 수 있게 되어 더욱 경제적인 시공이 가능하게 되는 장점이 있다. In addition to the function of supporting the embedding mold 3, the lower supporting frame 33 also functions as a reinforcing member embedded in the base portion, thereby reinforcing the base portion. That is, by the provision of the lower support frame 33 including the horizontal horizontal beam 330, the flexural rigidity and the tensile rigidity of the foundation itself are further strengthened and reinforced. Accordingly, the scale of the foundation can be reduced, It is possible to reduce the amount of the reinforcing steel reinforcement assembly for the foundation part, thereby enabling a more economical construction.

그러나 본 발명에 있어서, 하부지지프레임(33)의 형태는 위와 같은 강재 빔을 이용한 형태에 한정되지 않으며 매립 거푸집(3) 부재를 지지할 수 있는 것이라면 다양한 형태로 구성될 수 있다.However, in the present invention, the shape of the lower support frame 33 is not limited to the shape using the steel beam as described above, but may be formed in various forms as long as it can support the landfill mold 3.

한편, 이와 같이 하부지지프레임(33)이 하부를 지지한 형태로 매립 거푸집(3)을 설치함에 있어서, 도면에 예시된 것처럼, 매립 거푸집(3)에 오목부(36)가 형성된 경우, 매립 거푸집(3)이 기초부 보강용 철근조립체의 수평철근(25) 위에 배치될 때 수평철근(25)이 오목부(36) 내에 위치할 수 있게 되며, 그만큼 매립 거푸집(3)의 콘크리트 매립깊이가 증가하게 된다. 도 10의 (a) 및 (b)에는 각각 매립 거푸집(3)에 오목부(36)가 없는 실시예와 오목부(36)이 존재하는 실시예가 기초부 보강용 철근조립체(28)의 수평철근(25) 위에 배치되는 상태를 보여주는 개략적인 부분 측면도가 도시되어 있다. When the recessed portion 36 is formed in the landfill mold 3 as shown in the figure when the landfill mold 3 is installed in such a manner that the lower supporting frame 33 supports the lower portion, The horizontal reinforcing bars 25 can be positioned in the concave portion 36 when the reinforcing bars 3 are disposed on the horizontal reinforcing bars 25 of the reinforcing bars for foundation, . 10A and 10B show an embodiment in which the recessed portion 36 is not provided in the embedding form 3 and the embodiment in which the recessed portion 36 is present in the embedment mold 3 in the horizontal reinforcing bars 28 Is shown on the top surface (25).

도 10의 (a)에 도시된 것처럼, 오목부(36)이 없는 경우에는 앞서 살펴본 것처럼 매립 거푸집(3)의 하단부 가장자리는 수평철근(25) 위에 직접 놓이게 되며, 그에 따라 매립 거푸집(3)의 콘크리트 매립깊이는 수평철근(25)의 피복두께(H1) 이하가 될 수밖에 없다. 그러나 도 10의 (b)에 도시된 것처럼 오목부(36)가 존재하는 경우에는 수평철근(25)이 오목부(36) 내에 위치하게 되어, 매립 거푸집(3)의 위치가 더 아래쪽으로 내려가게 되고, 그만큼 매립 거푸집(3)의 콘크리트 매립깊이(H2)는 도 10의 (a)에 도시된 경우에서의 콘크리트 매립깊이(H1)보다 더 커지게 된다. 매립 거푸집(3)의 콘크리트 매립깊이가 커진다는 것은, 매립 거푸집(3)과 기초부(2) 간의 결합 및 일체화가 더욱 견고해진다는 것을 의미한다. 물론 수평철근(25)의 피복두께가 상당히 커서 충분한 크기의 매립 거푸집(3)의 콘크리트 매립깊이가 확보된다면 오목부(36)은 생략할 수도 있다. 10 (a), in the absence of the recess 36, the lower end edge of the landfill mold 3 is directly placed on the horizontal reinforcing bar 25, as described above, The concrete embedment depth must be less than the covering thickness H1 of the horizontal reinforcing bars 25. [ 10 (b), however, the horizontal reinforcing bars 25 are located in the recesses 36 so that the position of the embedding molds 3 is further lowered So that the concrete embedment depth H2 of the embedding form 3 becomes larger than the concrete embedment depth H1 in the case shown in FIG. 10 (a). The fact that the depth of concrete buried in the landfill 3 is increased means that the bonding and integration between the landfill 3 and the foundation 2 becomes more robust. Of course, the concave portion 36 may be omitted if the thickness of the covering of the horizontal reinforcing bars 25 is considerably large and the depth of concrete filling of the filler mold 3 of a sufficient size is secured.

한편, 본 발명에 따른 매립 거푸집(3)의 하단부가 기초부(2)의 콘크리트에 매립되었을 때, 매립 거푸집(3)과 기초부(2) 간의 더욱 견고한 결합 및 일체화를 위하여, 기초부(2)의 콘크리트가 통과할 수 있는 통과공(35)이 매립 거푸집(3)의 하단부에 관통 형성된 형태로 구비될 수 있다. In order to make the bottom part of the embedding form 3 according to the present invention more firmly engaged and integrated between the embedding form 3 and the foundation part 2 when the lower end part of the embedding form 3 according to the present invention is embedded in the concrete of the foundation part 2, The through hole 35 through which the concrete of the concrete structure can pass can be formed through the lower end of the landfill 3.

다음에서는 상기한 매립 거푸집(3)을 이용한 본 발명에 따른 기둥-기초부 일체 결합 시공방법의 구체적인 방법 단계에 대해 설명한다. Hereinafter, concrete method steps of the column-foundation integral assembly method according to the present invention using the above-mentioned embedding form 3 will be described.

도 11에는 기초부 보강용 철근조립체(28), 하부지지프레임(33) 및 매립 거푸집(3)을 배치한 상태를 보여주는 개략적인 측면도가 도시되어 있다. 도 11에서 기초부 보강용 철근조립체(28)는 본 발명의 설명에 필요한 일부 부분만을 도시하였고, 기초부 거푸집은 도시를 생략하였다.  Fig. 11 is a schematic side view showing a state in which the foundation reinforcing steel reinforcing assembly 28, the lower support frame 33, and the embedding mold 3 are arranged. In FIG. 11, the foundation reinforcing steel assembly 28 shows only a part necessary for the description of the present invention, and the base mold is omitted.

우선 기초부(2)의 제작을 위한 기초부 거푸집을 설치하고, 기초부 보강용 철근조립체(28)을 제작하여 기초부 거푸집 내에 배치한다. 이러한 기초부 보강용 철근조립체(28)의 배치와 동시에 또는 그에 후속하여 앞서 설명한 것처럼 하부지지프레임(33)을 기초부 거푸집 내에 배치한다. 후속하여 위에서 설명한 매립 거푸집(3)을 하부지지프레임(33)에 지지되는 형태로 배치한다. 즉, 하부지지프레임(33)에 의해 지지되는 상태로 하부지지프레임(33) 위에 매립 거푸집(3)을 설치하는 것이다. 한편, 도 11에는 도시되어 있지 않지만, 종래 기술과 마찬가지로, 기초부 보강용 철근조립체(28)에서 기둥보강철근망(40)과 연결될 연직결합철근(21)은 매립 거푸집(3) 내에 위치한다. First, the base part formwork for the manufacture of the base part 2 is provided, and the base part reinforcing steel assembly 28 is manufactured and placed in the base part formwork. Simultaneously with or subsequent to the placement of the base reinforcement reinforcement assembly 28, the lower support frame 33 is disposed within the base framework as previously described. Subsequently, the above-described embedding mold 3 is disposed in such a manner as to be supported by the lower support frame 33. [ That is, the buried formwork 3 is installed on the lower support frame 33 while being supported by the lower support frame 33. 11, the vertical joining reinforcing bar 21 to be connected to the column reinforcing steel net 40 in the foundation reinforcing steel reinforcing assembly 28 is located in the embedding mold 3, as in the prior art.

매립 거푸집(3)의 설치가 완료되면, 기초부 거푸집 내에 콘크리트를 타설하여 기초부(2)를 제작하게 된다. 도 12에는 도 11의 상태에 후속하여, 기초부 거푸집 내부와 매립 거푸집(3) 내부의 소정 높이까지 1차적인 콘크리트가 타설되어 기초부(2)와 기둥의 하단 일부가 형성되어 있는 상태를 보여주는 개략적인 단면도가 도시되어 있다. When the installation of the embedding mold 3 is completed, the foundation 2 is produced by pouring concrete into the base part mold. 12 shows a state in which a primary concrete is laid up to a predetermined height in the inside of the base part formwork and the inside of the buried formwork 3 to form a part of the base part 2 and a lower part of the column A schematic cross section is shown.

종래 기술에서는 기둥 거푸집(4)이 기초부(2)의 상면에 놓여야 하므로, 기초부(2)의 콘크리트가 충분히 양생되어 경화된 후에야 비로소 기둥 거푸집(4)의 설치작업이 진행되지만, 본 발명에서는 위와 같이 기초부 거푸집 내에 콘크리트를 타설하여 기초부(2)의 형태를 만든 후, 아직 타설된 콘크리트의 외부 노출 표면이 경화되기 전의 상태에서 매립 거푸집(3)의 내부에도 연속하여 콘크리트를 타설한다. 즉, 기초부(2)의 형태를 만들기 위하여 기초부 거푸집 내에 콘크리트를 타설하고 약 20~30분 정도 경과된 후, 연속하여 매립 거푸집(3)의 내부에도 콘크리트를 타설하는 것이다. 이 때 매립 거푸집(3)의 전체 연직 높이에 걸쳐 매립 거푸집(3)에 가득 차도록 콘크리트가 채워지는 것이 아니라, 매립 거푸집(3)의 연직 높이(기초부의 상면으로부터 매립 거푸집의 최상단까지의 높이) 보다 작은 높이까지만 콘크리트가 매립 거푸집(3) 내에 채워진다. 즉, 매립 거푸집(3) 내에는 기초부의 상면보다 더 높은 위치까지 콘크리트가 채워지되, 매립 거푸집(3)의 최상단보다는 아래의 위치까지만 콘크리트가 채워지는 것이다. 이렇게 매립 거푸집(3) 내에 콘크리트가 채워졌을 때, 연직결합철근(21)은 그 상단이 매립 거푸집(3) 내의 콘크리트 상면으로부터 돌출된 상태에 있어야 한다. 이는 기둥보강철근망과 결합하기 위함이다. In the prior art, since the column mold 4 must be placed on the upper surface of the foundation 2, the installation of the column mold 4 proceeds only after the concrete of the foundation 2 is sufficiently cured and cured, The concrete is placed in the inside of the landfill form 3 in a state before the external exposed surface of the concrete still laid is cured and then the concrete is laid continuously in the inside of the landfill form 3 . That is, in order to make the shape of the base part 2, concrete is poured into the base part form, and after about 20 to 30 minutes has elapsed, the concrete is continuously poured into the inside of the buried form 3 as well. At this time, the concrete is not filled in the filling mold 3 over the entire vertical height of the filling mold 3 but the height of the filling mold 3 is higher than the vertical height (the height from the upper surface of the base portion to the uppermost end of the filling mold) Only up to a small height, the concrete is filled into the landfill mold 3. That is, the concrete is filled up to a position higher than the upper surface of the foundation part in the landfill form 3, and the concrete is filled up to a position lower than the uppermost part of the landfill formwork 3. When the concrete is filled in the embedding mold 3, the vertical joining reinforcing bar 21 should be in a state in which the upper end thereof protrudes from the upper surface of the concrete in the embedding mold 3. This is to combine with the column reinforcing steel net.

이와 같이, 본 발명에서는 기초부(2)를 위한 콘크리트의 외부 노출 표면이 경화되기 전에 매립 거푸집(3) 내에 소정 높이로 콘크리트가 채워지게 되고, 이렇게 매립 거푸집(3)에 채워진 콘크리트는 결국 기둥(1)의 하단부를 이루게 되므로, 기초부(2)의 콘크리트와 기둥(1)의 하단부 콘크리트는 일체로 연속되는 것이며 기초부(2)와 기둥(1)의 하단부는 하나의 부재로서 일체화된 상태로 제작되는 것이다. As described above, in the present invention, concrete is filled in the filling mold 3 at a predetermined height before the externally exposed surface of the concrete for the foundation 2 is cured, and the concrete filled in the filling mold 3 finally reaches the pillar The concrete of the foundation part 2 and the concrete of the lower end of the column 1 are integrally continuous and the base part 2 and the lower end part of the column 1 are integrally formed as a single member It is produced.

후속하여 매립 거푸집(3) 위에 기둥(1)의 시공을 위한 기둥 거푸집(4)을 조립하여 적층 설치한다. 도 13에는 매립 거푸집(3) 위에 기둥 거푸집(4)을 적층 설치한 상태를 보여주는 개략적인 측면도가 도시되어 있다. 기둥 거푸집(4)은 거푸집 지지대(31) 위에 놓여서 매립 거푸집(3)과 일체로 조립된다. 즉, 기둥 거푸집(4)의 하단이 거푸집 지지대(31) 위에 놓이는 것이다. 이 때, 기둥 거푸집(4)과 매립 거푸집(3)이 견고하게 조립되도록 하기 위하여, 도면에 도시되지는 않았지만, 예를 들어 기둥 거푸집(4)과 거푸집 지지대(31)에 걸쳐서 연결판을 배치한 후, 연결판과 거푸집 지지대(31)를 볼트결합하고, 연결판을 기둥 거푸집(4)과 볼트결합할 수도 있다. Subsequently, the column formwork (4) for constructing the column (1) is assembled on the landform formwork (3) and stacked. 13 is a schematic side view showing a state in which the column formwork 4 is stacked on the landform form 3. The pillar formwork 4 is placed on the formwork support 31 and assembled with the embedding formwork 3 in one piece. That is, the lower end of the column die 4 is placed on the die support 31. At this time, in order to firmly assemble the column formwork 4 and the embedding formwork 3, for example, a connecting plate is arranged over the column formwork 4 and the formwork support 31 The connection plate and the form support 31 may be bolted together and the connection plate may be bolted to the column form 4.

매립 거푸집(3) 위에 기둥 거푸집(4)을 조립 적층 설치한 후, 기둥 거푸집(4) 내에 기둥보강철근망(40)을 삽입배치하고, 기둥보강철근망(40)과 연직결합철근(21)을 연결한 다음에 기둥 거푸집(4) 내에 2차적인 콘크리트(42)를 타설하고, 콘크리트의 양생 후 기둥 거푸집(4)을 해체하여 기둥(1)을 제작한다. 도 14에는 도 13에 도시된 상태에 후속하여, 매립 거푸집(3)의 내부 및 기둥 거푸집(4)의 내부에 2차적인 콘크리트(42)를 타설한 상태를 보여주는 개략적인 단면도가 도시되어 있다. 필요에 따라서는 기둥 거푸집(4)의 설치, 콘크리트의 타설 및 기둥 거푸집(4)의 해체를 반복하여 설계된 높이를 가지는 기둥(1)을 제작하게 된다. After the column formwork 4 is assembled and stacked on the embedding form 3, the column reinforced reinforcing net 40 is inserted into the column formwork 4 and the column reinforced reinforcing net 40 and the vertically- A secondary concrete 42 is laid in the column form 4 and the column form 1 is manufactured by disassembling the column form 4 after the concrete is cured. Fig. 14 is a schematic cross-sectional view showing a state in which a secondary concrete 42 is laid in the inside of the buried formwork 3 and inside the pillar form 4, following the state shown in Fig. The column 1 having the designed height can be manufactured by repeating the installation of the column formwork 4, the insertion of the concrete, and the disassembly of the column formwork 4, if necessary.

종래 기술에서 기초부의 콘크리트 타설 시기와 기둥의 콘크리트 타설 시기 사이의 시간 간격으로 인한 콘크리트 불연속면이 기초부(2)의 상면에 형성되었으나, 이와 같은 본 발명의 시공방법에 의하면, 이러한 콘크리트 불연속면이 매립 거푸집(3) 내에 형성된다. In the prior art, a concrete discontinuity due to a time interval between a concrete pouring time of the base part and a concrete pouring time of the pillar is formed on the upper surface of the base part 2. According to the construction method of the present invention, (3).

도 15에는 본 발명의 시공방법에 의해 기둥(1)-기초부(2) 결합 구조물이 시공됨으로써 매립 거푸집(3) 내의 위치에서 콘크리트 불연속면(J)이 형성된 것을 보여주는 개략적인 단면도가 도시되어 있다. 도 15에서는 편의상 콘크리트에 매립되어 있는 철근의 도시는 생략하고, 오로지 콘크리트만을 도시하였다. 15 is a schematic cross-sectional view showing that a concrete discontinuity J is formed at a position in the landfill 3 by the construction of the column 1-foundation 2 joint structure by the construction method of the present invention. In FIG. 15, for the sake of convenience, the illustration of the reinforcing bars embedded in the concrete is omitted, and only the concrete is shown.

본 발명에서는 기초부(2)의 콘크리트 타설에 연속하여 매립 거푸집(3) 내에서 소정 높이까지 콘크리트가 타설되므로, 기초부의 시공을 위해 1차적으로 타설되는 콘크리트가 단순히 기초부의 상면 높이까지만 존재하는 것이 아니라, 매립 거푸집(3) 내부에서 소정 높이까지 존재하게 된다. 이러한 상태에서 기둥을 위한 2차 콘크리트가 타설되면, 매립 거푸집(3)의 내부에서 1차 콘크리트가 채워진 높이 보다 위쪽의 비어 있는 공간에도 2차 콘크리트가 채워지면서 기둥 거푸집(4) 내에 콘크리트가 채워진다. 따라서 기초부 거푸집과 매립 거푸집(3)에 채워진 1차 콘크리트와, 매립 거푸집의 비어 있던 부분과 기둥 거푸집(4)에 채워지는 2차 콘크리트 사이에, 콘크리트 타설 시점 차이로 인하여 발생하게 되는 콘크리트 불연속면(J)은 매립 거푸집(3) 내에 위치하게 된다. 즉, 본 발명에 의하면 기초부와 기둥의 하단부를 이루도록 1차 타설된 콘크리트와 기둥의 본체를 이루도록 2차 타설된 콘크리트 사이의 콘크리트 불연속면(J)은 매립 거푸집(3) 내에 위치하게 되는 것이다. In the present invention, since the concrete is poured to a predetermined height in the landfill mold 3 in succession to the concrete pouring of the foundation part 2, the concrete which is primarily installed for the construction of the foundation part exists only up to the upper surface height of the foundation part But is present within the landfill form 3 to a predetermined height. When the secondary concrete for the column is poured in this state, the secondary concrete is filled in the empty space above the height of the primary concrete filled in the landfill form 3, and the concrete is filled in the column formwork 4. Therefore, a concrete discontinuity (hereinafter referred to as " concrete discontinuity ") that is generated due to a difference in the time of concrete placement between the primary formwork and the primary concrete filled in the embedding formwork 3, and between the vacant portion of the embedding formwork and the secondary concrete filled in the column formwork J are located in the landfill 3. That is, according to the present invention, the concrete discontinuity J between the concrete poured to form the base portion and the lower end portion of the pillar and the concrete poured to form the main body of the pillar is located in the landform form 3.

매립 거푸집(3)의 하단부는 기초부(2)의 콘크리트에 매립되므로 매립 거푸집(3)은 사후적으로 제거할 수 없으며, 매립 거푸집(3)은 기초부(2)와 결합된 상태로 영구적으로 존재하여 기둥(1)의 하단부를 구성하는 부재가 되는데, 이와 같이 영구적으로 기둥(1)의 하단부를 이루는 매립 거푸집(3) 내에 기초부와 기둥 사이의 콘크리트 불연속면이 위치하게 된다. 따라서 종래 기술과 달리, 본 발명에서는 기초부의 상면에는 기둥과 기초부간의 콘크리트 불연속면이 존재하지 않은 상태가 되며, 그에 따라 기둥과 기초부가 완전하고 견고한 일체화를 이룰 수 있게 되어 기둥-기초부의 접합 위치에서는 매우 큰 휨모멘트 저항력이 발휘되므로 구조적으로 매우 안정적인 상태를 유지할 수 있게 된다. 특히, 콘크리트의 타설 시간 간격으로 인하여 부득이하게 발생하는 콘크리트 불연속면이, 본 발명에서는 영구적으로 기둥(1) 하단의 일부를 이루게 되는 매립 거푸집(3)의 내부에서 매립 거푸집(3)에 의해 구속된 상태로 존재하게 되므로, 이러한 콘크리트 불연속면의 존재로 인한 구조적인 취약성을 최소화할 수 있게 된다. Since the lower end of the landfill 3 is embedded in the concrete of the foundation 2, the landfill 3 can not be removed afterwards and the landfill 3 is permanently connected to the foundation 2 And a concrete discontinuity surface between the foundation and the column is located in the embedding form 3 that forms the lower end of the column 1 permanently. Therefore, in contrast to the prior art, in the present invention, there is no concrete discontinuity between the column and the base portion on the upper surface of the base portion, so that the column and base portion can be integrated completely and firmly, A very large bending moment resistance is exerted, so that it can be structurally very stable. Particularly, a concrete discontinuity surface which is inevitably generated due to the time interval of the concrete pavement is formed in the state of being constrained by the embedding formwork 3 in the interior of the embedding formwork 3, which is a part of the lower end of the pillar 1, The structural weakness due to the existence of such a concrete discontinuity can be minimized.

특히, 큰 휨모멘트가 작용하게 되는 기둥(1)의 하단부가 매립 거푸집(3)에 의해 피복된 상태이므로, 매립 거푸집(3)은 기둥(1)의 일부분을 이루게 되며, 그에 따라 기둥(1) 하단부에서의 휨강성이 더욱 증가하게 되고, 구조적으로 더욱 안전한 기둥(1)을 시공할 수 있게 된다. Particularly, since the lower end of the column 1 to which a large bending moment is applied is covered by the buried formwork 3, the buried formwork 3 forms a part of the column 1, The bending stiffness at the lower end portion is further increased, and it becomes possible to construct the column 1 more structurally safe.

본 발명에서는 아직 기초부(2)를 위한 콘크리트가 타설되기 전의 상태에서 매립 거푸집(3)을 설치할 때, 매립 거푸집(3)의 연직도를 설계에 맞춰 조정하게 되므로, 1차 콘크리트 타설하여 기초부(2)와 매립 거푸집(3) 내부에서의 기둥(1) 하단 일부를 일체 시공한 후, 매립 거푸집(3) 위에 기둥 거푸집(4)을 적층 설치할 때에는 추가적으로 기둥 거푸집(4)의 연직도를 조정하지 않고서도 설계된 연직도를 가지는 기둥(1)을 용이하게 시공할 수 있게 된다. 따라서 본 발명에서는 종래 기술에서 요구되었던 기초부(2) 상면의 평탄성 확보를 위한 추가적인 작업이 전혀 필요하지 않으며, 그에 따라 종래 기술보다 월등히 향상된 작업 효율성을 발휘할 수 있게 되어, 시공비의 절감 및 시공기간의 단축의 잇점을 발휘하게 된다. In the present invention, when the buried formwork (3) is installed in the state before the concrete for the foundation (2) is still laid, the vertical degree of the buried formwork (3) is adjusted according to the design. The vertical posture of the column formwork 4 is additionally adjusted when the column formwork 4 is stacked on the embedment formwork 3 after a part of the lower end of the column 1 is integrally installed in the embedding formwork 2 and the embedment formwork 3 It is possible to easily construct the column 1 having the designed vertical degree without having to perform the above operation. Therefore, in the present invention, there is no need for additional work for securing the flatness of the upper surface of the base part 2, which is required in the prior art, and thus it is possible to exert a work efficiency much higher than that of the prior art, The advantage of shortening is exhibited.

또한 본 발명에서는 기둥 거푸집(4)을 지지하는 매립 거푸집(3)은, 그 하단부가 기초부(2)의 콘크리트에 매립된 상태로 견고하게 설치 위치를 유지하게 되므로, 매립 거푸집(3)과 기둥 거푸집(4)을 서로 견고하게 결합하는 것만으로도 기둥 거푸집(4)을 안정적으로 연직 설치할 수 있게 되며, 그에 따라 종래 기술에서 필요로 하였던 기둥 거푸집(4)의 전도, 기울어짐, 또는 수평이동을 방지를 위한 보조지지부재(9)의 설치 작업이 필요하지 않게 되며, 그에 따라 추가적인 작업효율 향상, 시공비 절감 및 시공기간 단축의 잇점을 발휘할 수 있게 된다. In the present invention, since the bottom end portion of the embedding form 3 supporting the column form 4 is firmly installed at a state where it is embedded in the concrete of the foundation 2, the embedding form 3 and the column It is possible to stably install the column formwork 4 in a stable manner by merely rigidly coupling the formwork 4 to each other so that the column formwork 4 which is required in the prior art is prevented from being tilted, It is unnecessary to install the auxiliary support member 9 for preventing the occurrence of the problem, thereby further improving the working efficiency, reducing the construction cost, and shortening the construction period.

1: 기둥
2: 기초부
3: 매립 거푸집
4: 기둥 거푸집
21: 연직결합철근
25: 수평철근
28: 기초부 보강용 철근조립체
30: 보강매립재
31: 거푸집 지지대
32: 통과공
33: 하부지지프레임
35: 통과공
36: 오목부
40: 기둥보강철근망
1: Column
2: Foundation
3: Landfill mold
4: Column form
21: vertical joining reinforcing bar
25: horizontal reinforcement
28: Reinforcement assembly for foundation part
30: reinforced landfill
31: die support
32: Through hole
33: Lower support frame
35: Through ball
36:
40: Column Reinforcing Net

Claims (4)

기초부에 기둥의 하단부가 결합된 기둥-기초부 결합 구조물의 시공방법으로서,
기초부(2)의 제작을 위한 기초부 거푸집을 설치하고, 기초부 보강용 철근조립체(28)을 제작하여 기초부 거푸집 내에 배치함과 동시에 또는 이에 후속하여 하부지지프레임(33)을 기초부 거푸집 내에 배치하는 단계;
기둥(1)의 연직방향 단면 형상에 대응되는 연직방향 단면을 가지는 통형상의 부재로 이루어진 매립 거푸집(3)을, 그 하단이 기초부(2)를 이루는 1차 콘크리트에 매립될 수 있도록, 하부지지프레임(33)에 의해 지지되는 상태로 하부지지프레임(33) 위에 배치하는 단계;
기초부 보강용 철근조립체(28)와 하부지지프레임(33)이 1차 콘크리트에 매립되도록 기초부 거푸집 내에 1차 콘크리트를 타설하여 채움으로써 기초부(2)를 제작하되, 매립 거푸집(3) 내부에도 기초부의 상면보다 더 높지만 매립 거푸집(3)의 최상단보다는 아래의 위치까지 1차 콘크리트가 채워지도록 함으로써, 매립 거푸집(3)의 하단이 기초부(2)의 상부에 매립되어 있는 상태가 되도록 기초부(2)를 제작하는 단계;
매립 거푸집(3) 위에 기둥(1)의 시공을 위한 기둥 거푸집(4)을 설치하는 단계;
기둥 거푸집(4) 내에 기둥보강철근망(40)을 삽입배치하고, 기초부(2)의 상면보다 더 높은 위치까지 매립 거푸집(3) 내에 채워져 있던 1차 콘크리트의 외부 노출 표면이 경화되기 전에, 매립 거푸집(3) 내에서 비어 있던 공간과 기둥 거푸집(4) 내에 2차 콘크리트를 타설하여 기둥(1)을 제작하는 단계; 및
매립 거푸집(3)은 남겨둔 채로, 기둥 거푸집(4)을 탈형하는 단계를 포함함으로써,
매립 거푸집(3)의 하부가 기초부(2)에 매립되고 매립 거푸집(3)이 기둥(1)의 하단부를 피복하여 기둥(1)의 일부분을 이루고 있으며, 기초부(2)와 기둥(1)의 하단부는, 기초부(2)를 이루는 1차 콘크리트에 의해 일체화된 하나의 부재로 이루어져 있고, 상기 1차 콘크리트와, 기둥(1)의 본체를 이루는 2차 콘크리트 사이에 발생하는 콘크리트 불연속면(J)이, 기초부(2)의 상면보다 더 높은 위치에서 매립 거푸집(3) 내에 존재하게 되도록 하며;
매립 거푸집(3)은 제거하지 않은 채, 기초부(2)와 결합된 상태로 영구적으로 존치시켜 기둥(1)의 하단부를 구성하는 부재가 되도록 하며;
하부지지프레임(33)은, 수평방향으로 길게 연장된 바닥수평빔(330)을 포함하여 강재 빔이 사다리꼴 형태로 조립된 형태를 가지고 있어서, 기초부(2)의 휨강성 및 인장강성을 보강하게 되는 것을 특징으로 하는 기둥-기초부 일체 결합 구조물의 시공방법.
A method of constructing a column-foundation coupling structure in which a lower end of a column is coupled to a foundation,
A base part for forming the base part 2 is provided and the base part reinforcing steel assembly 28 is manufactured and placed in the base part molding or simultaneously with or after the lower support frame 33 is fixed to the base part molding ;
The lower end of the landfill 3 formed of a tubular member having a vertical section corresponding to the vertical sectional shape of the column 1 can be embedded in the primary concrete constituting the foundation 2, Placing on a lower support frame (33) in a state of being supported by a support frame (33);
The foundation part 2 is formed by pouring the primary concrete in the base part mold so that the base part reinforcing steel reinforcing assembly 28 and the lower support frame 33 are embedded in the primary concrete, The primary concrete is filled up to a position lower than the uppermost end of the landfill 3 so that the lower end of the landfill 3 is buried in the upper part of the foundation 2, (2);
Installing a column mold (4) for installation of the column (1) on the landfill (3);
The column reinforcing net 40 is inserted in the column mold 4 and before the external exposed surface of the primary concrete which has been filled in the landfill 3 to a position higher than the upper surface of the foundation 2 is hardened, Preparing a column 1 by pouring a secondary concrete into the empty space in the landfill mold 3 and the column mold 4; And
By including the step of demolding the column form 4 while leaving the buried form 3,
The lower part of the buried form 3 is buried in the foundation 2 and the buried form 3 covers the lower end of the column 1 to form a part of the column 1. The foundation 2 and the columns 1 Is composed of a single member integrated with the primary concrete constituting the foundation part 2 and the lower end of the concrete inconsistency plane formed between the primary concrete and the secondary concrete constituting the main body of the column 1 J are present in the landfill mold 3 at a higher position than the top surface of the foundation 2;
The buried formwork 3 is permanently retained in a state of being engaged with the foundation 2 without being removed so as to become a member constituting the lower end of the column 1;
The lower support frame 33 includes a horizontal horizontal beam 330 extending in the horizontal direction so that the steel beams are assembled in a trapezoidal shape so that the bending stiffness and the tensile rigidity of the base portion 2 are reinforced Wherein the pillar-foundation integral joint structure is formed of a pillar-base integral structure.
제1항에 있어서,
매립 거푸집(3)의 하단부에서 매립 거푸집(3)의 하단 가장자리에는 위쪽으로 오목하게 파인 오목부(36)가 형성되어 있으며;
매립 거푸집(3)을 하부지지프레임(33) 위에 배치하는 단계에서는, 기초부 보강용 철근조립체(28)의 수평철근(25)이 오목부(36) 내에 위치하도록 매립 거푸집(3)을 설치하게 되는 것을 특징으로 하는 기둥-기초부 일체 결합 구조물의 시공방법.
The method according to claim 1,
At the lower end of the landfill form 3, a recess 36 is formed at the lower edge of the landfill 3 so as to be concave upwardly;
In the step of disposing the embedding form 3 on the lower support frame 33, the embedding mold 3 is installed so that the horizontal reinforcing bars 25 of the reinforcing bars 28 for foundation are located in the recesses 36 Wherein the pillar-to-foundation integral joint structure is formed on the base member.
제1항 또는 제2항에 있어서,
매립 거푸집(3)의 외면에는, 거푸집 지지대(31)가 외측으로 돌출된 상태로 구비되어 있으며;
매립 거푸집(3) 위에 기둥(1)의 시공을 위한 기둥 거푸집(4)을 설치하는 단계에서는, 기둥 거푸집(4)의 하단을 거푸집 지지대(31) 위에 놓은 후, 기둥 거푸집(4)과 거푸집 지지대(31)를 연결판에 의해 일체로 조립하는 것을 특징으로 하는 기둥-기초부 일체 결합 구조물의 시공방법.
3. The method according to claim 1 or 2,
On the outer surface of the embedding form 3, a form support 31 is provided so as to protrude outwardly;
In the step of installing the column formwork 4 for the construction of the column 1 on the embedment formwork 3, the lower end of the column formwork 4 is placed on the formwork support 31 and then the column formwork 4 and the formwork support 4, (31) are integrally assembled by a connecting plate.
기초부에 기둥의 하단부가 결합된 기둥-기초부 결합 구조물로서,
기초부(2)의 제작을 위한 기초부 거푸집을 설치하고, 기초부 보강용 철근조립체(28)을 제작하여 기초부 거푸집 내에 배치함과 동시에 또는 이에 후속하여 하부지지프레임(33)을 기초부 거푸집 내에 배치하는 단계; 기둥(1)의 연직방향 단면 형상에 대응되는 연직방향 단면을 가지는 통형상의 부재로 이루어진 매립 거푸집(3)을, 그 하단이 기초부(2)를 이루는 1차 콘크리트에 매립될 수 있도록, 하부지지프레임(33)에 의해 지지되는 상태로 하부지지프레임(33) 위에 배치하는 단계; 기초부 보강용 철근조립체(28)와 하부지지프레임(33)이 1차 콘크리트에 매립되도록 기초부 거푸집 내에 1차 콘크리트를 타설하여 채움으로써 기초부(2)를 제작하되, 매립 거푸집(3) 내부에도 기초부의 상면보다 더 높지만 매립 거푸집(3)의 최상단보다는 아래의 위치까지 콘크리트가 채워지도록 함으로써, 매립 거푸집(3)의 하단이 기초부(2)의 상부에 매립되어 있는 상태가 되도록 기초부(2)를 제작하는 단계; 매립 거푸집(3) 위에 기둥(1)의 시공을 위한 기둥 거푸집(4)을 설치하는 단계; 기둥 거푸집(4) 내에 기둥보강철근망(40)을 삽입배치하고, 기초부(2)의 상면보다 더 높은 위치까지 매립 거푸집(3) 내에 채워져 있던 1차 콘크리트의 외부 노출 표면이 경화되기 전에, 매립 거푸집(3) 내에서 비어 있던 공간과 기둥 거푸집(4) 내에 2차 콘크리트를 타설하여 기둥(1)을 제작하는 단계; 및 매립 거푸집(3)은 남겨둔 채로, 기둥 거푸집(4)을 탈형하는 단계를 포함하는 시공방법에 의해 시공되며;
매립 거푸집(3)의 하부가 기초부(2)에 매립되고 매립 거푸집(3)이 기둥(1)의 하단부를 피복하여 기둥(1)의 일부분을 이루고 있으며, 기초부(2)와 기둥(1)의 하단부는, 기초부(2)를 이루는 1차 콘크리트에 의해 일체화된 하나의 부재로 이루어져 있고, 상기 1차 콘크리트와, 기둥(1)의 본체를 이루는 2차 콘크리트 사이에 발생하는 콘크리트 불연속면(J)이, 기초부(2)의 상면보다 더 높은 위치에서 매립 거푸집(3) 내에 존재하며;
매립 거푸집(3)은 제거되지 않은 채, 기초부(2)와 결합된 상태로 영구적으로 존치하고 있어서, 기둥(1)의 하단부를 구성하는 부재가 되어 있고;
하부지지프레임(33)은, 수평방향으로 길게 연장된 바닥수평빔(330)을 포함하여 강재 빔이 사다리꼴 형태로 조립된 형태를 가지고 있어서, 기초부(2)의 휨강성 및 인장강성을 보강하고 있는 구성을 가지는 것을 특징으로 하는 기둥-기초부 일체 결합 구조물.
A column-base bonded structure having a base portion and a lower end portion joined to each other,
A base part for forming the base part 2 is provided and the base part reinforcing steel assembly 28 is manufactured and placed in the base part molding or simultaneously with or after the lower support frame 33 is fixed to the base part molding ; The lower end of the landfill 3 formed of a tubular member having a vertical section corresponding to the vertical sectional shape of the column 1 can be embedded in the primary concrete constituting the foundation 2, Placing on a lower support frame (33) in a state of being supported by a support frame (33); The foundation part 2 is formed by pouring the primary concrete in the base part mold so that the base part reinforcing steel reinforcing assembly 28 and the lower support frame 33 are embedded in the primary concrete, The lower end of the embedding form 3 is embedded in the upper portion of the foundation 2 so that the concrete is filled up to a position lower than the uppermost end of the embedding form 3, 2); Installing a column mold (4) for installation of the column (1) on the landfill (3); The column reinforcing net 40 is inserted in the column mold 4 and before the external exposed surface of the primary concrete which has been filled in the landfill 3 to a position higher than the upper surface of the foundation 2 is hardened, Preparing a column 1 by pouring a secondary concrete into the empty space in the landfill mold 3 and the column mold 4; And demolding the column form (4), leaving the fill form (3) left behind;
The lower part of the buried form 3 is buried in the foundation 2 and the buried form 3 covers the lower end of the column 1 to form a part of the column 1. The foundation 2 and the columns 1 Is composed of a single member integrated with the primary concrete constituting the foundation part 2 and the lower end of the concrete inconsistency plane formed between the primary concrete and the secondary concrete constituting the main body of the column 1 J are present in the landfill mold 3 at a higher position than the top surface of the foundation 2;
The buried formwork 3 is permanently retained in a state of being engaged with the foundation 2 without being removed and is a member constituting the lower end of the column 1;
The lower support frame 33 includes a horizontal horizontal beam 330 extended in the horizontal direction so that the steel beams are assembled in a trapezoidal shape to reinforce the flexural rigidity and the tensile rigidity of the base portion 2 Wherein the pillar-to-base integral connection structure has a structure in which the pillar-
KR1020160045071A 2016-04-12 2016-04-12 Structure and Constructing Method of Integrated Pier-Base KR101753744B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020160045071A KR101753744B1 (en) 2016-04-12 2016-04-12 Structure and Constructing Method of Integrated Pier-Base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020160045071A KR101753744B1 (en) 2016-04-12 2016-04-12 Structure and Constructing Method of Integrated Pier-Base

Publications (1)

Publication Number Publication Date
KR101753744B1 true KR101753744B1 (en) 2017-07-06

Family

ID=59353899

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020160045071A KR101753744B1 (en) 2016-04-12 2016-04-12 Structure and Constructing Method of Integrated Pier-Base

Country Status (1)

Country Link
KR (1) KR101753744B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236080A (en) * 2020-03-03 2020-06-05 重庆单轨交通工程有限责任公司 Door-shaped pier steel beam support installation method and door-shaped pier steel beam support installation component
CN114108486A (en) * 2021-12-09 2022-03-01 中铁四局集团第四工程有限公司 Installation and construction method of high-speed rail gate-type pier body invading existing line safety boundary
KR20230158891A (en) * 2022-05-12 2023-11-21 에스비엔지니어링 주식회사 Steel Column Foundation Connection Structure with Improved Resistance to Cone Breakage and its Construction Method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006328666A (en) * 2005-05-23 2006-12-07 Okumura Corp Construction method for integrating pile with column
JP2012162898A (en) * 2011-02-04 2012-08-30 Kawada Industries Inc Anchor frame, and construction method for foundation structure using anchor frame

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006328666A (en) * 2005-05-23 2006-12-07 Okumura Corp Construction method for integrating pile with column
JP2012162898A (en) * 2011-02-04 2012-08-30 Kawada Industries Inc Anchor frame, and construction method for foundation structure using anchor frame

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111236080A (en) * 2020-03-03 2020-06-05 重庆单轨交通工程有限责任公司 Door-shaped pier steel beam support installation method and door-shaped pier steel beam support installation component
CN114108486A (en) * 2021-12-09 2022-03-01 中铁四局集团第四工程有限公司 Installation and construction method of high-speed rail gate-type pier body invading existing line safety boundary
CN114108486B (en) * 2021-12-09 2023-10-03 中铁四局集团有限公司 High-speed railway gate pier body installation construction method for invading existing line safety boundary
KR20230158891A (en) * 2022-05-12 2023-11-21 에스비엔지니어링 주식회사 Steel Column Foundation Connection Structure with Improved Resistance to Cone Breakage and its Construction Method
KR102639094B1 (en) 2022-05-12 2024-02-22 에스비엔지니어링 주식회사 Steel Column Foundation Connection Structure with Improved Resistance to Cone Breakage and its Construction Method

Similar Documents

Publication Publication Date Title
KR101131679B1 (en) Splicing Method of Embedded type Baseplate with Steel Column
KR101523532B1 (en) Closed steel assembly for column
KR101556545B1 (en) Method for constructing using a double wall Precast Concrete
KR101314081B1 (en) Retaining wall and upeer structure connection method for rahmen structure
KR101301081B1 (en) Wall structure and the construction method therefor
KR101545936B1 (en) Precast wall structure construction
KR101753743B1 (en) Structure and Constructing Method of Integrated Pier-Base
KR20110103000A (en) Precast bridge joint structure with composite hollow concrete filled tube and a construction method for the same
KR20100005830A (en) Development of a set bridge post connector using unit filled concrete with internally confined hollow and a method for construction
KR101713141B1 (en) Hybrid bridge connecting structure and method for constructing thereof
KR101638093B1 (en) Rahmen using hinge type pc wall and method for constructing the same
KR101753744B1 (en) Structure and Constructing Method of Integrated Pier-Base
KR20170032826A (en) Precast concrete dual wall structure and construction method thereof
CN107313507B (en) Construction method for node structure of fabricated concrete frame overhead core column
KR101750404B1 (en) Structure using same time pouring process for wall and foundation concrete and construction method therefor
JP2017110346A (en) Construction method of pillar/beam using precast concrete pillar
KR101458435B1 (en) Half precast concrete column manufacturing method using saddle-type ties and dual hoops and constructing method using the same
KR100799848B1 (en) In place assembling top type block
JP5750246B2 (en) Composite beam, building, and composite beam construction method
JP2009046942A (en) Foundation block for retaining wall
KR101677431B1 (en) Large concrete retaining wall and method of construction
KR100880022B1 (en) Prefabricated precast concrete pumping plant manhole
KR102235873B1 (en) Fabrication method of partial pier cap, partial pier cap, and construction method of pier using partial pier cap
KR101017127B1 (en) Connecting Structure between Foundation and Pier, and Construction Method thereof
KR101747002B1 (en) Structure using reinforced concrete and composite beams and Construction method thereof

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant