KR101751991B1 - High-rise management surveying method - Google Patents

High-rise management surveying method Download PDF

Info

Publication number
KR101751991B1
KR101751991B1 KR1020170035386A KR20170035386A KR101751991B1 KR 101751991 B1 KR101751991 B1 KR 101751991B1 KR 1020170035386 A KR1020170035386 A KR 1020170035386A KR 20170035386 A KR20170035386 A KR 20170035386A KR 101751991 B1 KR101751991 B1 KR 101751991B1
Authority
KR
South Korea
Prior art keywords
measuring
verticality
building
measured
settlement
Prior art date
Application number
KR1020170035386A
Other languages
Korean (ko)
Inventor
이상태
박태식
Original Assignee
테이즈엔지니어링(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 테이즈엔지니어링(주) filed Critical 테이즈엔지니어링(주)
Priority to KR1020170035386A priority Critical patent/KR101751991B1/en
Application granted granted Critical
Publication of KR101751991B1 publication Critical patent/KR101751991B1/en

Links

Images

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C15/00Surveying instruments or accessories not provided for in groups G01C1/00 - G01C13/00
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01BMEASURING LENGTH, THICKNESS OR SIMILAR LINEAR DIMENSIONS; MEASURING ANGLES; MEASURING AREAS; MEASURING IRREGULARITIES OF SURFACES OR CONTOURS
    • G01B11/00Measuring arrangements characterised by the use of optical techniques
    • G01B11/16Measuring arrangements characterised by the use of optical techniques for measuring the deformation in a solid, e.g. optical strain gauge
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C9/00Measuring inclination, e.g. by clinometers, by levels
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01SRADIO DIRECTION-FINDING; RADIO NAVIGATION; DETERMINING DISTANCE OR VELOCITY BY USE OF RADIO WAVES; LOCATING OR PRESENCE-DETECTING BY USE OF THE REFLECTION OR RERADIATION OF RADIO WAVES; ANALOGOUS ARRANGEMENTS USING OTHER WAVES
    • G01S19/00Satellite radio beacon positioning systems; Determining position, velocity or attitude using signals transmitted by such systems
    • G01S19/01Satellite radio beacon positioning systems transmitting time-stamped messages, e.g. GPS [Global Positioning System], GLONASS [Global Orbiting Navigation Satellite System] or GALILEO
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Remote Sensing (AREA)
  • Business, Economics & Management (AREA)
  • General Health & Medical Sciences (AREA)
  • Economics (AREA)
  • Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Position Fixing By Use Of Radio Waves (AREA)

Abstract

본 발명은 초고층 관리측량 방법에 관한 것으로, 보다 상세하게는 GNSS(global navigation satellite system)와 경사계 및 연직계를 함께 운용하여 초고층 건물 공사중 수직도를 허용오차 범위내로 정밀시공함은 물론 초고층 건물의 거동 모니터링을 통해 건물의 비틀림 시공을 방지하며, 엘리베이터의 정확한 시공 기준선을 제공하고, 정확도 제고를 통한 재시공 방지, 원가절감을 이룰 수 있도록 창출된 초고층 관리측량 방법에 관한 것이다.More particularly, the present invention relates to a high-rise building management method, in which a GNSS (global navigation satellite system), an inclinometer and a direct line system are operated together to precisely construct the vertical degree in the construction of a skyscraper, Layer management control method to prevent torsional construction of a building through monitoring, provide an accurate construction baseline of an elevator, prevent rework by improving accuracy, and reduce cost.

Description

초고층 관리측량 방법{High-rise management surveying method}{High-rise management surveying method}

본 발명은 초고층 관리측량 방법에 관한 것으로, 보다 상세하게는 GNSS(global navigation satellite system)와 경사계 및 연직계를 함께 운용하여 초고층 건물 공사중 수직도를 허용오차 범위내로 정밀시공함은 물론 초고층 건물의 거동 모니터링을 통해 건물의 비틀림 시공을 방지하며, 엘리베이터의 정확한 시공 기준선을 제공하고, 정확도 제고를 통한 재시공 방지, 원가절감을 이룰 수 있도록 창출된 초고층 관리측량 방법에 관한 것이다.More particularly, the present invention relates to a high-rise building management method, in which a GNSS (global navigation satellite system), an inclinometer and a direct line system are operated together to precisely construct the vertical degree in the construction of a skyscraper, Layer management control method to prevent torsional construction of a building through monitoring, provide an accurate construction baseline of an elevator, prevent rework by improving accuracy, and reduce cost.

건물의 초고층화는 건축기술의 급격하게 발전 과 토지효율성, 고급주택의 많은 수요 등으로 신축하고 있다.The high-rise building of the building has been newly built with the rapid development of the building technology, the land efficiency, and the demand of the luxury housing.

또한, 경쟁하듯이 국가별로 랜드마크 개념으로 초고층 건물을 서로 앞다투어 짓고 있는게 현실이다.In addition, it is a fact that they are struggling with skyscrapers in the concept of landmark by country as they compete.

이러한 국가별 랜드마크 개념의 초고층 건물로는 예컨대, 아랍에미리트 두바이의 '버즈칼리파', 미국 오클라호마의 '데븐 타워', 홍콩의 'IFC 빌딩', 쿠웨이트의 '알-함라 타워', 아부다비의 '랜드마크 타워', 캐나다 캘거리의 '다운타운', '세계무역센터', 서울 잠실의 '롯데 슈퍼타워' 등을 예시할 수 있다.These landmark concept skyscrapers include the Burj Khalifa in UAE Dubai, the Devon Tower in Oklahoma in the US, the IFC Building in Hong Kong, the Al-Hamra Tower in Kuwait, the Abu Dhabi ' Landmark Tower 'in Canada,' Downtown 'in Calgary,' World Trade Center 'in Canada, and' Lotte Super Tower 'in Seoul Jamsil.

이와 같은 초고층 건물은 건설 자체가 매우 어렵기 때문에 수많은 신기술이 적용되고 있다.Because such a skyscraper is very difficult to construct itself, many new technologies are being applied.

특히, 초고층 건물의 경우에는 수직도를 측량하여 관리하는 것이 매우 중요한데, 이것은 건물의 중심 기준선 확정 및 후속공정(커튼월, 엘리베이터, 인테리어 시공 등)에 있어 매우 중요한 기준선을 제공하기 때문이다.Especially, in the case of a skyscraper, it is very important to survey and manage the verticality because it provides a very important baseline for determining the center line of the building and for subsequent processes (curtain wall, elevator, interior construction, etc.).

뿐만 아니라, 초고층 건물의 구조적 안전성, 엘리베이터 등의 주행 안전성, 건물 변형으로 인한 거주자 등의 불안요소 해소 등은 정확한 수직도 관리의 근본적인 필요성이라고 볼 수 있다.In addition, structural safety of skyscraper, driving safety such as elevators, and relieving the anxiety of residents due to building deformation are essential necessities for accurate vertical management.

하지만, 종래 방법은 평면(X,Y) 기준점을 수직으로 이동하면서 수직도를 관리는 전통적인 방법을 탈피하지 못하고 있어 비록 선행기술문헌과 같은 수직도 측량관리 방법이 개시되어 있음에도 불구하고 효과적으로 활용되지 못하고 있는 실정이다.However, the conventional method does not depart from the conventional method of managing the vertical degree while moving the plane (X, Y) reference point vertically, so that it can not be effectively utilized even though the vertical direction measurement management method such as the prior art document is disclosed In fact.

그런데, 이러한 종래 방법은 기준점 이동에 따른 오차 발생이 허용오차를 벗어나기 쉽고, 오차 누적으로 인한 수직도 관리상의 극심한 어려움, 건물 거동에 대한 보정 불가상황 발생, 측량사의 주관적인 판단이 개입될 가능성이 매우 높고, 기상상태, 야간 등 주변환경에 따른 제약이 많으며, 층고 상승에 따른 외부기준점에서의 측량 불가 등 상당한 문제를 안고 있다.However, such a conventional method has a problem in that an error due to movement of a reference point tends to deviate from an allowable error, an extreme difficulty in vertical management due to an error accumulation, an uncorrectable situation with respect to a building behavior, , Weather conditions, nighttime, etc., and there are considerable problems such as impossibility of surveying at an external reference point due to a rise in height.

대한민국 특허 등록번호 제10-1177889호(2012.08.22.) '초고층 건물 수직도 측량관리'Korea Patent Registration No. 10-1177889 (Aug. 22, 2012) 'Vertical Surveying of High-rise Buildings'

본 발명은 상술한 바와 같은 종래 기술상의 제반 문제점들을 감안하여 이를 해결하고자 창출된 것으로, GNSS(global navigation satellite system)와 경사계 및 연직계를 함께 운용하여 초고층 건물 공사중 수직도를 허용오차 범위내로 정밀시공함은 물론 초고층 건물의 거동 모니터링을 통해 건물의 비틀림 시공을 방지하며, 엘리베이터의 정확한 시공 기준선을 제공하고, 정확도 제고를 통한 재시공 방지, 원가절감을 이룰 수 있도록 창출된 초고층 관리측량 방법을 제공함에 그 주된 목적이 있다.SUMMARY OF THE INVENTION The present invention has been made in view of the above-described problems in the prior art, and has been made in order to solve the above problems, and it is an object of the present invention to provide a GNSS (Global Navigation Satellite System), an inclinometer, It also provides a high-rise management surveying method that can prevent the twisting of buildings by monitoring the behavior of skyscraper buildings, provide precise construction baselines of elevators, prevent rework by improving accuracy, and reduce costs. There is a main purpose.

본 발명은 상기한 목적을 달성하기 위한 수단으로, GNSS(global navigation satellite system)에 의한 수직도를 측량하는 제1단계, 경사계를 이용하여 수직도를 계측하는 제2단계, 연직기를 이용하여 수직도를 측정하는 제3단계, 디지털 수준측량기를 통한 부등침하를 모니터링하는 제4단계, 각 단계에서 취득된 정보를 제어부가 수집, 저장, 연산하여 수직도가 관리 시방기준의 오차범위 내에 속하는지 판단하는 제5단계를 거쳐 공사중인 초고층 건물의 수직도를 산출하는 초고층 관리측량 방법에 있어서;In order to achieve the above-mentioned object, the present invention provides a method for measuring a verticality by a GNSS (Global Navigation Satellite System), comprising the steps of: measuring a verticality using a slope meter; A fourth step of monitoring the differential settlement through the digital level meter, a fourth step of monitoring the differential settlement through the digital level instrument, a step of collecting, storing and calculating the information acquired in each step, and determining whether the vertical degree falls within the error range of the management standard reference A method for measuring a vertical height of a skyscraper under construction through a fifth step, the method comprising the steps of:

상기 GNSS에 의한 수직도를 측량하는 제1단계는, ACS(Automatic Climbing System) 폼(Foam) 상부에 GPS 거치대를 설치하고, 거치대 위에 4대의 GPS 리시버를 설치한 후 1-2시간 동안 데이터를 수집하는 과정; 4개의 GPS 리시버 가운데 지점에 토탈 스테이션을 설치한 후 토탈 스테이션을 이용하여 4대의 GPS 리시버의 레벨 변화를 측정하는 과정; 측정된 정보를 무선통신을 통해 지상에 설치된 상시관측소로 주기적으로 전송하는 과정;으로 이루어지고,In the first step of measuring the verticality by the GNSS, a GPS receiver is installed on an ACS (Automatic Climbing System) form, and four GPS receivers are installed on the receiver. Process; Measuring the level change of four GPS receivers using a total station after installing a total station at a point among four GPS receivers; And periodically transmitting the measured information to a regular observation station installed on the ground through wireless communication,

상기 경사계를 이용하여 수직도를 계측하는 제2단계는, 센터 코어 월(Center Core Wall) 내부에 틸트미터를 20개 층 단위로 설치하는 과정; 각 틸트미터로부터 측정된 기울기값을 상시관측소로 주기적으로 무선송신하는 과정; 측정된 기울기 정보를 수신한 상시관측소의 제어부는 건물이 외부영향에 가장 적게 노출되는 새벽 5시의 측정 기울기를 실제 위치로 간주하고 작업시간에 GPS로 측정한 월(Wall)의 현재위치를 비교하여 기울기 차이값을 메모리에 저장하는 과정;으로 이루어지며,The second step of measuring the verticality using the inclinometer includes the steps of: installing a tilt meter in a center core wall in units of 20 layers; Periodically transmitting a tilt value measured from each tilt meter to a regular observation station; When the measured slope information is received, the control unit of the permanent observatory considers the measurement slope at 5:00 am, which is the least exposed to external influences, as the actual location, compares the current location of the wall measured by the GPS with the work time And storing the slope difference value in a memory,

상기 연직기를 이용하여 수직도를 측정하는 제3단계는, 건물의 매 10개 층마다 슬리브를 설치하고, 슬리브 상에 메인 컨트롤 마크(Main Control Mark)를 구비하는 과정; 건물의 최하부 라프트 파운데이션(Raft Foundation)에서 옵티컬 플러밋(Optical Plummet)을 사용하여 각 메인 컨트롤 마크의 변위 여부를 측정하는 과정; 처음 설정해 둔 센터라인과 실측시 센터라인 간의 거리를 측정하여 변위를 확인하는 과정; 측정된 변위정보를 상시관측소로 송신하는 과정;으로 이루어지고,The third step of measuring the verticality using the vertical machine includes the steps of providing a sleeve for every ten layers of a building and providing a main control mark on the sleeve; The process of measuring displacement of each main control mark using optical plummet at the bottom of the building at Raft Foundation; Measuring the distance between the center line and the center line at the time of measurement; And transmitting the measured displacement information to a constant observing station,

상기 디지털 수준측량기를 통한 부등침하를 모니터링하는 제4단계는 기준점을 잡기 위해 정밀 디지털 수준측량기를 이용하여 0.1mm까지 정확하게 외부기준점을 측량하는 과정; 외부기준점을 기준으로 건물 내,외부 기초침하량과 기초 부등침하량을 측정하는 과정;으로 이루어지는 것을 특징으로 하는 초고층 관리측량 방법을 제공한다.The fourth step of monitoring the uneven settlement through the digital level meter is to accurately measure an external reference point up to 0.1 mm using a precision digital level meter to catch a reference point; And measuring a basic settlement amount and a basal settlement amount in the building based on the external reference point.

본 발명에 따르면, GNSS(global navigation satellite system)와 경사계 및 연직계를 함께 운용하여 초고층 건물 공사중 수직도를 허용오차 범위내로 정밀시공함은 물론 초고층 건물의 거동 모니터링을 통해 건물의 비틀림 시공을 방지하며, 엘리베이터의 정확한 시공 기준선을 제공하고, 정확도 제고를 통한 재시공 방지, 원가절감을 이루는 효과를 얻을 수 있다.According to the present invention, the GNSS (Global Navigation Satellite System) is operated together with the inclinometer and the direct line system to precisely construct the vertical degree within the tolerance range of the skyscraper building and to prevent the torsion of the building by monitoring the behavior of the skyscraper , It is possible to provide an accurate construction baseline of the elevator, prevent rework by improving the accuracy, and reduce costs.

또한, 수직도가 정확하게 됨으로써 후속공정(RC철골, 커튼월, ACS 등) 수행시 시공의 용이성이 확보되며, 프로젝트 좌표 적용으로 측량보안 및 각종 공사의 편의성이 향상되는 장점도 얻을 수 있다.Also, since the verticality is accurate, the easiness of construction is ensured in the subsequent process (RC steel frame, curtain wall, ACS, etc.), and the security of surveying and convenience of construction are improved by applying project coordinates.

도 1은 본 발명을 설명하기 위해 서울 잠실 롯데타워의 거동을 예시적으로 모니터링한 개념도이다.
도 2는 초고층 건물의 풍하중, 태양열 등에 의한 거동 파악예를 보인 예시도이다.
도 3은 본 발명에 따른 방법을 설명하는 모식도이다.
도 4는 본 발명에 따른 방법에 의해 관리되는 수직도 시방기준을 보인 개념도이다.
도 5는 본 발명을 설명하기 위한 GNSS에 의한 수직도 측량예를 보인 예시도이다.
도 6 내지 도 8은 본 발명을 설명하기 위한 경사계를 이용한 수직도 측정예를 보인 예시도이다.
도 9는 본 발명을 설명하기 위한 연직기를 이용한 수직도 측정예를 보인 예시도이다.
도 10은 본 발명을 설명하기 위한 디지털 수준측량기를 이용한 측량예를 보인 예시도이다.
도 11 및 도 12는 본 발명에 따른 수직도 관리에 보충되는 풍량과 양중에 의한 거동을 보인 예시도이다.
도 13는 본 발명에 따른 방법의 구현예를 보인 예시도이다.
도 14는 본 발명에서 사용되는 거치대의 다양한 형태를 보인 예시도이다.
FIG. 1 is a conceptual diagram illustrating the exemplary monitoring of the behavior of the Seoul Jamsil Lotte Tower to explain the present invention.
FIG. 2 is an illustration showing an example of understanding the behavior of a skyscraper due to wind load, solar heat, and the like.
3 is a schematic diagram illustrating a method according to the present invention.
FIG. 4 is a conceptual diagram showing a verticality specification standard managed by the method according to the present invention.
5 is a diagram illustrating an example of a vertical measurement by GNSS for explaining the present invention.
6 to 8 are diagrams illustrating examples of vertical measurement using an inclinometer for explaining the present invention.
9 is a diagram illustrating an example of vertical measurement using a vertical machine for explaining the present invention.
10 is an exemplary view showing a measurement example using a digital level instrument for explaining the present invention.
FIGS. 11 and 12 are diagrams showing behaviors of the air volume and the amount of air supplemented with the verticality management according to the present invention.
Figure 13 is an illustration showing an embodiment of a method according to the present invention.
14 is an exemplary view showing various forms of a cradle used in the present invention.

이하에서는, 첨부도면을 참고하여 본 발명에 따른 바람직한 실시예를 보다 상세하게 설명하기로 한다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

본 발명 설명에 앞서, 이하의 특정한 구조 내지 기능적 설명들은 단지 본 발명의 개념에 따른 실시예를 설명하기 위한 목적으로 예시된 것으로, 본 발명의 개념에 따른 실시예들은 다양한 형태로 실시될 수 있으며, 본 명세서에 설명된 실시예들에 한정되는 것으로 해석되어서는 아니된다.Before describing the present invention, the following specific structural or functional descriptions are merely illustrative for the purpose of describing an embodiment according to the concept of the present invention, and embodiments according to the concept of the present invention may be embodied in various forms, And should not be construed as limited to the embodiments described herein.

또한, 본 발명의 개념에 따른 실시예는 다양한 변경을 가할 수 있고 여러 가지 형태를 가질 수 있으므로, 특정 실시예들은 도면에 예시하고 본 명세서에 상세하게 설명하고자 한다. 그러나, 이는 본 발명의 개념에 따른 실시예들을 특정한 개시 형태에 한정하려는 것이 아니며, 본 발명의 사상 및 기술 범위에 포함되는 모든 변경물, 균등물 내지 대체물을 포함하는 것으로 이해되어야 한다.In addition, since the embodiments according to the concept of the present invention can make various changes and have various forms, specific embodiments are illustrated in the drawings and described in detail herein. However, it should be understood that the embodiments according to the concept of the present invention are not intended to limit the present invention to specific modes of operation, but include all modifications, equivalents and alternatives falling within the spirit and scope of the present invention.

모든 건물은 중력방향에 수직이어야 한다. 특히, 초고층 건물의 경우에는 더욱 그러하다.All buildings must be perpendicular to the direction of gravity. Especially in the case of skyscraper buildings.

그런데, 초고층 건물의 경우 거동 및 기울기 발생으로 인해 수직시공이 매우 어렵다.However, in the case of a skyscraper, vertical construction is very difficult due to the behavior and inclination.

이러한 거동 및 변형은 건물의 형태, 재료, 공사방법 등에 의해 기인하는데, 수직변형의 경우에는 주로 기초침하, 기둥 축소, 패턴 하중에 의하며, 수평변형은 기초부동침하, 기둥 부등축소 등에 따른다.These behaviors and deformation are caused by the shape of the building, materials, construction methods, etc. In the case of vertical deformation, the deformation depends mainly on the foundation settlement, the column reduction and the pattern load.

그리고, 거동의 경우에는 풍하중, 태양 복사열에 의해 콘크리트 및 부재의 팽창, 구조물의 강한 진동에 따른 움직임, 타워크레인 작업시 불균등 하중, 지진하중, 시공방법에 의한 편위 거동, 계절이나 일조에 따른 거동 등 다양한 형태가 존재한다.In the case of the behavior, the expansion and contraction of the concrete and the member by the wind load and the solar radiation, the movement due to the strong vibration of the structure, the uneven load during the operation of the tower crane, the earthquake load, the deviation behavior by the construction method, There are various forms.

이와 같은 거동 및 변형의 어려움에도 불구하고 두바이 버즈 칼리파 초고층 건물의 경우에는 3일 싸이클, 양중관리, 콘크리트 압송, 첨탑 리프트 업, 수직도 관리를 잘 함으로써 성공적으로 건축할 수 있었던 것으로 보고되어 있다.Despite this difficulty and difficulty in deformation, Dubai Buzz Khalifa has been reported to be able to successfully build the skyscraper with 3 days cycle, weight management, concrete conveyor, steeple lift up and vertical management.

특히, 초고층 건물에서 수직도 측량을 위해 고려되어야 할 사항으로 서울 잠실의 '롯데 슈퍼타워', 일명 제2롯데월드로 불리우는 국내 초고층 건물을 예시하자면 도 1과 같이, 초고층 건물의 거동에 직접적인 영향을 주는 요인을 모니터링해야 하는데, 이를 테면 풍하중, 타워크레인, 부등축소, 부등침하, 작업하중, 시공오차, 고유진동이 그것이다.In particular, as an example of a high-rise building called 'Lotte Super Tower' in Seoul Jamsil, which is called 'Lotte World 2', it should have a direct effect on the behavior of skyscraper buildings Factors such as wind loads, tower cranes, shrinkage, uneven settlement, working load, construction errors, and natural vibration must be monitored.

때문에, 이들 요인에 의해 설계조건대로 완공했다고 하더라도 최상부에서는 움직임이 발생하기 때문에 시공중 건물의 거동 현황을 파악하는 것은 매우 중요한 일이며, 도 2의 예시와 같이 동일 시간대 ACS(Automatic Climbing System) 폼(Foam) 상부에서 GPS 데이터와 지상의 고정된 메인 GPS 스테이션의 데이터를 비교 검토하여 변위량을 산정할 필요가 있다.Therefore, it is very important to understand the current state of the building during construction because the movement occurs at the top even if it is completed according to the design conditions by these factors. As shown in FIG. 2, the ACS (Automatic Climbing System) Foam), it is necessary to compare the GPS data with the data of the fixed main GPS station on the ground to estimate the displacement.

이를 위해, 본 발명에서는 도 3의 예시와 같이, 지상에 위치정보(좌표값)를 알고 있는 기준국(상시기준국)에 GPS를 설치하고, 공사를 수행하는 층에 각 구역별로 4개의 이동국 GPS를 설치하여 초고층 건물의 수평, 수직도를 측정하도록 하여 이를 비교 판독하도록 하는 것이 기본 개념이다.To this end, in the present invention, as shown in the example of FIG. 3, a GPS is installed in a reference station (always a reference station) that knows positional information (coordinate value) on the ground, and four mobile stations GPS And the horizontal and vertical degrees of the skyscraper buildings are measured and compared with each other.

이때, 관리 시방기준은 도 4의 예시와 같이, ACI(American Concrete Institute) 117-06±150mm(롯데의 경우는 더 엄격한 ±75mm)이고, 초고층 거동 예상값은 지상 10m, 10분 평균 풍속 30m/s일 때 상부 ±87cm 거동 기준이다.As shown in the example of FIG. 4, the management standard is 117-06 ± 150 mm (more strict ± 75 mm in the case of Lotte) than the ACI (American Concrete Institute) s, the upper ± 87cm is the standard for the behavior.

보다 구체적으로, 본 발명은 평면(X,Y) 기준점의 측정을 통한 연직관리를 위해 GNSS 수신기를 포함하며, 또한 초고층 건물의 거동을 측정하기 위해 경사계, 건물의 위치측량 및 오차 확인을 위해 토탈 스테이션, 거푸집의 연직도 조정 및 확인 그리고 시공층간의 연직상태를 교차 점검하기 위해 연직기, 시공표고 기준점 설치와 관리 및 기초침하량과 기둥축소량을 측정하기 위해 디지털 레벨기 및 광학레벨기를 포함한다.More specifically, the present invention includes a GNSS receiver for vertical management through measurement of planar (X, Y) reference points, and also includes a tilt gauge to measure the behavior of a skyscraper, a total station , Vertical level adjustment and confirmation of formwork, and vertical level, construction elevation reference point installation and management, and baseline settlement amount and column level reduction to check the vertical condition between construction layers.

그리하여, GNSS에 의한 수직도를 측량하는 제1단계, 경사계를 이용하여 수직도를 계측하는 제2단계, 연직기를 이용하여 수직도를 측정하는 제3단계, 디지털 수준측량기를 통한 부등침하를 모니터링하는 제4단계, 각 단계에서 취득된 정보를 제어부가 수집, 저장, 연산하여 수직도가 관리 시방기준의 오차범위 내에 속하는지 판단하는 제5단계를 거침으로써 본 발명에 따른 초고층 관리측량 방법이 완성된다.Thus, the first step of measuring the verticality by the GNSS, the second step of measuring the verticality using the inclinometer, the third step of measuring the verticality using the vertical machine, the monitoring of the differential settlement with the digital level instrument The fourth step, the control unit collects, stores, and computes the information acquired in each step, and determines whether the vertical degree is within the tolerance range of the management specification reference, thereby completing the skyscraper management surveying method according to the present invention .

이때, 상기 GNSS에 의한 수직도를 측량하는 제1단계는 도 5의 예시와 같이, ACS 폼 상부에 GPS 거치대를 설치하고, 거치대 위에 4대의 GPS 리시버를 설치한 후 1-2시간 동안 데이터를 수집하는 과정; 4개의 GPS 리시버 가운데 지점에 토탈 스테이션을 설치한 후 토탈 스테이션을 이용하여 4대의 GPS 리시버의 레벨 변화를 측정하는 과정; 측정된 정보를 무선통신을 통해 지상에 설치된 상시관측소로 주기적으로 전송하는 과정;을 포함하여 이루어진다.In the first step of measuring the verticality by the GNSS, as shown in FIG. 5, a GPS receiver is installed on the top of the ACS foam, and four GPS receivers are installed on the receiver. Process; Measuring the level change of four GPS receivers using a total station after installing a total station at a point among four GPS receivers; And periodically transmitting the measured information to a regular observation station installed on the ground via wireless communication.

그러면, 상시관측소의 제어부는 수신된 정보를 메모리에 저장한 후 다른 단계에서 계측된 정보를 수신한 후 연산모듈에 의해 연산처리하여 수직도를 산출하게 된다.Then, the control unit of the regular observation station stores the received information in the memory, receives the measured information at the other step, and calculates the vertical degree by calculating by the calculation module.

이때, 4개의 GPS 리시버는 수직도 변화에 여부를 확인하기 위해 정확한 좌표값을 확인하기 위한 것이며, 토탈 스테이션은 수직도 변화의 정확도를 검출하기 위해 4개의 GPS 리시버의 레벨변화를 관측하여 판단 자료로 활용하기 위함이다.At this time, the four GPS receivers are used to confirm the exact coordinate values to check whether the verticality is changed. The total station observes the level changes of the four GPS receivers to detect the accuracy of the vertical variation, It is for utilizing.

그리고, 상기 경사계를 이용하여 수직도를 계측하는 제2단계는 골조공사를 진행하는 매 순간 건물이 움직이고 있기 때문에 외부영향에 노출된 건물의 현재위치와 실제위치(외부 영향이 없을 때)를 파악하는 작업은 매우 중요하다.The second step of measuring the vertical degree using the inclinometer is to recognize the current position and the actual position of the building exposed to the external influences (when there is no external influence) since the building is moving at every moment of the frame construction Work is very important.

이를 위해, 상기 제2단계는 도 6,7과 같이, 센터 코어 월(Center Core Wall) 내부에 틸트미터를 20개 층 단위로 설치하는 과정; 각 틸트미터로부터 측정된 기울기값을 주기적으로 상기 상시관측소로 무선송신하는 과정; 측정된 기울기 정보를 수신한 상시관측소의 제어부는 건물이 외부영향에 가장 적게 노출되는 새벽 5시의 측정 기울기를 실제 위치로 간주하고 작업시간에 GPS로 측정한 월(Wall)의 현재위치를 비교하여 기울기 차이값을 메모리에 저장하는 과정;을 포함한다.For this, in the second step, as shown in FIG. 6 and FIG. 7, a tilt meter is installed in the center core wall in units of 20 layers. Periodically transmitting a tilt value measured from each tilt meter to the constant observing station; When the measured slope information is received, the control unit of the permanent observatory considers the measurement slope at 5:00 am, which is the least exposed to external influences, as the actual location, compares the current location of the wall measured by the GPS with the work time And storing the slope difference value in a memory.

이러한 제2단계의 경사계 모니터링을 통한 계산예는 도 8의 형태로 예시할 수 있다.An example of the calculation based on the inclinometer monitoring in the second step can be illustrated in the form of FIG.

또한, 상기 연직기를 이용하여 수직도를 측정하는 제3단계는, 도 9의 예시와 같이, 건물의 매 10개 층마다 슬리브를 설치하고, 슬리브 상에 메인 컨트롤 마크(Main Control Mark)를 구비하는 과정; 건물의 최하부 라프트 파운데이션(Raft Foundation)에서 옵티컬 플러밋(Optical Plummet)을 사용하여 각 메인 컨트롤 마크의 변위 여부를 측정하는 과정; 처음 설정해 둔 센터라인과 실측시 센터라인 간의 거리를 측정하여 변위를 확인하는 과정; 측정된 변위정보를 상시관측소로 송신하는 과정;으로 이루어진다.In the third step of measuring the verticality using the vertical machine, as shown in FIG. 9, a sleeve is provided for every ten layers of the building, and a main control mark is provided on the sleeve process; The process of measuring displacement of each main control mark using optical plummet at the bottom of the building at Raft Foundation; Measuring the distance between the center line and the center line at the time of measurement; And transmitting the measured displacement information to the constant observing station.

이때, 변위 측정은 건물의 거동이 최소화된 상태에서 이루어지도록 작업자의 이동이 거의 없고 타워크레인 및 호이스트의 작동이 중지된 시간을 선정하여 진행하여야 하며, 옵티컬 플러밋은 오차가 발생할 수 있는 레이저를 사용하지 않고 직접 육안으로 시준하는 것이 바람직하다.In this case, the displacement measurement should be carried out by selecting the time when the operation of the tower crane and the hoist is stopped so that the movement of the worker is hardly performed so that the behavior of the building is minimized, and the optical float may be caused by using a laser It is preferable to directly collimate with the naked eye.

그리고, 상기 디지털 수준측량기를 통한 부등침하를 모니터링하는 제4단계는 도 10의 예시와 같이, 수직도에 영향을 미치는 공사중 건물의 층고를 올릴 때 마다 변화되는 기초침하량과 기초 부등침하량을 확인하여 수직도 관리에 반영하기 위한 것으로, 기준점을 잡기 위해 정밀 디지털 수준측량기를 이용하여 0.1mm까지 정확하게 외부기준점을 측량하는 과정; 외부기준점을 기준으로 건물 내,외부 기초침하량과 기초 부등침하량을 측정하는 과정;으로 이루어진다.In the fourth step of monitoring the uneven settlement through the digital level instrument, as shown in FIG. 10, the basic settlement amount and the basal settlement amount, which change each time the floor height of a building under construction affecting the vertical degree is increased, The process of measuring the external reference point accurately up to 0.1mm using a precision digital level instrument to catch the reference point, And a process of measuring the basic settlement amount and the basal settlement amount in the building based on the external reference point.

한편, 도 11 및 도 12에서와 같이, 상기 경사계를 이용하여 수직도를 계측하는 제2단계에서는 풍속과 양중에 의한 공사중 건물의 거동량을 경사계로 계측할 때 반영하여 측정하면 더 정확한 초고층 건물의 수직도 산출이 가능하게 된다.As shown in FIGS. 11 and 12, in the second step of measuring the verticality using the inclinometer, the amount of movement of the building under construction due to the wind speed and the weight is measured when measured by an inclinometer, The vertical axis can be calculated.

이와 같은 방법을 통해 산출된 수직도는 시방기준과 비교하여 도 13과 같이 수직도 차이값을 매 공사시마다 확인할 수 있어 수직도를 정확하게 유지하도록 보정하는 정보를 제공하며, 그로 인해 시방기준의 오차범위 내의 수직도를 갖는 안전한 초고층 건물을 시공할 수 있게 된다.As shown in FIG. 13, the verticality calculated through the above method can be verified at every construction as shown in FIG. 13, so that correction information for correcting the verticality can be provided. As a result, It is possible to construct a safe skyscraper having a vertical degree in the building.

본 발명에 따른 방법을 단순하게 정리하자면, 움직이는 초고층 건물의 변위량을 네트워크로 연결하여 실시간 측정하고, GNSS 측량을 통한 기준점 좌표와 경사계에서 측정된 변위값을 이용하여 초고층 건물의 시공중 수직도 관리를 시방기준에 부합되게 유지하도록 한 것이다.The method according to the present invention can be summarized as follows. The displacement amount of a moving skyscraper is connected to a network in real time, and the vertical position is managed during the construction of a skyscraper using the reference point coordinates and the displacement value measured by the inclination gauge And to keep them in accordance with specification standards.

덧붙여, 본 발명에 따른 GPS 거치대 혹은 토탈 스테이션 거치대 혹은 경사계나 연직기의 설치를 위한 거치대는 도 14와 같이 다양한 형태가 사용될 수 있다.In addition, a variety of forms can be used as shown in FIG. 14 for a GPS stand or a total station stand or a stand for installing an inclinometer or a vertical stand according to the present invention.

예컨대, 도 14의 (a)는 콘크리트 벽면 코너에 부착하여 굴절된 공간에서 시준가능토록 하는 거치대의 형태이며, (b)는 콘크리트 벽면에 부착하여 전,후면 시준이 가능토록 하는 직선형 거치대 형태이고, (c)는 콘크리트 벽면에 부착하여 전,후면 시준이 가능토록 하는 고정형 거치대 형태이며, (d)는 콘크리트 벽면 코너에 부착하여 굴절된 공간에서 시준할 수 있도록 한 Y형 거치대이고, (e)는 철골(Column)에 부착하여 전,후면 시준이 가능토록 한 철골 부착용 굴절형 거치대의 형태이다.For example, FIG. 14 (a) is a form of a cradle that can be collimated in a refracted space attached to a corner of a concrete wall, (b) is a straight cradle type that is attached to a concrete wall, (d) is a Y-type cradle that can be collimated in the refracted space by attaching to the corner of the concrete wall, (e) is a cradle type cradle mounted on the concrete wall surface, It is in the form of a refractory mount for attaching a steel frame to front and back collimation by attaching to a column.

따라서, 이렇게 다양한 형태의 거치대를 활용하면 매 측정층이나 측정위치별로 변화되는 상황에 맞춰 정확한 계측이 가능하도록 안정적으로 지지할 수 있게 된다.Therefore, by using the various types of cradles, it is possible to stably support the measurement so that accurate measurement can be performed in accordance with the situation that changes depending on each measurement layer or measurement position.

다만, 도시된 사진예에서는 금속소재로 제조된 예를 예시적으로 보이고 있으나, 건물의 건축시공 현장이라는 점 때문에 부식에 따른 지지력 약화, 그로 인한 오차 발생의 우려가 있기 때문에 이들을 모두 강도가 높은 합성수지조성물로 성형하여 내구성, 내습성이 강화되게 구현할 수 있다.However, since there is a fear of weakening the bearing capacity due to corrosion due to the building construction site of the building, and there is a fear of generating an error therebetween, the synthetic resin composition So that durability and moisture resistance can be enhanced.

이를 위해, 본 발명에서는 상기 합성수지조성물을 다음과 같이 조성한 후 성형기로 성형하여 상술한 거치대를 구현할 수 있다.For this, in the present invention, the synthetic resin composition is formed as follows, and then molded into a molding machine to realize the above-mentioned stand.

여기에서, 상기 합성수지조성물은 폴리에틸렌수지 50중량%와 실리카 20중량% 및 나머지 기능성 첨가물로 이루어지되, 상기 기능성 첨가물은 상기 폴리에틸렌수지 100중량부에 대해, 1-2㎛의 입도를 갖는 ITO(Indium-tin oxide) 미분 1.5중량부, 디부틸 세바케이트(dibutyl sebacate) 1.5중량부, 다이벤질리덴 솔비톨 1.5중량부, 1,4-부틸렌글리콜 2중량부, 테트라이소프로필타이타네이트 3중량부, 마이카(Mica) 1.5중량부, 콜로이드성 실리카 3중량부, 알루미늄 알콕사이드 4중량부, 폴리락트산 10중량부, 1-2㎛의 입도를 갖는 알루미나 분말 2중량부, CZ(N-cyclohexybenzothiazole-2-sulfenamide) 2중량부, 몬모릴로나이트 3중량부, Ds(Dichlorodimethylsilane) 7중량부, 스테아린산칼슘 3중량부, 에틸렌글리콜모노메틸에테르 4중량부, 폴리소르베이트 80(Polysorbate 80) 5중량부, 규산소다(Sodium Silicates) 5중량부, 에르소르빈산나트륨 5중량부, 살리실산에스테르 3중량부, 테르븀 2중량부, 0.1-0.2㎛의 입도를 갖는 보크사이트 크링커 분말 5중량부, γ-아미노프로필트리에톡시실란 2중량부, 방향족 폴리아민 2중량부, 산화나트륨(Na2O) 1중량부, 삼산화이철(Fe2O3) 1중량부, 알킬렌 아마이드 2중량부, 황산에스테르 2중량부 및 0.1mm 이하의 입도를 갖는 수련(water lily) 분말 2중량부를 포함하도록 구성된다.Here, the synthetic resin composition comprises 50% by weight of a polyethylene resin, 20% by weight of silica, and the remaining functional additives, wherein the functional additive is an ITO (Indium- tin oxide 1.5 parts by weight, dibutyl sebacate 1.5 parts by weight, dibenzylidene sorbitol 1.5 parts by weight, 1,4-butylene glycol 2 parts by weight, tetraisopropyltitanate 3 parts by weight, 1.5 parts by weight of Mica, 3 parts by weight of colloidal silica, 4 parts by weight of aluminum alkoxide, 10 parts by weight of polylactic acid, 2 parts by weight of alumina powder having a particle size of 1-2 mu m, N-cyclohexybenzothiazole-2-sulfenamide , 2 parts by weight of montmorillonite, 3 parts by weight of montmorillonite, 7 parts by weight of Ds (dichlorodimethylsilane), 3 parts by weight of calcium stearate, 4 parts by weight of ethylene glycol monomethyl ether, 5 parts by weight of Polysorbate 80, ) Five 5 parts by weight of sodium erysurate, 3 parts by weight of salicylic acid ester, 2 parts by weight of terbium, 5 parts by weight of bauxite clinker powder having a particle size of 0.1-0.2 μm, 2 parts by weight of γ-aminopropyltriethoxysilane, 2 parts by weight of sodium oxide (Na 2 O), 1 part by weight of ferric trioxide (Fe 2 O 3 ), 2 parts by weight of alkylene amide, 2 parts by weight of sulfuric acid ester and water with a particle size of 0.1 mm or less 2 parts by weight of lily powder.

이때, 폴리에틸렌수지는 베이스 수지이고, 상기 ITO는 높은 광투과도를 갖기 때문에 투명성 향상에 기여하며 자외선은 모두 투과시키고 적외선 영역에 대해서는 높은 반사율을 갖기 때문에 복사에 따른 표면에서의 열 안정성을 높이기 위해 첨가된다.At this time, the polyethylene resin is a base resin, and the ITO is added to improve transparency because it has high light transmittance and to enhance thermal stability at the surface due to radiation because it transmits all ultraviolet rays and has a high reflectance in the infrared region .

뿐만 아니라, 투명성 강화를 위해 디부틸 세바케이트(dibutyl sebacate)과 다이벤질리덴 솔비톨을 더 첨가하며, 상기 1,4-부틸렌글리콜은 접착성을 강화시켜 부착력을 극대화시키기 위해 첨가되며, 상기 테트라이소프로필타이타네이트는 유기화타이타네이트 구조를 갖는 커플링제로서 고분자 수지와 무기물간의 계면 접착력을 강화시켜 내구성을 높이기 위해 첨가된다.In addition, dibutyl sebacate and dibenzylidene sorbitol are further added to enhance transparency. The 1,4-butylene glycol is added to enhance adhesion and maximize adhesion, and the tetra Isopropyl titanate is added as a coupling agent having an organic titanate structure to enhance the durability by enhancing the interfacial adhesion between the polymer resin and the inorganic material.

그리고, 상기 마이카는 규산염 광물의 일종으로, 0.1-0.2㎛ 크기로 분쇄된 후 체질된 것을 사용하며, 경질 특성으로 인해 내구성과 내충격성을 강화시키기 위해 첨가된다.The mica is a kind of silicate minerals, which is crushed to a size of 0.1-0.2 μm and sieved, and is added to enhance durability and impact resistance due to the hardness characteristics.

또한, 상기 콜로이드성 실리카는 5-50nm의 입경을 갖는 무정형의 실리카 졸이 바람직하며, 상기 알루미늄 알콕사이드는 경화 촉매 및 가교 결합제 기능을 수행하기 위해 첨가되며, 부수적으로 내구성이 높은 경도의 피막을 구현하는데 기여한다.In addition, the colloidal silica is preferably an amorphous silica sol having a particle diameter of 5-50 nm, and the aluminum alkoxide is added to perform a curing catalyst and a crosslinking agent function, and a secondary coating having a high hardness Contributing.

뿐만 아니라, 상기 폴리락트산은 합성고분자 타입의 수지로서 내습성, 가공성이 우수한 물성이 있으며, 용융온도는 150-200℃이고, 연성에 의한 연질화, 인장강도, 신장율을 향상시키는 특성이 있다.In addition, the polylactic acid is a synthetic polymer type resin having excellent moisture resistance and processability, has a melting temperature of 150 to 200 ° C, and is improved in softness, tensile strength and elongation by ductility.

그리고, 알루미나는 알루미늄과 산소의 화합물로서, 내구성 향상을 위해 첨가된다.And, alumina is a compound of aluminum and oxygen and added for improving durability.

뿐만 아니라, CZ(N-cyclohexybenzothiazole-2-sulfenamide)는 표면 슬립성을 증대시켜 이물부착방지성을 극대화시키기 위해 첨가된다.In addition, CZ (N-cyclohexybenzothiazole-2-sulfenamide) is added to increase surface slip property and to maximize prevention of foreign matter adhesion.

아울러, 몬모닐로나이트는 일종의 무기필러로서 기계적 물성을 증대시키기 위해 첨가되며, Ds(Dichlorodimethylsilane)는 강한 소수성을 가진 물질로서 방습성을 극대화시키기 위해 첨가된다.In addition, montmorillonite is added as an inorganic filler to increase mechanical properties, and Ds (Dichlorodimethylsilane) is added as a strong hydrophobic substance to maximize moisture resistance.

그리고, 스테아린산칼슘은 분산제로서 윤활기능을 촉진하여 첨가물들의 균질한 분산성을 유도하기 위해 첨가된다.And, calcium stearate is added as a dispersant to promote the lubricating function and induce homogeneous dispersibility of the additives.

또한, 에틸렌글리콜모노메틸에테르는 접착성을 강화시키기 위해 첨가되며, 부착력을 강하게 하여 내구성을 높이기 위해 첨가된다.In addition, ethylene glycol monomethyl ether is added to enhance the adhesiveness, and it is added to increase the durability by strengthening the adhesion force.

뿐만 아니라, 폴리소르베이트 80(Polysorbate 80)는 소르비톨에서 파생된 비이온성 계면 활성제중 하나로서 수분의 번짐을 막기 위해 첨가되고, 규산소다(Sodium Silicates)는 표면 접착력을 높이면서 점결성을 강화하기 위해 첨가되며, 에르소르빈산나트륨은 산화 방지를 위해 첨가된다.In addition, Polysorbate 80 (Polysorbate 80) is one of the nonionic surfactants derived from sorbitol, which is added to prevent moisture from spreading. Sodium silicates are added to enhance the surface adhesion and enhance the cohesiveness. And sodium erosorbate is added to prevent oxidation.

또한, 살리실산에스테르는 자외선을 흡수하여 자외선에 의해 수지가 변형되는 것을 방지하는 기능을 담당하게 된다.In addition, the salicylic acid ester has a function of absorbing ultraviolet rays to prevent the resin from being deformed by ultraviolet rays.

아울러, 테르븀은 란탄족에 속하는 희토류 금속으로서 전성과 연성이 커 코팅층의 완충 및 내마모도 향상에 기여하게 된다.In addition, terbium is a rare earth metal belonging to lanthanum family, and it has a good ductility and ductility, which contributes to improvement of buffering and wear resistance of the coating layer.

또한, 0.1-0.2㎛의 입도를 갖는 보크사이트 크링커 분말은 결합력을 증대시켜 압축강도를 높이기 위해 첨가된다.In addition, a bauxite clinker powder having a particle size of 0.1-0.2 mu m is added to increase the binding force to increase the compressive strength.

그리고, 상기 γ-아미노프로필트리에톡시실란은 멜라민수지 등의 열경화성수지와 무기재료와의 커플링을 위한 실란커플링제로서 결합성, 접착성, 표면강도를 높이기 위해 첨가된다.The? -Aminopropyltriethoxysilane is added as a silane coupling agent for coupling between a thermosetting resin such as a melamine resin and an inorganic material in order to increase the bonding property, the adhesion property, and the surface strength.

아울러, 상기 방향족 폴리아민은 경화를 촉진하기 위한 것이다.In addition, the aromatic polyamines are intended to promote curing.

또한, 상기 산화나트륨은 이산화규소와 반응하여 규산염을 형성함으로써 내화도를 높이는 기능을 수행하는데, 특히 산화나트륨은 산화방지기능도 수행한다.In addition, the sodium oxide performs a function of raising the refractivity by reacting with silicon dioxide to form a silicate. In particular, the sodium oxide also performs an antioxidant function.

그리고, 상기 삼산화이철은 방청기능을 위해 주로 사용되지만, 본 발명에서는 계면 분리를 억제하기 위해 첨가되며 산화철이라는 특성상 미량 첨가되어야 한다.The iron diiron trioxide is mainly used for anti-corrosive function, but it is added in order to suppress interfacial separation in the present invention, and it should be added in a small amount due to the characteristic of iron oxide.

아울러, 상기 알킬렌 아마이드는 윤활성 및 안정성을 유지하기 위해 첨가되는 것으로, 혼합을 원활하게 하고, 혼합 후 부서짐이 발생하지 않도록 하기 위해 첨가된다.In addition, the alkylene amide is added to maintain lubricity and stability, and is added in order to smoothly mix and prevent crushing after mixing.

또한, 상기 황산에스테르는 자외선에 대한 광열화 작용으로 분해 결합되면서 내열성을 증대시키기 위해 첨가된다.In addition, the sulfuric acid ester is added in order to increase the heat resistance while being decomposed by the photo-thermal effect for ultraviolet rays.

나아가, 상기 수련(water lily) 분말은 수련을 채취하여 충분히 건조한 다음 빻아서 분말화시킨 것으로, 천연 흡습제이면서 생분해성을 가지고 있어 친환경적이다. 수련은 특히 탄화수소나 오일미스트를 흡착하는데 탁월한 효과를 가지고 있다.Furthermore, the water lily powder is obtained by taking a water lily, drying it thoroughly, and pulverizing it into a powder, which is a natural moisture absorber and biodegradable, thus being eco-friendly. The training has an excellent effect especially for adsorbing hydrocarbons and oil mist.

이러한 조성에 따른 이물방지성 및 내부식성(내습성)을 확인하기 위해 10cm × 5cm × 0.5cm 크기의 시트로 성형한 후 표면에 물을 스프레이 한 후 시트를 90도까지 세웠을 때 물이 흘러내리는 것을 확인하였다. 실험결과, 15도를 넘어서자 마자 물이 흘러내려 내습성이 우수한 것으로 확인되었다. 이것은 이물방지성이 높다는 것도 의미한다.In order to confirm the foreign matter resistance and the corrosion resistance (moisture resistance) according to such composition, it is molded into a sheet of 10 cm × 5 cm × 0.5 cm size, and then water is sprayed on the surface, Respectively. As a result of the experiment, it was confirmed that the water flowed down after 15 degrees and the humidity was excellent. This also means that the foreign matter prevention property is high.

Claims (1)

GNSS(global navigation satellite system)에 의한 수직도를 측량하는 제1단계, 경사계를 이용하여 수직도를 계측하는 제2단계, 연직기를 이용하여 수직도를 측정하는 제3단계, 디지털 수준측량기를 통한 부등침하를 모니터링하는 제4단계, 각 단계에서 취득된 정보를 제어부가 수집, 저장, 연산하여 수직도가 관리 시방기준의 오차범위 내에 속하는지 판단하는 제5단계를 거쳐 공사중인 초고층 건물의 수직도를 산출하는 초고층 관리측량 방법에 있어서;
상기 GNSS에 의한 수직도를 측량하는 제1단계는, ACS(Automatic Climbing System) 폼(Foam) 상부에 GPS 거치대를 설치하고, 거치대 위에 4대의 GPS 리시버를 설치한 후 1-2시간 동안 데이터를 수집하는 과정; 4개의 GPS 리시버 가운데 지점에 토탈 스테이션을 설치한 후 토탈 스테이션을 이용하여 4대의 GPS 리시버의 레벨 변화를 측정하는 과정; 측정된 정보를 무선통신을 통해 지상에 설치된 상시관측소로 주기적으로 전송하는 과정;으로 이루어지고,
상기 경사계를 이용하여 수직도를 계측하는 제2단계는, 센터 코어 월(Center Core Wall) 내부에 틸트미터를 20개 층 단위로 설치하는 과정; 각 틸트미터로부터 측정된 기울기값을 상시관측소로 주기적으로 무선송신하는 과정; 측정된 기울기 정보를 수신한 상시관측소의 제어부는 건물이 외부영향에 가장 적게 노출되는 새벽 5시의 측정 기울기를 실제 위치로 간주하고 작업시간에 GPS로 측정한 월(Wall)의 현재위치를 비교하여 기울기 차이값을 메모리에 저장하는 과정;으로 이루어지며,
상기 연직기를 이용하여 수직도를 측정하는 제3단계는, 건물의 매 10개 층마다 슬리브를 설치하고, 슬리브 상에 메인 컨트롤 마크(Main Control Mark)를 구비하는 과정; 건물의 최하부 라프트 파운데이션(Raft Foundation)에서 옵티컬 플러밋(Optical Plummet)을 사용하여 각 메인 컨트롤 마크의 변위 여부를 측정하는 과정; 처음 설정해 둔 센터라인과 실측시 센터라인 간의 거리를 측정하여 변위를 확인하는 과정; 측정된 변위정보를 상시관측소로 송신하는 과정;으로 이루어지고,
상기 디지털 수준측량기를 통한 부등침하를 모니터링하는 제4단계는 기준점을 잡기 위해 정밀 디지털 수준측량기를 이용하여 0.1mm까지 정확하게 외부기준점을 측량하는 과정; 외부기준점을 기준으로 건물 내,외부 기초침하량과 기초 부등침하량을 측정하는 과정;으로 이루어지는 것을 특징으로 하는 초고층 관리측량 방법.
The first step of measuring the verticality by the GNSS (Global Navigation Satellite System), the second step of measuring the verticality using the inclinometer, the third step of measuring the verticality using the vertical machine, The fourth step of monitoring settlement, the fourth step of monitoring settlement, the fifth step of determining whether the vertical direction is within the tolerance range of the management specification reference, collecting, storing and calculating the information acquired in each step, A method for super-layer management surveying, said method comprising the steps of:
In the first step of measuring the verticality by the GNSS, a GPS receiver is installed on an ACS (Automatic Climbing System) form, and four GPS receivers are installed on the receiver. Process; Measuring the level change of four GPS receivers using a total station after installing a total station at a point among four GPS receivers; And periodically transmitting the measured information to a regular observation station installed on the ground through wireless communication,
The second step of measuring the verticality using the inclinometer includes the steps of: installing a tilt meter in a center core wall in units of 20 layers; Periodically transmitting a tilt value measured from each tilt meter to a regular observation station; When the measured slope information is received, the control unit of the permanent observatory considers the measurement slope at 5:00 am, which is the least exposed to external influences, as the actual location, compares the current location of the wall measured by the GPS with the work time And storing the slope difference value in a memory,
The third step of measuring the verticality using the vertical machine includes the steps of providing a sleeve for every ten layers of a building and providing a main control mark on the sleeve; The process of measuring displacement of each main control mark using optical plummet at the bottom of the building at Raft Foundation; Measuring the distance between the center line and the center line at the time of measurement; And transmitting the measured displacement information to a constant observing station,
The fourth step of monitoring the uneven settlement through the digital level meter is to accurately measure an external reference point up to 0.1 mm using a precision digital level meter to catch a reference point; And measuring a basal settlement amount and a basal settlement amount in the building based on the external reference point.
KR1020170035386A 2017-03-21 2017-03-21 High-rise management surveying method KR101751991B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020170035386A KR101751991B1 (en) 2017-03-21 2017-03-21 High-rise management surveying method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020170035386A KR101751991B1 (en) 2017-03-21 2017-03-21 High-rise management surveying method

Publications (1)

Publication Number Publication Date
KR101751991B1 true KR101751991B1 (en) 2017-06-30

Family

ID=59279408

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020170035386A KR101751991B1 (en) 2017-03-21 2017-03-21 High-rise management surveying method

Country Status (1)

Country Link
KR (1) KR101751991B1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101879804B1 (en) * 2018-02-20 2018-07-18 한진정보통신(주) System for managing verticality of high-rise buildings using gnss/inclinometer
CN110057348A (en) * 2019-04-22 2019-07-26 上海建工一建集团有限公司 Super high-rise building axis vertically throws survey method and its measurement point Turnoverplatform system
CN110260840A (en) * 2019-06-28 2019-09-20 中铁大桥局集团有限公司 The measurement method and system of long bridge bridge pier absolute settlement amount over strait
CN114001720A (en) * 2021-11-10 2022-02-01 中冶建工集团有限公司 Supervision control method for building engineering measurement
KR102359081B1 (en) * 2021-05-13 2022-02-08 기하토목기술(주) Method of perpendicularity supervising survey
CN114485557A (en) * 2021-12-08 2022-05-13 中铁二十局集团第六工程有限公司 Method for detecting structural deformation of super high-rise building
CN114791280A (en) * 2022-04-01 2022-07-26 北京城建集团有限责任公司 Door-span type differential settlement automatic measuring system

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101177889B1 (en) 2011-08-11 2012-08-29 (주)만경기술공사 Measuring the vertical management of high-rise buildings

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101177889B1 (en) 2011-08-11 2012-08-29 (주)만경기술공사 Measuring the vertical management of high-rise buildings

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101879804B1 (en) * 2018-02-20 2018-07-18 한진정보통신(주) System for managing verticality of high-rise buildings using gnss/inclinometer
CN110057348A (en) * 2019-04-22 2019-07-26 上海建工一建集团有限公司 Super high-rise building axis vertically throws survey method and its measurement point Turnoverplatform system
CN110057348B (en) * 2019-04-22 2024-05-28 上海建工一建集团有限公司 Super high-rise building axis vertical projection method and measuring point rotation platform system thereof
CN110260840A (en) * 2019-06-28 2019-09-20 中铁大桥局集团有限公司 The measurement method and system of long bridge bridge pier absolute settlement amount over strait
CN110260840B (en) * 2019-06-28 2021-06-29 中铁大桥局集团有限公司 Method and system for measuring absolute settlement of bridge pier of cross-sea long bridge
KR102359081B1 (en) * 2021-05-13 2022-02-08 기하토목기술(주) Method of perpendicularity supervising survey
CN114001720A (en) * 2021-11-10 2022-02-01 中冶建工集团有限公司 Supervision control method for building engineering measurement
CN114485557A (en) * 2021-12-08 2022-05-13 中铁二十局集团第六工程有限公司 Method for detecting structural deformation of super high-rise building
CN114791280A (en) * 2022-04-01 2022-07-26 北京城建集团有限责任公司 Door-span type differential settlement automatic measuring system

Similar Documents

Publication Publication Date Title
KR101751991B1 (en) High-rise management surveying method
RU2381448C1 (en) Method of geodetic measurements and system for high-rise constructions
US8209134B2 (en) Methods for modeling the structural health of a civil structure based on electronic distance measurements
Abdelrazaq Validating the structural behavior and response of Burj Khalifa: Synopsis of the full scale structural health monitoring programs
CN102828470B (en) Method for locating main girder cable sleeve of cable-stayed bridge
CN106703416A (en) Lifting method of steel structure roof truss pulling bar in narrow space
KR101743598B1 (en) Bridge structure deflection safety diagnosis system using multiple laser beams and geosynthetic information
CN106223623A (en) Steel construction box arched roof truss installation method
CN109443327A (en) A kind of distribution method of SURVEYING CONTROL NETWORK
CN204881624U (en) Super high -rise building core section of thick bamboo template location survey controlling means
CN111609833A (en) Settlement observation method for high-rise building
CN113884110A (en) Intelligent building sensor detection method
CN201391091Y (en) Super high-rise building giant steel member mounting measurement pre-control and correcting system
CN103196384A (en) Prism device used for deformation monitoring of dangerous slopes
Wróblewska Measurement methods of building structures deflections
CN104446018B (en) Two vertical limestone kilns of thorax many plane three-dimensionals coordinate is just being looked for, levelling method
CN102966254A (en) Measuring tower used for construction of stub matching method and arrangement thereof
CN105423880A (en) Method for suspending main cable to measure bridge deflection
CN101592481A (en) Laser internal control vertical section measuring method of high-rise building
CN207963844U (en) Mining influence lower room basic slope settles stretcher strain measuring device
KR101944445B1 (en) Apparatus for measuring position of construction in underground survey using gps
CA2851725A1 (en) Method for determination of the stability of a mast that has been properly set up at an installation site
KR102506511B1 (en) Rail Support, Apparatus for Measuring Rail Displacements and System for Measuring Rail Displacements Using the Same
CN214219763U (en) Foundation settlement observation system with variable datum
Šušić et al. Geodetic works for high-rise building construction monitoring

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant