KR101674435B1 - the establishment installation support for poor ground - Google Patents
the establishment installation support for poor ground Download PDFInfo
- Publication number
- KR101674435B1 KR101674435B1 KR1020150085921A KR20150085921A KR101674435B1 KR 101674435 B1 KR101674435 B1 KR 101674435B1 KR 1020150085921 A KR1020150085921 A KR 1020150085921A KR 20150085921 A KR20150085921 A KR 20150085921A KR 101674435 B1 KR101674435 B1 KR 101674435B1
- Authority
- KR
- South Korea
- Prior art keywords
- tubular
- anchor bit
- pillar
- reinforcing
- socket
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/38—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
- E02D5/44—Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with enlarged footing or enlargements at the bottom of the pile
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/80—Ground anchors
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
The present invention relates to a foundation for installing a soft ground facility, and more particularly, to a foundation for a solar panel and other various facilities in a soft foundation, a facility can be firmly installed without complicated processes such as a trowel and a foundation concrete work. And the like.
As a background of the invention, various supporting facilities such as a solar panel installation, a building facility, and a road facility are usually fixed on the ground in order to firmly fix the ground on the ground. After the foundation concrete is poured, the installation work is carried out on the anchor bolts embedded in the foundation concrete.
The foundation construction is inefficient considering the cost of trowel, mold work, remicon casting, demolition of formwork, and curing period of two weeks, and it takes 10-12% of the total civil works cost for the installation work of these facilities, Is creating problems.
In addition, in the case of laying the support of the facilities in the recent reclaimed land, wetland and water space, when the foundation concrete such as the previous one is laid, the process such as water draining is added and the economical efficiency is lowered and the waterside ecosystem is also affected.
In consideration of this problem, instead of fixing the facility to the foundation concrete, a general file is laid, and an oscillator method of rotating the bit and a rotary method (RCD) are applied. The pulling force is weak in the vertical direction, which leads to a decrease in the economic efficiency due to the extension of the depth of the pier and the operation time of the excavation equipment and the durability of the pillar.
On the other hand, in order to use only a spiral made landlord, the cost of the facility is excessively enforced and the economic efficiency due to the operation of the civil engineering equipment is accompanied.
As a reference, according to the related art according to Korean Patent No. 10-1190695, there is a technique of fixing a solar panel by using a screw anchor pillar having a predetermined length without pouring a foundation concrete. The screw anchor pillar is rotated, There is a problem that the installation depth is not constant depending on the stratum condition of the site due to the inconveniences such as cutting the upper end of the column and welding the foundation plate again.
As an alternative to this, a method of installing the screw anchors as described above is also disclosed. However, the used anchors or the anchors installed at the lower ends of the columns are not durable enough to cast gravel or rock layers for economical reasons.
Meanwhile, according to the related art according to Korean Registered Utility Model No. 20-0443819, a supporting structure for installing various facilities is composed of a wedge portion of an upper beam-lowered joint having a threaded outer periphery and a supporting portion at the upper end, In the case of soft ground with rock layer, there is a problem that the outer edge of the upper beam is made of thread and the wedge part of the upper beam structure causes the pulling force to fall, In the case of pouring the upper end, since the column fitting portion is broken, the installation depth becomes unstable, so that a part of the column is cut off, and a troublesome process of welding the column fitting portion again is accompanied.
In addition, the multipurpose mounting fixture according to the Japanese Laid-Open Utility Model Publication No. 20-2015-0000189 includes a tubular body configured to be inserted deeply into the strut, a nut forming a screw at the outer tubular periphery, and a nut for fixing the strut at the upper end of the tubular body, The lower end of the tube body is formed by a drill part formed by twisting a steel piece having a diameter smaller than the tube diameter.
In the above-described method, it is possible to install the tubular body in a pure soft ground by rotating the tubular body. However, when the soil layer is laid in a layer having gravel or rock in the bottom layer, the upper end of the tubular body is damaged. Of course, It can be seen that it is not an appropriate means.
The present invention provides an installation support for a soft ground that can firmly install a facility without complicated processes such as a trencher and a foundation concrete work in the foundation work of various facilities including a solar panel support in soft ground , It is possible to solve the problem pointed out as a problem related to the installation land of the conventional soft ground as described above, to enhance the durability while improving the economical efficiency, and in particular, to support the gravel or rock bed To be provided.
On the other hand, for the purpose of strengthening the pulling force in the soft ground, the spiral installation standard and the quantity of the spiral installation on the outer circumference of the column are adjusted to prevent the spiral from being installed in the pipe support more than necessary beforehand, Especially, the reinforcement core material to supplement the durability of the general piping pipe and the anchor bit structure of the special steel material which enables the pulling force in the soft ground and the casting in the gravel or the rock layer, The present invention aims to provide an installation support for a soft ground having a high economic efficiency and a use effect by providing an installation support for a soft ground,
In order to achieve the above object, the present invention provides a pipe support structure for a pipe, comprising: a
The installation
In the case where the
On the other hand, it solves the problem pointed out as a problem concerning the installation land for the existing soft ground, and enhances the durability while improving the economic efficiency.
Particularly, the concrete is disposed in the vicinity of the upper end of the tubular support pillar so that the upper end of the
In addition, the specification and quantity of the spiral installation can be adjusted in the field on the outer periphery of the columnar tube, thereby preventing the spiral from being installed and installed more than necessary.
In addition, it provides anchored bit structure of special steel material which can be installed in gravel or rock layer and anchor bit of special steel material that enables concrete to be poured into the underground deep part. It is a useful invention that provides a highly effective effect.
BRIEF DESCRIPTION OF THE DRAWINGS Fig. 1 is a perspective view of an installation main body of a facility for soft ground according to the present invention
Fig. 2 is an exploded perspective view of Fig.
3 is an exploded perspective view of the main part of the tubular support reinforcing core material and the anchor bit according to the present invention.
Figure 4 is a top perspective view of an anchor bit according to the present invention,
Fig. 5 is a perspective view of the bottom view in Fig.
Fig. 6 is a longitudinal sectional view showing the internal configuration of Fig. 4
FIG. 7 is a cross-sectional view showing the installation state of the installation main body of the facility for soft ground according to the present invention
Fig. 8 is a view showing the state of use of the facility for installing soft ground for a ground according to the present invention
FIG. 9 is an exploded perspective view of a tubular pillar height adjustment portion of a pillar for installation of soft ground according to the present invention
Fig. 10 is an exploded perspective view of the spiral split joint according to the present invention. Fig. 10 is an exploded perspective view of the spiral split joint according to the present invention.
BRIEF DESCRIPTION OF THE DRAWINGS The above and other objects, features and advantages of the present invention will be more apparent from the following detailed description taken in conjunction with the accompanying drawings, in which: FIG.
1 is an entire perspective view of a support main body for a soft ground according to the present invention, FIG. 2 is an exploded perspective view of FIG. 1,
Installment of Facility for Soft Ground The pillar
The lower end of the
The upper end of the
The upper portion of the height adjusting
The detailed constituent means of the installation
1 and 2 attached to the present invention, and FIG. 3 which is a perspective view of a main part of the present invention, which is a disassembled and assembled perspective view of a tubular support reinforcement core part and an anchor bit, 104), a hollow portion 85ø having a reinforcing groove formed on its rim, a
The reinforcing core
The
The
The
The spiral
10 is a view showing a state of use of a spiral split joint according to the present invention, in which a small diameter spiral split joint is fastened, and FIG. 10 is an example of tightening a large diameter spiral split joint.
As shown in FIG. 10, a selected one of the
Next, as shown in an exploded perspective view of the tubular column height adjusting portion of the installation for a soft ground according to the present invention, a
The tubular post
The tubular support
With reference to FIG. 8, which is a state of use of the installation support main body for a soft ground installation according to the present invention, the operation of the tubular
Since the
Therefore, the installation depth and the installation position are different from the originally designed values according to the geological condition of the site, and thus, the effort and cost of the construction cost have been considerable in setting the height and assembly position of the
For this purpose, even when the
The adjustment of the placement position of the
The process for installing the
The main body 100 for installing soft ground facilities according to the present invention includes a reinforcing core member 101 fixed integrally with the lower end of the tubular support 101 under the tubular support lower reinforcement pipe 108 reinforced and fixed at the lower end of the tubular support 101, The lower plate 107 and the anchor bit 110 are integrally fixed and the anchor bit 110 is formed in the anchor bit portion 110 in the inner diameter of the tube support 101, The reinforcing core material upper cap 108 is inserted into the reinforcing bar 104 protruding from the upper end of the tube support 101 in a state where the reinforcing bars 104 disposed in the reinforcing bar 150 are embedded, Is installed at the distal end of the ready-made filler pipe 103 which is inserted through the hollow portion of the reinforcing core member 150 reaching the lower end of the tube support 101 through the ready-made filler tube nipple 102 protruded from one side of the upper end of the tube support 101 A Y tube 103 'is formed on an upper surface of the anchor bit portion 110, There are formed four holes through which the reinforcing bars 104 of the base reinforcement core member 150 pass and two holes adjacent to the ready-mix injecting pipe 103 and four holes through which the reinforcing bars 104 pass, It is supplied on-site in the state of study.
The
The ready-mix concrete is inserted into the reinforcing core
The ready-mix filled from the lower end of the
The upper end of the
The
100: Body 101:
102: Remicon Injection Pipe Nipple 103: Remicon Injection Pipe
103 ': Y tube 103'': Racon injection cone
104: Rebar
105: space-maintaining plate 106: reinforcing core material center plate
107: reinforcing core material lower plate 108: tube supporting lower reinforcing tube
109: Upper holding cap
110:
110b:
110d: Anchor bit
110f: Anchor bit, crossed edge
120: Spiral split cube
120a:
120c: Spiral side mounting flange
120d, 130d,
130: height adjustment socket split joint part
130a: height adjustment socket split joint
130b: Split joint lower assembling flange
130c: Split joint Lateral assembling flange
140: tube holding Height adjusting portion
140a:
140b ': height-
140d:
140f ': Through bolt hole
150: reinforcing core member
Claims (7)
A tubular support 101 cut into a predetermined length of the pipe 100A (4t);
The lower end of the tubular support 101 includes an anchor bit 110 for integrally welding the tubular support lower reinforcement pipe 108 to the outer diameter portion and fixing the tubular support lower reinforcement pipe 108 to the distal end portion.
The middle part of the tubular support 101 includes a spiral split joint part 120 of a water tank to be detached by the assembly bolt 120d and the assembly nut 120e;
The upper end of the tubular support 101 has a height adjustment socket split joint 130 for reinforcing the upper support cap 109 and connecting the height adjustment socket 140f to the upper support cap 109;
The upper portion of the height adjustment socket split joint part 130 includes a tube support height adjustment part 140 which is fastened with a through bolt 140c, a washer 140d and a nut 140e. Installation holding.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150085921A KR101674435B1 (en) | 2015-06-17 | 2015-06-17 | the establishment installation support for poor ground |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150085921A KR101674435B1 (en) | 2015-06-17 | 2015-06-17 | the establishment installation support for poor ground |
Publications (1)
Publication Number | Publication Date |
---|---|
KR101674435B1 true KR101674435B1 (en) | 2016-11-09 |
Family
ID=57528782
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020150085921A KR101674435B1 (en) | 2015-06-17 | 2015-06-17 | the establishment installation support for poor ground |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101674435B1 (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101917846B1 (en) * | 2017-10-13 | 2018-11-12 | 주식회사 빛날에너지 | solar power plant support apparatus for slope land |
KR101946568B1 (en) * | 2018-12-13 | 2019-02-11 | (주)건국 | spiral For Ground Reinforcement |
KR102073061B1 (en) * | 2019-03-29 | 2020-02-04 | (주)뉴저스트 | Underground piles forming apparatus and underground piles forming method using the apparatus |
KR20210017358A (en) * | 2019-08-08 | 2021-02-17 | 주식회사 이안이엔지 | Pile support device for ground reinforcement |
KR20210105627A (en) * | 2020-02-19 | 2021-08-27 | 주식회사 이안이엔지 | Pile support device for ground reinforcement |
KR102609793B1 (en) | 2023-07-06 | 2023-12-05 | 주식회사 태신이앤씨 | The landfill support for soft ground |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100557010B1 (en) * | 2003-06-18 | 2006-03-07 | 주식회사 장평건설 | Earth anchor including a duplex grouting pipe and the earth anchor construction method using the same |
JP2007205108A (en) * | 2006-02-03 | 2007-08-16 | Sankin B & G Kk | Joint structure of foundation pile and strut of building and the foundation pile used therefor |
KR100874721B1 (en) * | 2007-01-31 | 2008-12-18 | 한상억 | Vertical auto jack adjustment |
KR200443819Y1 (en) | 2008-10-21 | 2009-03-13 | 크리너코리아 (주) | Installation structure of facilities post |
KR101190695B1 (en) | 2011-10-17 | 2012-10-12 | (주)지티씨코퍼레이션 | An assembling solar photovoltaic power generator |
KR20140128478A (en) * | 2013-04-25 | 2014-11-06 | 재단법인 포항산업과학연구원 | Foundation structure of modular building |
KR20150000189U (en) | 2013-07-05 | 2015-01-14 | 전선열 | Holder for multipurpose support installation |
-
2015
- 2015-06-17 KR KR1020150085921A patent/KR101674435B1/en active IP Right Grant
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100557010B1 (en) * | 2003-06-18 | 2006-03-07 | 주식회사 장평건설 | Earth anchor including a duplex grouting pipe and the earth anchor construction method using the same |
JP2007205108A (en) * | 2006-02-03 | 2007-08-16 | Sankin B & G Kk | Joint structure of foundation pile and strut of building and the foundation pile used therefor |
KR100874721B1 (en) * | 2007-01-31 | 2008-12-18 | 한상억 | Vertical auto jack adjustment |
KR200443819Y1 (en) | 2008-10-21 | 2009-03-13 | 크리너코리아 (주) | Installation structure of facilities post |
KR101190695B1 (en) | 2011-10-17 | 2012-10-12 | (주)지티씨코퍼레이션 | An assembling solar photovoltaic power generator |
KR20140128478A (en) * | 2013-04-25 | 2014-11-06 | 재단법인 포항산업과학연구원 | Foundation structure of modular building |
KR20150000189U (en) | 2013-07-05 | 2015-01-14 | 전선열 | Holder for multipurpose support installation |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101917846B1 (en) * | 2017-10-13 | 2018-11-12 | 주식회사 빛날에너지 | solar power plant support apparatus for slope land |
KR101946568B1 (en) * | 2018-12-13 | 2019-02-11 | (주)건국 | spiral For Ground Reinforcement |
KR102073061B1 (en) * | 2019-03-29 | 2020-02-04 | (주)뉴저스트 | Underground piles forming apparatus and underground piles forming method using the apparatus |
KR20210017358A (en) * | 2019-08-08 | 2021-02-17 | 주식회사 이안이엔지 | Pile support device for ground reinforcement |
KR102284782B1 (en) * | 2019-08-08 | 2021-08-04 | 주식회사 이안이엔지 | Pile support device for ground reinforcement |
KR20210105627A (en) * | 2020-02-19 | 2021-08-27 | 주식회사 이안이엔지 | Pile support device for ground reinforcement |
KR102368643B1 (en) * | 2020-02-19 | 2022-02-28 | 주식회사 이안이엔지 | Pile support device for ground reinforcement |
KR102609793B1 (en) | 2023-07-06 | 2023-12-05 | 주식회사 태신이앤씨 | The landfill support for soft ground |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101674435B1 (en) | the establishment installation support for poor ground | |
KR101212240B1 (en) | Structure for underground downward extension of structural remodeling and methode thereof | |
CN102162258B (en) | Concrete-filled steel tubular high-pile tower footing structure of tower crane and construction method thereof | |
CN112609703B (en) | Soil nailing wall support construction process | |
CN101294384A (en) | Pile, pole interface positioning device and construction method | |
CN109537604A (en) | A method of utilizing screw pile bolt anchorage Cut Slopes of Expansive Soil | |
JP2018028254A (en) | Repair method of existing canal | |
CN109931077B (en) | Support system for tunnel repair and construction method thereof | |
KR100642326B1 (en) | A temporary apparatus for constructing girder by top-down style construction method | |
US5806262A (en) | Post and method of emplacing a post | |
KR20120065844A (en) | Retaining wall structure and method thereof | |
JP5456627B2 (en) | Connection structure and method of connection between pile and steel column | |
JP4029191B2 (en) | Subsidence suppression structure, construction method of settlement suppression structure | |
KR101138499B1 (en) | Method for Head Setting of Micro-Pile and Apparatus for the Same | |
KR101624706B1 (en) | Foundation structure for pillar and construction method thereof | |
CN211974070U (en) | Built-in section steel column fixing system | |
JP2005240426A (en) | Erection structure for steel-pipe column | |
KR20080059951A (en) | Underground outer wall construction method using temporary retaining wall and connecting member strengthening shearing force therefor | |
EP3124705A1 (en) | Formers | |
KR101799237B1 (en) | Method of manufacturing grounding stone for pillar fixed and grounding stone for pillar fixed produced by the same | |
US10077539B1 (en) | Wall and retaining members and fluidizing installation of retaining members | |
KR20130073336A (en) | Pile structure and construction methods | |
KR101257905B1 (en) | Method for constructing foundation work | |
KR101357637B1 (en) | Horizontal shear connector for precast concrete bridge pier | |
CN110847498A (en) | Built-in section steel column fixing system and application construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20191021 Year of fee payment: 4 |