KR101586165B1 - Hot water supply system - Google Patents

Hot water supply system Download PDF

Info

Publication number
KR101586165B1
KR101586165B1 KR1020150010131A KR20150010131A KR101586165B1 KR 101586165 B1 KR101586165 B1 KR 101586165B1 KR 1020150010131 A KR1020150010131 A KR 1020150010131A KR 20150010131 A KR20150010131 A KR 20150010131A KR 101586165 B1 KR101586165 B1 KR 101586165B1
Authority
KR
South Korea
Prior art keywords
hot water
water supply
temperature
pipe
tank
Prior art date
Application number
KR1020150010131A
Other languages
Korean (ko)
Inventor
아카네 이리야
히로모토 이나미
Original Assignee
린나이코리아 주식회사
린나이가부시기가이샤
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 린나이코리아 주식회사, 린나이가부시기가이샤 filed Critical 린나이코리아 주식회사
Priority to KR1020150010131A priority Critical patent/KR101586165B1/en
Application granted granted Critical
Publication of KR101586165B1 publication Critical patent/KR101586165B1/en

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D17/00Domestic hot-water supply systems
    • F24D17/02Domestic hot-water supply systems using heat pumps
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24HFLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
    • F24H4/00Fluid heaters characterised by the use of heat pumps
    • F24H4/02Water heaters
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24HFLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
    • F24H4/00Fluid heaters characterised by the use of heat pumps
    • F24H4/02Water heaters
    • F24H4/04Storage heaters
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D2200/00Heat sources or energy sources
    • F24D2200/12Heat pump

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Heat-Pump Type And Storage Water Heaters (AREA)

Abstract

The present invention provides a hot water supply system which can supply hot water having an appropriate temperature to a hot water supply port in case of supplying hot water to the hot water supply port on the way of hot water supply operation supplying hot water into a bathtub. To achieve this, a bypass valve (39) is controlled in an opening state for a predetermined period right after starting hot water supply operation, and the bypass valve (39) is controlled in a closed state after the predetermined period, in case of starting hot water supply operation of a bathtub before elapsed time reaches predetermined time after the end of hot water supply operation performing temperature control of a hot water supply temperature by controlling an opening degree of the bypass valve (39) of a tapping bypass pipe (34).

Description

급탕시스템{HOT WATER SUPPLY SYSTEM}HOT WATER SUPPLY SYSTEM

본 발명은 저탕 탱크를 가지는 급탕시스템에 관한 것이다.
The present invention relates to a hot water supply system having a storage tank.

히트펌프 등의 가열장치에 의해 가열한 탕수를 저류하는 저탕 탱크를 가지는 급탕시스템으로서는, 종래, 예를 들면, 특허문헌 1에 보여지는 것이 알려져 있다.BACKGROUND ART [0002] As a hot water supply system having a storage tank for storing hot water heated by a heating device such as a heat pump, for example, as shown in Patent Document 1, is known heretofore.

이 급탕시스템은 저탕 탱크의 상부로부터 도출된 출탕관과, 저탕 탱크의 하부 및 출탕관의 도중부에 접속된 급수관과, 출탕관의 하류측에 배치된 연소식 급탕기(연소열에 의해 열교환기를 통하여 통수를 가열하는 급탕기)와, 출탕관의 상기 도중부에서 하류측으로 흐르는 탕수를, 연소식 급탕기를 바이패스시켜서 출탕관의 상류측에서 하류측으로 흘리는 출탕바이패스관을 가진다.This hot water supply system includes a water outlet pipe extending from the upper part of the storage tank, a water supply pipe connected to a lower part of the storage tank and a midway portion of the outlet pipe, and a combustion type hot water supply unit disposed downstream of the hot water supply pipe And a tapping bypass pipe through which hot water flowing from the midway portion of the outlet pipe to the downstream side is passed from the upstream side to the downstream side of the outlet pipe by bypassing the combustion type hot water heater.

또한, 연소식 급탕기의 열교환기의 하류측의 출탕관에는, 상기 열교환기에서 가열된 탕수를 욕조에 공급하는 탕수공급관이 접속되어 있으며, 상기 탕수공급관을 통하여 욕조로의 탕수 공급을 실행하는 것도 가능하게 되어 있다.A hot water supply pipe for supplying the hot water heated in the heat exchanger to the bathtub is connected to the hot water supply pipe on the downstream side of the heat exchanger of the combustion type hot water supply unit and the hot water supply to the bathtub can be performed through the hot water supply pipe .

이 급탕시스템에서는 저탕 탱크의 고온의 탕수가 충분히 존재하고 있는 상황(탕수소진상태가 아닌 상황)에서는, 연소식 급탕기의 가열운전을 실행하지 않고, 저탕 탱크 내의 고온의 탕수에 물을 혼합하여 이루어지는 탕수를 출탕관 종단의 급탕구, 혹은, 욕조에 공급한다.In this hot water supply system, in the state where the hot water of the storage tank is sufficiently present (in a situation where the hot water is not exhausted), the hot water of the hot water in the storage tank is mixed with hot water To the hot water supply port at the end of the hot water tank or to the bathtub.

또한, 저탕 탱크의 탕수소진상태가 되면, 연소식 급탕기의 가열운전을 실행하는 것에 의해, 저탕 탱크 혹은 급수관으로부터 연소식 급탕기에 탕수를 공급하면서, 상기 탕수를 연소식 급탕기의 가열운전에 의해 가열하고, 그 가열된 탕수를 출탕관 종단의 급탕구, 혹은, 욕조에 공급한다.When the boiled water in the boiling tank is in the boil-off state, the heating operation of the boiler is carried out to heat the boiled water by the heating operation of the boiler, while supplying the boiled water from the boiling tank or the water pipe to the combustion boiler , And the heated hot water is supplied to the hot water supply port at the end of the hot water tank or the bathtub.

더욱 상세하게는, 특허문헌 1에 보여지는 급탕시스템에서는, 출탕관의 급탕구로의 급탕을 실행하는 급탕운전시에는, 저탕 탱크가 탕수소진상태가 아닌 경우에는, 상기 출탕바이패스관에 개장(介裝)된 바이패스밸브를 개방한 상태에서 상기 출탕바이패스관을 통하여 급탕을 실행하고, 저탕 탱크의 탕수소진상태에서는 상기 바이패스밸브를 폐쇄하여 급탕구에 공급하는 탕수의 전량(全量)을 저탕 탱크 또는 급수관측으로부터 연소식 급탕기에 유입시키도록 하고 있다.More specifically, in the hot water supply system shown in Patent Document 1, in the hot water supply operation for hot water supply to the hot water supply port of the hot water tank, when the hot water tank is not in the hot water exhaust state, (Total amount) of the hot water to be supplied to the hot water supply opening is closed when the hot water in the hot water storage tank is exhausted, the hot water is supplied through the hot water supply pipe And is introduced into the combustion type hot water tank from the tank or the water supply observation side.

또한, 욕조의 탕수공급을 실행하는 탕수공급운전시에는, 저탕 탱크가 탕수소진상태인지 아닌지에 의하지 않으며, 상기 바이패스밸브를 폐쇄한 상태에서 저탕 탱크 또는 급수관으로부터 연소식 급탕기에 탕수를 도입하고, 상기 연소식 급탕기로부터 탕수공급관을 통하여 욕조의 탕수공급을 실행하도록 하고 있다.
In addition, when the hot water supply operation for supplying the hot water to the bathtub is performed, the hot water is introduced into the combustion type hot water tank from the storage tank or the water supply pipe without closing the bypass valve regardless of whether or not the storage tank is in the hot water exhaustion state, And the hot water supply of the bathtub is performed from the combustion type hot water supply device through the hot water supply pipe.

특허문헌 1: 일본국 특개2011-153797호 공보Patent Document 1: JP-A-2011-153797

그런데, 저탕 탱크의 탕수소진상태에서의 급탕운전시에, 상기 특허문헌 1에 보여지는 바와 같이, 급탕구에 공급하는 탕수의 전량을 연소식 급탕기에 공급하면, 상기 탕수의 유량이 큰 경우에 연소식 급탕기에서의 압력 손실이 커지기 쉽다.However, when the hot water supplied from the hot water tank to the hot water supply unit is supplied to the hot water supply unit as shown in the patent document 1, when the flow rate of the hot water is large, The pressure loss in the news hot water tank is likely to increase.

그래서, 상기 급탕운전시에, 출탕바이패스관의 바이패스밸브의 개방도를 조정하는(출탕바이패스관의 유량을 조정하는) 것에 의해, 연소식 급탕기와 바이패스출탕관의 양쪽에 탕수를 흘림과 아울러, 연소식 급탕기에서 가열한 탕수와 바이패스출탕관을 통과하는 탕수를 혼합하고, 그 혼합에 의해 목표의 급탕온도로 조정한 탕수를 출탕관의 급탕구에 공급하는 것을 생각할 수 있다.Thus, when the hot water supply operation is performed, the opening degree of the bypass valve of the hot water bypass pipe is adjusted (the flow rate of the hot water bypass pipe is adjusted), whereby hot water is flowed to both the combustion water heater and the bypass hot water pipe The hot water heated in the combustion type hot water heater and the hot water passing through the bypass hot water tank are mixed and the hot water adjusted to the target hot water temperature by mixing is supplied to the hot water supply port of the hot water tank.

이와 같이 한 경우에는, 급탕구에 공급하는 탕수의 전량을 연소식 급탕기와 출탕바이패스관에 분배할 수 있으므로, 연소식 급탕기에서의 압력 손실을 저감할 수 있다.In this case, the entire amount of the hot water supplied to the hot water supply port can be distributed to the combustion type hot water heater and the hot water bypass pipe, so that the pressure loss in the combustion type hot water heater can be reduced.

그런데, 이와 같이 한 경우에는, 다음과 같은 문제점이 발생하는 경우가 있는 것이 본원 발명자 등의 검토에 의해서 판명되었다.However, in such a case, the inventors of the present invention have found that the following problems may occur.

즉, 저탕 탱크의 탕수소진상태에서의 급탕운전시에, 상기한 바와 같이 연소식 급탕기에서 가열된 탕수와 출탕바이패스관을 통과하는 탕수를 혼합하도록 한 경우에는, 연소식 급탕기의 출구측의 유로(열교환기의 하류측의 유로) 중, 출탕바이패스관의 접속 개소보다도 상류측의 유로 내의 탕수는 목표급탕온도보다도 고온인 것으로 된다.That is, when the hot water heated in the combustion type hot water supply unit and the hot water passing through the tap water bypass pipe are mixed at the time of the hot water supply operation in the hot water storage tank in the hot water storage tank, (The flow path on the downstream side of the heat exchanger), the hot water in the flow path upstream of the connection point of the tap water bypass pipe is higher than the target hot water temperature.

한편, 특허문헌 1에 보여지는 급탕시스템에서는, 욕조의 탕수공급운전시에는, 출탕바이패스관의 바이패스밸브를 폐쇄상태로 하므로, 상기와 같은 급탕운전을 실행한 직후에, 욕조의 탕수공급운전을 실행하면, 연소식 급탕기의 출구측의 유로 속에 비교적 고온의 탕수가 잔존하게 된다.On the other hand, in the hot water supply system shown in Patent Document 1, since the bypass valve of the tap water bypass pipe is closed when the hot water supply operation of the bathtub is performed, immediately after the hot water supply operation as described above is performed, , Relatively hot water remains in the flow path on the outlet side of the combustion type hot water heater.

이로 인해, 이 탕수공급운전중에, 급탕운전을 재개하면, 연소식 급탕기의 출구측의 유로 속에 잔존하고 있었던 탕수가 목표급탕온도보다도 높은 온도 상태에서 급탕구에 공급되는 경우가 있다.Therefore, when the hot water supply operation is resumed during the hot water supply operation, the hot water remaining in the flow path on the outlet side of the combustion type hot water heater may be supplied to the hot water supply port at a temperature higher than the target hot water temperature.

본 발명은 상기의 배경에 감안하여 이루어진 것이며, 욕조의 탕수공급을 실행하는 탕수공급운전의 도중에서의 급탕구로의 급탕을 실행하는 경우에, 적절한 온도 상태의 탕수를 급탕구에 공급할 수 있는 급탕시스템을 제공하는 것을 목적으로 한다.
SUMMARY OF THE INVENTION The present invention has been made in view of the background described above, and it is an object of the present invention to provide a hot water supply system capable of supplying hot water of a suitable temperature state to a hot water supply port, And to provide the above objects.

본 발명의 급탕시스템은, 상기의 목적을 달성하기 위해, 저탕 탱크와, 상기 저탕 탱크 내의 탕수를 가열하는 가열수단과, 상기 저탕 탱크 내의 탕수가 공급되도록 상기 저탕 탱크로부터 도출되고, 종단에 급탕구를 가지는 출탕관과, 상기 저탕 탱크에 급수하도록 상기 저탕 탱크에 접속된 급수관과, 상기 출탕관의 도중에 설치된 열교환기를 가지며, 상기 열교환기에서 상기 출탕관을 흐르는 탕수를 버너의 연소열에 의해 가열하는 연소식 급탕기와, 상기 연소식 급탕기의 상류측에 있어서의 상기 출탕관의 도중부(A)와 상기 연소식 급탕기의 하류측에 있어서의 상기 출탕관의 도중부(B)를 연통시키는 출탕바이패스관과, 상기 출탕바이패스관을 개폐 가능하게 상기 출탕바이패스관에 설치된 바이패스밸브와, 상기 연소식 급탕기의 열교환기의 하류측에서 상기 도중부(B)에 이르는 상기 출탕관으로부터 분기되어 욕조에 접속된 탕수공급관을 구비하고, 상기 출탕관의 급탕구로의 급탕을 실행하는 급탕운전과 상기 욕조로의 탕수공급을 실행하는 탕수공급운전을 실행 가능하게 구성된 급탕시스템으로서,In order to achieve the above-mentioned object, the hot water supply system of the present invention is characterized in that it comprises a storage tank, heating means for heating the hot water in the storage tank, A water supply pipe connected to the storage tank to supply water to the storage tank, and a heat exchanger installed in the middle of the discharge pipe, wherein the hot water flowing in the hot water tank is heated by the combustion heat of the burner, A hot water boiler and a hot water bypass pipe for communicating an intermediate portion (A) of the hot water tank on the upstream side of the combustion type hot water heater with a middle portion (B) of the hot water tank on the downstream side of the flue gasifier, A bypass valve provided in the brewing bypass pipe so as to be able to open and close the brewing by-pass pipe, and a bypass valve provided on the downstream side of the heat exchanger of the combustion type hot- And a hot water supply pipe branched from the hot water supply pipe to the hot water supply pipe and connected to the hot water supply pipe to the hot water supply pipe, A hot water system comprising:

상기 급탕시스템의 운전제어를 실행하는 운전제어수단을 구비하고 있으며,And operation control means for executing operation control of the hot water supply system,

상기 운전제어수단은,Wherein the operation control means includes:

상기 급탕운전시에, 상기 연소식 급탕기에 상류측으로부터 유입되는 탕수를 상기 연소식 급탕기의 가열운전에 의해 가열함과 아울러, 이 가열된 탕수와 상기 연소식 급탕기의 상류측에서 상기 출탕바이패스관을 통과하여 하류측으로 흐르는 탕수를 상기 도중부(B)에서 혼합시킴으로써, 상기 급탕구에 공급하는 탕수의 온도가 목표급탕온도로 되도록 상기 연소식 급탕기의 가열운전과 상기 바이패스밸브의 개방도를 제어하는 처리인 바이패스혼합급탕제어처리를 실행하는 기능과,The hot water flowing from the upstream side to the combustion type hot water heater is heated by the heating operation of the combustion type hot water heater at the time of the hot water supply operation and at the same time, The heating operation of the combustion type hot water heater and the opening degree of the bypass valve are controlled so that the temperature of the hot water supplied to the hot water supply port becomes the target hot water temperature, A process for executing a bypass mixed hot water supply control process,

상기 바이패스혼합급탕제어처리를 실행하는 급탕운전의 종료 후, 소정시간이 경과되기 전에, 상기 탕수공급운전을 개시할 경우에는, 상기 탕수공급운전의 개시 직후의 소정기간은, 상기 탕수공급관을 통하여 상기 욕조로의 탕수의 공급을 실행시키면서, 상기 바이패스밸브를 개방상태로 제어하고, 또한, 상기 소정기간의 경과 후에 상기 바이패스밸브를 폐쇄상태로 제어하는 기능과,When the water supply operation is started before a predetermined time elapses after the completion of the hot water supply operation for executing the bypass mixed hot water supply control process, a predetermined period of time immediately after the start of the hot water supply operation is performed through the hot water supply pipe A function of controlling the bypass valve to be in the open state while the supply of the hot water to the bath is performed and controlling the bypass valve to be in the closed state after the lapse of the predetermined period,

상기 바이패스혼합급탕제어처리를 실행하는 급탕운전의 종료 후, 상기 소정시간이 경과된 후에, 상기 탕수공급운전을 개시할 경우에는, 상기 탕수공급관을 통하여 상기 욕조로의 탕수의 공급을 실행시키면서, 상기 바이패스밸브를 즉시 폐쇄상태로 제어하는 기능을 가지도록 구성되어 있는 것을 특징으로 한다(제 1 발명).Wherein when the water supply operation is started after the predetermined time has elapsed after the end of the hot water supply operation for executing the bypass mixed hot water supply control process, the supply of the hot water to the bathtub is performed through the hot water supply pipe, And a function of immediately controlling the bypass valve to be in a closed state (first invention).

상기의 제 1 발명에 있어서, 상기 바이패스혼합급탕제어처리를 실행하는 급탕운전에서는, 상기 도중부(B)보다도 연소식 열교환기측의 출탕관의 탕수가 목표급탕온도보다도 높은 온도가 되도록 상기 연소식 열교환기의 가열운전이 실행되게 된다.In the first aspect of the present invention, in the hot water supply operation for executing the bypass mixed hot water supply control process, the hot water in the hot water outlet of the combustion type heat exchanger is heated to a temperature higher than the target hot water temperature, The heating operation of the heat exchanger is executed.

여기서, 상기 바이패스혼합급탕제어처리를 실행하는 급탕운전의 종료 후, 소정시간 경과하기 전의 상황은, 상기 급탕운전의 종료 직후의 상황이므로, 상기 도중부(B)보다도 연소식 열교환기측의 출탕관의 탕수의 온도가 충분히 저하되어 있지 않은 것이 예측되는 상황이다.Here, the situation before the elapse of the predetermined time after the end of the hot water supply operation for executing the bypass mixed hot water supply control process is a situation immediately after the end of the hot water supply operation, and therefore, It is predicted that the temperature of the boiled water in the boiler is not sufficiently lowered.

그리고 이와 같은 상황에서, 상기 탕수공급운전을 개시할 경우에는, 상기 바이패스밸브는, 탕수공급운전의 개시 직후의 소정기간에서는, 개방상태로 제어되고, 상기 소정기간의 경과 후에 폐쇄상태로 제어된다.In such a situation, when the water supply operation is started, the bypass valve is controlled to be in the open state in a predetermined period immediately after the start of the water supply operation, and is controlled to be in the closed state after the predetermined period of time elapses .

이 경우, 탕수공급운전의 개시 직후의 소정기간에서는, 바이패스밸브를 개방상태로 해서 탕수공급관을 통하여 욕조로의 탕수의 공급을 실행하는 것에 의해, 상기 출탕관의 도중부(A)에 상류측으로부터 유입되는 탕수의 일부가, 출탕바이패스관 및 도중부(B)를 경유하여 상기 도중부(B)보다도 연소식 급탕기측의 출탕관에 하류측으로부터 유입되게 된다.In this case, in the predetermined period immediately after the start of the drinking water supply operation, by supplying the hot water to the tub through the hot water supply pipe with the bypass valve being opened, the hot water is supplied to the middle portion A of the hot water supply pipe A portion of the hot water flowing from the hot water supply side is introduced into the outlet duct on the side of the combustion type hot water supply unit from the downstream side via the hot water bypass pipe and the midway portion B,

또한, 이 경우에, 상기 출탕관의 도중부(A)에 상류측으로부터 유입되는 탕수는, 통상, 상기 바이패스혼합급탕제어처리를 실행하는 급탕운전의 종료 직후에 있어서, 도중부(B)보다도 연소식 급탕기측의 출탕관에 잔류하는 탕수의 온도보다도 낮다.In this case, the hot water flowing from the upstream side to the midway portion A of the outlet hot water pipe is, generally, immediately after the end of the hot water supply operation for performing the bypass mixed hot water control process, Is lower than the temperature of the hot water remaining in the outlet pipe on the side of the combustion type hot water heater.

이로 인해, 상기 도중부(B)보다도 연소식 열교환기측의 출탕관의 탕수의 온도를, 상기 탕수공급운전의 개시 직후의 상기 소정기간 내(바이패스밸브가 개방상태로 제어되는 기간 내)에, 신속하게 저하시키는 것이 가능하게 된다.Therefore, the temperature of the hot water in the hot water outlet of the combustion type heat exchanger is lower than that in the middle portion (B) within the predetermined period immediately after the start of the hot water supply operation (within a period in which the bypass valve is controlled to be open) It becomes possible to rapidly lower the temperature.

따라서, 상기 소정기간의 경과 후에 있어서의 바이패스밸브의 폐쇄상태에서의 탕수공급운전중에, 급탕구의 개전(開栓)에 의해서 상기 급탕구로의 급탕이 개시되어도, 그 개시 직후에, 상기 급탕구에 목표급탕온도에 비하여 고온인 탕수가 급탕되는 것이 방지된다.Therefore, even if the hot water supply to the hot water supply opening is started by the opening of the hot water supply opening during the water supply operation in the closed state of the bypass valve after the lapse of the predetermined period, immediately after the start of the hot water supply, The hot water having a higher temperature than the target hot water temperature is prevented from being heated.

또한, 상기 소정기간으로서는, 예를 들면, 탕수공급운전의 개시시부터, 제 2 소정시간이 경과될 때까지의 기간 등을 채용할 수 있다. 이 경우, 제 2 소정시간으로서는, 예를 들면, 미리 정한 일정시간, 혹은, 상기 바이패스혼합급탕제어처리를 실행하는 급탕운전의 종료시부터 탕수공급운전의 개시시까지의 경과시간 등에 따라서 가변적으로 설정한 시간을 채용할 수 있다. 상기 소정기간은, 예를 들면, 그 기간 내에 상기 도중부(B)보다도 연소식 열교환기측의 출탕관의 탕수의 온도를 목표급탕온도와 동일한 정도이던지 혹은 그 이하의 온도로 저하시킬 수 있도록 설정되어 있으면 좋다.The predetermined period may be, for example, a period from the start of the water supply operation to the elapse of the second predetermined time. In this case, as the second predetermined time, for example, it is possible to variably set a predetermined time according to an elapsed time from the end of the hot water supply operation for executing the bypass mixed hot water supply control process to the start of the hot water supply operation One hour can be employed. The predetermined period may be set so that the temperature of the hot water in the hot water outlet of the combustion type heat exchanger can be lowered to a temperature equal to or lower than the target hot water temperature within the period (B) It is good.

또한, 탕수공급운전의 개시 직후의 소정기간에 있어서의 바이패스밸브의 개방상태에서, 급탕구의 개전에 의해서 상기 급탕구로의 급탕이 개시된 경우, 그 개시 직후에는, 도중부(B)보다도 연소식 열교환기측의 출탕관에서 상기 도중부(B)로 향하여 흘러 오는 탕수와, 도중부(A)의 상류측에서 출탕바이패스관을 통과하여 도중부(B)로 흘러 오는 탕수가, 상기 도중부(B)에서 혼합되고, 그 혼합 후의 탕수가 급탕구에 공급되게 된다.When the hot water supply to the hot water supply opening is started by the opening of the hot water supply opening in the bypass valve opened state for a predetermined period immediately after the start of the water supply operation, immediately after the start of the hot water supply operation, The hot water flowing from the outlet duct to the intermediate portion B and the hot water flowing from the upstream side of the middle portion A to the middle portion B through the tapping bypass pipe are supplied to the middle portion B ), And the mixed water after the mixing is supplied to the hot water supply port.

이로 인해, 탕수공급운전의 개시 직후의 소정기간 내에 급탕구로의 급탕을 개시해도, 그 개시 직후에, 상기 급탕구에 목표급탕온도에 비하여 고온인 탕수가 급탕되는 것을 방지할 수 있다.Therefore, even if the hot water supply to the hot water supply opening is started within a predetermined period immediately after the start of the hot water supply operation, it is possible to prevent the hot water, which has a higher temperature than the target hot water temperature, from being supplied to the hot water supply opening immediately after the start of the hot water supply.

또한, 상기 바이패스혼합급탕제어처리를 실행하는 급탕운전의 종료 후, 상기 소정시간이 경과된 후에, 탕수공급운전이 개시된 경우에는, 상기 도중부(B)보다도 연소식 열교환기측의 출탕관의 탕수의 온도는, 상기 탕수공급운전의 개시 전의 방열에 의해서, 상기 탕수공급운전의 개시시에는 충분히 저하되어 있다.When the water supply operation is started after the predetermined time has elapsed after the end of the hot water supply operation for executing the bypass mixed hot water supply control process, the hot water supply from the hot water outlet of the combustion type heat exchanger Is sufficiently lowered at the start of the water supply operation by the heat radiation before the start of the water supply operation.

이로 인해, 상기의 탕수공급운전중에, 급탕구로의 급탕이 개시되어도, 그 개시 직후에, 상기 급탕구에 목표급탕온도에 비하여 고온인 탕수가 급탕되는 것을 방지할 수 있다.Therefore, even if the hot water supply to the hot water supply opening is started during the hot water supply operation, it is possible to prevent the hot water, which has a higher temperature than the target hot water temperature, from being supplied to the hot water supply opening immediately after the start of the hot water supply.

따라서, 제 1 발명에 따르면, 적절한 온도 상태의 탕수를 급탕구에 공급할 수 있다.Therefore, according to the first invention, it is possible to supply the hot water with an appropriate temperature state to the hot water supply port.

또한, 상기 소정기간의 경과 후의 탕수공급운전시, 혹은, 상기 바이패스혼합급탕제어처리를 실행하는 급탕운전의 종료 후, 상기 소정시간이 경과된 후에 개시된 탕수공급운전시에는, 바이패스밸브가 폐쇄상태로 제어되므로, 상기 출탕관의 도중부(A)에 상류측으로부터 유입되는 탕수의 전량이, 연소식 급탕기에 상류측으로부터 공급되게 된다.During the hot water supply operation after the lapse of the predetermined period or after the end of the hot water supply operation for executing the bypass mixed hot water supply control process and during the water supply operation operation started after the lapse of the predetermined time, The entire amount of the hot water flowing from the upstream side to the middle portion A of the outlet pipe is supplied from the upstream side to the combustion type hot water heater.

이로 인해, 연소식 급탕기에서의 탕수의 가열량을 제어하고, 혹은, 상기 도중부(A)의 상류측에서 저탕 탱크에서 출탕관으로 공급되는 탕수에, 물을 혼합시키면서, 그 혼합비를 제어함으로써, 욕조에 공급하는 탕수의 온도를 정밀도 좋게 목표온도로 제어하는 것이 가능하게 된다.This makes it possible to control the heating amount of the hot water in the combustion type hot water supply unit or to control the mixing ratio of the hot water supplied from the storage tank to the hot water supply pipe on the upstream side of the middle portion A while mixing water, It becomes possible to control the temperature of the hot water supplied to the bath to a target temperature with high accuracy.

상기 제 1 발명에서는, 상기 운전제어수단은, 상기 바이패스혼합급탕제어처리를 실행하는 급탕운전의 종료시부터 상기 탕수공급운전의 개시시까지의 시간이 길수록, 상기 탕수공급운전의 개시 직후의 소정기간을 짧게 하도록 상기 소정기간을 설정하도록 구성되어 있는 것이 바람직하다(제 2 발명).In the first aspect of the present invention, the operation control means controls the operation of the bypass mixed hot water supply control process so that the longer the time from the end of the hot water supply operation for executing the bypass mixed hot water supply control operation to the start of the hot water supply operation, (The second invention).

즉, 상기 바이패스혼합급탕제어처리를 실행하는 급탕운전의 종료시부터 상기 탕수공급운전의 개시까지의 시간이 길수록, 상기 탕수공급운전의 개시시에 있어서, 상기 도중부(B)보다도 연소식 열교환기측의 출탕관의 탕수의 온도는, 더욱 저하되어 있다고 생각할 수 있다.That is, the longer the time from the end of the hot water supply operation for executing the bypass mixed hot water supply control process to the start of the hot water supply operation, the lower the temperature at the beginning of the hot water supply operation, It can be considered that the temperature of the hot water in the hot water in the hot water tank is further lowered.

따라서, 상기 탕수공급운전의 개시 직후의 소정기간을 상기한 바와 같이 설정하는 것에 의해, 상기 소정기간, 즉, 바이패스밸브를 개방상태로 제어하는 기간을 필요 최소한의 시간의 기간으로 할 수 있다.Therefore, by setting the predetermined period immediately after the start of the water supply operation as described above, the predetermined period, that is, the period for controlling the bypass valve to be in the open state, can be set to the minimum necessary period of time.

또한, 상기 제 1 발명 또는 제 2 발명에서는, 상기 운전제어수단은, 상기 바이패스혼합급탕제어처리를 실행하는 급탕운전의 종료 후, 상기 소정시간이 경과되기 전에, 상기 탕수공급운전을 개시할 경우에, 상기 탕수공급운전의 개시 직후의 상기 소정기간에 상기 바이패스밸브를 서서히 폐쇄상태로 접근하여 가도록 상기 바이패스밸브를 제어하도록 구성되어 있는 것이 바람직하다(제 3 발명).In the first or second aspect of the present invention, the operation control means may be configured to start the hot water supply operation before the predetermined time elapses after the end of the hot water supply operation for executing the bypass mixed hot water supply control process (The third invention) so as to gradually approach the bypass valve in the predetermined period immediately after the start of the water supply operation.

이 제 3 발명에 따르면, 상기 소정기간 내에, 급탕구로의 급탕을 개시할 경우에, 상기 급탕의 개시타이밍이, 상기 소정기간의 종단에 가까울수록, 상기 급탕의 개시시에 있어서의 바이패스밸브의 개방도가 폐쇄측으로 억제되게 된다.According to the third aspect of the present invention, in the case where the hot water supply to the hot water supply opening is started within the predetermined period, the closer the start timing of the hot water supply is to the end of the predetermined period, The opening degree is restricted to the closed side.

따라서, 상기 급탕의 개시타이밍이, 상기 소정기간의 종단에 가까울수록, 상기 급탕의 개시시에, 출탕바이패스관을 통과하여 도중부(B)로 흘러 오는 탕수의 유량이 억제된다.Therefore, the closer to the end of the predetermined period the start timing of the hot water supply, the flow rate of the hot water flowing into the middle portion B through the hot water bypass pipe at the start of the hot water supply is suppressed.

한편, 상기 도중부(B)보다도 연소식 열교환기측의 출탕관의 탕수의 온도는, 일반적으로, 상기 소정기간의 종단에 가까울수록 저하된다.On the other hand, the temperature of the hot water in the hot water outlet of the combustion type heat exchanger is generally lower than that in the middle portion (B), as it approaches the end of the predetermined period.

따라서, 제 3 발명에 따르면, 상기 급탕의 개시시에, 출탕바이패스관을 통과하여 도중부(B)로 흘러 오는 탕수의 유량이, 상기 도중부(B)보다도 연소식 열교환기측의 출탕관의 탕수의 온도에 대해서 과잉으로 되는 것이 억제된다. 나아가서는, 급탕구에 공급하는 탕수의 온도를 목표온도에 접근하는 것을 신속하게 실행하도록 할 수 있다.
Therefore, according to the third aspect of the present invention, when the hot water supply is started, the flow rate of the hot water flowing into the middle portion B through the hot water bypass pipe is lower than the flow rate of the hot water flowing into the middle portion The excess of the temperature of the hot water is suppressed. Further, the temperature of the hot water supplied to the hot water supply port can be quickly approached to the target temperature.

도 1은 본 발명의 일실시형태의 급탕시스템의 구성을 나타내는 도면.
도 2는 도 1의 급탕시스템의 작동을 나타내는 흐름도.
도 3은 도 1의 급탕시스템의 작동을 나타내는 흐름도.
도 4는 도 3의 STEP 20의 처리 내용을 나타내는 흐름도.
BRIEF DESCRIPTION OF THE DRAWINGS Fig. 1 is a view showing a configuration of a hot water supply system according to an embodiment of the present invention; Fig.
2 is a flow chart illustrating operation of the hot water system of FIG.
3 is a flow chart illustrating the operation of the hot water system of FIG.
4 is a flowchart showing the processing contents of STEP 20 of FIG. 3;

본 발명의 일실시형태를 도 1∼도 4를 참조하여 이하에 설명한다.One embodiment of the present invention will be described below with reference to Figs.

도 1을 참조하여 본 실시형태의 급탕시스템은, 연소식 급탕기(10)와, 탱크유닛(30)과, 히트펌프유닛(60)을 구비한다.1, the hot water supply system of the present embodiment includes a combustion type hot water heater 10, a tank unit 30, and a heat pump unit 60.

히트펌프유닛(60)은, 본 발명에 있어서의 가열수단으로서의 히트펌프(61)를 구비한다. 이 히트펌프(61)는 압축기(62), 응축기(63), 감압기(64) 및 증발기(65)와, 이들을 경유시켜 냉매를 순환시키는 냉매순환로(66)를 구비하고 있다.The heat pump unit 60 is provided with a heat pump 61 as heating means in the present invention. The heat pump 61 includes a compressor 62, a condenser 63, a pressure reducer 64 and an evaporator 65, and a refrigerant circulation path 66 for circulating the refrigerant through them.

이 경우, 응축기(63)는 후술의 저탕 탱크(31) 내의 탕수와 냉매의 열교환을 실행하는 것에 의해 상기 탕수를 가열하는 열교환기로서의 기능을 가지는 것이며, 저탕 탱크(31)와 응축기(63)의 사이에서 탕수를 순환시키는 탱크순환로(67)를 통하여 저탕 탱크(31)에 접속되어 있다. 탱크순환로(67)는 저탕 탱크(31)의 하부 및 상부를 각각 응축기(63)의 탕수의 유입구, 유출구에 접속하고 있다. 그리고 탱크순환로(67)에는 순환펌프(68)가 개장되어 있다.In this case, the condenser 63 has a function as a heat exchanger for heating the hot water by performing heat exchange between the hot water and the coolant in the below-mentioned hot water tank 31, and the hot water in the hot water tank 31 and the condenser 63 And is connected to the storage tank 31 through a tank circulation path 67 circulating the hot water. The tank circulation path 67 connects the lower portion and the upper portion of the storage tank 31 to the inlet and outlet of the hot water of the condenser 63, respectively. A circulation pump 68 is opened in the tank circulation path 67.

따라서, 순환펌프(68)를 작동시키는 것에 의해, 저탕 탱크(31) 내의 탕수가 저탕 탱크(31)의 하부에서 응축기(63)로 공급된다. 그리고 상기 탕수는 응축기(63)를 경유한 후에, 저탕 탱크(31)의 상부에서 상기 저탕 탱크(31) 내로 환류(還流)한다. 이와 같이 저탕 탱크(31) 내의 탕수를 탱크순환로(67)에서 순환시키면서, 히트펌프(61)를 작동시키는 것에 의해, 상기 탕수가 응축기(63)에 있어서의 냉매[압축기(62)에서 압축되어 승온한 냉매]와의 열교환에 의해서 가열된다.Therefore, by operating the circulation pump 68, the hot water in the storage tank 31 is supplied to the condenser 63 from the lower portion of the storage tank 31. The boiled water passes through the condenser 63 and then returns to the inside of the storage tank 31 from the upper portion of the storage tank 31. By operating the heat pump 61 while circulating the hot water in the warming tank 31 through the tank circulation path 67, the hot water is compressed by the refrigerant (the compressor 62 in the condenser 63) Is heated by heat exchange with the refrigerant.

또한, 도 1에서는, 순환펌프(68)는 저탕 탱크(31)의 하부에서 응축기(63)에 이르는 유로에 개장되어 있지만, 응축기(63)에서 저탕 탱크(31)의 상부에 이르는 유로에 개장되어 있어도 좋다.1, the circulation pump 68 is opened in the flow path from the lower portion of the storage tank 31 to the condenser 63, but is opened in the flow path from the condenser 63 to the upper portion of the storage tank 31 There may be.

히트펌프유닛(60)은 히트펌프(61) 및 순환펌프(68)의 작동 제어를 실행하는 기능을 가지는 히트펌프컨트롤러(71)를 더 구비하고 있다. 상기 히트펌프컨트롤러 (71)는 마이크로컴퓨터 등을 포함하는 전자회로유닛에 의해 구성되어 있으며, 후술의 탱크컨트롤러(41)와 상호 통신 가능하게 되어 있다.The heat pump unit 60 further includes a heat pump controller 71 having a function of controlling the operation of the heat pump 61 and the circulation pump 68. [ The heat pump controller 71 is constituted by an electronic circuit unit including a microcomputer or the like and is capable of communicating with a tank controller 41 described later.

또한, 탱크순환로(67)에는 저탕 탱크(31)에 응축기(63)로부터 공급되는 탕수의 온도를 검출하는 온도센서(72)와, 응축기(63)에 저탕 탱크(31)로부터 공급되는 탕수의 온도를 검출하는 온도센서(73)가 장착되어 있다.The tank circulation path 67 is provided with a temperature sensor 72 for detecting the temperature of the hot water supplied from the condenser 63 to the storage tank 31 and a temperature sensor 72 for detecting the temperature of the hot water supplied from the storage tank 31 to the condenser 63 And a temperature sensor 73 for detecting the temperature of the liquid.

히트펌프컨트롤러(71)에는 후술의 탱크컨트롤러(41)로부터 저탕 탱크(31) 내의 탕수를 가열해야 할 취지의 저탕비등지령을 나타내는 데이터 등이 입력됨과 아울러, 상기 온도센서(72, 73)의 검출데이터가 입력된다.The heat pump controller 71 is supplied with data indicative of a boiling water boiling instruction for heating boiled water in the warming tank 31 from a tank controller 41 to be described later and detects the temperature of the temperature sensors 72 and 73 Data is input.

그리고 히트펌프컨트롤러(71)는 탱크컨트롤러(41)로부터 저탕비등지령을 수신하면, 저탕 탱크(31) 내의 탕수를 가열시키도록 히트펌프(61) 및 순환펌프(68)의 작동을 제어한다.The heat pump controller 71 controls the operation of the heat pump 61 and the circulation pump 68 so as to heat the hot water in the warming tank 31 upon receiving the hot water boiling instruction from the tank controller 41. [

이 경우, 히트펌프컨트롤러(71)는 상기 온도센서(72, 73)의 검출온도를 이용하여 소정의 제어프로그램을 실행하는 것에 의해, 저탕 탱크(31) 내의 탕수의 온도를, 급탕시스템의 기본동작모드에 따라서 규정되는 소정의 저탕비등온도까지 승온시키도록, 히트펌프(61)의 출력과 순환펌프(68)의 회전수[나아가서는, 탱크순환로 (67)를 흐르는 탕수의 유량]를 제어한다.In this case, the heat pump controller 71 executes a predetermined control program using the detected temperatures of the temperature sensors 72 and 73 to change the temperature of the hot water in the hot water tank 31 to the basic operation of the hot water system The output of the heat pump 61 and the rotation speed of the circulation pump 68 (that is, the flow rate of the flowing water flowing through the tank circulation path 67) are controlled so that the temperature of the heat pump 61 is raised to a prescribed low temperature boiling temperature.

다음에, 탱크유닛(30)은 히트펌프(61)에 의해 가열된 탕수를 저장하는 저탕 탱크(31)와, 출탕관(32), 급수관(33) 및 출탕바이패스관(34)을 구비한다.Next, the tank unit 30 is provided with a storage tank 31 for storing the hot water heated by the heat pump 61, a hot water supply pipe 32, a water supply pipe 33 and a hot water bypass pipe 34 .

출탕관(32)은 부엌, 세면소, 욕실 등에 배치되는 급탕구에 급탕하기 위한 유로이다. 이 출탕관(32)은 저탕 탱크(31)의 상부로부터 도출되어 연소식 급탕기[10, 상세한 것은 후술의 열교환기(13)]를 경유한 후, 종단의 급탕구에 이르도록 배관되어 있다. 출탕관(32) 종단의 급탕구에는, 예를 들면 크란(수도꼭지, 35)이 접속된다.The hot water extracting pipe 32 is a channel for hot water supply to a hot water supply port arranged in a kitchen, a washroom, a bathroom, and the like. The hot water supply pipe 32 is led from the upper part of the storage tank 31 and passes through the combustion type hot water supply unit 10 (more specifically, the heat exchanger 13 to be described later), and is then piped so as to reach the end hot water supply port. For example, a cran (faucet) 35 is connected to the hot water supply port at the end of the hot water supply pipe 32.

또한, 출탕관(32) 종단의 급탕구는 복수로 분기하고 있어도 좋고, 또한, 크란(35) 대신에, 샤워 등이 접속되어 있어도 좋다.The hot water supply port at the end of the hot water discharge pipe 32 may be branched into a plurality of pipes or a shower or the like may be connected instead of the cranes 35.

급수관(33)은 수도관 등으로부터 공급되는 물을 저탕 탱크(31)와 출탕관(32)에 급수하는 유로이다. 이 급수관(33)은 그 하류측의 도중부(33x)로부터 제 1 분기 급수관(33a)과 제 2 분기 급수관(33b)으로 분기되어 있다. 그리고 제 1 분기 급수관(33a)이 저탕 탱크(31)의 하부에 접속되고, 제 2 분기 급수관(33b)이 출탕관(32) 상류측의 제 1 도중부(32x)에 접속(합류)되어 있다.The water supply pipe 33 is an oil passage for supplying water supplied from a water pipe or the like to the holding tank 31 and the outlet pipe 32. This water supply pipe 33 is branched from the midway portion 33x on the downstream side thereof to the first branch water supply pipe 33a and the second branch water supply pipe 33b. The first branch water pipe 33a is connected to the lower portion of the storage tank 31 and the second branch water pipe 33b is connected to the first midway portion 32x on the upstream side of the hot water pipe 32 .

따라서, 급수관(33)은 제 1 분기 급수관(33a)을 통하여 저탕 탱크(31)에 그 하부로부터 급수함과 아울러, 제 2 분기 급수관(33b)을 통하여 출탕관(32)의 제 1 도중부(32x)에 급수하도록 구성되어 있다. 또한, 급수관(33)의 도중부(33x)보다도 상류측의 개소에는 감압밸브(36)가 개장되어 있다.Therefore, the water supply pipe 33 is supplied from the lower part thereof to the storage tank 31 through the first branch water supply pipe 33a, and the water supply pipe 33 is connected to the first intermediate pipe portion 32a of the outlet pipe 32 via the second branch water supply pipe 33b 32x. A pressure reducing valve 36 is opened at a position on the upstream side of the midway portion 33x of the water supply pipe 33.

출탕관(32)의 제 1 도중부(32x)는, 환언하면, 급수관(33)으로부터 제 1 분기 급수관(33a)을 통하여 저탕 탱크(31)에 급수하는 것에 수반하여 상기 저탕 탱크 (31)에서 출탕관(32)으로 공급되는 탕수와, 급수관(33)에서 제 2 분기 급수관(33b)을 통하여 출탕관(32)으로 공급되는 물의 혼합부이다.The first midway portion 32x of the outlet pipe 32 is connected to the bottom of the tank 31 via the first branch supply pipe 33a from the water supply pipe 33 to the storage tank 31, Water mixture supplied from the water supply pipe 33 to the outflow pipe 32 through the second branch water supply pipe 33b.

그리고 저탕 탱크(31)에서 출탕관(32)으로 공급되는 탕수의 유량[출탕관(32)의 제 1 도중부(32x)에 저탕 탱크(31)측으로부터 유입되는 탕수의 유량]인 탱크출탕유량을 조정하기 위한 유량조정밸브(37)가, 저탕 탱크(31)와 제 1 도중부(32x)의 사이에서 출탕관(32)에 개장되어 있다. 또한, 급수관(33)으로부터 제 2 분기 급수관(33b)을 통하여 출탕관(32)의 제 1 도중부(32x)에 공급되는 물의 유량인 혼합급수유량을 조정하기 위한 유량조정밸브(38)가 제 2 분기 급수관(33b)에 개장되어 있다.The flow rate of the hot water supplied from the filling tank 31 to the hot water tank 32 (the flow rate of hot water flowing from the side of the hot water tank 31 to the first midway portion 32x of the hot water pipe 32) A flow regulating valve 37 for regulating the flow rate of the refrigerant is opened in the outlet pipe 32 between the storage tank 31 and the first midway portion 32x. A flow rate regulating valve 38 for regulating the mixed supply flow rate, which is the flow rate of the water supplied from the water supply pipe 33 to the first intermediate portion 32x of the outlet pipe 32 through the second branch water supply pipe 33b, And is opened in the second branch water pipe 33b.

이들의 유량조정밸브(37, 38)에 의해, 각각 탱크출탕유량, 혼합급수유량을 조정함으로써, 저탕 탱크(31)에서 출탕관(32)으로 공급되는 탕수와 급수관(33)에서 제 2 분기 급수관(33b)을 경유하여 출탕관(32)으로 공급되는 물의 혼합비(상세한 것은, 탱크출탕유량과 혼합급수유량의 비}를 변경하는 것이 가능하게 되어 있다. 이후 이 혼합비를 탱크출탕혼합비라고 한다.The flow rate of water from the tank 31 to the hot water supply pipe 32 and the water supply pipe 33 from the second branch water supply pipe 33 are adjusted by adjusting the flow rate of the tank tap water and the mixed water supply flow rate by the flow rate adjusting valves 37, It is possible to change the mixing ratio of the water (more specifically, the ratio of the tank tap water flow rate and the mixed water supply flow rate) supplied to the hot water tank 32 via the hot water tank 33b.

또한, 유량조정밸브(37, 38)를 상기한 바와 같이 구비하는 대신에, 예를 들면, 출탕관(32)의 제 1 도중부(32x)에 삼방밸브를 개장하고, 이 삼방밸브에 의해 상기 탱크출탕혼합비를 변경하도록 해도 좋다.Instead of providing the flow control valves 37 and 38 as described above, for example, a three-way valve may be opened in the first intermediate portion 32x of the outlet pipe 32, The tank brine mixing ratio may be changed.

출탕바이패스관(34)은, 출탕관(32)의 제 1 도중부(32x)에서 하류측으로 흐르는 탕수(이후, 탱크출탕혼합탕수라고 한다)를 연소식 급탕기(10)의 상류측에서 하류측으로 바이패스시켜서 흘리기[연소식 급탕기(10)를 경유시키지 않고 흘리기] 위한 유로이다.The tapping bypass pipe 34 is a valve that allows the hot water flowing from the first intermediate portion 32x of the hot water pipe 32 to the downstream side to flow down from the upstream side to the downstream side of the combustion type hot water heater 10 And is flowed by bypassing (shedding without passing through the combustion type hot water heater 10).

이 출탕바이패스관(34)은 연소식 급탕기(10)의 상류측에 있어서의 출탕관 (32)의 제 2 도중부(32y)와 연소식 급탕기(10)의 하류측에 있어서의 출탕관(32)의 제 3 도중부(32z)를 연통시키도록 배관되어 있다. 또한, 상기 제 2 도중부(32y)는 제 1 도중부(32x)보다도 하류측의 도중부이다. 또한, 제 2 도중부(32y), 제 3 도중부(32z)는 각각 본 발명에 있어서의 도중부(A), 도중부(B)에 상당한다.The hot water bypass pipe 34 is connected to the second intermediate portion 32y of the hot water pipe 32 on the upstream side of the combustion type hot water heater 10 and the second midway portion 32y of the hot water pipe 10 on the downstream side of the combustion type hot water heater 10 32 to communicate with each other. The second midway portion 32y is a midway portion on the downstream side of the first midway portion 32x. The second intermediate portion 32y and the third intermediate portion 32z correspond to the intermediate portion A and the intermediate portion B of the present invention, respectively.

그리고 출탕바이패스관(34)에는 상기 출탕바이패스관(34)을 개폐 가능한 유량조정밸브에 의해 구성된 바이패스밸브(39)가 개장되어 있다.The bypass valve (39), which is constituted by a flow rate control valve capable of opening and closing the tapping bypass pipe (34), is opened in the tapping bypass pipe (34).

따라서, 바이패스밸브(39)를 폐쇄한 경우를 제외하고, 출탕관(32)의 제 1 도중부(32x)에서 하류측으로 흐르는 탱크출탕혼합탕수는, 그 일부가 연소식 급탕기 (10)의 내부의 유로를 통과하여 하류측으로 흐르며, 잔부가 출탕바이패스관(34)을 통과하여 하류측으로 흐른다. 그리고 출탕관(32) 종단의 급탕구로의 급탕을 실행할 경우에는, 연소식 급탕기(10)에서 출탕관(32)의 하류측으로 흘러 오는 탕수와, 출탕바이패스관(34)을 흐르는 탕수가 제 3 도중부[32z, 출탕바이패스관(34)의 출구]에서 합류하여 혼합되고, 그 혼합된 탕수(이후, 바이패스출구혼합탕수라고 한다)가 출탕관(32) 종단의 급탕구에 공급되어 출탕된다.Therefore, except for the case where the bypass valve 39 is closed, the mixed water of the tank tap water flowing from the first intermediate portion 32x of the tap water pipe 32 to the downstream side is partially supplied to the inside of the combustion type hot water heater 10 And the rest flows through the drinking water bypass pipe 34 to the downstream side. When hot water is supplied to the hot water supply port at the end of the hot water pipe 32, the hot water flowing from the combustion type hot water heater 10 to the downstream side of the hot water pipe 32 and the hot water flowing through the hot water pipe 34, (Hereinafter, referred to as "bypass outlet mixed water") is supplied to the hot water supply port at the end of the hot water supply pipe 32, do.

이 경우, 바이패스밸브(39)의 개방도를 조정하는[나아가서는, 출탕바이패스관(34)의 유량을 조정하는] 것에 의해, 제 3 도중부(32z)에 연소식 급탕기(10)로부터 유입되는 탕수의 유량과, 출탕바이패스관(34)으로부터 유입되는 탕수의 유량의 비율인 혼합비(이후, 바이패스출구혼합비라고 한다)를 조정할 수 있다.In this case, by adjusting the opening degree of the bypass valve 39 (moreover, by adjusting the flow rate of the tapping bypass pipe 34), the third midway portion 32z is supplied with the air from the combustion type hot water heater 10 (Hereinafter, referred to as the bypass outlet mixing ratio), which is the ratio of the flow rate of the flowing hot water to the flow rate of the hot water flowing from the hot tapping bypass pipe 34, can be adjusted.

또한, 바이패스밸브(39)를 폐쇄한 상태에서는, 출탕관(32)의 제 1 도중부 (32x)에서 하류측으로 흐르는 상류측 혼합탕수의 전체가 연소식 급탕기(10)에 공급되게 된다.When the bypass valve 39 is closed, the entire upstream mixed water flowing from the first intermediate portion 32x of the outlet pipe 32 to the downstream side is supplied to the combustion type hot water heater 10.

탱크유닛(30)은 상기 유량조정밸브(37, 38) 및 바이패스밸브(39)의 작동 제어 등을 실행하는 기능을 가지는 탱크컨트롤러(41)를 더 구비하고 있다. 상기 탱크컨트롤러(41)는 마이크로컴퓨터 등을 포함하는 전자회로유닛에 의해 구성되어 있으며, 히트펌프컨트롤러(71) 및 후술의 급탕컨트롤러(21)와 상호 통신 가능하게 되어 있다.The tank unit 30 further includes a tank controller 41 having a function of controlling the operation of the flow control valves 37 and 38 and the bypass valve 39. The tank controller 41 is constituted by an electronic circuit unit including a microcomputer or the like and is capable of communicating with the heat pump controller 71 and a hot water controller 21 described later.

또한, 탱크컨트롤러(41)에는 사용자가 급탕시스템의 운전조작 등을 실행하기 위한 리모컨(43)이 접속되어 있다.A remote controller 43 is connected to the tank controller 41 for executing a driving operation of the hot water supply system by the user.

리모컨(43)은 도시하지 않는 조작스위치의 조작, 혹은 음성입력 등에 따라서 급탕시스템의 급탕운전의 온 오프, 욕조의 탕수공급운전의 온 오프, 목표급탕온도, 목표탕수공급온도 등의 운전조작정보를 탱크컨트롤러(41)에 지시하는 단말기기이다.The remote controller 43 stores driving operation information such as on / off of the hot water supply operation of the hot water supply system, on / off of the hot water supply operation of the bathtub, the target hot water temperature and the target hot water supply temperature And instructs the tank controller (41).

또한, 탱크유닛(30)의 저탕 탱크(31), 출탕관(32), 급수관(33)에는 이하에 설명하는 여러 가지의 센서가 조립되어 있으며, 이들 센서의 검출데이터도 탱크컨트롤러(41)에 입력된다.Various sensors described below are assembled in the tank 31, the hot water supply pipe 32 and the water supply pipe 33 of the tank unit 30. The detection data of these sensors are also supplied to the tank controller 41 .

즉, 저탕 탱크(31)에는 상기 저탕 탱크(31)의 탕수소진상태[저탕 탱크(31) 내에 소정온도 이상의 탕수가 없던지, 혹은 거의 없다고 볼 수 있는 상태]를 검지하기 위한 탱크온도센서(48)가 부설되어 있다.That is, the tank tank 31 is provided with a tank temperature sensor 48 for detecting the boiled water exhaustion state of the storage tank 31 (a state in which there is no or no water in the storage tank 31 at a predetermined temperature) ).

이 탱크온도센서(48)는 저탕 탱크(31)의 소정의 높이 위치에서 상기 저탕 탱크(31)의 상부의 외주면 또는 내부에 장착되어 있으며, 그 높이 위치에서의 저탕 탱크(31) 내의 탕수의 온도를 검출한다.The tank temperature sensor 48 is mounted on the outer circumferential surface or inside of the upper portion of the storage tank 31 at a predetermined height position of the storage tank 31. The temperature of the hot water in the storage tank 31 at the height position .

여기서, 저탕 탱크(31) 내의 탕수가 가열된 상태에서, 급수관(33)의 제 1 분기 급수관(33a)에서 저탕 탱크(31)로의 급수가 실행되면, 상기 급수에 수반하여 저탕 탱크(31) 내의 고온의 탕수가 저탕 탱크(31)의 상부에서 출탕관(32)으로 공급된다. 이것에 수반하여, 기본적으로는, 저탕 탱크(31) 내의 하부에 저온인 물의 층이 생성됨과 아울러 상부에 고온인 탕수의 층이 생성된다. 그리고 저탕 탱크(31)로의 급수의 진행에 수반하여 저탕 탱크(31) 하부의 저온층이 증가함과 아울러, 상부의 고온층이 감소하여 간다.Here, when water is supplied from the first branch water supply pipe 33a of the water supply pipe 33 to the storage tank 31 in the state where the hot water in the storage tank 31 is heated, the inside of the storage tank 31 Hot water is supplied from the upper part of the holding tank 31 to the outlet pipe 32. Along with this, basically, a low-temperature water layer is generated in the lower portion of the storage tank 31, and a hot water layer is formed in the upper portion. As the water supply to the filling tank 31 progresses, the low temperature layer in the lower portion of the storage tank 31 increases and the upper high temperature layer decreases.

이로 인해, 탱크온도센서(48)의 검출온도가 소정온도보다도 높은 상태는, 저탕 탱크(31)의 잔여 탕수량이 탱크온도센서(48)의 높이 위치에 대응하는 소정량[탱크온도센서(48)보다도 상측의 저탕 탱크(31)의 용량]보다도 많은 것을 나타내고, 상기 검출온도가 소정온도보다도 낮은 상태는, 상기 잔여 탕수량이 상기 소정량보다도 적은 것을 나타낸다.The state in which the detection temperature of the tank temperature sensor 48 is higher than the predetermined temperature is a predetermined amount of water remaining in the storage tank 31 corresponding to the height position of the tank temperature sensor 48 (The capacity of the storage tank 31 at the upper side than the storage tank 31 at the upper side), and the state in which the detection temperature is lower than the predetermined temperature indicates that the residual water amount is smaller than the predetermined amount.

그래서, 본 실시형태에서는 탱크컨트롤러(41)는, 탱크온도센서(48)의 검출온도를 소정온도와 비교하고, 검출온도가 소정온도보다도 낮은 경우에, 저탕 탱크 (31)의 탕수소진상태가 발생한 것을 검지한다.Therefore, in the present embodiment, the tank controller 41 compares the detected temperature of the tank temperature sensor 48 with the predetermined temperature, and when the detected temperature is lower than the predetermined temperature, .

또한, 급수관(33) 중의 도중부(33x)보다도 상류측의 개소에는 상기 급수관 (33)을 흐르는 물의 유량[저탕 탱크(31) 및 출탕관(32)으로의 합계의 급수유량]을 검출하는 유량센서(49)가 장착되고, 제 2 분기 급수관(33b)에는 급수온도를 검출하는 온도센서(50)가 장착되어 있다.The flow rate of the water flowing through the water supply pipe 33 (the total supply flow rate to the storage tank 31 and the hot water supply pipe 32) is detected at a location on the upstream side of the middle portion 33x of the water supply pipe 33 A sensor 49 is mounted, and a second temperature sensor 50 for detecting the supply temperature is mounted on the second branch water supply pipe 33b.

또한, 출탕관(32)의 제 1 도중부(32x)보다도 상류측의 개소에는 상기 탱크출탕유량을 검출하는 유량센서(51)와, 저탕 탱크(31)측에서 제 1 도중부(32x)로 유입되는 탕수의 온도를 검출하는 온도센서(52)가 장착되어 있다.A flow sensor 51 for detecting the flow rate of the tank tap water is provided at a position on the upstream side of the first intermediate portion 32x of the outlet pipe 32 and a flow rate sensor And a temperature sensor 52 for detecting the temperature of the inflowing water.

또한, 출탕관(32)의 제 1 도중부(32x)와 제 2 도중부(32y) 사이의 개소에는 제 1 도중부(32x)에서 하류측으로 흐르는 탱크출탕혼합탕수의 온도를 검출하는 온도센서(53)가 장착되고, 제 3 도중부(32z) 하류측의 개소에는 급탕구로부터 출탕시키는 탕수의 온도(급탕온도)를 검출하는 온도센서(54)가 장착되어 있다.A temperature sensor (not shown) is provided at a location between the first midway portion 32x and the second midway portion 32y of the outlet pipe 32 to detect the temperature of the mixed hot water flowing from the first midway portion 32x to the downstream side And a temperature sensor 54 for detecting the temperature (hot water supply temperature) of the hot water for tapping the hot water from the hot water supply port is mounted at a location on the downstream side of the third intermediate portion 32z.

또한, 급수온도를 검출하기 위한 온도센서(50)는 도중부(33x)보다도 상류측의 급수관(33), 혹은, 제 1 분기 급수관(33a)에 장착되어 있어도 좋다. 또한, 유량센서(49, 51)의 어느 하나 대신에, 제 2 분기 급수관(33b)을 흐르는 물의 유량을 검출하는 유량센서가 상기 제 2 분기 급수관(33b)에 장착되어 있어도 좋다.The temperature sensor 50 for detecting the water supply temperature may be mounted on the water supply pipe 33 on the upstream side of the midway portion 33x or on the first branch water supply pipe 33a. Instead of any one of the flow sensors 49 and 51, a flow rate sensor for detecting the flow rate of the water flowing through the second branch supply pipe 33b may be mounted on the second branch supply pipe 33b.

그리고 탱크컨트롤러(41)는 모드설정스위치(42)로 설정된 기본동작모드, 리모컨(43)으로부터 부여되는 운전조작정보, 상기 각 센서(44∼54)의 검출데이터를 이용하여 소정의 제어프로그램을 실행한다.The tank controller 41 executes a predetermined control program using the basic operation mode set by the mode setting switch 42, driving operation information given from the remote controller 43, and detection data of the sensors 44 to 54 do.

이 경우, 탱크컨트롤러(41)는 제어프로그램을 실행하는 것에 의해 실현되는 기능으로서, 히트펌프컨트롤러(71)와 협동하여 히트펌프유닛(60)에 관련되는 제어를 실행하는 기능을 가진다. 이 제어에서는 탱크컨트롤러(41)는 탱크온도센서(48)의 검출온도를 감시하고, 상기 검출온도가 미리 설정된 저탕비등개시온도 이하로 되면, 히트펌프컨트롤러(71)에 상기 저탕비등지령을 출력한다. 또한, 저탕비등개시온도는 상기 비등온도보다도 낮은 온도이다.In this case, the tank controller 41 is a function realized by executing the control program, and has a function of executing control related to the heat pump unit 60 in cooperation with the heat pump controller 71. [ In this control, the tank controller 41 monitors the detected temperature of the tank temperature sensor 48, and when the detected temperature becomes equal to or lower than the predetermined low temperature boiling start temperature, the low temperature boiling instruction is outputted to the heat pump controller 71 . The low temperature boiling start temperature is lower than the boiling temperature.

또한, 탱크컨트롤러(41)는 탱크온도센서(48)의 검출온도에 의거하여 상기한 바와 같이 저탕 탱크(31)의 탕수소진상태를 검지하는 기능을 가진다. 또한, 이 경우, 저탕 탱크(31)가 탕수소진상태를 검지하기 위해, 탱크온도센서(48)의 검출온도와 비교하는 소정온도로서, 급탕운전시[출탕관(32)의 급탕구로의 급탕을 실행하는 운전시]에는 리모컨(43)에서 설정된 목표급탕온도가 사용되고, 욕조의 탕수공급운전시에는 리모컨(43)에서 설정된 목표탕수공급온도가 사용된다.The tank controller 41 has a function of detecting the hot water exhaustion state of the storage tank 31 as described above on the basis of the detected temperature of the tank temperature sensor 48. [ In this case, as the predetermined temperature to be compared with the detected temperature of the tank temperature sensor 48 in order to detect the boiled water exhaustion state of the storage tank 31, the hot water supply to the hot water supply port of the hot water extracting pipe 32 The target hot water supply temperature set by the remote controller 43 is used and the target hot water supply temperature set by the remote controller 43 is used during the hot water supply operation of the bathtub.

또한, 탱크컨트롤러(41)는 급탕컨트롤러(21)와 협동하는 것에 의해, 본 발명에 있어서의 운전제어수단으로서의 기능을 가지고 있다. 이 운전제어수단으로서의 기능을 개략적으로 설명하면, 탱크컨트롤러(41)는 저탕 탱크(31)의 탕수소진상태가 발생하고 있지 않은 경우에서의 급탕운전시 또는 탕수공급운전시에는, 연소식 급탕기(10)의 가열운전[상세한 것은, 연소식 가열원(11)에 의한 탕수의 가열을 실행하는 운전]을 금지한 상태에서, 상기 탱크출탕혼합비를 유량조정밸브(37, 38)를 통하여 조정하는 것에 의해, 출탕관(32)의 급탕구로의 급탕온도 또는 욕조의 탕수공급온도를 각각, 목표급탕온도, 목표탕수공급온도로 제어한다.In addition, the tank controller 41 has a function as the operation control means in the present invention by cooperating with the hot water supply controller 21. The tank controller 41 controls the operation of the combustion type hot water tank 10 (10) during the hot water supply operation or the hot water supply operation in the case where the hot water exhaustion state of the storage tank (31) ) Is controlled through the flow rate adjusting valves 37 and 38 while the heating operation of the tank brine (specifically, the operation of heating the boiled water by the combustion type heating source 11) is prohibited , The hot water supply temperature to the hot water supply port of the hot water extracting pipe (32), or the hot water supply temperature of the bathtub to the target hot water temperature and the target hot water supply temperature, respectively.

또한, 저탕 탱크(31)의 탕수소진상태에서의 급탕운전시에는, 탱크컨트롤러 (41)는 연소식 급탕기(10)의 가열운전을 실행시키면서, 상기 바이패스출구혼합비를 바이패스밸브(39)를 통하여 조정하는 것에 의해, 급탕구에 급탕하는 탕수의 급탕온도를 목표급탕온도로 제어한다.The tank controller 41 performs the heating operation of the combustion type hot water heater 10 while supplying the bypass outlet mixture ratio to the bypass valve 39 at the time of hot water supply operation in the hot water storage tank 31 So that the hot water supply temperature of the hot water for hot water supply to the hot water supply port is controlled to the target hot water temperature.

또한, 저탕 탱크(31)의 탕수소진상태에서의 탕수공급운전시에는, 탱크컨트롤러(41)는 연소식 급탕기(10)의 가열운전을 실행시킨다. 이 경우, 탱크컨트롤러(41)는 바이패스밸브(39)를 기본적으로는, 폐쇄상태로 제어하지만, 탕수공급운전의 개시 초기에 일시적으로 개방상태로 제어하는 경우도 있다. 또한, 탕수공급운전에서는, 욕조에 공급하는 탕수의 온도는 연소식 급탕기(10)의 가열운전에 의해서, 목표탕수공급온도로 제어된다.In addition, the tank controller 41 executes the heating operation of the combustion type hot water heater 10 at the time of the running water supply operation in the storage tank 31 with the hot water exhausted. In this case, the tank controller 41 basically controls the bypass valve 39 to be in a closed state, but may temporarily control the valve 39 to be in an open state at the beginning of the water supply operation. In addition, in the water supply operation, the temperature of the hot water supplied to the bath is controlled to the target hot water supply temperature by the heating operation of the combustion type hot water heater (10).

다음에, 연소식 급탕기(10)는 출탕관(32)에 의해 상류측으로부터 공급되는 탕수를 연소식 가열원(11)에 의해 적절히 가열하는 것이다. 이 연소식 가열원(11)은 가스 버너 등의 버너(12)와, 버너(12)의 연소열이 부여되는 열교환기(13)를 구비하고 있다. 그리고 연소식 급탕기(10)에 도입된 출탕관(32)은 상류측의 제 2 도중부(32y)로부터 공급되는 탕수를 열교환기(13)를 경유시켜서 하류측의 제 3 도중부(32z)에 흘리도록 배관되어 있다.Next, in the combustion type hot water heater 10, the hot water supplied from the upstream side by the hot water supply pipe 32 is appropriately heated by the combustion type heat source 11. The combustion heat source 11 includes a burner 12 such as a gas burner and a heat exchanger 13 to which combustion heat of the burner 12 is given. The hot water supplied from the second intermediate portion 32y on the upstream side is introduced into the third intermediate portion 32z on the downstream side via the heat exchanger 13 in the outflow pipe 32 introduced into the combustion type hot water heater 10, It is piped to shed.

연소식 급탕기(10)는 열교환기(13)의 상류측에서 하류측으로 상기 열교환기 (13)를 바이패스시켜서 탕수를 흘리기 위한 바이패스관(14)과, 열교환기(13)의 하류측으로부터 도시하지 않는 욕조에 탕수공급용의 탕수를 공급하는 탕수공급관(15)을 더 구비한다.The combustion type hot water heater 10 includes a bypass pipe 14 for bypassing the heat exchanger 13 from the upstream side to the downstream side of the heat exchanger 13 to flow the hot water, Water supply pipe 15 for supplying the unused water to the unused bathtub.

바이패스관(14)은 연소식 급탕기(10) 내부의 출탕관(32)에 있어서의 열교환기(13) 상류측의 도중부와 하류측의 도중부를 접속하고 있다. 그리고 연소식 급탕기(10) 내부의 출탕관(32)에는, 열교환기(13)의 상류측에 있어서의 바이패스관(14)과의 접속 개소에 상기 접속 개소에서 열교환기(13)로 흐르는 탕수의 유량과, 바이패스관(14)으로 흐른 탕수의 유량의 비율인 바이패스비를 조정하기 위한 바이패스서보밸브(16)가 개장되어 있다.The bypass pipe 14 connects an intermediate portion on the upstream side of the heat exchanger 13 and an intermediate portion on the downstream side of the outlet pipe 32 inside the combustion type hot water heater 10. The hot water supply pipe 32 in the combustion type hot water heater 10 is connected to the connection point with the bypass pipe 14 on the upstream side of the heat exchanger 13 with hot water flowing from the connection point to the heat exchanger 13 And a bypass servo valve 16 for adjusting the bypass ratio, which is a ratio of the flow rate of the hot water flowing into the bypass pipe 14, is opened.

또한, 연소식 급탕기(10)의 내부의 출탕관(32)에는 바이패스서보밸브(16) 상류측의 개소에, 연소식 급탕기(10)에 상류측으로부터 유입되는 탕수의 유량을 조정하기 위한 수량서보밸브(17)가 개장되어 있다.The amount of water for regulating the flow rate of the hot water flowing from the upstream side to the combustion type hot water heater 10 is set at a position on the upstream side of the bypass servo valve 16 in the hot water tank 32 inside the combustion type hot water heater 10, The servo valve 17 is opened.

또한, 상기 출탕관(32)에는, 열교환기(13) 하류측의 개소에, 수격(水擊)완충밸브(18)가 개장되어 있다. 이 수격완충밸브(18)는 연소식 급탕기(10)의 열교환기 (13)의 하류측의 출탕관(32)에 있어서, 하류측으로부터의 탕수의 역류를 억제하도록 기능한다. 상기 수격완충밸브(18)는 일반적으로, 상기 역류를 완전하게 저지하는 것은 아니고, 하류측에서 상류측으로의 소량의 탕수의 유통은 가능하다.A water hammer buffer valve 18 is opened in the outflow pipe 32 at a location on the downstream side of the heat exchanger 13. This water hammer damping valve 18 functions to suppress reverse flow of the hot water from the downstream side in the discharge pipe 32 on the downstream side of the heat exchanger 13 of the combustion type hot water heater 10. The water hammer buffering valve 18 generally does not completely prevent the backflow, and it is possible to distribute a small amount of the hot water from the downstream side to the upstream side.

탕수공급관(15)은 열교환기(13)의 하류측에 있어서의 출탕관(32)으로부터 분기되어 도시하지 않는 욕조에 접속되어 있다. 그리고 이 탕수공급관(15)에는 상기 탕수공급관(15)을 개폐하는 탕수공급밸브(19)가 개장되어 있다.The hot water supply pipe 15 branches from the hot water supply pipe 32 on the downstream side of the heat exchanger 13 and is connected to a bathtub (not shown). A water supply valve (19) for opening and closing the water supply pipe (15) is opened in the water supply pipe (15).

연소식 급탕기(10)는 버너(12)의 연소운전, 혹은, 바이패스서보밸브(16), 수량서보밸브(17) 및 탕수공급밸브(19)의 작동제어 등을 실행하는 기능을 가지는 급탕컨트롤러(21)를 더 구비하고 있다. 상기 급탕컨트롤러(21)는 마이크로컴퓨터 등을 포함하는 전자회로유닛에 의해 구성되어 있다.The combustion type hot water heater 10 has a function of performing a burning operation of the burner 12 or an operation control of the bypass servo valve 16, the quantity servo valve 17 and the water supply valve 19, (21). The hot water supply controller 21 is constituted by an electronic circuit unit including a microcomputer or the like.

또한, 연소식 급탕기(10) 내부의 출탕관(32)에는, 상류측에서 상기 연소식 급탕기(10)로 공급되는 탕수의 전체 유량을 바이패스서보밸브(16)의 상류측에서 검출하는 유량센서(22)와, 열교환기(13)의 하류측에 있어서의 바이패스관(14)의 접속 개소에서 하류측으로 공급되는 탕수의 온도(급탕기 출탕온도)를 상기 접속 개소의 하류측에서 검출하는 온도센서(23)가 장착되어 있다. 또한, 탕수공급관(15)에는, 상기 탕수공급관(15)에서 욕조로 공급되는 탕수의 유량을 검출하는 유량센서(24)가 장착되어 있다.A flow rate sensor (not shown) for detecting the total flow rate of the hot water supplied from the upstream side to the combustion type hot water heater 10 on the upstream side of the bypass servo valve 16 is provided in the hot water pipe 32 inside the combustion type hot water heater 10, (Hot water tank hot water temperature) supplied to the downstream side at the connection point of the bypass pipe 14 on the downstream side of the heat exchanger 13 from the downstream side of the connection point, (Not shown). The water supply pipe 15 is provided with a flow rate sensor 24 for detecting the flow rate of the hot water supplied from the hot water supply pipe 15 to the bathtub.

급탕컨트롤러(21)에는, 탱크컨트롤러(41)로부터, 급탕운전 또는 탕수공급운전을 실행해야 할 취지의 지령, 목표급탕온도 또는 목표탕수공급온도를 나타내는 데이터, 급탕운전시에 연소식 급탕기(10)의 가열운전을 허가하는지 아닌지를 나타내는 지령 등이 입력됨과 아울러, 상기 유량센서(22, 24) 및 온도센서(23)의 검출데이터가 입력된다.The hot water supply controller 21 is supplied with data from the tank controller 41 indicating that the hot water supply operation or the hot water supply operation should be executed, the target hot water temperature or the target hot water supply temperature, the combustion type hot water heater 10, And the detection data of the flow rate sensors 22 and 24 and the temperature sensor 23 are input to the input /

그리고 급탕컨트롤러(21)는 급탕운전을 실행하는 것이 지령되고, 또한, 연소식 급탕기(10)의 가열운전을 실행하는 것이 허가되어 있는 상태에서는, 유량센서 (22)에 의해 소정의 하한 유량 이상의 통수가 검지되는 경우에, 온도센서(23)의 검출온도가, 목표온도가 되도록, 버너(12)의 연소량과 바이패스서보밸브(16)에 의한 바이패스비를 제어하는 처리인 가열운전제어의 처리를 실행한다. 또한, 이 경우의 상기 목표온도는 목표급탕온도보다도 높은 온도로 설정된다.When the water heater controller 21 is instructed to execute the hot water supply operation and is allowed to perform the heating operation of the combustion type hot water heater 10, The process of the heating operation control which is the process of controlling the burning amount of the burner 12 and the bypass ratio by the bypass servo valve 16 so that the detected temperature of the temperature sensor 23 becomes the target temperature . In this case, the target temperature is set to a temperature higher than the target hot water temperature.

또한, 급탕컨트롤러(21)는 탕수공급운전을 실행하는 것이 지령되어 있는 상태에서는, 탕수공급밸브(19)를 개방함과 아울러, 온도센서(23)의 검출온도가 목표온도(여기에서는 목표탕수공급온도)가 되도록, 가열운전제어의 처리를 실행한다. 또한, 탕수공급운전시에는, 유량센서(24)의 검출유량의 적산값이 리모컨(43) 등에서 설정되는 목표탕수공급량에 도달하면, 탕수공급밸브(19)가 폐쇄됨과 아울러, 연소식 급탕기(10)의 가열운전이 종료된다.When the water supply controller 21 is instructed to execute the water supply operation, the water supply valve 19 is opened and the detection temperature of the temperature sensor 23 is lowered to the target temperature Temperature), as shown in Fig. When the integrated value of the detected flow rate of the flow sensor 24 reaches the target water supply amount set by the remote controller 43 or the like, the water supply valve 19 is closed and the combustion water heater 10 ) Is terminated.

본 실시형태에서는 상기한 탱크컨트롤러(41)와 급탕컨트롤러(21)에 의해 본 발명에 있어서의 운전제어수단이 구성된다.In this embodiment, the tank controller 41 and the hot water supply controller 21 constitute the operation control means of the present invention.

다음에, 본 실시형태의 급탕시스템의 급탕운전시 및 탕수공급운전시에 있어서의 탱크컨트롤러(41) 및 급탕컨트롤러(21)의 제어처리를 도 2∼도 5를 참조하여 상세히 설명한다.Next, control processing of the tank controller 41 and the hot water supply controller 21 at the time of hot water supply operation and hot water supply operation of the hot water supply system of the present embodiment will be described in detail with reference to Figs. 2 to 5. Fig.

도 2의 흐름도를 참조하여 급탕시스템의 전원이 투입된 당초의 대기상태(급탕운전 또는 탕수공급운전을 실행하는 것이 요구되어 있지 않은 상태)에서, 바이패스밸브(39)가 탱크컨트롤러(41)에 의해 개방상태로 제어됨과 아울러, 탕수공급밸브 (19)가 급탕컨트롤러(21)에 의해 폐쇄상태로 제어되어 있다(STEP 1).2, the bypass valve 39 is controlled by the tank controller 41 in the original standby state in which the power supply of the hot water supply system is turned on (in a state where it is not required to perform the hot water supply operation or the hot water supply operation) The hot water supply valve 19 is controlled to be in the closed state by the hot water supply controller 21 (STEP 1).

이 상태에서, 탱크컨트롤러(41)는 욕조의 탕수공급운전의 요구가 있는지 없는지를 판단한다(STEP 2).In this state, the tank controller 41 determines whether there is a demand for the water supply operation of the bathtub (STEP 2).

이 경우, 탱크컨트롤러(41)는 리모컨(43)의 조작에 의해서, 탕수공급운전을 실행해야 하는 것이 지시된 경우, 혹은, 미리 설정된 스케줄에 의해서, 탕수공급운전을 개시해야 할 시각이 된 경우에, 탕수공급운전의 요구가 있다고 판단한다.In this case, when the tank controller 41 is instructed to execute the water supply operation by the operation of the remote controller 43, or when it is time to start the water supply operation by the preset schedule , It is determined that there is a demand for the water supply operation.

그리고 탕수공급운전의 요구가 있다고 판단한 경우에는, 도 3의 흐름도에 나타내는 제어처리가 탱크컨트롤러(41) 및 급탕컨트롤러(21)에 의해 실행된다. 또한, STEP 2에서, 탕수공급운전의 요구가 없는 경우에는, 탱크컨트롤러(41)는 다음에 STEP 3에 있어서, 급수관(33)에 있어서의 통수[크란(35)의 개전 등에 기인하는 급탕구로의 통수]의 유무를 판단한다.When it is determined that there is a demand for the water supply operation, the control process shown in the flowchart of Fig. 3 is executed by the tank controller 41 and the hot water controller 21. In STEP 2, when there is no demand for the water supply operation, the tank controller 41 next determines whether or not water supply to the hot water supply pipe 33 due to the opening of the water supply pipe 33 Whether or not there is a water flow.

이 경우, 탱크컨트롤러(41)는 급수관(33)의 유량센서(49)의 검출유량이 미리 설정된 하한 유량 이상으로 된 경우에, 통수를 검지한다.In this case, the tank controller 41 detects the water flow rate when the detected flow rate of the flow rate sensor 49 of the water supply pipe 33 is equal to or higher than a preset lower limit flow rate.

그리고 STEP 3에서 통수가 검지되지 않는 경우에는, 탱크컨트롤러(41)는 STEP 2로부터의 처리를 계속한다.If no water is detected in STEP 3, the tank controller 41 continues the processing from STEP 2.

또한, STEP 3에서 통수가 검지되면, STEP 4로부터의 제어처리가 탱크컨트롤러(41) 및 급탕컨트롤러(21)에 의해 실행된다.When the water flow rate is detected in STEP 3, the control processing from STEP 4 is executed by the tank controller 41 and the hot water controller 21.

STEP 4에서는, 탱크컨트롤러(41)는 저탕 탱크(31)가 탕수소진상태인지 아닌지를 판단한다. 이 경우, 탱크컨트롤러(41)는 탱크온도센서(48)의 검출온도가 소정 온도(여기에서는 목표급탕온도)보다도 낮은지 아닌지에 의해서, 저탕 탱크(31)가 탕수소진상태인지 아닌지를 판단한다.In STEP 4, the tank controller 41 judges whether or not the storage tank 31 is in the hot water exhaust state. In this case, the tank controller 41 determines whether or not the storage tank 31 is in the hot water consumption state, depending on whether or not the detected temperature of the tank temperature sensor 48 is lower than a predetermined temperature (here, the target hot water temperature).

STEP 4에서, 저탕 탱크(31)가 탕수소진상태가 아닌 경우에는, STEP 5로부터의 제어처리가 실행된다. STEP 5에서는, 탱크컨트롤러(41)는 바이패스밸브(39)를 전개(全開)상태로 제어한다. 또한, 탱크컨트롤러(41)는 STEP 6에 있어서, 연소식 급탕기(10)의 가열운전을 금지하는 취지의 지령을 급탕컨트롤러(21)에 부여한다.In STEP 4, when the storage tank 31 is not in the hot water exhaust state, control processing from STEP 5 is executed. In STEP 5, the tank controller 41 controls the bypass valve 39 to a fully open state. The tank controller 41 gives a command to the hot water supply controller 21 to prohibit the heating operation of the combustion type hot water heater 10 in STEP6.

그리고 STEP 7에 있어서, 탱크컨트롤러(41)에 의해, 크란(35) 등의 급탕구에 공급되는 탕수의 온도(급탕온도)를 리모컨(43)에서 설정된 목표급탕온도로 제어하는 온도조절제어가 실행된다.In STEP 7, the tank controller 41 executes the temperature adjustment control for controlling the temperature (hot water supply temperature) of the hot water supplied to the hot water supply port such as the crown 35 to the target hot water temperature set by the remote controller 43 do.

이 온도조절제어에서는, 연소식 급탕기(10)의 가열운전이 금지되어 있으므로, 상기 연소식 급탕기(10)의 가열운전은 실행되지 않는다. 그리고 탱크컨트롤러 (41)는 온도센서(54, 또는 53)의 검출온도가 목표급탕온도로 되도록, 상기 탱크출탕혼합비를 유량조정밸브(37, 38)에 의해 조정한다. 이에 따라, 급탕온도가 목표급탕온도로 제어된다.In this temperature control, the heating operation of the combustion type hot water heater 10 is prohibited, so that the heating operation of the combustion type hot water heater 10 is not performed. The tank controller 41 adjusts the tank brine mixing ratio by the flow rate adjusting valves 37 and 38 so that the detected temperature of the temperature sensor 54 or 53 becomes the target hot water temperature. Thus, the hot water supply temperature is controlled to the target hot water supply temperature.

상기의 온도조절제어와 병행하여 탱크컨트롤러(41)는 급수관(33)이 지수(止水)상태(통수가 검지되지 않는 상태)로 되었는지 아닌지를 판단한다(STEP 8). 이 경우, 탱크컨트롤러(41)는 급수관(33)의 유량센서(49)의 검출유량이 하한 유량 미만으로 된 경우에, 지수상태를 검지한다.In parallel with the above temperature control, the tank controller 41 determines whether or not the water supply pipe 33 is in a water stop state (no water is detected) (STEP 8). In this case, the tank controller 41 detects the exponential state when the detected flow rate of the flow rate sensor 49 of the water supply pipe 33 is less than the lower limit flow rate.

그리고 급수관(33)이 지수상태가 아닌 경우에는, STEP 4로부터의 처리가 계속된다. 또한, 급수관(33)이 지수상태로 되면, 급탕운전이 종료되고, STEP 1로부터의 제어처리가 재개된다.If the water pipe 33 is not in the exponential state, the process from STEP 4 is continued. When the water supply pipe 33 is in the exponential state, the hot water supply operation is terminated and the control process from STEP 1 is resumed.

한편, 급탕운전의 계속 등에 의해서, STEP 4에서 저탕 탱크(31)가 탕수소진상태로 된 것이 검지되면, STEP 9로부터의 제어처리가 실행된다.On the other hand, when it is detected in STEP 4 that the water tank 31 is in the hot water exhaustion state due to the continuation of the hot water supply operation, the control process from STEP 9 is executed.

STEP 9에서는, 탱크컨트롤러(41)는 연소식 급탕기(10)의 가열운전을 허가하는 취지의 지령을 급탕컨트롤러(21)에 부여한다.In STEP 9, the tank controller 41 gives an instruction to permit the heating operation of the combustion type hot water heater 10 to the hot water supply controller 21.

그리고 STEP 10에 있어서, 탱크컨트롤러(41)와 급탕컨트롤러(21)의 협동에 의해서, 급탕온도를 목표급탕온도로 제어하는 온도조절제어가 실행된다.In STEP 10, the temperature controller is controlled to cooperate with the tank controller 41 and the hot water controller 21 to control the hot water supply temperature to the target hot water temperature.

이 온도조절제어에서는, 탱크컨트롤러(41)는 상기 온도센서(53)에 의해 검출되는 상기 탱크출탕혼합탕수의 온도가 목표급탕온도보다도 낮은 소정의 혼합목표온도 이하로 되도록, 상기 탱크출탕혼합비를 유량조정밸브(37, 38)를 통하여 조정한다.In this temperature control, the tank controller 41 controls the tank brine mixing ratio so that the temperature of the tank brine mixed water detected by the temperature sensor 53 becomes equal to or lower than a predetermined mixing target temperature which is lower than the target hot- Through adjustment valves 37 and 38, respectively.

또한, 급탕컨트롤러(21)는 온도센서(23)의 검출온도[연소식 급탕기(10)로부터 유출되는 탕수의 온도]가 목표급탕온도보다도 소정온도만큼 높은 목표급탕기출탕온도로 되도록 버너(12)의 연소량과 바이패스서보밸브(16)에 의한 바이패스비를 제어한다(가열운전제어의 처리를 실행한다). 또한, 바이패스비를 일정하게 하여 버너(12)의 연소량만을 제어하도록 해도 좋다.The hot water controller 21 controls the temperature of the burner 12 so that the detected temperature of the temperature sensor 23 (the temperature of the hot water flowing out from the combustion type hot water heater 10) becomes the target hot water temperature, And the bypass ratio by the bypass servo valve 16 is controlled (the heating operation control process is executed). In addition, it is also possible to control only the burning amount of the burner 12 by keeping the bypass ratio constant.

또한, 탱크컨트롤러(41)는 온도센서(54)에 의해 검출되는 온도(급탕온도의 검출값)가 목표급탕온도로 되도록 바이패스밸브(39)의 개방도(나아가서는, 상기 바이패스출구혼합비)를 제어한다.The tank controller 41 also controls the opening degree of the bypass valve 39 (that is, the bypass outlet mixing ratio) so that the temperature detected by the temperature sensor 54 (detected value of the hot water temperature) .

이에 따라, 급탕온도가 목표급탕온도로 제어된다. 또한, STEP 10의 제어처리는, 본 발명에 있어서의 바이패스혼합급탕제어처리에 상당하는 제어처리이다.Thus, the hot water supply temperature is controlled to the target hot water supply temperature. The control processing in STEP 10 is control processing equivalent to the bypass mixed hot water control processing in the present invention.

상기의 온도조절제어와 병행하여 탱크컨트롤러(41)는 급수관(33)이 지수상태로 되었는지 아닌지를 판단한다(STEP 11). 이 판단은, 상기 STEP 8과 마찬가지로 실행된다.In parallel with the above temperature control, the tank controller 41 determines whether or not the water supply pipe 33 is in the exponential state (STEP 11). This determination is performed in the same manner as in STEP 8.

그리고 급수관(33)이 지수상태가 아닌 경우에는, STEP 4로부터의 처리가 계속된다. 또한, 급수관(33)이 지수상태로 되면, 탱크컨트롤러(41)는 상기 지수로부터 제 1 소정시간이 경과되었는지 아닌지를 STEP 12에서 판단한다. 환언하면, 탱크컨트롤러(41)는 STEP 10의 온도조절제어의 처리(바이패스혼합급탕제어처리)를 실행하는 급탕운전의 종료 후의 경과시간이 제 1 소정시간에 도달했는지 아닌지를 STEP 12에서 판단한다. 상기 제 1 소정시간은 본 발명에 있어서의 「소정시간」에 상당하는 것이다. 본 실시형태에서는 상기 제 1 소정시간은, 예를 들면 20분이다.If the water pipe 33 is not in the exponential state, the process from STEP 4 is continued. Further, when the water supply pipe 33 is in the exponential state, the tank controller 41 determines in STEP 12 whether or not the first predetermined time has elapsed from the index. In other words, the tank controller 41 determines in STEP 12 whether the elapsed time after completion of the hot water supply operation for executing the temperature adjustment control process (bypass mixed hot water supply control process) in STEP 10 has reached the first predetermined time . The first predetermined time corresponds to " predetermined time " in the present invention. In the present embodiment, the first predetermined time is, for example, 20 minutes.

여기서, STEP 10의 온도조절제어가 실행되는 급탕운전에서는, 연소식 급탕기 (10)의 가열운전에 의해서, 연소식 급탕기(10)에서 출탕관(32)의 하류측으로 유출되는 탕수의 온도가 목표급탕온도보다도 높은 목표급탕기출탕온도로 되도록 제어된다.Here, in the hot water supply operation in which the temperature regulation control in STEP 10 is executed, the temperature of the hot water flowing out from the combustion type hot water heater 10 to the downstream side of the hot water pipe 32 is lowered by the heating operation of the combustion hot water heater 10, Is controlled so as to become the target hot-water extraction hot-water temperature higher than the temperature.

이로 인해, 상기 급탕운전의 종료 직후는, 연소식 급탕기(10)의 출탕관[32, 상세한 것은 열교환기(13)의 하류측에서 제 3 도중부(32z)에 이르는 출탕관(32)]의 내부에 목표급탕온도보다도 높은 온도의 탕수가 잔류한다.Therefore, immediately after the end of the hot water supply operation, the outlet pipe 32 of the combustion type hot water heater 10 (specifically, the outlet pipe 32 extending from the downstream side of the heat exchanger 13 to the third intermediate portion 32z) The hot water having a temperature higher than the target hot water temperature remains inside.

그리고 상기 제 1 소정시간(20분)은 상기 잔류하는 탕수가 목표급탕온도보다도 낮은 온도로 식을 때까지에 필요한 시간으로서, 미리 실험 등에 의거하여 설정된 시간이다.The first predetermined time (20 minutes) is a time required until the remaining hot water is cooled to a temperature lower than the target hot water temperature, which is a time set in advance based on experiment or the like.

그리고 STEP 12의 판단결과가 긍정적인 경우[급수관(33)이 지수상태로 되고 나서의 경과시간이 제 1 소정시간(20분)에 도달한 경우]에는, STEP 1로부터의 제어처리가 재개된다.If the result of the determination in STEP 12 is affirmative (the elapsed time after the water pipe 33 becomes the exponential state reaches the first predetermined time (20 minutes)), the control processing from STEP 1 is resumed.

한편, STEP 12의 판단결과가 부정적인 경우[급수관(33)이 지수상태로 되고 나서의 경과시간이 소정시간(20분)에 도달하고 있지 않은 경우]에는, 탱크컨트롤러 (41)는 STEP 13에 있어서, 탕수공급운전의 요구가 있는지 없는지를 판단한다. 이 판단은 상기 STEP 2와 마찬가지로 실행된다.On the other hand, when the result of the determination in STEP 12 is negative (the elapsed time from when the water supply pipe 33 becomes the exponential state does not reach the predetermined time (20 minutes)), , It is determined whether or not there is a demand for the water supply operation. This determination is performed in the same manner as in STEP 2.

STEP 13에서 탕수공급운전의 요구가 없는 경우에는, 탱크컨트롤러(41)는 STEP 15에 있어서, 급수관(33)에 있어서의 통수의 유무를 판단한다. 이 판단은 상기 STEP 3과 마찬가지로 실행된다.If there is no demand for the water supply operation in STEP 13, the tank controller 41 determines in STEP 15 whether or not water in the water supply pipe 33 exists. This determination is performed in the same manner as in STEP 3 above.

그리고 STEP 15에서 통수가 검지되지 않는 경우에는, STEP 12로부터의 처리가 반복된다. 또한, STEP 15에서 통수가 검지된 경우에는, 상기 STEP 4로부터의 처리가 실행된다.If no water is detected in STEP 15, the processing from STEP 12 is repeated. If the flow rate is detected in STEP 15, the process from STEP 4 is executed.

STEP 13에서 탕수공급운전의 요구가 있는 경우에는, 탱크컨트롤러(41)는 STEP 14의 처리를 실행하고, 또한 도 3의 흐름도에 나타내는 제어처리(탕수공급운전의 제어처리)를 급탕컨트롤러(21)와 협동하여 실행한다.If there is a request for the water supply operation in STEP 13, the tank controller 41 executes the process of STEP 14 and further executes the control process (control process of the water supply operation) shown in the flowchart of FIG. 3 to the hot water controller 21 .

상기 STEP 14에서는, 탱크컨트롤러(41)는 타이머를 기동하여 상기 타이머에 의한 계시(計時)를 시작한다. 이에 따라, 탕수공급운전의 개시시부터의 경과시간의 계시(計時)가 시작된다. 또한, 타이머는 계시(計時)시간이 미리 정해진 제 2 소정시간에 도달하면, 계시(計時)를 종료하는 타이머(예를 들면 카운트 다운 타이머)이다. 상기 제 2 소정시간은, 본 실시형태에서는 예를 들면 60초이다.In STEP 14, the tank controller 41 starts a timer and starts counting by the timer. As a result, the elapsed time from the start of the water supply operation is started. The timer is a timer (for example, a countdown timer) for terminating the time counting when the counting time reaches a predetermined second predetermined time. The second predetermined time is, for example, 60 seconds in the present embodiment.

상기 STEP 2 또는 13에서 탕수공급운전의 요구가 있었던 경우에, 도 3의 흐름도에 나타내는 제어처리는 다음과 같이 실행된다.When there is a request for the water supply operation in STEP 2 or 13, the control process shown in the flowchart of FIG. 3 is executed as follows.

우선, STEP 16에 있어서, 급탕컨트롤러(21)는 탱크컨트롤러(41)로부터의 지령에 의해 탕수공급밸브(19)를 개방상태로 제어한다. 이에 따라, 욕조로의 탕수의 공급을 실행하는 탕수공급운전이 개시된다.First, in STEP 16, the hot water supply controller 21 controls the water supply valve 19 to be in an open state by a command from the tank controller 41. Thereby, the water supply operation for supplying water to the bath is started.

이어서, STEP 17에 있어서, 탱크컨트롤러(41)는 상기 타이머가 계시(計時)중인지 아닌지[즉, 상기 타이머의 계시(計時)시간이 제 2 소정시간에 도달하기 전의 상태인지 아닌지]를 판단한다.Then, in STEP 17, the tank controller 41 determines whether or not the timer is in the timing (that is, whether or not the time of the timer reaches the second predetermined time).

여기서, 탕수공급운전의 개시시의 STEP 17에서 상기 타이머가 계시(計時)중인 상황은, 이번의 탕수공급운전의 개시 전에, STEP 10의 온도조절제어를 실행하는 급탕운전이 실행되고 있으며, 또한, 상기 급탕운전의 종료 후의 경과시간이 상기 제 1 소정시간(20분)에 도달하고 있지 않은 상태에서 이번의 탕수공급운전이 개시된 상황이다. 이 상황은, 환언하면, 이번의 탕수공급운전의 개시시부터 제 1 소정시간 전(20분전)까지의 기간 내에 STEP 10의 온도조절제어를 실행하는 급탕운전이 실행된 상황이다. 이 상황에서는, 연소식 급탕기(10)의 열교환기(13)의 하류측의 출탕관(32)의 내부에 목표급탕온도보다도 높은 온도의 탕수가 잔류하고 있을 가능성이 높은 상태이다.Here, in the situation where the timer is counting at STEP 17 at the start of the water supply operation, the hot water supply operation for executing the temperature adjustment control at STEP 10 is started before the start of the water supply operation at this time, The water supply operation is started in the state in which the elapsed time after the end of the hot water supply operation has not reached the first predetermined time (20 minutes). In other words, this situation is a situation where the hot water supply operation for executing the temperature adjustment control in STEP 10 is executed within the period from the start of the present water supply operation to the first predetermined time (20 minutes before). In this situation, there is a high possibility that hot water having a temperature higher than the target hot water temperature remains in the outlet pipe 32 on the downstream side of the heat exchanger 13 of the combustion type hot water heater 10.

한편, 탕수공급운전의 개시시의 STEP 17에서 상기 타이머가 계시(計時)중이 아닌 상황은, 이번 탕수공급운전의 개시 전에, STEP 10의 온도조절제어를 실행하는 급탕운전이 실행되어 있지 않던지, 또는 상기 급탕운전의 종료 후의 경과시간이 상기 제 1 소정시간에 도달한 후에 이번 탕수공급운전이 개시된 상황이다. 이 상황은, 환언하면, 이번 탕수공급운전의 개시시부터 제 1 소정시간 전(20분전)까지의 기간 내에 STEP 10의 온도조절제어를 실행하는 급탕운전이 실행되어 있지 않은 상황이다. 따라서, 이 상황에서는, 연소식 급탕기(10)의 열교환기(13)의 하류측의 출탕관(32)의 내부에 목표급탕온도보다도 높은 온도의 탕수가 잔류하고 있을 일은 없다.On the other hand, in STEP 17 at the start of the hot water supply operation, it is determined that the hot water supply operation for executing the temperature adjustment control in STEP 10 has not been executed before the start of the hot water supply operation, Or the elapsed time after the completion of the hot water supply operation reaches the first predetermined time. In other words, this situation is a situation where the hot water supply operation for executing the temperature adjustment control in STEP 10 is not executed within the period from the start of the present water supply operation to the first predetermined time (20 minutes before). Therefore, in this situation, no hot water having a temperature higher than the target hot water temperature remains in the outlet pipe 32 on the downstream side of the heat exchanger 13 of the combustion type hot water heater 10.

그래서, STEP 17에서 상기 타이머가 계시(計時)중이 아닌 경우에는, 탱크컨트롤러(41)는 STEP 18에 있어서 바이패스밸브(39)를 폐쇄상태로 제어한다. 따라서, 이번 탕수공급운전의 개시시부터 제 1 소정시간 전까지의 기간 내에 STEP 10의 온도조절제어를 실행하는 급탕운전이 실행되어 있지 않은 경우에는, 이번 탕수공급운전의 개시시에 즉시, 바이패스밸브(39)가 폐쇄상태로 제어된다.Thus, in STEP 17, when the timer is not being counted, the tank controller 41 controls the bypass valve 39 to be in a closed state in STEP 18. Therefore, in the case where the hot water supply operation for executing the temperature adjustment control in STEP 10 is not executed within the period from the start of the water supply operation to the first predetermined time, immediately at the start of the water supply operation, (39) is controlled to be in a closed state.

한편, STEP 17에서 상기 타이머가 계시(計時)중인 경우에는, 탱크컨트롤러 (41)는 최종적으로 STEP 17에서 상기 타이머가 계시(計時)중이 아닌 것[계시(計時)가 종료된 것]이 확인될 때까지, STEP 19에 있어서, 바이패스밸브(39)를 예를 들면 현상(現狀) 개방도로 유지한다. 상기 현상 개방도는 STEP 10의 온도조절제어를 실행하는 급탕운전의 종료시의 개방도(개방상태의 개방도)이다. 또한, 상기 바이패스밸브(39)의 개방도는 기정(旣定)값의 개방도라도 좋다.On the other hand, when the timer is being measured in STEP 17, the tank controller 41 finally determines in STEP 17 that the timer is not being measured (time measurement) In STEP 19, the bypass valve 39 is maintained at the presently open state, for example. The development opening degree is an opening degree (opening degree in the open state) at the end of the hot water supply operation for executing the temperature adjustment control in STEP10. The opening degree of the bypass valve 39 may be an open degree of a predetermined value.

여기서, 상기 STEP 16에서 탕수공급밸브(19)를 개방하고 있으므로, STEP 18에서 바이패스밸브(39)를 폐쇄상태로 한 경우에는, 출탕관(32)의 제 1 도중부(32x)에서 하류측으로 흐르는 탱크출탕혼합탕수의 전체가, 연소식 급탕기(10)의 열교환기(13) 상류측의 출탕관으로 유입되고, 또한, 상기 열교환기(13)의 하류측에서 탕수공급관(15)을 통과하여 욕조로 공급된다.Since the water supply valve 19 is opened in STEP 16, when the bypass valve 39 is closed in STEP 18, the water is supplied from the first intermediate portion 32x of the outlet pipe 32 to the downstream side The whole of the flowing mixed tank water flows into the outlet duct on the upstream side of the heat exchanger 13 of the combustion type hot water heater 10 and passes through the hot water supply pipe 15 on the downstream side of the heat exchanger 13 The bathtub is supplied.

한편, STEP 19에서, 바이패스밸브(39)를 개방상태의 개방도로 유지한 경우에는, 탱크출탕혼합탕수의 대부분은, 제 2 도중부(32y)에서 연소식 급탕기(10)의 열교환기(13) 상류측의 출탕관(32)으로 유입되고, 또한, 상기 열교환기(13)의 하류측에서 탕수공급관(15)을 통과하여 욕조로 공급된다.On the other hand, when the bypass valve 39 is kept open at the open state in STEP 19, most of the mixed water of the tank hot water flows from the second midway portion 32y to the heat exchanger 13 of the combustion type hot water heater 10 And is supplied from the downstream side of the heat exchanger 13 through the hot water supply pipe 15 to the bathtub.

단, 연소식 급탕기(10)에 있어서의 탕수공급관(15)의 분기 개소의 하류측에서 출탕관(32)에 개장되어 있는 수격완충밸브(18)는 하류측에서 상류측으로의 탕수의 유통이 어느 정도 가능하다. 이로 인해, 탱크출탕혼합탕수의 일부는, 출탕바이패스관(34) 및 제 3 도중부(32z)를 경유하여 연소식 급탕기(10)의 출탕관(32)에 하류측으로부터 유입되고, 또한, 수격완충밸브(18)를 역류 방향으로 통과한 후에, 탕수공급관(15)을 통과하여 욕조로 공급된다.It should be noted that the water hammer buffer valve 18 that is opened in the water outlet pipe 32 on the downstream side of the branching point of the water supply pipe 15 in the combustion type hot water heater 10 is not limited to the one in which the flow of the hot water from the downstream side to the upstream side Is possible. A part of the mixed water of the tank taps is introduced into the outlet pipe 32 of the combustion type hot water heater 10 from the downstream side via the hot water bypass pipe 34 and the third intermediate portion 32z, After passing the water hammer buffering valve 18 in the backward flow direction, the water is supplied to the bathtub through the water supply pipe 15.

이 경우, 탕수공급운전의 개시 직후에 연소식 급탕기(10)의 출탕관(32)에 하류측으로부터 유입되는 탕수의 온도는, 상기 출탕관(32)에 잔류하고 있었던 탕수의 온도보다도 낮으므로, 열교환기(13)의 하류측의 출탕관(32)의 탕수의 온도가 저하된다.In this case, the temperature of the hot water flowing from the downstream side to the hot water supply pipe 32 of the combustion type hot water heater 10 immediately after the start of the hot water supply operation is lower than the temperature of the hot water remaining in the hot water supply pipe 32, The temperature of the hot water in the outlet pipe 32 on the downstream side of the heat exchanger 13 is lowered.

상기한 바와 같이 바이패스밸브(39)를 폐쇄상태 또는 개방상태로 제어한 상태에서, STEP 20에 있어서, 탱크컨트롤러(41) 및 급탕컨트롤러(21)의 협동에 의해서, 욕조에 공급하는 탕수의 온도(탕수공급온도)를 제어하는 탕수공급온도조절제어처리가 실행된다.The control of the bypass valve 39 in the closed state or the open state allows the tank controller 41 and the hot water controller 21 to cooperate in STEP 20 to control the temperature of the hot water supplied to the bathtub (Hot water supply temperature) is controlled by the hot water supply temperature control process.

이 탕수공급온도조절제어처리는, 도 4의 흐름도에서 나타내는 바와 같이 실행된다. 즉, 탱크컨트롤러(41)는 STEP 31에 있어서, 저탕 탱크(31)의 탕수소진상태인지 아닌지를 판단한다. 이 판단처리는 상기 STEP 4와 마찬가지로 실행된다.This water supply temperature control process is executed as shown in the flowchart of Fig. That is, in STEP 31, the tank controller 41 determines whether or not the storage tank 31 is in the hot water exhaust state. This determination process is executed in the same manner as in STEP 4.

STEP 31에서 저탕 탱크(31)가 탕수소진상태가 아닌 경우에는, STEP 32, 33의 제어처리가 실행된다. STEP 32에서는, 탱크컨트롤러(41)는 연소식 급탕기(10)의 가열운전을 금지하는 취지의 지령을 급탕컨트롤러(21)에 부여한다.In STEP 31, when the storage tank 31 is not in the water-exhaustion state, the control processing of STEP 32, 33 is executed. In STEP 32, the tank controller 41 gives an instruction to prohibit the heating operation of the combustion type hot water heater 10 to the hot water controller 21.

그리고 STEP 33에 있어서, 탱크컨트롤러(41)에 의해, 욕조에 공급하는 탕수의 온도(탕수공급온도)를 리모컨(43)에서 설정된 목표탕수공급온도로 제어하는 온도조절제어가 실행된다.In STEP 33, the temperature controller for controlling the temperature of the hot water (hot water supply temperature) supplied to the bathtub to the target hot water supply temperature set by the remote controller 43 is executed by the tank controller 41.

이 온도조절제어에서는, 연소식 급탕기(10)의 가열운전이 금지되어 있으므로, 상기 연소식 급탕기(10)의 가열운전은 실행되지 않는다. 그리고 탱크컨트롤러 (41)는 온도센서(53, 또는 23)의 검출온도가 목표탕수공급온도로 되도록 상기 탱크출탕혼합비를 유량조정밸브(37, 38)에 의해 조정한다. 이에 따라, 욕조에 공급되는 탕수의 온도가 목표탕수공급온도로 제어된다.In this temperature control, the heating operation of the combustion type hot water heater 10 is prohibited, so that the heating operation of the combustion type hot water heater 10 is not performed. The tank controller 41 adjusts the tank brine mixing ratio by the flow rate adjusting valves 37 and 38 such that the detected temperature of the temperature sensor 53 or 23 becomes the target water supply temperature. Thus, the temperature of the hot water supplied to the bath is controlled to the target hot water supply temperature.

또한, STEP 31에서 저탕 탱크(31)가 탕수소진상태로 된 것이 검지된 경우에는, STEP 34, 35의 제어처리가 실행된다. STEP 34에서는, 탱크컨트롤러(41)는 연소식 급탕기(10)의 가열운전을 허가하는 취지의 지령을 급탕컨트롤러(21)에 부여한다.When it is detected in STEP 31 that the storage tank 31 is in the hot water exhausting state, the control processing of STEPs 34 and 35 is executed. In STEP 34, the tank controller 41 gives an instruction to permit the heating operation of the combustion type hot water heater 10 to the hot water controller 21.

그리고 STEP 35에 있어서, 탱크컨트롤러(41)와 급탕컨트롤러(21)의 협동에 의해서, 급탕온도를 목표급탕온도로 제어하는 온도조절제어가 실행된다.In STEP 35, the temperature controller for controlling the hot water supply temperature to the target hot water temperature is executed by the cooperation of the tank controller 41 and the hot water controller 21.

이 온도조절제어에서는, 탱크컨트롤러(41)는 상기 온도센서(53)에 의해 검출되는 상기 탱크출탕혼합탕수의 온도가 목표탕수공급온도보다도 낮은 소정의 혼합목표온도 이하로 되도록 상기 탱크출탕혼합비를 유량조정밸브(37, 38)를 통하여 조정한다.In this temperature control, the tank controller 41 controls the tank brine mixing ratio so that the temperature of the tank brine mixed water detected by the temperature sensor 53 becomes equal to or lower than a predetermined mixing target temperature which is lower than the target water- Through adjustment valves 37 and 38, respectively.

또한, 급탕컨트롤러(21)는 열교환기(13)의 하류측의 온도센서(23)의 검출온도(욕조에 공급되는 탕수의 온도의 검출값)가 목표탕수공급온도로 되도록, 버너 (12)의 연소량과 바이패스서보밸브(16)에 의한 바이패스비를 제어한다(가열운전제어의 처리를 실행한다). 또한, 바이패스비를 일정하게 하여 버너(12)의 연소량만을 제어하도록 해도 좋다.The hot water controller 21 controls the temperature of the burner 12 so that the detected temperature of the temperature sensor 23 on the downstream side of the heat exchanger 13 (the detected value of the temperature of the hot water supplied to the bath) The combustion amount and the bypass ratio by the bypass servo valve 16 are controlled (the heating operation control process is executed). In addition, it is also possible to control only the burning amount of the burner 12 by keeping the bypass ratio constant.

이에 따라, 욕조에 탕수공급관(15)으로부터 공급되는 탕수의 온도가, 목표탕수공급온도에 거의 일치하도록 제어된다.Thus, the temperature of the hot water supplied from the hot water supply pipe 15 to the bath is controlled so as to substantially coincide with the target hot water supply temperature.

도 3으로 되돌아가서, 상기한 바와 같이 탕수공급온도조절제어처리가 STEP 20에서 실행되는 것과 병행하여 탱크컨트롤러(41)는 인터럽트(interrupt) 급탕의 유무를 STEP 21에서 판단한다. 상기 인터럽트 급탕은, 욕조의 탕수공급운전 중에 출탕관(32)에 급탕구가 개전되는[예를 들면 크란(35)이 개전되는] 것에 따라서 급탕구로의 급탕을 실행하는 것이다.Returning to Fig. 3, the tank controller 41 determines in STEP 21 whether or not there is an interruption hot water in parallel with the control of the water supply temperature control process in STEP 20 as described above. The interruption hot water is to perform hot water supply to the hot water supply port in accordance with the fact that the hot water supply port is opened (for example, the crown 35 is opened) in the hot water supply pipe 32 during the hot water supply operation of the bathtub.

상기의 인터럽트 급탕이 개시되면, 급수관(33)의 급수유량이 탕수공급관(15)에서 욕조로 흐르는 탕수의 유량보다도 많아진다. 그래서, 탱크컨트롤러(41)는 급수관(33)의 유량센서(49)의 검출유량이, 탕수공급관(15)의 유량센서(24)의 검출유량보다도 소정량 이상 커진 경우에, 인터럽트 급탕이 이루어진 것을 검지한다.When the interruption hot water supply is started, the water supply flow rate of the water supply pipe (33) becomes larger than the flow rate of the hot water flowing from the water supply pipe (15) to the bathtub. When the detected flow rate of the flow rate sensor 49 of the water supply pipe 33 is larger than the detected flow rate of the flow rate sensor 24 of the hot water supply pipe 15 by a predetermined amount or more, Detection.

STEP 21에서 인터럽트 급탕이 검지되지 않는 경우에는, 탱크컨트롤러[41, 또는 급탕컨트롤러(21)]는 STEP 22에서 욕조의 탕수공급이 완료되었는지 아닌지를 판단한다.If the interruption hot water supply is not detected in STEP 21, the tank controller 41 or the hot water supply controller 21 determines in STEP 22 whether or not the hot water supply of the bathtub is completed.

이 경우, 탕수공급관(15)의 유량센서(24)의 검출유량의 적산값(탕수공급운전의 개시시부터의 적산값)이 리모컨(43)에서 설정되는 목표탕수공급량에 도달한 경우에, 탕수공급이 완료되었다고 판단된다.In this case, when the integrated value of the detected flow rate of the flow rate sensor 24 of the hot-water supply pipe 15 (the accumulated value from the start of the hot water supply operation) reaches the target hot water supply amount set by the remote controller 43, It is judged that the supply is completed.

그리고 STEP 22에서 탕수공급이 완료되어 있지 않은 경우에는, STEP 17로부터의 제어처리가 계속된다.If the water supply is not completed in STEP 22, the control process from STEP 17 is continued.

또한, STEP 22에서 탕수공급이 완료된 경우에는, 탕수공급운전이 종료되고, STEP 1로부터의 제어처리가 재개된다.When the water supply is completed in STEP 22, the water supply operation is terminated and the control process from STEP 1 is resumed.

이상과 같이 하여 탕수공급운전이 실행된다. 이 경우, 탕수공급운전의 개시시의 STEP 14에서 타이머가 기동된 경우에는, 상기 타이머의 계시(計時)가 종료될 때까지[탕수공급운전의 개시시부터 제 2 소정시간(60초)이 경과될 때까지], 바이패스밸브(39)가 개방상태로 되고, 상기 타이머의 계시(計時)가 종료된 후는 STEP 18의 처리에 의해서, 바이패스밸브(39)가 폐쇄상태로 제어된다. 따라서, 탕수공급운전에서는, 그 개시 직후에 상기 타이머가 계시(計時)중으로 되어 있는 기간(이것은 본 발명에 있어서의 소정기간에 상당한다)을 제외하고, 바이패스밸브(39)가 폐쇄상태로 유지된다.The water supply operation is performed as described above. In this case, when the timer is started in STEP 14 at the start of the water supply operation, the second predetermined time (60 seconds) elapses from the start of the water supply operation until the counting of the timer ends , The bypass valve 39 is brought into the open state and after the timing of the timer is completed, the bypass valve 39 is controlled to be closed by the process of STEP 18. Therefore, in the water supply operation, the bypass valve 39 is maintained in the closed state except for a period (corresponding to a predetermined period of time in the present invention) in which the timer is in the timing do.

보충하면, 상기 STEP 10의 온도조절제어를 실행하는 급탕운전시에, 예를 들면 목표급탕온도가 비교적 높은 경우, 혹은, 급수관(33)의 유량이 소량인 경우에는, 바이패스밸브(39)를 폐쇄상태로 유지해도 좋다. 이 경우에는, 상기 급탕운전의 종료시에 있어서의 연소식 급탕기(10)의 열교환기(13) 하류측의 출탕관(32) 내부의 탕수의 온도는, 목표급탕온도 혹은 그것에 가까운 온도로 되어 있다.In addition, when the target hot water temperature is relatively high, or when the flow rate of the water supply pipe 33 is a small amount, for example, when the hot water supply operation for executing the temperature adjustment control in STEP 10 is performed, the bypass valve 39 It may be kept closed. In this case, the temperature of the hot water in the hot water discharge pipe 32 on the downstream side of the heat exchanger 13 of the combustion type hot water heater 10 at the end of the hot water supply operation is the target hot water temperature or a temperature close to the target hot water temperature.

따라서, 이 경우에는, STEP 19에서 바이패스밸브(39)를 폐쇄상태로 제어해도 좋다. STEP 19에서 바이패스밸브(39)를 개방상태로 제어하는 것은, STEP 10의 온도조절제어를 실행하는 급탕운전시(상세하게는, 이번 탕수공급운전의 개시시부터 제 1 소정시간 전까지의 기간 내에서의 상기 급탕운전시)에, 바이패스밸브(39)가 개방상태의 개방도로 제어된 경우에만 실행하도록 해도 좋다.Therefore, in this case, the bypass valve 39 may be controlled to be in the closed state in STEP19. The control of the bypass valve 39 to the open state in STEP 19 is performed during the hot water supply operation for executing the temperature adjustment control in STEP 10 (specifically, during the period from the start of the hot water supply operation to the first predetermined time The bypass valve 39 may be operated only when the bypass valve 39 is controlled to open the open state.

STEP 21에서 인터럽트 급탕이 이루어진 것이 검지된 경우에는, STEP 23에 있어서, 급탕컨트롤러(21)는 탱크컨트롤러(41)의 지령에 의해, 탕수공급밸브(19)를 폐쇄상태로 제어한다. 이에 따라, 욕조의 탕수공급운전이 일단 중단된다.If it is detected in STEP 21 that the interruption hot water supply has been performed, the hot water supply controller 21 controls the water supply valve 19 to be in the closed state in STEP 23 by a command from the tank controller 41. Thus, the water supply operation of the bathtub is once stopped.

그리고 급탕컨트롤러(21) 및 탱크컨트롤러(41)의 협동에 의해서, 상기 STEP 4로부터의 제어처리가 실행된다. 이에 따라, 급탕구에 공급하는 탕수의 온도(급탕온도)가 목표급탕온도로 되도록 제어된다.The control processing from STEP 4 is executed by cooperation of the hot water supply controller 21 and the tank controller 41. Thus, the temperature of the hot water supplied to the hot water supply port (hot water supply temperature) is controlled to be the target hot water temperature.

또한, 이 경우, 급탕관(33)이 지수상태로 되어 인터럽트 급탕이 종료되면 (STEP 8 또는 STEP 11의 판단결과가 긍정적이 되면), 그 직후에 실행되는 STEP 2 또는 STEP 13의 처리에 있어서의 판단결과가 긍정적으로 되어 탕수공급운전이 재개된다.In this case, when the hot water supply pipe 33 is in the exponential state and the interruption of hot water supply is completed (when the result of the determination in STEP 8 or STEP 11 becomes positive), in STEP 2 or STEP 13 The judgment result becomes positive and the water supply operation is resumed.

또한, 타이머의 계시(計時)중에 인터럽트 급탕이 실행된 경우에는, 상기 타이머의 계시(計時)가 계속된다. 단, STEP 10의 온도조절제어가 실행되는 인터럽트 급탕의 종료 후에, 탕수공급운전이 재개되는 경우에는, 상기 탕수공급운전의 재개시에 STEP 14에서 타이머가 재기동된다.When the interruption hot water supply is executed during the timer time, the timer continues to be counted. However, if the water supply operation is restarted after the interruption of the hot water supply in which the temperature adjustment control in STEP 10 is executed, the timer is restarted in STEP 14 upon resumption of the water supply operation.

이상과 같이 하여 탕수공급운전 중에, 인터럽트 급탕이 있었던 경우에는, 탕수공급운전이 일단, 중단되고, 인터럽트 급탕의 종료 후에, 탕수공급운전이 재개된다.In the case where there is interrupt hot water during the hot water supply operation as described above, the hot water supply operation is temporarily stopped and the hot water supply operation is resumed after the interrupt hot water supply ends.

이상 설명한 실시형태에 따르면, STEP 10의 온도조절제어(상세하게는, 바이패스밸브(39)가 개방상태의 개방도로 제어되는 온도조절제어)를 실행하는 급탕운전이 실행되는 급탕운전이 실행된 후, 상기 급탕운전의 종료 후의 경과시간이 상기 제 1 소정시간(20분)에 도달하고 있지 않은 상태에서, 탕수공급운전을 개시한 경우에, 상기 탕수공급운전의 개시 직후는, 타이머의 계시(計時)가 종료될 때까지[탕수공급운전의 개시시부터의 경과시간이 제 2 소정시간(60초)에 도달할 때까지], 바이패스밸브(39)가 개방상태로 제어된다.According to the above-described embodiment, after the hot water supply operation in which the hot water supply operation for executing the temperature adjustment control in STEP 10 (specifically, the temperature adjustment control in which the bypass valve 39 is controlled to open the open state) Immediately after the start of the hot water supply operation when the hot water supply operation is started in a state where the elapsed time after the end of the hot water supply operation does not reach the first predetermined time (20 minutes) (Until the elapsed time from the start of the water supply operation reaches the second predetermined time (60 seconds)), the bypass valve 39 is controlled to be in an open state.

이로 인해, 타이머의 계시(計時)중에 인터럽트 급탕이 실행된 경우에는, 연소식 급탕기(10)의 출탕관(32)으로부터의 탕수와 상기 제 2 도중부(32y)에서 출탕바이패스관(34)을 통과하여 하류측으로 흘러 오는 탕수가 제 3 도중부(32z)에서 혼합된 후에, 급탕구에 공급된다.The hot water from the hot water pipe 32 of the combustion type hot water heater 10 and the hot water from the hot water bypass pipe 34 from the second midway portion 32y can be supplied to the hot water tank 10, Is mixed with the hot water flowing in the downstream side through the third intermediate portion 32z and then supplied to the hot water supply port.

이 경우, 제 2 도중부(32y)에 상류측으로부터 공급되는 탱크출탕혼합탕수의 온도는, 상기 STEP 10의 온도조절제어가 실행되는 급탕운전시의 종료시에 있어서의 연소식 급탕기(10)의 열교환기(13) 하류측의 출탕관[32, 제 3 도중부(32z)보다도 연소식 급탕기(10)측의 출탕관(32)]의 탕수의 온도보다도 낮다.In this case, the temperature of the mixed tank water supplied from the upstream side to the second midway portion 32y is lower than the temperature of the heat exchanging operation of the combustion type hot water heater 10 at the end of the hot water supply operation in which the temperature adjustment control in STEP 10 is performed Is lower than the temperature of the hot water in the outlet duct 32 on the downstream side of the apparatus 13 and the outlet duct 32 on the side of the combustion type hot water heater 10 more than the third intermediate position 32z.

따라서, 탕수공급운전 중에, 상기 타이머의 계시(計時)중으로 되어 있는 도중에, 인터럽트 급탕이 실행되어도, 급탕구에 목표급탕온도에 비하여 고온의 탕수가 공급되는 것이 방지된다.Therefore, even when the interruption hot water supply is performed during the time when the timer is being set during the hot water supply operation, hot water having a higher temperature than the target hot water temperature is prevented from being supplied to the hot water supply opening.

또한, STEP 10의 온도조절제어를 실행하는 급탕운전의 종료 후의 경과시간이 상기 제 1 소정시간(20분)에 도달한 후에 개시된 탕수공급운전의 도중에 인터럽트 급탕이 실행된 경우, 혹은, 탕수공급운전 중에 타이머의 계시(計時)가 종료된 후에, 인터럽트 급탕이 실행된 경우에는, 상기 인터럽트 급탕의 개시시에 바이패스밸브(39)가 폐쇄상태로 제어되어 있다.When the interruption hot water supply is executed in the middle of the hot water supply operation started after the elapsed time after the end of the hot water supply operation for executing the temperature adjustment control in STEP 10 reaches the first predetermined time (20 minutes), or when the hot water supply operation The bypass valve 39 is controlled to be in the closed state at the start of the interruption hot water supply when the interruption hot water supply is executed after the end of the timer counting.

단, 이 경우, 상기 인터럽트 급탕의 개시시에는, 제 3 도중부(32z)보다도 연소식 급탕기(10)측의 출탕관(32)의 탕수 온도는 이미 충분히 저하되어 있다.However, in this case, at the start of the interruption hot water supply, the hot water temperature of the hot water pipe 32 on the side of the combustion type hot water heater 10 is lower than that of the third intermediate portion 32z sufficiently.

따라서, 상기 인터럽트 급탕에 있어서도, 그 개시 직후에 급탕구에 목표급탕온도에 비하여 고온의 탕수가 공급되는 것이 방지된다.Therefore, even in the interruption hot water supply, hot water having a higher temperature than the target hot water temperature is prevented from being supplied to the hot water supply opening immediately after the start of the interruption hot water supply.

또한, 타이머의 계시(計時) 종료 후의 탕수공급운전에서는, 바이패스밸브 (39)가 폐쇄되어 있으므로, 출탕관(32)의 제 1 도중부(32x)에서 하류측으로 흐르는 탱크출탕혼합탕수의 전량이, 연소식 급탕기(10)의 그 상류측으로부터 공급된다. 이로 인해, 욕조에 공급하는 탕수의 온도를 매우 적합하게 목표탕수공급온도로 제어할 수 있다.Since the bypass valve 39 is closed in the water supply operation after the counting of the timer is completed, the total amount of the mixed water of the tank hot water flowing from the first midway portion 32x of the hot water supply pipe 32 to the downstream side , And is supplied from the upstream side of the combustion type hot water heater (10). This makes it possible to control the temperature of the hot water supplied to the bath to a target hot water supply temperature very favorably.

다음에, 이상 설명한 실시형태의 변형형태를 설명한다.Next, a modification of the embodiment described above will be described.

상기 실시형태에서는, STEP 10의 온도조절제어를 실행하는 급탕운전이 실행되는 급탕운전이 실행된 후, 상기 급탕운전의 종료 후의 경과시간이 상기 제 1 소정시간(20분)에 도달하고 있지 않은 상태에서, 탕수공급운전이 개시된 경우에, 타이머의 계시(計時)가 종료될 때까지[탕수공급운전의 개시시부터의 경과시간이 제 2 소정시간(60초)에 도달할 때까지], 바이패스밸브(39)를 일정 개방도의 개방상태로 제어했지만, 상기 바이패스밸브(39)의 개방도를, 타이머의 계시(計時)중에 서서히 감소시켜 가도록 해도 좋다. 예를 들면, 타이머의 계시(計時)중에, 바이패스밸브 (39)의 개방도를 일정한 감소속도로 감소시키거나 혹은, 타이머의 계시(計時) 종료시에 바이패스밸브(39)의 개방도가 제로(0)로 되도록 상기 바이패스밸브(39)의 개방도를 서서히 감소시키도록 해도 좋다.In the above-described embodiment, after the hot water supply operation in which the hot water supply operation for executing the temperature adjustment control in STEP 10 is executed and the elapsed time after the end of the hot water supply operation has not reached the first predetermined time (20 minutes) (Until the elapsed time from the start of the water supply operation reaches the second predetermined time (60 seconds)) until the timing of the timer is ended when the water supply operation is started, The degree of opening of the bypass valve 39 may be gradually reduced during the time of the timer. For example, the opening degree of the bypass valve 39 may be reduced to a constant decreasing rate during the counting of the timer, or the opening degree of the bypass valve 39 may be reduced to zero (0), the opening degree of the bypass valve 39 may be gradually decreased.

이와 같이 한 경우에는, 타이머의 계시(計時)중에 인터럽트 급탕이 실행된 경우에, 상기 인터럽트 급탕의 개시타이밍이 타이머의 계시(計時) 종료의 시각에 가까울수록, 상기 인터럽트 급탕의 개시 직후에 출탕바이패스관(34)을 통과하여 제 3 도중부(32z)로 유입되는 탕수[연소식 급탕기(10)측에서의 제 3 도중부(32z)로 흐르는 탕수에 혼합하는 탕수]의 유량을 억제할 수 있다.In such a case, when the interruption hot water supply is executed during the timer counting, the closer the start timing of the interruption hot water supply is to the time of the end of the counting of the timer, It is possible to suppress the flow rate of the hot water (hot water mixed in the hot water flowing to the third midway portion 32z on the side of the combustion type hot water heater 10) passing through the pass pipe 34 and flowing into the third midway portion 32z.

이로 인해, 제 3 도중부(32z)보다도 연소식 급탕기(10)측의 출탕관(32) 내의 탕수의 온도에 적합한 양의 탕수를 출탕바이패스관(34)에서 제 3 도중부(32z)로 유입시킬 수 있다. 나아가서는, 인터럽트 급탕의 개시 직후에 급탕구에 공급되는 탕수의 온도가 너무 낮아지지 않게 하여 상기 탕수의 온도를 신속하게 목표급탕온도에 가깝게 할 수 있다.Therefore, the amount of the hot water suitable for the temperature of the hot water in the hot water supply pipe 32 on the side of the third hot water supply unit 10 than the third intermediate portion 32z is supplied from the hot water bypass pipe 34 to the third midway portion 32z . Further, the temperature of the hot water supplied to the hot water supply opening immediately after the start of the interrupt hot water supply is prevented from becoming too low, and the temperature of the hot water can be quickly brought close to the target hot water temperature.

또한, 상기 실시형태에서는, STEP 10의 온도조절제어를 실행하는 급탕운전이 실행되는 급탕운전이 실행된 후, 상기 급탕운전의 종료 후의 경과시간이 상기 제 1 소정시간(20분)에 도달하고 있지 않은 상태에서, 탕수공급운전이 개시된 경우에, 상기 탕수공급운전의 개시 직후에, 바이패스밸브(39)를 개방상태로 제어하는 기간을, 상기 탕수공급운전의 개시시부터 일정시간으로서의 제 2 소정시간(60초)이 경과될 때까지의 기간으로 했다.In the above embodiment, it is assumed that the elapsed time after the completion of the hot water supply operation has reached the first predetermined time (20 minutes) after the hot water supply operation in which the hot water supply operation for executing the temperature adjustment control in STEP 10 is executed Immediately after the start of the water supply operation, the period for controlling the bypass valve (39) to be in the open state is referred to as a second predetermined time from the start of the water supply operation, And the period until the time (60 seconds) elapsed.

단, 탕수공급운전의 개시시부터 바이패스밸브(39)를 개방상태로 제어하는 기간의 시간을, 예를 들면, STEP 10의 온도조절제어를 실행하는 급탕운전의 종료시부터 탕수공급운전의 개시시까지의 시간(이후, 시간(X)이라고 한다)에 따라서 가변적으로 설정해도 좋다. 이 경우, 시간(X)이 길수록, 탕수공급운전의 개시시에 있어서 연소식 급탕기(10)의 열교환기(13)의 하류측의 출탕관(32) 내의 탕수의 온도가 저하되어 있다고 생각할 수 있다. 따라서, 예를 들면, 시간(X)이 길수록, 바이패스밸브(39)를 개방상태로 제어하는 기간의 시간이 짧아지도록 해도 좋다.It is to be noted that the period of time during which the bypass valve 39 is controlled to be in the open state from the start of the water supply operation is changed from the end of the hot water supply operation for executing the temperature adjustment control in STEP 10 to the start of the hot water supply operation (Hereinafter, referred to as time X). In this case, it can be considered that the longer the time X, the lower the temperature of the hot water in the hot water pipe 32 on the downstream side of the heat exchanger 13 of the combustion type hot water heater 10 at the start of the hot water supply operation . Therefore, for example, the longer the time X, the shorter the period of time during which the bypass valve 39 is controlled to be in the open state.

이와 같이 한 경우에는, 탕수공급운전 중에 바이패스밸브(39)를 개방상태로 유지하는 기간을 필요 최소한의 시간으로 여길 수 있다.In such a case, the period during which the bypass valve 39 is kept in the open state during the water supply operation can be regarded as the minimum necessary time.

또한, 예를 들면, 연소식 급탕기(10)의 열교환기(13) 하류측[탕수공급관(15)의 분기 개소보다도 하류측]의 출탕관(32) 내의 탕수의 온도를 검출하는 온도센서를 구비할 경우에는, 탕수공급운전의 개시 직후에 바이패스밸브(39)를 개방상태로 유지하는 기간을, 상기 온도센서에 의한 검출온도에 따라서 결정하도록 해도 좋다. 예를 들면, 탕수공급운전의 개시 후, 상기 검출온도가 목표급탕온도에 일치 혹은 거의 일치하는 온도로 저하될 때까지, 바이패스밸브(39)를 개방상태로 제어하도록 해도 좋다.Further, for example, a temperature sensor for detecting the temperature of hot water in the hot water pipe 32 on the downstream side of the heat exchanger 13 (downstream of the branching point of the hot water supply pipe 15) of the combustion type hot water heater 10 The period during which the bypass valve 39 is kept in the open state immediately after the start of the water supply operation may be determined according to the detected temperature by the temperature sensor. For example, after the start of the running water supply operation, the bypass valve 39 may be controlled to be in an open state until the detected temperature is lowered to a temperature that coincides with or substantially matches the target hot water temperature.

또한, 상기 실시형태에서는, 연소식 급탕기(10) 내의 출탕관(32)에는, 열교환기(13)의 하류측에 수격완충밸브(18)가 개장되어 있지만, 상기 수격완충밸브(18)가 생략되어 있어도 좋다.Although the water hammer damping valve 18 is opened on the downstream side of the heat exchanger 13 in the hot water tank 32 in the combustion type hot water heater 10 in the above embodiment, .

또한, 상기 실시형태에서는, 저탕 탱크(31)의 탕수소진상태를 검지하기 위해, 저탕 탱크(31)에 장착한 온도센서(48)를 사용했지만, 예를 들면 다음과 같은 수법으로 탕수소진상태를 검지하는 것도 가능하다.In the above embodiment, the temperature sensor 48 attached to the storage tank 31 is used to detect the boiled water exhaustion state of the storage tank 31. However, for example, in the following method, It is also possible to detect it.

즉, 저탕 탱크(31)의 비등상태[잔여 탕수량의 만배(滿杯)상태]로부터, 저탕 탱크(31)에서 출탕관(32)으로 흐르는 탕수(소정온도 이상의 탕수)의 유량을 적절한 유량센서에 의해 검출하고, 그 검출값을 적산한다. 그리고 상기 유량의 검출값의 적산값을, 저탕 탱크(31)의 용량으로부터 감산함으로써, 저탕 탱크(31)의 잔여 탕수량을 추정한다. 이 잔여 탕수량의 추정값을 탕수소진상태 판정용의 임계값을 비교하는 것에 의해, 저탕 탱크(31)의 탕수소진상태를 검지할 수도 있다.
That is to say, the flow rate of hot water (hot water at a predetermined temperature or more) flowing from the storage tank 31 to the hot water tank 32 from the boiling state of the storage tank 31 (full state of the remaining hot water) And integrates the detected values. The remaining amount of hot water in the storage tank 31 is estimated by subtracting the accumulated value of the detected value of the flow rate from the capacity of the storage tank 31. By comparing the estimated value of the residual water quantity with the threshold value for determining the water-heating state, it is also possible to detect the water-heating state of the storage tank 31.

10: 연소식 급탕기
15: 탕수공급관
19: 탕수공급밸브
21: 급탕컨트롤러(운전제어수단)
31: 저탕 탱크
32: 출탕관
32y: 제 2 도중부[도중부(A)]
32z: 제 3 도중부[도중부(B)]
33: 급수관
34: 출탕바이패스관
39: 바이패스밸브
41: 탱크컨트롤러(운전제어수단)
10: Combustion hot water heater
15: Potable water supply pipe
19: Water supply valve
21: Hot water supply controller (operation control means)
31: Storage tank
32: Hot water pipe
32y: Second midway portion (intermediate portion (A))
32z: Third midway portion (midway portion (B))
33: Water supply pipe
34: Hot water bypass pipe
39: Bypass valve
41: tank controller (operation control means)

Claims (3)

저탕 탱크와, 상기 저탕 탱크 내의 탕수를 가열하는 가열수단과, 상기 저탕 탱크 내의 탕수가 공급되도록 상기 저탕 탱크로부터 도출되고, 종단에 급탕구를 가지는 출탕관과, 상기 저탕 탱크에 급수하도록 상기 저탕 탱크에 접속된 급수관과, 상기 출탕관의 도중에 설치된 열교환기를 가지며, 상기 열교환기에서 상기 출탕관을 흐르는 탕수를 버너의 연소열에 의해 가열하는 연소식 급탕기와, 상기 연소식 급탕기의 상류측에 있어서의 상기 출탕관의 도중부(A)와 상기 연소식 급탕기의 하류측에 있어서의 상기 출탕관의 도중부(B)를 연통시키는 출탕바이패스관과, 상기 출탕바이패스관을 개폐 가능하게 상기 출탕바이패스관에 설치된 바이패스밸브와, 상기 연소식 급탕기의 열교환기의 하류측에서 상기 도중부(B)에 이르는 상기 출탕관으로부터 분기되어 욕조에 접속된 탕수공급관을 구비하고, 상기 출탕관의 급탕구로의 급탕을 실행하는 급탕운전과 상기 욕조로의 탕수공급을 실행하는 탕수공급운전을 실행 가능하게 구성된 급탕시스템으로서,
상기 급탕시스템의 운전제어를 실행하는 운전제어수단을 구비하고 있으며,
상기 운전제어수단은,
상기 급탕운전시에, 상기 연소식 급탕기에 상류측으로부터 유입되는 탕수를 상기 연소식 급탕기의 가열운전에 의해 가열함과 아울러, 이 가열된 탕수와 상기 연소식 급탕기의 상류측에서 상기 출탕바이패스관을 통과하여 하류측으로 흐르는 탕수를 상기 도중부(B)에서 혼합시킴으로써, 상기 급탕구에 공급하는 탕수의 온도가 목표급탕온도로 되도록 상기 연소식 급탕기의 가열운전과 상기 바이패스밸브의 개방도를 제어하는 처리인 바이패스혼합급탕제어처리를 실행하는 기능과,
상기 바이패스혼합급탕제어처리를 실행하는 급탕운전의 종료 후, 소정시간이 경과되기 전에, 상기 탕수공급운전을 개시할 경우에는, 상기 탕수공급운전의 개시 직후의 소정기간은, 상기 탕수공급관을 통하여 상기 욕조로의 탕수의 공급을 실행시키면서, 상기 바이패스밸브를 개방상태로 제어하고, 또한, 상기 소정기간의 경과 후에 상기 바이패스밸브를 폐쇄상태로 제어하는 기능과,
상기 바이패스혼합급탕제어처리를 실행하는 급탕운전의 종료 후, 상기 소정시간이 경과된 후에, 상기 탕수공급운전을 개시할 경우에는, 상기 탕수공급관을 통하여 상기 욕조로의 탕수의 공급을 실행시키면서, 상기 바이패스밸브를 즉시 폐쇄상태로 제어하는 기능을 가지도록 구성되어 있는 것을 특징으로 하는 급탕시스템.
A heating tank for heating the hot water in the storage tank; a hot water outlet pipe extending from the storage tank to supply hot water in the storage tank and having a hot water supply port at the end; And a heat exchanger installed in the middle of the hot water tank, wherein the heat exchanger is provided with a combustion type hot water heater for heating the hot water flowing in the hot water tank through the combustion heat of the burner, A brewing bypass pipe for connecting the middle portion (A) of the outlet pipe and the middle portion (B) of the outlet pipe on the downstream side of the combustion type hot water supply unit; and a brewing bypass pipe A bypass valve provided in the pipe and a branch pipe extending from the downstream side of the heat exchanger of the combustion type hot water supply unit to the middle portion B As the hot water supply operation and the hot water supply system for hot water supply operation configured to be executed to run the hot water supply to the tub having a hot water supply pipe and a hot water supply run of the hot water supply port of said output tank connected kettle,
And operation control means for executing operation control of the hot water supply system,
Wherein the operation control means includes:
The hot water flowing from the upstream side to the combustion type hot water heater is heated by the heating operation of the combustion type hot water heater at the time of the hot water supply operation and at the same time, The heating operation of the combustion type hot water heater and the opening degree of the bypass valve are controlled so that the temperature of the hot water supplied to the hot water supply port becomes the target hot water temperature, A process for executing a bypass mixed hot water supply control process,
When the water supply operation is started before a predetermined time elapses after the completion of the hot water supply operation for executing the bypass mixed hot water supply control process, a predetermined period of time immediately after the start of the hot water supply operation is performed through the hot water supply pipe A function of controlling the bypass valve to be in the open state while the supply of the hot water to the bath is performed and controlling the bypass valve to be in the closed state after the lapse of the predetermined period,
Wherein when the water supply operation is started after the predetermined time has elapsed after the end of the hot water supply operation for executing the bypass mixed hot water supply control process, the supply of the hot water to the bathtub is performed through the hot water supply pipe, And a function of immediately controlling the bypass valve to a closed state.
청구항 1에 있어서,
상기 운전제어수단은, 상기 바이패스혼합급탕제어처리를 실행하는 급탕운전의 종료시부터 상기 탕수공급운전의 개시시까지의 시간이 길수록, 상기 탕수공급운전의 개시 직후의 소정기간을 짧게 하도록 상기 소정기간을 설정하도록 구성되어 있는 것을 특징으로 하는 급탕시스템
The method according to claim 1,
Wherein the operation control means controls the operation of the control means so that the longer the time from the end of the hot water supply operation for executing the bypass mixed hot water supply control process to the start of the hot water supply operation, Is configured to set the temperature of the hot water supply system
청구항 1 또는 청구항 2에 있어서,
상기 운전제어수단은, 상기 바이패스혼합급탕제어처리를 실행하는 급탕운전의 종료 후, 상기 소정시간이 경과되기 전에, 상기 탕수공급운전을 개시할 경우에, 상기 탕수공급운전의 개시 직후의 상기 소정기간에 상기 바이패스밸브를 서서히 폐쇄상태로 접근하여 가도록 상기 바이패스밸브를 제어하도록 구성되어 있는 것을 특징으로 하는 급탕시스템.
The method according to claim 1 or 2,
Wherein the operation control means controls the operation of the hot water supply operation control means so that when the hot water supply operation is started after the end of the hot water supply operation for executing the bypass mixed hot water supply control process and before the predetermined time has elapsed, Wherein the control unit controls the bypass valve so as to gradually approach the bypass valve in a closed state during a period when the bypass valve is closed.
KR1020150010131A 2015-01-21 2015-01-21 Hot water supply system KR101586165B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020150010131A KR101586165B1 (en) 2015-01-21 2015-01-21 Hot water supply system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020150010131A KR101586165B1 (en) 2015-01-21 2015-01-21 Hot water supply system

Publications (1)

Publication Number Publication Date
KR101586165B1 true KR101586165B1 (en) 2016-01-15

Family

ID=55173575

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020150010131A KR101586165B1 (en) 2015-01-21 2015-01-21 Hot water supply system

Country Status (1)

Country Link
KR (1) KR101586165B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021063010A1 (en) * 2019-09-30 2021-04-08 芜湖美的厨卫电器制造有限公司 Heating hot water boiler and control method therefor, and computer readable storage medium

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011153797A (en) 2010-01-28 2011-08-11 Rinnai Corp Hot water supply system
JP2011163711A (en) * 2010-02-12 2011-08-25 Rinnai Corp Hot water supply system
KR20110127259A (en) * 2009-03-11 2011-11-24 린나이가부시기가이샤 Hot-water supply system
KR101482847B1 (en) * 2012-04-20 2015-01-14 린나이코리아 주식회사 Hot water supply system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110127259A (en) * 2009-03-11 2011-11-24 린나이가부시기가이샤 Hot-water supply system
JP2011153797A (en) 2010-01-28 2011-08-11 Rinnai Corp Hot water supply system
JP5295986B2 (en) * 2010-01-28 2013-09-18 リンナイ株式会社 Hot water system
JP2011163711A (en) * 2010-02-12 2011-08-25 Rinnai Corp Hot water supply system
KR101482847B1 (en) * 2012-04-20 2015-01-14 린나이코리아 주식회사 Hot water supply system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021063010A1 (en) * 2019-09-30 2021-04-08 芜湖美的厨卫电器制造有限公司 Heating hot water boiler and control method therefor, and computer readable storage medium
US11828475B2 (en) 2019-09-30 2023-11-28 Wuhu Midea Kitchen And Bath Appliances Mfg. Co., Ltd. Heating water heater and control method thereof, and computer-readable storage medium

Similar Documents

Publication Publication Date Title
JP5084768B2 (en) Hot water system
KR101467095B1 (en) Hot water supply system
US10824178B2 (en) Heating and hot water supply apparatus and control method thereof
KR101467088B1 (en) Storage type hot water supply device
KR20150092160A (en) Heat pump heat supply system
JP6129033B2 (en) Hot water system
JP2009192107A (en) Hot water supply device
JP6628643B2 (en) Hot water supply system
JP5836794B2 (en) Hot water storage system
KR101586165B1 (en) Hot water supply system
JP6129032B2 (en) Hot water system
KR20130118793A (en) Heat pump heat source system
KR101661844B1 (en) Hot water supply system
KR101579399B1 (en) Hot water supply system
KR101797646B1 (en) Hot water proportional control device to the season of the instantaneous boiler and method thereof
JP2006349273A (en) Water heater
KR20150092159A (en) Heat pump heat supply system
JP5833062B2 (en) Hot water system
JP2012013335A (en) Hot water supply system
JP6129031B2 (en) Hot water system
JP2019132463A (en) Instantaneous hot water tapping device
KR101648666B1 (en) Hot water supply system
JP6998778B2 (en) Immediate hot water discharge device
JPH11173671A (en) Water heater
KR101621189B1 (en) Hot water supply system

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee