KR101387702B1 - Structure for connects beam on the coulmn of korena-style house and construction methode for there of - Google Patents

Structure for connects beam on the coulmn of korena-style house and construction methode for there of Download PDF

Info

Publication number
KR101387702B1
KR101387702B1 KR1020130139018A KR20130139018A KR101387702B1 KR 101387702 B1 KR101387702 B1 KR 101387702B1 KR 1020130139018 A KR1020130139018 A KR 1020130139018A KR 20130139018 A KR20130139018 A KR 20130139018A KR 101387702 B1 KR101387702 B1 KR 101387702B1
Authority
KR
South Korea
Prior art keywords
fixing
connection
pillar
column
hanok
Prior art date
Application number
KR1020130139018A
Other languages
Korean (ko)
Inventor
김승호
Original Assignee
(주) 툇마루
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주) 툇마루 filed Critical (주) 툇마루
Priority to KR1020130139018A priority Critical patent/KR101387702B1/en
Application granted granted Critical
Publication of KR101387702B1 publication Critical patent/KR101387702B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/19Three-dimensional framework structures
    • E04B1/1903Connecting nodes specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/388Separate connecting elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/58Connections for building structures in general of bar-shaped building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/388Separate connecting elements
    • E04B2001/389Brackets

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The present invention relates to a structure for connecting a beam to a column in a Korea-style house and a construction method for the same, capable of improving user reliability on a product by obtaining structural safety. The present invention also improves the appearance by finishing a square pipe of the column, an upper beam, and a center beam with a finishing member and reduces construction costs by improving work efficiency with reduction of processes by fixing the upper beam, the lower beam, and the center beam to a foundation column with a fixing member such as a bolt and a nut and enabling accurate construction.

Description

한옥의 기둥에 보를 연결하는 구조 및 이의 시공방법{Structure for connects beam on the coulmn of Korena-style house and construction methode for there of}Structure for connects beam on the coulmn of Korena-style house and construction methode for there of}

본 발명은 한옥의 기둥에 보를 연결하는 구조에 관한 것으로, 보다 상세하게는, 상부보와 대종보 및 중간보를 기초기둥에 볼트/너트의 고정부재로 고정하여 정밀시공이 가능하도록 하는 한옥의 기둥에 보를 연결하는 구조 및 이의 시공방법에 관한 것이다.
The present invention relates to a structure that connects the beam to the pillar of the hanok, and more particularly, to the pillar of the hanok to secure the upper beam, Daejongbo and intermediate beam to the foundation column by fixing the bolt / nut fixing member It relates to a structure for connecting the beam and its construction method.

일반적으로 한옥이란 우리나라의 오랜 전통양식에 의하여 시공된 건축물을 말하며, 이의 건축과정은 먼저 건축하고자 하는 터에 기초공사를 실시하고, 기둥을 세울 자리에 주초석을 놓고, 주초석 위에 기둥을 세운 후, 기둥 위에 대들보와 중간보를 가로 세로방향으로 교차시켜 공간을 형성하고, 공간의 안쪽 바닥에 온돌을 구비하는 방바닥을 형성하고, 기둥과 기둥 사이에는 흙벽돌 또는 창문 등으로 막아 방과 마루를 구획하며, 서까래 또는 부연 등 위에 기와를 얹어 지붕을 형성하게 된다.In general, Hanok refers to a building constructed by Korea's long-standing traditional style. The construction process is based on the foundation to be built first, the foundation stone on the place where the pillar is to be built, the pillar on the foundation stone, and then the pillar. Cross the girders and the intermediate beams horizontally and vertically to form a space, and form a floor with ondol on the inner bottom of the space, and divide the room and the floor by blocking it with a brick or window between pillars and columns, Roofs are formed by placing roof tiles on the parapets.

상기 한옥의 생활이 다소 불편하다는 인식 때문에 일반 수요자들에게 외면 되었으나, 개성을 존중하고 환경친화적인 건물을 선호하는 수요자들이 늘어나면서 최근에는 크게 각광받고 있는 실정이며, 한옥에 대한 수요도 날로 증대되고 있다.It was neglected by general consumers because of the perceived inconvenience of Hanok's life, but the demand for hanok is increasing day by day as the number of consumers who respect individuality and prefer environmentally friendly buildings increases. .

그러나 한옥의 전통적 건축방식은 대목장 또는 도편수라는 소수의 전문가에게만 전해지고 있고, 목조건축의 최고 장인이 직접 설계, 자재선정, 부재 가공 및 조립 등의 모든 것을 결정하고 각 부재를 일일이 수작업으로 가공한 후 조립하는 방법을 따라 건축되므로 작업공정이 매우 복잡하고 공사기간이 길다는 단점이 있다.However, the traditional building method of hanok is passed down only to a few experts, such as large ranches or swordsmen, and the master craftsmen in wood building decide all things such as designing, selecting materials, processing and assembling parts, and processing each member by hand. As it is built according to the method, the work process is very complicated and the construction period is long.

또한, 상기 한옥의 건축을 용이하게 하기 위하여 대한민국 공개특허공보 제10-2005-0064276호로 소경재를 이용한 표준화 목조건축 구법이 공개된 바 있다.In addition, in order to facilitate the construction of the hanok has been published in the Republic of Korea Patent Publication No. 10-2005-0064276 standardized wooden construction method using a small hardwood.

선 공개된 특허는, 인접기둥과 인접기둥의 상부를 수평으로 지지하는 보 기능의 창방에 암,수장부를 형성하여 결합하는 구성이나, 각 부재에 암,수장부를 형성하는 과정이 복잡하여 공사기간이 늘어남은 물론 각 부재간의 복잡한 결합관계로 인하여 수리기간 및 수리비용이 많이 드는 문제점이 있었고, 보 기능을 하는 창방이 하중에 의해 발생하는 굽힘 모멘트에 취약한 단점이 있어 건축 후, 비틀림이나 갈라지는 현상으로 구조적 안전성이 취약한 문제점이 있었다.
The previously disclosed patent is a construction in which the arm and the neck are formed at the window of the beam function that horizontally supports the adjacent column and the upper part of the adjacent column, and the process of forming the arm and the neck is complicated. In addition to the increased period, there is a problem that repair period and repair cost are high due to the complicated coupling relationship between each member. As a result, structural safety was weak.

이에 상술한 바와 같은 종래의 제반 문제점을 감안하여 이루어진 것으로, 본 발명의 목적은, 기둥과 상부보 및 중간보의 각관을 볼트/너트의 고정부재로 고정하여 정밀시공이 가능함은 물론 작업공정의 단축으로 작업능률을 향상시킬 수 있는 한옥의 기둥에 보를 연결하는 구조 및 이의 시공방법을 제공함에 있다.Thus, in view of the above-mentioned conventional problems, the object of the present invention is to fix the square tube of the column and the upper beams and intermediate beams with the fixing member of the bolt / nut is possible to precise construction as well as shortening the work process The purpose is to provide a structure for connecting beams to the pillars of hanok that can improve the work efficiency and its construction method.

또한, 본 발명의 다른 목적은, 볼트/너트의 고정부재가 기둥과 상부보 및 중간보 외부로 돌출되지 않으면서 기둥과 상부보 및 중간보의 각관을 마감부재로 마감하여 미관을 미려하게 함은 물론 구조적 안전성을 확보할 수 있는 한옥의 기둥에 보를 연결하는 구조 및 이의 시공방법을 제공함에 있다.
In addition, another object of the present invention, while the fixing member of the bolt / nut does not protrude to the outside of the column and the upper beams and intermediate beams to finish the crown of the pillars and the upper beams and intermediate beams as a finishing member to aesthetically beautiful Of course, the present invention provides a structure for connecting beams to the pillars of hanok that can secure structural safety, and a construction method thereof.

본 발명 한옥의 기둥에 보를 연결하는 구조는,The structure connecting the beam to the pillar of the hanok of the present invention,

한옥을 받쳐 지지하는 기초기둥과;A basic pillar supporting the hanok;

상기 기초기둥 상단부에 설치되어 상부보 및 대종보를 연결고정하는 연결기둥과;A connection pillar installed at an upper end of the foundation pillar to connect and fix the upper beam and the large beam;

상기 연결기둥과 상부보 및 대종보를 연결고정하는 연결고정부를 포함하여 구성되는 것을 특징으로 하는 것이다.
It characterized in that it comprises a connection fixing portion for fixing the connection column and the upper beam and the large beam.

또한, 본 발명 한옥의 기둥에 보를 연결하는 시공방법은,In addition, the construction method of connecting the beam to the pillar of the hanok of the present invention,

한옥을 받쳐 지지하는 기초기둥을 형성하여 지면에 설치하는 단계와;Forming a foundation pillar supporting and supporting the hanok and installing it on the ground;

상기 기초기둥의 상단부에 상부보 및 대종보를 고정시키도록 제1판체의 돌부를 제2판체의 홈부에 결합하면서 제1,2판체의 단부를 용접하여 고정한 연결기둥을 설치하는 단계와;Installing a connecting column for welding the end portions of the first and second plate bodies by coupling the protrusions of the first plate body to the grooves of the second plate body to fix the upper beam and the large beam to the upper end of the base pillar;

상기 연결기둥에 제1연결고정부의 간격유지부재를 밀착하는 단계와;Bringing the gap maintaining member of the first connection fixing part into close contact with the connection column;

상기 간격유지부재와 연결기둥을 제1고정부재로 고정하는 단계와;Fixing the gap retaining member and the connection column with a first fixing member;

상기 상부보에 구비된 각관으로 수용부재를 고정시킨 후, 상기 수용부재가 제1고정부재를 수용하여 간격유지부재에 밀착되도록 하는 단계와;Fixing the receiving member with a square tube provided on the upper beam, and receiving the first fixing member to be in close contact with the gap maintaining member;

상기 연결기둥과 수용부재를 제2고정부재로 고정하는 단계를 포함하여 이루어지는 것을 특징으로 하는 것이다.
It characterized in that it comprises a step of fixing the connecting column and the receiving member with a second fixing member.

본 발명에 의하면, 기둥과 상부보 및 중간보의 각관을 볼트/너트의 고정부재로 고정하여 정밀시공이 가능함은 물론 작업공정의 단축으로 작업능률을 향상시켜 시공비용을 절감할 수 있는 이점을 가질 수 있는 것이다.According to the present invention, it is possible to precisely install the pillars, the upper beams, and the intermediate beams by fixing members of bolts / nuts, and to improve the work efficiency by shortening the work process, thereby reducing the construction cost. It can be.

또한, 본 발명에 의하면, 볼트/너트의 고정부재가 기둥과 상부보 및 중간보 외부로 돌출되지 않으면서 기둥과 상부보 및 중간보의 각관을 마감부재로 마감하여 미관을 미려하게 함은 물론 구조적 안전성을 확보하여 사용자로 하여금 제품에 대한 신뢰성을 향상시킬 수 있는 이점을 가질 수 있는 것이다.
In addition, according to the present invention, while the fixing member of the bolt / nut does not protrude to the outside of the column and the upper beams and intermediate beams to finish the corners of the pillars and the upper beams and intermediate beams as a finishing member to make the beauty of beauty as well as structural By ensuring safety, users can have the advantage of improving the reliability of the product.

도 1은 본 발명의 사시도
도 2는 본 발명의 분리사시도
도 3은 본 발명의 단면도
도 4는 본 발명 연결기둥의 분리사시도
도 5 내지 도 7은 본 발명의 확대단면도
BRIEF DESCRIPTION OF THE DRAWINGS FIG.
2 is an exploded perspective view
Figure 3 is a cross-
Figure 4 is an exploded perspective view of the connection column of the present invention
5 to 7 is an enlarged cross-sectional view of the present invention

이하, 첨부된 도면에 의거하여 본 발명을 상세히 설명한다. 도 1은 본 발명의 사시도이고, 도 2는 본 발명의 분리사시도이며, 도 3은 본 발명의 단면도이다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings. 1 is a perspective view of the present invention, Figure 2 is an exploded perspective view of the present invention, Figure 3 is a cross-sectional view of the present invention.

본 발명 한옥 기둥과 보의 연결구조(100)는, 한옥을 받쳐 지지하는 기초기둥(110)이 구성되고, 상기 기초기둥(110) 상단부에 설치되어 상부보(10) 및 대종보(10')를 연결고정하는 연결기둥(120)이 구성되며, 상기 연결기둥(120)과 상부보(10) 및 대종보(10')를 연결고정하는 연결고정부(130)를 포함하여 구성되는 것으로, 이를 좀더 구체적으로 설명하면 다음과 같다.The connection structure 100 of the hanok pillar and the beam of the present invention, the foundation pillar 110 supporting the hanok is configured, the foundation pillar 110 is installed on the upper end of the upper beam 10 and the Daejongbo 10 ' It is configured to include a connection column 120 for fixing the connection, and comprises a connection fixing part 130 for fixing the connection column 120 and the upper beam 10 and the large bell beam (10 '), More specifically described as follows.

상기 연결기둥(120)은, 도 4에 도시된 바와 같이, 양측에 돌부(121')가 형성된 한 쌍의 제1판체(121)가 구비되고, 상기 돌부(121')가 결합되는 홈부(122')가 형성된 한 쌍의 제2판체(122)가 구비되며, 상기 돌부(121')가 홈부(122')에 결합된 제1,2판체(121)(122)의 단부를 용접하여 고정한다.As shown in FIG. 4, the connection column 120 is provided with a pair of first plate bodies 121 having protrusions 121 'formed at both sides thereof, and a groove portion 122 to which the protrusions 121' are coupled. ') Is provided with a pair of second plate body 122, the protrusion 121' is welded and fixed to the end of the first and second plate body 121, 122 coupled to the groove portion 122 '. .

상기 연결고정부(130)는, 도 5 내지 도 6에 도시된 바와 같이, 상기 연결기둥(120)에 밀착되는 간격유지부재(131a)가 구비되고, 상기 간격유지부재(131a)를 연결기둥(120)에 고정하는 제1고정부재(131b)가 구비되며, 상기 제1고정부재(131b)를 수용하면서 간격유지부재(131a)에 밀착되도록 상부보(10)의 각관(11)에 고정되는 수용부재(131c)가 구비되고, 상기 수용부재(131c)와 연결기둥(120)을 고정하는 제2고정부재(131d)가 구비된 제1연결고정부(131a)가 구성되고, 상기 연결기둥(120)에 밀착되는 간격유지부재(132a)가 구비되고, 상기 간격유지부재(132a)와 기초기둥(110)에 밀착되도록 대종보(10')의 프레임(11')에 고정되는 연결판재(132b)가 구비되며, 상기 연결판재(132b)와 연결기둥(120)을 간격유지부재(132a) 및 기초기둥(110)을 통해 고정하는 제3고정부재(132c)가 구비된 제2연결고정부(131b)를 포함하여 구비된다.The connection fixing part 130, as shown in Figures 5 to 6, is provided with a gap holding member 131a in close contact with the connection pillar 120, the gap holding member 131a is connected to the pillar ( The first fixing member 131b is fixed to the 120, the accommodation is fixed to the square tube 11 of the upper beam 10 to be in close contact with the space maintaining member (131a) while receiving the first fixing member (131b) A first connection fixing part 131a having a member 131c and having a second fixing member 131d for fixing the receiving member 131c and the connecting pillar 120 is configured, and the connecting pillar 120 is provided. A connection plate member 132b fixed to the frame 11 'of the Daejongbo 10' to be in close contact with the gap maintaining member 132a and the base pillar 110. Is provided, the second connection fixing having a third fixing member 132c for fixing the connecting plate member 132b and the connecting pillar 120 through the gap maintaining member 132a and the base pillar 110. It is provided, including (131b).

또한, 상기 상부보(10) 하부의 기초기둥(110)에 중간보(20)를 연결하는 중간연결고정부(140)를 더 포함하여 구성되며, 상기 중간연결고정부(140)는, 도 7에 도시된 바와 같이, 상기 기초기둥(110)에 중간연결부재(142)가 설치되도록 절단되어 관통된 설치공(141)이 구비되고, 상기 설치공(141)에 장착고정되는 중간연결부재(142)가 구비되며, 상기 중간연결부재(142)에 밀착되도록 중간보(20)의 각관(21)에 고정되는 수용부재(143)가 구비되고, 상기 중간보(20) 각관(21)에 형성된 작업공간(22)을 통해 수용부재(143)와 중간연결부재(142)를 고정하는 연결고정부재(144)를 포함하여 구비된다.
In addition, the intermediate beam fixing unit 140 for connecting the intermediate beam 20 to the base pillar 110 of the lower upper beam 10 is configured to further include, the intermediate connection fixing unit 140, Figure 7 As shown in, the intermediate pillar 141 is provided to be cut through the intermediate connection member 142 is installed to be installed in the base pillar 110, the intermediate connection member 142 is fixed to the mounting hole 141 ) Is provided, the receiving member 143 is fixed to the square tube 21 of the intermediate beam 20 so as to be in close contact with the intermediate connecting member 142, the work formed on the square tube 21 of the intermediate beam 20 It includes a connection fixing member 144 for fixing the receiving member 143 and the intermediate connecting member 142 through the space 22.

다음은 상기와 같이 구성된 본 발명의 시공과정을 설명한다.Hereinafter, a construction process of the present invention will be described.

먼저, 돌부(121')가 형성된 제1판체(121)를 홈부(122')가 형성된 제2판체(122)에 동일선상으로 위치시킨 상태에서 상기 제1판체(121)의 돌부(121')를 제2판체(122)의 홈부(122')에 결합하는 방법을 반복하여 사각기둥을 형성하고, 상기 제1,2판체(121)(122)의 단부 즉, 모서리를 용접고정하여 연결기둥(120)을 형성한다.First, the protrusion 121 'of the first plate body 121' is formed in the same line as the first plate body 121 on which the protrusion 121 'is formed on the second plate body 122 on which the groove portion 122' is formed. To form a square pillar by repeating the method of coupling the groove 122 'of the second plate body 122, and fixing the end portions, that is, the edges, of the first and second plate bodies 121 and 122 to the connecting column ( 120).

여기서, 상기 돌부(121')와 홈부(122')는, 제1,2판체(121)(122)에 한 쌍으로 대향되게 각각 형성되거나 판체에 돌부와 홈부가 동일선상으로 형성될 수도 있는 것이다.Here, the protrusions 121 'and the grooves 122' may be formed to face the first and second plate bodies 121 and 122 in pairs, or the protrusions and the grooves may be formed in the same line on the plate body. .

상기의 과정으로 형성된 연결기둥(120)은, 한옥을 받쳐 지지하는 기초기둥(110) 상단부에 결합하여 설치하는데, 상기 기초기둥(110)과 연결기둥(120)은 볼트/너트로 체결하여 고정하는 것이 바람직하다.The connection column 120 formed by the above process is installed to be coupled to the upper end of the base pillar 110 supporting the hanok, the base pillar 110 and the connection column 120 is fixed by fastening with a bolt / nut It is preferable.

또한, 상기 연결기둥(120)의 대향하는 제2판체(122)에 상부보(10)를 설치하기 위해서는, 상기 제2판체(122)에 제1연결고정부(131)의 간격유지부재(131a)를 밀착시킨 상태에서 상기 간격유지부재(131a)와 제2판체(122)를 제1고정부재(131a)로 고정시키는데, 상기 간격유지부재(131a)를 보강하기 위해 보강부재(131a')를 더 밀착시킨 후, 제1고정부재(131b)로 고정시킬 수도 있는 것이다.In addition, in order to install the upper beam 10 on the second plate body 122 of the connecting column 120, the space maintaining member 131a of the first connection fixing portion 131 to the second plate body 122 ) To fix the gap holding member 131a and the second plate body 122 with the first fixing member 131a in a state of being in close contact with each other, and to reinforce the gap holding member 131a. After further contacting, the first fixing member 131b may be fixed.

상기 간격유지부재(131a)가 제2판체(122)에 제1고정부재(131b)로 고정되면, 상기 제1고정부재(131b) 및 보강부재(131a')를 수용하는 수용부재(131c)를 상부보(10)의 각관(11)에 결합하여 용접으로 고정시킨 상태에서 상기 각관(11)을 이동시켜 수용부재(131c)가 제1고정부재(131b) 및 보강부재(131a')를 수용하면서 간격유지부재(131a)에 밀착되도록 한다.When the gap holding member 131a is fixed to the second plate body 122 as the first fixing member 131b, an accommodation member 131c for accommodating the first fixing member 131b and the reinforcing member 131a 'is provided. The receiving member 131c receives the first fixing member 131b and the reinforcing member 131a 'by moving the square tube 11 while being coupled to the square tube 11 of the upper beam 10 and fixed by welding. To be in close contact with the gap holding member (131a).

상기 수용부재(131c)가 간격유지부재(131a)에 밀착되면, 상기 연결기둥(120) 내부에서 제2고정부재(131d)로 연결기둥(120)과 수용부재(131c)를 고정시키는데, 상기 제1,2고정부재(131b)(131d)는 볼트와 너트를 포함하는 구성이며, 상기 너트는 연결기둥(120) 내면 및 수용부재(131c) 일면에 용접으로 고정되는 것이 바람직하나, 상기 제1,2고정부재(131b)(131d)가 체결되도록 연결기둥(120) 및 수용부재(131c)에 탭가공하여 체결고정할 수도 있는 것이다.When the receiving member 131c is in close contact with the gap maintaining member 131a, the connecting pillar 120 and the receiving member 131c are fixed to the second fixing member 131d inside the connecting pillar 120. The first and second fixing members 131b and 131d may include a bolt and a nut, and the nut may be fixed by welding to an inner surface of the connecting column 120 and one surface of the receiving member 131c. 2 fixing members 131b and 131d may be fastened and fixed by tapping the connection column 120 and the receiving member 131c to be fastened.

또한, 상기 연결기둥(120)의 제1판체(121)에 대종보(10')를 설치하기 위해서는, 상기 제1판체(121)에 제2연결고정부(132)의 간격유지부재(132a)를 밀착시킨 후, 대종보(10')의 프레임(11')에 연결판재(132b)를 용접으로 고정시킨다.In addition, in order to install the large beam 10 'on the first plate body 121 of the connecting column 120, the space maintaining member 132a of the second connection fixing portion 132 on the first plate body 121. After closely contacting, the connecting plate member 132b is fixed to the frame 11 'of the Daejongbo 10' by welding.

상기 연결판재(132b)가 고정된 프레임(11')을 이동시켜 간격유지부재(132a) 및 연결기둥(120)에 밀착되도록 한 후, 상기 연결기둥(120) 내부에서 제3고정부재(132c)로 연결기둥(120)과 연결판재(132b)를 고정시키는데, 상기 제3고정부재(132c)는 연결기둥(120)과 간격유지부재(132a) 및 연결판재(132b)를 고정시켜야 하고, 상기 연결기둥(120)과 기초기둥(110) 및 연결판재(132b)를 고정시켜야 한다.The connecting plate member 132b is moved to fix the fixed frame 11 'to the space maintaining member 132a and the connecting pillar 120, and then the third fixing member 132c in the connecting pillar 120. The connection column 120 and the connection plate member 132b is fixed, and the third fixing member 132c has to fix the connection column 120, the space keeping member 132a and the connection plate member 132b, and the connection The pillar 120 and the base pillar 110 and the connecting plate 132b should be fixed.

여기서 상기 제3고정부재(132c)는 볼트와 너트를 포함하는 구성이며, 상기 너트는 연결판재(132b) 내면에 용접으로 고정되는 것이 바람직하나, 상기 제3고정부재(132c)가 체결되도록 연결판재(132b)에 탭가공하여 체결고정할 수도 있는 것이다.Here, the third fixing member 132c is a configuration including a bolt and a nut, the nut is preferably fixed to the inner surface of the connecting plate member 132b by welding, the connecting plate member so that the third fixing member 132c is fastened. It is also possible to fasten the fastening by tapping (132b).

또한, 상기 상부보(10) 하부의 연결기둥(120)에 중간보(20)를 설치하기 위해서는, 상부보(10) 하부의 연결기둥(120)을 절단하여 중간연결고정부(140)의 설치공(141)을 형성하는데, 상기 설치공(141)은 중간연결부재(142)가 장착되는 크기로 절단함이 바람직하다.In addition, in order to install the intermediate beam 20 in the connection column 120 below the upper beam 10, the installation of the intermediate connection fixing part 140 by cutting the connection column 120 of the lower upper beam 10. Forming the ball 141, the installation hole 141 is preferably cut to the size that the intermediate connecting member 142 is mounted.

상기와 같이 형성된 설치공(141)에 적어도 1개 이상 중간연결부재(142)를 장착하여 용접으로 고정시키고, 수용부재(143)를 중간보(20)의 각관(21)에 결합하여 용접으로 고정시킨 상태에서 상기 각관(21)을 이동시켜 수용부재(143) 및 각관(21)이 중간연결부재(142)에 밀착되도록 한 후, 상기 각관(21)에 형성된 작업공간(22)을 통해 수용부재(143)와 중간연결부재(142)를 연결고정부재(144)로 고정시키면서 연결구조(100)가 완성되는 것이다.At least one intermediate connection member 142 is mounted on the installation hole 141 formed as described above and fixed by welding, and the receiving member 143 is coupled to the square tube 21 of the intermediate beam 20 to be fixed by welding. In order to move the square tube 21 in such a state that the receiving member 143 and the tube 21 is in close contact with the intermediate connecting member 142, the receiving member through the working space 22 formed in the square tube 21 The connection structure 100 is completed while fixing the 143 and the intermediate connection member 142 to the connection fixing member 144.

이때, 상기 연결고정부재(144)는 볼트와 너트를 포함하며, 상기 너트는 중간연결부재(142) 내면에 용접으로 고정되는 것이 바람직하나, 상기 연결고정부재(144)가 체결되도록 중간연결부재(142)에 탭가공할 수도 있는 것이다.At this time, the connection fixing member 144 includes a bolt and a nut, the nut is preferably fixed to the inner surface of the intermediate connecting member 142 by welding, the intermediate connecting member (144) so that the connection fixing member 144 is fastened 142 may be tapped.

상기의 과정으로 완성된 연결구조(100)의 기초기둥(110)에 상부보(10)의 각관(11)과 대종보(10')의 프레임(11') 및 중간보(20)의 각관(21)이 고정되면, 상기 각관(11)(21)과 프레임(11') 및 기초기둥(110)을 통상의 방법으로 마감부재(30)로 마감하여 기둥 및 보를 형성할 수 있는 것이다.Square tube 11 of the upper beam 10 and the frame 11 'and the intermediate beam 20 of the intermediate beam 20 on the base column 110 of the connection structure 100 completed by the above process ( When the 21 is fixed, it is possible to form the pillars and beams by finishing the corners 11, 21, the frame 11 'and the base pillar 110 with the finishing member 30 in a conventional manner.

이상과 같이 본 발명은, 비록 한정된 실시예와 도면에 의해 설명되었으나, 본 명세서 및 청구범위에 사용된 용어나 단어는 통상적이거나 사전적인 의미로 한정되어 해석되어서는 아니되며, 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다. 따라서, 본 명세서에 기재된 실시예와 도면에 도시된 구성은 본 발명의 일실시예에 불과할 뿐이고, 본 발명의 기술적 사상을 모두 대변하는 것은 아니므로, 본 발명의 청구범위를 벗어나지 않는 한도 내에서 다양한 균등물과 변형예들이 있을 수 있음을 이해하여야 한다.
While the present invention has been described with reference to the particular embodiments and drawings, it is to be understood that the phraseology and terminology employed herein are for the purpose of description and should not be regarded as limiting in any ordinary or prejudicial sense. It must be interpreted in terms of meaning and concept. Therefore, the embodiments described in the present specification and the configurations shown in the drawings are only examples of the present invention, and not all of the technical ideas of the present invention are described. Therefore, It is to be understood that equivalents and modifications are possible.

100: 기둥과 보의 연결구조 110: 기초기둥
120: 연결기둥 130: 연결고정부
140: 중간연결고정부
100: connection structure of column and beam 110: foundation pillar
120: connection column 130: connection fixing
140: Interim fixed government

Claims (8)

한옥을 받쳐 지지하는 기초기둥과;
상기 기초기둥 상단부에 설치되어 상부보 및 대종보를 연결고정하는 연결기둥과;
상기 연결기둥과 상부보 및 대종보를 연결고정하는 연결고정부와;
상기 상부보 하부의 기초기둥에 중간보를 연결하는 중간연결고정부를 포함하여 구성되는 것을 특징으로 하는 한옥의 기둥에 보를 연결하는 구조.
A basic pillar supporting the hanok;
A connection pillar installed at an upper end of the foundation pillar to connect and fix the upper beam and the large beam;
A connection fixing part for connecting and fixing the connection column and the upper beam and the large beam;
The structure of connecting the beam to the pillar of the hanok, characterized in that it comprises an intermediate connection fixing for connecting the intermediate beam to the base column of the upper beam lower.
청구항 1에 있어서, 상기 연결기둥은,
일측 또는 양측에 돌부가 형성된 제1판체와;
상기 제1판체의 돌부가 결합되도록 일측 또는 양측에 홈부가 형성된 제2판체와;
돌부가 홈부에 결합된 제1,2판체를 용접하여 고정하는 것을 특징으로 하는 한옥의 기둥에 보를 연결하는 구조.
The method according to claim 1, wherein the connecting column,
A first plate body having protrusions formed on one or both sides thereof;
A second plate body having grooves formed on one side or both sides thereof such that the protrusions of the first plate body are coupled;
A structure for connecting the beam to the pillar of the hanok, characterized in that the protrusion is fixed by welding the first and second plate body coupled to the groove.
청구항 1에 있어서, 상기 연결고정부는,
상기 연결기둥에 밀착되는 간격유지부재가 구비되고, 상기 간격유지부재를 연결기둥에 고정하는 제1고정부재가 구비되며, 상기 제1고정부재를 수용하면서 간격유지부재에 밀착되도록 상부보의 각관에 고정되는 수용부재가 구비되고, 상기 수용부재와 연결기둥을 고정하는 제2고정부재가 구비된 제1연결고정부와;
상기 연결기둥에 밀착되는 간격유지부재가 구비되고, 상기 간격유지부재와 기초기둥에 밀착되도록 대종보의 프레임에 고정되는 연결판재가 구비되며, 상기 연결판재와 연결기둥을 간격유지부재 및 기초기둥을 통해 고정하는 제3고정부재가 구비된 제2연결고정부를 포함하여 구성되는 것을 특징으로 하는 한옥의 기둥에 보를 연결하는 구조.
The method according to claim 1, The connection fixing portion,
A spacing member is provided to be in close contact with the connecting pillar, and a first fixing member is provided to fix the spacing member to the connecting pillar, and is provided at each tube of the upper beam to be in close contact with the spacing member while receiving the first fixing member. A first connection fixing part provided with a receiving member to be fixed and having a second fixing member for fixing the receiving member and the connection column;
A gap maintaining member is provided to be in close contact with the connection pillar, and a connection plate member fixed to the frame of Daejongbo is provided to be in close contact with the gap maintenance member and the foundation pillar, and the gap maintenance member and the foundation pillar are connected to the connection plate member and the connection pillar. A structure for connecting the beam to the pillar of the hanok, characterized in that it comprises a second connection fixing portion provided with a third fixing member fixed through.
삭제delete 청구항 1에 있어서, 상기 중간연결고정부는,
상기 기초기둥에 중간연결부재가 설치되도록 절단되어 관통된 설치공과;
상기 설치공에 장착고정되는 중간연결부재와;
상기 중간연결부재에 밀착되도록 중간보의 각관에 고정되는 수용부재와;
상기 중간보 각관에 형성된 작업공간을 통해 수용부재와 중간연결부재를 고정하는 연결고정부재를 포함하여 구비되는 것을 특징으로 하는 한옥의 기둥에 보를 연결하는 구조.
The method according to claim 1, wherein the intermediate connection fixing unit,
An installation hole cut and penetrated to install an intermediate connection member on the foundation pillar;
An intermediate connection member fixed to the installation hole;
A receiving member fixed to each tube of the intermediate beam to be in close contact with the intermediate connecting member;
A structure for connecting the beam to the pillar of the hanok characterized in that it comprises a connection fixing member for fixing the receiving member and the intermediate connection member through the working space formed in the intermediate beam pipe.
한옥을 받쳐 지지하는 기초기둥을 형성하여 지면에 설치하는 단계와;
상기 기초기둥의 상단부에 상부보 및 대종보를 고정시키도록 제1판체의 돌부를 제2판체의 홈부에 결합하면서 제1,2판체의 단부를 용접하여 고정한 연결기둥을 설치하는 단계와;
상기 연결기둥에 제1연결고정부의 간격유지부재를 밀착하는 단계와;
상기 간격유지부재와 연결기둥을 제1고정부재로 고정하는 단계와;
상기 상부보에 구비된 각관으로 수용부재를 고정시킨 후, 상기 수용부재가 제1고정부재를 수용하여 간격유지부재에 밀착되도록 하는 단계와;
상기 연결기둥과 수용부재를 제2고정부재로 고정하는 단계를 포함하여 이루어지는 것을 특징으로 하는 한옥의 기둥에 보를 연결하는 시공방법.
Forming a foundation pillar supporting and supporting the hanok and installing it on the ground;
Installing a connecting column for welding the end portions of the first and second plate bodies by coupling the protrusions of the first plate body to the grooves of the second plate body to fix the upper beam and the large beam to the upper end of the base pillar;
Bringing the gap maintaining member of the first connection fixing part into close contact with the connection column;
Fixing the gap retaining member and the connection column with a first fixing member;
Fixing the receiving member with a square tube provided on the upper beam, and receiving the first fixing member to be in close contact with the gap maintaining member;
Construction method for connecting the beam to the pillar of the hanok characterized in that it comprises the step of fixing the connecting column and the receiving member with a second fixing member.
청구항 6에 있어서,
상기 연결기둥에 제2연결고정부의 간격유지부재를 밀착하는 단계와;
상기 대종보에 구비된 프레임에 연결판재를 고정시켜 간격유지부재 및 연결기둥에 밀착하는 단계와;
상기 연결판재와 연결기둥을 간격유지부재 및 기초기둥을 통해 제3고정부재로 고정하는 단계를 더 포함하여 이루어지는 것을 특징으로 하는 한옥의 기둥에 보를 연결하는 방법.
The method of claim 6,
Bringing the gap maintaining member of the second connection fixing part into close contact with the connection column;
Fixing the connecting plate to the frame provided in the Daejongbo to closely adhere to the gap maintaining member and the connecting pillar;
And connecting the beams to the pillars of the hanok, further comprising fixing the connecting plate and the connecting column to the third fixing member through the gap maintaining member and the base pillar.
청구항 6에 있어서,
상기 상부보 하부의 기초기둥을 절단하여 중간보를 설치하는 설치공을 형성하는 단계와;
상기 설치공에 중간연결부재를 장착고정하는 단계와;
상기 중간보에 구비된 각관으로 수용부재를 고정시킨 후, 상기 중간연결부재에 밀착시키는 단계와;
상기 중간보에 형성된 작업공간을 통해 상기 수용부재와 중간연결부재를 연결고정부재로 고정하는 단계를 더 포함하여 이루어지는 것을 특징으로 하는 한옥의 기둥에 보를 연결하는 시공방법.
The method of claim 6,
Cutting the base column of the upper beam lower to form an installation hole for installing an intermediate beam;
Mounting and fixing an intermediate connecting member to the installation hole;
Fixing the receiving member with a square tube provided in the intermediate beam, and closely contacting the intermediate connecting member;
Construction method for connecting the beam to the pillar of the hanok, characterized in that further comprising the step of fixing the receiving member and the intermediate connecting member with a connection fixing member through the working space formed in the intermediate beam.
KR1020130139018A 2013-11-15 2013-11-15 Structure for connects beam on the coulmn of korena-style house and construction methode for there of KR101387702B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020130139018A KR101387702B1 (en) 2013-11-15 2013-11-15 Structure for connects beam on the coulmn of korena-style house and construction methode for there of

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020130139018A KR101387702B1 (en) 2013-11-15 2013-11-15 Structure for connects beam on the coulmn of korena-style house and construction methode for there of

Publications (1)

Publication Number Publication Date
KR101387702B1 true KR101387702B1 (en) 2014-04-22

Family

ID=50658327

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020130139018A KR101387702B1 (en) 2013-11-15 2013-11-15 Structure for connects beam on the coulmn of korena-style house and construction methode for there of

Country Status (1)

Country Link
KR (1) KR101387702B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101586385B1 (en) * 2014-10-13 2016-01-20 동서 피, 씨, 씨 주식회사 Coupled PC Composite Girder and Construction Method thereof
CN113202189A (en) * 2021-05-10 2021-08-03 江苏华木空间结构有限公司 Steel construction assembly type building subassembly and steel construction assembly type building

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100903988B1 (en) * 2001-02-15 2009-06-25 이대준 Tubular structure and modular building assembly using the same
KR20100106431A (en) * 2007-12-28 2010-10-01 가부시기가이샤 우찌다요우고우 Joining device

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100903988B1 (en) * 2001-02-15 2009-06-25 이대준 Tubular structure and modular building assembly using the same
KR20100106431A (en) * 2007-12-28 2010-10-01 가부시기가이샤 우찌다요우고우 Joining device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101586385B1 (en) * 2014-10-13 2016-01-20 동서 피, 씨, 씨 주식회사 Coupled PC Composite Girder and Construction Method thereof
CN113202189A (en) * 2021-05-10 2021-08-03 江苏华木空间结构有限公司 Steel construction assembly type building subassembly and steel construction assembly type building
CN113202189B (en) * 2021-05-10 2022-05-31 江苏华木空间结构有限公司 Steel construction assembly type building subassembly and steel construction assembly type building

Similar Documents

Publication Publication Date Title
KR101006225B1 (en) Modern korean-style house having steel structure
CN103195214B (en) Wood roof cornice decking and concrete composite structure in archaized buildings and construction method thereof
CN203769225U (en) Aluminum alloy grid system
KR20110088812A (en) Curtain wall system
JP5690644B2 (en) Simple building
KR101387702B1 (en) Structure for connects beam on the coulmn of korena-style house and construction methode for there of
JP2010077781A (en) Attaching structure for heat-insulating panel, and building
KR101310889B1 (en) Connection structure of the building panel
CN102817427B (en) Component type curtain wall system provided with vertical keel at outdoor side
KR101222115B1 (en) Roof structure
JP6648983B2 (en) Handrail device
CN105298145A (en) Vertical external sun-shading welding-free construction method of hidden-frame curtain wall
CN204282608U (en) A kind of floor slab structure of Fast Installation
CN212656381U (en) Sunlight room frame
CN204475919U (en) The steel-structure factory building that a kind of antidetonation is windproof
CN203834839U (en) Guardrail and installation structure with same
CN102454306A (en) Movable house
CN202131672U (en) Combined-type steel structure house
CN201687081U (en) Wooden house
CN201195924Y (en) Guardrail
CN110578402A (en) Tool type outer hanging rack installation method for prefabricated wall with sun shield
KR20160065451A (en) A glass wall fixing device
CN204299376U (en) A kind of steel structure factory building special complete doorframe
CN203320698U (en) Novel concrete connecting component of building
CN219887326U (en) Assembled prefabricated slab for high-rise building

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee