KR101324982B1 - Walking bridge construction method using psc girder with connecting anchor block - Google Patents

Walking bridge construction method using psc girder with connecting anchor block Download PDF

Info

Publication number
KR101324982B1
KR101324982B1 KR1020120034142A KR20120034142A KR101324982B1 KR 101324982 B1 KR101324982 B1 KR 101324982B1 KR 1020120034142 A KR1020120034142 A KR 1020120034142A KR 20120034142 A KR20120034142 A KR 20120034142A KR 101324982 B1 KR101324982 B1 KR 101324982B1
Authority
KR
South Korea
Prior art keywords
psc girder
psc
girder
fixing end
connection
Prior art date
Application number
KR1020120034142A
Other languages
Korean (ko)
Other versions
KR20130111902A (en
Inventor
이상윤
송재준
김형열
이영호
주봉철
이정미
Original Assignee
한국건설기술연구원
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한국건설기술연구원 filed Critical 한국건설기술연구원
Priority to KR1020120034142A priority Critical patent/KR101324982B1/en
Publication of KR20130111902A publication Critical patent/KR20130111902A/en
Application granted granted Critical
Publication of KR101324982B1 publication Critical patent/KR101324982B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D1/00Bridges in general
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

인접한 세그먼트 PSC거더의 연결부 강성을 보다 확실하게 증진시킬 수 있으며, 가로빔의 설치에 이용할 수 있어 보다 용이한 가로빔 설치작업이 가능하면서 전도방지수단을 손쉽게 설치할 수 있는 기능 및 보도를 PSC 거더에 형성된 연결부 정착단을 이용하여 보도를 설치할 수 있도록 하여 보다 안정적으로 보도를 설치할 수 있는 연결부 정착단을 구비한 피에스씨 거더를 이용한 보도교 시공방법을 제공하게 된다.The rigidity of the connection of adjacent segment PSC girder can be improved more reliably, and it can be used for the installation of horizontal beams, so that the horizontal beams can be installed more easily and the function and sidewalks that can easily install fall prevention means are formed on the PSC girder. It is possible to install the sidewalk by using the connection part fixing end to provide a construction method of the sidewalk bridge using the PS girder equipped with a connection part fixing end that can be installed more stably.

Figure R1020120034142
Figure R1020120034142

Description

연결부 정착단을 구비한 피에스씨 거더를 이용한 보도교 시공방법{WALKING BRIDGE CONSTRUCTION METHOD USING PSC GIRDER WITH CONNECTING ANCHOR BLOCK}WALKING BRIDGE CONSTRUCTION METHOD USING PSC GIRDER WITH CONNECTING ANCHOR BLOCK}

본 발명은 연결부 정착단을 구비한 피에스씨 거더를 이용한 보도교 시공방법에 관한 것이다. 더욱 구체적으로 다수의 PSC 거더 세그먼트를 서로 종방향으로 연결시켜 PSC 거더를 제작한 후, 교량하부구조에 거치하여 교량을 설치하되 보도를 피에스씨 거더의 연결부 정착단을 이용하여 설치한 보도교 시공방법에 대한 것이다.The present invention relates to a method for constructing a pedestrian bridge using a PS girder having a connecting part fixing end. More specifically, after manufacturing a PSC girder by connecting a plurality of segments of the PSC girder in the longitudinal direction to each other, the bridge is installed on the bridge undercarriage, but the sidewalk is installed in the bridge construction method using the connection settling end of the PS girder. It is about.

도 1a와 같이 종래 포스트 텐션 방식에 의한 PSC 거더(10,프리스트레스 콘크리트 거더,Prestressed Concrete Girder)는 다수의 부재(40)로 제작된 강재 거푸집을 이용하여 그 내부에 긴장재를 배치시켜 놓은 상태에서 콘크리트(C)를 타설하여 양생시킨 다음,PSC girder (10, prestressed concrete girder) by the conventional post-tension method as shown in Figure 1a is a concrete in a state in which the tension material is disposed therein using steel formwork made of a plurality of members 40 By curing C),

상기 강재 거푸집을 해체하여 쉬스에 PSC 긴장재(30)를 삽입하고 이를 긴장 후 PSC 거더 단부에 상기 PSC 긴장재 단부를 정착함으로서 소요의 프리스트레스(Prestress)가 PSC 거더에 도입되도록 하게 된다.By dismantling the steel formwork, the PSC tension member 30 is inserted into the sheath, and after the tension, the PSC tension member ends are fixed to the PSC girder end so that the required prestress is introduced into the PSC girder.

이에 I 형 단면의 PSC 거더(10)는 도 1b와 같이 전체적으로 I형 단면으로서 상부플랜지(11), 복부(12) 및 하부플랜지(13)로 구성되어 그 내부에 PSC 긴장재(30)가 형성된 상태로 제작됨을 알 수 있다.Accordingly, the PSC girder 10 having an I cross section is composed of an upper flange 11, an abdomen 12, and a lower flange 13 as an I cross section as shown in FIG. 1B, and a PSC tension member 30 is formed therein. It can be seen that produced.

이러한 I 형 단면의 PSC 거더(10)는 상부플랜지(11)의 폭은 하부플랜지(13)의 폭 보다 더 큰 폭을 가진 확폭된 상부플랜지로 형성시킬 수 있다.(벌브티 방식)The PSC girder 10 of the I-type cross section may be formed of an expanded upper flange having a width of the upper flange 11 larger than that of the lower flange 13 (bulb type).

이와 같이 상부플랜지의 폭이 하부플랜지의 폭보다 크게 형성된 PSC 거더는 상기 상부플랜지가 추후 슬래브(Slab)를 시공할 때 일종의 거푸집으로 이용할 수도 있고, 상기 상부플랜지 자체가 슬래브로 기능할 수 있도록 할 수 있다는 장점이 있다.As such, the PSC girder formed with the width of the upper flange larger than the width of the lower flange may be used as a formwork when the upper flange is later constructed with slab, and the upper flange itself may function as a slab. There is an advantage.

도 1c는 PSC 거더(10)를 교대, 교각과 같은 교량하부구조물(50)에 설치하고 슬래브(60)를 형성시킨 상태를 사시도로 도시한 것이다.FIG. 1C is a perspective view illustrating a state in which the PSC girder 10 is installed on the bridge substructure 50 such as shifts and piers and the slab 60 is formed.

상기 도 1c에 의하면, 횡방향으로 PSC 거더(10a,10b)가 가로빔(20)에 의하여 구속되도록 함을 알 수 있으려 이러한 가로빔(20)을 연결 설치하기 위하여 PSC 거더(10)에는 보강리브(14)가 별도로 형성시키고 있음을 알 수 있다.According to FIG. 1C, it can be seen that the PSC girders 10a and 10b are constrained by the horizontal beam 20 in the lateral direction so that the PSC girder 10 is reinforced to connect and install the horizontal beam 20. It can be seen that the ribs 14 are formed separately.

이러한 가로빔(20)은 현장타설 콘크리트로 설치하거나 프리캐스트 부재로 설치하기도 하는데, 강관 형태의 구조물로도 설치하기도 한다.The horizontal beam 20 may be installed as cast-in-place concrete or installed as a precast member, and may also be installed as a steel pipe structure.

하지만, 이러한 가로빔(20)은 PSC 거더(10)의 자체 기능과는 큰 상관없이 PSC 거더(10)를 횡방향 구속시켜 주기 위해 설치되는 것인데 횡방향으로 병렬로 이격된 거리에 따라 다양한 길이를 가지게 된다.However, the horizontal beam 20 is installed to laterally restrain the PSC girder 10 regardless of the function of the PSC girder 10 itself. To have.

하지만, 이러한 가로빔(20)는 PSC 거더의 복부 사이에 설치되기 때문에 별도의 비계를 PSC 거더의 길이방향(종방향)으로 설치하여 작업가능한 지지대를 설치해야 하고, 현장에서 콘크리트를 타설하여 설치해야 하는 경우라면 거푸집을 별도로 설치해야 하는 등의 시공에 있어 작업성 및 시공성이 떨어질 수밖에 없다는 문제점이 있었다.However, since the horizontal beam 20 is installed between the abdomen of the PSC girder, a separate scaffold should be installed in the longitudinal direction (longitudinal direction) of the PSC girder to install a workable support, and the concrete should be installed on the site. If there is a problem in that workability and workability inevitably fall in the construction, such as the need to install a separate formwork.

나아가, 가로빔(20)은 반드시 설치하여야 하지만 PSC 거더(10)를 횡방향으로 서로 구속시켜 주는 기능이외에 달리 PSC 거더 자체의 구조적 기능을 가질 수 있도록 설치되는 것은 아니기 때문에 그 설치에 있어 이용 효율성이 낮다는 문제점이 있었다.Furthermore, the horizontal beam 20 must be installed, but besides the function of restraining the PSC girders 10 laterally, the horizontal beam 20 is not installed to have the structural functions of the PSC girders themselves. There was a problem of low.

도 1d는 종래 PSC 거더용 전도방지수단을 도시한 것이다.Figure 1d shows a fall prevention means for a conventional PSC girder.

즉 PSC 거더(10)는 소정의 높이를 가지게 되는데 이러한 높이를 가진 PSC 거더를 교량하부구조에 거치할 때 풍하중, 시공에 따라 PSC 거더가 전도되어 안전사고가 발생하는 경우가 있어 PSC 거더(10)를 교량하부구조(20)에 임시적으로 고정시키기 위하여 와이어(71)를 이용하여 PSC 거더(10)를 교량하구조에(20)에 앵커(72)로 고정시켜 놓게 된다.That is, the PSC girder 10 has a predetermined height. When the PSC girder having such a height is mounted on the bridge undercarriage, the PSC girder is inverted depending on the wind load and construction, so that a safety accident may occur. In order to temporarily fix the to the bridge substructure 20, the wires 71 are used to fix the PSC girder 10 to the bridge substructure 20 with an anchor 72.

하지만 이러한 전도방지수단은 고공에서 작업해야 하고 PSC 거더(10)의 측방에서 작업자가 일일이 와이어, 앵커 등을 설치하는 작업이 수반되므로 시공성이 매우 떨어질 수밖에 없었다.However, the fall prevention means has to work at high altitude, and since the work of installing the wire, anchor, etc. by the worker on the side of the PSC girder 10 was inevitably deteriorated in construction.

도 1e는 상기 PSC 거더(10)를 다수의 세그먼트 PSC 거더(10a)로 분할 제작하고, 서로 종방향으로 접하도록 세팅한 후, PSC 긴장재(30)를 이용하여 서로를 압착시켜 최종 일정한 길이의 PSC 거더(10)를 제작하는 예가 도시되어 있다.FIG. 1E shows that the PSC girder 10 is divided into a plurality of segmented PSC girder 10a, and is set to be in contact with each other in the longitudinal direction, and then pressed together using a PSC tension member 30 to finalize a PSC of a constant length. An example of manufacturing the girder 10 is shown.

하지만 각 세그먼트 PSC거더(10a)들의 연결부(A)는 시간이 경과함에 따라 도입된 프리스트레스가 감소하는 현상(릴랙세이션) 등이 발생하게 되고, 상기 연결부(A)로 우수 등이 침투하여 동절기에 팽창하는 등의 이유로 연결부 하자 문제가 발생할 수 있다는 문제점이 지적되었다.However, the connection portion (A) of each segment PSC girder (10a) is a phenomenon that the pre-stress is introduced (relaxation) is reduced over time, the rain or the like penetrates into the connection portion (A) in winter It has been pointed out that a problem of connection defects may occur due to expansion or the like.

도 1f는 종래 보도교를 도시한 것이다.Figure 1f shows a conventional pedestrian bridge.

즉, 연석(74)의 폭에 대응하여 폭 조절이 가능하게 결합되는 제 1, 2 고정That is, the first and the second fixing coupled to the width adjustment corresponding to the width of the curb 74

브라켓(71,72)과, 상기 제 1, 2 고정브라켓(71,72)을 서로 연결시키면서 상기 제 1, 2 고정브라켓(71,72)을 연석(74)에 고정시키는 복수의 앵커볼트(73)로 구성된다.A plurality of anchor bolts 73 for fixing the first and second fixing brackets 71 and 72 to the curb 74 while connecting the brackets 71 and 72 to the first and second fixing brackets 71 and 72. It consists of

이때 상기 보도(75)를 지지하기 위하여 브라켓(76)이 보도 저면에 설치되는데 상기 브라켓(76)은 수직재(76a)가 연석(74) 외측면에 고정되도록 하고 경사재(76b)가 보도 저면으로부터 수직재(76a)에 연결되도록 설치된다.At this time, a bracket 76 is installed on the bottom of the sidewalk to support the sidewalk 75. The bracket 76 allows the vertical member 76a to be fixed to the outer surface of the curb 74, and the inclined member 76b from the bottom of the sidewalk. It is installed to be connected to the vertical member (76a).

이에 보도(75)는 자중이 커지지 않도록 하게 되며 이는 차량이 아닌 보행인의 통행하중을 고려한 것이라 할 수 있다.Therefore, the sidewalk 75 is to prevent the self-weight is increased, which may be considered considering the traffic load of the pedestrian, not the vehicle.

이에 본 발명은 피에스씨 거더 세그먼트로 분할 제작하여 서로 압착시켜 제작되는 PSC 거더에 있어서, 인접한 피에스씨 거더 세그먼트의 연결부 강성을 보다 확실하게 증진시킬 수 있으며, 이를 위해 상기 피에스씨 거더 세그먼트의 연결부에는 연결부 정착단을 형성시키되, 이러한 연결부 정착단을 가로빔의 설치에 이용하여 보다 용이한 가로빔 설치작업이 가능하도록 하면서 전도방지수단도 피에스씨 거더 세그먼트에 손쉽게 설치할 수 있는 기능을 가지도록 함과 더불어 상기 연결부 정착단을 이용하여 보도를 설치할 수 있도록 하여 보다 안정적으로 보도를 설치할 수 있는 연결부 정착단을 구비한 피에스씨 거더를 이용한 보도교 시공방법 제공을 발명의 목적으로 한다.Accordingly, the present invention can be more reliably promoted the connection stiffness of the adjacent PS-C girder segment in the PSC girder produced by splitting the PS-C girder segment to be compressed to each other, for this purpose, the connection portion of the PS girder segment Forming the fixing end, but using the connection unit fixing end in the installation of the horizontal beam to facilitate the installation of the horizontal beam while having a function to easily install the fall prevention means in the PS girder segment It is an object of the present invention to provide a method for constructing a pedestrian bridge using PS girder having a connecting part fixing end capable of installing the sidewalk more stably by using a connecting part fixing end.

상기 목적을 달성하기 위하여 본 발명은The present invention to achieve the above object

첫째, 피에스씨 거더 세그먼트로 분할 제작하여 서로 압착시켜 제작되는 PSC 거더에 있어서, 인접한 피에스씨 거더 세그먼트 각각에 연결부 정착단을 형성시키고, 상기 연결부 정착단을 긴장강봉과 같은 연결부긴장재로 압착시켜 인접한 피에스씨 거더 세그먼트의 연결부 강성이 증진될 수 있도록 하였다.First, in the PSC girder, which is manufactured by splitting into pieces of PS girder segments and pressing them to each other, a connection fixing end is formed on each adjacent PS C girder segment, and the connecting part fixing ends are crimped with a connecting part tension member such as a tension bar to close the adjacent PS. The joint stiffness of the seed girder segment can be improved.

이를 위해 상기 연결부 정착단은 PSC 거더 세그먼트의 상부플랜지 및 복부 양 측에 돌출 연장된 블록형태로 형성되도록 하였다.To this end, the connection fixing unit is formed in a block shape protruding on both sides of the upper flange and the abdomen of the PSC girder segment.

둘째, 이러한 연결부 정착단은 모듈러 피에스씨 거더교의 가로빔 설치에 이용함으로서 별도의 가로빔 설치를 위한 공종이 배제될 수 있도록 하였다. 즉 횡방향으로 인접한 연결부 정착단들이 횡방향으로 설치되는 가로빔 연결패널에 간단하게 삽입되어 연결되도록 함으로서 효과적인 가로빔 설치가 가능하도록 하였다.Second, the connection part fixing stage is used to install the horizontal beam of the modular PS Girder bridge so that the work for the separate horizontal beam installation can be excluded. That is, the transversely adjacent connecting part fixing ends are simply inserted into and connected to the horizontal beam connecting panel installed in the horizontal direction, thereby enabling effective horizontal beam installation.

셋째, PSC 거더의 양 단부에 형성된 피에스씨 거더 세그먼트에는 관통홀을 형성시켜 이러한 관통공은 본 발명의 전도방지수단이 삽입되어 설치되는 삽입홀로 이용함으로서 별도의 전도방지수단이 없이도 PSC 거더의 안정적인 운반 및 거치가 가능하도록 하였다.Third, through-holes are formed in the PSG girder segments formed at both ends of the PSC girder, so that the through-holes are used as insertion holes in which the fall-prevention means of the present invention are inserted, so that the PSC girder can be stably transported. And it was possible to mount.

넷째, PSC 거더의 연결부 정착단과 하부플랜지에는 각각 스트럿이 설치되고 상기 보도교는 스트럿에 의하여 지지되도록 하였다.Fourth, struts are respectively installed at the connection fixing end and the lower flange of the PSC girder, and the sidewalk bridge is supported by the struts.

본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present invention is shown by the following claims rather than the above description, and all changes or modifications derived from the meaning and scope of the claims and their equivalents should be construed as being included in the scope of the present invention. do.

본 발명에 의한 PSC 거더는 안정적으로 운반 및 거치가 가능하고 이러한 작업에 필요한 전도방지수단의 설치 공종, 가로빔 설치공종을 최적화시켜 보다 효율적이고 경제적인 모듈러 피에스씨 거더교 시공이 가능하도록 하고,PSC girder according to the present invention can be stably transported and mounted, and to optimize the installation work of the fall prevention means, horizontal beam installation work required for such a work to enable a more efficient and economical modular PS girder bridge construction,

다수의 피에스씨 거더 세그먼트를 서로 연결시켜 PSC 거더를 제작하게 되므로 제작 및 운반에 제약이 큰 영향을 받지 않고 피에스씨 거더 세그먼트의 연결부 강성이 크게 증진되어 효과적인 PSC 거더 제작이 가능하게 되며,Since the PSC girder is manufactured by connecting a plurality of PS girder segments to each other, the rigidity of the connection portion of the PS girder segment is greatly enhanced without the restriction of manufacturing and transportation, and thus, an effective PSC girder can be manufactured.

보도교를 간단하게 설치할 수 있는 교량시공이 가능하게 된다.It is possible to construct a bridge that can be installed easily.

도 1a는 종래 PSC 거더에 제작사시도,
도 1b는 종래 PSC 거더의 사시도,
도 1c는 종래 PSC 거더교의 완성사시도,
도 1d는 종래 PSC 거더의 전도방지수단이 설치사시도,
도 1e는 종래 PSC거더 세그먼트의 제작 순서도,
도 1f는 종래 보도교 발췌도,
도 2a, 도 2b 및 도 2c는 본 발명의 모듈러 PSC 거더 사시도, 분리사시도 및 연결부 발췌사시도,
도 2a, 도 2b 및 도 2c는 본 발명의 PSC 거더 사시도, 분리사시도 및 연결부 발췌사시도,
도 3은 본 발명의 PSC 거더의 가로빔 설치사시도,
도 4a, 도 4b, 도 4c 및 도 4d는 본 발명의 PSC 거더를 이용한 교량시공방법의 순서도
도 4e는 본 발명의 보도교의 시공 사시도 및 단면도이다.
Figure 1a is a manufacturing perspective view of a conventional PSC girder,
1B is a perspective view of a conventional PSC girder,
Figure 1c is a complete perspective view of a conventional PSC girder bridge,
Figure 1d is a perspective view of the installation prevention means of the conventional PSC girder,
1E is a manufacturing flowchart of a conventional PSC girder segment;
Figure 1f is a conventional footbridge excerpt,
2a, 2b and 2c is a perspective view of the modular PSC girder of the present invention, an exploded perspective view and an excerpt of the connection portion,
Figure 2a, 2b and 2c is a perspective view of the PSC girder of the present invention, a perspective view of the separation and the excerpt of the connection,
3 is a perspective view of the horizontal beam installation of the PSC girder of the present invention,
Figures 4a, 4b, 4c and 4d is a flow chart of the bridge construction method using the PSC girder of the present invention
4E is a construction perspective view and a cross-sectional view of the sidewalk bridge of the present invention.

아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명한다. 그러나 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.DETAILED DESCRIPTION Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those skilled in the art may easily implement the present invention. The present invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein. In order to clearly illustrate the present invention, parts not related to the description are omitted, and similar parts are denoted by like reference characters throughout the specification.

[ 본 발명의 연결부 정착단(140)을 구비한 피에스씨 거더 세그먼트 및 PSC 거더(100) ][PSC girder segment and PSC girder 100 with connection fixing unit 140 of the present invention]

본 발명의 PSC 거더(100)는 도 2a와 같이 전체적으로 I형 단면으로 형성되는 상부플랜지(110), 복부(120) 및 하부플랜지(130)를 포함하여 구성된다.The PSC girder 100 of the present invention includes an upper flange 110, an abdomen 120, and a lower flange 130, which are generally formed in an I-shaped cross section as illustrated in FIG. 2A.

상기 상부플랜지(110)는 교량에 있어 슬래브로 기능하는 판형부재로 형성되며 소정의 폭(W1)과 두께(T1)로 철근콘크리트 부재로 형성시키게 된다.The upper flange 110 is formed of a plate-like member that functions as a slab in the bridge and is formed of a reinforced concrete member with a predetermined width (W1) and thickness (T1).

이때 상기 폭과 두께는 제작, 운반 및 거치를 고려하여 정하게 된다.At this time, the width and thickness are determined in consideration of manufacturing, transportation and mounting.

상기 복부(120)는 상부플랜지(110)의 중앙 저면으로부터 하부로 연장되는 수직부재로 형성되며 역시 소정의 폭(W2)과 높이(H1)로 철근콘크리트 부재로 형성시키게 된다.The abdomen 120 is formed of a vertical member extending downward from the center bottom of the upper flange 110 and is formed of a reinforced concrete member with a predetermined width W2 and height H1.

이러한 PSC 거더(100)는 일정한 길이(L)를 가지도록 제작되며 도 4d와 같이 상부플랜지(110)의 측면이 서로 횡방향으로 서로 접하도록 설치되어 상부플랜지(110)에 의하여 교량의 슬래브가 형성될 수 있도록 함으로서 별도의 슬래브 시공이 필요 없도록 하게 된다.The PSC girder 100 is manufactured to have a predetermined length (L) and as shown in Figure 4d is installed so that the sides of the upper flange 110 in contact with each other in the transverse direction to form a slab of the bridge by the upper flange (110) By doing so, there is no need for a separate slab construction.

이때 상기 PSC 거더(100)의 내부에는 종방향(길이방향, 교축방향)으로 연장되도록 PSC 긴장재(30)가 배치된다.At this time, the PSC tension member 30 is disposed in the PSC girder 100 to extend in the longitudinal direction (length direction, axial direction).

이러한 PSC 긴장재(30)는 상부플랜지(110)와 복부(120)의 단부면에 각각 긴장 후 정착되도록 설치된다.The PSC tension member 30 is installed to be fixed after the tension on the end surface of the upper flange 110 and the abdomen 120, respectively.

또한 상기 PSC 거더(100)는 미리 공장에서 제작되는 프리캐스트 방식으로 제작하게 되는데 이에 현장타설 콘크리트에 의한 제작 방식과 대비하여 품질관리에 유리한 장점이 있다. 하지만 그 운반 및 시공 상의 한계에 의하여 제작 길이에는 한계가 있을 수밖에 없다.In addition, the PSC girder 100 is produced by a precast method that is manufactured in advance in the factory, which is advantageous in quality control as compared to the production method by cast-in-place concrete. However, due to the limitations of the transport and construction, there is no limit to the manufacturing length.

이에 도 2b 및 도 2c와 같이 공장에서 PSC거더를 일정한 길이(L1<L)로 분할하여 다수의 PSC거더 세그먼트(100a)로 제작한 후, 현장에 반입하고, 현장에서 다시 PSC거더 세그먼트(100a)들을 서로 연결하는 방식을 채택하게 된다. 2B and 2C, the PSC girder is divided into a predetermined length (L1 <L) in the factory, and then manufactured into a plurality of PSC girder segments 100a, and then brought to the site, and the PSC girder segment 100a is again in the field. They will adopt a way of connecting them.

이와 같이 다수의 PSC거더 세그먼트(100a)들을 연결하는 방법은 여러 가지 방법이 있을 수 있지만 통상은 시공의 편의성을 고려하여 다수의 PSC거더 세그먼트(100a)들을 서로 종방향으로 접하여 연속되도록 세팅한 후 PSC 긴장재(30)를 전체 PSC거더 세그먼트(100a)들을 관통하도록 배치하고, 상기 PSC 긴장재(30)를 긴장 후 상부플랜지와 복부에 정착시켜 다수의 PSC거더 세그먼트(100a)들에 프리스트레싱을 가하여 종방향으로 연속화되도록 하여 연결부 정착단을 구비한 피에스씨 거더 세그먼튿르을 서로 연결시키게 된다.As described above, there may be various methods of connecting the plurality of PSC girder segments 100a, but in general, the PSC girder segments 100a are set in continuous contact with each other in the longitudinal direction in consideration of construction convenience and then PSC. The tension member 30 is disposed to penetrate the entire PSC girder segments 100a, and after the tension, the PSC tension member 30 is fixed to the upper flange and the abdomen to apply prestressing to the plurality of PSC girder segments 100a in the longitudinal direction. In order to be continuous, the PSG girder segment with the connection fixing end is connected to each other.

이에 상기 PSC거더 세그먼트(100a)들의 내부에는 미리 쉬스(SHEATH)를 배치하여 PSC 긴장재(30)를 삽입하여 배치할 수 있도록 하게 된다.Accordingly, the sheath SHEATH is disposed in advance in the PSC girder segments 100a to insert and insert the PSC tension member 30.

이로서 도 2b와 같이 각 PSC거더 세그먼트(100a)들의 연결부(A)는 압착되어 서로 일체성을 확보하게 되지만 시간이 경과함에 따라 도입된 프리스트레스가 감소하는 현상(릴랙세이션) 등이 발생하게 되고, 상기 연결부(A)로 우수 등이 침투하여 동절기에 팽창하는 등의 이유로 연결부 하자 문제가 발생할 수 있다.As a result, as shown in FIG. 2B, the connection parts A of the respective PSC girder segments 100a are compressed to secure unity with each other. However, as the time passes, the introduced prestress decreases (relaxation). Rainfall may penetrate into the connection portion A and cause a connection problem.

실제 이러한 연결부(A)의 품질 및 시공관리는 사실상 PSC 거더(100)의 이용여부를 결정하는데 매우 중요한 요인이 된다.In fact, the quality and construction management of the connection (A) is in fact a very important factor in determining the use of the PSC girder (100).

이에 본 발명은 상기 문제를 해결하기 위하여 PSC거더 세그먼트(100a)에 연결부 정착단(140)을 형성시키게 된다.Accordingly, the present invention forms a connection fixing end 140 to the PSC girder segment (100a) to solve the above problem.

이러한 연결부 정착단(140)은 PSC거더 세그먼트(100a)의 연결부를 보다 확실하게 압착시키는 기능을 가질 수 있도록 하기 위한 것이다.The connection part fixing end 140 is intended to have a function to more surely crimp the connection of the PSC girder segment (100a).

이에 도 2c와 같이 상기 연결부 정착단(140)에는 종방향으로 긴장홀(141)이 적어도 1개 이상 형성되도록 하되 PSC거더 세그먼트(100a)의 복부(120) 양 측면에 돌출되도록 형성시키게 된다.Accordingly, as shown in FIG. 2C, at least one tension hole 141 is formed in the connecting portion fixing end 140 in the longitudinal direction, but protrudes on both sides of the abdomen 120 of the PSC girder segment 100a.

이에 종방향으로 인접한 PSC거더 세그먼트(100a)의 복부(120)에는 연결부 정착단(140)이 서로 종방향으로 접하게 되고, 서로 접하여 연통된 긴장홀(141)들에는 연결부긴장재(150)를 삽입하여, 연결부긴장재(150)를 긴장 후 양 단부를 연결부 정착단(140)에 정착시킴으로서 PSC거더 세그먼트(100a)의 연결부를 압착시키게 된다.Therefore, the connection part fixing end 140 is in contact with each other in the longitudinal direction in the abdomen 120 of the PSC girder segment 100a adjacent to the longitudinal direction, and the connection part tension member 150 is inserted into the tension holes 141 which are in contact with each other. After the tension of the connecting part tension member 150, both ends are fixed to the connecting part fixing end 140 to compress the connecting part of the PSC girder segment 100a.

상기 연결부긴장재(150)는 강봉을 이용할 수 있고, 연결부긴장재(150)의 정착은 체결너트를 이용할 수 있을 것이다.The connecting portion tension member 150 may use a steel bar, and the fixing portion of the connecting portion tension member 150 may use a fastening nut.

시간이 경과함에 따라 PSC 긴장재에 하여 도입된 프리스트레스가 감소할 수 있는데 이러한 감소를 보완하기 위하여 상기 연결부긴장재(150)를 추가 긴장 후 연결부 정착단(140)에 정착시켜 추가 프리스트레스가 도입되도록 할 수 있어 유지관리에도 매우 효과적이게 된다.The prestress introduced by the PSC tension material may decrease with time. To compensate for this reduction, the connection tension member 150 may be settled at the connection fixing unit 140 after the additional tension so that the additional prestress may be introduced. It is also very effective for maintenance.

나아가 상기 복부(120)뿐만 아니라 상부플랜지(110)의 저면에도 연결부 정착단(140)이 양 저면에 하방으로 돌출되어 복부(120)의 연결부 정착단(140)과 일체로 형성되도록 할 수 있으며 도 2a 내지 도 2c에는 상기 연결부 정착단(140)이 상부플랜지(110) 및 복부(120) 측면과 저면에 각각 형성되어 일체로 형성된 경우가 도시되어 있다.Furthermore, not only the abdomen 120 but also the connection fixing unit 140 may protrude downward on both bottom surfaces of the upper flange 110 so as to be integrally formed with the connecting unit fixing end 140 of the abdomen 120. 2A to 2C illustrate the case in which the connection part fixing end 140 is formed on the upper flange 110 and the side and the bottom of the abdomen 120, respectively, and is integrally formed.

이로서 본 발명의 연결부 정착단(140)은 PSC거더 세그먼트(100a) 제작시 일체로 형성되어 연결부(A)의 단면적을 크게 형성시키게 되므로 연결부 강성을 증가시키는 기능을 가지게 되고 연결부긴장재(150)에 의하여 압착됨으로서 PSC거더 세그먼트(100a)의 연결부(A)를 압착시켜 연결성능이 증진될 수 있도록 하게 된다.As a result, the connection part fixing end 140 of the present invention is integrally formed at the time of manufacturing the PSC girder segment 100a to form a large cross-sectional area of the connection part A, and thus has a function of increasing the connection part rigidity and the connection part tension member 150. By being compressed, the connection portion (A) of the PSC girder segment (100a) is compressed so that the connection performance can be enhanced.

상기 하부플랜지(130)는 PSC 거더(100)의 양 단부의 경우 PSC 긴장재(30)의 긴장 후 정착에 의한 응력집중에 저항하기 위하여 복부(120)의 폭과 하부플랜지(130)의 폭을 동일하게 형성(단부 구체로 형성)되도록 하게 된다.The lower flange 130 is equal to the width of the abdomen 120 and the width of the lower flange 130 in order to resist stress concentration due to fixation after the tension of the PSC tension member 30 at both ends of the PSC girder 100. To form (end sphere).

이러한 PSC 거더에 있어 양 단부에 위한 PSC거더 세그먼트(100a)의 하부플랜지(130)에는 후술되는 전도방지수단(300)이 설치된다.In the PSC girder, the lower flange 130 of the PSC girder segment 100a for both ends is provided with fall prevention means 300 to be described later.

앞서 살펴본 것과 같이 상부플랜지(110), 복부(120), 하부플랜지(130) 및 연결부 정착단(140)을 포함하는 본 발명의 PSC거더 세그먼트(100a)는 소정의 길이(L1)를 가지게 되는데 상부플랜지(110)가 슬래브 역할을 하게 되다 보니 폭(W1)이 통상의 거더와 대비하여 다소 커지게 된다.As described above, the PSC girder segment 100a of the present invention including the upper flange 110, the abdomen 120, the lower flange 130, and the connector fixing end 140 has a predetermined length L1. Since the flange 110 serves as a slab, the width W1 becomes slightly larger than that of a conventional girder.

이에 제작 후 야적장에 거치하거나 교대 또는 교각으로 이루어지는 교량하부구조(200)에 거치할 때 전도가 될 여지가 있다.Thus there is room for conduction when mounted on the yard or the bridge substructure 200 made of alternating or pier after production.

이에 통상의 전도방지수단을 설치할 수 있지만 이러한 종래의 전도방지수단은 도 1d와 같이 앵커 또는 와이어를 이용하게 된다. 하지만 이러한 전도방지수단은 임시로 설치되 것이므로 그 설치 및 해체작업을 수반하게 되며 전도방지수단을 별도로 설치하거나 해체하는 경우 공종이 복잡해지게 되고 시공성이 떨어질 수밖에 없다.This can be provided with a conventional fall prevention means, but such a conventional fall prevention means is to use the anchor or wire as shown in FIG. However, these fall prevention means will be temporarily installed, so the installation and dismantling work will be involved, and if you install or dismantle the fall prevention means separately, the work becomes complicated and the construction is inevitably deteriorated.

이에 본 발명은 도 2b와 같이 전도방지수단(300)을 PSC 거더(100)에 있어서 양 단부에 위치한 PSC거더 세그먼트(100a)에 설치하게 된다.Accordingly, in the present invention, as shown in FIG. 2B, the fall prevention means 300 is installed in the PSC girder segment 100a located at both ends of the PSC girder 100.

즉, PSC 거더에 있어서 양 단부에 위치한 PSC거더 세그먼트(100a)의 하부플랜지(130)와 상부플랜지(110)의 측면과 저면에 횡방향으로 관통홀(111,131)을 형성시키게 된다.That is, through holes 111 and 131 are formed in the side and bottom of the lower flange 130 and the upper flange 110 of the PSC girder segment 100a located at both ends of the PSC girder.

이에 상기 하부플랜지(130)에 형성된 관통홀(131)에는 본 발명의 전도방지수단(300)의 하부가 삽입되어 고정되고, 상부는 상부플랜지(110)의 저면에 형성된 관통홀(111)에 삽입되도록 하여 상기 전도방지수단(300)을 설치할 수 있도록 하게 된다.The lower portion of the fall prevention means 300 of the present invention is inserted into and fixed to the through hole 131 formed in the lower flange 130, and the upper portion is inserted into the through hole 111 formed on the bottom surface of the upper flange 110. It is to be able to install the fall prevention means 300.

이때 상기 전도방지수단(300)은 전체적으로 수평재(310)와 수직재(320)로 구성된 역 자 형태로 제작된 것을 이용할 수 있는데 PSC거더 세그먼트(100a)의 측방에서 간단하게 설치할 수 있어 설치 및 해체에 매우 유리하게 된다.At this time, the fall prevention means 300 can be used in the form of a transverse consisting of a horizontal member 310 and a vertical member 320 as a whole can be easily installed on the side of the PSC girder segment (100a), very easy to install and dismantle Is advantageous.

구체적으로 살펴보면 상기 수평재(310)와 수직재(320)의 단부는 수평판 형태의 연결판(330)을 형성시키고, 상기 PSC거더 세그먼트(100a)에는 관통홀(111,131)에 매립된 정착너트(미도시)를 설치하고, 상기 연결판(330)의 연결홀(미도시)을 관통하는 앵커볼트(340)가 상기 관통홀들에 체결되도록 함으로서 PSC거더 세그먼트(100a)에 전도방지수단(300)을 간단하게 설치하게 된다.Specifically, the ends of the horizontal member 310 and the vertical member 320 form a connecting plate 330 in the form of a horizontal plate, and fixing nuts (not shown) embedded in the through holes 111 and 131 in the PSC girder segment 100a. ), And the anchor bolt 340 penetrating the connection hole (not shown) of the connecting plate 330 is fastened to the through holes to simplify the fall prevention means 300 in the PSC girder segment 100a. Will be installed.

이로서 도 2a와 같이 본 발명의 PSC거더 세그먼트(100a)들은 연결부 정착단(140)에 의하여 서로 압착 연결되도록 제작되어 PSC 거더(100)가 완성되고, 전도방지수단(300)이 설치되어 야적 및 교량하부구조 거치에 이용됨을 알 수 있다.As such, as shown in FIG. 2A, the PSC girder segments 100a of the present invention are manufactured to be press-connected to each other by the connection fixing unit 140 to complete the PSC girder 100, and the fall prevention means 300 is installed to prevent the field and the bridge. It can be seen that it is used to mount the infrastructure.

[ 본 발명의 PSC 거더(100)와 가로빔의 연결 ][Connection of Horizontal Beam to PSC Girder 100 of the Present Invention]

통상 PSC 거더 또는 본 발명과 같이 상부플랜지가 슬래브로 기능을 가지는 PSC 거더(100)는 횡방향 구속을 위하여 가로빔(Cross beam)을 설치해야 한다.Ordinarily, the PSC girder or the PSC girder 100 having the upper flange functioning as a slab, as in the present invention, should be provided with a cross beam for lateral restraint.

이러한 가로빔은 철근콘크리트 또는 강재를 이용하여 설치할 수 있다. 이에 상기 가로빔을 별도로 설치하는 경우 교량하부구조(200)에 거치된 상태의 PSC 거더(100)의 복부(120) 측면에서 작업이 이루어져야 하고, 가로빔 제작을 위한 콘크리트 타설 또는 연결 작업이 수반되므로 시공성이 매우 떨어지게 된다.Such horizontal beams can be installed using reinforced concrete or steel. Therefore, when the horizontal beam is installed separately, the work should be made at the side of the abdomen 120 of the PSC girder 100 mounted on the bridge lower structure 200, and thus the concrete placement or connection work for the horizontal beam is accompanied. The workability is very poor.

이에 상기 가로빔 설치를 보다 간단하게 할 수 있다면 이는 PSC 거더(100)의 시공성 증진에 매우 효과적이게 된다.Therefore, if the horizontal beam installation can be made simpler, it is very effective in improving the constructability of the PSC girder 100.

이를 위해 본 발명은 도 3과 같이 연결부 정착단(140)을 이용하게 된다.To this end, the present invention uses the connector fixing end 140 as shown in FIG.

즉 연결부긴장재(150)를 정착시키기 전에 연결부 정착단(140)의 배면들에는 콘크리트 패널 또는 강판으로 제작된 가로빔연결패널(400)을 설치하게 된다.That is, before fixing the connection part tension member 150, the horizontal beam connection panel 400 made of a concrete panel or a steel plate is installed on the rear surfaces of the connection part fixing end 140.

이러한 가로빔연결패널(400)은 한 쌍을 준비하여 가로빔연결패널 사이에 횡방향으로 인접한 PSC거더 세그먼트(100a)의 연결부 정착단(140)이 끼워지도록 설치하게 된다.The horizontal beam connection panel 400 is prepared so that a pair is installed so that the connection part fixing end 140 of the PSC girder segment 100a adjacent in the horizontal direction is fitted between the horizontal beam connection panels.

이에 상기 가로빔연결패널(400)에는 긴장홀(141)에 대응한 연결홀(410)이 형성되어 연결부긴장재(150)를 정착시킬 때 연결부 정착단(140)에 한쌍의 가로빔연결패널(400)이 함께 고정 설치되도록 하게 된다.Therefore, the horizontal beam connecting panel 400 has a connection hole 410 corresponding to the tension hole 141 is formed to fix the connecting portion tension member 150, a pair of horizontal beam connecting panel 400 to the connecting portion fixing end 140 ) Will be fixed together.

결국 상기 가로빔연결패널(400)은 연결부에 있어 서로 종방향으로 이격되어 한 쌍이 마주보도록 설치되는데 이러한 이격되어 형성되는 공간에 횡방향으로 인접한 PSC거더 세그먼트(100a)의 연결부 정착단(140)이 끼워져 설치된다.As a result, the horizontal beam connecting panel 400 is installed in the connecting portion so as to be spaced apart from each other in the longitudinal direction so as to face each other, the connecting portion fixing end 140 of the PSC girder segment 100a adjacent in the space formed by such a space It is fitted and installed.

이에 끼워진 PSC거더 세그먼트(100a)의 연결부 정착단(140)과 가로빔연결패널(400)은 연결부긴장재(150)에 의하여 서로 결속될 수 있도록 함으로서 최종 서로 횡방향으로 인접한 PSC거더 세그먼트(100a)의 상기 가로빔연결패널(400)과 연결부 정착단(140)을 이용하여 가로빔을 간단하게 설치할 수 있도록 하게 된다.The connecting portion fixing end 140 and the horizontal beam connecting panel 400 of the PSC girder segment 100a inserted therein may be bound to each other by the connecting portion tensioner 150, so that the ends of the PSC girder segments 100a adjacent to each other laterally cross each other. By using the horizontal beam connecting panel 400 and the connecting portion fixing end 140 it is possible to simply install the horizontal beam.

이에 본 발명의 상기 연결부 정착단(140)은 가로빔의 기능도 함께 가지고 있음을 알 수 있다.Therefore, it can be seen that the connection part fixing end 140 of the present invention also has a function of a horizontal beam.

[ 본 발명의 연결부 정착단을 구비한 피에스씨 거더를 이용한 보도교 시공방법 ][A method for constructing a pedestrian bridge using a PS girder equipped with a connection fixing unit of the present invention]

본 발명의 모듈러 PSC 거더교는 도 4a와 같이 PSC 거더 세그먼트(100a)들을 이용하여 PSC 거더(100)를 먼저 제작하게 된다.The modular PSC girder bridge of the present invention will first manufacture the PSC girder 100 using the PSC girder segments 100a as shown in FIG. 4A.

즉, 상기 PSC 거더(100)는 공장에서 미리 일정한 길이(L)를 가지도록 제작하게 되는데, 운반 가능하다면 현장에 반입하여 교량하부구조(200)에 거치하여 설치하면 되는데, 운반이 용이하지 않을 경우에는 PSC거더 세그먼트(100a) 다수로 분할하여 제작한 후, 각 PSC거더 세그먼트를 현장에 반입하고 서로 연결시켜 교량하부구조(200)에 거치시키게 된다.That is, the PSC girder 100 is to be manufactured to have a predetermined length (L) in advance in the factory, if it is possible to carry in the site to install it mounted on the bridge substructure 200, if not easy to carry After the PSC girder segment is divided into a plurality of fabrication (100a) is produced, each of the PSC girder segments are brought into the site and connected to each other to be mounted on the bridge substructure 200.

이러한 PSC거더 세그먼트(100a)의 제작은 도 1a와 같은 강재 거푸집을 이용하여 도 2a와 같이 제작하게 된다.The PSC girder segment 100a is manufactured as shown in FIG. 2A using steel formwork as shown in FIG. 1A.

이러한 PSC거더 세그먼트(100a)는 역시 상부플랜지, 복부 및 하부플랜지로 구성되어 전체적으로 I형 단면으로 제작되고 PSC 거더의 양 단부에 있어서는 상부플랜지 및 복부와 하부플랜지가 서로 동일한 폭을 가진 단부구체로 형성되도록 하되, PSC거더 세그먼트(100a)의 연결부에는 앞서 살펴본 연결부 정착단(140)들이 형성되어 있음을 알 수 있다.The PSC girder segment 100a is also composed of an upper flange, an abdomen, and a lower flange, and is generally formed in an I-shaped cross section, and both ends of the PSC girder are formed of end spheres having the same width as the upper flange and the abdomen and the lower flange. The connection part fixing end 140 described above is formed at the connection part of the PSC girder segment 100a.

즉, 상기 연결부 정착단(140)은 연결부에 있어 PSC거더 세그먼트(100a)의 상부플랜지와 복부에 각각 형성되어 있음을 알 수 있다.That is, it can be seen that the connection part fixing end 140 is formed in the upper flange and the abdomen of the PSC girder segment 100a at the connection part, respectively.

또한 상기 상부플랜지와 복부 내부에는 PSC 긴장재(30) 설치를 위한 쉬스가 미리 형성되어 있다.In addition, a sheath for installing the PSC tension member 30 is formed in the upper flange and the abdomen in advance.

이에 상기 PSC거더 세그먼트(100a)의 제작이 완료되면 거푸집을 탈형하여 PSC거더 세그먼트(100a) 다수를 야적시켜 놓게 된다.Accordingly, when the production of the PSC girder segment 100a is completed, the mold is demolded to deposit a plurality of PSC girder segments 100a.

다음으로는 상기 PSC거더 세그먼트(100a)들의 제작 및 야적이 완료되면 운반차량을 이용하여 현장에 반입시키게 되는데 현장에서는 미리 교량하부구조(200)가 시공된 상태이다.Next, when the fabrication and yardage of the PSC girder segments 100a are completed, the PSC girder segments 100a are brought into the site using a transport vehicle, and the bridge substructure 200 is constructed in advance.

현장에서는 도 4b와 같이 다수의 PSC거더 세그먼트(100a)를 서로 종방향으로 연결시켜 일정한 길이(L)로 PSC 거더(100)로 세팅하게 된다.In the field, as shown in FIG. 4B, a plurality of PSC girder segments 100a are longitudinally connected to each other to set the PSC girder 100 to a predetermined length L.

이때 전도방지를 위하여 전도방지수단(300)을 설치하게 된다.At this time, the fall prevention means 300 is installed to prevent fall.

이러한 전도방지수단(300)은 연결부 정착단(140)과 하부플랜지(130)의 관통홀(111,131)에 수평재(310)와 수직재(320)의 연결판(330)을 이용하여 상기 PSC거더 세그먼트(100a)에는 매립된 정착너트에 연결판(330)의 연결홀(331)을 관통하는 앵커볼트(340)를 이용하여 PSC거더 세그먼트(100a)에 전도방지수단(300)을 간단하게 설치하게 된다.The fall prevention means 300 is connected to the PSC girder segment using the connecting plate 330 of the horizontal member 310 and the vertical member 320 in the through holes 111 and 131 of the connector fixing end 140 and the lower flange 130. In the 100a), the anchoring prevention means 300 is simply installed in the PSC girder segment 100a by using the anchor bolt 340 penetrating through the connection hole 331 of the connecting plate 330 in the embedded fixing nut.

이러한 전도방지수단(300)은 PSC 거더(100)의 양 단부에 설치되고 있음을 알 수 있다.It can be seen that the fall prevention means 300 are installed at both ends of the PSC girder 100.

이에 예컨대 3개의 PSC거더 세그먼트(100a)를 서로 종방향으로 서로 연결부가 형성되도록 한 상태에서 쉬스에 PSC 긴장재(30)를 삽입 한 후 양 단부의 PSC거더 세그먼트(100a)에 PSC 긴장재(30)를 긴장 후 정착시켜 PSC거더 세그먼트(100a)에 프리스트레스를 도입시켜 서로가 압착 연결되도록 하게 된다.For example, the three PSC girder segments 100a are inserted into the PSC tension member 30 in the sheath in a state in which the connecting portions are formed in the longitudinal direction of each other, and then the PSC tension members 30 are attached to the PSC girder segments 100a at both ends. After the tension is settled to introduce a prestress to the PSC girder segment (100a) to be crimped to each other.

이러한 연결 상태에서 연결부 정착단(140)의 긴장홀(141)에 연결부긴장재(150)를 설치함으로서 연결부를 더욱 압착 연결시키게 된다.In this connection state, the connection part tensioner 150 is installed in the tension hole 141 of the connection part fixing end 140 to further connect the connection part by pressing.

이때 상기 긴장홀(141)에는 앞서 살펴본 가로빔연결패널(400)을 PSC거더 세그먼트(100a)에 함께 설치한 PSC 거더(100)도 함께 준비하게 된다.At this time, the tension hole 141 is also prepared with the PSC girder 100 installed together with the horizontal beam connecting panel 400 in the PSC girder segment (100a).

이에 도 4c와 같이 상기 연결부긴장재(150)에 의한 PSC거더 세그먼트(100a)의 압착 연결이 완료되면 교량하부구조(200) 즉 교대, 교각 사이에 종방향으로 PSC 거더(100)의 양 단부가 교량받침(210)에 의하여 지지되도록 거치하게 된다.Therefore, as shown in FIG. 4C, when the crimp connection of the PSC girder segment 100a by the connecting part tension member 150 is completed, both ends of the PSC girder 100 in the longitudinal direction between the bridge substructure 200, that is, the bridges and the bridges are bridged. It is mounted to be supported by the support (210).

이러한 PSC 거더(100)는 먼저 가로빔연결패널(400)이 설치된 PSC 거더(100)를 서로 횡방향으로 이격시켜 설치하게 된다.The PSC girder 100 is installed by first separating the PSC girder 100 in which the horizontal beam connecting panel 400 is installed laterally from each other.

다음으로는 상기 가로빔연결패널(400)이 설치된 PSC 거더(100) 사이사이에 가로빔연결패널(400)이 설치되지 않은 PSC 거더(100)를 역시 거치하면서 PSC 거더(100)의 가로빔연결패널(400)에 연결부 정착단(140)이 횡방향으로 삽입되도록 하고,Next, the horizontal beam connection of the PSC girder 100 is also mounted while also mounting the PSC girder 100 in which the horizontal beam connection panel 400 is not installed between the PSC girder 100 where the horizontal beam connection panel 400 is installed. The connector fixing end 140 is inserted into the panel 400 in the transverse direction,

상기 가로빔연결패널(400)에 삽입된 연결부 정착단(140)을 가로빔연결패널(400)과 서로 결속시키게 된다.The connection part fixing end 140 inserted into the horizontal beam connecting panel 400 is coupled with the horizontal beam connecting panel 400.

이에 횡방향으로 서로 접하여 다수의 PSC 거더(100)는 가로빔연결패널(400)에 의하여 횡방향으로 구속되는 효과가 있어 별도로 종래 가로빔을 설치하는 공종이 배제될 수 있음을 알 수 있다.Accordingly, the plurality of PSC girders 100 in contact with each other in the lateral direction has the effect of being constrained in the lateral direction by the horizontal beam connecting panel 400 can be seen that can be excluded separately from the conventional installation of the horizontal beam.

이로서 PSC 거더(100)는 종방향으로 교량하부구조 사이에 설치되도록 하되 상부플랜지는 횡방향으로 서로 접하도록 형성되어 별도의 슬래브 시공이 필요 없게 됨을 알 수 있다.As a result, the PSC girder 100 may be installed between the lower bridge structures in the longitudinal direction, but the upper flanges may be formed to be in contact with each other in the transverse direction so that no additional slab construction is required.

다음으로는 상기 전도방지수단(300)을 제거하거나 그대로 영구 설치하여도 상관은 없다.Next, the fall prevention means 300 may be removed or permanently installed as it is.

이에 최종 도 4d와 같이 상기 상부플랜지 상면에는 포장층 등을 추가 시공하여 최종 본 발명의 모듈러 피에스씨 거더교가 시공될 수 있음을 알 수 있다.Thus, it can be seen that the modular PSC girder bridge of the present invention can be constructed by additionally constructing a packaging layer on the upper surface of the upper flange as shown in FIG. 4D.

모듈러 피에스씨 거더교는 본 발명의 가로빔 및 전도방지수단이 함께 설치된 PSC 거더를 제작하여 교량을 시공하여 종래 가로빔, 전도방지수단을 별도로 시공하지 않는다는 의미의 거더교라 할 수 있다.Modular PS girder bridge can be said to be a girder bridge means that does not construct the conventional horizontal beam, fall prevention means by constructing a bridge by manufacturing the PSC girders installed with the horizontal beam and fall prevention means of the present invention.

이러한 모듈러 PSC 거더교는 단경간 또는 다경간으로 설치될 수 있을 것이다.Such a modular PSC girder bridge may be installed in a short span or multi span.

이와 같이 모듈러 PSC 거더교가 최종 완성되면 시간이 경과함에 따라 SPC 긴장재에 하여 도입된 프리스트레스가 감소할 수 있는데 이러한 감소를 보완하기 위하여 상기 연결부긴장재(150)를 추가 긴장 후 연결부 정착단(140)에 의하여 추가 프리스트레스가 도입되도록 할 수 있어 유지관리에도 매우 효과적이게 된다.As such, when the modular PSC girder bridge is finally completed, the prestress introduced to the SPC tension member may decrease as time passes. In order to compensate for the decrease, the connection tension member 150 is further tensioned by the connection anchoring end 140. Additional prestresses can be introduced, making them very effective for maintenance.

다음으로 완성된 모듈러 PSC 거더교는 보도(500)를 시공하게 되는데 이러한 보도(500)는 모듈러 PSC 거더(100)의 상부플랜지(110)에 걸쳐지도록 설치된다.Next, the completed modular PSC girder bridge will be constructed with a sidewalk 500. The sidewalk 500 is installed to span the upper flange 110 of the modular PSC girder 100.

이때 상기 보도(500)는 도 4e와 같이 일정강도(예컨대 120MPa) 이상의 압축강도를 가지는 초고성능 콘크리트(예컨대 Ultra High Performance Concrete/"UHPC")를 이용하여 제작함으로서 두께를 최소화시켜 자중을 최소화시킨 판형부재로 제작된 것을 이용하게 된다.At this time, the sidewalk 500 is made of ultra-high performance concrete (eg, Ultra High Performance Concrete / "UHPC") having a compressive strength of a certain strength (for example, 120 MPa) or more as shown in FIG. What is produced by the member is used.

이에 먼저 역 L자 형태의 보도(500)의 일측을 모듈러 PSC 거더의 상부플랜지 상면에 지지되도록 하고, 외측단부를 스트럿(510)을 이용하여 지지되도록 하되, 상기 스트럿(510)의 하부는 앵커(미도시)를 이용하여 PSC 거더의 상부플랜지 또는 복부 또는 하부플랜지에 형성된 연결부 정착단(140)의 관통홀(141) 등을 이용하여 설치되도록 하게 된다.First, one side of the inverted L-shaped sidewalk 500 is supported on the upper surface of the upper flange of the modular PSC girder, and the outer end is supported by the strut 510, but the lower portion of the strut 510 is anchor ( It is to be installed using the through-hole 141 of the connecting portion fixing end 140 formed in the upper flange or the abdominal or lower flange of the PSC girder using the (not shown).

나아가 상기 스트럿(510)의 하부는 연결부 정착단의 외측면에 지지되도록 설치해도 상관은 없다.Furthermore, the lower part of the strut 510 may be installed to be supported on the outer surface of the connection fixing unit.

100: PSC 거더 100a: PSC거더 세그먼트
110: 상부플랜지 111,131: 관통홀
120: 복부
130: 하부플랜지 30: PSC 긴장재
140: 연결부 정착단 141: 긴장홀
150: 연결부긴장재
200: 교량하부구조
210: 교량받침
300: 전도방지수단
400: 가로빔연결패널
410: 연결홀
500: 보도 510: 스트럿
100: PSC girder 100a: PSC girder segment
110: upper flange 111,131: through hole
120: abdomen
130: lower flange 30: PSC tension material
140: fixing portion 141: tension hole
150: connecting part tension material
200: bridge undercarriage
210: bridge bearing
300: fall prevention means
400: horizontal beam connecting panel
410: connecting hole
500: sidewalk 510: strut

Claims (3)

상부플랜지(110), 복부(120) 및 하부플랜지(130)를 포함하는 PSC 거더(100)를 PSC거더 세그먼트로 분할 제작하여 서로 압착시켜 일정한 길이를 가진 PSC 거더로 제작되는 PSC 거더 세그먼트(100a)에 있어서,
상기 PSC거더 세그먼트(100a)의 연결부(A)에는 상부플랜지(110)와 복부(120)의 측면에 돌출 형성된 블록으로서 종방향으로 긴장홀(141)이 형성된 연결부 정착단(140)이 형성되도록 하여, 상기 긴장홀(141)에 삽입되어 긴장 후 연결부 정착단에 정착된 연결부긴장재(150)에 의하여 PSC거더 세그먼트의 연결부가 압착되도록 하되, 상기 연결부긴장강재(150)를 긴장홀(141)에 삽입 설치하면서 가로빔연결패널(400)의 단부도 함께 고정되도록 하되,
상기 가로빔연결패널(400)은 연결부 정착단(140)이 종방향으로 압착될 때 서로 종방향으로 이격되어 한쌍이 함께 설치되도록 하며, 상기 이격된 가로빔연결패널(400) 사이에 횡방향으로 인접한 PSC거더 세그먼트의 연결부 정착단(140)이 삽입되어 가로빔연결패널(400)과 연결부 정착단(140)이 서로 결속되도록 하고,
상기 연결부 정착단(140)에 스트럿(510)의 일측단부를 앵커를 이용하여 설치하여 상기 스트럿(510)에 의하여 보도(500)를 PSC 거더의 상부플랜지 상면에 지지되도록 설치하는 단계를 포함하는 것을 특징으로 하는 연결부 정착단을 구비한 피에스씨 거더를 이용한 보도교 시공방법.
PSC girder segment 100a including the upper flange 110, the abdomen 120, and the lower flange 130 is made of PSC girder segments by pressing and splitting them into PSC girder segments. To
The connection portion A of the PSC girder segment 100a is a block protruding from the sides of the upper flange 110 and the abdomen 120 so that the connection portion fixing end 140 in which the tension hole 141 is formed in the longitudinal direction is formed. After the tension is inserted into the tension hole 141, the connection part of the PSC girder segment is compressed by the connection part tension member 150 fixed to the connection part fixing end, and the connection part tension steel 150 is inserted into the tension hole 141. While installing the end of the horizontal beam connecting panel 400 is also fixed together,
The horizontal beam connecting panel 400 is spaced apart from each other in the longitudinal direction when the connecting portion fixing end 140 is compressed in the longitudinal direction so that a pair is installed together, and in the horizontal direction between the spaced horizontal beam connecting panel 400 The connection part fixing end 140 of the adjacent PSC girder segment is inserted so that the horizontal beam connecting panel 400 and the connection part fixing end 140 are coupled to each other.
And installing one side end of the strut 510 on the connection part fixing end 140 by using an anchor so that the sidewalk 500 is supported on the upper flange upper surface of the PSC girder by the strut 510. Method for constructing a pedestrian bridge using a PS girder having a connecting part fixing end.
제 1항에 있어서,
상기 PSC 거더(100)의 양 단부에 위치한 PSC 거더 세그먼트의 하부플랜지와 상부플랜지 측면과 저면에는 매립너트가 설치되어, 상기 매립너트에 앵커볼트(340)에 의하여 전도방지수단(300)이 더 설치되도록 하되,
상기 전도방지수단(300)은 하부플랜지에 형성된 매립너트에 앵커볼트에 의하여 고정되는 연결판(330)이 단부에 형성된 수평재(310); 및 상기 상부플랜지에 형성된 매립너트에 앵커볼트에 의하여 고절되는 연결판(330)이 형성된 수직재(320);를 포함하는 전도방지수단(300)이 PSC거더의 양 단부에 미리 설치될 수 있도록 하는 것을 특징으로 하는 연결부 정착단을 구비한 피에스씨 거더를 이용한 보도교 시공방법.
The method of claim 1,
A buried nut is installed on the lower flange side and the upper flange side and the bottom of the PSC girder segment located at both ends of the PSC girder 100, and the fall prevention means 300 is further installed by the anchor bolt 340 in the buried nut. But to be
The fall prevention means 300 includes a horizontal member 310 formed at the end of the connection plate 330 fixed to the buried nut formed in the lower flange by the anchor bolt; And a vertical member 320 having a connecting plate 330 which is anchored by an anchor bolt to a buried nut formed in the upper flange. The fall prevention means 300 may be installed at both ends of the PSC girder. Method for constructing a pedestrian bridge using a PS girder having a connecting part fixing end.
제 1항 또는 제 2항에 있어서,
상기 보도(500)는 초고성능 콘크리트(Ultra High Performance Concrete/"UHPC")를 이용하여 두께를 최소화시켜 자중을 최소화시킨 판형부재로 제작된 것을 이용하는 것을 특징으로 하는 연결부 정착단을 구비한 피에스씨 거더를 이용한 보도교 시공방법.
3. The method according to claim 1 or 2,
The sidewalk 500 is a PS girder having a connection fixing part, characterized in that it is made of a plate member that minimizes the weight by minimizing the thickness by using ultra high performance concrete ("UHPC") Construction method of pedestrian bridge using
KR1020120034142A 2012-04-02 2012-04-02 Walking bridge construction method using psc girder with connecting anchor block KR101324982B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020120034142A KR101324982B1 (en) 2012-04-02 2012-04-02 Walking bridge construction method using psc girder with connecting anchor block

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020120034142A KR101324982B1 (en) 2012-04-02 2012-04-02 Walking bridge construction method using psc girder with connecting anchor block

Publications (2)

Publication Number Publication Date
KR20130111902A KR20130111902A (en) 2013-10-11
KR101324982B1 true KR101324982B1 (en) 2013-11-05

Family

ID=49633108

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020120034142A KR101324982B1 (en) 2012-04-02 2012-04-02 Walking bridge construction method using psc girder with connecting anchor block

Country Status (1)

Country Link
KR (1) KR101324982B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101941942B1 (en) 2018-07-03 2019-04-11 김문홍 Integrated form structure for constructing cantilever slab and protective wall of bridge, and construction method using the same

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107974943A (en) * 2017-11-30 2018-05-01 广州华夏职业学院 A kind of road and bridge pavement construction method
KR102438599B1 (en) * 2021-01-21 2022-08-31 (주)리빌텍이엔씨 Bridge Expansion Structure, and Method for Installing Thereof
KR102676231B1 (en) * 2022-04-19 2024-06-19 현대건설(주) Connecting structure of different girders

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060114973A (en) * 2005-05-03 2006-11-08 주식회사 기주건설 Earthquake-proof reinforcement shock relaxation system of bridge structure
KR200432594Y1 (en) 2006-09-27 2006-12-05 (주)신승건설 A constructed footpath of a bridge
KR100785634B1 (en) 2006-10-30 2007-12-12 장신찬 Continuation structure of prestressed concrete composite beam bridge and method thereof
KR20110052101A (en) * 2009-11-12 2011-05-18 한국건설기술연구원 Ultra high performance concrete slab for cable bridge

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060114973A (en) * 2005-05-03 2006-11-08 주식회사 기주건설 Earthquake-proof reinforcement shock relaxation system of bridge structure
KR200432594Y1 (en) 2006-09-27 2006-12-05 (주)신승건설 A constructed footpath of a bridge
KR100785634B1 (en) 2006-10-30 2007-12-12 장신찬 Continuation structure of prestressed concrete composite beam bridge and method thereof
KR20110052101A (en) * 2009-11-12 2011-05-18 한국건설기술연구원 Ultra high performance concrete slab for cable bridge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101941942B1 (en) 2018-07-03 2019-04-11 김문홍 Integrated form structure for constructing cantilever slab and protective wall of bridge, and construction method using the same

Also Published As

Publication number Publication date
KR20130111902A (en) 2013-10-11

Similar Documents

Publication Publication Date Title
KR100423757B1 (en) Prestressed composite truss girder and construction method of the same
KR101222620B1 (en) Prestressed concrete girder and it&#39;s manufacture and construction method which used pretensioning steel plate
CN109736206B (en) Cast-in-situ bracket structure for bridge side span closure of corrugated steel web continuous beam and construction method
KR101326170B1 (en) Psc girder segment with connecting anchor block, psc girder and modular psc girder bridge construction method using the same
KR100693872B1 (en) Connection structure and construction method for steel and concrete composite deck with a blocked out
KR101324982B1 (en) Walking bridge construction method using psc girder with connecting anchor block
KR101335382B1 (en) Constrution method of Prestressed Composite Truss girder with internal hinge structure
WO1997014849A1 (en) Bridge deck system
CA2023198C (en) Composite girder construction and method of making same
KR20140144035A (en) The hybrid girder structures prestressed by using the external prestressing mechanism, and the construction method by rigid connection
KR100984249B1 (en) Bridge construction method using strength connector detail and composite curing pannel
JP3737475B2 (en) Box girder bridge structure and construction method
KR100860796B1 (en) Continuationization method by which psc which used upper and lower symmetry or asymmetric fixed bracket
KR100871831B1 (en) Prestressed temporary bridge preloaded by cable-tie and method thereof
KR100937252B1 (en) Prestressed steel composite beam and a manufacturing method thereof
JP3877995B2 (en) How to build a string string bridge
KR100690395B1 (en) Continuous Beam Construction Method of Prestressed Concrete Beam
KR100565384B1 (en) Structure of continuous PSC beam with connection member and steel cross beam and bridge construction method using the same
KR20080099061A (en) Psc beam for connection steel width step of psc bridges
KR100989153B1 (en) Psc girder connection structure with strength connector detail for substitution of rebar placement in deck and bridge construction method using the same
KR20130090709A (en) Construction method for corrugated steel plate web-psc composite beam
KR20030094195A (en) Improved prestressed steel reinforced concrete beam and bridge construction method using the same beam
KR100984247B1 (en) Bridge construction method using strength connector detail joined with rebar of upper flange concrete
KR20060017949A (en) Field-fabricated prestressing steel-composed girder and construction method of continuous bridge using the girder
KR100984248B1 (en) Bridge construction method using strength connector detail for curing pannel of upper strength reinforcing block

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20160928

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20181002

Year of fee payment: 6